Target route generation system for work vehicle and target route generation method for work vehicle

The target route generation system automatically generates field-aligned routes for work vehicles, addressing the inefficiencies of manual data input by allowing users to select priority items and correct generated routes, thus optimizing automated work processes.

JP2024169566AInactive Publication Date: 2024-12-05YANMAR POWER TECH CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2024161021
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2024-09-18
Publication Date
2024-12-05
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing target route generation systems for work vehicles require users to input arbitrary setting data, which can be time-consuming for inexperienced users and may result in inappropriate routes that do not align with user values, leading to inefficiencies and increased non-working distances.

Method used

A target route generation system that automatically generates multiple straight routes based on the shape of the field, allowing users to select priority items or input data to create routes suitable for their values, with options for manual correction and modification.

Benefits of technology

Enables efficient and user-friendly route generation for automatic driving, reducing the need for manual data input, minimizing non-working distances, and ensuring routes align with user preferences, thereby enhancing the profitability of automated work operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024169566000001_ABST
    Figure 2024169566000001_ABST
Patent Text Reader

Abstract

To obtain a target route for automatic travel suitable for user's sense of value with simple operation.SOLUTION: A target route generation system for a work vehicle includes a route generation unit that generates multiple straight routes (second straight work route section P2b) for causing a work vehicle (tractor 1) to automatically travel in a farm field. The route generation unit adjusts an orientation of each of the multiple straight routes (second straight work route section P2b) on the basis of a shape of the farm field.SELECTED DRAWING: Figure 17
Need to check novelty before this filing date? Find Prior Art

Description

[Technical Field]

[0001] The present invention relates to a target path generation system for a work vehicle, which generates a target path for automatically driving riding work vehicles such as tractors, riding rice transplanters, combine harvesters, riding mowers, wheel loaders, and snowplows, and unmanned work vehicles such as unmanned mowers, and a target path generation method for a work vehicle. [Background technology]

[0002] An example of a target route generation system for a work vehicle as described above is a route generation device configured so that a user manually inputs, based on work site data such as the size and shape of a field (work site) obtained by a tractor (work vehicle) driving along the perimeter of the field, a number of work area specific points such as corner positions and inflection points of the field, the work start position, the work start direction, the work end position, etc., as optional setting data for target route generation based on the user's values, etc., and generates a target route for automatic driving that corresponds to the user's values, etc., based on the input optional setting data (see, for example, Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Laid-Open No. 2017-173986 Summary of the Invention [Problem to be solved by the invention]

[0004] In the target route generation system for a work vehicle described in Patent Document 1, the user is required to input all of the optional setting data necessary to generate the target route. This allows a user who is accustomed to inputting optional setting data to input optional setting data based on the user's values, etc., and enables the target route generation system to generate a target route that suits the user's values, etc. However, for users who are not good at inputting optional setting data, inputting the optional setting data is often time-consuming, and therefore simplification of the input process is desired. Furthermore, if the optional setting data is not input appropriately based on the user's values, for example, the target route generated by the target route generation system may result in a small work area, or the target route generated by the target route generation system may result in a long non-work driving distance, which is inconsistent with the user's values ​​and may result in the generation of an inappropriate target route that causes disadvantages during work by automated driving.

[0005] In view of this situation, the main objective of the present invention is to generate a target route for automatic driving that is suited to the user's values, etc., without forcing the user to input arbitrary setting data, thereby making it possible to make work performed by automatic driving more profitable. [Means for solving the problem]

[0006] A target path generation system for a work vehicle according to one aspect includes a path generation unit that generates a plurality of straight paths for the work vehicle to automatically travel in a field, and the path generation unit adjusts the orientation of each of the plurality of straight paths based on the shape of the field. A target route generation method for a work vehicle according to one embodiment includes generating a plurality of straight-line routes for automatically driving the work vehicle in a field, and adjusting the orientation of each of the plurality of straight-line routes based on the shape of the field. [Brief explanation of the drawings]

[0007] [Figure 1] Left side view of the tractor [Figure 2] Block diagram showing the control configuration for automatic driving of the tractor [Figure 3] Flowchart of target route generation control [Figure 4] A diagram showing the identification of a work area and the selection of a reference work direction, etc., by a target path generation unit. [Figure 5]FIG. 10 is a diagram showing a first example route among the target routes generated by the target route generating unit; [Figure 6] FIG. 10 is a diagram showing a second example route among the target routes generated by the target route generation unit; [Figure 7] FIG. 10 is a diagram showing a third example route among the target routes generated by the target route generation unit; [Figure 8] FIG. 10 is a diagram showing a fourth example route among the target routes generated by the target route generation unit; [Figure 9] FIG. 10 is a diagram showing a fifth example route among the target routes generated by the target route generation unit; [Figure 10] FIG. 10 is a diagram showing a sixth example route among the target routes generated by the target route generation unit. [Figure 11] FIG. 10 is a diagram showing a seventh example route among the target routes generated by the target route generation unit. [Figure 12] FIG. 10 is a diagram showing an eighth example route among the target routes generated by the target route generation unit. [Figure 13] FIG. 10 is a diagram showing a ninth example route among the target routes generated by the target route generation unit. [Figure 14] FIG. 10 is a diagram showing a tenth example route among the target routes generated by the target route generation unit. [Figure 15] FIG. 11 is a diagram showing an eleventh example route among the target routes generated by the target route generation unit. [Figure 16] FIG. 12 is a diagram showing a twelfth example route among the target routes generated by the target route generation unit. [Figure 17] FIG. 13 is a diagram showing a thirteenth example route among the target routes generated by the target route generation unit. [Figure 18] FIG. 10 is a diagram showing a first example route portion among the direction-changing route portions in the target route generated by the target route generating unit; [Figure 19] FIG. 10 is a diagram showing a second example path portion among the direction-changing path portions in the target path generated by the target path generating unit; DETAILED DESCRIPTION OF THE INVENTION

[0008] An embodiment in which a target route generation system for a work vehicle according to the present invention is applied to a tractor, which is an example of a work vehicle, will be described with reference to the drawings. The target path generation system for work vehicles according to the present invention can be applied to ride-on work vehicles other than tractors, such as riding rice transplanters, combine harvesters, riding brush cutters, wheel loaders, and snowplows, as well as unmanned work vehicles such as unmanned brush cutters.

[0009] As shown in Figures 1 and 2, the tractor 1 illustrated in this embodiment is configured to be able to travel automatically in a farm field, which is an example of a work area, by using an automatic travel system for a work vehicle. The automatic travel system for a work vehicle includes an automatic travel unit 2 mounted on the tractor 1, and a mobile communication terminal 3 that is set up to be able to communicate with the automatic travel unit 2. The mobile communication terminal 3 is a tablet-type personal computer that includes a touch-operable liquid crystal panel (an example of a display unit) 4 and the like. The mobile communication terminal 3 may be a notebook personal computer or a smartphone.

[0010] As shown in Figure 1, a rotary tiller 6, which is an example of a working implement, is connected to the rear of the tractor 1 via a three-point linkage mechanism 5 so that the rotary tiller 6 can be raised, lowered, and rolled. This makes the tractor 1 configured for rotary tilling. Instead of the rotary tilling implement 6, a work implement such as a plow, a seeding implement, or a spraying implement can be connected to the rear of the tractor 1.

[0011] As shown in Figures 1 and 2, the tractor 1 includes left and right front wheels 7 that can be driven and steered, left and right rear wheels 8 that can be driven, a cabin 9 that forms a riding driver's section, an electronically controlled diesel engine (hereinafter referred to as the engine) 10 having a common rail system, an electronically controlled transmission 11 that changes the speed of power from the engine 10, a fully hydraulic power steering mechanism 12 that steers the left and right front wheels 7, left and right side brakes (not shown) that brake the left and right rear wheels 8, and an electronically controlled brake operation mechanism that enables hydraulic operation of the left and right side brakes. The vehicle is equipped with a work clutch (not shown) 13 that interrupts transmission of power to the rotary tillage device 6, an electronically controlled clutch operating mechanism 14 that enables hydraulic operation of the work clutch, an electronically hydraulically controlled lifting drive mechanism 15 that drives the rotary tillage device 6 to raise and lower, an on-board electronic control unit 16 that has various control programs related to the automatic driving of the vehicle (tractor) 1, a vehicle speed sensor 17 that detects the vehicle speed of the vehicle 1, a steering angle sensor 18 that detects the steering angle of the front wheels 7, and a positioning unit 19 that measures the current position and current direction of the vehicle 1. The engine 10 may be an electronically controlled gasoline engine equipped with an electronic governor. The transmission 11 may be a hydromechanical continuously variable transmission (HMT), a hydrostatic continuously variable transmission (HST), or a belt-type continuously variable transmission. The power steering mechanism 12 may be an electric power steering mechanism equipped with an electric motor.

[0012] As shown in Fig. 1, the interior of the cabin 9 is provided with a steering wheel 20 that enables manual steering of the left and right front wheels 7 via a power steering mechanism 12, and a user seat 21. Also provided, although not shown, are a gear shift lever that enables manual operation of the transmission 11, left and right brake pedals that enable manual operation of the left and right side brakes, and a lift lever that enables manual lifting and lowering of the rotary tilling implement 6.

[0013] As shown in Figure 2, the on-board electronic control unit 16 includes a transmission control unit 16A that controls the operation of the transmission 11, a braking control unit 16B that controls the operation of the left and right side brakes, an implement control unit 16C that controls the operation of the rotary tillage implement 6, a non-volatile on-board memory unit 16D that stores vehicle body data including the minimum turning radius and working width of the vehicle 1 and a pre-generated target route P for automatic driving, and a steering angle setting unit 16E that sets target steering angles for the left and right front wheels 7 during automatic driving and outputs the target steering angles to the power steering mechanism 12.

[0014] 1 and 2, the positioning unit 19 includes a satellite navigation device 22 that measures the current position and current orientation of the vehicle 1 using a global positioning system (GPS), which is an example of a global navigation satellite system (GNSS), and an inertial measurement unit (IMU) 23 that has a three-axis gyroscope, a three-directional acceleration sensor, and the like, and measures the attitude and orientation of the vehicle 1. Positioning methods that use GPS include differential GPS (DGPS: a relative positioning method) and real-time kinematic GPS (RTK-GPS: an interferometric positioning method), and this embodiment employs RTK-GPS, which is suitable for positioning moving objects. For this reason, reference stations 24 that enable positioning using RTK-GPS are installed at known positions around the field.

[0015] The tractor 1 and the reference station 24 are each equipped with GPS antennas 26, 27 that receive radio waves transmitted from GPS satellites 25, and communication modules 28, 29 that enable wireless communication of various data including positioning data between the tractor 1 and the reference station 24. This allows the satellite navigation device 22 to measure the current position and current orientation of the host vehicle 1 with high accuracy based on the positioning data obtained by the GPS antenna 26 on the tractor receiving radio waves from the GPS satellites 25 and the positioning data obtained by the GPS antenna 27 on the base station receiving radio waves from the GPS satellites 25. Furthermore, the positioning unit 19 is equipped with the satellite navigation device 22 and the inertial measurement unit 23, and is therefore able to measure the current position, current orientation, and attitude angles (yaw angle, roll angle, pitch angle) of the host vehicle 1 with high accuracy.

[0016] As shown in Figure 2, the mobile communication terminal 3 is equipped with a terminal electronic control unit 30 having various control programs for controlling the operation of the LCD panel 4 and the like, and a communication module 31 that enables wireless communication of various data with the communication module 28 on the tractor side.

[0017] The terminal electronic control unit 30 includes a terminal storage unit (an example of a storage unit) 30A that stores vehicle body data and the like obtained through wireless communication with the tractor side, a positioning data acquisition unit 30B that acquires positioning data through wireless communication with the tractor side, a field data acquisition unit 30C that acquires field data including the size and shape of the field from the acquired positioning data, and a target route generation unit 30D that generates a target route P for automatic driving. When a target route generation mode is selected by touching the liquid crystal panel 4, the terminal electronic control unit 30 displays on the liquid crystal panel 4 a route selection unit 32 that allows the user to select the target route P, an arbitrary data input unit 33 that inputs arbitrary setting data for target route generation, a priority item selection unit 34 that allows the user to select priority items for generating the target route P, and a generation command unit 35 that commands the target route generation unit 30D to generate the target route P. That is, in this embodiment, the mobile communication terminal 3 configures a target route generation system that generates a target route P for automatic driving of the tractor 1.

[0018] The terminal storage unit 30A stores vehicle data and field data as basic data required to generate the target route P. The optional setting data input to the optional data input unit 33 includes a work area specification point for specifying the work area A in the field, an automatic travel start point ps, an automatic travel end point pe, a reference work direction θp, and a turning method. The priority items selected by the priority item selection unit 34 include maximizing the work area, minimizing the non-work travel distance, optimizing the circular travel route portion P1 that follows the periphery of the field, and avoiding the generation of an overlapping route portion P0.

[0019] When a target route generation mode is selected by a touch operation on the liquid crystal panel 4, the target route generation unit 30D executes target route generation control. Hereinafter, the control operation of the target route generating section 30D in the target route generation control will be described with reference to the flowchart shown in FIG.

[0020] In the target route generation control, when the target route generation mode is selected, the target route generation unit 30D first performs a field data confirmation process (step #1) to confirm whether or not the corresponding field data is stored in the terminal memory unit 30A based on the current position of the tractor 1 acquired by the positioning data acquisition unit 30B. If the corresponding field data is stored in the field data confirmation process (step #1), a target route confirmation process (step #2) is performed to confirm whether the corresponding target route P is stored in the terminal memory unit 30A based on the field data and the vehicle data stored in the terminal memory unit 30A. If the corresponding target route P is stored in the target route confirmation process (step #2), the stored target route P is read out from the terminal storage unit 30A, and the read out target route P and the above-mentioned route selection unit 32 are displayed on the liquid crystal panel 4, and a stored route selection process (step #3) is performed to prompt the user to select whether or not to adopt the read out target route P. Then, if the user selects to adopt the read out target route P, the target route generation control is terminated. If the corresponding field data is not stored in the field data confirmation process (step #1), a field data acquisition guidance display process (step #4) is performed to display guidance for performing a field data acquisition drive to obtain field data on the LCD panel 4, prompting the user to perform the field data acquisition drive by driving the tractor 1 along the periphery of the field. The control unit 30B is also caused to perform a positioning data acquisition process (step #5) to acquire, via wireless communication with the tractor, positioning data measured by the positioning unit 19 of the tractor 1 during the field data acquisition drive. The control unit 30C is then caused to perform a field data acquisition process (step #6) to acquire field data including the size and shape of the field from the positioning data acquired by the positioning data acquisition unit 30B. This allows the field data of the field corresponding to the current position of the tractor 1 to be acquired. If the corresponding target route P is not stored in the target route confirmation process (step #2), if the user chooses not to adopt the target route P read out in the stored route selection process (step #3), or if field data is acquired in the field data acquisition process (step #6), an operation screen display process (step #7) is performed to display the optional data input unit 33, priority item selection unit 34, and generation command unit 35, etc., on the liquid crystal panel 4 together with the shape of the field included in the field data, etc. This allows the user to input optional setting data related to the generation of the target route P or select priority items. In the operation screen display process (step #7), if the user does not input any optional setting data in the optional data input unit 33, but instead selects a priority item in the priority item selection unit 34, and then performs a command operation in the generation command unit 35, a first target route generation process (step #8) is performed to generate a first target route according to the priority item as the target route P based on the vehicle data, field data, and the selected priority item. In the operation screen display process (step #7), if the user does not select a priority item in the priority item selection unit 34, but instead inputs each optional setting data in the optional data input unit 33, and then performs a command operation in the generation command unit 35, a second target route generation process (step #9) is performed to generate a second target route as target route P based on the aforementioned vehicle data, field data, and each optional setting data input. After the target route P is generated by each of the above target route generation processes (steps #8-9), the generated target route P is displayed on the liquid crystal panel 4 together with the shape of the field and the above-mentioned route selection unit 32, etc., and a generated route selection process (step #10) is performed to allow the user to select whether or not to adopt the generated target route P. In the generated route selection process (step #10), if the user selects to adopt the generated target route P, the target route generation control ends. If the user selects not to use the generated target route P in the generated route selection process (step #10), the process returns to the operation screen display process (step #7), where the user again inputs arbitrary setting data in the arbitrary data input unit 33 or selects a priority item in the priority item selection unit 34. If the user performs a correction operation such as correcting or adding arbitrary setting data in the arbitrary data input unit 33 or selecting an additional priority item in the priority item selection unit 34 in this operation screen display process (step #7), and then performs a command operation in the generation command unit 35, the process proceeds to the target route correction process (step #11), where the previously generated target route P is corrected based on the arbitrary setting data input this time or the priority item selected this time, and then the process proceeds to the generated route selection process (step #10).

[0021] Next, the generation of the target route P by the first target route generation processing or the second target route generation processing of the target route generation unit 30D will be described in detail with reference to FIG. 2 and FIGS.

[0022] In the first target route generation process, the target route generation unit 30D first automatically selects a plurality of work area identification points (four work area identification points Ap1 to Ap4 in Figure 4) to identify a work area A that is suitable for the shape of the field (for example, the outer shape of the field shown by the dashed line in Figure 4) based on the above-mentioned vehicle data, field data, and selected priority items, and identifies the work area A.The user is then notified by displaying the selected work area identification points Ap1 to Ap4 and the identified work area A together with the shape of the field, etc. on the liquid crystal panel 4 (see Figure 4). In specifying the working area A, if the number of work area specification points is increased, it is possible to specify a working area A that is faithful to the shape of the field, but the control load required to specify the working area A becomes heavy. Moreover, a working area A specified faithfully to the shape of the field is not necessarily suitable for generating a target path P for automatic travel of the tractor 1, and it is necessary to select work area specification points that allow appropriate simplification of the working area A relative to the shape of the field, taking into account the working width of the tractor 1, etc. For this reason, the number of selectable work area specification points is limited to a predetermined number (for example, 30 points) so that a working area A that is suitable for the shape of the field can be specified while preventing the control load from becoming excessive. Next, the reference working direction θp, the automatic driving start point ps, and the automatic driving end point pe are automatically selected taking into consideration priority items, etc., and the selected reference working direction θp, the automatic driving start point ps, and the automatic driving end point pe are displayed on the liquid crystal panel 4 together with the working area A, etc., to inform the user (see Figure 4). Then, based on the identified work area A, the selected reference work direction θp, the automatic driving start point ps, and the automatic driving end point pe, a first target route is generated as a target route P according to the priority items, and the generated first target route is displayed on the liquid crystal panel 4 together with the work area A, etc., to inform the user.

[0023] When the user selects the input of a work area identification point for identifying the work area A by touching the optional data input unit 33 (see Figure 2) and arbitrarily inputs multiple work area identification points (four work area identification points Ap1 to Ap4 in Figure 4), the target route generation unit 30D identifies the work area A based on each of the arbitrarily input work area identification points Ap1 to Ap4, and notifies the user by displaying each of the arbitrarily input work area identification points Ap1 to Ap4 and the identified work area A together with the shape of the field, etc. on the liquid crystal panel 4 (see Figure 4). Furthermore, when the user touches the arbitrary data input unit 33 to select input of the reference working direction θp and arbitrarily input the reference working direction θp, the arbitrarily input reference working direction θp is displayed on the liquid crystal panel 4 together with the working area A, etc., to inform the user (see FIG. 4). Furthermore, when the user selects input of the automatic driving start point ps and the automatic driving end point pe by touching the optional data input unit 33 and arbitrarily inputs the automatic driving start point ps and the automatic driving end point pe, the arbitrarily input automatic driving start point ps and automatic driving end point pe are displayed on the liquid crystal panel 4 together with the work area A, etc., to notify the user (see Figure 4). Then, when a command is received from the generation command unit 35 by the user operating the generation command unit 35 (see Figure 2), the second target route generation process generates a second target route as a target route P based on the identified work area A, the arbitrarily input reference work direction θp, the automatic driving start point ps, and the automatic driving end point pe, and displays the generated second target route together with the work area A, etc. on the liquid crystal panel 4 to inform the user.

[0024] For example, when a user operates the operation screen display process for a rectangular field as shown in Figures 5 and 6, and multiple work area specification points (four work area specification points Ap1 to Ap4 in Figures 5 and 6) are arbitrarily input to specify a rectangular work area A that can secure a circular travel path portion (circular travel area) P1 between the outer periphery of the field, as shown in Figure 5, and an automatic travel start point ps and an automatic travel end point pe are arbitrarily input so as to correspond to the entrance and exit of the field, and a reference work direction θp is arbitrarily input in a direction along the short side of the work area A, the target path generation unit 30D generates the second target path shown in Figure 5 as the target path P by second target path generation process.The generated second target path is then displayed on the liquid crystal panel 4 together with the above-mentioned path selection unit 32 and the like by the generated path selection process, and the user is prompted to select whether or not to adopt the generated second target path. The second target route shown in Figure 5 has multiple first straight work path sections P2a that have the same length as the short side of the work area A and are arranged in parallel at a fixed distance corresponding to the work width, and multiple direction change path sections P3 that extend from the end point to the starting point of adjacent first straight work path sections P2a, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe, which is arbitrarily input by the user.

[0025] For example, when a user operates the operation screen display process for a rectangular field as shown in Figures 5 and 6, and multiple work area specification points (four work area specification points Ap1 to Ap4 in Figures 5 and 6) are arbitrarily input to specify a rectangular work area A that can secure a circular travel path portion (circular travel area) P1 between the outer periphery of the field, as shown in Figure 6, and an automatic travel start point ps and an automatic travel end point pe are arbitrarily input so as to correspond to the entrance and exit of the field, and a reference work direction θp is arbitrarily input in a direction along the long side of the work area A, the target route generation unit 30D generates the second target route shown in Figure 6 as the target route P by second target route generation process. Then, by generated route selection process, the generated second target route is displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like, and the user is prompted to select whether or not to adopt the generated second target route. The second target route shown in Figure 6 has multiple second straight work path sections P2b that have the same length as the long side of the work area A and are arranged in parallel at a certain distance corresponding to the work width, and multiple direction change path sections P3 that extend from the end point to the starting point of adjacent second straight work path sections P2b, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe, which is arbitrarily input by the user. 6 has fewer direction-changing path sections P3 than the second target path shown in Fig. 5, and the travel distance of the tractor 1 is shorter, which can reduce fuel consumption and shorten work time. Furthermore, the number of path sections constituting the target path P is reduced, which can reduce the load required to generate the target path P.

[0026] For example, when the target route generating unit 30D receives a command from the generation command unit 35 in a state in which optimization of the circular travel path section P1 is selected as a priority item by a user's operation in an operation screen display process for a rectangular field as shown in Figures 5 to 6, the target route generating unit 30D automatically identifies, by a first target route generating process as shown in Figures 5 to 6, a plurality of work area specifying points (four work area specifying points Ap1 to Ap4 in Figures 5 to 6), an automatic traveling start point ps, an automatic traveling end point pe, etc., so as to obtain a rectangular work area A in which a circular travel path section (circular travel area) P1 can be secured between the outer periphery of the field, and generates two first target routes as shown in Figures 5 to 6 as target routes P corresponding to the optimization of the circular travel path section P1. Then, by a generated route selection process, the generated two first target routes are displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like, and the user is prompted to select whether or not to adopt one of the generated two first target routes. The first target route shown in Figure 5 has the aforementioned multiple first straight-line working route sections P2a and multiple direction-changing route sections P3, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe identified by the target route generation unit 30D. The first target route shown in Figure 6 has the aforementioned multiple second straight working route sections P2b and multiple direction change route sections P3, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe identified by the target route generation unit 30D. In this case, the user can use the route selection unit 32 to select whether or not to adopt one of the two first target routes as the target route P. When one of these first target routes is selected as the target route P, the width of the circular travel route section P1, which is made up of the unworked area remaining around the work area A in the center of the field after the tractor 1 has performed tillage work by automatically traveling thereon, can be made the same or approximately the same as an integer multiple of the work width. As a result, it becomes easier for the tractor 1 to perform circular work travel by manually driving or automatically traveling thereon. Here, if the user wishes to swap the positions of the automatic driving start point ps and the automatic driving end point pe on the first target route shown in Figures 5 to 6, for example, in relation to the entrance and exit of the tractor 1 in the field, the user can select not to adopt the first target route shown in Figures 5 to 6 in the route selection unit 32, input and correct any setting data to swap the positions of the automatic driving start point ps and the automatic driving end point pe, and then perform a command operation in the generation command unit 35.Based on this, the target route generation unit 30D will perform a target route correction process to generate a first target route in which the positions of the automatic driving start point ps and the automatic driving end point pe on the first target route shown in Figures 5 to 6 have been swapped.

[0027] For example, when the target route generation unit 30D receives a command from the generation command unit 35 in a state in which maximization of the work area and optimization of the circular travel route portion are selected as priority items by a user's operation in an operation screen display process for a rectangular field as shown in Figures 5 and 6, the target route generation unit 30D generates, by a first target route generation process, two first target routes shown in Figures 5 and 6 as target routes P. Then, by a generated route selection process, the generated two first target routes are displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like, and the user is prompted to select whether or not to adopt the generated two first target routes.

[0028] For example, when the target route generation unit 30D receives a command from the generation command unit 35 in a state in which minimizing the non-work travel distance and optimizing the circular travel path portion are selected as priority items by a user's operation in the operation screen display process for a rectangular field as shown in Figures 5 and 6, the target route generation unit 30D performs a first target route generation process as shown in Figure 6, in which a rectangular work area A is obtained that can secure a circular travel path portion (circular travel area) P1 between the outer periphery of the field, and the target route generation unit 30D automatically identifies multiple work area identification points (four work area identification points Ap1 to Ap4 in Figures 5 and 6), an automatic travel start point ps, an automatic travel end point pe, a reference work direction θp, etc., so as to minimize the non-work travel distance included in the automatic travel distance, and generates the first target route shown in Figure 6 as the target route P. Then, the generated first target route is displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like by the generated route selection process, and the user is prompted to select whether or not to adopt the generated first target route. The first target route shown in Figure 6 has the aforementioned multiple second straight working route sections P2b and multiple direction change route sections P3, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe identified by the target route generation unit 30D. In this case, the first target route shown in Fig. 6 has fewer direction-changing path sections P3 than the first target route shown in Fig. 5, thereby minimizing the non-work travel distance. Furthermore, after tillage work is performed in the work area A in the center of the field by the tractor 1 traveling automatically, the width of the circular travel path section P1 consisting of the remaining unworked area around it can be made the same or approximately the same as an integer multiple of the work width. As a result, it is possible to reduce fuel consumption and work time by shortening the non-work travel distance, and it becomes easier to perform circular work travel by the tractor 1, either manually or automatically.

[0029] For example, when the target route generating unit 30D receives a command from the generation command unit 35 in a state in which maximization of the work area, minimization of the non-work travel distance, and optimization of the circular travel route portion are selected as priority items by user operation in the operation screen display process for a rectangular field as shown in Figures 5 and 6, the target route generating unit 30D generates the first target route shown in Figure 6 as the target route P by first target route generating process. Then, by generated route selection process, the generated first target route is displayed on the liquid crystal panel 4 together with the above-mentioned route selection unit 32 and the like, and the user is prompted to select whether or not to adopt the generated first target route.

[0030] For example, when a user operates the operation screen display process for a concave-shaped field having a protruding portion 36 shown in Figures 7 and 8 to arbitrarily input a plurality of work area specification points (eight work area specification points Ap1 to Ap4 in Figure 7) for specifying the work area A as a concave shape that substantially follows the outer periphery of the field so as to maximize the work area A as shown in Figure 7, arbitrarily input an automatic traveling start point ps and an automatic traveling end point pe to correspond to the entrance and exit of the field, and arbitrarily input a reference work direction θp in a direction along the long side of the work area A, the target path generation unit 30D generates the second target path shown in Figure 7 as the target path P by a second target path generation process, and then displays the generated second target path on the liquid crystal panel 4 together with the path selection unit 32 and the like by a generated path selection process, prompting the user to select whether or not to adopt the generated second target path. The second target route shown in Figure 7 comprises the aforementioned multiple second straight work path sections P2b, a detour work path section P4 adjacent to the final second straight work path section P2b and equipped with a detour path section Pa that interrupts tillage work and bypasses the overhang section 36, and multiple direction change path sections P3 extending from the end points of the adjacent second straight work path sections P2b and detour work path sections P4 to their starting points, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe, which is arbitrarily input by the user. In this case, in the final second straight working path section P2b, the path section adjacent to the detour path section Pa is trampled when the tractor 1 automatically travels through the detour path section Pa, becoming an unworked section Pb, thereby narrowing the final working area.

[0031] For example, when the target path generation unit 30D receives a command from the generation command unit 35 with maximizing the work area selected as a priority item by a user operation in the operation screen display process for a concave-shaped field having an overhang 36 shown in Figures 7 and 8, the target path generation unit 30D first determines, through a first target path generation process, the difference in work area that occurs depending on whether or not there is a detour work path section P4 shown in Figure 7. Then, if the work area will be larger due to the presence of a detour work path section P4, as shown in Figure 7, the target path generation unit 30D automatically identifies multiple work area specification points (eight work area specification points Ap1 to Ap8 in Figure 7), an automatic traveling start point ps, an automatic traveling end point pe, a reference work direction θp, etc., so as to obtain a wide, concave work area A that roughly follows the outer periphery of the field in which the detour work path section P4 can be generated, as shown in Figure 7, and generates the first target path shown in Figure 7 as the target path P. Then, the generated first target route is displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like by the generated route selection process, and the user is prompted to select whether or not to adopt the generated first target route. Conversely, if the work area becomes narrower due to the inclusion of a detour work path section P4, then multiple work area specification points (four work area specification points Ap1 to Ap4 in FIG. 8), the automatic driving start point ps, the automatic driving end point pe, the reference work direction θp, etc. are automatically specified so as to obtain a narrow rectangular work area A in which no detour work path section P4 is generated, as shown in FIG. 8, and a first target route shown in FIG. 8 is generated as the target route P. Then, by a generated route selection process, the generated first target route is displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like described above, and the user is prompted to select whether or not to adopt the generated first target route. The first target route shown in Figure 7 has the aforementioned multiple second straight work path sections P2b, detour work path section P4, and multiple direction change path sections P3, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe identified by the target route generation unit 30D. The first target route shown in Figure 8 has the aforementioned multiple second straight working route sections P2b and multiple direction change route sections P3, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe identified by the target route generation unit 30D.

[0032] For example, when the target route generation unit 30D receives a command from the generation command unit 35 in a state in which minimizing the non-work travel distance has been selected as a priority item by a user operation in the operation screen display process for a concave-shaped field having an overhanging portion 36 shown in Figures 7 and 8, the target route generation unit 30D performs a first target route generation process to generate a first target route that does not include the detour work route section P4 shown in Figure 8 as the target route P. Then, by a generated route selection process, the generated first target route is displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like described above, and the user is prompted to select whether or not to adopt the generated first target route.

[0033] In other words, when generating a first target route (target route P) using the first target route generation process for a concave-shaped field with overhanging sections 36 as shown in Figures 7 and 8, the target route generation unit 30D determines, at the stage of identifying the working area A, whether it is more advantageous to identify a wide, concave working area A (see Figure 7) that requires a detour work path section P4, or to identify a narrow, rectangular working area A (see Figure 8) that does not require a detour work path section P4. If it is more advantageous to identify a wide, concave working area A, it selects a large number of work area identification points (eight work area identification points Ap1 to Ap8 in Figure 7) required for that identification, and then generates the first target route as described above. Conversely, if it is more advantageous to identify a narrow, rectangular working area A, it selects a small number of work area identification points (four work area identification points Ap1 to Ap4 in Figure 8) required for that identification, and then generates the first target route as described above.

[0034] For example, when the target route generating unit 30D receives a command from the generation command unit 35 while optimization of the circular travel path portion is selected as a priority item by a user's operation in the operation screen display process for a substantially rectangular field having an overhang portion 37 shown in Figures 9 to 12, the target route generating unit 30D automatically identifies, by a first target route generating process, a plurality of work area specifying points (four work area specifying points Ap1 to Ap4 in Figures 9 to 12), an automatic traveling start point ps, an automatic traveling end point pe, and the like, so as to obtain a rectangular work area A that can secure a circular travel path portion (circular travel area) P1 between the outer periphery of the field, and generates the first target route shown in Figure 9 as the target route P corresponding to the optimization of the circular travel path portion P1. Then, by a generated route selection process, the generated first target route is displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like, and the user is prompted to select whether or not to adopt the generated first target route. Here, if the user wishes to change the automatic driving end point pe from the position shown in Figure 9 to a position shown in Figures 10 to 12, for example, in relation to the entrance and exit of the tractor 1 in the field, the user can select not to adopt the first target route shown in Figure 9, etc. in the route selection unit 32, specify the reference working direction θp to a direction along the short side of the working area A, input and correct any setting data to change the position of the automatic driving end point pe to the position shown in Figures 10 to 12, and then perform a command operation in the generation command unit 35.Based on this, the target route correction process of the target route generation unit 30D can generate, for example, three systems of first target routes shown in Figures 10 to 12 as first target routes corresponding to the changed automatic driving end point pe. The first target route shown in Figure 10 comprises the above-mentioned multiple first straight work path sections P2a, a detour movement path section P5 adjacent to the final first straight work path section P2a and equipped with a detour path section Pa that bypasses the overhang section 37, and multiple direction change path sections P3 extending from the end points of the adjacent first straight work path sections P2a and detour movement path sections P5 to their starting points, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps identified by the target route generation unit 30D to the automatic travel end point pe corrected and input by the user. The first target route shown in Figure 11 comprises the aforementioned multiple first straight-line work path sections P2a, multiple direction-changing path sections P3 extending from the end point to the starting point of adjacent first straight-line work path sections P2a, and a circular driving path section P1 extending from the end point of the final first straight-line work path section P2a to the automatic driving end point pe, thereby enabling the tractor 1 to automatically drive from the automatic driving start point ps identified by the target route generation unit 30D to the automatic driving end point pe corrected and input by the user. The first target route shown in Figure 12 comprises the aforementioned multiple first straight work path sections P2a, multiple direction change path sections P3 extending from the end point to the starting point of adjacent first straight work path sections P2a, a single return direction change path section P6 extending from the end point of the final first straight work path section P2a to the starting point of the immediately preceding first straight work path section P2a adjacent to the final first straight work path section P2a, and a movement path section P7 extending from the end point of the immediately preceding first straight work path section P2a to the automatic driving end point pe.This route setting enables the tractor 1 to automatically drive from the automatic driving start point ps identified by the target route generation unit 30D to the automatic driving end point pe corrected and input by the user on the immediately preceding first straight work path section P2a. In this case, the user can use the route selection unit 32 to select whether or not to adopt one of the three first target routes as the target route P through the generated route selection process of the target route generation unit 30D. If the first target route shown in Figure 10 is selected as the target route P, the non-work travel distance on the target route P will be relatively short, which can reduce fuel consumption and work time by shortening the non-work travel distance. On the other hand, in the final first straight work route section P2a, the route portion adjacent to the detour route section Pa will be trampled when the tractor 1 automatically travels on the detour route section Pa, leaving an unworked section Pb, which will narrow the final work area. 11 is selected as the target route P, work can be performed over the entire working area A, and it is possible to avoid problems such as the tractor 1 traveling multiple times along the same route portion that overlaps with the target route P, causing that portion to become compacted and making work difficult. On the other hand, the inclusion of the circular travel route portion P1 increases the non-work travel distance on the target route P, which increases fuel consumption and lengthens work time. 12 is selected as the target route P, not only can work be carried out across the entire working area A, but the shorter non-work travel distance on the target route P can reduce fuel consumption and work time by shortening the non-work travel distance. On the other hand, there is a risk that overlapping travel, in which the tractor 1 travels twice along the immediately-final first straight work path section P2a, may cause the immediately-final first straight work path section P2a to become compacted, making it difficult to work.

[0035] 9 to 12, multiple work area specification points (four work area specification points Ap1 to Ap4 in FIG. 10) for specifying the work area A as a rectangular shape different from the shape of the field are arbitrarily input, an automatic traveling start point ps and an automatic traveling end point pe are arbitrarily input so as to correspond to the entrance and exit of the field, and a reference work direction θp is arbitrarily input in a direction along the short side of the work area A. In this state, when a command is received from the generation command unit 35, the target route generation unit 30D generates the second target route shown in FIG. 10 as the target route P by second target route generation processing. Then, by generated route selection processing, the generated second target route is displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like, and the user is prompted to select whether or not to adopt the generated second target route. Here, for example, if the user is dissatisfied with the second target route shown in Figure 10 due to the occurrence of an unworked portion Pb in the final first straight work route section P2a, the user can select not to adopt the second target route shown in Figure 10 in the route selection unit 32, select maximization of the work area as the priority item for correction, and then perform a command operation in the generation command unit 35.Based on this, the target route correction process of the target route generation unit 30D can generate, for example, two systems of second target routes as shown in Figures 11 and 12 as second target routes after correction based on maximization of the work area. Furthermore, if the user is dissatisfied with the second target route shown in FIG. 10 as described above, for example, the user can select not to adopt the second target route shown in FIG. 10 in the route selection unit 32, and then select maximization of the working area and avoidance of the generation of overlapping route section P0 as the priority items for correction, and then perform a command operation in the generation command unit 35.The target route correction process of the target route generation unit 30D based on this will generate, for example, the second target route shown in FIG. 11 as the second target route after correction based on maximization of the working area and avoidance of the generation of overlapping route section P0. Furthermore, if the user is dissatisfied with the second target route shown in Figure 10 as described above, for example, the user can select not to adopt the second target route shown in Figure 10 in the route selection unit 32, select maximization of the work area and minimization of the non-work travel distance as the priority items for correction, and then perform a command operation in the generation command unit 35.The target route correction process of the target route generation unit 30D based on this will generate a second target route, for example, as shown in Figure 12, as a modified second target route based on maximization of the work area and minimization of the non-work travel distance.

[0036] 13 to 15, the target route generating unit 30D generates the second target route shown in FIG. 13 as the target route P by second target route generation processing when the user operates the operation screen display processing for a concave-shaped field having a protruding portion 38 shown in FIGS. 13 to 15, and when the user arbitrarily inputs a plurality of work area specifying points (eight work area specifying points Ap1 to Ap8 in FIG. 13) for specifying the work area A as a concave shape similar to the shape of the field, arbitrarily inputs an automatic traveling start point ps and an automatic traveling end point pe so as to correspond to the entrance and exit of the field, and arbitrarily inputs a reference work direction θp in a direction along the long side of the work area A. Then, when the target route generating unit 30D receives a command from the generation command unit 35 in this state, the target route generating unit 30D generates the second target route shown in FIG. 13 as the target route P by second target route generation processing, and when the user operates the operation screen display processing for a concave-shaped field having a protruding portion 38 shown in FIGS. 13 to 15, the user arbitrarily inputs a plurality of work area specifying points (eight work area specifying points Ap1 to Ap8 in FIG. 13) for specifying the work area A as a concave shape similar to the shape of the field, arbitrarily inputs an automatic traveling start point ps and an automatic traveling end point pe so as to correspond to the entrance and exit of the field, and arbitrarily inputs a reference work direction θp in a direction along the long side of the work area A. Then, the generated second target route is displayed on the liquid crystal panel 4 by the generated route selection processing, together with the route selection unit 32 and the like, and the user is prompted to select whether or not to adopt the generated second target route. The second target route shown in Figure 13 comprises the aforementioned multiple second straight work path sections P2b, two detour work path sections P4 having a common detour path portion Pa that bypasses the overhanging portion 38, and multiple direction change path sections P3 extending from the terminal points to the starting points of the adjacent first straight work path section P2a and detour work path section P4, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe, which is arbitrarily input by the user. In this case, the common detour route portion Pa becomes an overlapping route portion P0 where the tractor 1 overlaps during automatic driving of the tractor 1, which may cause problems such as the detour route portion Pa being compacted by the overlapping driving of the tractor 1, making it difficult to carry out work.

[0037] For example, when the target route generating unit 30D receives a command from the generation command unit 35 while optimization of the circular travel path portion is selected as a priority item by a user's operation in the operation screen display process for a concave-shaped field having an overhanging portion 38 shown in FIGS. 13 to 15, the target route generating unit 30D automatically identifies, by a first target route generating process, a plurality of work area specifying points (eight work area specifying points Ap1 to Ap8 in FIGS. 13 and 14, nine work area specifying points Ap1 to Ap9 in FIG. 15), an automatic traveling start point ps, an automatic traveling end point pe, and the like, so as to obtain a concave-shaped work area A that can secure a circular travel path portion (circular travel area) P1 between the outer periphery of the field, and generates the first target route shown in FIG. 13 as a target route P corresponding to the optimization of the circular travel path portion P1. Then, by a generated route selection process, the generated first target route is displayed on the liquid crystal panel 4 together with the route selection unit 32 and the like, and the user is prompted to select whether or not to adopt the generated first target route. Here, if the user is dissatisfied with the presence of an overlapping path section P0 in the first target path shown in FIG. 13, for example, the user can select not to adopt the first target path shown in FIG. 13 in the path selection unit 32, and then select avoiding the generation of the overlapping path section P0 as a priority item for correction, and then perform a command operation in the generation command unit 35. Based on this, the target path correction process of the target path generation unit 30D can generate, for example, two systems of first target paths as shown in FIGS. 14 to 15 as first target paths after correction based on avoiding the generation of the overlapping path section P0. In generating the first target route shown in Fig. 15, the target route generation unit 30D selects nine work area specification points Ap1 to Ap9, automatically divides the concave-shaped work area A into two areas: a wider, L-shaped first area A1 and a narrower, rectangular second area A2, and automatically specifies the travel start and end points in the first area A1 and the second area A2. The first target route shown in Fig. 14 includes the aforementioned multiple second straight work path sections P2b, two detour work path sections P4 with detour path sections Pa that bypass the overhanging section 38, and multiple direction change path sections P3 that extend from the end points of the adjacent first straight work path section P2a and detour work path section P4 to the start points, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe specified by the target route generation unit 30D. In other words, the first target route shown in Figure 14 has two detour work path sections P4, and therefore eliminates the overlapping path section P0 where the tractor 1 would travel in an overlapping manner, which was generated in the first target route shown in Figure 13.This prevents the overlapping path section P0 from becoming compacted, making it difficult to carry out work. The first target route shown in Figure 15 includes the aforementioned multiple second straight work path sections P2b generated in the wide area of ​​the first area A1, multiple third straight work path sections P2c generated in the narrow area of ​​the first area A1 with the same layout as the second straight work path section P2b, a fourth straight work path section P2d generated in the second area A2 with the same layout as the second straight work path section P2b, multiple direction change path sections P3 extending from the end points to the start points of the adjacent first straight work path sections P2a to fourth straight work path sections P2d, and a single detour movement route section P8 having a detour route section Pa that bypasses the overhang section 38 and extending from the end point of travel in the first area A1 to the start point of travel in the second area A2, thereby enabling the tractor 1 to travel automatically from the automatic travel start point ps to the automatic travel end point pe identified by the target route generation unit 30D. In other words, the first target route shown in Figure 15 has a single detour movement route section P8, and therefore does not have the overlapping route section P0 where the tractor 1 travels in an overlapping manner, which was generated in the first target route shown in Figure 13.This makes it possible to avoid problems such as the overlapping route section P0 becoming compacted and making it difficult to work.

[0038] For example, when the target route generation unit 30D receives a command from the generation command unit 35 in a state in which, through user operation in the operation screen display process for a trapezoidal field as shown in Figures 16-17, multiple work area specification points (four work area specification points Ap1-Ap4 in Figure 16) are arbitrarily input to specify the work area A as a rectangle different from the shape of the field, as shown in Figure 16, the automatic driving start point ps and the automatic driving end point pe are arbitrarily input to correspond to the entrance and exit of the field, and the reference work direction θp is arbitrarily set in a direction along the long side of the work area A, the target route generation unit 30D generates the second target route shown in Figure 16 as the target route P by the second target route generation process. The second target route shown in Figure 16 has the above-mentioned multiple second straight-line work path sections P2b and multiple direction-changing path sections P3 extending from the end point to the starting point of adjacent second straight-line work path sections P2b, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe, which is arbitrarily input by the user.

[0039] For example, when the target route generation unit 30D receives a command from the generation command unit 35 with optimization of the circular driving path section P1 selected as a priority item as shown in Figure 17 through a user operation in the operation screen display process for a trapezoidal field as shown in Figures 16-17, the target route generation unit 30D automatically identifies multiple work area identification points (four work area identification points Ap1-Ap4 in Figure 17), the automatic driving end point pe, the work width, etc., through a first target route generation process so as to obtain a trapezoidal working area A that can secure a circular driving path section (circular driving area) P1 between it and the outer edge of the field, and generates the first target route shown in Figure 17 as the target route P. The first target route shown in Figure 17 has the above-mentioned multiple second straight work path sections P2b and multiple direction change path sections P3 extending from the end point to the starting point of adjacent second straight work path sections P2b, thereby enabling the tractor 1 to automatically travel from the automatic travel start point ps to the automatic travel end point pe identified by the target route generation unit 30D. The multiple second straight-line work path sections P2b in the first target route shown in Figure 17 are set so that the orientation of each second straight-line work path section P2b has a different adjustment angle θa relative to the reference work direction θp, based on the trapezoidal shape of the work area A, so that when the tractor 1 automatically travels along the second straight-line work path sections P2b, the amount of overlap in the work width gradually changes according to the trapezoidal shape of the work area A. As a result, after the tractor 1 has completed tilling work in the work area A in the center of the field by autonomous driving, the width of the circular travel path section P1 consisting of the remaining unworked area around it can be made the same or approximately the same as an integral multiple of the work width. As a result, it becomes easier for the tractor 1 to perform circular work travel by manual driving or autonomous driving.

[0040] For example, in a state where a user inputs a switchback turn shown in FIG. 19, which uses a switchback that is applied when the minimum turning radius is greater than half the working width, as a turning method through an operation screen display process, rather than the normal U-turn shown in FIG. 18, which is applied when the minimum turning radius is equal to or less than half the working width, as the turning method, through a second target route generation process, the target route generation unit 30D generates a second target route having a second direction change route section P3b for the switchback turn shown in FIG. 19 as the target route P. If a command is received from the generation command unit 35 with maximizing the working area selected as the priority item for correction, the target route generation unit 30D first determines, through a target route correction process, whether or not the use of a switchback turn is appropriate based on the minimum turning radius and working width of the tractor 1 included in the vehicle body data. If the use of a switchback turn is appropriate, the user inputs the switchback turn and generates the above-mentioned direction change route section P3 as the second direction change route section P3b for the switchback turn shown in FIG. Furthermore, if the use of a switchback turn is inappropriate, the turning method is changed from the arbitrarily input switchback turn to a U-turn, and the above-mentioned direction change path section P3 is generated as the first direction change path section P3a for a U-turn shown in Figure 18. This change in turning method makes it possible to eliminate the non-working area A3 at the edge of the field that had to be secured in order to use a switchback turn with a switchback path section Pc that is longer than the working width, thereby maximizing the working area.

[0041] Although not shown in the figure, when the target route generation unit 30D generates multiple target routes P, it performs a calculation process to determine the differences in the working area, non-working travel distance, etc. based on those target routes P, and then performs a difference display process to notify the user of the differences in the working area, non-working travel distance, etc. obtained by this calculation process by displaying them on the liquid crystal panel 4 together with the multiple generated target routes P. This allows the user to easily visually recognize the differences between multiple target routes P when the target route generation unit 30D generates them, and to easily select a target route P that is more suited to the user's own values, etc.

[0042] The target route generating unit 30D stores the generated target route P in the terminal storage unit 30A as route data associated with vehicle body data, farm field data, and the like. This allows the target route generation unit 30D to perform the aforementioned field data confirmation processing based on the current position of the tractor 1 acquired by the positioning data acquisition unit 30B, and the aforementioned target route confirmation processing based on the field data and vehicle data.

[0043] Although not shown in the figure, if the target route generation unit 30D finds that the arbitrary setting data input by the user's operation in the operation screen display process is inappropriate and therefore it is not possible to generate a target route P based on the arbitrary setting data, it performs an error display process to notify the user that it is not possible to generate the target route P and the cause of this by displaying it on the liquid crystal panel 4, and a solution display process to suggest a solution to the problem to the user by displaying it on the liquid crystal panel 4. For example, if the work area A identified from multiple work area identification points input by the user's operation in the operation screen display process is too small to generate the target route P, first, in the error display process, error messages such as "Target route generation error" and "Target route not generated because work area is too small" are displayed on the LCD panel 4 to notify the user. Then, in the solution display process, the shape of the field to be worked on, the appropriate work area A for this field shape, and a message to confirm changing the settings to this appropriate work area A are displayed on the LCD panel 4 to notify the user. For example, if the shape of the work area A identified from multiple work area identification points input by user operation in the operation screen display process is too complex and it is impossible to generate the target route P, first, in the error display process, error messages such as "Target route generation error" and "Target route not generated because the work area is too complex" are displayed on the LCD panel 4 to notify the user. Then, in the solution display process, the shape of the field to be worked on, the work area A that has been appropriately simplified in relation to the shape of this field, and a message to confirm changes to the settings for this simplified work area A are displayed on the LCD panel 4 to notify the user. For example, if the reference working direction θp input by the user's operation in the operation screen display process is inappropriate and it is impossible to generate the target path P, first, in the error display process, error messages such as "Target path generation error" and "Target path not generated due to inappropriate reference working direction" are displayed on the LCD panel 4 to notify the user. Then, in the solution display process, the shape of the field to be worked on, the reference working direction θp appropriate for this field shape, and a message to confirm changing the setting to this appropriate reference working direction θp are displayed on the LCD panel 4 to notify the user.

[0044] From the above points, according to this target route generation system, when generating a target route P for automatic driving, the user can select between a normal operation in which all of the optional setting data required to generate the target route P is input at the optional data input unit 33, and a simplified operation in which priority items are selected at the priority item selection unit 34 according to the user's own values, etc. As a result, if the user is accustomed to inputting the arbitrary setting data, the user can obtain a target route P (second target route) based on his / her own values, etc., by performing a normal operation. Also, if the user is not good at inputting the arbitrary setting data, the user can easily obtain a target route P (first target route) that suits his / her own values, etc., by performing a simple operation. Then, if the user is dissatisfied with the generated target route P, the user can correct or add the arbitrary setting data in the arbitrary data input unit 33, or select additional priority items in the priority item selection unit 34, as a correction operation to resolve the dissatisfaction, thereby obtaining a target route P that resolves the dissatisfaction.

[0045] [Another embodiment] Another embodiment of the present invention will now be described. The configurations of the embodiments described below are not limited to being applied independently, but can also be applied in combination with the configurations of other embodiments.

[0046] (1) The target route generation system for the work vehicle may be included in the work vehicle 1.

[0047] (2) The configuration of the work vehicle 1 can be modified in various ways. For example, the work vehicle 1 may be configured as a hybrid vehicle equipped with the engine 10 and an electric motor for running, or may be configured as an electric vehicle equipped with an electric motor for running instead of the engine 10. For example, the work vehicle 1 may be configured as a rear-wheel steering vehicle in which the left and right rear wheels 8 function as steering wheels. For example, the work vehicle 1 may be configured as a semi-crawler vehicle having left and right crawlers instead of the left and right rear wheels 8. For example, the work vehicle 1 may be configured as a full crawler vehicle, provided with left and right crawlers instead of the left and right front wheels 7 and the left and right rear wheels 8.

[0048] (3) When generating a second target route based on arbitrarily set data as the target route P, the target route generation unit 30D may be configured to automatically generate a first target route based on priority items, and to display the second target route and the first target route on the display unit 4, as well as to display the difference between the second target route and the first target route based on the priority items.

[0049] (4) When generating a first target route based on a priority item selected as the target route P, the target route generation unit 30D may be configured to automatically generate first target routes based on other priority items, and display those first target routes on the display unit 4, as well as display differences in those first target routes based on the priority items.

[0050] (5) The priority item selection unit 34 may be configured to have, as the above-mentioned priority items, reduction in fuel consumption, reduction in work time, reduction in the number of each route section on the target route P, or the like.

[0051] (6) The route selection unit 32, the arbitrary data input unit 33, and the priority item selection unit 34 may be configured, for example, by a keyboard equipped with key switches.

[0052] <Notes on the invention> A first configuration is a target path generation system for a work vehicle, a storage unit that stores basic data necessary to generate a target route for automatic driving; a priority item selection unit that selects priority items related to the generation of the target route; a target route generation unit that generates the target route based on the basic data and the selected priority items; The point is that it has the following.

[0053] According to this configuration, when a user selects priority items in the priority item selection unit according to their own values, etc., the target route generation unit generates a target route that is appropriate for the user's values, etc., based on the basic data stored in the memory unit and the priority items selected by the user. This allows the user to obtain a target route that suits their own values, etc., simply by selecting priority items according to their own values, etc., without having to input any optional setting data required to generate the target route, such as multiple work area specific points, work start position, work start direction, and work end position. In other words, it is possible to generate a target route for automatic driving that is suited to the user's values, etc., without forcing the user to input arbitrary setting data, thereby making work through automatic driving more profitable.

[0054] The second configuration is The present invention is characterized in that, when the target route generating unit generates a plurality of the target routes, the present invention has a route selecting unit that selects one of the plurality of the target routes alternatively.

[0055] According to this configuration, for example, if the target route generation unit generates multiple target routes, the user can select a target route for automatic driving from the multiple target routes that is more suitable for the user's own values, etc., and can more effectively make work more profitable through automatic driving.

[0056] The third configuration is: The target route generating unit generates a plurality of the target routes for one of the priority items.

[0057] According to this configuration, even if a user selects a single priority item in the priority item selection unit that corresponds to their own values, etc., multiple target routes corresponding to that priority item are generated by the target route generation unit, so the user can select a target route for automatic driving that is more suitable to their own values, etc. from the multiple target routes that correspond to the single priority item selected, thereby making it possible to more effectively make work more profitable through automatic driving.

[0058] The fourth configuration is: an arbitrary data input unit into which arbitrary setting data for generating a target route is input; The target route generation unit generates a plurality of target routes, including a first target route based on the basic data and the priority items, and a second target route based on the basic data and the arbitrarily set data.

[0059] According to this configuration, when generating a target route for automatic driving, the user can choose between a simple operation of simply selecting a priority item in the priority item selection section, and a normal operation of arbitrarily inputting all of the optional setting data required to generate the target route in the optional data input section. As a result, if the user is not good at inputting arbitrary setting data, by performing a simple operation, the first target route that suits the user's own values, etc. can be obtained without any hassle. Also, if the user is accustomed to inputting arbitrary setting data, by performing a normal operation, the second target route based on the user's own values, etc. can be obtained. As a result, users who are not good at inputting optional setting data can make the work performed by the automated driving more effective by performing a simple selection operation, while users who are accustomed to inputting optional setting data can make the work performed by the automated driving more effective by inputting the optional setting data properly.

[0060] The fifth configuration is: a display unit that displays the target route, When the target route generating section generates a plurality of target routes, the display section displays the plurality of target routes together with a difference between the plurality of target routes.

[0061] According to this configuration, when the target route generation unit generates multiple target routes, the user can easily visually see the differences between them, thereby enabling the user to easily select a target route that is more suited to the user's own values, etc.

[0062] The sixth configuration is: an arbitrary data input unit into which at least a part of arbitrary setting data for generating a target route is input; The target route generating unit modifies the first target route based on the arbitrarily set data.

[0063] According to this configuration, if the user is dissatisfied with the target route generated by the target route generation unit based on the priority items selected by the user, the user inputs optional setting data suitable for resolving the dissatisfaction into the optional data input unit. The target route generation unit then corrects the target route according to the priority items based on the optional setting data input by the user. This allows the user to obtain a target route that resolves the dissatisfaction. Specifically, if the user is dissatisfied because the start point or end point of the automatic driving on the target route is far from the entrance / exit of the work vehicle at the work site, the user can input an automatic driving start point or end point that is suitable for resolving that dissatisfaction into the optional data input unit, and the target route generation unit will modify the target route according to the priority items based on the automatic driving start point and end point input by the user, allowing the user to obtain a target route in which the automatic driving start point and end point are set close to the entrance / exit of the work vehicle at the work site. As a result, by performing relatively simple operations, the user can obtain a target route that is more suited to their own values, etc., and can more effectively make work more profitable through automated driving.

[0064] The seventh configuration is: The priority items include at least one of maximizing the work area, minimizing non-work driving distance, optimizing the circular driving route portion along the periphery of the work area, and avoiding the creation of overlapping route portions.

[0065] According to this configuration, for example, if the priority item is maximizing the work area, the target route generation unit generates a target route based on this priority item that maximizes the work area that can be achieved by the work vehicle's automatic driving. For example, if the priority item is minimizing non-work driving distance, the target route generation unit generates a target route based on this priority item that can reduce fuel consumption required for non-work driving and shorten work time when the work vehicle is driving automatically. For example, if the priority is optimization of the circular travel path section, the target route generation unit generates a target route based on this priority, such that the width of the circular travel path section that becomes the unworked area after traveling through the center of the work area during automatic driving of the work vehicle is the same as or approximately the same as an integer multiple of the work width of the work vehicle, regardless of the shape of the work area. This makes it easier for the work vehicle to perform circular work driving by automatic driving or manual driving. This target route is suitable for automatic driving of work vehicles such as plowing work using a tilling-spec tractor or planting work using a riding rice transplanter. For example, if the priority item is to avoid generating overlapping route sections, the target route generation unit generates a target route that does not have overlapping route sections based on this priority item. This makes it possible to avoid problems that occur when a work vehicle travels multiple times on the same route section that overlaps with the target route, causing the route section to become compacted and making it difficult to work. This target route is suitable for use in automated driving of work vehicles, such as plowing work using a tilling-spec tractor or planting work using a riding rice transplanter. In other words, it is possible to generate a target route according to each priority item, which makes it easier to make work more profitable through automated driving that suits the different values ​​of each user.

[0066] A target path generation system for a work vehicle according to one embodiment includes a target path generation unit that generates a target path for automatically driving a work vehicle from an automatic driving start point to an automatic driving end point. The target path includes a plurality of straight work path sections that are set in parallel. Among the plurality of straight work path sections, one straight work path section other than a final straight work path section that is in the opposite direction to the traveling direction of the final straight work path section is subjected to overlapping driving in which the work vehicle drives multiple times, with the first drive of the overlapping drives being a non-work drive and the second drive being a work drive.

[0067] A target route generation system for a work vehicle according to one aspect includes a target route generation unit that generates a target route for automatic driving of the work vehicle. The target route is generated based on specific items. [Explanation of symbols]

[0068] 4 Display 30A storage section 30D Target path generation unit 32 Route selection section 33 Optional data input section 34 Priority selection section P Target Route

Claims

1. A route generating unit that generates a plurality of straight-line routes for automatically driving a work vehicle in a farm field, The path generation unit adjusts the orientation of each of the plurality of straight path based on the shape of the field. A target path generation system for a work vehicle.

2. the path generation unit generates the plurality of straight-line paths based on a reference working direction, and when a non-parallel outer edge that is an outer edge of the field that is non-parallel to the reference working direction is located in a direction in which the plurality of straight-line paths are aligned, adjusts the orientation of each of the plurality of straight-line paths based on the reference working direction and the non-parallel outer edge. The target route generation system for a work vehicle according to claim 1 .

3. the path generation unit adjusts the orientation of each of the plurality of straight-line paths such that a straight-line path having a shorter distance to the non-parallel outer edge among the plurality of straight-line paths has an orientation closer to the non-parallel outer edge. The target route generation system for a work vehicle according to claim 2 .

4. generating a plurality of straight-line paths for automatically driving a work vehicle in a farm field; and adjusting an orientation of each of the plurality of linear paths based on a shape of the field. A method for generating a target path for a work vehicle.

Citation Information

Patent Citations

  • Device for preparing running data of working vehicle, and guidance and control device

    JP1997178481A

  • Agricultural working vehicle

    JP2017127289A

  • Route generation device

    JP2017173986A

  • Work vehicle automatic traveling system and traveling route management device

    JP2018038291A

  • Method for avoiding point rows for quadrilateral fields using autoguidance

    US20100262342A1