Method for managing sending
The method uses a sensor to detect piston movement and adjust for concrete hardness, ensuring accurate delivery speed and amount, thereby improving concrete placement control and reducing defects.
Patent Information
- Application Number
- JP2024116012
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2024-07-19
- Publication Date
- 2024-10-16
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing methods for delivering concrete using pump trucks fail to accurately control the actual delivery speed and amount due to variations in concrete hardness, leading to potential inaccuracies.
A delivery management method using a sensor to detect the reciprocating motion of the piston, combined with correction values based on concrete slump, to determine the actual delivery speed and amount of cement composition.
Enables accurate management of concrete delivery speed and amount, preventing excessive stress on formwork and reducing defects by using a sensor to detect piston movement and adjust for concrete fluidity.
Smart Images

Figure 2024147754000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a method for controlling the delivery of a cement composition. [Background technology]
[0002] A known method for pouring concrete (an example of a cement composition) is to use a pump truck equipped with a cylinder and a piston. In this method, concrete filled in the cylinder of the pump truck is pushed out of the cylinder by moving the piston with the driving force generated by the pump. The concrete pushed out of the cylinder is sent to the pouring location through a supply pipe. For example, Patent Document 1 discloses a system in which a sensor is placed in the pumping path of the pump truck and the sensor is used to evaluate the pumping performance of the concrete. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2017-9596 A Summary of the Invention [Problem to be solved by the invention]
[0004] Even if the above-mentioned system is used, there is a risk that the speed and amount of concrete actually discharged from the pump vehicle may not be accurately controlled.
[0005] The present invention has been made in consideration of such problems, and aims to accurately manage the actual delivery speed and delivery amount, taking into account that the degree to which concrete flows into the cylinder differs depending on the hardness (fresh properties) of the concrete. [Means for solving the problem]
[0006] The main invention for achieving the above object is a delivery management method for delivering a cement composition using a pump vehicle equipped with a cylinder and a piston for delivering the cement composition, the delivery management method comprising: detecting the reciprocating motion of the piston in the cylinder with a sensor; determining the delivery speed or delivery amount of the cement composition actually delivered from the pump vehicle based on the detection result of the sensor, the volume of the cylinder, and a correction value according to the slump of the cement composition; and the cement composition is ordinary concrete, and the correction value is 0.65 to 0.90 for a slump of 8 cm to 21 cm. Other features of the present invention will become apparent from the following detailed description of the present invention and the accompanying drawings. Effect of the Invention
[0007] According to the present invention, the actual delivery speed and delivery amount can be accurately controlled. [Brief description of the drawings]
[0008] [Figure 1] FIG. 1 is a schematic explanatory diagram showing a concrete application method. [Diagram 2] FIG. 1 is an explanatory diagram of a double-cylinder type reciprocating pump. [Diagram 3] 3A to 3C are diagrams showing measurement data of the acceleration sensor 30. Fig. 3A is a diagram when the pumping speed is 30 m3 / h, Fig. 3B is a diagram when the pumping speed is 53 m3 / h, and Fig. 3C is a diagram when the pumping speed is 70 m3 / h. [Figure 4] FIG. 2 is a flow chart showing an example of a concrete delivery management method in the present embodiment. [Diagram 5] FIG. 11 is a flow chart showing another example of the concrete delivery management method in the present embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0009] At least the following points will become apparent from the description of this specification and the accompanying drawings.
[0010] A delivery management method for delivering a cement composition using a pump vehicle equipped with a cylinder and a piston for delivering the cement composition has been revealed, characterized in that the reciprocating motion of the piston in the cylinder is detected by a sensor, and the delivery speed or delivery amount of the cement composition actually delivered from the pump vehicle is calculated based on the detection result of the sensor, the capacity of the cylinder, and a correction value according to the slump of the cement composition.
[0011] According to this delivery control method, the delivery speed and delivery amount of the cement composition actually delivered from the pump vehicle can be accurately controlled.
[0012] In such a delivery management method, it is preferable that the reciprocating speed of the piston is detected by the sensor, and the delivery speed is calculated based on the reciprocating speed, the capacity of the cylinder, and the correction value.
[0013] According to this delivery control method, the delivery speed of the cement composition delivered from the pump vehicle can be accurately determined.
[0014] In the delivery management method, a required time for one stroke of the piston may be detected by the sensor, and the delivery speed may be calculated based on the required time, the volume of the cylinder, and the correction value.
[0015] According to this delivery management method, the delivery amount of the cement composition delivered from the pump vehicle can be accurately determined.
[0016] In such a method of controlling delivery, it is preferable to determine a pour height rate by dividing the delivery rate by a cross-sectional area of the cement composition at the pour site.
[0017] According to this type of delivery management method, the pouring height speed (the amount of change in pouring height per unit time) can be managed in real time, preventing excessive stress from being placed on formwork, etc.
[0018] In such a delivery management method, it is preferable that the number of reciprocating movements of the piston is detected by the sensor, and the delivery amount is calculated based on the cumulative number of reciprocating movements, the capacity of the cylinder, and the correction value.
[0019] According to this delivery management method, the delivery amount of the cement composition delivered from the pump vehicle can be accurately determined.
[0020] In such a method of controlling delivery, it is preferable to determine the pouring height by dividing the delivered amount by the cross-sectional area of the cement composition at the pouring site.
[0021] According to this type of delivery management method, the pouring height can be managed in real time, and there is no need for equipment or personnel to measure the pouring height.
[0022] In such a delivery management method, it is desirable that the cement composition is cast inside the steel pipe of the CFT column.
[0023] This type of delivery management method makes it easy to manage the pouring height and pouring speed of concrete into the steel pipe of a CFT column.
[0024] In the delivery management method, the sensor may detect vibrations of the pump vehicle caused by reciprocating motion of the piston.
[0025] According to this delivery management method, the reciprocating motion of the piston can be detected by the vibration of the pump vehicle.
[0026] In such a delivery management method, the sensor may detect a sound generated in association with the reciprocating movement of the piston.
[0027] According to this delivery management method, the reciprocating motion of the piston can be detected by a sensor that detects sound (sound sensor).
[0028] In such a delivery management method, the sensor may detect a stroke end of the piston in the cylinder.
[0029] According to this delivery management method, the reciprocating motion of the piston can be detected by a sensor that detects the stroke end of the piston.
[0030] ===This embodiment=== <About concrete construction> Fig. 1 is a schematic diagram showing an example of a concrete application method, in which concrete is poured into a steel pipe 2 of a concrete-filled steel pipe column 1 (hereinafter also referred to as a CFT column 1) at a construction site.
[0031] A ready mixed concrete truck 10 and a pump truck 20 are positioned near the steel pipe 2 .
[0032] The ready mixed concrete truck 10 is also called a mixer truck or an agitator truck, and is a vehicle that transports the concrete materials delivered from a concrete manufacturing plant to a pouring site while mixing them. The ready mixed concrete truck 10 is equipped with a drum 12 and a chute 14.
[0033] The drum 12 is a generally cylindrical container for loading ready mixed concrete (hereinafter, simply referred to as concrete). The drum 12 keeps rotating all the time while the ready mixed concrete truck 10 is traveling, kneading and mixing the concrete materials. This prevents separation of the aggregate and water, and keeps the concrete homogeneous.
[0034] The chute 14 is a member for guiding (discharging) the concrete in the drum 12 to a target unloading position (a hopper 21 of a pump vehicle 20 in this embodiment), and is provided at an incline behind the drum 12.
[0035] The pump vehicle 20 is a vehicle for pumping the concrete transported to the site by the ready-mix concrete vehicle 10 to a pouring position (steel pipe 2 in this embodiment). The pump vehicle 20 includes a hopper 21, a pump 22, and a concrete supply pipe 29.
[0036] The hopper 21 is provided at the rear of the pump truck 20 and is disposed so as to face the chute 14 of the ready-mix concrete truck 10. The hopper 21 receives the concrete discharged from the chute 14 of the ready-mix concrete truck 10.
[0037] The pump 22 pumps the concrete supplied to the hopper 21 at high pressure into the concrete supply pipe 29. The pump 22 in this embodiment is a double-cylinder type reciprocating pump. The pump 22 will be described later. The concrete supply pipe 29 is a tubular member that delivers (sends) concrete to a pouring location such as a formwork (steel pipe 2 in this embodiment).
[0038] The steel pipe 2 is a hollow member with a square or round cross section, and the CFT column 1 is formed by filling the inside of the steel pipe 2 (corresponding to the pouring portion of the cement composition) with concrete. In constructing such a CFT column 1, it is important to fill the concrete without imposing excessive stress on the steel pipe 2.
[0039] An injection port 2a is formed at the bottom of the steel pipe 2, and a concrete supply pipe 29 of a pump vehicle 20 is connected to the injection port 2a.
[0040] The concrete delivered from the chute 14 of the ready-mix concrete truck 10 to the hopper 21 of the pump truck 20 is continuously sent to the injection port 2a of the steel pipe 2 through the concrete supply pipe 29 by the drive of the pump 22, and is poured into the steel pipe 2. In this way, the CFT column 1 is formed.
[0041] Fig. 2 is an explanatory diagram showing an example of a double-cylinder type reciprocating pump. As shown in Fig. 2, a double-cylinder type pump 22 has a pair of concrete cylinders 23 connected to one side of a hopper 21.
[0042] A concrete piston 24 is provided in each of the pair of concrete cylinders 23. The concrete piston 24 is reciprocated back and forth by a hydraulic cylinder 25 provided at the rear side thereof.
[0043] A swing pipe 26 having one end connected so as to be able to swing is provided on the other side of the hopper 21, and a concrete supply pipe 29 is connected to this swing pipe 26.
[0044] A piston rod 28 of a pipe drive cylinder 27 is connected to the swing pipe 26 . When the pipe drive cylinder 27 is driven, the piston rod 28 advances and retreats, causing the swing pipe 26 to swing within the hopper 21 .
[0045] The other end of the swing pipe 26 is slidably abutted against one side of the hopper 21, and when the swing pipe 26 is swung within the hopper 21 by the pipe drive cylinder 27, the opening at the other end of the swing pipe 26 is selectively connected to the openings of a pair of concrete cylinders 23.
[0046] The concrete pistons 24 of the pair of concrete cylinders 23 are driven in opposite directions. The swing pipe 26 is swung in accordance with the drive of the concrete pistons 24. In other words, when the concrete piston 24 of one concrete cylinder 23 is pushed out by the hydraulic cylinder 25, the swing pipe 26 is connected to that concrete cylinder 23. As a result, the concrete (ready mixed concrete) that has been drawn into one concrete cylinder 23 is pushed out into the swing pipe 26.
[0047] At this time, in the other concrete cylinder 23, the concrete piston 24 is retracted by the hydraulic cylinder 25. As a result, the concrete (ready mixed concrete) in the hopper 21 is drawn into the other concrete cylinder 23.
[0048] Thereafter, when concrete is pushed out from one of the concrete cylinders 23 into the swing pipe 26, the swing pipe 26 is swung by the pipe drive cylinder 27 and connected to the other concrete cylinder 23 into which the concrete has been drawn.
[0049] By repeating the above operation, the concrete in the hopper 21 is delivered to the steel pipe 2 via the swing pipe 26 and the concrete supply pipe 29.
[0050] 2, an acceleration sensor 30 is provided below the hopper 21. The acceleration sensor 30 detects vibrations (pulsation of the pump 22) that occur with the reciprocating motion (stroke) of the concrete piston 24 of the concrete cylinder 23.
[0051] The output of the acceleration sensor 30 is transmitted to a terminal device (not shown), such as a personal computer (PC) or a tablet terminal, via a communication means such as wireless communication. The terminal device has a memory unit that stores data and programs, a calculation unit that performs various calculations based on the programs, a display unit that displays the measurement data (waveforms, etc.), and a warning unit that issues warnings by sound, light emission, etc. The terminal device manages the measured data.
[0052] 3A to 3C are diagrams showing an example of measurement data of the acceleration sensor 30. 3 In the case of the pumping speed of 53 m / h, Fig. 3B shows 3 / h, Fig. 3C shows the pumping speed of 70 m 3 The horizontal axis of each figure is time (s), and the vertical axis is acceleration (m / s 2The pumping speed is set by the pump vehicle 20.
[0053] In each figure (FIG. 3A to FIG. 3C), the portion where the terminal device detects that a waveform peak has appeared is circled. The method for reading the number of strokes and stroke time from the output (waveform) of acceleration sensor 30 is not particularly limited, and may be waveform analysis or learning using AI.
[0054] As shown in the figure, there is a correlation between the number of strokes and the pumping speed. For example, at a pumping speed of 30 m 3 / h, stroke is 10 times / min, pumping speed is 53m 3 / h, stroke is 16 times / min, pumping speed is 70m 3 At 100 / h, the stroke rate is 22 strokes / min. The higher the pumping speed, the more strokes there are. Also, the higher the pumping speed, the larger the waveform (amplitude).
[0055] In this embodiment, concrete is pumped alternately from a pair of concrete cylinders 23, so the multiple pulsations in each figure are alternating strokes by one concrete cylinder 23 and strokes by the other concrete cylinder 23. For example, five of the ten strokes in Figure 3A (e.g., odd-numbered strokes) are strokes by one concrete cylinder 23, and the other five (e.g., even-numbered strokes) are strokes by the other concrete cylinder 23.
[0056] In this way, by providing the acceleration sensor 30, the number of strokes involved in pumping concrete can be accurately determined regardless of the pumping speed.
[0057] It should be noted that the fluidity of concrete decreases over time after production. When the fluidity of concrete decreases, it becomes difficult to draw (fill) into the concrete cylinder 23, and the rate at which the concrete flows into the concrete cylinder 23 decreases. In this case, less concrete is pushed out from the concrete cylinder 23, and, for example, the concrete cannot be pumped out at the speed (pumping speed) set by the pump vehicle 20.
[0058] Therefore, in this embodiment, as will be described later, the delivery of concrete is managed using an efficiency (corresponding to a correction value) according to the fluidity (slump) of concrete.
[0059] <Concrete delivery management method> Fig. 4 is a flow diagram showing an example of a concrete delivery management method in this embodiment. Here, a case of managing the pouring height (corresponding to the pouring height) of the CFT column 1 into the steel pipe 2 will be described. Note that the main body of the following operations is the terminal device.
[0060] First, the number of strokes of the concrete cylinder 23 (the number of reciprocating movements of the concrete piston 24) is counted from the output of the acceleration sensor 30 (output waveform: see FIG. 3) (S101). That is, the appearance of waveform peaks is detected from the acceleration waveform as shown in FIG. 3A to FIG. 3C, and the number of peaks is counted. In this way, the strokes of each of the pair of concrete cylinders 23 are counted together.
[0061] Next, the actual delivery amount is calculated by the cumulative number of strokes x cylinder capacity x efficiency (corresponding to the correction value) (S102). Here, the cylinder capacity is the capacity of one concrete cylinder 23 (one of the pair of concrete cylinders 23).
[0062] Moreover, efficiency is the ratio of the actual delivery amount to the theoretical delivery amount (the degree of inflow of concrete inside the concrete cylinder 23). In other words, if the fluidity of the concrete is low, it becomes difficult for the concrete to be filled into the concrete cylinder 23, and the actual delivery amount from the concrete cylinder 23 becomes smaller than the theoretical delivery amount. Efficiency is used to correct this. Specifically, the theoretical delivery amount is expressed as Qa(m 3 / h), and the actual delivery rate Qb(m 3 / h) and efficiency is η. Qa=Qb / η That is, η = Qb / Qa The efficiency η is determined according to the type of concrete and its slump (fluidity).
[0063] Table 1 shows some examples of efficiency.
[0064] [Table 1] As shown in Table 1, when the type of concrete is the same, the smaller the slump (the less fluidity), the lower the efficiency.
[0065] In this embodiment, a table associating slump with efficiency as shown in Table 1 is stored in the storage unit of the terminal device. Then, for example, when the result of a slump test is input, the efficiency corresponding to that result is selected and used in the calculation in step S102 (here, calculation of the delivery amount). Note that the relationship between slump and efficiency is not limited to Table 1, and a numerical value based on actual performance (a numerical value other than that in Table 1) may be used. Furthermore, when slump can be detected in real time, the detection result may be input at any time.
[0066] Next, the delivery amount calculated in step S102 is divided by the cross-sectional area of the steel pipe 2 (specifically, the cross-sectional area of the portion where the concrete is poured) (S103). This makes it possible to determine the pouring height of the concrete in the steel pipe 2 (pouring height).
[0067] Next, it is determined whether or not the driving is complete based on the calculated driving height (S104). If it is determined that the driving is not complete (NO in S104), the process returns to step S101, and if it is determined that the driving is complete (YES in S104), the driving is completed.
[0068] In this way, the amount of concrete actually delivered from the pump vehicle 20 can be calculated based on the cumulative number of strokes of the concrete cylinder 23 counted by the acceleration sensor 30, the cylinder capacity, and the efficiency. In addition, the pouring height can be calculated from this delivery amount.
[0069] FIG. 5 is a flow diagram of another example of the concrete pouring management method in this embodiment. Here, a case of managing the concrete pouring height speed (corresponding to the pouring height speed) will be described. The pouring height speed is the amount of change in pouring height per unit time, and is the height that rises due to the concrete poured in the unit time. In this case as well, the main operation is the terminal device. Also, the pouring height management of FIG. 4 may be performed at the same time.
[0070] First, similarly to step S101 in Fig. 4, the number of strokes of the concrete cylinder 23 (the number of reciprocating movements of the concrete piston 24) is counted (S201) from the output of the acceleration sensor 30 (output waveform: see Fig. 3). Here, too, the strokes of a pair of concrete cylinders 23 are counted together.
[0071] Next, the actual delivery speed (delivery amount per unit time) is calculated by the number of strokes per unit time x cylinder capacity x efficiency (S202). The number of strokes per unit time (corresponding to the reciprocating speed of the piston) is the number of strokes detected per unit time (e.g., 1 minute), and in the case of Fig. 3A, for example, it is 10. The cylinder capacity and efficiency are the same as those in step S102 of Fig. 4, so their explanation will be omitted.
[0072] Next, the delivery speed calculated in step S202 is divided by the cross-sectional area of the steel pipe 2 (specifically, the cross-sectional area of the portion where the concrete is poured) to determine the pouring height speed of the concrete in the steel pipe 2 (S203).
[0073] Next, it is determined whether the calculated driving height speed is within a threshold value (for example, 1 m / min) (S204). If the driving height speed exceeds the threshold value (NO in S204), a warning is generated. If the driving height speed is within the threshold value (YES in S204), it is determined whether driving is complete (S205). If it is determined that driving is not complete (NO in S205), the process returns to step S201. If it is determined that driving is complete (YES in S205), driving is completed.
[0074] In the above example, the number of strokes was counted, but as will be described below, it is also possible to detect the time required for one stroke (one stroke) and calculate the delivery speed (delivery amount (discharge amount) per unit time) from that required time.
[0075] The discharge volume (Q(m) per unit time (here, 1 hour) of the pump vehicle 20 3 / h) is the volume of concrete discharged from the concrete cylinder 23 in one go, Vc (capacity of the concrete cylinder 23: m 3 / times) × number of strokes of the concrete piston 24 per hour N (times / h).
[0076] Therefore, the discharge amount Q can be calculated from the time Ts (sec) required for one stroke using formula (1). Note that the efficiency η is the degree of inflow of concrete inside the concrete cylinder 23, as above, and varies depending on the slump, becoming smaller as the slump becomes smaller.
[0077] Q = 3600 × Vc × η / Ts (Equation 1) Where, Q: Discharge volume (m 3 / h) Vc: Volume of concrete cylinder 23 (m 3) η: Efficiency Ts: Time required for one stroke (sec) In this way, the delivery speed (delivery amount per unit time) may be obtained by detecting the time required for one stroke.
[0078] As described above, by detecting the stroke of the concrete cylinder 23 of the pump vehicle 20 using the acceleration sensor 30, it becomes possible to manage the delivery and pouring of concrete in real time. This eliminates the need for equipment and personnel to measure the pouring height and the like. Furthermore, in this embodiment, the efficiency η is used to perform correction according to the fluidity (slump) of the concrete, so that the amount and speed of the concrete actually delivered from the pump vehicle 20 can be accurately determined. Furthermore, the waveform of the acceleration sensor 30 can also be used to monitor the presence or absence of abnormalities in pumpability.
[0079] ===Other embodiments=== Although the embodiment of the present invention has been described above, the above embodiment is intended to facilitate understanding of the present invention and is not intended to limit the present invention. Furthermore, the present invention may be modified or improved without departing from the spirit of the present invention, and it goes without saying that the present invention includes equivalents. For example, the following modifications are possible.
[0080] In the above embodiment, concrete is poured into the steel pipe 2 of the CFT column 1 by the press-in method, but the present invention is not limited to this. For example, concrete may be poured by the drop-in method. The present invention can also be applied to pouring concrete into columns other than CFT structures, formwork such as walls, etc. In this case, too, if a warning is issued when the pouring height speed exceeds the management value (threshold value), deformation and collapse of the formwork due to the action of excessive lateral pressure can be prevented. Furthermore, by controlling the delivery speed to an appropriate level, defects such as bean shingles can be reduced, and quality can be improved.
[0081] It can also be applied to pouring concrete into underground walls by the press-in method in the inverted pouring method. In this case, the same effect as above can be obtained. In the press-in method for underground walls, since it is not possible to visually check inside the formwork, more concrete than the planned amount is ordered. In this embodiment, the total amount of concrete delivered can be accurately grasped, so that the appropriate amount of concrete can be ordered, and the amount of leftover concrete (remaining concrete) can be reduced.
[0082] In addition, in the above-described embodiment, the acceleration sensor 30 was provided in the hopper 21 of the pump vehicle 20, but it may be provided in any location where the stroke can be detected, such as another part of the pump vehicle 20 (for example, the concrete supply pipe 29).
[0083] In addition, in the above-described embodiment, the vibration of the pump vehicle 20 is detected by the acceleration sensor 30, but this is not limited thereto. For example, a sound sensor (sound sensor) may be used to detect the sound generated by the stroke. Alternatively, if the concrete cylinder 23 is provided with a sensor that detects the stroke end of the concrete piston 24, the stroke may be detected by the sensor. Even in these cases, the number of strokes can be counted (detected) in the same manner as in the above-described embodiment.
[0084] In addition, in the above embodiment, the case where concrete is poured has been described, but the present invention is not limited to concrete, and can be similarly applied to other cement compositions (for example, mortar). [Explanation of symbols]
[0085] 1 concrete filled steel pipe structural column (CFT column), 2 steel pipe, 2a press inlet, 10 ready-mix concrete trucks, 12 drums, 14 chutes, 20 Pump car, 21 Hopper, 22 Pump, 23 Concrete cylinder (cylinder), 24 Concrete piston (piston), 25 hydraulic cylinder, 26 swing pipe, 27 pipe drive cylinder, 28 piston rod, 29 Concrete supply pipes, 30 Accelerometer
Claims
1. A method for managing delivery of a cement composition using a pump vehicle having a cylinder and a piston for delivering the cement composition, comprising: Detecting the reciprocating motion of the piston in the cylinder with a sensor; Calculating the delivery speed or delivery amount of the cement composition actually delivered from the pump vehicle based on the detection result of the sensor, the volume of the cylinder, and a correction value according to the slump of the cement composition; The cement composition is normal concrete, and the correction value is 0.65 to 0.90 for a slump of 8 cm to 21 cm. A transmission management method comprising:
2. A method for managing delivery of a cement composition using a pump vehicle having a cylinder and a piston for delivering the cement composition, comprising: Detecting the reciprocating motion of the piston in the cylinder with a sensor; Calculating the delivery speed or delivery amount of the cement composition actually delivered from the pump vehicle based on the detection result of the sensor, the volume of the cylinder, and a correction value according to the slump of the cement composition; The cement composition is a lightweight concrete, and the correction value is 0.50 to 0.85 for a slump of 12 cm to 21 cm. A transmission management method comprising:
3. A method for managing delivery of a cement composition using a pump vehicle having a cylinder and a piston for delivering the cement composition, comprising: Detecting the reciprocating motion of the piston in the cylinder with a sensor; Calculating the delivery speed or delivery amount of the cement composition actually delivered from the pump vehicle based on the detection result of the sensor, the volume of the cylinder, and a correction value according to the slump of the cement composition; The cement composition is a high-flow, high-strength concrete, and the correction value is 0.85 to 0.90 for a slump flow of 55 cm to 65 cm. A transmission management method comprising:
4. A transmission management method according to any one of claims 1 to 3, comprising: Detecting the reciprocating speed of the piston with the sensor; The delivery speed is calculated based on the reciprocating speed, the capacity of the cylinder, and the correction value. A transmission management method comprising:
5. A transmission management method according to any one of claims 1 to 3, comprising: The sensor detects the time required for one stroke of the piston; The delivery rate is calculated based on the required time, the capacity of the cylinder, and the correction value. A transmission management method comprising:
6. A transmission management method according to any one of claims 1 to 3, comprising: Dividing the delivery rate by the cross-sectional area of the cement composition at the pour site to obtain a pour height rate; A transmission management method comprising:
7. A transmission management method according to any one of claims 1 to 3, comprising: The number of reciprocations of the piston is detected by the sensor; The delivery amount is calculated based on the cumulative number of reciprocations, the volume of the cylinder, and the correction value. A transmission management method comprising:
8. A transmission management method according to any one of claims 1 to 3 and claim 7, comprising: The delivery volume is divided by the cross-sectional area of the cement composition to determine the pour height. A transmission management method comprising:
9. A transmission management method according to any one of claims 1 to 8, comprising: The cement composition is cast into the inside of the steel pipe of the CFT column; A transmission management method comprising:
10. A transmission management method according to any one of claims 1 to 9, comprising: The sensor detects vibrations of the pump vehicle caused by the reciprocating motion of the piston. A transmission management method comprising:
11. A transmission management method according to any one of claims 1 to 9, comprising: The sensor detects a sound generated in association with the reciprocating motion of the piston. A transmission management method comprising:
12. A transmission management method according to any one of claims 1 to 9, comprising: The sensor detects a stroke end of the piston in the cylinder. A transmission management method comprising:
Citation Information
Patent Citations
Discharge rate display device for piston type concrete pump
JP1994073380U
Display device for concrete spraying apparatus
JP1996303191A
Method and apparatus for detecting operation time and status of use of hydraulic striking unit, specially hydraulic hammer
JP2001017873A
Filling material placing method and placing apparatus
JP2010084365A
Pressure delivery performance evaluation system of fresh concrete
JP2017009596A