Pump installation device, pump installation method, and pump withdrawal method

The pump installation device with a closed work chamber and remote-controlled crane system addresses the challenges of purge gas usage and worker safety during submersible pump operations in liquefied gas storage tanks, achieving safe and efficient pump installation and removal.

JP2024141406APending Publication Date: 2024-10-10EBARA CORP
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2023053021
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-29
Publication Date
2024-10-10

AI Technical Summary

Technical Problem

The existing methods for installing and removing submersible pumps from liquefied gas storage tanks require large amounts of expensive purge gas to prevent boil-off gas release and pose safety risks to workers due to exposure to low-temperature cables and hazardous atmospheres.

Method used

A pump installation device with an actuator-driven door, suspension and power cables, and a crane system that operates within a closed work chamber, allowing remote control for safe installation and removal of submersible pumps, minimizing purge gas usage and preventing boil-off gas release.

Benefits of technology

The system enables safe and efficient installation and removal of submersible pumps by reducing purge gas consumption to zero and preventing boil-off gas release, while ensuring worker safety by maintaining a controlled environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024141406000001_ABST
    Figure 2024141406000001_ABST
Patent Text Reader

Abstract

To provide a pump installation device which can reduce a quantity of purge gas for use in prevention of discharge of boil-off gas (BOG) from a pump column at the carry-in of a submerged-type pump to the pump column and the pull-up of the pump from the pump column, and can construct safe working environment.SOLUTION: A pump installation device includes a working chamber 1 which forms a closed working space 15, an actuator drive-type door 12 for covering an upper opening 3a of a pump column 3, a suspension cable 23 for suspending a submerged-type pump 2 into the pump column 3, a power cable 36 for supplying electric power to the submerged-type pump 2, and a crane 40 for ascending and descending the suspension cable 23 and the power cable 36. The upper opening 3a of the pump column 3, the actuator drive-type door 12, and the crane 40 are arranged in the working space 15.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a pump installation device for installing a submersible pump for pressurizing liquefied gas such as liquefied ammonia, liquefied natural gas (LNG), or liquid hydrogen in a pump column and removing the submersible pump from the pump column. The present invention further relates to a method for installing a submersible pump in a pump column and a method for removing the submersible pump from the pump column using the pump installation device. [Background technology]

[0002] Natural gas is widely used for thermal power generation and as a chemical raw material. Ammonia and hydrogen are also expected to be energy sources that do not generate carbon dioxide, which causes global warming. Applications of hydrogen as an energy source include fuel cells and turbine power generation. Natural gas, ammonia, and hydrogen are in a gaseous state at room temperature, so they are cooled and liquefied in order to be stored and transported. Liquefied gases such as liquefied natural gas (LNG), liquefied ammonia, and liquefied hydrogen are temporarily stored in liquefied gas tanks and then transported to power plants, factories, etc. by pumps.

[0003] 23 is a schematic diagram showing a liquefied gas tank in which liquefied gas is stored, and a conventional example of a pump for pumping up the liquefied gas. Pump 500 is installed in a vertical pump column 505 installed in a liquefied gas tank 501. The upper end opening of pump column 505 is closed by upper lid 510. Pump column 505 is filled with liquefied gas, and pump 500 is entirely immersed in the liquefied gas. Therefore, pump 500 is a submerged pump that can be operated in liquefied gas.

[0004] When the pump 500 is operated, the liquefied gas in the liquefied gas storage tank 501 is sucked into the pump column 505, moves up the pump column 505, and is discharged from the pump column 505 through the liquefied gas discharge port 509. The pump column 505 is provided with a purge gas introduction port 512. This purge gas introduction port 512 is closed when the pump 500 is operating.

[0005] 24 is a diagram for explaining the work of carrying the pump 500 into the pump column 505 and the work of lifting the pump 500 from the pump column 505. When installing the pump 500 in the pump column 505 and when lifting the pump 500 from the pump column 505 for the purpose of maintenance or the like, the top cover 510 is removed and the cable 508 is connected to a hoist 513. The pump 500 is suspended from the cable 508 and is raised or lowered within the pump column 505 by the hoist 513.

[0006] The liquefied gas remaining in the pump column 505 is gasified to form boil-off gas (BOG). During the loading and unloading of the pump 500, a purge gas is introduced into the pump column 505 through a purge gas introduction port 512 to prevent the boil-off gas (BOG) from being released into the atmosphere. The purge gas also serves to prevent air from entering the pump column 505. An inert gas such as N2 gas or He gas is used as the purge gas. [Prior art documents] [Patent documents]

[0007] [Patent Document 1] Patent No. 3197645 [Patent Document 2] Patent No. 3198248 [Patent Document 3] Patent No. 3472379 Summary of the Invention [Problem to be solved by the invention]

[0008] However, since the upper opening of the pump column 505 is larger than the width of the pump 500, a large amount of purge gas is required to prevent air from entering the pump column 505 while preventing boil-off gas (BOG) from being discharged outside the pump column 505. In particular, He gas is expensive, which increases the cost of carrying in and lifting the pump 500.

[0009] In addition, during the work of carrying in and lifting the pump 500, workers may be exposed to boil-off gas, and a safe working environment may not be ensured. In particular, when the cable 508 is lifted from the pump column 505, the cable 508, which has been in contact with the liquefied gas, is at a very low temperature, and handling the cable 508 is dangerous.

[0010] Therefore, the present invention provides a pump installation device that can reduce the amount of purge gas used to prevent boil-off gas (BOG) from being released from a pump column when a submersible pump is carried into and raised from the pump column, and can create a safe working environment. The present invention also provides a method for installing a submersible pump in a pump column and a method for removing a submersible pump from a pump column using the pump installation device. [Means for solving the problem]

[0011] In one aspect, there is provided a pump installation apparatus for installing and removing a submersible pump used to transport liquefied gas into and from a pump column, the pump installation apparatus comprising: a working chamber forming an enclosed working space; an actuator-driven door covering an upper opening of the pump column; a lifting cable for suspending the submersible pump within the pump column; a power cable for supplying power to the submersible pump; and a crane for raising and lowering the lifting cable and the power cable, wherein the upper opening of the pump column, the actuator-driven door, and the crane are disposed within the working space.

[0012] In one aspect, the suspension cable has a plurality of split suspension cables and a plurality of connecting links connecting the plurality of split suspension cables, the power cable has a plurality of split power cables and a plurality of electrical connectors electrically connecting the plurality of split power cables, the plurality of electrical connectors being respectively attached to the plurality of connecting links, and the pump installation device further includes a link operating device that operates the connecting links to cause the connecting links to connect and disconnect the plurality of split suspension cables and the plurality of split power cables. In one embodiment, each of the multiple connecting links includes a first link mechanism connected to the lower end of each split suspension cable, a second link mechanism connected to the upper end of each split suspension cable, and a connecting pin that connects and disconnects the first link mechanism and the second link mechanism, and the link operating device is configured to move the connecting pin to connect and disconnect the first link mechanism and the second link mechanism using the connecting pin.

[0013] In one aspect, each of the plurality of electrical connectors includes a first electrical connector connected to a lower end of each split power cable and a second electrical connector connected to an upper end of each split power cable, the first electrical connector being held by the first link mechanism and the second electrical connector being held by the second link mechanism. In one embodiment, each of the plurality of connecting links further includes a positioning device that vertically positions the first link mechanism and the second link mechanism. In one embodiment, the positioning device includes a spring that biases the first link mechanism toward the second link mechanism. In one aspect, the working chamber includes a purge gas inlet port communicating with the working space and a purge gas supply line coupled to the purge gas inlet port.

[0014] In one aspect, there is provided a method of installing a submersible pump used to transport liquefied gas in a pump column, the method comprising the steps of opening an actuator driven door located in an enclosed working space formed by a working chamber, the actuator driven door being coupled to an upper portion of the pump column, coupling a lifting cable and a power cable to the submersible pump in the working space, and lowering the lifting cable, the power cable and the submersible pump in the pump column by a crane located in the working space, the upper opening of the pump column being located in the working space.

[0015] In one aspect, the suspension cable has a plurality of split suspension cables and a plurality of connecting links connecting the plurality of split suspension cables, the power cable has a plurality of split power cables and a plurality of electrical connectors electrically connecting the plurality of split power cables, the plurality of electrical connectors being respectively attached to the plurality of connecting links, and the step of lowering the suspension cable, the power cable, and the submersible pump within the pump column is a step of lowering the plurality of split suspension cables, the plurality of split power cables, and the submersible pump within the pump column by the crane while operating the connecting links with a link operating device to connect the plurality of split suspension cables one by one, and while connecting the plurality of split power cables one by one. In one aspect, the method further includes providing a purge gas into the working space prior to loading the submersible pump into the pump column to expose the submersible pump to the purge gas within the working space.

[0016] In one aspect, a method is provided for removing a submersible pump used to transport liquefied gas from a pump column, the method comprising the steps of opening an actuator driven door located in an enclosed working space formed by a working chamber, the actuator driven door being coupled to an upper portion of the pump column, lifting a lifting cable and a power cable connected to the submersible pump with a crane located in the working space to raise the lifting cable, the power cable and the submersible pump within the pump column, disconnecting the lifting cable and the power cable from the submersible pump, and lifting the submersible pump from the pump column into the working space with the crane, wherein an upper opening of the pump column is located within the working space.

[0017] In one aspect, the suspension cable has a plurality of split suspension cables and a plurality of connecting links connecting the plurality of split suspension cables, the power cable has a plurality of split power cables and a plurality of electrical connectors electrically connecting the plurality of split power cables, the plurality of electrical connectors being respectively attached to the plurality of connecting links, and the step of raising the suspension cable, the power cable, and the submersible pump within the pump column is a step of raising the plurality of split suspension cables, the plurality of split power cables, and the submersible pump within the pump column by the crane while operating the connecting links with a link operating device to detach the plurality of split suspension cables one by one and while detaching the plurality of split power cables one by one. In one aspect, the method further includes supplying a purge gas into the working space after raising the submersible pump from the pump column into the working space to expose the submersible pump to the purge gas within the working space. Effect of the Invention

[0018] According to the present invention, the submersible pump can be automatically installed on the pump column and lifted out of the pump column by remotely operating the crane and the actuator-driven door from outside the working chamber. Therefore, the workers are not exposed to a dangerous atmosphere. In addition, since the upper opening of the pump column is within the closed working space, boil-off gas (BOG) is not discharged into the atmosphere. As a result, the amount of purge gas used to prevent the discharge of boil-off gas (BOG) into the atmosphere can be reduced to substantially zero. Furthermore, when the submersible pump is carried into the pump column, the working space is filled with a gas having the same components as the liquefied gas, thereby preventing the entry of gas containing other components such as air into the pump column.

[0019] The power cable is not permanently installed in the liquefied gas tank, but is carried into and out of the pump column together with the hanging cable. Therefore, when the power cable deteriorates, it can be replaced with a new one without discharging the liquefied gas in the liquefied gas tank. [Brief description of the drawings]

[0020] [Figure 1] FIG. 1 illustrates one embodiment of a pump system for transporting liquefied gas. [Diagram 2] FIG. 13 is a cross-sectional view showing one embodiment of a connecting link. [Diagram 3] 4A to 4C are diagrams illustrating how the first link mechanism is connected to the second link mechanism. [Figure 4] 4A to 4C are diagrams illustrating how the first link mechanism is connected to the second link mechanism. [Diagram 5] 4A to 4C are diagrams illustrating how the first link mechanism is connected to the second link mechanism. [Figure 6] 4A to 4C are diagrams illustrating how the first link mechanism is connected to the second link mechanism. [Figure 7] 11A and 11B are diagrams illustrating a state in which the first link mechanism is separated from the second link mechanism. [Figure 8]11A and 11B are diagrams illustrating a state in which the first link mechanism is separated from the second link mechanism. [Figure 9] FIG. 2 is a top view illustrating an embodiment of the support plate shown in FIG. [Figure 10] 1 is a diagram showing the state before the lifting cable, the power cable, and the submersible pump are brought into the pump column. FIG. [Figure 11] 1A-1C are diagrams illustrating one embodiment of a method for installing a submersible pump in a pump column. [Figure 12] 1A-1C are diagrams illustrating one embodiment of a method for installing a submersible pump in a pump column. [Figure 13] 1A-1C are diagrams illustrating one embodiment of a method for installing a submersible pump in a pump column. [Figure 14] 1A-1C are diagrams illustrating one embodiment of a method for installing a submersible pump in a pump column. [Figure 15] 1A-1C are diagrams illustrating one embodiment of a method for installing a submersible pump in a pump column. [Figure 16] 1A-1C are diagrams illustrating one embodiment of a method for installing a submersible pump in a pump column. [Figure 17] 1A-1C illustrate an embodiment of a method for removing a submersible pump from a pump column. [Figure 18] 1A-1C illustrate an embodiment of a method for removing a submersible pump from a pump column. [Figure 19] 1A-1C illustrate an embodiment of a method for removing a submersible pump from a pump column. [Figure 20] 1A-1C illustrate an embodiment of a method for removing a submersible pump from a pump column. [Figure 21] 1A-1C illustrate an embodiment of a method for removing a submersible pump from a pump column. [Figure 22] 1A-1C illustrate an embodiment of a method for removing a submersible pump from a pump column. [Figure 23] 1 is a schematic diagram showing a conventional example of a liquefied gas storage tank in which liquefied gas is stored and a pump for pumping up the liquefied gas. [Figure 24] 10A to 10C are diagrams illustrating the operation of carrying a pump into a pump column and the operation of lifting the pump out of the pump column. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0021] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. Fig. 1 is a diagram showing one embodiment of a pump system for transporting liquefied gas. Examples of liquefied gas that may be transported by the pump system shown in Fig. 1 include liquefied ammonia, liquefied hydrogen, liquefied nitrogen, liquefied natural gas, liquefied ethylene gas, and liquefied petroleum gas.

[0022] As shown in Fig. 1, the pump system includes a submersible pump 2 for transferring liquefied gas, a pump column 3 in which the submersible pump 2 is housed, and a head plate 10 that closes an upper opening 3a of the pump column 3. The pump column 3 is installed in a liquefied gas storage tank 5 in which liquefied gas is stored. The pump column 3 is a hollow container extending vertically, and its upper portion protrudes upward from the liquefied gas storage tank 5. The pump column 3 has a purge gas introduction port 8 and a discharge port 9. The discharge port 9 is connected to a liquefied gas transfer pipe (not shown).

[0023] A suction valve 6 is provided at the bottom of the pump column 3. The submersible pump 2 is installed on the suction valve 6 of the pump column 3. The suction valve 6 has a valve body 6A that covers the lower opening of the pump column 3, and multiple springs 6B that urge the valve body 6A upward. When the submersible pump 2 is not placed on the valve body 6A, the valve body 6A is pressed against the lower end of the pump column 3 by the multiple springs 6B, closing the lower opening of the pump column 3. When the submersible pump 2 is placed on the valve body 6A, the valve body 6A moves downward against the force of the springs 6B due to the weight of the submersible pump 2, thereby opening the suction valve 6. The suction valve 6 may be an actuator-driven valve (e.g., an electric valve).

[0024] A hoisting cable 23 for suspending the submersible pump 2 in the pump column 3 and a power cable 36 for supplying power to the electric motor 2a of the submersible pump 2 extend vertically in the pump column 3. A head plate 10 is placed at the upper end of the pump column 3. The head plate 10 is covered by an actuator-driven door 12. The hoisting cable 23, the power cable 36, and the connecting structure 28 are suspended from the head plate 10. The hoisting cable 23 extends vertically in the pump column 3. The hoisting cable 23 has a plurality of divided hoisting cables 23B connected by connecting links 24. The power cable 36 extends vertically in the pump column 3 along the hoisting cable 23.

[0025] The first electrical terminal 35A is fixed to the actuator-driven door 12, and the second electrical terminal 35B is fixed to the wall of the working chamber 1. The second electrical terminal 35B is connected to a power source (not shown). The first electrical terminal 35A is electrically connected to the second electrical terminal 35B by a connecting cable 34. The connecting cable 34 extends between the first electrical terminal 35A and the second electrical terminal 35B, and is detachably connected to the first electrical terminal 35A and the second electrical terminal 35B.

[0026] The first electrical terminal 35A fixed to the outer surface of the actuator-driven door 12 is electrically connected to the first electrical contact 33A fixed to the inner surface of the actuator-driven door 12. The first electrical terminal 35A and the first electrical contact 33A move with the opening and closing of the actuator-driven door 12. The second electrical contact 33B is fixed to the upper surface of the head plate 10, and the power cable 36 is connected to the second electrical contact 33B. When the actuator-driven door 12 is closed, the first electrical contact 33A comes into contact with the second electrical contact 33B on the head plate 10, thereby establishing an electrical connection between the first electrical contact 33A and the second electrical contact 33B. Electric power is supplied to the power cable 36 from a power source (not shown) via the second electrical terminal 35B, the connecting cable 34, the first electrical terminal 35A, the first electrical contact 33A, and the second electrical contact 33B. When the actuator door 12 is opened, the first electrical contact 33A is disconnected from the second electrical contact 33B on the head plate 10, thereby cutting off the power supply.

[0027] An upper end of the power cable 36 is electrically connected to the first electrical terminal 35A via a first electrical contact 33A and a second electrical contact 33B, and a lower end of the power cable 36 is electrically connected to the electric motor 2a of the submersible pump 2. The power cable 36 has a plurality of split power cables 37. These multiple split power cables 37 are also connected by a connecting link 24. The uppermost split power cable 37 is connected to the second electrical contact 33B on the head plate 10.

[0028] The connecting structure 28 is attached to the submersible pump 2. The connecting structure 28 is connected to the lower ends of the suspension cable 23 and the power cable 36. More specifically, the connecting structure 28 includes a link mechanism 28A connected to the suspension cable 23 and the power cable 36, a connecting member 28B connecting the link mechanism 28A to the submersible pump 2, and a conductive member 28C electrically connecting the link mechanism 28A to the electric motor 2a of the submersible pump 2. The connecting member 28B may be a cable, a rod-shaped member, or the like. The conductive member 28C may be composed of a power cable, or the like.

[0029] The link mechanism 28A has a width greater than that of the connecting member 28B and the conductive member 28C. The suspension cable 23 is connected to the submersible pump 2 via the link mechanism 28A and the connecting member 28B. The power cable 36 is electrically connected to the electric motor 2a of the submersible pump 2 via the conductive member 28C.

[0030] When the submersible pump 2 is in operation, the liquefied gas in the liquefied gas storage tank 5 is introduced into the pump column 3 through the suction valve 6, and the pump column 3 is filled with liquefied gas. When the submersible pump 2 is in operation, the entire submersible pump 2 is immersed in liquefied gas. Therefore, the submersible pump 2 is configured to be able to operate in liquefied gas. The liquefied gas pressurized by the submersible pump 2 is transferred to the outside through the discharge port 9 and a liquefied gas transfer pipe (not shown). When the submersible pump 2 is in operation, the purge gas introduction port 8 is closed by a valve (not shown).

[0031] Next, a pump installation device for installing the submersible pump 2 in the pump column 3 and removing it from the pump column 3 will be described. The pump system includes the pump installation device described below. The pump installation device includes the work chamber 1 forming a closed work space 15, the actuator-driven door 12 covering the upper opening 3a of the pump column 3, the hoisting cable 23 for suspending the submersible pump 2 in the pump column 3, the power cable 36 for supplying power to the submersible pump 2, and a crane 40 for raising and lowering the hoisting cable 23. The upper opening 3a of the pump column 3, the actuator-driven door 12, and the crane 40 are arranged in the work space 15. The work chamber 1 has a work door 16 for carrying the submersible pump 2, the hoisting cable 23, the power cable 36, and the like into and out of the work space 15. This work door 16 is usually closed.

[0032] The working chamber 1 is fixed to the upper wall 5A of the liquefied gas storage tank 5. The working chamber 1 has a purge gas inlet port 17 and a gas outlet port 18 that communicate with the working space 15. A purge gas supply line 71 extending from a purge gas supply source 70 is connected to the purge gas inlet port 17, and a vacuum line 74 is connected to the gas outlet port 18. The vacuum line 74 is connected to a vacuum source (not shown) such as a vacuum pump. Examples of the purge gas supply source 70 include a nitrogen gas supply source, a helium gas supply source, a hydrogen gas supply source, or a combination thereof. In one embodiment, the purge gas supply source 70 may include at least two of different types of purge gas supply sources, for example, a nitrogen gas supply source, a helium gas supply source, and a hydrogen gas supply source. In this case, the multiple purge gas supply sources may be selectively connected to the purge gas supply line 71.

[0033] The purge gas used is a gas composed of components having a boiling point equal to or lower than the boiling point of the liquefied gas to be pumped by the submersible pump 2. This is to prevent the purge gas from liquefying when it comes into contact with the liquefied gas. Examples of purge gas include inert gases such as nitrogen gas and helium gas. For example, when the liquefied gas to be pumped by the submersible pump 2 is liquefied natural gas, nitrogen gas, which is a gas composed of nitrogen having a boiling point (-196°C) lower than the boiling point of liquefied natural gas (-162°C), is used as the purge gas. In another example, when the liquefied gas to be pumped by the submersible pump 2 is liquid hydrogen, helium gas, which is a gas composed of helium having a boiling point (-269°C) lower than the boiling point of hydrogen (-253°C), is used as the purge gas.

[0034] A portion of the purge gas may be a gas having the same composition as the liquefied gas. When the gas outlet port 18 is connected to a gas processing device, all of the purge gas may be a gas having the same composition as the liquefied gas. For example, when the liquefied gas is liquefied hydrogen, some or all of the purge gas may be hydrogen gas. In another example, when the liquefied gas is liquefied ammonia, some or all of the purge gas may be ammonia gas.

[0035] The actuator-driven door 12 is connected to the upper part of the pump column 3. The actuator-driven door 12 covers the upper opening 3a of the pump column 3 and the head plate 10 that closes the upper opening 3a. The actuator-driven door 12 is equipped with an actuator 13 such as an electric motor or an air cylinder. The actuator-driven door 12 is configured to open and close in response to a command signal transmitted from outside the working chamber 1. During operation of the submersible pump 2, the actuator-driven door 12 is closed as shown in FIG. 1.

[0036] When the actuator-driven door 12 is closed, a sealed space is formed between the actuator-driven door 12 and the upper part of the pump column 3. The head plate 10 is located in this sealed space. The actuator-driven door 12 can prevent boil-off gas (BOG) that has passed through a minute gap between the head plate 10 and the upper part of the pump column 3 from leaking into the working space 15 of the working chamber 1.

[0037] The crane 40 is configured to be movable in the work space 15. More specifically, the crane 40 is movable on a support rail 41 arranged in the work space 15, as indicated by an arrow. The crane 40 can move between a position above the pump column 3 and a position away from the pump column 3. The crane 40 includes a gripping mechanism (gripper) 44, a wire 45 for suspending the gripping mechanism 44, and a hoist 46 for reeling out and winding the wire 45. The gripping mechanism 44 is configured to be capable of gripping the head plate 10, the hoisting cable 23, the connecting link 24, the connecting structure 28, and the like. Examples of the hoist 46 include a hoist and a winch. The crane 40 is configured to operate upon receiving a command signal transmitted from outside the work chamber 1.

[0038] The suspension cable 23 includes a plurality of split suspension cables 23B and a plurality of connecting links 24 connecting these split suspension cables 23B. In FIG. 1, only one connecting link 24 is illustrated. The length of each split suspension cable 23B is shorter than the length of the pump column 3. The multiple split suspension cables 23B are connected in series by the connecting links 24. Similarly, the power cable 36 includes a plurality of split power cables 37. These multiple split power cables 37 are connected in series by the connecting links 24.

[0039] The pump installation device further includes a link operation device 50 that operates each connecting link 24 to connect and disconnect the divided suspension cable 23B and the divided power cable 37, a support plate 55 that supports the link operation device 50, and a plate actuator 58 that moves the support plate 55 between a position directly above the pump column 3 and a retracted position. The link operation device 50 is disposed on the support plate 55, and the support plate 55 is connected to the plate actuator 58. The plate actuator 58 can move the link operation device 50 and the support plate 55 together. The link operation device 50 has an actuator 52 such as a linear motor or an air cylinder, and the link operation device 50 is configured to be movable on the support plate 55. That is, the link operation device 50 is movable relative to the support plate 55.

[0040] The link operation device 50 has an operation pin 51 that protrudes toward the connecting link 24. When the connecting link 24 is operated by this operation pin 51, the connecting link 24 is configured to connect or disconnect the split suspension cable 23B and the split power cable 37.

[0041] Fig. 2 is a cross-sectional view showing one embodiment of the connecting link 24. As shown in Fig. 2, the connecting link 24 includes a first link mechanism 62, a second link mechanism 63, and a connecting pin 68 that connects and disconnects the first link mechanism 62 and the second link mechanism 63. The link operating device 50 shown in Fig. 1 is configured to connect and disconnect the first link mechanism 62 and the second link mechanism 63 by moving the connecting pin 68.

[0042] The first link mechanism 62 and the second link mechanism 63 are connected to both ends of each divided suspension cable 23B. In the embodiment shown in Fig. 2, the first link mechanism 62 is connected to the lower end of each divided suspension cable 23B, and the second link mechanism 63 is connected to the upper end of each divided suspension cable 23B. Since the link mechanism 28A of the connecting structure 28 shown in Fig. 1 has the same configuration as the second link mechanism 63, the following description also applies to the link mechanism 28A of the connecting structure 28.

[0043] The power cable 36 has a first electrical connector 21 and a second electrical connector 22 connected to either end of each split power cable 37. In the embodiment shown in Figure 2, the first electrical connector 21 is connected to the bottom end of each split power cable 37 and the second electrical connector 22 is connected to the top end of each split power cable 37.

[0044] The first electrical connector 21 is held by a first link mechanism 62, and the second electrical connector 22 is held by a second link mechanism 63. When the first electrical connector 21 connected to the lower end of a split power cable 37 is connected to the second electrical connector 22 connected to the upper end of the other split power cable 37, these two split power cables 37 are electrically connected by the first electrical connector 21 and the second electrical connector 22. The multiple first electrical connectors 21 and the multiple second electrical connectors 22 are attached to the multiple connecting links 24, respectively.

[0045] The first link mechanism 62 has an insertion portion 64A and a flange portion 64B protruding outward from the insertion portion 64A. The insertion portion 64A has a horizontal hole 62a extending horizontally. The first electric connector 21 is held by the flange portion 64B. The second link mechanism 63 has a housing 66 having a vertical hole 65 into which the insertion portion 64A is inserted, and a connecting pin 68 housed in a horizontal hole 67 formed in the housing 66. The connecting pin 68 is movable in the horizontal hole 67. The horizontal hole 67 penetrates the housing 66 in the horizontal direction. The diameter of the horizontal hole 62a of the first link mechanism 62 is larger than the diameter of the connecting pin 68, and the connecting pin 68 can pass through the horizontal hole 62a of the first link mechanism 62.

[0046] The second link mechanism 63 has a tapered guide surface 75 formed on the upper surface of the housing 66. The tapered guide surface 75 is connected to the upper end of the vertical hole 65 and is inclined downward toward the vertical hole 65. The tapered guide surface 75 is provided to guide the insertion portion 64A of the first link mechanism 62 into the vertical hole 65.

[0047] The upper end of the split suspension cable 23B is connected to the lower part of the housing 66. The upper part of the split power cable 37 extends vertically within the housing 66 and is held by the housing 66. That is, both the split suspension cable 23B and the split power cable 37 are connected to the housing 66 of the second link mechanism 63. Therefore, the split suspension cable 23B and the split power cable 37 can move integrally with the second link mechanism 63. The second electrical connector 22 is fixed to the upper part of the housing 66. The split power cable 37 extends within the housing 66 and is connected to the second electrical connector 22.

[0048] 2, when the connecting pin 68 is disposed across the horizontal hole 62a of the first link mechanism 62, the first link mechanism 62 and the second link mechanism 63 are connected to each other. On the other hand, when the connecting pin 68 is outside the horizontal hole 62a of the first link mechanism 62, the first link mechanism 62 can be separated from the second link mechanism 63.

[0049] The second link mechanism 63 further includes a positioning device 80 for positioning the first link mechanism 62 and the second link mechanism 63 in the vertical direction. The positioning device 80 in this embodiment is a ball plunger having a ball 82 disposed in a horizontal hole 81 formed in the housing 66 and a spring 83 for pressing the ball 82 against the insertion portion 64A of the first link mechanism 62. In this embodiment, two sets of balls 82 and springs 83 are provided, but one set, or three or more sets of balls 82 and springs 83 may be provided. The insertion portion 64A has a recess 86 on its outer surface. The spring 83 presses the ball 82 against the recess 86, thereby fixing the relative position of the insertion portion 64A in the vertical direction with respect to the housing 66.

[0050] The positioning device 80 consisting of a ball plunger also has the function of pressing the first electrical connector 21 held by the first link mechanism 62 against the second electrical connector 22 held by the second link mechanism 63. That is, the spring 83 urges the first link mechanism 62 toward the second link mechanism 63. Therefore, the positioning device 80 can ensure the electrical connection between the first electrical connector 21 held by the first link mechanism 62 and the second electrical connector 22 held by the second link mechanism 63.

[0051] 3 to 6 are diagrams for explaining how the first link mechanism 62 is connected to the second link mechanism 63. As shown in Fig. 3, when the connecting pin 68 is positioned outside the vertical hole 65, the insertion portion 64A of the first link mechanism 62 enters the vertical hole 65 of the second link mechanism 63. The tip of the insertion portion 64A is guided by the tapered guide surface 75 and enters the vertical hole 65. As shown in Fig. 4, when the insertion portion 64A of the first link mechanism 62 comes into contact with the ball 82 of the positioning device 80, the insertion portion 64A pushes the ball 82 outward against the force of the spring 83.

[0052] 5, when the ball 82 is pressed against the recess 86 of the insertion portion 64A by the spring 83, the vertical relative position of the insertion portion 64A with respect to the second link mechanism 63 is maintained. At this time, the first electric connector 21 held by the first link mechanism 62 is pressed against the second electric connector 22 held by the second link mechanism 63, whereby the split power cable 37 connected to the first electric connector 21 is electrically connected to the other split power cable 37 connected to the second electric connector 22. The horizontal hole 62a formed in the insertion portion 64A is aligned in a straight line with the horizontal hole 67 of the second link mechanism 63.

[0053] 6, in a state in which the horizontal hole 62a of the first link mechanism 62 and the horizontal hole 67 of the second link mechanism 63 are aligned in a straight line, the link operating device 50 moves toward the second link mechanism 63 of the connecting link 24, and the operating pin 51 of the link operating device 50 pushes the connecting pin 68 into the horizontal hole 62a. The connecting pin 68 moves into the horizontal hole 62a, whereby the first link mechanism 62 and the second link mechanism 63 are connected by the connecting pin 68. As a result, the upper split suspension cable 23B is connected to the lower split suspension cable 23B, and the upper split power cable 37 is connected to the lower split power cable 37.

[0054] 7 and 8 are diagrams for explaining how the first link mechanism 62 is separated from the second link mechanism 63 by the link operation device 50. As shown in FIG. 7, the link operation device 50 moves toward the second link mechanism 63 of the connecting link 24, and the operation pin 51 of the link operation device 50 pushes the connecting pin 68 out of the horizontal hole 62a. Thereafter, as shown in FIG. 8, the operation pin 51 of the link operation device 50 is pulled out of the horizontal holes 62a and 67, and the first link mechanism 62 is separated from the second link mechanism 63. As a result, the upper split suspension cable 23B is separated from the lower split suspension cable 23B, and the upper split power cable 37 is separated from the lower split power cable 37.

[0055] 9 is a top view showing one embodiment of the support plate 55 shown in FIG. The support plate 55 has a horizontally elongated notch 55a. The width of this notch 55a is larger than the width of the split suspension cable 23B, the width of the split power cable 37, and the width of the connecting member 28B and the conductive member 28C of the connecting structure 28, and is smaller than the width of the second link mechanism 63 of the connecting link 24 and the width of the link mechanism 28A of the connecting structure 28. Therefore, the split suspension cable 23B, the split power cable 37, the connecting member 28B, and the conductive member 28C can pass through the notch 55a, but the second link mechanism 63 of the connecting link 24 and the link mechanism 28A of the connecting structure 28 cannot pass through the notch 55a.

[0056] FIG. 10 is a diagram showing a state before the hoisting cable 23, the power cable 36, and the submersible pump 2 are carried into the pump column 3. As shown in FIG. 10, the multiple divided hoisting cables 23B constituting the hoisting cable 23, the multiple divided power cables 37 constituting the power cable 36, and the submersible pump 2 are disposed in a location away from the pump column 3 in the working space 15 of the working chamber 1. The first link mechanism 62 and the second link mechanism 63 of the connecting link 24 are connected in advance to each divided hoisting cable 23B and each divided power cable 37. The head plate 10 is attached in advance to one of the multiple divided hoisting cables 23B and one of the multiple divided power cables 37. The valve body 6A of the suction valve 6 is pressed against the lower end of the pump column 3 by multiple springs 6B to close the lower opening of the pump column 3.

[0057] Next, an embodiment of a method for installing the submersible pump 2 in the pump column 3 will be described with reference to Figs. 10 to 16. The series of operations shown in Figs. 10 to 16 includes an operation of lowering the submersible pump 2 in the pump column 3, an operation of connecting the multiple divided suspension cables 23B one by one, and an operation of connecting the multiple divided power cables 37 one by one. Before the operations described below, liquefied gas is discharged from the pump column 3. Specifically, with the actuator-driven door 12 open, purge gas is supplied into the working space 15 through the purge gas inlet port 17 to increase the pressure in the pump column 3, thereby discharging the liquefied gas from the pump column 3 through the suction valve 6. Then, the actuator-driven door 12 is closed.

[0058] In step 101, as shown in FIG. 10, with the upper opening 3a of the pump column 3 closed by the actuator-driven door 12, an operator connects the connecting cable 34 to the first electric terminal 35A and the second electric terminal 35B. Then, the working space 15 in the working chamber 1 in which the submersible pump 2 is housed is evacuated through the gas outlet port 18. Then, a purge gas (e.g., an inert gas and / or a gas having the same components as the liquefied gas) is supplied from the purge gas inlet port 17 to the working space 15, and the working space 15 is filled with the purge gas. The submersible pump 2 is exposed to (comes into contact with) the purge gas in the working space 15, thereby removing air and moisture from the surface of the submersible pump 2. This process is a drying-up process that drives out air and moisture from the submersible pump 2. The evacuation of the working space 15 and the supply of the purge gas to the working space 15 may be repeated.

[0059] In step 102, the actuator-driven door 12 is opened, and the submersible pump 2 is transported by the crane 40 to a position above the pump column 3. More specifically, the gripping mechanism 44 of the crane 40 grips the link mechanism 28A of the connecting structure 28 connected to the submersible pump 2, and the crane 40 transports the submersible pump 2 and the connecting structure 28 together to a position above the pump column 3. In step 103, the submersible pump 2 and the connecting structure 28 are lowered together using the crane 40, and the submersible pump 2 is moved into the pump column 3, while the link mechanism 28A of the connecting structure 28 is positioned above the pump column 3.

[0060] In step 104, with the link mechanism 28A of the connecting structure 28 located above the pump column 3, the plate actuator 58 (see FIG. 1) moves the support plate 55 and the link operating device 50 toward the pump column 3, and the support plate 55 covers the upper opening 3a of the pump column 3. As described with reference to FIG. 9, the support plate 55 has a notch 55a, and the width of the notch 55a is larger than the width of the connecting member 28B and the width of the conductive member 28C of the connecting structure 28, and smaller than the width of the link mechanism 28A. In this step 104, the support plate 55 moves onto the pump column 3 such that the connecting member 28B and the conductive member 28C are positioned within the notch 55a of the support plate 55.

[0061] In step 105, the crane 40 further lowers the connecting structure 28 and the submersible pump 2 until the link mechanism 28A of the connecting structure 28 comes into contact with the support plate 55. The submersible pump 2 is suspended from the support plate 55 by the connecting structure 28. In other words, the load of the submersible pump 2 is supported by the support plate 55.

[0062] In step 106, the gripping mechanism 44 of the crane 40 releases the link mechanism 28A of the connecting structure 28, and then the crane 40 transports one of the multiple divided suspension cables 23B prepared in advance in the working chamber 1 and one of the multiple divided power cables 37 prepared in advance in the working chamber 1 to a position above the pump column 3. The second link mechanism 63 of the connecting link 24 is connected in advance to the upper ends of the divided suspension cable 23B and the divided power cable 37, and the first link mechanism 62 of the connecting link 24 is connected in advance to the lower ends of the divided suspension cable 23B and the divided power cable 37. The gripping mechanism 44 of the crane 40 grips the second link mechanism 63 connected to the upper ends of the divided suspension cable 23B and the divided power cable 37, thereby transporting the divided suspension cable 23B, the divided power cable 37, and the second link mechanism 63 together and moving them up and down.

[0063] In step 107, the split suspension cable 23B and the split power cable 37 are lowered by the crane 40 until the insertion portion 64A of the first link mechanism 62 attached to the lower end of the split suspension cable 23B enters the vertical hole 65 of the link mechanism 28A on the support plate 55 (see Figures 2 to 5). In step 108, the link operating device 50 moves toward the link mechanism 28A on the support plate 55, and the operating pin 51 of the link operating device 50 moves the connecting pin 68 of the link mechanism 28A into the horizontal hole 62a (see FIG. 6). As a result, the first link mechanism 62 is connected to the link mechanism 28A, and the split suspension cable 23B and the split power cable 37 are connected to the connecting structure 28.

[0064] In step 109, the link operating device 50 moves in a direction away from the link mechanism 28A until the operating pin 51 of the link operating device 50 is positioned outside the link mechanism 28A. Then, the crane 40 slightly pulls up the split suspension cable 23B, the split power cable 37, the connecting structure 28, and the submersible pump 2. The load of the submersible pump 2 is supported by the crane 40. In step 110, the plate actuator 58 (see FIG. 1) moves the support plate 55 and the link operating device 50 in a direction away from the pump column 3. Next, the crane 40 lowers the split suspension cable 23B, the split power cable 37, the connecting structure 28, and the submersible pump 2, moving the submersible pump 2 within the pump column 3 while positioning the second link mechanism 63 of the connecting link 24 above the pump column 3. When the submersible pump 2 is lowered, the weight of the submersible pump 2 is applied only to the split suspension cable 23B, and not to the split power cable 37.

[0065] In step 111, before the second link mechanism 63 attached to the uppermost split suspension cable 23B enters the pump column 3, the plate actuator 58 (see FIG. 1) moves the support plate 55 and the link operating device 50 toward the pump column 3, and the support plate 55 covers the upper opening 3a of the pump column 3. As described with reference to FIG. 9, the width of the notch 55a of the support plate 55 is larger than the width of the split suspension cable 23B and the width of the split power cable 37, and is smaller than the width of the second link mechanism 63. In this step 111, the support plate 55 moves onto the pump column 3 so that the split suspension cable 23B and the split power cable 37 are positioned within the notch 55a of the support plate 55.

[0066] In step 112, the crane 40 further lowers the split suspension cable 23B, the split power cable 37, the connecting structure 28, and the submersible pump 2 within the pump column 3 until the second link mechanism 63 connected to the uppermost split suspension cable 23B and the split power cable 37 contacts the support plate 55. The submersible pump 2 is suspended from the support plate 55 by the split suspension cable 23B and the connecting structure 28. In other words, the load of the submersible pump 2 is supported by the support plate 55.

[0067] Then, until the submersible pump 2 approaches the bottom of the pump column 3, steps similar to those from step 106 to step 112 are repeated while adding the remaining multiple split suspension cables 23B one by one and while adding the remaining multiple split power cables 37 one by one. That is, while the link operating device 50 operates the connecting links 24 to connect the multiple split suspension cables 23B one by one and while connecting the multiple split power cables 37 one by one, the crane 40 lowers the multiple split suspension cables 23B, the multiple split power cables 37, and the submersible pump 2 within the pump column 3.

[0068] In step 113, when the submersible pump 2 approaches the bottom of the pump column 3, the final split suspension cable 23B and split power cable 37 are added to the suspension cable 23 and the power cable 36, respectively. The head plate 10 is pre-connected to the upper ends of the final split suspension cable 23B and split power cable 37. In step 114, the crane 40 lowers the head plate 10 and the split suspension cable 23B and split power cable 37 connected thereto, and connects the first link mechanism 62 attached to the lower end of the uppermost split suspension cable 23B to the second link mechanism 63 on the support plate 55, as described with reference to Figures 3 to 6.

[0069] In step 115, the plate actuator 58 (see FIG. 1) moves the support plate 55 and the link operating device 50 in a direction away from the pump column 3. Next, the head plate 10, the split lifting cable 23B, the split power cable 37, the connecting structure 28, and the submersible pump 2 are lowered by the crane 40, the upper opening 3a of the pump column 3 is closed by the head plate 10, and the submersible pump 2 is placed on the suction valve 6. The suction valve 6 opens due to the weight of the submersible pump 2.

[0070] In step 116, the gripping mechanism 44 of the crane 40 moves away from the head plate 10. Furthermore, the actuator-driven door 12 is closed, and the first electrical contact 33A fixed to the actuator-driven door 12 comes into contact with the second electrical contact 33B fixed to the head plate 10. This completes the installation of the submersible pump 2 on the pump column 3.

[0071] An operator can automatically install the submersible pump 2 on the pump column 3 by remotely operating the crane 40, the link operating device 50, and the actuator-driven door 12 from outside the working chamber 1. Therefore, the operator is not exposed to a dangerous atmosphere. In addition, since the upper opening 3a of the pump column 3 is located within the closed working space 15, boil-off gas (BOG) is not discharged into the atmosphere. As a result, the amount of purge gas used to prevent the discharge of boil-off gas (BOG) into the atmosphere can be made substantially zero. Furthermore, when the submersible pump 2 is carried into the pump column 3, the working space 15 is filled with a gas having the same components as the liquefied gas, thereby preventing the entry of gas containing other components such as air into the pump column 3.

[0072] The power cable 36 (including the multiple split power cables 37) is not permanently installed in the liquefied gas storage tank 5, but is carried into the pump column 3 together with the hanging cable 23. Therefore, when the power cable 36 deteriorates, the deteriorated power cable 36 can be replaced with a new one without discharging the liquefied gas in the liquefied gas storage tank 5.

[0073] Next, one embodiment of a method for removing the submersible pump 2 from the pump column 3 will be described with reference to Figures 1, 17 to 22. When removing the submersible pump 2, the steps described with reference to Figures 10 to 16 are basically performed in reverse order. The series of operations shown in Figures 1, 17 to 22 includes an operation of raising the submersible pump 2 in the pump column 3, an operation of disconnecting the multiple split suspension cables 23B one by one, and an operation of disconnecting the multiple split power cables 37 one by one.

[0074] In step 201, with the upper opening 3a of the pump column 3 closed by the head plate 10 and the actuator-driven door 12, an operator removes the connecting cable 34 shown in FIG. 1 from the first electric terminal 35A and the second electric terminal 35B. Then, the working space 15 in the working chamber 1 is evacuated through the gas outlet port 18. Then, a purge gas (e.g., an inert gas and / or a gas having the same components as the liquefied gas) is supplied from the purge gas inlet port 17 into the working space 15, and the working space 15 is filled with the purge gas. The evacuation of the working space 15 and the supply of the purge gas to the working space 15 may be repeated.

[0075] In step 202, as shown in FIG. 17, the actuator-driven door 12 is opened, and the first electrical contact 33A on the actuator-driven door 12 is separated from the second electrical contact 33B on the head plate 10. Next, the head plate 10 is gripped by the gripping mechanism 44 of the crane 40, and the head plate 10, the multiple split suspension cables 23B, the multiple split power cables 37, the connecting structure 28, and the submersible pump 2 are slightly raised by the crane 40, and the suction valve 6 is closed. Furthermore, purge gas is supplied into the working chamber 1 through the purge gas inlet port 17 to increase the pressure in the pump column 3. As the pressure in the pump column 3 increases, liquefied gas is discharged from the pump column 3 through the suction valve 6.

[0076] In step 203, the head plate 10, the multiple split suspension cables 23B, the multiple split power cables 37, the connecting structure 28, and the submersible pump 2 are lifted by the crane 40 until the entire uppermost split suspension cable 23B and the split power cable 37 are positioned above the pump column 3. Thereafter, the support plate 55 and the link operating device 50 are moved toward the pump column 3 by the plate actuator 58 (see FIG. 1 ), and the upper opening 3a of the pump column 3 is covered by the support plate 55.

[0077] In step 204, the crane 40 slightly lowers the multiple split suspension cables 23B, the multiple split power cables 37, the connecting structure 28, and the submersible pump 2 until the second link mechanism 63 of the connecting link 24 directly above the support plate 55 comes into contact with the support plate 55. The submersible pump 2 is suspended from the support plate 55 by the split suspension cables 23B and the connecting structure 28. In other words, the load of the submersible pump 2 is supported by the support plate 55.

[0078] In step 205, the link operating device 50 moves toward the second link mechanism 63 on the support plate 55, and the operating pin 51 of the link operating device 50 moves the connecting pin 68 of the second link mechanism 63 out of the horizontal hole 62a (see FIG. 7). In step 206, the operating pin 51 of the link operating device 50 moves away from the second link mechanism 63 on the support plate 55. This causes the first link mechanism 62 to be separated from the second link mechanism 63, allowing the uppermost split suspension cable 23B to be separated from the other split suspension cables 23B, and the uppermost split power cable 37 to be separated from the other split power cables 37.

[0079] In step 207, the uppermost split suspension cable 23B and the split power cable 37 are raised by the crane 40 and moved to a position further away from the pump column 3 (see FIG. 10). In step 208 , the second link mechanism 63 on the support plate 55 is gripped by the gripping mechanism 44 of the crane 40 .

[0080] In step 209, the remaining split suspension cable 23B, the remaining split power cable 37, the connecting structure 28, and the submersible pump 2 are slightly raised by the crane 40, and then the plate actuator 58 (see FIG. 1 ) moves the support plate 55 and the link operating device 50 in a direction away from the pump column 3. Furthermore, the multiple split suspension cables 23B, the multiple split power cables 37, the connecting structure 28, and the submersible pump 2 are raised by the crane 40 until the entire uppermost split suspension cable 23B and split power cable 37 are positioned above the pump column 3.

[0081] In step 210, the plate actuator 58 (see FIG. 1) moves the support plate 55 and the link operating device 50 toward the pump column 3, so that the support plate 55 covers the upper opening 3a of the pump column 3. Furthermore, the crane 40 slightly lowers the multiple split suspension cables 23B, the multiple split power cables 37, the connecting structure 28, and the submersible pump 2 until the second link mechanism 63 of the connecting link 24 directly above the support plate 55 comes into contact with the support plate 55.

[0082] Then, the same steps as those from step 205 to step 210 are repeated while disconnecting the multiple split suspension cables 23B one by one and while disconnecting the multiple split power cables 37 one by one until all the split suspension cables 23B and all the split power cables 37 are removed by the crane 40. That is, the multiple split suspension cables 23B, the multiple split power cables 37, and the submersible pump 2 are raised in the pump column 3 by the crane 40 while the multiple split suspension cables 23B are disconnected one by one and while disconnecting the multiple split power cables 37 one by one by operating the connecting link 21 by the link operating device 50. When all the split suspension cables 23B and all the split power cables 37 have been removed, the link mechanism 28A of the connecting structure 28 attached to the submersible pump 2 is supported by the support plate 55.

[0083] In step 211, the link mechanism 28A of the connecting structure 28 is gripped by the gripping mechanism 44, and the connecting structure 28 and the submersible pump 2 are slightly raised by the crane 40. Next, the support plate 55 and the link operating device 50 are moved in a direction away from the pump column 3 by the plate actuator 58 (see FIG. 1). In step 212, the entire connecting structure 28 and the submersible pump 2 are lifted from the pump column 3 by the crane 40, and are then transported to a position away from the pump column 3 within the working space 15 (see FIG. 10). In step 213, the actuator door 12 is closed.

[0084] In step 214, as shown in Fig. 10, a purge gas (e.g., an inert gas and / or a gas having the same components as the liquefied gas) is supplied to the working space 15 of the working chamber 1 through the purge gas inlet port 17 to fill the working space 15 with the purge gas. The submersible pump 2 is exposed to (comes into contact with) the purge gas in the working space 15, thereby heating the submersible pump 2. This is a hot-up process for heating the submersible pump 2. This completes the removal of the submersible pump 2 from the pump column 3.

[0085] An operator can automatically remove the submersible pump 2 from the pump column 3 by remotely operating the crane 40, the link operating device 50, and the actuator-driven door 12 from outside the working chamber 1. Therefore, the operator is not exposed to a dangerous atmosphere. In addition, since the upper opening 3a of the pump column 3 is located within the closed working space 15, boil-off gas (BOG) is not discharged to the atmosphere. As a result, the amount of purge gas used to prevent the discharge of boil-off gas (BOG) to the atmosphere can be substantially reduced to zero. Furthermore, when the submersible pump 2 is raised from the pump column 3, the working space 15 is filled with a gas having the same components as the liquefied gas, thereby preventing the entry of gas containing other components such as air into the pump column 3.

[0086] The power cable 36 (including the multiple split power cables 37) is not permanently installed in the liquefied gas storage tank 5, and is carried out from the pump column 3 together with the hanging cable 23. Therefore, when the power cable 36 deteriorates, the deteriorated power cable 36 can be replaced with a new one without discharging the liquefied gas in the liquefied gas storage tank 5.

[0087] The above-described embodiments have been described for the purpose of enabling a person having ordinary skill in the art to practice the present invention. Various modifications of the above-described embodiments are naturally possible for a person skilled in the art, and the technical idea of ​​the present invention can be applied to other embodiments. Therefore, the present invention is not limited to the described embodiments, but is to be interpreted in the broadest scope according to the technical idea defined by the claims. [Explanation of symbols]

[0088] 1 Working chamber 2 Submersible pump 2a electric motor 3. Pump column 5 Liquefied gas storage tank 6. Suction valve 8 Purge gas inlet port 9 Discharge port 10 Head Plate 12 Actuator-driven door 13 Actuator 15. Working Space 16 Working door 17 Purge gas inlet port 18 Gas outlet port 21 First electrical connector 22 Second Electrical Connector 23 Suspension Cable 23B Split suspension cable 24 Connecting Links 28 Connected structure 28A Link mechanism 28B Connecting member 28C Conductive materials 33A, 33B Electrical contacts 34 Connecting cable 35A, 35B Electrical terminals 36 Power Cable 37 Split Power Cable 40 Crane 41 Support Rail 44 Gripping mechanism 45 Wire 46 Windlass 50 Link operation device 51 Operation pin 52 Actuator 55 Support Plate 58 Plate Actuator 62 First link mechanism 62a Side Cave 63 Second link mechanism 65 Vertical Hole 66 Housing 67 Side Cave 68 Connecting pin 70 Purge gas supply source 71 Purge gas supply line 74 Vacuum Line 75 Tapered guide surface 80 Positioning device 81 Side Cave 82 Ball 83 Spring 86 Depression

Claims

1. 1. A pump installation device for installing and removing a submersible pump used to transport liquefied gas into and from a pump column, comprising: a working chamber forming an enclosed working space; an actuator-driven door covering an upper opening of the pump column; a lifting cable for suspending the submersible pump within the pump column; a power cable for supplying power to the submersible pump; a crane for raising and lowering the suspension cable and the power cable; The pump installation device, wherein the pump column top opening, the actuator driven door, and the crane are disposed within the work space.

2. The suspension cable includes a plurality of divided suspension cables and a plurality of connecting links that connect the plurality of divided suspension cables, the power cable includes a plurality of split power cables and a plurality of electrical connectors electrically connecting the plurality of split power cables; the electrical connectors are attached to the connecting links, respectively; The pump installation device according to claim 1 , further comprising a link operating device that operates the connecting link to cause the connecting link to perform connection and disconnection of the multiple split suspension cables and the multiple split power cables.

3. Each of the plurality of connecting links includes a first link mechanism connected to a lower end of each divided suspension cable, a second link mechanism connected to an upper end of each divided suspension cable, and a connecting pin that connects and disconnects the first link mechanism and the second link mechanism, The pump installation device according to claim 2 , wherein the link operation device is configured to move the connecting pin to connect and disconnect the first link mechanism and the second link mechanism via the connecting pin.

4. Each of the plurality of electrical connectors includes a first electrical connector connected to a lower end of each of the split power cables and a second electrical connector connected to an upper end of each of the split power cables; 4. The pump mounting device of claim 3, wherein the first electrical connector is held by the first linkage and the second electrical connector is held by the second linkage.

5. The pump installation device according to claim 3 , wherein each of the plurality of connecting links further includes a positioning device that vertically positions the first link mechanism and the second link mechanism.

6. 6. The pump installation device of claim 5, wherein the positioning device includes a spring that biases the first link mechanism toward the second link mechanism.

7. 2. The pump installation apparatus of claim 1, wherein the working chamber comprises a purge gas inlet port communicating with the working space, and a purge gas supply line connected to the purge gas inlet port.

8. 1. A method of installing a submersible pump used to transport liquefied gas in a pump column, comprising: opening an actuator-driven door disposed within an enclosed working space defined by a working chamber, the actuator-driven door being coupled to an upper portion of the pump column; connecting a lifting cable and a power cable to the submersible pump within the working space; lowering the lifting cable, the power cable, and the submersible pump within the pump column by a crane located within the work space; The upper opening of the pump column is disposed within the working space.

9. The suspension cable includes a plurality of divided suspension cables and a plurality of connecting links that connect the plurality of divided suspension cables, the power cable includes a plurality of split power cables and a plurality of electrical connectors electrically connecting the plurality of split power cables; the electrical connectors are attached to the connecting links, respectively; 9. The method of claim 8, wherein the step of lowering the suspension cable, the power cable, and the submersible pump within the pump column comprises the step of lowering the multiple split suspension cables, the multiple split power cables, and the submersible pump within the pump column by the crane while operating the connecting links with a link operating device to connect the multiple split suspension cables one by one, and while connecting the multiple split power cables one by one.

10. 9. The method of claim 8, further comprising providing a purge gas into the working space prior to loading the submersible pump into the pump column to expose the submersible pump to the purge gas within the working space.

11. 1. A method for removing a submersible pump used to transport liquefied gas from a pump column, comprising the steps of: opening an actuator-driven door disposed within an enclosed working space defined by a working chamber, the actuator-driven door being coupled to an upper portion of the pump column; Lifting a lifting cable and a power cable connected to the submersible pump with a crane disposed in the work space, thereby raising the lifting cable, the power cable, and the submersible pump within the pump column; Disconnecting the lifting cable and the power cable from the submersible pump; lifting the submersible pump from the pump column into the work space with the crane; The upper opening of the pump column is disposed within the working space.

12. The suspension cable includes a plurality of divided suspension cables and a plurality of connecting links that connect the plurality of divided suspension cables, the power cable includes a plurality of split power cables and a plurality of electrical connectors electrically connecting the plurality of split power cables; the electrical connectors are attached to the connecting links, respectively; 12. The method of claim 11, wherein the step of raising the suspension cable, the power cable, and the submersible pump within the pump column comprises the step of raising the multiple split suspension cables, the multiple split power cables, and the submersible pump within the pump column by the crane while a link operating device operates the connecting links to detach the multiple split suspension cables one by one and while detaching the multiple split power cables one by one.

13. 12. The method of claim 11, further comprising the step of: supplying a purge gas into the working space after raising the submersible pump from the pump column into the working space to expose the submersible pump to the purge gas within the working space.

Citation Information

Patent Citations

  • Submerged pump device for liquefied gas tank

    JP3197645B2

  • Submerged pump device for liquefied gas tank and its lifting jig

    JP3198248B2

  • Installation equipment for submerged motor pumps

    JP3472379B2