Maintenance plan support method and maintenance plan support system

The maintenance plan support method optimizes nuclear power plant maintenance by updating plans based on equipment status and regulatory frameworks, enhancing reliability and compliance.

JP2024132720AActive Publication Date: 2024-10-01HITACHI GE NUCLEAR ENERGY LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
JP2023043612
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-17
Publication Date
2024-10-01
Estimated Expiration
2043-03-17

AI Technical Summary

Technical Problem

There is a need to optimize maintenance activities in nuclear power plants to enhance reliability, particularly in the context of higher safety requirements post-earthquake and adherence to comprehensive optimization frameworks like ROP and SNPM, which existing systems fail to adequately address.

Method used

A maintenance plan support method and system that utilizes design and field information to update maintenance plans based on equipment status, incorporating equipment management indices, performance, deterioration, and failure data, to optimize maintenance schedules and resource allocation.

Benefits of technology

The system effectively supports appropriate maintenance activities by updating plans to align with regulatory requirements, equipment condition, and operational trends, ensuring comprehensive and efficient maintenance strategies.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024132720000001_ABST
    Figure 2024132720000001_ABST
Patent Text Reader

Abstract

To provide a maintenance plan support method capable of properly supporting maintenance activities for a nuclear power plant.SOLUTION: The present invention relates to a maintenance plan support method that supports a maintenance plan for a nuclear power plant by utilizing design and / or information from the field, and when a maintenance plan for preventing a facility management index is made based thereupon in maintenance activities and maintenance actions of facilities which are executed according to the maintenance plan, an update plan for a next maintenance plan which is determined from facility situations in the field and an update plan for a long-period maintenance plan after the next and subsequent maintenance plan are set for a long-period maintenance plan for a plurality of times of periodic inspections planned in advance.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a maintenance plan support method and a maintenance plan support system for supporting maintenance activities in a nuclear power plant. [Background technology]

[0002] Nuclear power plants are made up of hundreds of systems and numerous pieces of equipment. In order to maintain safety and maximize the performance of the power plant, maintenance activities are carried out to maintain and improve its reliability.

[0003] Since the beginning of construction, conservation activities have been carried out under strict standards, but considering recent regulatory trends, operating records both domestically and overseas, and technological improvements since construction, there is a need to further optimize conservation activities.

[0004] The maintenance support system of Patent Document 1 is disclosed to include a grouping unit that groups devices among a plurality of devices installed in a plant that have common conditions related to device deterioration, and a display control unit that, for a designated representative device set in each group, displays on a display device a message indicating that no maintenance is required until the next inspection, even when deterioration of a device included in the group of the representative device is detected, if the expected time from when deterioration of the representative device is detected to when the failure occurs is equal to or longer than a first predetermined value. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 2022-138712 A Summary of the Invention [Problem to be solved by the invention]

[0006] Higher reliability is required in the operation of domestic nuclear power plants after the earthquake disaster. Examples from overseas include the proven regulations (ROP: Reactor Oversight Process) in the United States and industry best practices (for example, the Standard Nuclear Performance Model (SNPM)), both of which aim to optimize the maintenance of existing reactor plants from a comprehensive perspective. In Japan, too, there was a desire to build a maintenance process that promotes comprehensive optimization by taking inspiration from the United States, although US regulations and operational track records differ.

[0007] The present invention has been made to solve the above-mentioned problems, and an object of the present invention is to provide a maintenance plan support method and a maintenance plan support device that can appropriately support maintenance activities in a nuclear power plant. [Means for solving the problem]

[0008] In order to achieve the above object, the maintenance plan support method of the present invention is a method for supporting a maintenance plan in a nuclear power plant by utilizing information from design and / or the site, and is characterized in that, in the maintenance activities and maintenance actions of the equipment executed according to the maintenance plan, in formulating a maintenance plan for preventing the occurrence of the above-mentioned problems based on equipment management indexes, an update plan for the next maintenance plan determined from the on-site equipment status and an update plan for the next and subsequent long-term maintenance plans are set for a long-term maintenance plan for multiple periodic inspections that has been formulated in advance. Other aspects of the present invention will be described in the embodiments described later. Effect of the Invention

[0009] According to the present invention, maintenance activities for a nuclear power plant can be appropriately supported. [Brief description of the drawings]

[0010] [Figure 1] 1 is a diagram illustrating a configuration of a maintenance plan support system according to an embodiment of the present invention. [Diagram 2]FIG. 11 is a diagram illustrating an example of configuration data of a device management DB. [Diagram 3] FIG. 13 is a diagram showing an example of configuration data of an FMEA DB. [Figure 4] FIG. 13 is a diagram showing an example of configuration data of a maintenance activity / monitoring item DB. [Diagram 5] FIG. 13 is a diagram showing an example of data constituting a field maintenance / monitoring data DB. [Figure 6] FIG. 13 is a diagram illustrating an example of configuration data of a work plan management DB. [Figure 7] FIG. 13 is a diagram illustrating an example of data (long-term maintenance plan) in a maintenance plan management DB. [Figure 8] FIG. 13 is a diagram illustrating an example of data (next maintenance plan) in a maintenance plan management DB. [Figure 9] 10 is a flowchart showing details of a maintenance plan support process during plant operation. [Figure 10] 13 is a flowchart showing details of a maintenance plan support process during a regular inspection period. [Figure 11] 13 is a flowchart showing a reflection process (part 1) in a maintenance plan. [Figure 12] 13 is a flowchart showing a second process of reflecting the maintenance plan. [Figure 13A] FIG. 13 is a diagram showing a method for selecting inspection candidates for the next regular inspection (change over time). [Figure 13B] This figure shows the method for selecting candidates for inspection at the next regular inspection (changes in similar individuals). [Figure 14A] FIG. 13 is a diagram showing an example of a recommendation for equipment to be maintained next based on a long-term plan. [Figure 14B] This figure shows an example of a recommended equipment to be maintained next (life of similar equipment) based on a long-term plan. [Figure 15A] FIG. 13 is a diagram showing an example of a recommended plan for future regular inspections (a plan that standardizes the number of vehicles). [Figure 15B] FIG. 13 is a diagram showing an example of a recommended plan for future regular inspections (a plan to maintain a large number of vehicles at a certain regular inspection). [Figure 16A]FIG. 1 is a diagram showing a base example (Nth operation cycle and Nth regular inspection) for reviewing maintenance tasks and cycles. [Figure 16B] FIG. 13 is a diagram showing a base example for reviewing maintenance tasks and cycles (time change in the case where only the tasks performed while the plant was down are plotted). [Figure 17] FIG. 13 is a diagram illustrating an example of visualization of constraints for a long-term maintenance plan. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment for carrying out the present invention will be described in detail with reference to the accompanying drawings. <Maintenance planning support system> FIG. 1 is a diagram showing a configuration of a maintenance plan support system 300 according to this embodiment. The maintenance plan support system 300 includes a maintenance plan support device 100 and a database device 200, which is an external storage device. The maintenance plan support device 100 includes a processing unit 10, a storage unit 20, an input unit 30, an output unit 40, and a communication unit 50. The processing unit 10 includes an equipment status management unit 11 that manages the status of the nuclear power plant, such as performance, deterioration, and failure, through inspection, testing, monitoring, and patrol, a maintenance plan update unit 12 that updates a maintenance plan for the next operation cycle based on the status of the nuclear power plant and updates a long-term maintenance plan for the next and subsequent operation cycles, a maintenance execution management unit 13 that manages maintenance management indexes, maintenance tasks and cycles that are required by laws, regulations, standards, and the like, resources required for maintenance, and the number of units to be maintained, and a maintenance plan planning unit 14 that plans a maintenance plan.

[0012] The memory unit 20 stores configuration management extraction information 21, FMEA extraction information 22, maintenance activity and monitoring item extraction information 23, field maintenance and monitoring extraction information 24, work plan management extraction information 25, maintenance plan management extraction information 26, and the like.

[0013] In Fig. 1, the processing unit 10 is a central processing unit (CPU) that executes various programs stored in a RAM, a HDD, or the like. The storage unit 20 is a HDD that stores various data for the maintenance plan support device 100 to execute processing. The input unit 30 is a device for inputting instructions to a computer, such as a keyboard or a mouse, and inputs instructions such as starting a program. The output unit 40 is a display or the like that displays the execution status and execution results of processing by the maintenance plan support device 100. The communication unit 50 exchanges various data and commands with other devices via a network NW.

[0014] The database device 200 has a configuration management DB 210, an FMEA DB 220, a maintenance activity / monitoring item DB 230, a field maintenance / monitoring data DB 240, a work plan management DB 250, a maintenance plan management DB 260, etc. Note that DB means database. FMEA is an abbreviation for Failure Mode and Effect Analysis, and is a systematic analysis method of potential failures with the aim of preventing failures and malfunctions.

[0015] The data stored in each DB is explained below. The configuration management DB 210 is a database that is composed of design requirements, design documents, and actual data for the power plant. For systems and equipment (collectively referred to as "facilities") that are the subject of maintenance, the equipment that is the subject of maintenance activities such as inspection, testing, monitoring, and repair, and the timing (cycle) of carrying out such activities are determined for the more important facilities in terms of maintaining and improving safety, in order to maintain the required specifications and functions. When changing the inspection cycle of a certain facility, as in this embodiment, the change must be made within a range that complies with laws and regulations, in principle. For example, the regulations may require a certain percentage of non-destructive testing within a certain number of years, such as 10 years.

[0016] FMEA DB220 is a database that includes the deterioration modes of equipment that constitutes a power plant, i.e., failure locations, deterioration mechanisms, effects of deterioration, severity of deterioration, frequency of deterioration, and effective maintenance activities and monitoring items.

[0017] The maintenance activity / monitoring item DB230 is a database that contains information on the power plant's maintenance activities and monitoring items, i.e., their contents, frequency, and target deterioration events. Here, the maintenance activities and monitoring items for the equipment subject to maintenance include those specified by laws, regulations, etc. in the "configuration management DB210". If the equipment to be maintained and the implementation timing (cycle) of maintenance and monitoring for maintaining the functionality of more important equipment (facilities, systems) from the viewpoint of maintaining safety are specified, it is necessary to comply with them.

[0018] The field maintenance and monitoring data DB 240 is a database that stores the actual on-site status of the maintenance activities and monitoring items defined in the maintenance activity and monitoring item DB 230. In other words, it is information on the deterioration state of the equipment (or information required to determine the deterioration state). If the results of the maintenance activities or the trends of the monitoring parameters may indicate a malfunction or deterioration, a request for corrective activities such as function recovery will be generated.

[0019] The work plan management DB250 is a database that stores standard information that is the basis for creating a site work plan. Specifically, it is a packaged piece of information (see Figure 6) related to the maintenance of a certain piece of equipment, and is a collection of multiple individual maintenance activities (= work orders) that make up the maintenance of that piece of equipment. In order to create a work plan with a certain amount of time, number of people, and parts, it is a database that contains information that organizes standard time, work personnel, and parts and equipment required for that work for each work order.

[0020] The maintenance plan management DB 260 stores and manages information on the next operation cycle, i.e., the maintenance plan related to operation and subsequent regular inspection, and the long-term maintenance plan including operation and subsequent regular inspection for the next operation cycle and thereafter, for example, for about 5 to 10 operation cycles in the future, for the equipment to be maintained. Therefore, information on each equipment to be maintained is stored.

[0021] <Examples of configuration data for each DB> 2 is a diagram showing an example of configuration data of the configuration management DB 210. The configuration management DB 210 is composed of categories and their configuration data. The categories include design requirements, facility configuration information, and physical configuration. For example, the design requirements include laws and regulations, design criteria documents, and calculation and analysis results.

[0022] Figure 3 is a diagram showing an example of data configuration of the FMEA DB 220. The FMEA DB 220 has data such as equipment name, deterioration mode, effective maintenance activities, monitoring items, etc. The deterioration mode includes the failure part, deterioration mechanism, deterioration effect, deterioration severity, and deterioration frequency. In Figure 3, for example, the equipment includes a control drive mechanism, ◇◇ pump, 〇〇 valve, △△ valve, etc.

[0023] The control rod drive (CRD) consists of the CRD body, a spool piece, and a motor unit. The control rod drive includes a part housed in the control rod drive housing installed in the lower part of the reactor pressure vessel, and a shaft seal part of the drive shaft housed in the spool piece attached to the lower part. Figure 3 shows that in the case of the spool piece of the control rod drive device, leakage may occur due to deterioration of the resin in the seal part.

[0024] Further details of the control rod drive mechanism will be described. The improved control rod drive mechanism (hereinafter referred to as FMCRD, an abbreviation for Fine Motion Control Rod Drive) is a device for driving the control rods, and is hydraulically driven during scram and electrically driven during normal control rod drive. In scram drive, the control rod is inserted using high-pressure water from the hydraulic control unit. In normal drive, an electric motor drives step insertion / removal and continuous insertion / removal. Of these, in normal drive, the rotation of the electric motor is converted into linear motion by a ball screw mechanism to insert and remove the control rods.

[0025] The structure of the FMCRD consists of a part housed in the control rod drive mechanism housing (CRD housing) installed at the bottom of the reactor pressure vessel, a spool piece that houses wear parts such as the shaft seal of the drive shaft attached to the bottom, and an electric motor. The part housed in the CRD housing is called the CRD main body, and includes the hollow piston that transmits the movement to the control rod, the ball screw mechanism, etc.

[0026] FIG. 4 is a diagram showing an example of data configuration of the maintenance activity / monitoring item DB 230. The maintenance activity / monitoring item DB 230 has inspection items, monitoring items, and test items for the target equipment. The inspection items include the frequency of maintenance and the target deterioration events. The monitoring items include the frequency of monitoring and the target deterioration events. Similarly, the test items include the frequency of testing and the target deterioration events. Specifically, in the case of the control rod drive mechanism, it can be seen that the inspection item of disassembly and inspection of the main body is carried out every x years.

[0027] Fig. 5 is a diagram showing an example of data constituting the field maintenance and monitoring data DB 240. The field maintenance and monitoring data DB 240 in Fig. 5 is data corresponding to the maintenance activity and monitoring item DB 230 in Fig. 4. Specifically, in the case of the control rod drive mechanism, an inspection is performed every x years to check the soundness of the main body as an inspection item.

[0028] 6 is a diagram showing an example of data configuration of the work plan management DB 250. The work plan management DB 250 has work packages, standard plan values, and related documents. Specifically, it can be seen that the target device is CRD-M001, the work order ID number is A01, the work time is x days, the number of workers is x, and the upper part is to be disassembled and inspected.

[0029] Fig. 7 is a diagram showing an example of data (long-term maintenance plan) of the maintenance plan management DB 260A. The maintenance plan management DB 260A has equipment name, maintenance activity, number of target equipment in operation, number of target equipment in the Nth regular inspection, number of target equipment in the N+1th regular inspection, ..., number of target equipment in the N+10th regular inspection. Specifically, in the case of the control rod drive mechanism, in the Nth regular inspection, three CRD bodies will be disassembled and inspected, and all of them will be monitored for current. It can also be seen that 10 spool pieces will be disassembled and inspected.

[0030] FIG. 8 is a diagram showing an example of data (next maintenance plan) of the maintenance plan management DB 260B. FIG. 8 is an example of data of the details of the next maintenance plan in FIG. 7. The maintenance plan management DB 260B has equipment name, maintenance activity, and target of maintenance in the Nth regular inspection (target equipment has a circle). Specifically, in the case of the control rod drive mechanism, three units of the CRD main body are to be disassembled and inspected in the Nth regular inspection, and the rods #51, #52, and #53 are to be inspected. All units of the CRD main body are to be monitored for current, so all rods # are to be inspected. In addition, ten units of the spool pieces are to be disassembled and inspected, so the rods #51, #52, #53, #54, . . ., #58, #59, and #60 are to be inspected.

[0031] <Maintenance planning support processing> 9 is a flowchart showing details of the maintenance plan support process S100 during plant operation. When the facility status management unit 11 finds a malfunction or a symptom thereof in the system or equipment to be maintained (step S102, YES) by carrying out maintenance activities (monitoring and testing during operation, etc.) during operation of the nuclear power plant (step S101), it proceeds to step S103, and when it does not find a malfunction or a symptom thereof in the system or equipment to be maintained (step S102, NO), it returns to step S101.

[0032] The equipment status management unit 11 evaluates whether or not corrective action is necessary for the malfunction (step S103), and if corrective action is not necessary (step S103, not necessary), proceeds to step S106, and if it is determined that corrective action is necessary for the malfunction (step S106, required), proceeds to step S104.

[0033] In step S106, the equipment status management unit 11 continues operation of the plant, and returns to step S101, while acquiring monitoring and test data during operation (step S107), calculating and recording maintenance management indexes (step S108), and proceeding to reflecting the maintenance plan (step S110, see FIG. 11).

[0034] In step S104, the equipment status management unit 11 formulates a plan for corrective measures, executes the plan, and acquires measurement data before the maintenance (step S105), and the process proceeds to step S108.

[0035] 10 is a flowchart showing details of the maintenance plan support process S200 for the periodic inspection period. When the facility status management unit 11 finds a malfunction or a symptom thereof in the system or equipment to be maintained (step S202, YES) by carrying out maintenance activities (monitoring and testing during operation, etc.) while the nuclear power plant is out of operation (step S201), it proceeds to step S203, and when it finds no malfunction or a symptom thereof in the system or equipment to be maintained (step S202, NO), it returns to step S201.

[0036] The equipment status management unit 11 evaluates whether or not corrective action is necessary for the malfunction (step S203), and if corrective action is not necessary (step S203, not necessary), proceeds to step S206, and if it is determined that corrective action is necessary for the malfunction (step S206, required), proceeds to step S204.

[0037] In step S206, the equipment status management unit 11 continues the regular inspection, returns to step S201, and evaluates whether additional measurement is necessary (step S207), and if additional measurement is necessary (step S207, necessary), acquires additional measurement data (step S208), and calculates and records the maintenance management index (step S109). On the other hand, if additional measurement is not necessary (step S207, not necessary), the equipment status management unit 11 proceeds to step S110.

[0038] In step S204, the equipment status management unit 11 formulates a plan for corrective measures, executes the plan, and acquires measurement data before the maintenance (step S205), and the process proceeds to step S209.

[0039] Fig. 11 is a flowchart showing a process of reflection in a maintenance plan (part 1). Fig. 12 is a flowchart showing a process of reflection in a maintenance plan (part 2). In reflection in a maintenance plan (step S110), the equipment status management unit 11 determines whether or not a discovered malfunction is estimated to be an expected deterioration mode (step S301), and if it is estimated to be an expected deterioration mode (step S301, YES), the process proceeds to step S302, and if it is not estimated to be an expected deterioration mode (step S301, NO), the process proceeds to step S306.

[0040] In step S302, the equipment status management unit 11 evaluates the current progress of the deterioration mode, evaluates whether the deterioration has progressed more than expected (step S303), and if the deterioration has progressed more than expected (step S303, YES), adds it to candidates for maintenance during plant operation and the next regular inspection (step S304), adds it to related DBs (e.g., FMEA DB 220, maintenance activity / monitoring item DB 230) (step S305), and ends the process. On the other hand, if the deterioration has not progressed more than expected (step S303, NO), proceed to step S309 (see FIG. 12).

[0041] In step S306, the equipment status management unit 11 identifies the range of the affected systems and equipment, adds the affected systems and equipment to candidates for maintenance during plant operation and the next regular inspection (step S307), adds them to related DBs (e.g., FMEA DB 220, maintenance activity and monitoring item DB 230) (step S308), and ends the process.

[0042] In step S309 of FIG. 12, the equipment status management unit 11 determines whether or not there is a relative change in the deterioration trend over time, and if there is a relative change in the deterioration trend over time (step S309, YES), the equipment status management unit 11 proceeds to step S317, and if there is no relative change in the deterioration trend over time (step S309, NO), the equipment status management unit 11 proceeds to step S310.

[0043] In step S310, the equipment status management unit 11 determines whether or not there is a relative change in the deterioration trend compared to similar equipment, and if there is a relative change in the deterioration trend compared to similar equipment (step S310, YES), proceeds to step S317, and if there is no relative change in the deterioration trend compared to similar equipment (step S310, NO), proceeds to step S311.

[0044] In step S317, the maintenance plan update unit 12 adds the plant to candidates for maintenance during plant operation and the next regular inspection.

[0045] In step S311, the equipment status management unit 11 evaluates the future progress status regarding the deterioration mode, and proceeds to step S312.

[0046] In step S312 (see Figures 16A and 16B), the equipment status management unit 11 checks the trend of maintenance management indicators (e.g., KPIs; Key Performance Indicators), checks the maintenance tasks and number of units to be maintained for the equipment in question or similar equipment, and the expected operation period of the equipment in question (step S313, see Figures 15A and 15B), and checks the laws, regulations, standards, and constraints on the long-term maintenance plan (step S314, see Figure 17).

[0047] FIG. 15A is a diagram showing an example of a recommended plan for future regular inspections (Case A: a plan that standardizes the number of units). FIG. 15B is a diagram showing an example of a recommended plan for future regular inspections (Case B: a plan to maintain a large number of units at a certain regular inspection). The number of years that each piece of equipment will be used in future long-term plans is shown in a table or the like, and the recommended plan is presented as a case study of candidates for future regular inspection plans. In FIG. 15A, the number of units inspected in maintenance activities is standardized to 3 or 4 units. On the other hand, in FIG. 15B, it can be seen that the number of units inspected is 30 units at the N+1 regular inspection, and 1 unit at the Nth regular inspection.

[0048] Fig. 16A is a diagram showing an example of a base for reviewing a maintenance task and period (the Nth operation cycle and the Nth periodic inspection). Fig. 16B is a diagram showing an example of a base for reviewing a maintenance task and period (time change in the case where only the work performed during plant shutdown is plotted). Figs. 16A and 16B are bases for reviewing a maintenance task and period.

[0049] Fig. 17 is a diagram showing an example of visualization of constraints for a long-term maintenance plan. The horizontal axis shows the expected number of days for regular inspections, and the vertical axis shows the number of units that can be maintained. Regarding how many units a work team can maintain, the maximum and minimum numbers of units that can be maintained are calculated as a case study. Note that data from the work plan management DB 250 (see Fig. 6) is used for the calculation.

[0050] Then, returning to Figure 12, the maintenance plan update unit 12 adds the candidate to be subject to maintenance during plant operation, reflects this in the next and subsequent long-term maintenance plans (step S315), and updates the next maintenance plan from the above long-term maintenance plan (step S316, see Figures 14A and 14B).

[0051] FIG. 14A is a diagram showing an example of equipment recommended for the next maintenance based on a long-term plan. FIG. 14B is a diagram showing an example of equipment recommended for the next maintenance based on a long-term plan (number of years of use of similar solids). The number of years each piece of equipment has been used is shown in a table or the like in the long-term plan, and if there is an abnormality during operation, that is given priority, and if there is no abnormality, it is recommended as the equipment to be maintained next based on the number of years of use. For example, referring to FIG. 14B, it can be seen that lot numbers #203, #204, and #205 are the solids recommended for the next maintenance.

[0052] (Example of monitoring the control rod drive mechanism) The main structure of the FMCRD is installed in the lower part of the reactor pressure vessel (inside the reactor containment vessel), and consists of 205 units, the same number as the number of control rods. The electric motors used to drive the FMCRD continuously are controlled from a control panel installed outside the reactor containment vessel.

[0053] Tests of the control rod drive mechanism are conducted during operation and regular inspections. Tests during operation are conducted over a set period of time, such as one month, to cycle through all 205 rods, and only within a limited range of up and down positions (such as one notch) that each control rod can be driven (hereafter referred to as "operational tests").

[0054] In addition, during regular inspections conducted while the plant is shut down, maintenance activities such as disassembly and part replacement are carried out on the FMCRD body, spool pieces, motors, etc. After that, before restarting the plant, tests are conducted on all 205 units to operate the control rods over the entire range of their driving range (upper and lower positions) (hereinafter referred to as "normal driving tests").

[0055] Since the control rod drive mechanism is composed of mechanical mechanisms such as ball screws and electrical components such as electric motors, it is desirable to ensure reliability through appropriate maintenance activities against mechanical and electrical deterioration.

[0056] Therefore, one example of FMCRD maintenance activities would be to monitor control signals.For comparison, to measure the vibration, sound, etc. of the FMCRD, it would be necessary to install vibration and sound sensors on all 205 units installed inside the reactor containment vessel, lay cables for signal transmission, and make it possible to perform measurements outside the containment vessel.

[0057] In contrast, when monitoring control signals, it is possible to more easily monitor all FMCRDs by measuring the control signals directly or indirectly from a control panel originally installed outside the reactor containment vessel.

[0058] Direct measurements include the operating time for moving through a specified vertical range, and waveforms such as drive voltage. Indirect measurements include current waveforms obtained by installing a circuit such as a current transformer in a control panel. Regarding waveforms such as voltage and current, feature quantities such as signal magnitude (peak value) and frequency spectrum components may be extracted.

[0059] In this way, the control signal of the motor can be monitored during an in-service test as the in-service monitoring of the FMCRD, and the control signal of the motor can be monitored during a regular inspection as the monitoring during a regular operation test.

[0060] Fig. 13A is a diagram showing a method for selecting an inspection candidate for the next regular inspection (change over time), and Fig. 13B is a diagram showing a method for selecting an inspection candidate for the next regular inspection (change in similar individuals). As shown in steps S309 and S310 of the flowchart in Fig. 12, the monitored signals can be used to create a maintenance plan update plan based on the overall change in the deterioration tendency over time of the control signals of each FMCRD or the feature values ​​extracted therefrom (step S309, see Fig. 13A) or the relative change by mutual comparison of the control signals of the FMCRD in question and the other FMCRDs or the feature values ​​extracted therefrom (step S310, see Fig. 13B) among the 205 FMCRDs, that is, when there is a change over time or a change by mutual comparison, it can be used to add it to the candidates for the equipment to be maintained next. For example, referring to Fig. 13B, it can be seen that rod #203 is the one recommended for the next maintenance.

[0061] The maintenance plan support method and the maintenance plan support device 100 of the present embodiment described above have the following features. (1) A method for supporting a maintenance plan in a nuclear power plant, which utilizes information from design and / or the field to support a maintenance plan, and is characterized in that, in the maintenance activities and actions (e.g., inspection, testing, monitoring, and patrol of equipment) of the equipment executed according to the maintenance plan, a maintenance plan to prevent the occurrence of the problems is formulated based on equipment management indicators (e.g., the status of performance, deterioration, and malfunctions), and an update plan for the next maintenance plan and update plans for the next and subsequent long-term maintenance plans are set for a long-term maintenance plan for multiple periodic inspections formulated in advance, the long-term maintenance plan being determined from the on-site equipment status. This makes it possible to appropriately support the maintenance activities of the nuclear power plant.

[0062] (2) In (1) above, when setting an update proposal for the next maintenance plan, the update proposal is made using both information on the time-varying trends of the performance, deterioration, and malfunction status of the equipment in question, and mutual comparison of the deterioration and malfunction status of similar equipment (steps S309 and S310, see Figures 13A and 13B).

[0063] (3) In (1) above, when setting an update plan for the next maintenance plan, the operation period of the equipment to be maintained or similar equipment is calculated from the long-term maintenance plan, and an update plan is created using the operation period (see Figures 14A and 14B).

[0064] (4) In the above (1), when setting the next and subsequent update proposals for the long-term maintenance plan, calculate the future maintenance tasks and number of units to be maintained for the equipment or similar equipment to be maintained, as well as the expected operating period of the equipment (see Figures 15A and 15B).

[0065] (5) In (2) above, when setting an update proposal for the next maintenance plan, the monitoring tasks for grasping the performance, deterioration, and malfunction status of the equipment are classified into whether the monitoring tasks are performed while the power plant is in operation or while the plant is shut down, and whether the monitoring tasks require disassembly of the equipment or not. The results of performing the monitoring tasks and the degree of the performance, deterioration, and malfunction status of the equipment are recorded as maintenance management indicators (see Figures 16A and 16B).

[0066] (6) In (4) above, when setting a proposal for updating the long-term maintenance plan for the next and subsequent years, at least information on the resources such as the standard number of days and number of personnel required for maintenance tasks of the equipment and information on the expected number of days for regular inspections to be carried out in the future are used to calculate the maximum number of machines for which maintenance tasks will be performed on the equipment and the minimum number of machines for which maintenance tasks will be performed on the equipment, which is required under the constraint that it does not exceed the period of the maintenance tasks imposed on the equipment (see Figure 17).

[0067] (7) A maintenance plan support device 100 for supporting a maintenance plan in a nuclear power plant by utilizing information from the design and / or the site, the device having an equipment status management unit 11 for managing equipment management indexes (e.g., the status of malfunctions such as performance, deterioration, and failure) of the nuclear power plant through equipment maintenance activities and maintenance actions (e.g., inspection, testing, monitoring, and patrol), a maintenance plan update unit 12 for updating a maintenance plan for the next operating cycle based on the status of the nuclear power plant and updating a long-term maintenance plan for the next and subsequent operating cycles, and a maintenance execution management unit 13 for managing the maintenance management indexes, maintenance tasks and cycles that are mandatory to be performed according to laws, regulations, and standards, resources required for maintenance, and the number of units for which maintenance is to be performed. This makes it possible to appropriately support maintenance activities in the nuclear power plant.

[0068] The present invention is not limited to the above-mentioned embodiment, and various modifications are included. For example, the above-mentioned embodiment has been described in detail to easily explain the present invention, and is not necessarily limited to those having all the configurations described. It is also possible to replace a part of the configuration of a certain embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of a certain embodiment. It is also possible to add, delete, or replace a part of the configuration of each embodiment with another configuration. In addition, each of the above-mentioned configurations, functions, processing units, processing means, etc. may be realized by hardware, for example, by designing them as integrated circuits. In addition, each of the above-mentioned configurations, functions, etc. may be realized by software by a processor interpreting and executing a program that realizes each function. Information such as a program, table, file, etc. that realizes each function can be placed in a memory, a recording device such as a hard disk or SSD (Solid State Drive), or a recording medium such as an IC card, SD card, or DVD. [Explanation of symbols]

[0069] 10 Processing section 11 Equipment Status Management Department 12 Maintenance Plan Update Division 13 Maintenance Execution Management Department 14. Conservation Planning Department 20 Memory section 21 Configuration management extraction information 22 FMEA Extraction Information 23 Maintenance activities / monitoring item extraction information 24 Field Preservation and Monitoring Extraction Information 25 Work plan management extraction information 26 Maintenance Plan Management Extraction Information 30 Input section 40 Output section 50 Communications Department 100 Maintenance planning support device 200 Database device 210 Configuration management DB 220 FMEA DB 230 Maintenance activities / monitoring item DB 240 Field maintenance and monitoring data DB 250 Work plan management DB 260 Maintenance Plan Management DB 300 Maintenance Planning Support System S100, S200 Maintenance planning support processing

Claims

1. A maintenance planning support method for supporting a maintenance plan in a nuclear power plant by utilizing information from design and / or a site, comprising: In the maintenance activities and actions for the equipment, which are carried out in accordance with the maintenance plan, when formulating a maintenance plan to prevent this based on equipment management indicators, an update plan for the next maintenance plan, which is determined based on the on-site equipment status, and an update plan for the next and subsequent long-term maintenance plans are set for the long-term maintenance plan for multiple periodic inspections that was previously planned. A maintenance planning support method comprising:

2. When setting the update proposal for the next conservation plan, A renewal plan is created using both information on the time trends of the performance, deterioration, and malfunction status of the equipment in question, and mutual comparison of the deterioration and malfunction status of similar equipment.

2. The maintenance planning support method according to claim 1 .

3. When setting the update proposal for the next conservation plan, From the long-term maintenance plan, calculate the operation period of the equipment to be maintained or similar equipment, and use the operation period to create a renewal plan.

2. The maintenance planning support method according to claim 1 .

4. When setting the next and subsequent long-term conservation plan updates, Calculate future maintenance tasks and the number of units to be maintained for the equipment or similar equipment to be maintained, and the expected operation period of the equipment 2. The maintenance planning support method according to claim 1 .

5. When setting the update proposal for the next conservation plan, Regarding the monitoring tasks for grasping the performance, deterioration, and malfunction status of the equipment, the monitoring tasks are classified according to whether they are performed while the power plant is in operation or while the plant is stopped, and whether the monitoring tasks require disassembly of the equipment or not, and the performance results of the monitoring tasks and the degree of the performance, deterioration, and malfunction status of the equipment are recorded as maintenance management indexes.

3. The maintenance planning support method according to claim 2.

6. When setting the next and subsequent long-term conservation plan updates, At least, by using information on the resources related to the standard number of days and number of personnel required for maintenance tasks of the equipment, and information on the estimated number of days for regular inspections scheduled to be performed in the future, the maximum number of machines for which maintenance tasks are performed on the equipment and the minimum number of machines for which maintenance tasks are performed on the equipment, which is required under the constraint that the period of the maintenance tasks imposed on the equipment is not exceeded, are calculated.

5. The maintenance planning support method according to claim 4.

7. A maintenance planning support device for supporting a maintenance plan in a nuclear power plant by utilizing information from design and / or a site, an equipment status management unit that manages equipment management indexes of the nuclear power plant based on equipment maintenance activities and maintenance actions; a maintenance plan updating unit that updates a maintenance plan for a next operation cycle based on a status of the nuclear power plant and updates a long-term maintenance plan for the next and subsequent operation cycles; A maintenance execution management unit that manages maintenance management indicators, maintenance tasks and cycles that are required by law, regulations, specifications, and standards, resources required for maintenance, and the number of units to be maintained. A maintenance planning support device comprising:

Citation Information

Patent Citations

  • Preventive maintenance information system

    JP1992121694A

  • Monitor, diagnosis, inspection and maintenance system for power-generating plant

    JP2003114294A

  • Life cycle maintenance schedule planning system for plant

    JP2004170225A

  • System and method for monitoring nuclear power plant

    JP2011209127A

  • Plant inspection plan creation method, plant inspection plan creation program, and plant inspection plan creation system

    JP2016014958A