Construction method of half-precast concrete member, frame structure and reinforced concrete beam
The integration of an upward protrusion on half precast concrete beams enables direct damping device installation, enhancing workability by eliminating the need for temporary materials.
Patent Information
- Application Number
- JP2023077282
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-09
- Publication Date
- 2024-11-21
AI Technical Summary
The installation of vibration damping devices on reinforced concrete beams made of half precast concrete members is cumbersome due to the need for temporary materials, which increases time and effort.
A half precast concrete beam with an upward protrusion that supports the vibration damping device during construction, eliminating the need for temporary materials.
Improves workability by allowing direct installation of damping devices on the protrusion without temporary materials, reducing construction time and effort.
Smart Images

Figure 2024162090000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a method for constructing a half-precast concrete member, a frame structure, and a reinforced concrete beam. [Background technology]
[0002] Patent Document 1 discloses a technology related to a precast prestressed concrete U-shaped beam. In this prior art, the precast prestressed concrete U-shaped beam is characterized in that the cross section is in the shape of a U-shaped trough and the beam is provided with at least one diaphragm, and the diaphragm is provided with a PC cable insertion hole.
[0003] Patent Document 2 discloses a technique related to a precast concrete beam used in the construction of a reinforced concrete structure. In this prior art, a precast concrete beam is erected between the columns of a reinforced concrete structure to form a part of a main girder. The precast concrete beam is a precast beam with stirrups and bottom reinforcement embedded in it, and the main body has a U-shaped cross section formed from the bottom plate and side plates, with the tops of the stirrups protruding from the top ends of the side plates and the ends of the bottom reinforcement protruding from both ends. Ribs are protruding from the hollow between the side plates at required intervals in the longitudinal direction of the main body in a direction perpendicular to the axis, and both side plates are connected. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] Japanese Patent Application Publication No. 7-82836 [Patent Document 2] Japanese Utility Model Application Publication No. 2-144915 Summary of the Invention [Problem to be solved by the invention]
[0005] When attaching a vibration control device to a reinforced concrete beam whose underside is made of half-precast concrete members, it is common to set up a temporary material on the half-precast members supported by supporting members such as shoring, and then pour concrete on the half-precast members in place with the vibration control device placed on the temporary material. However, in this case, it is time-consuming to set up the temporary material on the half-precast members.
[0006] In view of the above, an object of the present invention is to improve the ease of installation when attaching a vibration control device to a reinforced concrete beam whose underside is constructed of a half-precast concrete member. [Means for solving the problem]
[0007] The first aspect is a half-precast concrete member comprising a beam member that forms the underside of the portion of the reinforced concrete beam where the vibration control device is to be attached, and a protrusion that protrudes upward from the beam member and on which the vibration control device is placed during construction.
[0008] In the half precast concrete member of the first embodiment, the vibration control device is placed on the protrusion during construction to construct the reinforced concrete beam, so no temporary material is required to place the vibration control device on the half precast concrete member. Therefore, workability is improved compared to when a half precast concrete member without a protrusion is used.
[0009] A second aspect is a half-precast concrete member described in the first aspect, in which the outer side surface of the protrusion in the beam direction is inclined downward so that the width of the protrusion in the beam direction increases.
[0010] In the half-precast concrete member of the second embodiment, damage to the base portion of the protrusion when it functions as a cotter is prevented or suppressed, compared to when the sides are not inclined.
[0011] The third aspect is a structural frame comprising a vibration control device attached to an upper beam and a lower reinforced concrete beam, and a half-precast concrete member as described in claim 1 or claim 2, which forms the underside of the portion of the lower reinforced concrete beam where the vibration control device is attached, and in which the vibration control device is placed on a protrusion.
[0012] In the frame structure of the third aspect, no temporary materials are required for placing the vibration control device on the half-precast concrete members during construction, improving workability.
[0013] A fourth aspect is a method for constructing a reinforced concrete beam, comprising the steps of supporting and installing the half-precast concrete member described in the first or second aspect with a support member, placing a vibration control device on the protrusion of the half-precast concrete member, and pouring concrete around the half-precast concrete member to construct a reinforced concrete beam.
[0014] In the fourth aspect of the method for constructing a reinforced concrete beam, no temporary materials are required for placing and installing the vibration control device on the half-precast concrete member during construction, thereby improving workability. Effect of the Invention
[0015] According to the present invention, temporary materials for placing and installing a vibration control device on a half-precast concrete member during construction are not required, thereby improving workability. [Brief description of the drawings]
[0016] [Figure 1] FIG. 2 is a front view of a frame provided with half precast concrete members and vibration-damping studs. [Diagram 2] FIG. 2 is a front view of a single precast member of FIG. 1. [Diagram 3] 3A is a cross-sectional view taken along line 3-3 in FIG. 1, and FIG. 3B is a cross-sectional view of a modified example of the same portion. [Figure 4]4A is a cross-sectional view taken along line 4-4 in FIG. 1, and FIG. 4B is a cross-sectional view of a modified example of the same portion. [Diagram 5] FIG. 13 is a front view of a frame provided with a modified half precast concrete member and vibration-damping studs. [Figure 6] FIG. 6 is a front view of a single precast member of the modified example of FIG. 5. [Figure 7] This is a process diagram showing the process of installing vibration-damping studs to reinforced concrete beams, in the order of (A) to (C). DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0017] <Embodiment> The frame structure of this embodiment will be described. The two directions perpendicular to the horizontal direction are the X direction and the Y direction, and are indicated by the arrows X and Y, respectively. The vertical direction perpendicular to the X direction and the Y direction is the Z direction, and is indicated by the arrow Z. The X direction is the left-right direction. The direction from the outside toward the center in the X direction of a reinforced concrete beam, which will be described later, is the inside, and the opposite direction is the outside.
[0018] In addition, all drawings used in the following description are schematic, and the dimensions and ratios of each element may not necessarily correspond to the actual ones. The dimensions and ratios of each element may not necessarily correspond between multiple drawings. Unless otherwise specified in the specification, each element is not limited to one, and may exist multiple times. Substantially identical elements are given the same reference numerals, and their description may be omitted.
[0019] [Frame structure] First, a frame structure 11 of a frame 10 in which a vibration-damping stud 50 is installed as an example of a vibration-damping device will be described.
[0020] As shown in Fig. 1, the frame 10 is composed of left and right reinforced concrete columns 20 and upper and lower reinforced concrete beams 30, 100. Vibration-damping studs 50 are attached to the upper reinforced concrete beam 30 and the lower reinforced concrete beam 100. Note that Fig. 1 does not show a slab 90 (see Figs. 3(A) and 4(A)). Also, in Figs. 3 and 4 described below, the vibration-damping studs 50 are not shown.
[0021] 1, the vibration-damping stud 50 of this embodiment is configured to include an upper stud 60, a lower stud 70, and a vibration-damping member 52. The upper stud 60 and the lower stud 70 of this embodiment are configured from steel frame material or the like, but are not limited to this.
[0022] The vibration-damping member 52 is provided between the lower end 64 of the upper stud 60 and the upper end 72 of the lower stud 70 and joined to them. The vibration-damping member 52 is a viscoelastic damper configured by laminating in the Y direction plate-shaped high-damping rubber and steel plates whose plate thickness direction is in the Y direction, and exhibits a vibration-damping effect by shear deformation in the X direction which is the axial direction of the reinforced concrete beams 30, 100. Note that the vibration-damping member 52 may have any structure as long as it exhibits a vibration-damping effect by shear deformation in the X direction which is the material axial direction of the reinforced concrete beams 30, 100.
[0023] In this embodiment, the upper stud 60 is joined to the upper reinforced concrete beam 30 by fastening a base plate 63 at the upper end 62 of the upper stud 60 to a base plate 65 provided on the upper surface of the reinforced concrete beam 30 with a PC steel bar 80 and a nut 82 that penetrate the reinforced concrete beam 30. Similarly, in this embodiment, the lower stud 70 is joined to the lower reinforced concrete beam 100 by fastening a base plate 73 at the lower end 74 of the lower stud 70 to a base plate 75 provided on the underside of the reinforced concrete beam 100 with a PC steel bar 80 and a nut 82 that penetrate the reinforced concrete beam 100.
[0024] In this embodiment, for ease of understanding, the penetration parts of the PC steel bars 80 are also shown with solid lines, but in reality, the penetration parts are not visible from the outside because they are embedded in the reinforced concrete beams 30, 100. Also, the PC steel bars 80 pass through sheath pipes (not shown) that are embedded in the reinforced concrete beams 30, 100.
[0025] As shown in Figures 3(A) and 4(B), a reinforced concrete slab 90 is joined to and supported by the lower reinforced concrete beam 100. The slab 90 has slab main reinforcements 92 and distribution bars 94 arranged in a grid pattern at the upper and lower ends, respectively. Although not shown, a reinforced concrete slab is also joined to and supported by the upper reinforced concrete beam 30 (see Figure 1) in a similar manner, and the slab has slab main reinforcements and distribution bars arranged in a grid pattern at the upper and lower ends, respectively.
[0026] At the upper end of the lower reinforced concrete beam 100, upper end beam main reinforcements 110A and 110B (see FIG. 2) constituting the upper end beam main reinforcement 110 are arranged along the X direction, which is the material axis direction. Similarly, at the lower end of the reinforced concrete beam 100, lower end beam main reinforcements 112A and 112B (see FIG. 2) constituting the lower end beam main reinforcement 112 are arranged along the X direction, which is the material axis direction. Around the upper end beam main reinforcements 110A and 110B and the lower end beam main reinforcements 112A and 112B (see FIG. 2) of the reinforced concrete beam 100, rectangular frame-shaped shear reinforcements 120 are arranged at intervals in the Y direction, which is the material axis direction (see FIG. 2 as well). In FIG. 2, members other than a half precast concrete member 200, which will be described later, are shown by imaginary lines.
[0027] The upper end beam main bars 110A and the upper end beam main bars 110B are connected at their ends as described below, and similarly, the lower end beam main bars 112A and the lower end beam main bars 112B are connected at their ends as described below.
[0028] Although not shown, the upper reinforced concrete beam 30 (see FIG. 1) also has upper end main beam bars, lower end main beam bars, and shear reinforcement bars arranged in a similar manner.
[0029] [Reinforced Concrete Beam] Next, the lower reinforced concrete beam 100 will be described in detail.
[0030] As shown in Fig. 1, the reinforced concrete beam 100 is composed of a half precast concrete member 200 that is fabricated in advance in a factory or the like, and a beam body 150 that is constructed by casting on site. The half precast concrete member 200 is provided directly below the vibration-damping stud 50 described above in the reinforced concrete beam 100.
[0031] 2, the half precast concrete member 200 is configured to have a beam member 210 and a protrusion 220. The beam member 210 constitutes the lower side of the portion of the reinforced concrete beam 100 where the vibration-damping stud 50 is attached. The protrusion 220 protrudes upward from the center of the upper surface 212 of the beam member 210 in the X direction.
[0032] The upper end surface 224 of the protrusion 220 is a horizontal surface or a substantially horizontal surface. The side surfaces 222 on both outer sides in the X direction of the protrusion 220 are inclined so that the width of the protrusion 220 in the beam direction increases downward. In other words, the protrusion 220 is trapezoidal when viewed from the Y direction, and the base portion is wider in the X direction. In this embodiment, the angle of the side surfaces 222 with respect to the upper end surface 224 is 45° or substantially 45°, but is not limited to this.
[0033] The vibration-damping stud 50 is placed on the upper end surface 224 of the protrusion 220 (see FIG. 1). Therefore, it is desirable that the width in the X direction of the upper end surface 224 of the protrusion 220 is a length that allows the vibration-damping stud 50 to be stably installed, for example, about 0.5 m to 1.0 m.
[0034] As described above, the upper end beam main bars 110, the lower end beam main bars 112, and the shear reinforcement bars 120 are arranged in the reinforced concrete beam 100 (see Figs. 2, 3(A), and 4(A)).
[0035] In the half precast concrete member 200, upper end beam main reinforcement 110A, lower end beam main reinforcement 112B, and shear reinforcement 120 are embedded.
[0036] The upper end beam main bar 110A is embedded in the protruding portion 220 and protrudes from the side surface 222. The lower end beam main bar 112A is embedded in the beam member 210 and protrudes from the end surface portion 211 in the material axis direction. The upper end beam main bar 110A is connected to the upper end beam main bar 110B by a lap joint or the like, and the lower end beam main bar 112B is connected to the lower end beam main bar 112B by a lap joint or the like.
[0037] The upper side 122 of the shear reinforcement 120 in the half precast concrete member 200 in the area other than the protrusion 220 is exposed from the upper surface 212 of the beam member 210. The shear reinforcement 120 in the area of the protrusion 220 in the half precast concrete member 200 is embedded within the protrusion 220 without being exposed.
[0038] As shown in Figures 3(A) and 4(A), slab main reinforcement 92 and distribution reinforcement 94 are arranged at the upper and lower ends of the slab 90, respectively. As shown in Figure 3(A), in the areas of the slab main reinforcement 92 other than the protrusions 220 of the half precast concrete member 200, the reinforcement is arranged above the beam member 210 without interfering with the half precast concrete member 200.
[0039] As shown in FIG. 4(A), the portion of the slab main reinforcement 92 that interferes with the protrusion 220 of the half precast concrete member 200 is connected by a relay joint 230, which is an example of a joint, and a connecting rebar 232. Specifically, the relay joint 230 is embedded in the side portion 223 of the protrusion 220 that is perpendicular to the beam direction, and the relay joints 230 are connected to each other by the connecting rebar 232 embedded in the protrusion 220. The end 92A of the slab main reinforcement 92 is connected to the relay joint 230. Note that the distribution bars 94 of the slab 90 are not arranged on the upper side of the half precast concrete member 200. Therefore, the distribution bars 94 do not interfere with the protrusion 220.
[0040] In addition, in the half precast concrete member 200 of this embodiment, a sheath pipe through which the above-mentioned PC steel rod 80 is inserted is embedded in advance.
[0041] [Construction process] Next, an example of a construction process for attaching the vibration-damping stud 50 to the lower reinforced concrete beam 100 will be described.
[0042] As shown in Fig. 7(A), the half precast concrete member 200 is lifted, supported by shoring 500 as an example of a support member, and set in a predetermined position. The shoring 500 is set and fixed on the beams or slabs of the lower floor.
[0043] As shown in Figure 7 (B), the vibration-damping stud 50 is installed on the protrusion 220 of the half precast concrete member 200. Then, the base plate 73 of the lower stud 70 of the vibration-damping stud 50 and the base plate 75 provided on the underside of the half precast concrete member 200 are temporarily fixed with PC steel rods 80 and nuts 82.
[0044] Upper end beam main reinforcement 110B, lower end beam main reinforcement 112B, and shear reinforcement 120 are arranged around the half precast concrete member 200 shown in Figures 3(A) and 4(A). In addition, slab main reinforcement 92 and distribution reinforcement 94 are arranged. Note that, as shown in Figure 4(A), the end 92A of the slab main reinforcement 92 that interferes with the protrusion 220 of the half precast concrete member 200 is connected to a relay joint 230.
[0045] As shown in Fig. 7(C), concrete is poured around the half precast concrete member 200 to construct the reinforced concrete beam 100. Concrete is also poured to construct a slab 90 (see Figs. 3(A) and 4(A)). When the poured-in-place concrete hardens and the strength of the reinforced concrete beam 100 reaches a predetermined level, the nuts 82 are tightened to fix the vibration-damping studs 50 to the reinforced concrete beam 100. The shoring 500 is then removed.
[0046] Then, as shown in FIG. 1, the upper reinforced concrete beam 30 is constructed, and after the concrete has hardened, the nuts 82 are tightened to fix the vibration-damping stud 50 to the reinforced concrete beam 30.
[0047] [Effect] Next, the operation of this embodiment will be described.
[0048] During construction, the vibration-damping stud 50 is placed on the protrusion 220 of the half precast concrete member 200 to construct the reinforced concrete beam 100, eliminating the need for temporary materials for placing the vibration-damping stud 50 on the half precast concrete member. This improves workability compared to when a half precast concrete member without the protrusion 220 is used.
[0049] When full precast concrete members are used, vibration-damping studs 50 can be placed on top of the full precast concrete members, so no temporary materials are required. However, full precast concrete members have higher component costs than half precast concrete members 200. In addition, full precast concrete members are heavier than half precast concrete members 200, so transportation costs and lifting costs are higher. In addition, there are more areas of interference with the slab main reinforcement bars 92, so there are more connection points at relay joints 230, which increases the amount of work required for construction.
[0050] In addition, when the reinforced concrete beam 100 is horizontally displaced during an earthquake, the protrusions 220 of the half-precast concrete members 200 function as cotters to prevent or suppress shear slippage.
[0051] When the protrusion 220 functions as a cotter, stress is concentrated at the boundary between the side surface 222 of the protrusion 220 and the upper surface 214 of the beam member 210, and this portion is prone to chipping. However, in the protrusion 220 of this embodiment, the outer side surface 222 is inclined and forms an angle of 45° with the upper surface 214. Therefore, damage such as chipping at the boundary between the side surface 222 of the protrusion 220 and the upper surface 214 of the beam member 210 is prevented or suppressed.
[0052] <Modification> Next, a modification of the above embodiment will be described.
[0053] [Slab deformation] First, the modified slab will be described.
[0054] 3(B), the lower side of the slab 91 is composed of a half-precast concrete slab 93. The slab main reinforcement 92 at the lower end is not arranged on top of the beam member 210 of the half-precast concrete member 200.
[0055] In the modified slab 95 shown in Fig. 4(B), reinforcement is not provided in the protruding portion 220 of the half precast concrete member 200. In other words, this portion of the slab 95 is treated the same as a slab opening, making construction easy. In this case, the relay joint 230 and connecting rebar 232 (Fig. 4(A)) are not embedded in the protruding portion 220 of the half precast concrete member 200.
[0056] [Modification of half-precast concrete members] Next, modified examples of half-precast concrete members will be described.
[0057] A modified half precast concrete member 300 shown in Figures 5 and 6 is configured to include a beam member 210 and protrusions 310, 320. The protrusions 310, 320 protrude upward from both sides of the central portion in the X direction of the upper surface portion 212 of the beam member 210, and carry vibration-damping studs 50 (see Figure 5). Note that in Figure 6, members other than the half precast concrete member 300 are shown with imaginary lines, as in Figure 2.
[0058] 6, the outer side surface 312 of the protrusion 310 in the X direction is inclined downward so that the width of the protrusion 310 in the beam direction increases. The inner side surface 313 is vertical or approximately vertical. In other words, the protrusion 310 is trapezoidal when viewed from the Y direction, and the base portion is wider in the X direction.
[0059] Similarly, the outer side surface 322 of the protrusion 320 in the X direction is inclined downward so that the width of the protrusion 320 in the beam direction increases. The inner side surface 323 is vertical or approximately vertical. In other words, the protrusion 320 is trapezoidal when viewed from the Y direction, and the base portion is wider in the X direction.
[0060] In this embodiment, the upper end faces 314, 324 of the protrusions 310, 320 are horizontal or approximately horizontal. The angle of the side faces 312, 322 with respect to the upper face 212 is 45° or approximately 45°, but is not limited to this.
[0061] The configuration other than the projections 310, 320 is the same as that of the half precast concrete member, so a description thereof will be omitted. Also, the half precast concrete member 300 of this modified example has a sheath pipe through which the PC steel rod 80 described above is inserted embedded in advance.
[0062] In the half precast concrete member 300 of this modified example, the vibration-damping stud 50 is placed on the upper end surfaces 314 and 324 of the protrusions 310 and 320, which are spaced apart in the X direction. This allows the vibration-damping stud 50 to be installed more stably.
[0063] In addition, when the reinforced concrete beam 100 is horizontally displaced during an earthquake, the protrusions 310, 320 of the half precast concrete member 300 function as cotters to prevent or suppress shear slippage.
[0064] When the protrusions 310, 320 function as cotters, stress is concentrated at the boundary between the side surfaces 312, 322 of the protrusions 310, 320 and the upper surface 214, making them prone to chipping. However, the side surfaces 312, 322 of the protrusions 310, 320 are inclined and form an angle of 45° with the upper surface 214. This prevents or suppresses damage such as chipping at the boundary between the side surfaces 312, 322 of the protrusions 310, 320 and the upper surface 214 of the beam member 210.
[0065] <Other> The present invention is not limited to the above embodiment.
[0066] For example, in the above embodiment, the number of protrusions is one or two, but the present invention is not limited to this and may be a half precast concrete member having three or more protrusions.
[0067] Also, for example, in the above embodiment, the vibration-damping stud 50 is attached to the reinforced concrete beam 30, 100 by the PC steel bar 80 and the nut 82, but this is not limited to this. For example, the vibration-damping stud 50 may be attached to the reinforced concrete beam 30, 100 by using an anchor bolt or the like.
[0068] In addition, for example, in the above embodiment, the vibration-damping stud 50 is used as the vibration-damping device, but the present invention is not limited to this. For example, a friction wall, a viscous wall, or the like can be used as the vibration-damping device.
[0069] Also, for example, in the above embodiment, the upper beam is a reinforced concrete beam 30, but this is not limited thereto, and the upper beam may be, for example, a steel beam.
[0070] Furthermore, the present invention can be embodied in various forms without departing from the spirit and scope of the present invention. [Explanation of symbols]
[0071] 50 Vibration-damping stud (an example of a vibration-damping device) 100 Reinforced concrete beam 200 Semi-precast concrete members 210 Beam member 220 Protrusion 222 Side 300 Semi-precast concrete members 310 Protrusion 312 Side 320 Protrusion 322 Side
Claims
1. A beam member constituting a lower side of a portion of a reinforced concrete beam where a vibration damping device is to be attached; A protrusion portion that protrudes upward from the beam member and on which the vibration damping device is placed during construction; A half precast concrete member equipped with
2. An outer side surface of the protrusion in the beam direction is inclined downward so that the width of the protrusion in the beam direction increases. The half precast concrete member according to claim 1.
3. a vibration control device attached to the upper beam and the lower reinforced concrete beam; 3. The half precast concrete member according to claim 1 or 2, which constitutes a lower side of a portion of the lower reinforced concrete beam where the vibration damping device is attached, and the vibration damping device is placed on a protrusion; A structural frame equipped with:
4. A step of supporting and installing the half precast concrete member according to claim 1 or 2 with a support member; placing a vibration control device on the protrusion of the half precast concrete member; A step of constructing a reinforced concrete beam by pouring concrete around the half-precast concrete member; A method for constructing reinforced concrete beams.
Citation Information
Patent Citations
JP1990144915U
U-shaped beam of precast prestressed concrete
JP1995082836A