Fatigue testing machine management device and fatigue testing machine management system

The fatigue testing machine management device and system address the labor-intensive issue of monitoring multiple machines by enabling centralized progress tracking and display, enhancing operator efficiency.

JP7559560B2Active Publication Date: 2024-10-02SHIMADZU SEISAKUSHO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
JP2021002355
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-01-08
Publication Date
2024-10-02
Estimated Expiration
2041-01-08

AI Technical Summary

Technical Problem

Existing fatigue testing machines require operators to manually check the progress status of multiple machines, which is time-consuming and labor-intensive, especially when managing a large number of machines.

Method used

A fatigue testing machine management device and system that communicates with multiple machines to acquire and display progress information, allowing centralized monitoring and management of fatigue tests across multiple machines.

Benefits of technology

Enables operators to easily check the progress of each machine's fatigue test, reducing labor and improving efficiency by providing centralized monitoring and display of test status.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007559560000001
    Figure 0007559560000001
  • Figure 0007559560000002
    Figure 0007559560000002
  • Figure 0007559560000003
    Figure 0007559560000003
Patent Text Reader

Abstract

To allow operators to easily confirm the progress situation of a fatigue test corresponding to each of a plurality of fatigue testers.SOLUTION: A management device 3 of a fatigue tester 1 communicatively connected to a plurality of fatigue testers 1 includes: an acquisition unit 312 that acquires progress information JP indicating a progress situation of a fatigue test in each of the fatigue testers 1 from each of the fatigue testers 1; and a display control unit 313 that displays the progress information JP of the fatigue test corresponding to each of the fatigue testers 1 on an LCD 331.SELECTED DRAWING: Figure 4
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a fatigue testing machine management device and a fatigue testing machine management system. [Background technology]

[0002] Various techniques are known for reducing the burden on operators in fatigue testing machines. For example, the fatigue testing machine described in Patent Document 1 is provided with a means for setting the amplitude and frequency range of the repeating waveform, and while a test specimen is attached, it automatically changes the frequency in sequence within the set frequency range, drives and controls the loading mechanism (hydraulic cylinder) so that a test force is applied to the test specimen at the set amplitude, takes in the output of the force detection means for each frequency, creates a graph showing the frequency response characteristics of the system including the test specimen, and outputs it for display or the like. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2006-292400 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, in the fatigue testing machine described in Patent Document 1, the progress of the fatigue test is shown on a display located in an easy-to-operate position on the main body of the testing machine, so in order to check the progress of multiple fatigue testing machines, an operator had to display and check the progress on the corresponding display for each fatigue testing machine. This could be time-consuming for the operator to check the progress of each fatigue test on multiple fatigue testing machines. For example, it may take several hours for one operator to check the progress of fatigue tests on 50 to 100 fatigue testing machines.

[0005] The present invention has been made in consideration of the above circumstances, and has an object to provide a fatigue testing machine management device and a fatigue testing machine management system that can reduce the burden on operators. [Means for solving the problem]

[0006] A fatigue testing machine management device according to a first aspect of the present invention is a fatigue testing machine management device that is communicatively connected to a plurality of fatigue testing machines, and includes an acquisition unit that acquires progress information indicating the progress of fatigue testing in each of the plurality of fatigue testing machines from each of the plurality of fatigue testing machines, and a display control unit that displays the progress information corresponding to each of the plurality of fatigue testing machines.

[0007] A fatigue testing machine management system according to a second aspect of the present invention is a fatigue testing machine management system comprising a plurality of fatigue testing machines and a management device communicatively connected to the plurality of fatigue testing machines, the management device comprising an acquisition unit that acquires progress information indicating the progress of fatigue testing in each of the plurality of fatigue testing machines from each of the plurality of fatigue testing machines, and a display control unit that displays the progress information corresponding to each of the plurality of fatigue testing machines. Effect of the Invention

[0008] The fatigue testing machine management device according to the first embodiment of the present invention and the fatigue testing machine management system according to the second embodiment of the present invention display progress information of fatigue tests corresponding to each of the plurality of fatigue testing machines, so that an operator can easily check the progress of the fatigue tests corresponding to each of the plurality of fatigue testing machines, thereby reducing the operator's workload. [Brief description of the drawings]

[0009] [Figure 1] FIG. 1 is a diagram illustrating an example of a configuration of a management system according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a diagram showing an example of the configuration of a fatigue testing machine. [Diagram 3] FIG. 13 is a diagram showing an example of a change in stress acting on a test piece. [Figure 4]FIG. 2 illustrates an example of the configuration of a management device and a control device. [Diagram 5] FIG. 13 is a screen diagram showing an example of a progress management screen. [Figure 6] 13(A) to 13(C) are diagrams showing other embodiments of the progress bar. [Figure 7] 10 is a flowchart illustrating an example of a process of a management device according to the present embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0010] Hereinafter, the present embodiment will be described with reference to the drawings.

[0011] [1. Management system configuration] FIG. 1 is a diagram showing an example of the configuration of a management system 100 according to the present embodiment. The management system 100 includes a plurality of fatigue testing machines 1 and a management device 3 . The plurality of fatigue testing machines 1 include a first fatigue testing machine 1A, a second fatigue testing machine 1B, and an Nth fatigue testing machine. The integer N is, for example, 50 or 100. In this embodiment, for convenience of explanation, the plurality of fatigue testing machines 1 are, for example, a first fatigue testing machine 1A to a seventh fatigue testing machine 1G. The management system 100 corresponds to an example of a "fatigue testing machine management system".

[0012] Each of the first fatigue testing machine 1A to the Nth fatigue testing machine performs a fatigue test on the test piece SP. Each of the first fatigue testing machine 1A to the Nth fatigue testing machine repeatedly applies, for example, a tensile stress σ to the test piece SP. The tensile stress σ and the number of repetitions are set in advance. The number of repetitions is, for example, 10 2 times ~10 8 times. The first fatigue test machine 1A to the Nth fatigue test machine have substantially the same configuration, and therefore in the following description, when the first fatigue test machine 1A to the Nth fatigue test machine are not to be distinguished from one another, they may be referred to as fatigue test machine 1. The configuration of the fatigue testing machine 1 will be described later with reference to FIG.

[0013] The management device 3 is communicably connected to each of the first fatigue test machine 1A to the Nth fatigue test machine via the network NW. The management device 3 manages the progress of the fatigue test of each of the first fatigue test machine 1A to the Nth fatigue test machine. In this embodiment, the network NW is a local area network (LAN), and is configured with, for example, cables conforming to the Ethernet (registered trademark) standard. The configuration of the management device 3 will be described later with reference to FIG.

[0014] In this embodiment, the network NW is configured with cables conforming to the Ethernet (registered trademark) standard, but the network NW may perform wireless communication such as Wi-Fi (registered trademark). In addition, in this embodiment, the case where the network NW is a LAN will be described, but the network NW may be a WAN (Wide Area Network) or the Internet. When the network NW is the Internet, the management device 3 is configured as, for example, a server device.

[0015] [2. Configuration of fatigue testing machine] 2 is a diagram showing an example of the configuration of the fatigue testing machine 1. The fatigue testing machine 1 includes a testing machine main body 10 and a control unit 20. The testing machine main body 10 performs a fatigue test on the test piece SP in accordance with instructions from the control unit 20. The control unit 20 controls the operation of the testing machine main body 10.

[0016] As shown in FIG. 2, the testing machine body 10 is configured by forming a load frame on a base 11 with a pair of support columns 12a, 12b and a yoke 13, and by fixing a crosshead 14 to the support columns 12a, 12b.

[0017] A hydraulic actuator 15 is disposed on the base 11, and a lower jig 16a for fixing the lower end of the test piece SP is attached to a piston rod 15a of the hydraulic actuator 15. In addition, an upper jig 16b for fixing the upper end of the test piece SP is attached to the crosshead 14 via a load cell 17. The load cell 17 detects the test force acting on the test piece SP.

[0018] In the hydraulic actuator 15, the direction and amount of pressure oil are controlled by the servo valve 18, and the piston rod 15a extends and retracts. As a result, a test force is applied to the test piece SP fixed between the upper jig 16b and the lower jig 16a. The stroke of the hydraulic actuator 15, i.e., the displacement of the test piece SP, is detected by a differential transformer 19 attached to the hydraulic actuator 15.

[0019] The control unit 20 includes a signal input / output device 21A, a control device 21B, and an input / output device 22. The signal input / output device 21A is disposed between the testing machine main body 10 and the control device 21B, and processes various signals input to and output from the control device 21B. The signal input / output device 21A includes a first amplifier 23, a first A / D converter 24, a second amplifier 27, a second A / D converter 28, a third amplifier 25, and a D / A converter 26.

[0020] The first amplifier 23 amplifies the test force signal output from the load cell 17 and outputs the amplified signal to the first A / D converter 24 . The first A / D converter 24 performs A / D conversion on the test force signal amplified by the first amplifier 23 to generate test force information, and outputs the generated test force information to the control device 21B. The second amplifier 27 amplifies the displacement signal output from the differential transformer 19 and outputs it to the second A / D converter . The second A / D converter 28 A / D converts the displacement signal amplified by the second amplifier 27 to generate displacement information, and outputs the generated displacement information to the control device 21B.

[0021] The control device 21B generates command information based on the test force information input from the first A / D converter 24 and the displacement information input from the second A / D converter 28, and outputs the command information to the D / A converter 26. The D / A converter 26 performs D / A conversion on the command information input from the control device 21B to generate a command signal, and outputs the generated command signal to the third amplifier 25. The third amplifier 25 amplifies the control signal output from the D / A converter 26 and outputs it to the servo valve 18 . The servo valve 18 controls the direction and amount of pressure oil for the hydraulic actuator 15 in accordance with the control signal output from the third amplifier 25 .

[0022] The input / output device 22 has an input section that inputs the amplitude σa, average value σm, frequency, etc. of the load waveform applied to the test piece SP to the control device 21B, and an output section that outputs the load-displacement characteristics, etc. of the test piece SP as test results.

[0023] FIG. 3 is a diagram showing an example of a change in the stress σ acting on the test piece SP. The vertical axis of FIG. 3 represents the stress σ acting on the test piece SP, and the horizontal axis represents the time T. The test execution section 212 of the control device 21B controls the servo valve 18 so that the stress σ changes along the graph G1 shown in FIG. The test execution unit 212 will be described later with reference to FIG.

[0024] As shown in graph G1, the change in stress σ is represented by a sine wave and is defined by an average value σm, an amplitude σa, and a period W. The average value σm indicates the average value of the stress σ. The amplitude σa indicates the amplitude of the stress σ. The amplitude σa is half the difference between the maximum value σx of the stress σ and the minimum value σn of the stress σ. The period W is defined by the frequency of the stress σ.

[0025] The fatigue test performed by the fatigue testing machine 1 is continuously performed until the number of repetitions reaches, for example, NTT. The number of repetitions NTT is, for example, 10 2 times ~10 8One repetition NTT corresponds to the change in stress σ over a period W. The number of repetitions NTT corresponds to an example of the "total number of times the fatigue test is performed." In other words, the fatigue testing machine 1 continuously executes the fatigue test for a time period equal to NTT times the number of repetitions of the cycle W shown in Fig. 3. However, if the test piece SP breaks, or if it is determined that the test piece SP is damaged due to a change in the amplitude σa, the fatigue testing machine 1 ends the fatigue test. The number of repetitions NTT will be described later with reference to FIG.

[0026] [3. Configuration of management device and control device] FIG. 4 is a diagram showing an example of the configuration of the management device 3 and the control device 21B.

[0027] [3-1. Control device configuration] The control device 21B causes the testing machine main body 10 to carry out a fatigue test. The control device 21B includes a computer having a storage device such as a hard disk drive (HDD) or a solid state drive (SSD), an interface circuit with the signal input / output device 21A, and various electronic circuits. The control device 21B is not limited to a computer, and may be configured by one or more appropriate circuits such as an integrated circuit, such as an IC chip or an LSI.

[0028] The control device 21B is configured, for example, by a personal computer, and controls the operation of the test machine main body 10. The control device 21B includes a first processor 21C and a first memory 21D. The first processor 21C is configured with a CPU (Central Processing Unit), an MPU (Micro-Processing Unit), and the like. The first memory 21D is composed of a ROM (Read Only Memory), a RAM (Random Access Memory), or the like.

[0029] The control device 21B is not limited to a personal computer, and may be configured by one or more appropriate circuits such as integrated circuits such as IC chips and LSIs. The control device 21B may also be configured by, for example, a tablet terminal, a smartphone, or the like. The control device 21B may also include programmed hardware such as a digital signal processor (DSP) or a field programmable gate array (FPGA). The control device 21B may also include a system-on-a-chip (SoC)-FPGA.

[0030] As shown in FIG. 4, the control device 21B includes a first communication unit 211, a test execution unit 212, and a first progress storage unit 213. Specifically, the first processor 21C of the control device 21B executes the first control program PR1 stored in the first memory 21D, thereby functioning as a first communication unit 211 and a test execution unit 212. In addition, the first processor 21C of the control device 21B executes the first control program PR1 stored in the first memory 21D, thereby causing the first memory 21D to function as a first progress storage unit 213.

[0031] The first progress storage unit 213 stores progress information JP that indicates the progress of the fatigue test performed by the fatigue testing machine 1. The test execution unit 212 records the progress information JP in the first progress storage unit 213. The progress information JP includes a start date and time TS, which is the date and time when the fatigue tester 1 starts the fatigue test, and scheduled end date and time information indicating a scheduled end date and time TE, which is the date and time when the fatigue tester 1 plans to end the fatigue test. The progress information JP also includes execution count information indicating the execution count NTA, which is the number of times the fatigue test has been repeated by the fatigue testing machine 1, and scheduled count information indicating the scheduled number NTR, which is the number of times the fatigue test is scheduled to be repeated by the fatigue testing machine 1. The sum of the execution count NTA and the scheduled number NTR corresponds to the number of repetitions NTT. The progress information JP also includes execution time information indicating execution time TA, which is the time it took for the fatigue testing machine 1 to execute the fatigue test, and scheduled time information indicating scheduled time TR, which is the time it is planned for the fatigue testing machine 1 to execute repeated fatigue tests. The sum of the execution time TA and the scheduled time TR corresponds to the fatigue testing time TT, which is the time required for the fatigue testing machine 1 to execute the fatigue test.

[0032] The progress information JP also includes execution count ratio information indicating the execution count ratio PNA, which is the ratio of the execution count NTA to the repetition count NTT, and scheduled count ratio information indicating the scheduled count ratio PNR, which is the ratio of the scheduled count NTR to the repetition count NTT. The sum of the execution count ratio PNA and the scheduled count ratio PNR is 100%. The progress information JP also includes execution time ratio information indicating an execution time ratio PA, which is the ratio of the execution time TA to the fatigue test time TT, and scheduled time ratio information indicating a scheduled time ratio PR, which is the ratio of the scheduled time TR to the fatigue test time TT. The sum of the execution time ratio PA and the scheduled time ratio PR is 100%. When the period W in the fatigue test is constant over the fatigue test time TT, the execution count ratio PNA coincides with the execution time ratio PA, and the scheduled number ratio PNR coincides with the scheduled time ratio PR.

[0033] In addition, when the fatigue testing machine 1 is executing a fatigue test and the fatigue test is terminated before the number of executions NTA reaches the number of repetitions NTT, the progress information JP includes termination date and time information indicating the termination date and time TF, which is the date and time when the fatigue test was terminated, and termination reason information indicating the termination reason RE, which is the reason for the termination. In addition, the progress information JP includes execution time ratio information indicating the execution time ratio PB at the time when the fatigue test is terminated before the number of executions NTA reaches the number of repetitions NTT while the fatigue testing machine 1 is executing the fatigue test. The execution time ratio PB is the ratio of the execution time TA to the fatigue test time TT when the fatigue test is completed, that is, at the end date and time TF.

[0034] The scheduled end date and time TE, the execution time ratio PA, the scheduled time TR, the execution time ratio PB, the end date and time TF, and the end reason RE will be described later with reference to FIG. The execution count NTA, scheduled count NTR, and repetition count NTT will be described later with reference to Fig. 6(A). The execution time TA, scheduled time TR, and fatigue test time TT will be described later with reference to Fig. 6(B). The execution time ratio PA and scheduled time ratio PR will be described later with reference to Fig. 6(C).

[0035] The first communication unit 211 controls communication with the signal input / output device 21A. Specifically, the first communication unit 211 receives, from the signal input / output device 21A, information indicating the test force detected by the load cell 17 and information indicating the displacement output from the differential transformer 19. In addition, the first communication unit 211 transmits, to the signal input / output device 21A, command information output from the test execution unit 212 to the servo valve 18.

[0036] Moreover, the first communication unit 211 controls the communication with the management device 3 . Specifically, the first communication unit 211 transmits the progress information JP to the management device 3 via the network NW.

[0037] The test execution unit 212 controls the testing machine body 10 so that the testing machine body 10 executes a fatigue test. Specifically, the test execution unit 212 generates command information for the servo valve 18 so that the stress σ acting on the test piece SP changes in a sinusoidal shape as shown in Fig. 3. In addition, the test execution unit 212 generates command information for the servo valve 18 based on information indicating the test force detected by the load cell 17 and information indicating the displacement output from the differential transformer 19. Furthermore, the test execution unit 212 periodically records the progress information JP in the first progress storage unit 213. The predetermined period is, for example, one minute.

[0038] [3-2. Management device configuration] The management device 3 manages the progress of fatigue tests performed by the multiple fatigue testers 1. The management device 3 is configured by, for example, a personal computer. The management device 3 includes a second processor 31, a second memory 32, and a display unit 33. The second processor 31 is composed of a CPU, an MPU, and the like. The second memory 32 is composed of a ROM, a RAM, and the like.

[0039] The management device 3 is not limited to a personal computer, and may be configured by one or more appropriate circuits such as integrated circuits such as IC chips and LSIs. The management device 3 may also be configured by, for example, a tablet terminal, a smartphone, or the like.

[0040] The display unit 33 includes an LCD (Liquid Crystal Display) 331, and displays various images on the LCD 331 in accordance with instructions from the second processor 31. The display unit 33 displays, for example, a progress management screen 400 shown in FIG. The LCD 331 corresponds to an example of a "display."

[0041] As shown in FIG. 4, the management device 3 includes a second communication unit 311, an acquisition unit 312, a display control unit 313, and a second progress storage unit 321. Specifically, the second processor 31 of the management device 3 executes the second control program PR2 stored in the second memory 32, thereby functioning as a second communication unit 311, an acquisition unit 312, and a display control unit 313. In addition, the second processor 31 of the management device 3 executes the second control program PR2 stored in the second memory 32, thereby causing the second memory 32 to function as a second progress storage unit 321.

[0042] The second progress storage unit 321 stores progress information JP indicating the progress of the fatigue test performed by each of the multiple fatigue testing machines 1 in association with identification information that identifies each of the multiple fatigue testing machines 1. The acquisition unit 312 records the progress information JP of each of the multiple fatigue testing machines 1 in the second progress storage unit 321. The progress information JP of each of the multiple fatigue testing machines 1 is read out from the second progress storage unit 321 by the display control unit 313.

[0043] The second communication unit 311 controls the communication with the control device 21B. Specifically, the second communication unit 311 receives the progress information JP from each of the control devices 21B of the multiple fatigue testing machines 1 via the network NW in accordance with an instruction from the acquisition unit 312.

[0044] The acquisition unit 312 acquires the progress information JP from each of the control devices 21B of the multiple fatigue testing machines 1. Specifically, the acquiring unit 312 acquires the progress information JP from each of the first fatigue testing machine 1A to the Nth fatigue testing machine at a preset predetermined period. The predetermined period is, for example, every 10 minutes. The longer the predetermined period, the more the load on the second processor 31 can be reduced. The shorter the predetermined period, the more frequently the progress management screen 400 shown in FIG.

[0045] The display control unit 313 displays the progress information JP corresponding to each of the first fatigue test machine 1A to the Nth fatigue test machine on the LCD 331. Moreover, the display control unit 313 updates the progress information JP displayed on the LCD 331 every time the acquisition unit 312 acquires the progress information JP from each of the first fatigue test machine 1A to the Nth fatigue test machine. Specifically, the display control unit 313 displays the progress management screen 400 shown in FIG. 5 on the LCD 331. That is, the display control unit 313 displays the progress information JP of each of the first fatigue test machine 1A to the seventh fatigue test machine 1G as progress bars 410 to 470. The display control unit 313 also displays the progress information JP in association with date information indicating the date. In this embodiment, the date information indicating the date is displayed in a calendar format in the calendar display unit CL. The display control unit 313 also displays the progress information JP in association with identification information for identifying each of the first fatigue test machine 1A to the seventh fatigue test machine 1G. In this embodiment, the identification information is displayed as a test machine number NP. The progress bars 410 to 470, the calendar display section CL, and the testing machine number NP will be described later with reference to FIG.

[0046] [4. Progress Management Screen Configuration] 5 is a screen diagram showing an example of the progress management screen 400. The progress management screen 400 is displayed on the LCD 331 by the display control unit 313. As shown in FIG. 5, the progress management screen 400 displays a testing machine number NP, a calendar display section CL, progress bars 410 to 470, and a current date and time display section TN.

[0047] The testing machine number NP is displayed in the leftmost column of the progress management screen 400, and corresponds to an example of identification information for identifying each of the first fatigue testing machine 1A to the Nth fatigue testing machine. In this embodiment, a testing machine number NP of "1" indicates a first fatigue testing machine 1A. A testing machine number NP of "2" indicates a second fatigue testing machine 1B. A testing machine number NP of "N" indicates an Nth fatigue testing machine. The integer N is, for example, 1 to 7. The progress management screen 400 displays progress information JP for each of the first fatigue testing machine 1A to the seventh fatigue testing machine 1G.

[0048] The calendar display section CL is displayed at the top of the progress management screen 400, and displays calendar information including the year, month, and date. In this embodiment, the "year and month" are displayed at the top of the calendar display section CL, and the "day" is displayed at the bottom of the calendar display section CL. The numbers indicating each day are displayed so that the days of the week can be distinguished. For example, the numbers indicating days corresponding to Saturdays are displayed in blue, the numbers indicating days corresponding to Sundays and holidays are displayed in red, and the numbers indicating days corresponding to weekdays are displayed in black.

[0049] A progress bar 410 indicates the progress of the fatigue test in the first fatigue test machine 1 A. A progress bar 420 indicates the progress of the fatigue test in the second fatigue test machine 1 B. A progress bar 4N0 indicates the progress of the fatigue test in the Nth fatigue test machine. The progress bars 410 to 470 are displayed in the shape of a rectangle extending in the left-right direction. The left end of each of the progress bars 410 to 470 is displayed in a position corresponding to the start date and time TS in the calendar display section CL. The right end of each of the progress bars 410 to 470 is displayed in a position corresponding to the planned end date and time TE in the calendar display section CL. The start date and time TS indicates the date and time when the fatigue testing machine 1 starts the fatigue test. The planned end date and time TE indicates the date and time when the fatigue testing machine 1 is scheduled to end the fatigue test. In addition, since the fatigue tests have been completed in each of the sixth fatigue testing machine 1F and the seventh fatigue testing machine 1G, the progress bars 460 and 470 are displayed in a manner different from the progress bars 410 to 450 corresponding to the first fatigue testing machine 1A to the fifth fatigue testing machine 1E. For example, the contour lines of the progress bars 410 to 450 are displayed in solid lines, and the contour lines of the progress bars 460 and 470 are displayed in dashed lines.

[0050] In the following description, the date and time when the progress information JP displayed on the progress management screen 400 is recorded in the first progress storage unit 213 by the test execution unit 212 of the control device 21B is referred to as the "current date and time" for convenience. The current date and time display section TN indicates the date and time when the test execution section 212 of the control device 21B recorded the progress information JP displayed on the progress management screen 400 in the first progress storage section 213. In Figure 5, the current date and time display unit TN indicates that the progress information JP displayed on the progress management screen 400 was recorded in the first progress memory unit 213 by the test execution unit 212 of the control device 21B at "15:12, May 18, 2020." To make it possible to visually confirm that the progress information JP displayed on the progress management screen 400 is the date and time recorded in the first progress storage unit 213, i.e., the current date and time is "May 18, 2020", the display control unit 313 displays the corresponding day in the calendar display unit CL in an identifiable manner. For example, the column showing the corresponding day in the calendar display unit CL is displayed in inverted black and white. Moreover, the current date and time being "15:12" is displayed on the current date and time display section TN. Furthermore, the current date and time display section TN includes a current date and time display line TNL that indicates the current date and time. The current date and time display line TNL is a straight line that extends in the vertical direction passing through the progress bars 410 to 470. The horizontal position of the current date and time display line TNL corresponds to the current date and time in the calendar display section CL.

[0051] Each of the progress bars 410 to 450 is displayed so that the left side of the current date and time display line TNL and the right side of the current date and time display line TNL can be distinguished. In Fig. 5, each of the progress bars 410 to 450 is displayed so that the left side of the current date and time display line TNL is shaded and the right side of the current date and time display line TNL is displayed in white. In each of the progress bars 410 to 450, the left side of the current date and time display line TNL corresponds to the elapsed period from the start date and time TS of the fatigue test to the current date and time. In each of the progress bars 410 to 450, the right side of the current date and time display line TNL corresponds to the period from the current date and time to the scheduled end date and time TE of the fatigue test.

[0052] Each of the progress bars 410 to 450 displays an execution time ratio PA, a scheduled time TR, and a scheduled end date and time TE. The execution time ratio PA is displayed to the left of the current date and time display line TNL, and indicates the ratio of the execution time TA to the fatigue test time TT. The execution time TA indicates the time that the fatigue test has been performed up to the current date and time. In other words, the execution time TA indicates the time from the start date and time TS to the current date and time. The fatigue test time TT indicates the planned time required to perform the fatigue test. For example, the progress bar 410 displays "49%" as the execution time ratio PA, indicating that 49% of the fatigue test time TT has been completed at the current date and time. Also, for example, the progress bar 420 displays "35%" as the execution time ratio PA, indicating that 35% of the fatigue test time TT has been completed at the current date and time.

[0053] The scheduled time TR and the scheduled end date and time TE are displayed to the right of the current date and time display line TNL. The scheduled end date and time TE is displayed at the right end of each of the progress bars 410 to 450. The scheduled time TR is displayed between the current date and time display line TNL and the scheduled end date and time TE. The scheduled time TR indicates the time from the current date and time for which the fatigue test is to be repeated, in other words, the scheduled time TR indicates the time required from the current date and time to reach the scheduled end date and time TE. For example, the progress bar 410 displays "17 days, 21 hours and 3 minutes" as the scheduled time TR, indicating that the fatigue test is scheduled to end "17 days, 21 hours and 3 minutes" from the current date and time. Also, for example, the progress bar 420 displays "26 days, 21 hours and 3 minutes" as the scheduled time TR, indicating that the fatigue test is scheduled to end "26 days, 21 hours and 3 minutes" from the current date and time. In other words, the fatigue test in the second fatigue test machine 1B is scheduled to end about one week (7 days) after the fatigue test in the first fatigue test machine 1A ends.

[0054] The scheduled end date and time TE indicates the date and time when the fatigue test is scheduled to end. For example, the progress bar 410 displays "June 5th (Friday) 12:05" as the scheduled end date and time TE, indicating that the fatigue test is scheduled to end at "June 5th (Friday) 12:05." Also, for example, the progress bar 420 displays "June 12th (Friday) 12:15" as the scheduled end date and time TE, indicating that the fatigue test is scheduled to end at "June 12th (Friday) 12:15."

[0055] In each of the progress bars 460 and 470, a predetermined area to the left of the current date and time display line TNL is displayed in a shaded manner, and the other areas are displayed in a blank manner. The predetermined area corresponds to the period from the start date and time of the fatigue test to the end date and time of the fatigue test. Each of the progress bars 460 and 470 displays an execution time ratio PB, a finish date and time TF, a finish reason RE, and a scheduled finish date and time TE.

[0056] In each of the progress bars 460 and 470, the execution time ratio PB is displayed in a specified area to the left of the current date and time display line TNL, and indicates the ratio of the execution time TB to the fatigue test time TT. The execution time TB indicates the time from the start date and time TS to the end date and time TF. The start date and time TS indicates the date and time when the fatigue test started. The end date and time TF indicates the date and time when the fatigue test ended. The fatigue test time TT indicates the time scheduled to be required to perform the fatigue test. For example, the progress bar 460 displays "32%" as the execution time ratio PB, which indicates that the fatigue test has been completed in 32% of the fatigue test time TT.

[0057] The end date and time TF, the reason for ending RE, and the scheduled end date and time TE are displayed to the right of a predetermined shaded area of ​​each of the progress bars 460 and 470. The scheduled end date and time TE is displayed at the right end of each of the progress bars 460 and 470. The end date and time TF is located near the right end of a predetermined shaded area of ​​each of the progress bars 460 and 470. The reason for ending RE is displayed between the end date and time TF and the scheduled end date and time TE.

[0058] The end date and time TF indicates the date and time when the fatigue test was completed. For example, in the progress bar 460, the end date and time TF is displayed as "16th, 4:08", indicating that the fatigue test ended at "16th, 4:08". The termination reason RE indicates the reason why the fatigue test was terminated. For example, in the progress bar 460, the reason for termination RE is displayed as "alarm", indicating that the sixth fatigue testing machine 1F issued some kind of warning and terminated the test. In other words, this indicates that some kind of abnormality occurred in the sixth fatigue testing machine 1F and the fatigue test was terminated. The abnormality may include, for example, overheating of a member constituting the fatigue testing machine 1. Also, for example, in the progress bar 470, the reason for termination RE is displayed as "break", which indicates that the fatigue test was terminated by the breakage of the test piece SP. In other words, the seventh fatigue testing machine 1G indicates that the fatigue test was normally terminated.

[0059] The display control unit 313 displays a progress bar 460 in a manner that distinguishes between a case where the fatigue test has ended due to the occurrence of an abnormality and a case where the fatigue test has ended normally, as in the case of the progress bar 470. For example, the display control unit 313 changes the display color of the progress bar between a case where the fatigue test has ended due to the occurrence of an abnormality and a case where the fatigue test has ended normally. Specifically, for example, the display control unit 313 displays the progress bar in red when the fatigue test has ended due to the occurrence of an abnormality and displays the progress bar in green when the fatigue test has ended normally. Furthermore, the display control unit 313 displays the progress bars 410 to 450 corresponding to the fatigue testing machine 1 currently performing a fatigue test in a color different from the progress bars 460 and 470. The display control unit 313 displays the progress bars 410 to 450 in, for example, blue.

[0060] 5, the progress management screen 400 displays the progress bars 410 to 470 in association with the testing machine numbers NP, so that the user can easily recognize the progress of the fatigue tests in each of the first fatigue testing machine 1A to the seventh fatigue testing machine 1G. In this embodiment, the user includes the operator.

[0061] In addition, the scheduled end date and time TE is displayed on each of the progress bars 410 to 450 corresponding to the fatigue testing machine 1 currently performing a fatigue test, so that the user can easily check the date and time when the fatigue test is scheduled to end on the fatigue testing machine 1 currently performing the fatigue test.

[0062] Furthermore, since the reason for termination RE is displayed on each of the progress bars 460 and 470 corresponding to the fatigue testing machine 1 for which the fatigue testing has been completed, the user can easily confirm the reason why the fatigue testing machine 1 has terminated the fatigue testing.

[0063] In this embodiment, the progress management screen 400 has been described as including the progress bars 410 to 470 including the current date and time, but the embodiment of the present invention is not limited to this. A progress bar indicating that the fatigue test has been completed, in other words, a progress bar indicating a fatigue test performed in the past, may be displayed. In this case, it is preferable to display the operation rate of each of the fatigue testing machines 1. By displaying the operation rate of each of the fatigue testing machines 1, the user can appropriately plan future fatigue tests.

[0064] Each of Figs. 6(A) to 6(C) is a diagram showing another embodiment of the progress bar. In the progress bar of FIG. 6(A), the display control unit 313 displays the number of executions NTA, the planned number of times NTR, and the number of repetitions NTT. The execution count NTA is the number of repetitions of the fatigue test that have been performed up to the current date and time, and the planned number NTR is the number of repetitions of the fatigue test that are scheduled to be performed after the current date and time. The repetition count NTT is the total number of repetitions that are scheduled to be performed in the fatigue test, and is equal to the sum of the execution count NTA and the planned number NTR.

[0065] In this case, the user can easily check the number of executions NTA, the planned number of times NTR, and the number of repetitions NTT for each fatigue testing machine 1, thereby improving user convenience.

[0066] 6A shows the execution count NTA, the scheduled count NTR, and the repetition count NTT, but the execution count ratio PNA and the scheduled count ratio PNR may be shown on the progress bar. The execution count ratio PNA indicates the ratio of the execution count NTA to the repetition count NTT, and the scheduled count ratio PNR indicates the ratio of the scheduled count NTR to the repetition count NTT.

[0067] In the progress bar of FIG. 6(B), the display control unit 313 displays the execution time TA, the scheduled time TR, and the fatigue test time TT. The execution time TA is the time that the fatigue test has been performed up to the current date and time, and the scheduled time TR is the time that the fatigue test is scheduled to be repeated after the current date and time. The fatigue test time TT is the total time required to perform the fatigue test, and is equal to the sum of the execution time TA and the scheduled time TR.

[0068] In this case, the user can easily check the execution time TA, the scheduled time TR, and the fatigue test time TT for each fatigue testing machine 1, thereby improving user convenience.

[0069] In the progress bar of FIG. 6(C), the display control unit 313 displays the execution time ratio PA and the planned time ratio PR. The execution time ratio PA is the ratio of the execution time TA to the fatigue test time TT, and the planned time ratio PR is the ratio of the planned time TR to the fatigue test time TT. The sum of the execution time ratio PA and the planned time ratio PR is 100%.

[0070] In this case, the user can easily check the execution time ratio PA and the planned time ratio PR for each of the fatigue testing machines 1, thereby improving user convenience.

[0071] [5. Operation of management device] FIG. 7 is a flowchart showing an example of the process of the management device 3 according to the present embodiment. First, in step S101, the acquisition unit 312 determines whether or not a predetermined period has elapsed. The predetermined period is a period in which the display control unit 313 updates the progress management screen 400 displayed on the LCD 331, and is, for example, 10 minutes. If the acquisition unit 312 determines that the predetermined period has not elapsed (step S101; NO), the process goes to a standby state. If the acquisition unit 312 determines that the predetermined period has elapsed (step S101; YES), the process proceeds to step S103. Then, in step S103, the acquiring unit 312 acquires information indicating the start date and time TS from each of the control devices 21B of the multiple fatigue testing machines 1. Next, in step S105, the acquiring unit 312 acquires information indicating the scheduled end date and time TE from each of the control devices 21B of the multiple fatigue testing machines 1. Next, in step S107, the acquisition unit 312 acquires information indicating the execution time ratio PA from each of the control devices 21B of the multiple fatigue testing machines 1.

[0072] Next, in step S109, the acquisition unit 312 determines whether or not the fatigue test has been completed in each of the multiple fatigue testing machines 1. The acquisition unit 312 determines whether or not the fatigue test in the fatigue testing machine 1 has been completed based on, for example, whether or not the test execution unit 212 of the control device 21B of the fatigue testing machine 1 is executing control of the fatigue test. If the acquisition unit 312 determines that the fatigue test in the fatigue testing machine 1 has not been completed (step S109; NO), the process proceeds to step S115. If the acquisition unit 312 determines that the fatigue test in the fatigue testing machine 1 has been completed (step S109; YES), the process proceeds to step S111. Then, in step S111, the acquiring unit 312 acquires information indicating the end date and time TF from the control device 21B of the fatigue testing machine 1. Next, in step S113, the acquisition unit 312 acquires information indicating the reason for termination RE from the control device 21B of the fatigue testing machine 1.

[0073] Next, in step S115, the acquisition unit 312 determines whether or not progress information JP has been acquired from the control devices 21B of all of the fatigue testing machines 1. In this embodiment, all of the fatigue testing machines 1 are the first fatigue testing machine 1A to the seventh fatigue testing machine 1G. If the acquiring unit 312 determines that the progress information JP has not been acquired from the control devices 21B of all the fatigue testing machines 1 (step S115; NO), the process returns to step S103. If the acquiring unit 312 determines that the progress information JP has been acquired from the control devices 21B of all the fatigue testing machines 1 (step S115; YES), the process proceeds to step S117. Then, in step S117, the display control unit 313 displays the progress information JP corresponding to each of the first fatigue testing machine 1A to the seventh fatigue testing machine 1G on the LCD 331. In other words, the display control unit 313 updates, for example, the progress management screen 400 displayed on the LCD 331. Then, the process returns to step S101.

[0074] In this way, the display control unit 313 displays the progress information JP corresponding to each of the first fatigue test machine 1A to the seventh fatigue test machine 1G on the LCD 331, so that the operator can easily check the progress information JP corresponding to each of the first fatigue test machine 1A to the seventh fatigue test machine 1G. This reduces the operator's work.

[0075] [6. Aspects and Effects] It will be understood by those skilled in the art that the above-described embodiment is a specific example of the following aspects.

[0076] (Section 1) The fatigue testing machine management device of the first embodiment is a fatigue testing machine management device that is communicatively connected to a plurality of fatigue testing machines, and includes an acquisition unit that acquires progress information indicating the progress status of the fatigue test in each of the plurality of fatigue testing machines from each of the plurality of fatigue testing machines, and a display control unit that displays the progress information of the fatigue test corresponding to each of the plurality of fatigue testing machines.

[0077] According to the management device for fatigue testing machines described in item 1, the display control unit displays on the display the progress information indicating the progress of the fatigue test corresponding to each of the plurality of fatigue testing machines. Therefore, the operator can easily check the progress of the fatigue tests corresponding to each of the plurality of fatigue testing machines, thereby reducing the burden on the operator.

[0078] (Section 2) In the management device for a fatigue testing machine described in item 1, the progress information includes scheduled end date and time information indicating a date and time when the fatigue test is scheduled to end.

[0079] According to the management device for a fatigue testing machine described in item 2, the progress information includes scheduled end date and time information indicating the date and time when the fatigue test is scheduled to end. Therefore, the operator can easily check the date and time when the fatigue test is scheduled to end for each of the multiple fatigue testing machines, thereby improving the convenience for the operator.

[0080] (Section 3) In the management device for a fatigue testing machine described in paragraph 1 or paragraph 2, the progress information includes at least one of execution count information indicating the number of times the fatigue test has been repeated, execution time information indicating the time the fatigue test was performed, planned count information indicating the planned number of times the fatigue test is to be repeated, and planned time information indicating the planned time for performing the fatigue test.

[0081] According to the fatigue testing machine management device described in paragraph 3, the progress information includes at least one of execution count information indicating the number of times the fatigue test has been repeated, execution time information indicating the time the fatigue test was performed, planned count information indicating the planned number of times the fatigue test is repeated, and planned time information indicating the planned time for performing the fatigue test. Therefore, the operator can easily check at least one of the number of times the fatigue test has been repeated, the time for which the fatigue test has been performed, the number of times the fatigue test is scheduled to be repeated, and the time for which the fatigue test is scheduled to be repeated, for each of the multiple fatigue testing machines, thereby improving the convenience for the operator.

[0082] (Section 4) In the management device for a fatigue testing machine described in any one of paragraphs 1 to 3, the progress information includes at least one of: execution count ratio information indicating the ratio of the number of times the fatigue test has been repeated to the total number of times the fatigue test has been performed; execution time ratio information indicating the ratio of the time the fatigue test has been performed to the total execution time of the fatigue test; planned number ratio information indicating the ratio of the number of times the fatigue test is planned to be performed to the total number of times the fatigue test is performed; and planned time ratio information indicating the ratio of the time planned to be used to perform the fatigue test repetition to the total execution time of the fatigue test.

[0083] According to the fatigue testing machine management device described in paragraph 4, the progress information includes at least one of the following: execution count ratio information indicating the ratio of the number of times the fatigue test was performed to the total number of times the fatigue test was performed; execution time ratio information indicating the ratio of the time the fatigue test was performed to the total execution time of the fatigue test; planned number ratio information indicating the ratio of the number of times the fatigue test is planned to be performed to the total number of times the fatigue test is performed; and planned time ratio information indicating the ratio of the time planned to be used to perform the fatigue test. Therefore, the operator can easily check at least one of the ratio of the number of executions to the number of repetitions, the ratio of the planned number of repetitions to the number of repetitions, the ratio of the execution time to the fatigue test time, and the ratio of the planned time to the fatigue test time for each of the multiple fatigue testers, thereby improving the convenience for the operator.

[0084] (Section 5) In the management device for a fatigue testing machine according to any one of claims 1 to 4, the display control unit displays the progress information as a progress bar.

[0085] According to the material testing machine described in paragraph 5, the display control unit displays, as a progress bar, progress information indicating the progress of the fatigue test for each of the plurality of fatigue testing machines. Therefore, the operator can easily check the progress of the fatigue test for each of the multiple fatigue test machines, thereby reducing the operator's workload.

[0086] (Section 6) In the management device for a fatigue testing machine according to any one of claims 1 to 5, the display control unit displays the progress information in association with date information indicating a date.

[0087] According to the management device for fatigue testing machines described in item 6, the display control unit displays the progress information for each of the plurality of fatigue testing machines in association with date information indicating the date. Therefore, the operator can easily check the progress of the fatigue test for each of the multiple fatigue test machines, thereby reducing the operator's workload.

[0088] (Section 7) In the management device for fatigue testing machines according to any one of claims 1 to 6, the display control unit displays the progress information in association with identification information for identifying each of the plurality of fatigue testing machines.

[0089] According to the management device for fatigue testing machines described in item 7, the display control unit displays the progress information in association with identification information for identifying each of the plurality of fatigue testing machines. Therefore, the operator can easily check the progress of the fatigue test for each of the multiple fatigue test machines, thereby reducing the operator's workload.

[0090] (Section 8) The fatigue testing machine management system relating to the second embodiment is a fatigue testing machine management system comprising a plurality of fatigue testing machines and a management device communicatively connected to the plurality of fatigue testing machines, the management device comprising an acquisition unit that acquires progress information indicating the progress of fatigue testing in each of the plurality of fatigue testing machines from each of the plurality of fatigue testing machines, and a display control unit that displays the progress information corresponding to each of the plurality of fatigue testing machines.

[0091] According to the fatigue testing machine management system described in paragraph 8, the same effects as those of the fatigue testing machine management device described in paragraph 1 are achieved.

[0092] [7. Other embodiments] The fatigue testing machine 1 according to this embodiment is merely an example of an embodiment of a material testing machine according to the present invention, and can be modified and applied as desired without departing from the spirit and scope of the present invention. For example, in the present embodiment, a case will be described in which the network NW that communicatively connects the management device 3 and the multiple fatigue testing machines 1 is a LAN, but the network NW may be a WAN or the Internet. When the network NW is the Internet, the management device 3 is configured as a server device.

[0093] 1, 2, and 4 show functional configurations, and the specific implementation form is not particularly limited. In other words, it is not necessary to implement hardware that corresponds to each functional unit individually, and it is of course possible to implement a configuration in which one processor executes a program to realize the functions of multiple functional units. Also, some of the functions realized by software in the above embodiments may be realized by hardware, or some of the functions realized by hardware may be realized by software.

[0094] In addition, the processing units in the flowchart shown in Fig. 7 are divided according to the main processing contents in order to facilitate understanding of the processing of the management device 3. There is no limitation to the manner of division or names of the processing units shown in the flowchart of Fig. 7, and the processing units can be further divided into more processing units according to the processing contents, or one processing unit can be divided to include more processes. In addition, the processing order of the above flowchart is not limited to the example shown in the figure.

[0095] The management device 3 of the fatigue testing machine 1 causes the second processor 31 to execute the second control program PR2. The second control program PR2 can also be recorded in a computer-readable recording medium. The recording medium can be a magnetic or optical recording medium or a semiconductor memory device. Specifically, a portable or fixed recording medium such as a flexible disk, HDD, CD-ROM (Compact Disk Read Only Memory), DVD, Blu-ray (registered trademark) Disc, magneto-optical disk, flash memory, or card-type recording medium can be used. The recording medium can also be a non-volatile storage device such as a RAM, ROM, or HDD, which is an internal storage device provided in the management device 3. The second control program PR2 can also be stored in a server device or the like, and the second control program PR2 can be downloaded from the server device to the management device 3. [Explanation of symbols]

[0096] 100 Management System (Fatigue Testing Machine Management System) 1. Fatigue testing machine 1A~1G 1st fatigue testing machine~7th fatigue testing machine 10 Testing machine body 11 Foundation 12a Post 12b Post 13 York 14 Crosshead 15 Hydraulic Actuator 15a Piston rod 16a Lower jig 16b Upper jig 17 Load Cell 18 Servo valve 19 Differential transformer 20 Control Unit 21A signal input / output device 21B Control device 21C 1st processor 21D 1st Memory 211 First Communications Department 212 Test Execution Department 213 First Progress Memory Unit 3 Management device 31 Second Processor 311 2nd Communications Department 312 Acquisition Department 313 Display control unit 32 Second Memory 321 Second Progress Memory Unit 33 Display section 331 LCD 400 Progress Management Screen 410~470 Progress bar CL Calendar display JP Progress Report NP Tester Number NTA execution count NTR Scheduled Number of Times NTT repeat count PA execution time ratio PB execution time ratio PNA execution ratio PNR Scheduled Frequency Ratio PR Scheduled Time Ratio PR1 First control program PR2 2nd control program RE Termination Reason TA, TB execution time TE Scheduled End Date TF End Date TN Current date and time display section TNL Current date and time display line TR Scheduled Time TS start date and time TT Fatigue test time

Claims

1. A fatigue testing machine management device communicatively connected to a plurality of fatigue testing machines, an acquisition unit that acquires progress information indicating a progress status of a fatigue test in each of the plurality of fatigue testing machines from each of the plurality of fatigue testing machines; a display control unit that displays the progress information corresponding to each of the plurality of fatigue testing machines; Equipped with the progress information includes scheduled end date and time information indicating a date and time when the fatigue test is scheduled to be completed, when the fatigue test in each of the plurality of fatigue testing machines is completed, the acquisition unit acquires, from the fatigue testing machine in which the fatigue test has been completed, a termination reason indicating a reason why the fatigue test has been completed; the display control unit distinguishably displays a case where the fatigue test has been terminated due to an abnormality and a case where the fatigue test has been terminated normally based on the reason for termination. Fatigue testing machine control device.

2. the progress information includes at least one of execution count information indicating the number of times the fatigue test has been repeated, execution time information indicating the time during which the fatigue test has been performed, scheduled count information indicating the number of times the fatigue test is scheduled to be repeated, and scheduled time information indicating the time during which the fatigue test is scheduled to be repeated.

2. A management device for a fatigue testing machine according to claim 1.

3. The progress information includes at least one of: execution count ratio information indicating the ratio of the number of times the fatigue test has been repeated to the total number of times the fatigue test has been performed; execution time ratio information indicating the ratio of the time the fatigue test has been performed to the total execution time of the fatigue test; planned count ratio information indicating the ratio of the number of times the fatigue test is scheduled to be performed to the total number of times the fatigue test is performed; and planned time ratio information indicating the ratio of the time the fatigue test is scheduled to be performed to the total execution time of the fatigue test.

3. A management device for a fatigue testing machine according to claim 1 or 2.

4. the display control unit displays the progress information as a progress bar. The management device for a fatigue testing machine according to any one of claims 1 to 3.

5. the display control unit displays the progress information in association with date information indicating a date. The management device for a fatigue testing machine according to any one of claims 1 to 4.

6. the display control unit displays the progress information in association with identification information for identifying each of the plurality of fatigue testing machines. The management device for a fatigue testing machine according to any one of claims 1 to 5.

7. A fatigue testing machine management system including a plurality of fatigue testing machines and a management device communicably connected to the plurality of fatigue testing machines, The management device includes: an acquisition unit that acquires progress information indicating a progress status of a fatigue test in each of the plurality of fatigue testing machines from each of the plurality of fatigue testing machines; a display control unit that displays the progress information corresponding to each of the plurality of fatigue testing machines; Equipped with the progress information includes scheduled end date and time information indicating a date and time when the fatigue test is scheduled to be completed, when the fatigue test in each of the plurality of fatigue testing machines is completed, the acquisition unit acquires, from the fatigue testing machine in which the fatigue test has been completed, a termination reason indicating a reason why the fatigue test has been completed; the display control unit distinguishably displays a case where the fatigue test has been terminated due to an abnormality and a case where the fatigue test has been terminated normally based on the reason for termination. Fatigue testing machine management system.

Citation Information

Patent Citations

  • Measuring control apparatus for material testing machine

    JP2001194281A

  • Material testing machine

    JP2006292400A

  • Material testing system

    JP2007121065A

  • Agriculture management support system

    JP2014199517A

  • Material tester and material testing system

    JP2018054399A