METHOD FOR OPERATING A HEATING SYSTEM
Patent Information
- Application Number
- DE502022001675
- Authority / Receiving Office
- DE · DE
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2021-03-03
- Filing Date
- 2022-02-25
- Publication Date
- 2024-10-10
- Estimated Expiration
- 2042-02-25
AI Technical Summary
The synchronous commissioning of heating systems leads to load peaks and instabilities in the energy network, particularly due to the simultaneous startup of heat pumps and electric heaters, causing voltage drops and customer complaints, which existing methods fail to address effectively.
A method that generates a random variable to determine a new start time for heating systems, dispersing the startup times of high-load components, thereby avoiding load peaks by setting a time offset for the programmatic start time, allowing for independent operation without user involvement.
This method effectively reduces the likelihood of load peaks and network instabilities by statistically scattering the startup times of heating systems, ensuring stable energy network operation without requiring user intervention or structural changes to existing heating systems.
Description
[0001] The invention relates to a method for commissioning a heating system without negative impact on the stability of the energy network, a computer program, a machine-readable storage medium and a control device.
[0002] To optimize energy consumption, heating systems are usually switched on and off according to a timer. Typically, the heating systems are shut down in the evening or at night and restarted in the morning to heat the thermal zones and provide hot water.
[0003] The heaters are usually factory-installed with a standard timer program that, across all manufacturers, usually shuts down the heater at 10 p.m. and starts it up again at 6 a.m. A significant proportion of users retain these factory-installed timers, perhaps because they meet their needs or because they don't want the effort of reprogramming.
[0004] The heater clocks are usually synchronized by an external signal, such as a DCF radio signal, eliminating the need for user adjustment. This means that a potentially considerable number of heaters can be started at exactly the same time because their clocks are synchronized and follow a factory-installed time program.
[0005] Particularly in the case of heating systems that incorporate heat pumps and / or electric heaters, this leads to a peak load in the required electricity supply. It has been recognized that this can lead to a voltage drop, noticeable, for example, through flickering lighting, or even repercussions at nodes in the electricity grid. It has also been recognized that the main cause of this is the high starting currents of heat pump compressors. Due to the increasing prevalence of heating systems with heat pumps, an increase in the problems described is expected. In addition, when reprogramming the time program, users often choose "round" times, such as on the full, half-hour, or quarter-hour. As a result, the problems mentioned can also occur at other times.In addition, the load peaks perceived by users via flickering lighting devices are often the subject of customer complaints to the manufacturer, as a malfunction of the heating system is suspected to be the cause.
[0006] DE 10 2017 002 193 A1 proposes a method and arrangement for the flexible use of electricity in boilers, with which the shutdown current of systems for the use of renewable energy, such as PV or wind turbines, can be reduced. If shutdowns of renewable energy systems occur, an external signal can activate an electric heating device on a heating appliance, which reduces the use of fossil fuels by the heating system. Thus, an energy supplier can use surplus electricity (shutdown current) at any time by switching on / off an electric heating system to utilize the consumption of fossil fuels. The proposed method is not applicable to the above problem, since heating systems cannot generally be switched on by the grid operator.
[0007] US2016 / 0040907 A1 relates in particular to the power control of heating, ventilation, and cooling systems with an electric heater comprising heating elements. The heating elements are controlled by at least one relay. To ensure even wear of the relay contacts, it is proposed to use a time-delay switch that prevents switching from occurring at the upper and lower maximums of the AC voltage.
[0008] EP 0 908 678 A2 relates to a method for operating a boiler system with a burner. To increase energy consumption, pollutant emissions, and the service life of a burner, it is proposed to delay the burner start after a burner start request for essentially constant times of 2 to 25 minutes. Furthermore, the time delay or the time interval between two burner starts can be varied. This method is not suitable for reducing peak loads in the power supply.
[0009] Based on this, the object of the invention is to provide a method for commissioning a heating system without negatively impacting the stability of the power grid, which at least partially overcomes the problems described in the prior art and, in particular, avoids peak loads and instabilities in the power grid by synchronously commissioning a large number of heating systems. Furthermore, a computer program, a machine-readable storage medium, and a control unit are to be specified for this solution.
[0010] In addition, the proposed procedure should be as independent as possible from user participation in order to ensure safe operation.
[0011] These objects are achieved by the features of the independent patent claims. Further advantageous embodiments of the solution proposed here are specified in the independent patent claims. It is pointed out that the features listed in the dependent patent claims can be combined with one another in any technologically expedient manner and define further embodiments of the invention. Furthermore, the features specified in the patent claims are further specified and explained in the description, with further preferred embodiments of the invention being presented, the invention being defined by the patent claims.
[0012] For this purpose, a procedure for commissioning a heating system without negative impact on the stability of the energy network is proposed, which comprises the following procedural steps: a) Generating a random variable, b) Determining a new start time for operation of the heating system, including the random variable as a time offset for a program-based and / or permanently stored start time of the heating system, c) Commissioning at least one component of the heating system or the entire heating system at the new start time determined in step b).
[0013] Steps a) to c) can be performed at least once in the specified order. However, steps a) and b) can also be performed only once, and the heating system can then be operated with the new start time permanently or as long as the heating system is not reconfigured (e.g., due to a change in the installed components).
[0014] In particular, the method relates to the operation of a heating system (also used here as a generic term for a heating system or a heating device) of a building or a floor of a building, a building complex, or a facility comprising several buildings that have a single or shared energy source to operate the heating system. The heating system may comprise electrically operated or electrically power-requiring components, such as heaters, fans, air conditioners, heat pumps, circulating pumps, auxiliary heaters, e.g., in the form of (electrical) resistance heating elements, etc. In particular, the components of the heating system can be categorized according to their power consumption, whereby "high-load components" can be defined that have a particularly high energy demand when switched on, compared to other "low-load components" of the heating system.
[0015] In step a), a random variable is generated. In a simple implementation, this can be done using a random generator. Step a) can, for example, be performed after the installation of a new heating system in the building and / or after the installation of new components in an existing heating system. If necessary, a classification step can be performed before step a), in which the components of the heating system are categorized according to their power consumption, defining "high-load components" and "low-load components" of the heating system. If several heating systems in a building, building complex, or building system use the same energy source, step a) can perform a comparison of the generated random variable with those of the other heating system(s) and (immediately) repeat step a) if identical random variables are determined.
[0016] In step b), a new start time for the heating system's operation is defined using the random variable from step a). The start time refers specifically to the time at which the heating system is "woken up" from a sleep or night state. The start time can be a regular or daily event. A new start time is determined using the random variable, including the random variable as a time offset for the programmatic and / or permanently stored start time of the heating system. The new start time can be determined by adding the offset to the old start time. An old or programmatic start time can be a start point (time) permanently stored in a control unit of the heating system component or a control unit of the entire heating system. The determined time offset can be positive or negative.
[0017] It goes without saying that the new start time should have only a small offset from the old, program-based start time to avoid restricting functionality for the user. A reasonable offset for the start time could be in the range of a few tenths of a second to minutes.
[0018] In step c), at least one component of the heating system or the entire heating system is commissioned. Commissioning involves, in particular, the use of electrical energy. It is therefore possible to set the starting point offset for (only) one or more ("high-load") components of a heating system, or to assign a different offset to components of a floor or building, or to a building system. The ("high-load") component can, in particular, be a component with a high starting current, for example, a compressor of a heat pump or a heater of the heating system ("high-load" component).Advantageously, the process is carried out in a way that is either not noticeable or barely noticeable to the user, because the phenomena associated with the commissioning of the heating system, such as a starting noise and / or a change in a display, continue to take place exactly at the programmed time.
[0019] For example, a simple computational model could consist of generating a random variable between 0 and 1 or between -1 and 1 and multiplying it by a defined maximum offset. This allows a temporal offset to be determined for the starting time, which is then added to the old starting time to determine a new starting time.
[0020] In step a), the random variable can be generated using a device-specific key figure. This allows a new, device-specific start time to be defined for each heating system, further reducing the probability of peak loads. In particular, it is proposed to use a device-specific key figure that is already available to a process-executing device, such as a heating system control unit. The key figure can be selected depending on a classification step of the components (devices).
[0021] In this context, it is noted that the term random variable does not have to be understood in the mathematical sense, but rather refers in particular to a variable that allows for a dispersion of the starting times.
[0022] The device-specific key figure can be determined based on the serial number of a component in the heating system. In particular, the random variable could be part of the serial number of a component in the heating system, for example, the last two digits. The advantage of this design is seen as a targeted variance of the newly determined start times by including a serial number.
[0023] In step b), the defined new start time can be stored in a time program of the heating system so that the new start time replaces the old program time.
[0024] According to a further aspect, a computer program is also proposed that is configured to carry out a method presented here. In other words, this relates in particular to a computer program (product) comprising instructions that, when executed by a computer, cause the computer to execute a method described here.
[0025] According to a further aspect, a machine-readable storage medium on which the computer program is stored is also proposed.
[0026] The machine-readable storage medium is usually a computer-readable data carrier.
[0027] According to a further aspect, a control unit for a heating system is also proposed, configured to carry out a method presented here. For this purpose, the control unit can, for example, comprise or have a processor. In this context, the processor can, for example, execute the method stored in a memory (of the control unit).
[0028] According to a further aspect, a heating system with a control unit presented here is also proposed. The heating system is, in particular, a heating system comprising a heat pump or a comparable "high-load" component for heat generation.
[0029] Thus, a method for operating a heating system, a computer program, a machine-readable storage medium and a control device are specified here, which at least partially solve the problems described with reference to the prior art.
[0030] The method proposed here, the computer program, the machine-readable storage medium, and the control unit contribute to preventing instabilities in an energy grid through the synchronous commissioning of a large number of heating systems. Furthermore, the method can be implemented without user involvement, thus achieving a high level of process reliability because human error is eliminated. A further advantage is the fact that the method can be implemented on state-of-the-art heating systems without structural modifications.
[0031] The invention will now be explained in detail using a figure. Fig. 1 shows an example and schematically a sequence of a method proposed here. In particular, Fig. 1 the process steps a) to c), which are represented by blocks 110 to 130.
[0032] The procedure allows a heating system to be put into operation without affecting the stability of the energy network in a local area.
[0033] In block 110, a random variable is generated according to step a). This can, for example, be a random number between 0 and +1. In a preferred embodiment, the random variable can be determined based on the last two digits of a serial number of a component of the heating system. To derive a random number between 0 and +1 from these two digits, a division by 100 could be performed.
[0034] In step 120, according to step b), a new start time is determined or defined using the random variable from block 110. This step is performed by including the random variable as a time offset for a program-based start time of the heating system. This time offset value can define a new start time by adding it to the program-based start time. The program-based start time can, for example, be a factory-programmed start time.
[0035] According to step b), a temporal offset value can be determined, for example, by multiplying a random variable between 0 and +1 or -1 and +1 by a defined maximum temporal offset. The maximum temporal offset defines a period of time, whereby load peaks and the associated impacts on the power grid can be avoided if the switch-on times are spread out within this period. The maximum temporal offset could, for example, be a period of one minute.
[0036] In block 130, according to step c), at least one component of the heating system or heating systems is commissioned at the start time defined in block 120 (step b). Commissioning of heating systems or components thereof, particularly those with high starting currents, after implementation of the method proposed here would be carried out with statistical dispersion based on the random variable within the period defined by the maximum time offset. List of reference symbols
[0037] 110Step a) 120Step b) 130Step c)
Claims
1. Method for operating a heating assembly without a negative effect on the stability of the electricity network, comprising at least the following steps: a) generation of a random variable, b) determining a new start time point for an operation of the heating assembly, taking into consideration random variable as a temporal offset for a start time point of the heating assembly which is defined in a program and / or is permanently stored, c) operating at least one component of the heating assembly, or the entire heating assembly, at the new start time point determined in step b).
2. Method according to claim 1, wherein in step c) a component with high starting current is taken into operation.
3. Method according to claim 2, wherein the component with high starting current is a compressor of a heat pump.
4. Method according to any of the preceding claims, wherein in step a) the random variable is generated taking into consideration a metric of the heating assembly which is specific to the device.
5. Method according to claim 4, wherein the metric which is specific to the device is specified on the basis of a serial number of a component of the heating assembly.
6. Computer program, which is configured to carry out a method according to any one of the preceding claims.
7. Machine-readable storage medium on which the computer program according to claim 6 is stored.
8. Control device for a heating assembly configured to carry out a method according to any one of claims 1 to 5.
9. Heating assembly having a control device according to claim 8.