Control device, control method, and program
The control device stabilizes electricity supply and demand by managing power storage and generation facilities to adjust power amounts, prioritizing energy storage charging and generation, improving the grid's ability to match planned and actual power.
Patent Information
- Application Number
- JP2023080399
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-15
- Publication Date
- 2024-11-27
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing technologies for adjusting electricity supply and demand are inadequate in stabilizing the match between planned and actual power amounts.
A control device that includes a control unit to manage power storage and generation facilities, adjusting power supply and demand by charging or discharging energy storage equipment based on differences between planned and actual power amounts, prioritizing energy storage usage before discharging to stabilize the grid.
Improves the ability to adjust power supply and demand by prioritizing energy storage charging and generation, enhancing the likelihood of matching planned and actual power amounts even with sudden changes in power generation.
Smart Images

Figure 2024164717000001_ABST
Abstract
Description
[Technical field]
[0001] The present disclosure relates to a control device, a control method, and a program. [Background technology]
[0002] Conventionally, techniques related to the adjustment of power supply and demand are known. In order to stabilize power supply and demand, a control is performed to adjust power supply and demand so that a planned amount of power that is planned in advance matches an actual amount of power that is actually supplied (hereinafter, referred to as simultaneous balancing). For example, Patent Document 1 discloses a technique related to a control to approximately match the planned amount of power and the actual amount of power. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2022-115359 A Summary of the Invention [Problem to be solved by the invention]
[0004] There was room for improvement in the technology for adjusting electricity supply and demand.
[0005] An object of the present disclosure, made in consideration of the above circumstances, is to improve technology relating to the adjustment of power supply and demand. [Means for solving the problem]
[0006] A control device according to one embodiment of the present disclosure is a control device having a control unit that sends instructions to control a power storage equipment and a power generation equipment, and the control unit causes the power storage equipment to charge a first adjustment amount corresponding to the difference when the planned power amount exceeds the actual power amount, causes the power generation equipment to generate a second adjustment amount corresponding to the difference when the first adjustment amount exceeds the amount of power charged to the power storage equipment, causes the power generation equipment to generate a third adjustment amount corresponding to the difference when the planned power amount is equal to or less than the actual power amount, and causes the power storage equipment to discharge a fourth adjustment amount corresponding to the difference when the third adjustment amount exceeds the amount of power generated by the power generation equipment.
[0007] A control method according to one embodiment of the present disclosure is a control method executed by a control device that sends instructions to a power storage equipment and a power generation equipment to control each of them, and the control device calculates the difference between a planned power amount and an actual power amount, causes the power storage equipment to charge a first adjustment amount corresponding to the difference when the planned power amount exceeds the actual power amount, causes the power generation equipment to generate power of a second adjustment amount corresponding to the difference when the first adjustment amount exceeds the power amount charged to the power storage equipment, causes the power generation equipment to generate power of a third adjustment amount corresponding to the difference when the planned power amount is equal to or less than the actual power amount, and causes the power storage equipment to discharge a fourth adjustment amount corresponding to the difference when the third adjustment amount exceeds the power amount generated by the power generation equipment.
[0008] A program according to one embodiment of the present disclosure is executed by a control device that sends instructions to control the power storage equipment and the power generation equipment, and the control device executes the following steps: a supply and demand determination step of calculating the difference between a planned amount of power and an actual amount of power; causing the power storage equipment to charge a first adjustment amount corresponding to the difference when the planned amount of power exceeds the actual amount of power; causing the power generation equipment to generate a second adjustment amount corresponding to the difference when the first adjustment amount exceeds the amount of power charged to the power storage equipment; causing the power generation equipment to generate a third adjustment amount corresponding to the difference when the planned amount of power is equal to or less than the actual amount of power; and causing the power storage equipment to discharge a fourth adjustment amount corresponding to the difference when the third adjustment amount exceeds the amount of power generated by the power generation equipment. Effect of the Invention
[0009] According to one embodiment of the present disclosure, a technique for adjusting power supply and demand is improved. [Brief description of the drawings]
[0010] [Figure 1] 1 is a block diagram showing a schematic configuration example of a power network according to an embodiment; [Diagram 2] 4 is a flowchart showing an example of the operation of the control device. [Diagram 3] FIG. 1 is a diagram illustrating an example of a method for adjusting power supply and demand. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] Hereinafter, embodiments of the present disclosure will be described. <Overview of the embodiment> Fig. 1 is a block diagram showing a schematic configuration example of a power grid according to an embodiment. The power grid 1 includes a control device 10, a power generation facility 20, a power storage facility 30, a customer facility 40, and a substation facility 50. The power generation facility 20, the power storage facility 30, and the customer facility 40 and the substation facility 50 are interconnected by a power cable 3. Power is supplied to the power grid 1 from a power company 2 via the substation facility 50. The control device 10 is communicatively connected to the power generation facility 20, the power storage facility 30, the customer facility 40, and the substation facility 50 via a communication network 4.
[0012] The power grid 1 is, for example, a microgrid. A microgrid is a system in which energy supply sources and consumption facilities are grouped together within a certain range to produce and consume energy locally. Distributed power sources such as solar power generation and wind power generation are used as energy supply sources. A microgrid installs small-scale power generation facilities 20 near power consumers and stably adjusts power supply and demand by utilizing distributed power sources.
[0013] An electric power company 2 supplies electric power to the power grid 1. The electric power company 2 concludes a power supply contract in advance with an electric power consumer, and supplies a predetermined planned amount of electric power to the consumer at predetermined intervals (for example, every month).
[0014] The control device 10 is, for example, a computer such as a server device, etc. The control device 10 is connected to a power generation facility 20, a power storage facility 30, a customer facility 40, and a power receiving and transforming facility 50 via a communication network 4 so as to be able to communicate with each other.
[0015] The power generation facility 20 is a "distributed power source" that converts renewable energy into electricity, such as a solar power generator, a heat storage power generator, or a wind power generator. The power generation facility 20 is connected to a power storage facility 30 and a substation facility 50 via a power cable 3. In the present disclosure, the power generation facility 20 includes a heat storage facility that converts heat stored in a heat storage tank into electricity and performs heat storage power generation. The power generation facility 20 transmits the generated electricity to the power storage facility 30 or the substation facility 50 via the power cable 3. The power generation facility 20 is connected to the control device 10 via a communication network 4 so as to be able to communicate with each other.
[0016] The power storage equipment 30 is a storage battery that stores electricity supplied from the electric power company 2 or electricity generated by the power generation equipment 20 and discharges the stored electricity. The power storage equipment 30 is charged with electricity transmitted from the power receiving and transforming equipment 50 or the power generation equipment 20 via the power cable 3, and discharges the electricity to the power receiving and transforming equipment 50. The power storage equipment 30 is connected to the control device 10 via a communication network so as to be able to communicate with each other.
[0017] The consumer equipment 40 is a building, an apartment building, a public facility (e.g., a school), a store, a house, etc., and is equipped with electrical appliances that consume power, such as air conditioners and lighting fixtures. The consumer equipment 40 receives power from a power receiving and transforming facility 50 via a power cable 3. The consumer equipment 40 is connected to the control device 10 so as to be able to communicate with each other via a communication network.
[0018] The power receiving and transforming equipment 50 receives high-voltage electricity supplied from the electric power company 2, transforms the voltage, and distributes the electricity to each device within the area of the power grid 1. The power receiving and transforming equipment 50 distributes electricity to be charged to the power storage equipment 30. The power receiving and transforming equipment 50 converts the voltage to a voltage that can be used by the consumer equipment 40, and distributes the electricity to the consumer equipment 40. The power receiving and transforming equipment 50 is connected to the control device 10 via a communication network 4 so as to be able to communicate with each other.
[0019] The control device 10 of this embodiment causes the storage equipment 30 to charge a first adjustment amount corresponding to the difference when the planned power amount exceeds the actual power amount, causes the power generation equipment 20 to generate a second adjustment amount corresponding to the difference when the first adjustment amount exceeds the amount of power charged to the storage equipment 30, causes the power generation equipment 20 to generate a third adjustment amount corresponding to the difference when the planned power amount is equal to or less than the actual power amount, and causes the power storage equipment 30 to discharge a fourth adjustment amount corresponding to the difference when the third adjustment amount exceeds the amount of power generated by the power generation equipment 20.
[0020] Thus, according to this embodiment, charging the power storage equipment 30 is prioritized in order to adjust the power supply and demand. Therefore, even in a situation where discharging from the power storage equipment 30 is required, the power generation equipment 20 is first made to generate power within the range of its power generation capacity, and if the power supply and demand still cannot be adjusted, the power storage equipment 30 is made to discharge. Therefore, even when the output of a main power source such as a solar power generator suddenly drops, the technology related to the adjustment of power supply and demand is improved in that the probability of being able to adjust the power supply and demand is improved.
[0021] (Control device configuration) The control device 10 includes a communication unit 11, a storage unit 12, and a control unit 13.
[0022] The communication unit 11 includes one or more communication interfaces connected to the communication network 4. The communication interfaces correspond to, for example, a wired LAN (Local Area Network) standard or a wireless LAN standard, but are not limited to these and may correspond to any communication standard. In this embodiment, the control device 10 communicates with the power generation facility 20, the power storage facility 30, the customer facility 40, and the power receiving and transforming facility 50 via the communication unit 11 and the communication network 4.
[0023] The storage unit 12 includes one or more memories. The memories are, for example, but not limited to, semiconductor memories, magnetic memories, or optical memories. Each memory included in the storage unit 12 may function as, for example, a main storage device, an auxiliary storage device, or a cache memory. The storage unit 12 stores any information used in the operation of the control device 10. For example, the storage unit 12 may store a system program, an application program, embedded software, and a planned amount of power contracted between the power company 2 and the consumer. The information stored in the storage unit 12 may be updatable with information acquired from the communication network 4 via the communication unit 11, for example.
[0024] The control unit 13 includes one or more processors, one or more programmable circuits, one or more dedicated circuits, or a combination of these. The processor is, for example, but is not limited to, a general-purpose processor such as a CPU (Central Processing Unit) or a GPU (Graphics Processing Unit), or a dedicated processor specialized for a specific process. The programmable circuit is, for example, but is not limited to, an FPGA (Field-Programmable Gate Array). The dedicated circuit is, for example, but is not limited to, an ASIC (Application Specific Integrated Circuit). The control unit 13 controls the operation of the entire control device 10.
[0025] The control unit 13 acquires the planned power amount from the storage unit 12. The control unit 13 constantly receives the amount of power generated by the power generation facility 20, the amount of power charged and discharged by the power storage facility 30, the amount of power consumed by the customer facility 40 (electrical appliances 43), and the actual amount of power supplied to the power receiving and transforming facility 50 from the electric power company 2, via the communication unit 11 and the communication network. The control unit 13 calculates a first adjustment amount, a second adjustment amount, a third adjustment amount, a fourth adjustment amount, and a fifth adjustment amount, which will be described later, based on the values of the various amounts of power received. The control unit 13 transmits the first to fifth adjustment amounts to the power generation facility 20, the power storage facility 30, the customer facility 40, and the power receiving and transforming facility 50, via the communication unit 11 and the communication network 4.
[0026] (Power generation equipment configuration) The power generation facility 20 includes a power transmission unit 21, a communication unit 22, a power generation unit 23, and a control unit 24. The power generation facility 20 is a “distributed power source” installed within the area of a power grid (microgrid) 1.
[0027] The power transmission unit 21 transmits the electricity generated by the power generation unit 23 to the power receiving and transforming equipment 50 or the power storage equipment 30 via the power cable 3.
[0028] The communication unit 22 includes one or more communication interfaces that connect to the communication network 4. The communication interface corresponds to, for example, a wired LAN (Local Area Network) standard or a wireless LAN standard, but is not limited to these and may correspond to any communication standard. In this embodiment, the power generation facility 20 communicates with the control device 10 via the communication unit 22 and the communication network 4.
[0029] The power generation unit 23 is, but is not limited to, a solar power generator, a wind power generator, a heat storage power generator, or the like. The power generation unit 23 generates power based on instructions from the control device 10 via the communication unit 22 and the communication network 4.
[0030] The control unit 24 includes one or more processors, one or more programmable circuits, one or more dedicated circuits, or a combination of these. The control unit 24 controls the operation of the entire power generation facility 20. The control unit 24 controls the power generation unit 23 to set the power adjustment amount (also referred to as the first adjustment amount, the second adjustment amount, or the third adjustment amount in the operation flow of the control unit 10 described later) notified by the control device 10 to a target value and have the power generation unit 23 generate power. The control unit 24 constantly notifies the control device 10 of the amount of power generated by the power generation unit 23 via the communication unit 22 and the communication network.
[0031] (Configuration of the energy storage facility) The power storage facility 30 includes a charge / discharge unit 31, a communication unit 32, a power storage unit 33, and a control unit .
[0032] The charging / discharging unit 31 receives electricity to be stored in the storage unit 33 transmitted from the power receiving and transforming equipment 50 or the power generation equipment 20 via the power cable 3, and transmits electricity discharged by the storage unit 33 of the power storage equipment 30 to the power receiving and transforming equipment 50 via the power cable 3.
[0033] The communication unit 32 includes one or more communication interfaces that connect to the communication network 4. The communication interface corresponds to, for example, a wired LAN (Local Area Network) standard or a wireless LAN standard, but is not limited thereto, and may correspond to any communication standard. In this embodiment, the power storage facility 30 communicates with the control device 10 via the communication unit 32 and the communication network 4.
[0034] The power storage unit 33 is a stationary storage battery, but is not limited thereto. The power storage unit 33 may be a battery (on-board storage battery) of an electric vehicle (BEV (Battery Electric Vehicle) or PHEV (Plug-in Hybrid Electric Vehicle)). The power storage unit 33 charges or discharges based on an instruction from the control device 10 via the communication unit 32 and the communication network 4.
[0035] The control unit 34 includes one or more processors, one or more programmable circuits, one or more dedicated circuits, or a combination of these. The control unit 24 controls the operation of the entire power storage facility 30. The control unit 34 sets the adjustment amount instructed by the control device 10 to a target value, and controls the power storage unit 33 to charge or discharge the power storage unit 33. The control unit 34 constantly notifies the control device 10 of the amount of power being charged in the power storage unit 33 via the communication unit 32 and the communication network 4.
[0036] (Configuration of consumer equipment) The customer facility 40 includes a power distribution unit 41, a communication unit 42, an electric appliance 43, and a control unit 44. The customer facility 40 is a building, an apartment, a store, a house, or a public facility (e.g., a school) owned or rented by a customer and installed within the area of the power grid (microgrid) 1. The customer facility 40 includes electric appliances that consume power, such as air conditioners, lighting fixtures, or freezers / refrigerators.
[0037] The power distribution unit 41 receives power from the power receiving and transforming equipment 50 via the power cable 3 and reduces the distributed voltage (for example, from 200 VAC to 100 VAC). The power distribution unit 41 is, but is not limited to, a distribution board, a distribution board that distributes the power lines from the distribution board to a plurality of electrical appliances, or the like.
[0038] The communication unit 42 includes one or more communication interfaces that connect to the communication network 4. The communication interface corresponds to, for example, a wired LAN (Local Area Network) standard or a wireless LAN standard, but is not limited to these and may correspond to any communication standard. In this embodiment, the customer facility 40 communicates with the control device 10 via the communication unit 42 and the communication network 4.
[0039] The electric appliances 43 are loads that consume electric power, such as air conditioners, lighting fixtures, freezers, refrigerators, etc., but are not limited to these.
[0040] The control unit 44 includes one or more processors, one or more programmable circuits, one or more dedicated circuits, or a combination of these. The control unit 44 controls the operation of the entire customer facility 40. The control unit 44 is a home controller. The control unit 44 sets a power adjustment amount (also referred to as a fourth adjustment amount in the operation flow of the control device 10 described later) instructed by the control device 10 to a target value, and controls the electric appliance 43 to promote or suppress power consumption by the electric appliance 43. The control unit 44 constantly notifies the control device 10 of the amount of power consumed by the electric appliance 43 via the communication unit 42 and the communication network 4.
[0041] (Configuration of substation equipment) The power receiving and transforming equipment 50 includes a transforming unit 51, a communication unit 52, and a control unit 53. The power receiving and transforming equipment 50 serves as an entrance (gate) when the power company 2 transmits (sells) a planned amount of power to the power grid (microgrid) 1. The power receiving and transforming equipment 50 receives high-voltage electricity from the power company 2, transforms (steps down) the voltage, and distributes the electricity to the power generation equipment 20, the power storage equipment 30, and the customer equipment 40 connected by power cables 3 within the area of the power grid 1.
[0042] The transformer 51 receives an actual amount of power from the electric power company 2. The transformer 51 steps down the high-voltage electricity received from the electric power company 2, and distributes the electricity to the power generation equipment 20, the power storage equipment 30, and the consumer equipment 40 connected by the power cable 3 within the area of the power grid 1.
[0043] The communication unit 52 includes one or more communication interfaces connected to the communication network 4. The communication interface corresponds to, for example, a wired LAN (Local Area Network) standard or a wireless LAN standard, but is not limited to these and may correspond to any communication standard. In this embodiment, the power receiving and transforming equipment 50 communicates with the control device 10 via the communication unit 52 and the communication network 4. The communication unit 52 constantly notifies the control device 10 of the state of power supply and demand within the area of the power grid 1.
[0044] The control unit 53 includes one or more processors, one or more programmable circuits, one or more dedicated circuits, or a combination of these. The control unit 53 controls the operation of the entire power receiving and transforming equipment 50. The control unit 53 constantly notifies the control device 10 of the actual amount of power supplied from the power company 2 via the communication unit 52 and the communication network 4. The control unit 53 supplies the actual amount of power supplied from the power company 2 to devices within the area of the power grid 1, and if there is any surplus power, causes the power storage equipment 30 to be charged via the transformation unit 51.
[0045] (Control device operation flow) 2 is a flowchart showing an example of the operation of the control device 10. This operation relates to the adjustment of power supply and demand within the area of the power grid 1 by the control device 10.
[0046] In steps S101 to S102, the control unit 13 calculates the planned power amount W plan and the actual power consumption W act The total adjustment amount W 0 Calculate the total adjustment amount W 0 A supply and demand determination step is executed to determine whether or not the supply and demand exceeds 0 kWh.
[0047] Step S101: The control unit 13 calculates the planned power amount W plan Actual power consumption W act Subtract the total adjustment amount W 0 Calculate.
[0048] Planned power consumption W plan is the amount of power supplied to the power grid 1 within a given period (for example, every month) based on a power supply plan (contract) between the consumer and the power company 2. act is the amount of power actually supplied from power company 2 to power grid 1. The total adjustment amount W 0 is the planned power consumption W plan and the actual power consumption W act The control unit 13 calculates the planned power amount W plan The control unit 13 acquires the actual power amount W actis acquired from the power receiving and transforming equipment 50 via the communication unit 11 and the communication network 4. plan , actual power consumption W act , and the total adjustment amount W 0 The unit is kWh. W 0 =W plan -W act (1)
[0049] Step S102: The control unit 13 calculates the total adjustment amount W 0 Determine whether or not the total adjustment amount W exceeds 0 kWh. 0 If exceeds 0 kWh, proceed to step S103, and the total adjustment amount W 0 If the current consumption is less than or equal to 0 kWh, the process proceeds to step S106.
[0050] Overall adjustment amount W 0 When the supply of electric power from the power company 2 exceeds 0 kWh, the supply of electric power from the power company 2 can be expected.
[0051] In steps S103 to S105, the control unit 13 calculates the planned power amount W plan is the actual power consumption W act The first adjustment amount W corresponding to the difference when it exceeds 1 The first adjustment amount W 1 A second adjustment amount W corresponding to the difference when the amount of electric power stored in the electric storage equipment 30 exceeds the amount of electric power stored in the electric storage equipment 30. 2 In the following, for the sake of convenience, the total adjustment amount W 0 Overall adjustment amount W when exceeds 0 kWh 0 The first adjustment amount W 1 and the total adjustment amount W 0 When the total adjustment amount W is 0 kWh or less 0 The third adjustment amount W 3 He said.
[0052] Step S103: The control unit 13 calculates the first adjustment amount W 1 is 0 kWh or more, the first adjustment amount W 1 is set as a target value and the power storage equipment 30 is caused to perform charging.
[0053] The control unit 13 determines the first adjustment amount W 1 is set to a target value, and the power storage facility 30 is controlled to perform charging.
[0054] The control unit 13 determines the first adjustment amount W 1 When the first adjustment amount W 1 is set as a target value, and charging is performed within the range of the storage capacity of the storage equipment 30.
[0055] Step S104: The control unit 13 calculates the first adjustment amount W 1 A second adjustment amount W obtained by subtracting the amount of power stored in the power storage facility 30 from 2 It is determined whether the second adjustment amount W exceeds 0 kWh. 2 If exceeds 0 kWh, proceed to step S105, and the second adjustment amount W 2 If it is equal to or less than 0 kWh, the process ends.
[0056] 2nd adjustment amount W 2 is the first adjustment amount W 1 The amount of electric power W charged to the power storage facility 30 from bat The control unit 13 receives the amount of electric power W bat is acquired from the power storage facility 30. Note that the amount of power W bat , and the second adjustment amount W 2 The unit is kWh. W 2 =W 1 -W bat (2)
[0057] The control unit 13 determines the second adjustment amount W 2 is 0 kWh or a negative value, the power generation facility 20 is not caused to generate power, and the process ends. This is because the power grid 1 does not have the amount of power that the power generation facility 20 can generate.
[0058] Step S105: The control unit 13 calculates the second adjustment amount W 2 When exceeds 0 kWh, the second adjustment amount W 2is set as a target value and the power generation facility 20 is caused to generate power.
[0059] The control unit 13 determines the second adjustment amount W 2 When the power generation capacity of the power generating facility 20 exceeds 0 kWh, the second adjustment amount W 2 is set as a target value, and power generation is performed within the range of the power generation capacity of the power generation equipment 20. In the present disclosure, the power generation equipment 20 includes a heat storage equipment that converts heat stored in a heat storage tank into electricity and performs heat storage power generation.
[0060] In steps S106 to S108, the control unit 13 calculates the planned power amount W plan is the actual power consumption W act The third adjustment amount W corresponding to the difference when 3 The power generation equipment 20 generates the third adjustment amount W 3 A fourth adjustment amount W corresponding to the difference when the amount of power generated by the power generation equipment 20 exceeds the amount of power generated by the power generation equipment 20. 4 A power discharging step is performed to cause the power storage facility to discharge the power.
[0061] Step S106: The control unit 13 calculates the third adjustment amount W 3 The absolute value of is set as a target value, and the power generation facility 20 is caused to generate power.
[0062] Overall adjustment amount W 0 is 0 kWh or less, further supply of power from the power company 2 is not expected. In such a case, in order to adjust the power supply and demand, discharge from the power storage equipment 30 is generally required. However, in the present disclosure, the control unit 13 controls the power generation equipment 20 to supply the third adjustment amount W 3 The absolute value of the third adjustment variable W is set as the target value, and power generation is performed within the range of the power generation capacity of the power generation facility 20. 3 The "absolute value" of the third adjustment amount W 3 This is because the value of becomes a negative value. The control unit 13 causes the power generation facility 20 to generate power in order to make up for the shortage of power supply.
[0063] Step S107: The control unit 13 calculates the third adjustment amount W 3A fourth adjustment amount W obtained by subtracting the absolute value of the amount of power generated by the power generation equipment 20 from the absolute value of 4 It is determined whether the fourth adjustment amount W exceeds 0 kWh. 4 If exceeds 0 kWh, proceed to step S108, and the fourth adjustment amount W 4 If it is equal to or less than 0 kWh, the process ends.
[0064] 4th adjustment amount W 4 is the third adjustment amount W 3 Absolute value of |W 3 The absolute value of the amount of power generated by the power generation facility 20 from |W gen The control unit 13 receives the amount of electric power W via the communication unit 11 and the communication network 4. gen is obtained from the power generation facility 20. gen , and the fourth adjustment amount W 4 The unit is kWh. W 4 =|W 3 |-|W gen | (3)
[0065] The control unit 13 determines the fourth adjustment amount W 4 is 0 kWh or a negative value, the processing ends without discharging the power storage equipment 30. This is because the shortage of power supply in the power grid 1 has been made up for by power generation.
[0066] Step S108: The control unit 13 calculates the fourth adjustment amount W 4 When exceeds 0 kWh, the fourth adjustment amount W 4 is set to a target value and the power storage equipment 30 is caused to discharge.
[0067] As described above, the control unit 13 controls the power generation equipment 20 to adjust the third adjustment amount W before discharging the power storage equipment 30. 3 The absolute value of the fourth adjustment variable W is set as the target value, and power generation is performed within the range of the power generation capacity of the power generation facility 20. 4When the fourth adjustment amount W 1 exceeds 0 kWh, that is, when the power supply is still insufficient even though the power generation equipment 20 has generated power, the control unit 13 adjusts the fourth adjustment amount W 2 , which corresponds to the shortage of the power supply, to the power storage equipment 30. 4 is set to a target value and discharge is performed.
[0068] In steps S109 to S110, the control unit 13 calculates the second adjustment amount W 2 is the second adjustment amount W 2 A fifth adjustment amount W corresponding to the difference when the amount of power generated by the power generation facility 20 exceeds the amount of power generated by the power generation facility 20. 5 The power consumption step causes the customer facility 40 to consume the power.
[0069] Step S109: After executing the power storage step, the control unit 13 calculates the second adjustment amount W 2 From the above, the amount of power generated by the power generation equipment 20 W gen The fifth adjustment amount W 5 It is determined whether or not exceeds 0 kWh.
[0070] 5th adjustment amount W 5 is the second adjustment amount W 2 From the above, the amount of power generated by the power generation equipment 20 W gen The fifth adjustment amount W 5 The unit is kWh. W 5 =W 2 -W gen (4)
[0071] The control unit 13 determines the fifth adjustment amount W 5 is 0 kWh or a negative value, the process ends without encouraging the customer equipment 40 to consume power. This is because the power grid 1 does not have the amount of power to allow the customer equipment 40 to consume power.
[0072] Step S110: The control unit 13 calculates the fifth adjustment amount W 5 When exceeds 0 kWh, the fifth adjustment amount W 5 is set as a target value to promote power consumption in the customer facility 40.
[0073] 5th adjustment amount W 5 When the power consumption exceeds 0 kWh, even if the power storage facility 30 is made to store power within its storage capacity and the power generation facility 20 is made to generate power within its power generation capacity, there is still a surplus in the power supply. For this reason, the control unit 13 adjusts the power supply and demand by encouraging the customer facility 40 to operate air conditioning facilities, lighting fixtures, etc.
[0074] In steps S111 to S112, the control unit 13 calculates a fourth adjustment amount W 4 exceeds the amount of power discharged to the power storage facility 30. 6 The power consumption reduction step is executed to cause the customer facility 40 to reduce its power consumption.
[0075] Step S111: After executing the power discharging step, the control unit 13 calculates the third adjustment amount W 3 From the absolute value of dis The sixth adjustment amount W 6 It is determined whether or not exceeds 0 kWh.
[0076] 6th adjustment amount W 6 is the third adjustment amount W 3 Absolute value of |W 3 |, the amount of electricity discharged to the storage facility 30 W dis Absolute value of |W dis The control unit 13 receives the amount of electric power W via the communication unit 11 and the communication network 4. dis is acquired from the power storage facility 30. Note that the amount of power W dis and the sixth adjustment amount W 6 The unit is kWh. W 6 =|W 3 |-|W dis | (5)
[0077] The control unit 13 determines the sixth adjustment amount W 6is 0 kWh or a negative value, the process ends without suppressing power consumption in the customer facility 40. This is because the shortage of power supply in the power grid 1 has been made up for by power generation and discharge.
[0078] Step S112: The control unit 13 calculates the sixth adjustment amount W 6 When exceeds 0 kWh, the sixth adjustment amount W 6 is set as a target value to cause the customer facility 40 to reduce its power consumption.
[0079] 6th adjustment amount W 6 When the power consumption exceeds 0 kWh, the power supply is still insufficient even if the power generation facility 20 generates power within the range of its power generation capacity and the power storage facility 30 discharges power within the range of its power storage capacity. For this reason, the control unit 13 adjusts the power supply and demand by controlling the customer facility 40 to suppress the operation of air conditioning facilities, lighting fixtures, etc.
[0080] When the power generated by a photovoltaic generator is introduced into the power grid 1, if the output of the photovoltaic generator suddenly drops due to a change in weather conditions, it may take time for other generators in the area of the power grid 1 to complete startup and connection, and therefore the sudden drop in the output of the photovoltaic generator cannot be fully compensated for. For example, when the weather is clear during the day, the output of the photovoltaic generator is large, but if cumulonimbus clouds cover the sun, the output of the photovoltaic generator suddenly drops. In such a case, as shown in Figure 3, for example, if the power of another generator is turned on at 13:00, the grid connection is performed at 13:15, but it takes about 15 minutes in between. Therefore, even if the output of the photovoltaic generator suddenly drops, the generated power cannot be immediately compensated for by the other generator. In that case, if the storage capacity of the storage battery is 0kWh, the storage battery cannot be discharged, and a mismatch between power supply and demand occurs. For this reason, it is desirable to charge the storage battery at all times in preparation for a sudden drop in the output of the photovoltaic generator, but if the storage battery is dedicated to charging, the adjustment ability of the storage battery cannot be used during charging.
[0081] In this regard, the control device 10 according to the present embodiment has a planned power amount W plan is the actual power consumption W act The first adjustment amount W corresponding to the difference when it exceeds 1The first adjustment amount W 1 A second adjustment amount W corresponding to the difference when the amount of electric power stored in the electric storage equipment 30 exceeds the amount of electric power stored in the electric storage equipment 30. 2 The power generation facility 20 generates the planned power amount W plan is the actual power consumption W act The third adjustment amount W corresponding to the difference when 3 The power generation equipment 20 generates the third adjustment amount W 3 A fourth adjustment amount W corresponding to the difference when the amount of power generated by the power generation equipment 20 exceeds the amount of power generated by the power generation equipment 20. 4 The power storage equipment 30 is made to discharge the stored power. In this way, charging the power storage equipment 30, i.e., storing power, is given priority in order to adjust the power supply and demand. Therefore, even in a situation where discharge from the power storage equipment 30 is required, the power generation equipment 20 is made to generate power first, and if the power supply and demand still cannot be adjusted, the power storage equipment 30 is made to discharge the stored power. This increases the likelihood that the power supply and demand can be adjusted even when the output of a main power source such as a solar power generator suddenly drops. This improves the technology for adjusting the power supply and demand.
[0082] Although the present disclosure has been described based on the drawings and examples, it should be noted that those skilled in the art may make various modifications and alterations based on the present disclosure. Therefore, it should be noted that these modifications and alterations are included in the scope of the present disclosure. For example, the functions included in each component or step can be rearranged so as not to be logically inconsistent, and multiple components or steps can be combined or divided into one.
[0083] For example, in the above-described embodiment, the configuration and operation of the control device 10 may be distributed among a plurality of computers that can communicate with each other. Also, for example, an embodiment in which some or all of the components of the control device 10 are provided in the power generation facility 20, the power storage facility 30, or the customer facility 40 may be provided.
[0084] Also, for example, an embodiment is possible in which a general-purpose computer functions as the control device 10 according to the above-described embodiment. Specifically, a program describing the processing contents for realizing each function of the control device 10 according to the above-described embodiment is stored in the memory of the general-purpose computer, and the program is read and executed by a processor. Therefore, the present disclosure can also be realized as a program executable by a processor, or a non-transitory computer-readable medium that stores the program. [Explanation of symbols]
[0085] 1. Power grid (microgrid) 2. Electric power companies 3 Power Cable 4. Communication Network 10 Control device 11 Communications Department 12 Storage section 13 Control section 20 Power generation facilities 21 Power Transmission Section 22 Communications Department 23 Power Generation Department 24 Control Unit 30 Energy storage facilities 31 Charge / discharge section 32 Communications Department 33 Power storage unit 34 Control section 40 Consumer equipment 41 Power Distribution Department 42 Communications Department 43 Electrical appliances 44 Control section 50 Power receiving and transforming equipment 51 Transformation Department 52 Communications Department 53 Control section
Claims
1. A control device having a control unit that sends instructions to control the power storage equipment and the power generation equipment, The control unit causes the power storage equipment to charge a first adjustment amount corresponding to the difference when the planned power amount exceeds the actual power amount, causes the power generation equipment to generate a second adjustment amount corresponding to the difference when the first adjustment amount exceeds the amount of power charged to the power storage equipment, causes the power generation equipment to generate a third adjustment amount corresponding to the difference when the planned power amount is equal to or less than the actual power amount, and causes the power storage equipment to discharge a fourth adjustment amount corresponding to the difference when the third adjustment amount exceeds the amount of power generated by the power generation equipment.
2. The control device according to claim 1 , The control unit further causing the consumer equipment to consume a fifth adjustment amount of power corresponding to a difference when the second adjustment amount exceeds an amount of power generated by the power generation equipment; The control device causes the consumer equipment to suppress power consumption of a sixth adjustment amount corresponding to a difference when the fourth adjustment amount exceeds the amount of power discharged to the power storage equipment.
3. The control device according to claim 1 or 2, The power generation facility includes a heat storage facility that converts heat stored in a heat storage tank into electricity and performs heat storage power generation.
4. A control method executed by a control device that sends instructions to control a power storage facility and a power generation facility, The control device Calculating a difference between a planned power amount and an actual power amount; causing the power storage equipment to charge a first adjustment amount corresponding to a difference when the planned power amount exceeds the actual power amount; causing the power generation facility to generate a second adjustment amount corresponding to a difference when the first adjustment amount exceeds an amount of power stored in the power storage facility; causing the power generation facility to generate a third adjustment amount corresponding to a difference when the planned power amount is equal to or less than an actual power amount; causing the power storage facility to discharge a fourth adjustment amount corresponding to a difference when the third adjustment amount exceeds an amount of power generated by the power generation facility; A control method for performing the above.
5. The control device transmits instructions to control the power storage equipment and the power generation equipment, and the control device Calculating a difference between a planned power amount and an actual power amount; causing the power storage equipment to charge a first adjustment amount corresponding to a difference when the planned power amount exceeds the actual power amount; causing the power generation facility to generate a second adjustment amount corresponding to a difference when the first adjustment amount exceeds an amount of power stored in the power storage facility; causing the power generation facility to generate a third adjustment amount corresponding to a difference when the planned power amount is equal to or less than the actual power amount; causing the power storage facility to discharge a fourth adjustment amount corresponding to a difference when the third adjustment amount exceeds an amount of power generated by the power generation facility; Execute program.
Citation Information
Patent Citations
Electric energy control system
JP2017175786A
Adjustment method, control device, power adjustment system and program
JP2018205871A
Power management system, server, and method for adjusting power supply and demand
JP2022115359A
Energy management system in home network interworking with smart grid
US20120166004A1