Automatic marking system and method for automatic marking
The automatic marking system addresses positioning inaccuracies by using a three-dimensional measuring device and control device to adjust marking positions, ensuring precise and gap-free application of interior finishes.
Patent Information
- Application Number
- JP2023046619
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-23
- Publication Date
- 2024-10-04
- Estimated Expiration
- 2043-03-23
AI Technical Summary
The existing automatic marking systems face issues with positioning accuracy due to construction errors and concrete shrinkage, leading to deviations in marking points, which can result in improper application of interior finishes.
An automatic marking system that incorporates a three-dimensional measuring device and control device to adjust marking positions based on actual spatial coordinates, using conversion rates to correct for construction errors and potential concrete shrinkage, ensuring precise marking.
Enables accurate marking at appropriate positions, preventing gaps and ensuring proper application of interior finishes by compensating for construction deviations and concrete shrinkage.
Smart Images

Figure 2024135763000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to an automatic marking system and an automatic marking method. [Background technology]
[0002] Patent Document 1 discloses an automatic marking system equipped with a marking robot that marks preset target points. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2019-2849 A Summary of the Invention [Problem to be solved by the invention]
[0004] In the automatic marking system described in Patent Document 1, a coordinate for marking is set based on a reference mark (parent mark) marked on the floor surface in advance, and a marking robot is moved to a target point on the coordinate and marking is performed at the target point. On the other hand, the reference mark used as a reference when setting the coordinate for marking may slightly deviate from the expected position depending on the construction error of the building. If marking is performed using coordinates set based on such a slightly deviated reference mark, the difference (error) between the target point on the coordinate and the point to be marked increases as the distance from the reference point increases, and as a result, there is a risk that interior finishing, etc. cannot be performed at the specified position. In addition, generally, marking is performed when the concrete has hardened to a certain extent, but the point where marking was performed may deviate slightly from the target point due to the drying shrinkage of the concrete thereafter, and in such a case, there is a risk that interior finishing, etc. cannot be performed at the specified position.
[0005] An object of the present invention is to mark out at a more appropriate position. [Means for solving the problem]
[0006] The present invention is an automatic marking system comprising a marking device having a marking section that marks out a marking surface, a three-dimensional measuring device capable of measuring the three-dimensional spatial position of the marking device, and a control device that controls marking by the marking device based on the three-dimensional spatial position of the marking device measured by the three-dimensional measuring device, and when setting a target marking position on the marking coordinates based on the installation position of the three-dimensional measuring device from the designed marking position on the design data, the control device converts the position of the designed marking position using a predetermined conversion rate.
[0007] The present invention also provides an automatic marking method that includes the steps of setting a target marking position on a marking coordinate system based on the installation position of a three-dimensional measuring device, based on a designed marking position on design data, and controlling the movement of a marking device having a marking unit so that marking is performed at the target marking position, and when setting the target marking position based on the designed marking position, the designed marking position is converted in position using a predetermined conversion rate. Effect of the Invention
[0008] According to the present invention, marking can be performed at a more appropriate position. [Brief description of the drawings]
[0009] [Figure 1] FIG. 2 is an image diagram showing an image of marking work performed by an automatic marking system according to an embodiment of the present invention. [Diagram 2] 1 is a block diagram showing the overall configuration of an automatic marking system according to an embodiment of the present invention. [Diagram 3] 4 is a flowchart showing a procedure of marking work performed by the automatic marking system according to the embodiment of the present invention. [Figure 4] FIG. 13 is a diagram for explaining setting of a reference point. [Diagram 5] FIG. 13 is a diagram for explaining measurement of a reference point. [Figure 6]11 is a diagram for explaining the relative positional relationship between a design data coordinate system and a marking coordinate system. FIG. [Figure 7] FIG. 13 is a diagram for explaining the setting of a conversion rate. [Figure 8] FIG. 13 is a diagram for explaining setting of a reference point in a modified example. [Figure 9] 13A and 13B are diagrams for explaining measurement of a reference point in a modified example. [Figure 10] 13 is a diagram for explaining the relative positional relationship between a design data coordinate system and a marking coordinate system in a modified example. FIG. [Figure 11] FIG. 13 is a diagram for explaining the setting of a conversion rate in a modified example. [Figure 12] FIG. 13 is an image diagram showing an image of a marking operation performed by a modified example of the automatic marking system according to an embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0010] Hereinafter, an automatic marking system and an automatic marking method according to an embodiment of the present invention will be described with reference to the drawings.
[0011] An automatic marking system 100 according to an embodiment of the present invention is a system that automatically draws marking lines and the like that serve as a reference for construction work on the floor surface of a building, etc. First, the configuration of the automatic marking system 100 will be described with reference to Figs. 1 and 2.
[0012] 1, the automatic marking system 100 includes a marking device 10 having a marking section 18 that marks a marking surface such as a floor surface 1, a three-dimensional measuring device 50 that can measure the three-dimensional spatial position of the marking device 10, and a control device 30 that controls marking by the marking device 10 based on the three-dimensional spatial position of the marking device 10 measured by the three-dimensional measuring device 50. In the following, a case will be described in which the control device 30 is built into the marking device 10, but the control device 30 may be built into the three-dimensional measuring device 50 or may be provided separately from the marking device 10 and the three-dimensional measuring device 50.
[0013] The marking device 10 is an autonomous mobile robot that does not require external operation, and has, for example, as shown in Figure 1, a running unit 12 capable of running on a floor surface 1, a marking unit 18 that marks the floor surface 1, and a target unit 20 that is tracked by a three-dimensional measuring device 50.
[0014] The traveling unit 12 has three omni-wheels (omnidirectional wheels) whose rotation direction and rotation speed are independently controlled. Each omni-wheel is rotated by an electric motor (not shown) via an axle (not shown).
[0015] The three omni-wheels are arranged at equal intervals (120° intervals) on the circumference of a common circle, and the axial directions of the axles are directed toward the center of the common circle. In other words, the three omni-wheels are arranged so that the axial directions of the axles are directed toward a common center point. Note that the omni-directional wheels of the running unit 12 are not limited to omni-wheels, and may be, for example, Mecanum wheels or Moebius wheels.
[0016] By configuring the traveling unit 12 to have a plurality of omnidirectional wheels in this manner, the marking device 10 can move smoothly in all directions without turning.
[0017] The marking unit 18 is an inkjet printing device and has a nozzle head (not shown) which has multiple nozzles arranged at a predetermined small interval that can eject ink onto the floor surface 1, and an ink supply unit (not shown) which supplies ink to the nozzle head.
[0018] The target unit 20 is a directional prism capable of reflecting the laser light irradiated from the three-dimensional measuring device 50, and is rotated by a target rotation unit 21 described below so as to constantly point the target unit 20 toward the three-dimensional measuring device 50. Note that the target unit 20 may be a 360-degree prism, in which case a target rotation unit need not be provided.
[0019] 2, in addition to the traveling unit 12, marking unit 18, and target unit 20, the marking device 10 is provided with an attitude detection unit 26 capable of detecting the attitude of the marking device 10 while traveling, a communication unit 27 for transmitting and receiving data to and from the three-dimensional measuring device 50 and an external server 90, a target rotation unit 21 for rotating the target unit 20 so that the target unit 20 faces the three-dimensional measuring device 50, and a battery (not shown) for supplying power to the traveling unit 12 and other electrical equipment. In addition, the marking device 10 is provided with a control device 30 as described above.
[0020] The attitude detection unit 26 is a so-called inertial measurement unit (IMU) in which an acceleration sensor, a gyro sensor, and a geomagnetic sensor that can detect the attitude of the marking device 10 are integrated into one unit, and for example, even if the traveling direction of the marking device 10 changes, it is possible to grasp the position where marking is being performed by the marking unit 18.
[0021] The communication unit 27 is a short-range wireless communication device such as BLE (Bluetooth (registered trademark) Low Energy) or Wi-Fi (registered trademark), and is mainly used when transmitting and receiving data to and from the three-dimensional measuring device 50. Note that the communication unit 27 may be equipped with a general wireless communication device capable of transmitting and receiving data via an Internet line.
[0022] As shown in FIG. 1, the three-dimensional measuring device 50 includes a cart unit 60 that is movable on a floor surface 1, and a measuring unit 55 that is placed on the cart unit 60 and is capable of measuring the three-dimensional spatial position of an object to be measured based on the reflected light of laser light irradiated onto the object to be measured.
[0023] The cart unit 60, like the traveling unit 12 of the marking device 10, has three omni wheels 61, a motor (not shown) provided for each omni wheel 61, and a battery (not shown) that supplies power to the motor. This allows the three-dimensional measuring device 50 to move smoothly in all directions without turning, like the marking device 10.
[0024] The wheels of the cart unit 60 are not limited to the omni wheels 61, and may be Mecanum wheels or Moebius wheels. Since the movement of the cart unit 60 is not as frequent as that of the marking device 10, the cart unit 60 may be a general traveling device that is capable of moving forward, backward, left and right and can move to a predetermined position by itself.
[0025] Further, the cart unit 60 is provided with an installation base 62 for installing the measurement unit 55 on the cart unit 60. Note that, although the installation base 62 shown in Fig. 1 is simply a columnar structure, it may be configured to be extendable and contractible in the vertical direction.
[0026] The measuring unit 55 is a three-dimensional coordinate measuring instrument such as a laser tracker or a tracking total station, and has an optical measuring unit 56 consisting of an emitter that irradiates laser light and a light receiving unit that receives the reflected laser light, and a camera 57 that can capture a wide range of images in the direction of the laser light irradiated from the optical measuring unit 56.
[0027] The optical measuring unit 56 and the camera 57 are configured to be rotatable in the horizontal direction around the vertical axis C1 and to be rotatable in the vertical direction around the horizontal axis C2. Therefore, the measuring unit 55 can capture and track the measurement object by the camera 57 even if the measurement object moves.
[0028] The measuring unit 55 measures the distance to the measurement object based on the time from when laser light is irradiated from the light emitting unit of the optical measuring unit 56 to when the laser light reflected by the measurement object is received by the light receiving unit, and is capable of measuring the three-dimensional spatial position coordinates of the measurement object based on the measured distance, the self-position of the measuring unit 55, and the irradiation angle of the laser light.
[0029] The measuring unit 55 automatically determines its own position in the space in advance by measuring the distance and angle to a plurality of reference prisms 70 installed in the space where marking is performed. The measuring unit 55 automatically updates its own position every time the three-dimensional measuring device 50 moves and stops. In this way, the measuring unit 55 always grasps its own position coordinates in the space where marking is performed, and therefore can always accurately measure, for example, the three-dimensional spatial position coordinates of the target unit 20 in the space where marking is performed, i.e., the three-dimensional spatial position coordinates of the marking device 10. The three-dimensional measuring device 50 also transmits the depression angle and rotation angle of the measuring unit 55 required to control the rotation angle of the target rotation unit 21 to the control device 30.
[0030] As shown in the block diagram of Figure 2, the three-dimensional measuring device 50 has a CPU (Central Processing Unit) as a control unit 51, a ROM (Read Only Memory) and RAM (Random Access Memory) as a memory unit 52, a microcomputer equipped with an input / output interface (I / O interface), and a communication unit 53 for sending and receiving data to and from the marking device 10 and an external server 90.
[0031] Based on instructions from the control device 30, the control unit 51 controls the operation of the trolley unit 60 and the measurement unit 55, and transmits the measurement values measured by the measurement unit 55 to the marking device 10 and an external server 90 via the communication unit 53.
[0032] The memory unit 52 pre-stores control programs and the like to be executed by the control unit 51, and also stores measurement values measured by the measurement unit 55 and data acquired from an external server 90, etc. via the communication unit 53.
[0033] The communication unit 53 is a short-range wireless communication device similar to the short-range wireless communication device provided in the marking device 10, and is mainly used when transmitting and receiving data to and from the marking device 10. Note that the communication unit 53 may be equipped with a general wireless communication device capable of transmitting and receiving data via an Internet line.
[0034] In this way, the three-dimensional measuring device 50 is configured to be able to measure the three-dimensional spatial position (position coordinates) of the target portion 20 in a predetermined coordinate system based on its own position determined from the positions of multiple reference prisms 70.
[0035] In addition, the three-dimensional spatial position of the target portion 20 may be calculated in the control device 30. In this case, various data such as distance and angle required to calculate the three-dimensional spatial position of the target portion 20 is transmitted from the three-dimensional measuring device 50 to the control device 30.
[0036] The control device 30 controls the operation of the traveling section 12 and the marking section 18 of the marking device 10 based on the three-dimensional spatial position of the target section 20 of the marking device 10 measured by the three-dimensional measuring device 50 and design data such as a CAD drawing that has been loaded in advance.
[0037] As shown in FIG. 2, the control device 30 is a microcomputer including a CPU (Central Processing Unit) as a control unit 31, a ROM (Read Only Memory) and a RAM (Random Access Memory) as a storage unit 32, and an input / output interface (I / O interface).
[0038] The control unit 31 has a relative relationship calculation unit 33 that calculates the relative positional relationship between a marking coordinate system (measurement coordinate system) based on the installation position of the three-dimensional measuring device 50 and a design data coordinate system set in the design data, a conversion rate calculation unit 34 that calculates a conversion rate (conversion scale) for enlarging or reducing the size of the design marking surface to match the size of the actual marking surface, and a target marking position setting unit 35 that converts the design marking position on the design data coordinate system to calculate the target marking position on the marking coordinate system. Note that these relative relationship calculation unit 33 and the like are shown as virtual units of the respective functions of the control unit 31 and do not mean that they exist physically. Also, the above functions are part of the control executed by the control unit 31, and the control unit 31 also executes controls related to functions other than these as needed.
[0039] The relative relationship calculation unit 33 obtains the relative positional relationship between the origin position of the marking coordinate system and the origin position of the design data coordinate system by matching, under predetermined conditions, the position coordinates in the design data, which are the design coordinates of the multiple reference points P1, P2, P3 set in advance, with the position coordinates of the reference prism 70 installed at the multiple reference points P1, P2, P3 actually measured by the three-dimensional measuring device 50. Specifically, the relative positional relationship is obtained, for example, as a transformation matrix A capable of transforming the design data into the marking coordinate system.
[0040] Here, in order to grasp the relative positional relationship between the design data coordinate system and the marked-out coordinate system based on the installation position of the three-dimensional measuring device 50, the positions of multiple reference points P1, P2, and P3 where the reference prism 70 will be installed are marked out in advance on the floor surface 1 of the building.
[0041] The positions of the reference points P1, P2, and P3 are marked based on reference marks (parent marks) such as center lines and center lines marked on pillars and walls, but the positions of the reference marks may deviate slightly from the expected positions depending on the construction error of the building. For this reason, the positions of the reference points P1, P2, and P3 may also deviate slightly from the designed positions.
[0042] If marking is performed using a marking coordinate system set based on reference points P1, P2, and P3 that are slightly offset from the designed positions in this way, the difference (error) between the actual marked position and the designed position to be marked increases as the distance from the origin of the coordinate system increases, and as a result, there is a risk that interior finishing, etc., cannot be performed in the designated position. For example, if a span (beam) with a length of L1 (7200 mm) in the design is actually L2 (7204 mm), and N locations (8 locations) are marked out at equal intervals from one end as designed, and a panel with a width of L1 / N (900 mm width) is laid along the marking line, a gap of (L2-L1) size (4 mm) will be created on the other end.
[0043] In order to suppress the influence of such building construction errors and the like on the marking position, the conversion rate calculation unit 34 calculates a conversion rate G based on the difference between the measurement position data of the multiple reference points P1, P2, P3 measured by the three-dimensional measuring device 50, i.e., the data corresponding to the size of the actual marking surface, and the design position data of the multiple reference points P1, P2, P3 calculated from the design data, i.e., the data corresponding to the size of the designed marking surface. A specific example of a method for calculating the conversion rate G will be described later.
[0044] The target marking position setting unit 35 converts the design marking position on the design data coordinate system using the conversion rate G calculated by the conversion rate calculation unit 34, and further converts the coordinates using the conversion matrix A calculated by the relative relationship calculation unit 33, thereby calculating the target marking position on the marking coordinate system. The target marking position converted from the design marking position by the target marking position setting unit 35 is stored in the memory unit 32.
[0045] In this manner, the marking device 10 is controlled by the control device 30 so that the marking unit 18 advances by tracing the target marking position set by the target marking position setting unit 35. In other words, the control device 30 controls the traveling unit 12 of the marking device 10 so that the target marking position (target position coordinates) set by the target marking position setting unit 35 and the three-dimensional spatial position coordinates of the marking unit 18 always coincide with each other.
[0046] The design data transmitted in advance from an external server 90 or the like to the control device 30 and stored in the memory unit 32 includes data regarding the locations where marking is to be performed. However, this data has not been created with consideration given to the efficiency of the marking work by the marking device 10, and therefore, if marking is to be performed faithfully according to the design data, the work time may be lengthened.
[0047] Therefore, the target marking position setting unit 35 may have a function of converting the designed marking position on the design data into drawing data suitable for marking by the marking device 10 before setting the target marking position.
[0048] Specifically, since it is relatively easier to draw each of the two line segments that make up a broken line with a bend point than to draw the broken line with a bend point all at once, for example, if the design data contains a broken line with a bend point, the two line segments that make up the broken line are each extended at the bend point, and the bend point is converted into an intersection where the two line segments intersect.
[0049] In this way, by preventing broken lines from being included in the drawing data generated by the target marking position setting unit 35, it is possible to improve the efficiency of the marking work and to make the positions of intersections drawn by marking almost coincide with the positions of the designed bend points. Note that such data conversion may be performed on the target marking positions determined by the target marking position setting unit 35, rather than on the designed marking positions.
[0050] Next, an automatic marking method for automatically marking the floor surface 1 by the automatic marking system 100 configured as described above will be described with reference to Figs. 3 to 7. Fig. 3 is a flow diagram showing the procedure when the automatic marking system 100 automatically performs marking work, and Figs. 4 to 7 are diagrams for explaining the method for calculating the conversion rate G described above.
[0051] When measuring the position of the reference prism 70 by the three-dimensional measuring device 50 installed at an arbitrary position on the floor surface 1, first, in step S11, the control device 30 extracts position coordinates (x1 to x3, y1 to y3) on the design data of multiple reference points P1, P2, P3 where the reference prism 70 is installed, as shown in Fig. 4 (data extraction process). The design data is BIM (Building Information Modeling) or the like including three-dimensional data of the space where marking out is to be performed, and is read in advance from an external server 90 or the like and stored in the storage unit 32.
[0052] Subsequently, in step S12, the position coordinates of the reference prism 70 installed at each of the reference points P1, P2, and P3 are successively measured by the three-dimensional measuring device 50 (reference point measuring step).
[0053] Specifically, first, a reference prism 70 is placed at the first reference point P1 to obtain the position coordinates of the first reference point P1 in the marking coordinate system (measurement coordinate system) (first measurement point P1t(x1t, y1t)), then a reference prism 70 is placed at the second reference point P2 to obtain the position coordinates of the second reference point P2 in the marking coordinate system (second measurement point P2t(x2t, y2t)), and similarly, the position coordinates of the third reference point P3 in the marking coordinate system (third measurement point P3t(x3t, y3t)) are obtained (see Figure 5).
[0054] The data of the measurement points P1t, P2t, and P3t thus measured is stored in the storage unit 32 as measurement position data.
[0055] Next, in step S13, the relative positional relationship between the design data coordinate system and the marking coordinate system is calculated by the relative relationship calculation unit 33 based on the position coordinates of each reference point P1, P2, P3 extracted in step S11 and the position coordinates of each measurement point P1t, P2t, P3t measured in step S12 (relative relationship calculation process).
[0056] In order to obtain the relative positional relationship between the design data coordinate system and the marking coordinate system, first, when the position of the first reference point P1 and the position of the first measurement point P1t are the same position, as shown in Fig. 6, the origin position of the design data coordinate system and the X- and Y-axis directions of the design data coordinate system are obtained when the second distance L2 between the second reference point P2 and the second measurement point P2t and the third distance L3 between the third reference point P3 and the third measurement point P3t are respectively minimum, for example, when the difference distance (L2+L3) obtained by adding the second distance L2 and the third distance L3 is minimum. Note that the first reference point P1 may be a point closer to the origin position of the design data coordinate system than the second reference point P2 and the third reference point P3, and may be a point corresponding to the origin position of the design data coordinate system.
[0057] Once the relative positional relationship between the origin positions of each coordinate system and the axial relationship between each coordinate system are obtained in this way, a transformation matrix A for transforming data from the design data coordinate system to the marking coordinate system or from the marking coordinate system to the design data coordinate system is obtained as a matrix indicating the relative positional relationship between the design data coordinate system and the marking coordinate system. Note that the transformation matrix for transforming the coordinates from the design data coordinate system to the marking coordinate system is a regular matrix, and the transformation matrix for transforming the coordinates from the marking coordinate system to the design data coordinate system is its inverse matrix, but in the following explanation, either matrix will be referred to as transformation matrix A.
[0058] In the next step S14, a conversion rate G for enlarging or reducing the size of the designed marked-out surface to match the size of the actual marked-out surface is calculated (conversion rate calculation step).
[0059] As described above, the actual positions of reference points P1, P2, and P3 may deviate slightly from their designed positions, and such errors appear as a difference between the position of the second measurement point P2t and the position of the second reference point P2, and a difference between the position of the third measurement point P3t and the position of the third reference point P3, assuming that the position of the first measurement point P1t coincides with the position of the first reference point P1, as shown in Figure 7.
[0060] For this reason, the conversion rate calculation unit 34 calculates the conversion rate G based on the difference between the measurement position data of multiple reference points P1, P2, P3 measured by the three-dimensional measuring device 50 and the design position data of multiple reference points P1, P2, P3 calculated from the design data.
[0061] Specifically, the X-axis conversion rate Gx in the X-axis direction is calculated using the following formula (1) based on the difference dx (=x2t-x2) between the X-coordinate value (x2t) of the second measurement point P2t and the X-coordinate value (x2) of the second reference point P2.
[0062] Gx=dx / x2 (1)
[0063] Similarly, the Y-axis conversion rate Gy in the Y-axis direction is calculated using the following equation (2) based on the difference dy (=y3t-y3) between the Y coordinate value (y3t) of the third measurement point P3t and the Y coordinate value (y3) of the third reference point P3.
[0064] Gy=dy / y3 (2)
[0065] In other words, the conversion rate G is set based on the ratio between the design length and the actual length of the marking surface in the X-axis direction, and the ratio between the design length and the actual length of the marking surface in the Y-axis direction.
[0066] Therefore, by using the conversion rate G to convert the position (scale) of the design data along the X-axis direction according to the X-axis conversion rate Gx, and converting the position (scale) of the design data along the Y-axis direction according to the Y-axis conversion rate Gy, the marking position on the design data will be converted to a position corresponding to the size of the actual marking surface.
[0067] For example, if the design span (beam) length in the X-axis direction is L1 and the actual span length is L2, then if N locations are marked out at equal intervals from one end of the beam as designed, and a panel with a width of L1 / N is laid along the marked out lines, a gap of size (L2-L1) will be created on the other end.
[0068] In contrast, when the marking positions on the design data are converted at a predetermined conversion rate Gx as described above, the marking positions between beams are converted to positions that are expanded or contracted by an amount corresponding to the difference between the design span and the actual span ((L2-L1) / L1). Therefore, a gap of size (L2-L1) is distributed to N joints by (L2-L1) / N each, preventing a relatively large gap from occurring on the other end side.
[0069] The conversion rate G thus obtained is stored in the memory unit 32.
[0070] Note that the above-mentioned formula for calculating the conversion rate G is an example and is not limited to this. For example, the X-axis conversion rate Gx may be calculated from the X-coordinate values of the third measurement point P3t and the third reference point P3, or may be the average value of the value calculated from the X-coordinate values of the second measurement point P2t and the second reference point P2 and the value calculated from the X-coordinate values of the third measurement point P3t and the third reference point P3.
[0071] Furthermore, the number of reference points is not limited to three, and may be four or more, or may be two. When there are two reference points, the X-axis conversion rate Gx is calculated from the X-coordinate value of the second measurement point P2t and the second reference point P2, and the Y-axis conversion rate Gy is calculated from the Y-coordinate value of the second measurement point P2t and the second reference point P2.
[0072] Also, in the above example, the conversion rate G is calculated for both the X-axis and Y-axis components, but if there is a direction in which precision is not required in construction such as interior finishing, it is possible to set the differences dx, dy in that direction to zero so that the conversion rate in that direction is not calculated.
[0073] In addition, the difference for calculating the conversion rate G is not limited to the difference in the X-axis and Y-axis directions, but may be the difference in any axis direction on the XY plane (for example, the axis direction defined by y=x). In other words, the conversion rate G is calculated based on the ratio between the design length and the actual length of the marking surface in any axis direction.
[0074] Once the conversion rate G is calculated, the process proceeds to step S15, where the target marking position at which marking is to be performed by the marking device 10 is set by the above-mentioned target marking position setting unit 35 (target position setting step).
[0075] Specifically, a designed marking position within a predetermined range from the current position of the marking device 10 measured by the three-dimensional measuring device 50 is extracted from the design data, and the X coordinate value of the extracted designed marking position is scaled by an X-axis conversion rate Gx according to the magnitude of the X coordinate value, and the Y coordinate value is scaled by a Y-axis conversion rate Gy according to the magnitude of the Y coordinate value. In other words, the closer a designed marking position is to the origin, the smaller the change in its position will be, and the farther a designed marking position is from the origin, the greater the change in its position will be.
[0076] Then, the design marking position on the design data coordinate system, which has been position-transformed using the conversion rate G, is transformed into the marking coordinate system using the transformation matrix A obtained in step S13, thereby determining the target marking position on the marking coordinate system within a specified range from the current position of the marking device 10.
[0077] In other words, the target marking position where marking is performed by the marking device 10 is calculated as the marking device 10 moves.
[0078] By calculating the target marking positions only around the marking device 10 in this manner, the calculation load on the control device 30 can be reduced.
[0079] In the following step S16, the control device 30 controls the traveling unit 12 of the marking device 10 to perform marking to the target marking position set in step S15 (marking execution step).
[0080] When marking at the set target marking position is completed, the process proceeds to step S17, where the control device 30 determines whether or not all of the planned marking work has been completed.
[0081] When all the scheduled marking work has been completed, the processing ends and the marking device 10 goes into a standby state until an instruction for the next work is received from the server 90.
[0082] On the other hand, if the scheduled marking work has not yet been completed, the process returns to step S15, and the marking work continues. After that, the marking work is performed through the above-mentioned steps until the scheduled marking work is completed.
[0083] As described above, while the reference points P1, P2, and P3 may deviate slightly from the design positions, the marking by the marking device 10 is performed when the concrete has hardened to a certain extent, so the marking points may deviate slightly from the target points depending on the drying shrinkage of the concrete. Therefore, in such cases, there is a risk that the interior finishing, etc. cannot be performed at the specified position.
[0084] Therefore, the above-mentioned conversion rate G may be preset based on the shrinkage rate of the concrete to be marked out, and in this case, as shown in step S21 in Fig. 3, input of the conversion rate G is performed instead of step S14. The conversion rate G based on the shrinkage rate of the concrete may be stored in the storage unit 32 in advance, and in this case, the conversion rate G stored in the storage unit 32 is read in step S21.
[0085] Also, a conversion rate G based on the shrinkage rate of concrete may be added to the conversion rate G calculated in step S14. This makes it possible to reduce the influence on marking of both errors caused by the deviation of the positions of the reference points P1, P2, and P3, i.e., errors occurring before marking is performed, and errors caused by the drying shrinkage of concrete, i.e., errors occurring after marking is performed.
[0086] 3, instead of step S15, all the design marking positions in the design data may be converted collectively by the conversion rate G to obtain all the target marking positions. If the design data is not CAD data but is, for example, image data in which the design marking positions are visualized, it is possible to convert all the design marking positions collectively by stretching or reducing the image data along a predetermined axial direction.
[0087] According to the above embodiment, the following effects are achieved.
[0088] In the automatic marking system 100 configured as described above, the target marking position at which the marking device 10 marks out is determined by converting the designed marking position set based on the design data using a predetermined conversion rate G set in accordance with the deviation of the reference mark (parent mark) and the drying shrinkage of concrete.
[0089] In this way, by calculating the target marking position by converting (enlarging / reducing) the design marking position at a predetermined conversion rate G rather than using the design marking position as is, it is possible to mark out at a more appropriate position even if the reference mark is misaligned or the concrete dries and shrinks after marking. As a result, it becomes possible to carry out interior finishing and the like at the specified position according to the marking line.
[0090] For example, if the design span (beam) length is L1 and the actual span length is L2, then if you mark out N locations at equal intervals from one end of the beam as designed, and then lay a panel with a width of L1 / N along the marking lines, a gap of size (L2-L1) will be created on the other end.
[0091] In contrast, when the marking positions on the design data are converted at a predetermined conversion rate G as in the above embodiment, the marking positions between beams are converted to positions that are expanded or contracted by an amount corresponding to the difference between the design span and the actual span ((L2-L1) / L1). Therefore, a gap of size (L2-L1) is distributed to N joints by (L2-L1) / N each, preventing a relatively large gap from occurring on the other end side. This makes it possible to carry out interior finishing and the like without creating excessive gaps.
[0092] In addition, the following modified examples are also within the scope of the present invention, and it is possible to combine the configuration shown in the modified example with the configuration described in the above embodiment, or to combine the configurations described in the different modified examples below.
[0093] In the above embodiment, the conversion rate G is calculated as two directional components, an X-axis component and a Y-axis component. Alternatively, the conversion rate may be calculated as a transformation matrix that takes into account stretching changes and distortions that accompany movement, expansion / contraction, rotation, and shear. The marking out procedure when the conversion rate G is calculated as a transformation matrix will be described below with reference to Figs. 3, 8 to 11.
[0094] In this case, when measuring the position of the reference prism 70 using the three-dimensional measuring device 50 installed at any position on the floor surface 1, first, in step S11, the control device 30 extracts the position coordinates (x1 to x4, y1 to y4) on the design data of multiple reference points P1, P2, P3, and P4 at which the reference prism 70 is installed, as shown in FIG. 8 (data extraction process).
[0095] Subsequently, in step S12, the position coordinates of the reference prism 70 installed at each of the reference points P1, P2, P3, and P4 are sequentially measured by the three-dimensional measuring device 50 as shown in Fig. 9 (reference point measuring step). The data of each of the measurement points P1t, P2t, P3t, and P4t thus measured is stored in the storage unit 32 as measurement position data.
[0096] Next, in step S13, the relative positional relationship between the design data coordinate system and the marking coordinate system is calculated by the relative relationship calculation unit 33 based on the position coordinates of each reference point P1, P2, P3, and P4 extracted in step S11 and the position coordinates of each measurement point P1t, P2t, P3t, and P4t measured in step S12 (relative relationship calculation process).
[0097] In order to determine the relative positional relationship between the design data coordinate system and the marking out coordinate system, first, as shown in Figure 10, the origin position of the design data coordinate system is determined when the first distance L1 between the first reference point P1 and the first measurement point P1t, the second distance L2 between the second reference point P2 and the second measurement point P2t, the third distance L3 between the third reference point P3 and the third measurement point P3t, and the fourth distance L4 between the fourth reference point P4 and the fourth measurement point P4t are each minimum, that is, when the differential distance (L1+L2+L3+L4) obtained by adding up the distances L1, L2, L3, and L4 is minimum.
[0098] Once the relative positional relationship between the origin positions of each coordinate system and the axial relationship between each coordinate system are determined in this manner, a transformation matrix A for coordinate transforming data from the design data coordinate system to the marking coordinate system, or from the marking coordinate system to the design data coordinate system, is determined to indicate the relative positional relationship between the design data coordinate system and the marking coordinate system, as in the above embodiment.
[0099] In the next step S14, a conversion rate G for enlarging or reducing the size of the designed marked-out surface to match the size of the actual marked-out surface is calculated (conversion rate calculation step).
[0100] As described above, the actual positions of reference points P1, P2, P3, and P4 may deviate slightly from their designed positions, and such errors appear as a difference between the position of the first measurement point P1t and the position of the first reference point P1, a difference between the position of the second measurement point P2t and the position of the second reference point P2, a difference between the position of the third measurement point P3t and the position of the third reference point P3, and a difference between the position of the fourth measurement point P4t and the position of the fourth reference point P4, as shown in Figure 11.
[0101] In other words, in this modified example, the error between the actual position and the designed position appears as a distortion in the shape of the quadrangle (solid line in Figure 11), which is a polygon formed by each of the reference points P1, P2, P3, and P4, and the quadrangle (dashed line in Figure 11), which is a polygon formed by each of the measurement points P1t, P2t, P3t, and P4t.
[0102] For this reason, in this modified example, the transformation rate G is obtained as an affine transformation matrix B, which is a transformation matrix capable of indicating a change in shape accompanied by distortion.
[0103] Specifically, by appropriately combining various transformation matrices such as translation transformation, scaling transformation, rotation transformation, and shear transformation, an affine transformation matrix B capable of transforming each reference point P1, P2, P3, and P4 into each corresponding measurement point P1t, P2t, P3t, and P4t is obtained using a known method as a transformation rate G.
[0104] In other words, the conversion rate G in this modified example is set based on the difference between the design position data of the polygon formed by multiple reference points P1, P2, P3, and P4 and the measurement position data of the polygon formed by the corresponding multiple measurement points P1t, P2t, P3t, and P4t, i.e., based on how the shape formed by the measurement position data is distorted relative to the shape formed by the design position data.
[0105] Therefore, if the design data is transformed on the design data coordinate system by the affine transformation matrix B (transformation rate G), the designed marking position on the design data is transformed to a position according to the size of the actual marking surface.
[0106] Specifically, for example, a design marking position close to the first reference point P1 is transformed in position along the direction from the first reference point P1 to the first measurement point P1t (the distortion direction of the first reference point P1), while a design marking position close to the fourth reference point P4 is transformed in position along the direction from the fourth reference point P4 to the fourth measurement point P4t (the distortion direction of the fourth reference point P4). Note that the design marking positions near the center of the polygon formed by the multiple reference points P1, P2, P3, and P4 hardly change position due to the position transformation, while the design marking positions farther from the center change position more greatly due to the position transformation.
[0107] In this way, the direction in which the design marking position is converted is not a fixed direction, but differs depending on the location of the design marking position, and is a direction along the distortion direction estimated to be occurring at the location of the design marking position.
[0108] 11, even if the directions in which each of the reference points P1, P2, P3, and P4 deviate from the design position are different, all the design marking positions in the design data are converted to positions that are expanded or contracted according to the ratio of the design length and the actual length of the marking surface in the direction of deviation estimated at the location of the design marking position. Therefore, in this modified example as well, it is possible to prevent relatively large gaps from occurring locally when a panel having a predetermined width is laid, as in the above embodiment.
[0109] The reference points forming the polygon are not limited to four, but may be five or more, or may be three. When there are three reference points, a triangle is formed.
[0110] The affine transformation matrix B thus obtained is stored as a transformation rate G in the storage unit 32 .
[0111] Once the affine transformation matrix B is determined, the process proceeds to step S15, where the target marking position at which marking is to be performed by the marking device 10 is set by the above-mentioned target marking position setting unit 35 (target position setting step).
[0112] Specifically, a design marking position within a predetermined range from the current position of the marking device 10 measured by the three-dimensional measuring device 50 is extracted from the design data, and the extracted design marking position is transformed in position using an affine transformation matrix B (transformation rate G).
[0113] Then, the design marking position on the design data coordinates, which has been position-transformed by the affine transformation matrix B, is coordinate-transformed onto the marking coordinates using the transformation matrix A obtained in step S13, thereby obtaining the target marking position on the marking coordinates within a specified range from the current position of the marking device 10.
[0114] Steps S16 and onwards are the same as in the above embodiment, and therefore the description thereof will be omitted.
[0115] In the above example, both the X-axis component and the Y-axis component are referenced when determining the affine transformation matrix B, but if there is a direction in which precision is not required for construction such as interior finishing, it is possible to set the difference in that direction to zero so that the difference in that direction is not referenced. Also, the affine transformation matrix B may be preset based on the shrinkage rate of the concrete on which marking is performed.
[0116] In the above modified example, as in the above embodiment, the designed marking position is not used as the target marking position as it is, but the target marking position is obtained by converting (enlarging / reducing) the designed marking position at a predetermined conversion rate G, so that marking can be performed at a more appropriate position even if the reference mark is misaligned or the concrete dries and shrinks after marking. As a result, it becomes possible to carry out interior finishing and the like at a predetermined position according to the marking line.
[0117] Further, the marking device 10 in the above embodiment is a marking robot that performs marking while moving, but it may be a marking robot that is capable of performing marking even in a stationary state, such as the marking device 110 shown in FIG. 12.
[0118] The automatic marking system 200 shown in Figure 12 comprises a marking device 110 having a marking section 118 that marks a marking surface such as a floor surface 1, a three-dimensional measuring device 50 that can measure the three-dimensional spatial position of the marking device 110, and a control device 130 that controls marking by the marking device 110 based on the three-dimensional spatial position of the marking device 110 measured by the three-dimensional measuring device 50.
[0119] The marking device 110 has a running section 112 capable of running on the floor surface 1, a multi-joint arm section 114 extending from the running section 112 toward the marking surface, a marking section 118 provided at the tip of the multi-joint arm section 114, and a target section 120 provided at the tip of the multi-joint arm section 114 together with the marking section 118 and whose position and orientation are detected by the three-dimensional measuring device 50, and is configured so that the marking section 118 is provided at the tip of the multi-joint arm section 114 as shown in Figure 12.
[0120] Therefore, with this automatic marking system 200, it is possible to draw marking lines within the movable range of the articulated arm unit 114 while the marking device 110 is stopped, and it is also possible to draw marking lines on the marking surface while the marking device 110 is moving.
[0121] In the above embodiment, the conversion rate G has been described as converting the position of the designed marking position on a plane, but since the three-dimensional measurement device 50 can measure the three-dimensional position of the reference point, the conversion rate G may be set as converting the three-dimensional position of the designed marking position. In this case, it becomes possible to mark out at a more appropriate position not only when marking out a floor surface, but also when marking out a wall surface or a step surface.
[0122] Although the embodiments of the present invention have been described above, the above-mentioned embodiments merely show some of the application examples of the present invention, and it is not intended that the technical scope of the present invention be limited to the specific configurations of the above-mentioned embodiments. [Explanation of symbols]
[0123] 100,200···Automatic marking system 10,110... Marking device 18,118... Marking section 30,130...Control device 50...3D measuring device 70...Reference prism
Claims
1. An automatic marking system, A marking device having a marking unit for marking a marking surface; A three-dimensional measuring device capable of measuring a three-dimensional spatial position of the marking device; a control device that controls marking by the marking device based on the three-dimensional spatial position of the marking device measured by the three-dimensional measuring device; the control device converts the designed marking position in the design data into a target marking position on a marking coordinate system based on an installation position of the three-dimensional measuring device, using a predetermined conversion rate when setting the designed marking position on the design data. Automatic marking system.
2. the conversion rate is set based on a difference between measurement position data of the reference point measured by the three-dimensional measuring device and design position data of the reference point calculated from the design data. The automatic marking system according to claim 1 .
3. The conversion ratio is set based on the difference in a predetermined axial direction, The target marking position is set based on the designed marking position converted by the conversion ratio along the predetermined axis direction. The automatic marking system according to claim 2.
4. the conversion rate is set based on a distortion of the measurement position data with respect to the design position data of a polygon formed by a plurality of the reference points; The target marking position is set based on the design marking position that has been transformed by the transformation ratio along the distortion direction estimated at the location of the design marking position. The automatic marking system according to claim 2.
5. The conversion rate is set based on the shrinkage rate of the concrete to be marked out. The automatic marking system according to claim 1 .
6. The target marking position to be marked by the marking device is calculated at any time by the control device based on the designed marking position and the conversion rate.
6. The automatic marking system according to claim 1 .
7. An automatic marking method, comprising: A step of setting a target marking position on a marking coordinate system based on an installation position of the three-dimensional measuring device, based on a designed marking position on the design data; A step of controlling the movement of a marking device having a marking portion so that the marking is performed at the target marking position by the marking device, When setting the target marking position based on the designed marking position, the designed marking position is converted into a position by a predetermined conversion rate. Automatic marking method.
8. setting the conversion rate based on a difference between measurement position data of the reference point measured by the three-dimensional measuring device and design position data of the reference point calculated from the design data, The automatic marking method according to claim 7.
Citation Information
Patent Citations
Large-scale grotto instrument-measuring imaging visual geological recording method
CN101709964A
Laser positioning automatic paying-off device and method in tunnel
CN109655045A
Insert installation position collating method and insert installation position collating system
JP2009133082A
Method and system for verifying installation position of metal insert
JP2010048581A
Construction method for reducing crack in reinforced concrete structure
JP2011080223A