Power management system and charge / discharge plan creation method
By calculating multiple predicted values with error margins based on past data, the system optimizes storage battery charging and discharging to ensure cost-effectiveness and constraint adherence despite forecast uncertainties.
Patent Information
- Application Number
- JP2022179369
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-11-09
- Publication Date
- 2024-10-03
- Estimated Expiration
- 2042-11-09
AI Technical Summary
Existing power management systems for storage batteries fail to create optimal charging and discharging plans that can reliably satisfy constraints when faced with uncertain power generation and demand forecasts, leading to potential deviations from planned operations.
The system calculates multiple predicted power generation and demand values, incorporating prediction errors based on past actual values, to create an optimization model that minimizes electricity procurement fees while ensuring constraint satisfaction.
This approach ensures a high probability of constraint satisfaction even with incorrect forecasts, reducing electricity costs and maintaining battery health by optimizing charging and discharging plans under appropriate constraints.
Smart Images

Figure 0007561171000006 
Figure 0007561171000007 
Figure 0007561171000008
Abstract
Description
[Technical field]
[0001] The present invention relates to a power management system and a method for creating a charge and discharge plan, and is particularly suitable for use in a system that creates a charge and discharge plan for a storage battery that is optimized to reduce power procurement fees. [Background technology]
[0002] In recent years, energy management systems that utilize power generation and storage have been developed and widely provided from the perspective of expanding the introduction of renewable energy and adjusting the balance of power supply and demand toward a decarbonized society. For example, a system is known that aims to reduce electricity procurement fees by charging surplus electricity from solar power generation into a storage battery and using it at other times, such as at night. Attention is also being paid to the use of storage batteries installed in electric vehicles (EVs), which are likely to become more widespread in the future.
[0003] In this regard, there is a conventional system known that performs power management based on the predicted power generation by a power generation device, the predicted power consumption due to the power load, the usage plan or predicted usage state of an EV equipped with a storage battery, and electricity rates by time period to minimize electricity charges without compromising the convenience of the EV as a form of mobility (see, for example, Patent Documents 1 and 2). In the following description, an EV is referred to as a vehicle, and a storage battery installed in the vehicle is referred to as an on-board storage battery.
[0004] The power management system described in Patent Document 1 includes a natural energy power generation device, a power load, a power management device, and a vehicle equipped with a storage battery (on-board storage battery), and the power management device calculates the amount of power stored in the on-board storage battery for each hour based on an off-site use schedule including a scheduled time to start off-site use of the on-board storage battery, a scheduled time to end said use, and a predicted amount of power required for said use, a predicted power consumption of the power load, and a predicted power generation of the natural energy power generation device.The power management device then plans charging of the on-board storage battery using externally supplied power during a time period when electricity rates are relatively cheap so that the maximum value of the obtained amount of power stored for each hour is a predetermined maximum amount of power stored, and plans charging and discharging of the on-board storage battery so that the amount of power stored in the on-board storage battery at the scheduled end time of off-site use is equal to or greater than a predetermined minimum amount of power stored.
[0005] In the power supply system described in Patent Document 2, a charge / discharge schedule showing the progress of charge and discharge of the power storage means including the on-board battery during the prediction period is calculated based on consumption prediction data, power generation prediction data, and data for the period during which the on-board battery is electrically connected to the wiring, which is calculated based on the vehicle usage history, and the charge / discharge power of the power storage means during the prediction period is controlled according to the calculated charge / discharge schedule. The charge / discharge schedule is calculated by formulating it into a mixed integer programming problem so that an evaluation index (power purchase fee according to the amount of power supplied from the AC power line) used to determine the charge / discharge power of the power storage means becomes a predetermined value.
[0006] Also known are systems that aim to optimize a charge / discharge plan for a storage battery from the standpoint of both reducing electricity charges and reducing deterioration of the storage battery (see, for example, Patent Documents 3 to 5). The charge / discharge control device described in Patent Document 3 generates constraint conditions for calculating a charge / discharge plan based on a demand forecast for power supplied from a power system in which electricity charges are generated according to use and a storage battery that is charged with power from the power system, and generates an objective function that minimizes the electricity charges and deterioration of the storage battery to solve an optimization problem, thereby generating a charge / discharge plan for the storage battery that increases the amount of savings in electricity charges and keeps the deterioration of the storage battery low.
[0007] In the charge / discharge plan setting described in Patent Document 4, an optimization problem is solved to reduce the electricity bill and suppress the deterioration of the storage battery based on a power demand forecast, etc., to create an optimal charge / discharge plan for the electricity bill and the deterioration level. Patent Document 4 describes that the constraints are that the storage battery does not flow reverse power to the grid, that the storage battery does not exceed its storage capacity limit, and that the storage battery does not exceed its hourly charge / discharge limit, and an optimization problem is solved to find a charge / discharge plan for each predetermined time period, with a function for finding an optimal solution that minimizes the sum of the electricity bill and the deterioration level of the storage battery as the objective function.
[0008] Patent Document 5 discloses an electric power load leveling device that can optimize the peak of electric power consumption and the timing of charging and discharging a storage battery, and can perform load leveling including power peak cutting more efficiently using a storage battery. In the electric power load leveling device described in Patent Document 5, when the predicted required discharge amount (power amount required for peak cutting) is lower than a predetermined value (for example, about 80% SOC), the lithium ion battery is charged using nighttime power. Also, when the predicted required discharge amount is higher than a predetermined value, the lithium ion battery is charged so that charging is completed just before the predicted power peak. This makes it possible to both suppress deterioration of the lithium ion battery to improve its lifespan and charge the lithium ion battery using a nighttime rate at which electricity rates are relatively low.
[0009] In the systems described in Patent Documents 1 to 5, optimization calculations are performed based on prediction results of power generation, power demand, and the usage state of the on-board storage battery, and a charge / discharge plan for the storage battery that satisfies given constraints is created. In other words, the charge / discharge plan is created by applying the prediction results to the constraint equations assuming that the prediction results are correct. However, the actual power generation state, demand state, and usage state of the on-board storage battery do not always turn out as predicted. Therefore, when charge / discharge control of the storage battery is performed according to a charge / discharge plan created based on uncertain prediction results, there is a problem that the charge / discharge control may not actually satisfy the constraints.
[0010] Robust optimization is known as a modeling technique for optimization problems that can return reliable results even when the data defining the problem is inaccurate or uncertain. Conventionally, systems that apply robust optimization to create power operation plans are also known (see, for example, Patent Documents 6 and 7). However, the techniques described in Patent Documents 6 and 7 do not optimize the charging and discharging plans of storage batteries.
[0011] The operation plan creation device described in Patent Document 6 generates forecast data indicating a statistically possible range based on data indicating actual power demand and data indicating actual power generation by renewable energy. Then, a generator operation plan is created by solving a problem of satisfying a constraint equation including the range indicated by the forecast data and predetermined constraints related to the generator specifications and the state of the power system, and bringing the value of an objective function, which has at least the cost of suppressing renewable energy, closer to a desired value. Here, problem data is generated by applying input values to the objective function and the constraint equation, and the problem data is transformed to be applied to a robust optimization method, and a generator operation plan is created based on the transformed equation based on the robust optimization method.
[0012] In the information processing device described in Patent Document 7, the amount of power procured from each of a plurality of power procurement means is used as an operational variable, a value including the total cost required to procure an amount of power corresponding to predicted demand using the plurality of power procurement means is used as an objective function, an optimization model having constraints on the amount of power that can be procured from the power procurement means is generated, and a power procurement plan indicating the amount of power to be procured from each of the plurality of power procurement means is determined by solving the optimization model using a mathematical optimization technique. Here, even if an uncertain constraint is given to the power demand, a robust optimization problem assuming replanning is formulated, and an optimal solution to the formulated robust optimization problem is obtained, thereby determining an optimal power generation plan for the input power demand. [Prior art documents] [Patent documents]
[0013] [Patent Document 1] Patent No. 6053554 [Patent Document 2] Patent No. 5672186 [Patent Document 3] JP 2016-73113 A [Patent Document 4] JP 2018-23188 A [Patent Document 5] JP 2016-116401 A [Patent Document 6] Patent Publication No. 2021-33625 [Patent Document 7] JP 2021-157724 A Summary of the Invention [Problem to be solved by the invention]
[0014] The present invention has been made to solve the problems described above, and aims to enable a system that creates a charging / discharging plan for a storage battery based on at least a power generation forecast and a demand forecast to create an optimal charging / discharging plan that is likely to satisfy given constraints even if the forecasts are incorrect, and that comes as close as possible to the objective. [Means for solving the problem]
[0015] In order to solve the above problems, in the present invention, a predicted value of the amount of power generation at each time during a prediction period is acquired, and another predicted value of power generation at each time during the prediction period is calculated using the acquired predicted value of power generation and a prediction error of the amount of power generation expected at each time during the prediction period calculated based on the actual value of the amount of power generation in the past. A predicted value of the amount of power demand at each time during the prediction period is acquired, and another predicted value of demand at each time during the prediction period is calculated using the acquired predicted value of demand and a prediction error of the amount of power demand expected at each time during the prediction period calculated based on the actual value of the amount of power demand in the past. Then, using information on the electricity rate system by time period during the prediction period, an optimization calculation is performed to reduce the power procurement fee for purchasing electricity while the multiple predicted values of power generation and multiple predicted values of demand and the state of the storage battery acquired and calculated as described above satisfy the constraint conditions set for the predicted value of power generation, the predicted value of demand, and the state of the storage battery, thereby creating a charging and discharging plan for the storage battery. Effect of the Invention
[0016] According to the present invention configured as described above, an optimization calculation is performed using a plurality of power generation forecast values and a plurality of demand forecast values, including not only the actual power generation forecast value and the demand forecast value that are initially acquired, but also another power generation forecast value and a demand forecast value that are calculated based on the acquired actual power generation forecast value and the demand forecast value. That is, an optimization calculation is performed such that the plurality of power generation forecast values and the plurality of demand forecast values and the state of the storage battery satisfy the constraint conditions and the power procurement fee for purchasing power is reduced. As a result, even if the actual power generation forecast and the demand forecast are incorrect, it is highly likely that the constraint conditions will be satisfied, and an optimal charging and discharging plan can be created that keeps the power procurement fee for purchasing power as low as possible.
[0017] In particular, in the present invention, since the actual power generation forecast value and the demand forecast value and the forecast error calculated based on the past actual values are used to calculate another power generation forecast value and another demand forecast value, the possibility of calculating an inappropriate forecast value as the other power generation forecast value and another demand forecast value can be reduced. Therefore, in order to satisfy the constraint conditions for all of the multiple power generation forecast values and the multiple demand forecast values during the optimization calculation, it is not necessary to unnecessarily relax the constraint conditions. As a result, it is possible to perform an optimization calculation that reduces the power procurement fee while satisfying the constraint conditions under appropriate constraint conditions. In other words, if the optimization calculation is performed using the multiple power generation forecast values and the multiple demand forecast values acquired and calculated by the present invention, it is possible to create a charge / discharge plan that is applicable within a range that satisfies the appropriately set constraint conditions even if the actual power generation power and demand power deviate from the actual forecast values. [Brief description of the drawings]
[0018] [Figure 1] 1 is a diagram illustrating an example of the overall configuration of a power management system according to an embodiment of the present invention. [Diagram 2] 2 is a block diagram showing an example of a functional configuration of a power management device according to the present embodiment. FIG. [Diagram 3] 5 is a diagram showing an example of power generation result data stored in a power generation result data storage unit; FIG. [Figure 4] 11 is a diagram showing an example of demand result data stored in a demand result data storage unit. FIG. [Diagram 5] 10 is a diagram showing an example of vehicle usage record data stored in a vehicle usage record data storage unit; FIG. [Figure 6] 4 is a block diagram showing a specific example of a functional configuration of a vehicle state prediction unit; FIG. [Figure 7] 2 is a schematic diagram showing the concept of a prediction model used as an example by a vehicle usage state prediction unit; FIG. [Figure 8] 11 is a schematic diagram for explaining the process of predicting a vehicle usage state for each predetermined unit time by beam search. FIG. [Figure 9] 11 is a diagram for explaining a processing example of a consumption prediction value calculation unit. FIG. [Figure 10] FIG. 13 is a diagram for explaining an example of calculation of a prediction error. [Figure 11] 4 is a flowchart showing an example of the operation of the power management device according to the present embodiment. [Figure 12] FIG. 13 is a diagram illustrating an example of gradual relaxation of constraint conditions. [Figure 13] 11 is a block diagram showing another example of the functional configuration of the power management device according to the present embodiment. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0019] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. Fig. 1 is a diagram showing an example of the overall configuration of a power management system according to this embodiment. The power management system of this embodiment is configured to include a power management device 100 installed as a server device on a cloud, for example, a system (EMS: Energy Management System) 101 that manages the power used by consumers, and a V2H (Vehicle to Home) system 102 that enables the power stored in an on-board storage battery 113 to be used as home power.
[0020] A consumer is a person who receives and uses the supply of electric power, and in one example, it is a general household. A consumer may be a business establishment such as a factory, an office, a sales office, a school, or a hospital. The consumer's facility includes an EMS 101, a V2H system 102, a solar power generation device 111, which is an example of a renewable energy power generation device, and various power loads 112 that consume electric power. -1 ,112 -2 ,... (hereinafter simply referred to as power load 112), an in-vehicle storage battery 113, and a non-vehicle storage battery 114 are set. In the case of an ordinary home, the power load 112 is various electrical appliances such as lighting, a television, a refrigerator, a washing machine, and an air conditioner, and the storage battery 114 is a small residential storage battery. In the following, the residential storage battery 114 will be described.
[0021] The EMS 101 is connected to a V2H system 102, a solar power generation device 111, a power load 112, and a residential storage battery 114. By using the EMS 101, it is possible to measure the power usage in the power load 112 in real time and visualize the energy usage status of the entire building, each room, each electrical appliance, and each hour. It is also possible to perform "peak shifting" by shifting the peak to another time period by using the power load 112 while avoiding the time period of high power usage, and "peak cutting" by preventing the power usage from exceeding a predetermined target value by optimally using the power generated by the solar power generation device 111 and the power stored in the vehicle storage battery 113 and the residential storage battery 114.
[0022] An on-board storage battery 113 of the vehicle is detachably connected to the V2H system 102 by a dedicated cable. When the V2H system 102 and the on-board storage battery 113 are connected, it is possible to charge the on-board storage battery 113 with power generated by the solar power generation device 111 (hereinafter referred to as generated power) or power purchased from a power company via a grid not shown (hereinafter referred to as purchased power), or to discharge power stored in the on-board storage battery 113 (hereinafter referred to as stored power) for use by the power load 112.
[0023] On the other hand, when the vehicle is used as mobility (a means of transportation), the dedicated cable connecting the V2H system 102 and the on-board storage battery 113 is disconnected, and the vehicle is allowed to move freely. In this embodiment, the V2H system 102 determines that the vehicle is "at home" when the on-board storage battery 113 is connected by a dedicated cable, and that the vehicle is "out" (being used as mobility) when the on-board storage battery 113 is not connected by a dedicated cable.
[0024] The power management device 100 is connected to an EMS 101 via a communication network such as the Internet, and acquires various types of data via the EMS 101. The power management device 100 is also connected to an electricity rate providing server 200 via the communication network, and acquires data on electricity rate systems by time period from the electricity rate providing server 200. Then, using this acquired data, the power management device 100 executes processes such as various predictions and the creation of charge / discharge plans, which will be described later, and controls the EMS 101 based on the results.
[0025] Fig. 2 is a block diagram showing an example of a functional configuration of the power management device 100 according to the present embodiment. As shown in Fig. 2, the power management device 100 of the present embodiment includes, as functional configurations, a power generation record data recording unit 1A, a power generation prediction unit 1B, a power generation prediction error calculation unit 1C, a separate power generation prediction value calculation unit 1D, a demand record data recording unit 2A, a power demand prediction unit 2B, a demand prediction error calculation unit 2C, a separate demand prediction value calculation unit 2D, a vehicle use record data recording unit 3A, a vehicle state prediction unit 3B, a consumption prediction error calculation unit 3C, a separate consumption prediction value calculation unit 3D, a fee data acquisition unit 4, a charge / discharge plan creation unit 5, and a charge / discharge control unit 6. In addition, the power management device 100 of the present embodiment includes, as storage media, a power generation record data storage unit 11, a demand record data storage unit 12, a vehicle use record data storage unit 13, and a fee table storage unit 14.
[0026] The above-mentioned functional blocks 1A to 1D, 2A to 2D, 3A to 3D, and 4 to 6 can be configured by any of hardware, DSP (Digital Signal Processor), and software. For example, when configured by software, the above-mentioned functional blocks are actually configured with a CPU, RAM, ROM, etc. of a computer, and are realized by the operation of a program stored in a storage medium such as the RAM, ROM, hard disk, or semiconductor memory.
[0027] 2, the power management device 100 creates a charge / discharge plan for the storage batteries 113, 114 based on the predicted power generation by the photovoltaic power generation device 111, the predicted power demand by the power load 112, the predicted power consumption by the in-vehicle storage battery 113, the charge / discharge amount of the storage batteries 113, 114, and a time-of-day electricity rate system. In this embodiment, the charge / discharge amount of the storage batteries 113, 114 at each time point in the prediction target period is set as one of the explanatory variables, and a mathematical optimization model function with the power procurement price through power purchase as the objective function is used to perform optimization calculations based on multiple predicted values, thereby creating a charge / discharge plan that minimizes the objective function while satisfying all predetermined constraint conditions.
[0028] The power generation performance data recording unit 1A acquires measurement data of the amount of power generated by the solar power generation device 111 from the EMS 101 in real time, and stores the data in the power generation performance data storage unit 11. In this embodiment, the power generation performance data recording unit 1A acquires measurement data of the amount of power generated transmitted from the EMS 101 at predetermined unit times, and stores the data in the power generation performance data storage unit 11. The power generation performance data recording unit 1A may acquire the measurement data recorded by the EMS 101 at predetermined unit times in batches.
[0029] Fig. 3 is a diagram showing an example of power generation record data stored in the power generation record data storage unit 11. As shown in Fig. 3, the power generation record data storage unit 11 stores in chronological order the time, weather, and amount of power generation for each predetermined unit time (for example, every 30 minutes). The weather is obtained, for example, from a website or server that provides meteorological information via a communication network such as the Internet.
[0030] The demand result data recording unit 2A acquires measurement data of the demand power amount (power consumption amount) of the power load 112 from the EMS 101 in real time, and stores the data in the demand result data storage unit 12. In this embodiment, the demand result data recording unit 2A acquires measurement data of the demand power amount (power consumption amount) of the power load 112 from the EMS 101 at predetermined unit time intervals. -1 ,112 -2,..., and stores the measurement data of the total power consumption in the demand actual data storage unit 12. The demand actual data recording unit 2A may acquire the measurement data recorded by the EMS 101 for each predetermined unit time in batches.
[0031] Fig. 4 is a diagram showing an example of demand record data stored in the demand record data storage unit 12. As shown in Fig. 4, the demand record data storage unit 12 stores the time, day of the week, and demand energy amount for each predetermined unit time (e.g., every 30 minutes) in chronological order. The day of the week is obtained, for example, from calendar data stored in advance in the power management device 100.
[0032] The vehicle usage history data recording unit 3A acquires in real time from the EMS 101 the detection data of the usage state of the vehicle as a mobility (either at home or away from home) and the measurement data of the power consumption of the vehicle-mounted storage battery 113, and stores them in the vehicle usage history data storage unit 13. In this embodiment, the vehicle usage history data recording unit 3A acquires the detection data of the vehicle usage state transmitted from the EMS 101 at predetermined unit times and stores them in the vehicle usage history data storage unit 13. The vehicle usage history data recording unit 3A also acquires the measurement data of the power consumption transmitted when the EMS 101 detects that the usage state of the vehicle has changed from away to at home, and stores them in the vehicle usage history data storage unit 13. The power consumption of the vehicle-mounted storage battery 113 can be calculated from the difference between the stored power of the vehicle-mounted storage battery 113 measured when the usage state of the vehicle has changed from at home to away from home (at the time of departure) and the stored power of the vehicle-mounted storage battery 113 measured when the usage state of the vehicle has changed from away to at home (at the time of return). The vehicle usage history data recording unit 3A may acquire the detection data of the usage state for each predetermined unit time recorded by the EMS 101 and the measurement data of the power consumption amount for each state change in a batch manner.
[0033] FIG. 5 is a diagram showing an example of vehicle usage history data stored in the vehicle usage history data storage unit 13. As shown in FIG. 5, the vehicle usage history data storage unit 13 stores the time, day of the week, and vehicle usage state for each predetermined unit time (for example, every 30 minutes) in chronological order, and stores the power consumption of the vehicle-mounted storage battery 113 when the vehicle is out. In FIG. 5, a circle in the vehicle usage state indicates that the vehicle is at home, and a cross indicates that the vehicle is out. In the example of FIG. 5, it is recorded that the vehicle was out for 7 hours and 30 minutes from 8:30 to 15:30 on 4 / 1 / 2019, and the power consumption of the vehicle-mounted storage battery 113 during that time. Since the vehicle was not out before 8:30 and after 16:00, the power consumption of the vehicle-mounted storage battery 113 is not recorded. For the power consumption for each predetermined unit time (every 30 minutes), for example, a value obtained by averaging the power consumption recorded as in FIG. 5 is used.
[0034] The power generation prediction unit 1B uses the power generation performance data stored in the power generation performance data storage unit 11 to predict the amount of power generated by the solar power generation device 111 for each specified unit time during the prediction period (corresponding to the "amount of power generated at each time during the prediction period" described in the claims. The amount of power generated at time t means the amount of power generated from time t to time t+1. The same applies to the amount of power demand and the amount of power consumption described below).
[0035] Here, the power generation prediction unit 1B repeats prediction of the amount of power generated by the photovoltaic power generation device 111 at a predetermined cycle as a batch process. For example, the power generation prediction unit 1B predicts the amount of power generated at a set time every day (for example, midnight) for a prediction target period of 24 hours the following day. Note that the time and the prediction target period are merely examples and are not limited to these.
[0036] The power generation prediction unit 1B uses the power generation record data stored in the power generation record data storage unit 11 to analyze the tendency of how much power generation can be obtained in what time period and under what weather conditions, and predicts the amount of power generation for each predetermined unit time during the prediction period based on the analysis result and predicted weather information for each predetermined unit time during the prediction period. The predicted weather information is obtained, for example, from a website or server that provides weather information via a communication network such as the Internet.
[0037] As an example, the power generation prediction unit 1B uses the power generation record data stored in the power generation record data storage unit 11 to generate a prediction model consisting of a function with time zones and weather as explanatory variables and the amount of power generation as a response variable. Then, predicted weather information for each predetermined unit time during the prediction period is input to the prediction model to predict the amount of power generation for each predetermined unit time during the prediction period. The prediction model can be generated, for example, by using known machine learning. For example, the prediction model can be a regression prediction model using machine learning such as random forest.
[0038] The power demand prediction unit 2B predicts the amount of power demand at the power load 112 for each predetermined unit time during the prediction period (the amount of power demand at each time during the prediction period) using the actual demand data stored in the actual demand data storage unit 12. Here, the power demand prediction unit 2B repeatedly predicts the amount of power demand by the power load 112 as a batch process. For example, the power demand prediction unit 2B predicts the amount of power demand at a set time each day (for example, midnight) for a prediction period of 24 hours the following day. Note that the time at which this prediction is made and the prediction period are merely examples and are not limited to these.
[0039] The electricity demand prediction unit 2B uses the actual demand data stored in the actual demand data storage unit 12 to analyze the tendency of how much electricity demand will occur at what time of day on what day of the week, and predicts the amount of electricity demand for each specified unit time during the prediction period based on the analysis result and information on the day of the week during the prediction period.
[0040] As an example, the power demand prediction unit 2B uses the demand result data stored in the demand result data storage unit 12 to generate a prediction model consisting of a function with the time period and the day of the week as explanatory variables and the power demand amount as a response variable. Then, by inputting information on the day of the week during the prediction target period into the prediction model, the power demand amount for each predetermined unit time during the prediction target period is predicted. The prediction model can be generated using, for example, known machine learning. For example, the prediction model can be a regression prediction model using machine learning such as random forest. Note that a prediction model using other information such as weather information (weather, temperature, humidity, etc.) as explanatory variables in addition to the time period and the day of the week may be generated. In this case, the demand result data stored in the demand result data storage unit 12 also includes other information.
[0041] The vehicle state prediction unit 3B predicts the usage state of the vehicle as mobility and the power consumption of the in-vehicle storage battery 113 for each predetermined unit time during the prediction target period (the vehicle usage state and the power consumption at each time during the prediction target period) using the vehicle usage record data of the in-vehicle storage battery 113 stored in the vehicle usage record data storage unit 13. Here, the vehicle state prediction unit 3B repeatedly predicts the vehicle usage state and the power consumption of the in-vehicle storage battery 113 as a batch process. For example, the vehicle state prediction unit 3B predicts the vehicle usage state and the power consumption at a set time every day (for example, 0:00 a.m.) for a prediction target period of 24 hours the following day. Note that the time and the prediction target period at which this prediction is performed are merely examples and are not limited thereto.
[0042] The vehicle state prediction unit 3B uses the vehicle usage history data of the in-vehicle storage battery 113 stored in the vehicle usage history data storage unit 13 to analyze the tendency of the vehicle being used as mobility during which time of day and the amount of power consumption, and predicts the vehicle usage state and power consumption for each predetermined unit time during the prediction target period based on the analysis result and the day of the week information during the prediction target period. For example, the vehicle state prediction unit 3B predicts the vehicle usage state for each predetermined unit time during the prediction target period. Then, the vehicle state prediction unit 3B extracts a vehicle usage state similar to the predicted vehicle usage state from the past vehicle usage states stored as vehicle usage history data in the vehicle usage history data storage unit 13, and predicts the power consumption of the in-vehicle storage battery 113 based on the actual value of the power consumption corresponding to the extracted similar vehicle usage state.
[0043] Fig. 6 is a block diagram showing a specific example of the functional configuration of the vehicle state prediction unit 3B. As shown in Fig. 6, the vehicle state prediction unit 3B includes a vehicle use state prediction unit 31, a pattern extraction unit 32, and a consumption prediction value calculation unit 33.
[0044] The vehicle usage state prediction unit 31 predicts a plurality of patterns of the usage state of the vehicle as a mobility at each time of the prediction target period, and calculates the occurrence probability indicating the likelihood of each pattern becoming the usage state. The vehicle usage state prediction unit 31 predicts the vehicle usage state for each predetermined unit time during the prediction target period, and calculates the occurrence probability of the predicted vehicle usage state, by performing a process similar to that disclosed in, for example, JP 2022-2449 A.
[0045] That is, the vehicle usage state prediction unit 31 uses the vehicle usage history data stored in the vehicle usage history data storage unit 13 to generate a prediction model consisting of a function with the time period and day of the week as explanatory variables and the vehicle usage state as a target variable. Then, by inputting information about the day of the week during the prediction period into the prediction model, the vehicle usage state is predicted for each predetermined unit time during the prediction period. Note that a prediction model may be generated that uses other information, such as weather information, as explanatory variables in addition to the time period and day of the week. In this case, the vehicle usage history data stored in the vehicle usage history data storage unit 13 also includes other information.
[0046] Fig. 7 is a schematic diagram showing the concept of a prediction model used as an example by the vehicle usage state prediction unit 31. The prediction model shown in Fig. 7 is a prediction model configured to input date and time information and day of the week information for each predetermined unit time to a neural network, and output the vehicle usage state for each predetermined unit time from the neural network. The neural network includes an LSTM layer (Long short-term memory) and a function layer between the input layer and the output layer, and calculates the vehicle usage state for each predetermined unit time t n The vehicle usage status for the previous specified unit time t n-1 The predicted vehicle usage state (label) is inherited and predicted.
[0047] By using such a prediction model, it is possible to reduce the possibility that the prediction result of the vehicle usage state by the vehicle usage state prediction unit 31 will be an erroneous prediction in which the time period when the vehicle is predicted to be at home and the time period when the vehicle is predicted to be away alternate at short time intervals. In other words, alternating between being at home and being away at short time intervals of 30 minutes is not a typical usage state for a vehicle as a mobility, and both the time period when the vehicle is at home and the time period when the vehicle is away often last for a relatively long time. By assigning a label representing the prediction result of the vehicle usage state for each predetermined unit time and generating a prediction model to which sequence labeling is applied using LSTM, it becomes possible to predict the vehicle usage state in accordance with general trends.
[0048] The vehicle usage state prediction unit 31 inputs prediction period information (date and time information and day of the week information for the prediction target period) to a prediction model conceptually illustrated in Fig. 7, and predicts multiple patterns of vehicle usage state as mobility for each predetermined unit time during the prediction target period while pruning some of the prediction results with low occurrence probability from the multiple prediction results for each predetermined unit time. When making this prediction, the vehicle usage state prediction unit 31 uses, for example, a technique called beam search.
[0049] Fig. 8 is a schematic diagram for explaining the process of predicting the vehicle usage state for each predetermined unit time by beam search. In Fig. 8, time t1 is the first predetermined unit time of the prediction target period, time t2 is the second predetermined unit time of the prediction target period, and time t3 is the third predetermined unit time of the prediction target period. The fourth and subsequent predetermined unit times are not shown. In Fig. 8, a ■ symbol indicates that the vehicle is predicted to be out, and the attached numerical value indicates the occurrence probability. A □ symbol indicates that the vehicle is predicted to be at home, and the attached numerical value indicates the occurrence probability.
[0050] In the example of Fig. 8, the usage state prediction unit 63 predicts that the probability of the vehicle usage state at time t1 is 0.8 for being out and 0.2 for being at home. Here, the vehicle usage state prediction unit 31 prunes, for example, prediction results other than those with the top N occurrence probabilities from among the two prediction results related to the vehicle usage state at time t1. Pruning means not adopting them. Here, it is assumed that N = 3, and prediction results other than those with the top three occurrence probabilities are pruned. At time t1, only two patterns are predicted, so pruning is not performed.
[0051] Next, the vehicle usage state prediction unit 31 predicts that the probability of the vehicle usage state at time t2 remaining as the out state from the out state at time t1 is 0.5, the probability of the out state at time t1 changing to the at-home state is 0.3, the probability of the at-home state at time t1 changing to the out state is 0.05, and the probability of the at-home state at time t1 continuing to the at-home state is 0.15. In this case, the vehicle usage state prediction unit 31 prunes the prediction result of the pattern "time t1: at-home -> time t2: out", which is predicted to have the lowest occurrence probability of 0.05, among the four prediction results.
[0052] Next, the vehicle usage state prediction unit 31 predicts the vehicle usage state at time t3. Here, the vehicle usage state prediction unit 31 does not perform predictions after time t3 for the vehicle usage states pruned at time t2, but takes over the prediction results of the three surviving patterns at time t2 and predicts the probability of being out / at home for each. Therefore, six patterns of vehicle usage states are predicted as follows: (1) Time t1: Going out → Time t2: Going out → Time t3: Going out... Probability 0.1 (2) Time t1: out → Time t2: out → Time t3: at home... Probability 0.4 (3) Time t1: out → Time t2: at home → Time t3: out... Probability 0.1 (4) Time t1: out → Time t2: at home → Time t3: at home... Probability 0.2 (5) Time t1: At home → Time t2: At home → Time t2: Out... Probability 0.12 (6) Time t1: At home → Time t2: At home → Time t2: At home... Probability 0.03 In this case, the vehicle usage state prediction unit 31 prunes patterns (1), (3), and (6) that are outside the top three occurrence probabilities.
[0053] Thereafter, the vehicle usage state prediction unit 31 similarly predicts six patterns of vehicle usage states for each time period from time t4 (not shown) to time t48, which is the last predetermined unit time of the prediction target period (the next 24 hours) (the final time when the predetermined unit time is 30 minutes), while pruning prediction results of patterns other than the top three occurrence probabilities. Then, by pruning three patterns other than the top three occurrence probabilities from the six prediction results at time t48, three patterns of predicted usage states are finally obtained.
[0054] The pruning method shown here is an example and is not limited thereto. For example, a prediction result with an occurrence probability equal to or less than a predetermined value (for example, equal to or less than 0.1) may be pruned. In addition, although an example of predicting three patterns of vehicle use states has been described here, a vehicle use state with a greater number of patterns may be predicted. In addition, although not described in detail here, a plurality of patterns of vehicle use states may be predicted by the method described as Modification 1 or Modification 2 in JP2022-2449A. In addition, any method may be used as long as the occurrence probability is calculated for each pattern, and the method is not limited to the method described in JP2022-2449A.
[0055] The pattern extraction unit 32 extracts one usage state prediction pattern based on the occurrence probability from among the multiple usage state prediction patterns generated by the vehicle usage state prediction unit 31. For example, the pattern extraction unit 32 extracts the usage state prediction pattern with the highest occurrence probability.
[0056] The consumption prediction value calculation unit 33 calculates a prediction value of the power consumption of the on-board storage battery 113 at each time of the prediction period based on the usage state prediction pattern extracted by the pattern extraction unit 32 and the actual values of the past power consumption of the on-board storage battery 113 stored in the vehicle usage actual data storage unit 13. Here, the consumption prediction value calculation unit 33 uses the actual values close to the departure time and the return home time in order to predict the power consumption of the on-board storage battery 113 for each outing.
[0057] Fig. 9 is a diagram for explaining an example of processing by the consumption prediction value calculation unit 33. Fig. 9(0) shows a usage state prediction pattern extracted by the pattern extraction unit 32. First, as shown in Fig. 9(a), the consumption prediction value calculation unit 33 extracts a usage state actual pattern whose departure time and return home time differ from the usage state prediction pattern in Fig. 9(0) by within one hour from the usage state actual pattern for D days (D=5 in the example of Fig. 9(a)) prior to the prediction target period of 4 / 6.
[0058] Next, as shown in Fig. 9(b), the consumption prediction value calculation unit 33 extracts K (K=3 in the case of Fig. 9(b)) actual usage state patterns in descending order of the greatest time overlap with the predicted usage state pattern. Finally, the consumption prediction value calculation unit 33 calculates the median of the power consumption when going out for the K actual usage state patterns, and sets this as the predicted value of the power consumption of the in-vehicle storage battery 113. If there is no actual usage state pattern that meets the first condition, the power consumption of the actual usage state pattern that has the greatest time overlap with the predicted usage state pattern, among the actual usage state patterns for the past 30 days, is set as the predicted value of the power consumption of the in-vehicle storage battery 113.
[0059] The power generation prediction error calculation unit 1C calculates prediction errors of the amount of power generation expected at each time of the prediction period (hereinafter referred to as power generation prediction errors) based on the actual values of the amount of power generation in the past of the photovoltaic power generation device 111 stored in the power generation result data storage unit 11. That is, the power generation prediction error calculation unit 1C calculates the power generation prediction errors for each of the times t1 to t48 at 30-minute intervals during the prediction period. The power generation prediction error calculation unit 1C calculates at least one, and preferably multiple, power generation prediction errors for each time.
[0060] For example, the power generation prediction error calculation unit 1C calculates the standard deviation of the actual values of the past power generation amounts, and generates a random value within a predetermined value range specified based on the standard deviation to set the power generation prediction error. As an example, the power generation prediction error calculation unit 1C assumes a normal distribution from the standard deviation σ as shown in Fig. 10, using the power generation prediction value acquired by the power generation prediction unit 1B as the average, and generates a random value within the range of ±2σ to set the power generation prediction error. In this way, in this embodiment, errors with standard deviations exceeding the range of ±2σ, that is, errors that are unlikely to occur probabilistically, are not adopted.
[0061] The separate power generation prediction value calculation unit 1D calculates a separate power generation prediction value at each time of the prediction target period using the power generation prediction value acquired by the power generation prediction unit 1B and the power generation prediction error calculated by the power generation prediction error calculation unit 1C. The separate power generation prediction value calculation unit 1D calculates at least one, and preferably multiple, separate power generation prediction values for each time.
[0062] For example, the power generation forecast value for each time t during the forecast period is calculated as PPV t The expected power generation forecast error at each time t is PPE t The separate power generation forecast value calculation unit 1D calculates a separate power generation forecast value PPV t ' is calculated by the following (Equation 1), where rand(σ) is a function that generates a single random number within the range of ±2σ according to a normal distribution with a mean of 0 and a standard deviation of σ.
[0063]
number
[0064] The demand forecast error calculation unit 2C calculates a forecast error of the amount of power demand expected at each time of the prediction period (hereinafter, called a demand forecast error) based on the actual values of the past amount of power demand of the power load 112 stored in the demand result data storage unit 12. That is, the demand forecast error calculation unit 2C calculates a demand forecast error for each of the times t1 to t48 at 30-minute intervals during the prediction period. The demand forecast error calculation unit 2C calculates at least one, and preferably multiple, demand forecast errors for each time.
[0065] For example, the demand forecast error calculation unit 2C calculates the standard deviation of the actual values of the past demand energy amounts, and generates a random value within a predetermined value range specified based on the standard deviation to set the demand forecast error. As an example, the demand forecast error calculation unit 2C, like the power generation forecast error calculation unit 1C, also assumes a normal distribution as shown in Fig. 10, and generates a random value within a range of ±2σ to set the demand forecast error.
[0066] The separate demand forecast value calculation unit 2D calculates a separate demand forecast value at each time of the forecast target period using the demand forecast value acquired by the power demand forecast unit 2B and the demand forecast error calculated by the demand forecast error calculation unit 2C. The separate demand forecast value calculation unit 2D calculates at least one, and preferably multiple, separate demand forecast values for each time. For example, the demand forecast value at each time t during the forecast target period is calculated as DPV t , the expected demand forecast error at each time t is DPE t The separate demand forecast value calculation unit 2D calculates a separate demand forecast value DPV t ' is calculated using the following (Equation 2).
[0067]
number
[0068] The consumption prediction error calculation unit 3C calculates a prediction error (hereinafter referred to as a consumption prediction error) of the battery power consumption expected at each time during the prediction period based on the actual values of the past power consumption of the in-vehicle storage battery 113 stored in the vehicle usage actual data storage unit 13. That is, the consumption prediction error calculation unit 3C calculates a consumption prediction error for each of the times t1 to t48, which are 30 minutes apart during the prediction period. The consumption prediction error calculation unit 3C calculates at least one, and preferably multiple, consumption prediction errors for each time.
[0069] For example, the consumption prediction error calculation unit 3C calculates the standard deviation of the past actual values of the power consumption of the storage battery, and generates a random value within a predetermined value range specified based on the standard deviation to set the consumption prediction error. As an example, like the power generation prediction error calculation unit 1C, the consumption prediction error calculation unit 3C also assumes a normal distribution as shown in Fig. 10, and generates a random value within a range of ±2σ to set the consumption prediction error.
[0070] The separate consumption prediction value calculation unit 3D calculates a separate storage battery consumption prediction value at each time of the prediction target period using the storage battery consumption prediction value acquired by the vehicle state prediction unit 3B and the consumption prediction error calculated by the consumption prediction error calculation unit 3C. For example, the consumption prediction value at each time t during the prediction target period is expressed as CPV t , the expected consumption forecast error at each time t is CPE t The separate consumption prediction value calculation unit 3D calculates a separate consumption prediction value CPV t ' is calculated using the following (Equation 3).
[0071]
number
[0072] The fee data acquisition unit 4 acquires data on the electricity fee system by time period in the prediction target period from the electricity fee provider server 200 via the communication network, and stores the data in the fee table storage unit 14. The electricity fee system data acquired here is, for example, data on the next day's transaction price (contract price) provided by the Japan Electric Power Exchange (JEPX), and this can be treated as a predicted value in the prediction target period. Note that a prediction service provided by a third party other than JEPX may be used to acquire a predicted value of the transaction price, or the fee data acquisition unit 4 may be provided with a function for predicting the transaction price.
[0073] The charge / discharge plan creation unit 5 creates a charge / discharge plan for the storage batteries 113, 114 by performing optimization calculations using each predicted value calculated by the power generation prediction unit 1B, the individual power generation predicted value calculation unit 1D, the power demand prediction unit 2B, the individual demand predicted value calculation unit 2D, the vehicle state prediction unit 3B, and the individual consumption predicted value calculation unit 3D, as well as information on the electricity rate system by time period during the prediction period stored in the rate table memory unit 14, to reduce the electricity procurement fee for purchasing electricity while satisfying specified constraints and without causing a shortage of the amount of stored electricity required for use as the mobility of the vehicle.
[0074] Here, each predicted value used by the charge / discharge plan creation unit 5 is a plurality of predicted power generation values PPV obtained by the power generation prediction unit 1B and the separate power generation predicted value calculation unit 1D. t , PPV t ' and a plurality of demand forecast values DPV obtained by the power demand forecast unit 2B and the separate demand forecast value calculation unit 2D. t ,D.P.V. t ', and a plurality of predicted consumption values CPV obtained by the predicted consumption value calculation unit 33 of the vehicle state prediction unit 3B and the separate predicted consumption value calculation unit 3D. t ,CPV t ' is the vehicle usage state predicted by the vehicle usage state prediction unit 31 of the vehicle state prediction unit 3B.
[0075] The charge / discharge plan creation unit 5 creates a charge / discharge plan for each specified unit time during the prediction period for the storage batteries 113, 114 under specified constraint conditions so that the above-mentioned predicted values and the states of the storage batteries 113, 114 satisfy the constraint conditions, while reducing the electricity procurement fee for purchasing electricity without causing a shortage of the amount of stored electricity required for use as vehicle mobility.
[0076] For example, the power procurement fee for purchasing electricity is PPF, and the charging amount of the storage batteries 113 and 114 at each time t during the forecast period is CAT t The discharge amount of the storage batteries 113 and 114 at each time t is represented as DAT t , multiple power generation forecast values at each time t are calculated as PPV t,p , multiple demand forecast values at each time t are calculated as DPV t.p , the electricity price at each time t is EP t In this case, the charge / discharge plan creation unit 5 uses the following (Equation 4) as an objective function and performs optimization calculations to create a charge / discharge plan that minimizes the power procurement fee PPF while satisfying all of the predetermined constraints. In (Equation 4), the charge amount CAT of the storage batteries 113, 114 at each time t is expressed as t and discharge amount DAT t are the manipulated variables (optimization variables) to be optimized by the optimization calculation.
[0077]
number
[0078] Here, multiple power generation forecast values PPV t,p and multiple demand forecast values DPV t.p The symbol "p" used in the above indicates the pattern number of the predicted value. For example, the power generation predicted value PPV for p=1 t,1 is the actual power generation predicted value PPV predicted by the power generation prediction unit 1B t In addition, the power generation forecast value PPV for p=2, 3,... t,p is the other power generation forecast value PPV calculated by the other power generation forecast value calculation unit 1D t Similarly, the demand forecast value DPV for p=1 t,1is the actual demand forecast value DPV predicted by the power demand forecast unit 2B t In addition, the demand forecast value DPV for p=2,3,... t,p is another demand forecast value DPV calculated by the another demand forecast value calculation unit 2D t ' is.
[0079] Note that minimizing the power procurement charge PPF through optimization calculation is not limited to finding the actual minimum value strictly. For example, the number of times the recursive calculation is performed may be limited in consideration of the calculation load, and the power procurement charge PPF may be minimized within the limit. Alternatively, the recursive calculation may be performed until the power procurement charge PPF falls below a desired threshold, and the minimized value at the point when the power procurement charge PPF falls below the desired threshold may be regarded as the solution.
[0080] The predetermined constraint conditions used by the charge / discharge plan creation unit 5 in the optimization calculation are described below. In this embodiment, the predetermined constraint conditions include a plurality of constraint conditions set for a power generation forecast value, a demand forecast value, and the state (charge / discharge amount and stored power) of the storage batteries 113, 114. The plurality of constraint conditions include a peak value-related constraint condition for keeping the peak value of the power usage amount due to purchased power equal to or less than a target peak value, and a battery deterioration-related constraint condition for suppressing deterioration of the storage batteries 113, 114 due to charging and discharging.
[0081] The following (Equation 5) is an example of a peak-related constraint: where PT is the peak target value. (D.P.V. t,p +CAT t )-(PPV t,p +DAT t )≦PT (Formula 5) In this (Equation 5), the first term in the first parentheses on the left-hand side indicates the amount of power usage at each time t, and the second term indicates the amount of power procured other than through power purchases at each time t. Thus, the left-hand side indicates the amount of power procured and used through power purchases. Generally, electricity rates consist of a basic charge and a metered charge, and the basic charge is determined by the annual maximum peak value of power usage. For this reason, a constraint is set to keep power usage through purchased power below the peak target value PT.
[0082] The following (Equation 6) to (Equation 11) are examples of battery degradation-related constraint conditions. Here, VCAT t is the charge amount of the in-vehicle storage battery 113 from time t to time t+1, and VDAT in (Equation 7) t is the discharge amount of the in-vehicle storage battery 113 from time t to time t+1, and R t is the charge amount of the residential storage battery 114 from time t to time t+1, and RDAT t is the amount of discharge of the residential storage battery 114 from time t to time t+1. Lower limit value ≦ VCAT t ≦Upper limit value (Equation 6) Lower limit value ≦ VDAT t ≦Upper limit value (Equation 7) Lower limit ≦ RCAT t ≦Upper limit value (Equation 8) Lower limit value ≦ RDAT t ≦Upper limit value (Equation 9) Minimum value ≦ VBHP t,p ≦Maximum value (Equation 10) Minimum value ≦ RBHP t ≦Maximum value (Eq. 11)
[0083] In addition, VBHP in the above formula (10) t,p is the stored power of the vehicle-mounted battery 113 at each time t, and is calculated by the following (Equation 12). In this (Equation 10), the symbol "p" indicates the pattern number. For example, the stored power VBHP for p=1 is t,1 is the actual consumption predicted value CPV predicted by the vehicle state prediction unit 3B t The holding power is calculated using the following formula: t,pis another consumption prediction value CPV calculated by the another consumption prediction value calculation unit 3D. t ' is the holding power calculated using the RBHP in the above (Equation 11). t is the stored power of the residential storage battery 114 at each time t, and is calculated by the following (Equation 13).
[0084]
number
[0085] In the above (Equation 12), VBP0 is the initial stored power of the in-vehicle storage battery 113 at the first time t0 of the prediction target period. t is a flag value indicating the vehicle usage state predicted by the vehicle usage state prediction unit 31, and is "1" when the user is out and "0" when the user is at home. In addition, in the above (Equation 13), RBP0 is the initial stored power of the residential storage battery 114 at the first time t0 of the prediction target period.
[0086] The charge / discharge schedule creation unit 5 performs optimization calculations by applying the peak value-related constraint condition shown in (Equation 5) above and the battery degradation-related constraint conditions shown in (Equations 6) to (Equations 11) as well as, for example, the constraint conditions shown below. The use of the power generated by the photovoltaic power generation device 111 for the power load 112 is prioritized over the purchase of power from the grid. When the power generated by the solar power generation device 111 exceeds the power consumed by the power load 112 (that is, when surplus power is generated), charging of the storage batteries 113, 114 with the surplus power takes precedence over charging with purchased power. During the time period when the vehicle is predicted to be at home, charging and discharging are performed with priority given to the in-vehicle storage battery 113 over the residential storage battery 114. Ensure that the stored power of the in-vehicle storage battery 113 at the time when the vehicle usage state is predicted to switch from at home to away is not below the predicted value of the power consumption during the time when the vehicle is away until the next time when the vehicle usage state is predicted to switch from away to at home.
[0087] In addition, the following constraints may be further applied. Considering emergency use of the vehicle as a form of mobility, if the remaining charge of the in-vehicle storage battery 113 at the time of returning home (when the in-vehicle storage battery 113 is connected to the V2H system 102 via a dedicated cable) is below a threshold, charging will be performed up to a predetermined amount regardless of the vehicle usage state predicted by the vehicle usage state prediction unit 31. · Since charging and discharging the in-vehicle battery 113 immediately after returning home after using the vehicle as a form of mobility and while the battery is still hot will cause rapid battery deterioration, charging and discharging should be performed after a predetermined time has elapsed since returning home.
[0088] The charge / discharge control unit 6 controls the actual charging / discharging of the storage batteries 113, 114 during the planned period (=prediction period) in accordance with the charge / discharge plan created by the charge / discharge plan creation unit 5 under the above-mentioned constraints.
[0089] Fig. 11 is a flowchart showing an example of the operation of the power management device 100 according to this embodiment configured as described above. Note that the processes of the power generation record data recording unit 1A, the demand record data recording unit 2A, and the vehicle usage record data recording unit 3A are executed sequentially, and the processes of storing the respective record data in the power generation record data storage unit 11, the demand record data storage unit 12, and the vehicle usage record data storage unit 13 are executed separately and asynchronously with the flowchart shown in Fig. 11.
[0090] 11, the power generation prediction unit 1B predicts the amount of power generation at each time during the prediction period using the power generation result data stored in the power generation result data storage unit 11 (step S1). The power generation prediction error calculation unit 1C calculates the power generation prediction error expected at each time during the prediction period based on the past power generation amount actual values stored in the power generation result data storage unit 11 (step S2). The separate power generation prediction value calculation unit 1D calculates another power generation prediction value at each time during the prediction period using the power generation prediction value acquired by the power generation prediction unit 1B and the power generation prediction error calculated by the power generation prediction error calculation unit 1C (step S3).
[0091] Next, the power demand prediction unit 2B predicts the amount of power demand at each time during the prediction period using the actual demand data stored in the actual demand data storage unit 12 (step S4). The demand prediction error calculation unit 2C calculates the demand prediction error expected at each time during the prediction period based on the actual values of the amount of power demand in the past stored in the actual demand data storage unit 12 (step S5). The separate demand prediction value calculation unit 2D then calculates another demand prediction value at each time during the prediction period using the demand prediction value acquired by the power demand prediction unit 2B and the demand prediction error calculated by the demand prediction error calculation unit 2C (step S6).
[0092] Furthermore, the vehicle state prediction unit 3B predicts the usage state of the vehicle as a mobility and the power consumption of the in-vehicle storage battery 113 at each time of the prediction target period using the vehicle usage record data of the in-vehicle storage battery 113 stored in the vehicle usage record data storage unit 13 (step S7). Furthermore, the consumption prediction error calculation unit 3C calculates the consumption prediction error expected at each time of the prediction target period based on the past power consumption record value of the in-vehicle storage battery 113 stored in the vehicle usage record data storage unit 13 (step S8). Then, the separate consumption prediction value calculation unit 3D calculates another consumption prediction value at each time of the prediction target period using the consumption prediction value acquired by the vehicle state prediction unit 3B and the consumption prediction error calculated by the consumption prediction error calculation unit 3C (step S9).
[0093] The fee data acquisition unit 4 also acquires data on the electricity fee system by time period in the prediction target period from the electricity fee providing server 200, and stores the data in the fee table storage unit 14 (step S10). Note that the processes in steps S1 to S3, S4 to S6, S7 to S9, and S10 do not necessarily have to be performed in this order.
[0094] Next, the charge / discharge plan creation unit 5 uses the respective predicted values calculated by the power generation prediction unit 1B, the separate power generation prediction value calculation unit 1D, the power demand prediction unit 2B, the separate demand prediction value calculation unit 2D, the vehicle state prediction unit 3B, and the separate consumption prediction value calculation unit 3D in the above steps S1 to S10, and information on the time-of-day electricity rate system in the prediction target period stored in the rate table storage unit 14 to perform optimization calculations that reduce the electricity procurement fee for purchasing electricity while satisfying predetermined constraints and without causing a shortage of the amount of stored electricity required for use as the mobility of the vehicle, thereby creating a charge / discharge plan for the storage batteries 113, 114 (step S11). This ends the processing of the flowchart shown in FIG. 11.
[0095] As described above in detail, in this embodiment, a power generation forecast value (a forecast value of power generation amount) of the photovoltaic power generation device 111 at each time of the prediction target period is acquired, and another power generation forecast value is calculated. In addition, a demand forecast value (a forecast value of demanded power amount) of the power load 112 at each time of the prediction target period is acquired, and another demand forecast value is calculated. In addition, a consumption forecast value (a forecast value of power consumption amount) of the storage batteries 113, 114 at each time of the prediction target period is acquired, and another consumption forecast value is calculated. Then, using information on the time-of-day electricity rate system in the prediction target period, under constraint conditions set for the power generation forecast value, the demand forecast value, and the state of the storage battery, a charging and discharging plan for the storage batteries 113, 114 is created by performing an optimization calculation that reduces the power procurement fee for purchasing electricity without causing a shortage of the amount of storage required for use as the mobility of the vehicle while the multiple power generation forecast values, multiple demand forecast values, and multiple consumption forecast values acquired and calculated as described above and the state of the storage battery satisfy all constraint conditions.
[0096] According to the present embodiment configured as described above, the optimization calculation is performed using a plurality of power generation forecast values, a plurality of demand forecast values, and a plurality of consumption forecast values, including not only the actual power generation forecast value, the demand forecast value, and the consumption forecast value that are acquired first, but also another power generation forecast value, a demand forecast value, and a consumption forecast value that are calculated based on the acquired actual power generation forecast value, the demand forecast value, and the consumption forecast value. That is, the optimization calculation is performed such that all of the power generation forecast values, the demand forecast values, and the consumption forecast values and the state of the storage battery satisfy the constraint conditions, and the power procurement fee for purchasing power is reduced without causing a shortage of the amount of storage required for use as the mobility of the vehicle. As a result, even if the actual power generation forecast, the demand forecast, and the consumption forecast are not accurate, it is possible to create an optimal charging and discharging plan that is highly likely to satisfy the constraint conditions, and that reduces the power procurement fee for purchasing power as much as possible without causing a shortage of the amount of storage required for use as the mobility of the vehicle.
[0097] In particular, in this embodiment, since a different predicted value is calculated using an actual predicted value and a prediction error calculated based on past actual values, the possibility of calculating an incorrect predicted value as the different predicted value can be reduced. Therefore, in order to satisfy the constraint conditions for all of the multiple predicted values during optimization calculation, it is not necessary to unnecessarily relax the constraint conditions, such as by increasing the peak target value PT in (Equation 5), decreasing the lower limit or minimum value in (Equation 6) to (Equation 11), or increasing the upper limit or maximum value in (Equation 6) to (Equation 11). This makes it possible to perform optimization calculations that reduce the power procurement fee while satisfying appropriate constraint conditions.
[0098] Moreover, in this embodiment, the standard deviation σ is calculated based on past actual values, and another predicted value is calculated using only the prediction error extracted from the range of ±2σ of the normal distribution, so that it is possible to avoid the calculation of another predicted value, which is unlikely to occur probabilistically. In this way, by performing optimization calculations using multiple predicted values acquired and calculated by this embodiment, it is possible to create a charge / discharge plan that is applicable within a range that satisfies appropriately set constraint conditions, even if the actual generated power, demanded power, and consumed power deviate from the actual predicted values.
[0099] In addition, when the optimization calculation is performed under the constraint conditions that are appropriately set as described above (constraint conditions that are not unnecessarily loose), there may be cases where a solution that satisfies all of the constraint conditions is not obtained. In this case, the charge / discharge schedule creation unit 5 may relax at least one of the constraint conditions and perform the optimization calculation again to reduce the power procurement fee under the relaxed constraint conditions.
[0100] In this case, for example, the charge / discharge plan creation unit 5 may assign a higher priority to the peak value-related constraint condition than the battery degradation-related constraint condition, and repeat the optimization calculation while gradually relaxing the multiple constraint conditions according to the priority until a solution that satisfies the constraint conditions is obtained. For example, when a solution that satisfies all of the multiple constraint conditions shown in the above (Equation 5) to (Equation 11) cannot be obtained, the battery degradation-related constraint condition is first relaxed and the optimization calculation is performed again. Then, when a solution that satisfies all of the multiple constraint conditions including the relaxed battery degradation-related constraint condition is still not obtained, the peak value-related constraint condition is relaxed and the optimization calculation is performed again. When relaxing the peak value-related constraint condition, it is preferable to restore the battery degradation-related constraint condition to its original state.
[0101] Here, relaxing the battery degradation-related constraint condition means relaxing one or more of the constraint conditions shown in the above (Equation 6) to (Equation 11). That is, relaxing one or more of the lower limit values or minimum values shown in (Equation 6) to (Equation 11) means reducing one or more of the lower limit values or minimum values shown in (Equation 6) to (Equation 11), increasing one or more of the upper limit values or maximum values shown in (Equation 6) to (Equation 11), or both. Relaxing the peak value-related constraint condition means increasing the peak target value PT shown in (Equation 5).
[0102] Here, an example of two-stage constraint relaxation, in which the battery degradation-related constraint is relaxed first and then the peak value-related constraint is relaxed, may be relaxed in three or more stages. FIG. 12 is a diagram showing an example of relaxation in this case. In the example of FIG. 12, first, only the battery degradation-related constraint is relaxed by one stage from the previous stage, the battery degradation-related constraint is restored to the previous state and the peak value-related constraint is relaxed by one stage from the previous stage, and the battery degradation-related constraint and the peak value-related constraint are relaxed by one stage each, which are regarded as one set, and these sets are sequentially repeated to relax the constraint in stages. Note that this is merely an example, and other methods may be used.
[0103] In addition, as a battery degradation-related constraint to be relaxed, a condition that a certain time period after returning home is required before charging or discharging may be added to the constraints shown in (Equation 6) to (Equation 11). In this case, the relaxation of the condition is either shortening the certain time period or removing the constraint.
[0104] In the above embodiment, the configuration is shown in which both the in-vehicle storage battery 113 and the residential storage battery 114 are provided as storage batteries, but only one of them may be provided. In the case of a configuration in which only the residential storage battery 114 is provided, the vehicle usage history data recording unit 3A, the vehicle state prediction unit 3B, the consumption prediction error calculation unit 3C, the separate consumption prediction value calculation unit 3D, and the vehicle usage history data storage unit 13 are omitted. In addition, the constraint conditions shown in (Equation 6), (Equation 7), and (Equation 10) are excluded. Then, the charge / discharge plan creation unit 5 creates a charge / discharge plan for the residential storage battery 114 by performing optimization calculations to reduce the power procurement fee under the multiple constraint conditions shown in (Equation 5), (Equation 8), (Equation 9), and (Equation 11).
[0105] In the above embodiment, the pattern extraction unit 32 of the vehicle state prediction unit 3B extracts one usage state prediction pattern having the highest occurrence probability, and the consumption prediction value calculation unit 33 calculates one predicted consumption value using the extracted usage state prediction pattern, while the other predicted consumption value calculation unit 3D calculates another predicted consumption value using the consumption prediction error calculated by the consumption prediction error calculation unit 3C. However, the present invention is not limited to this. For example, the following configuration may be used.
[0106] That is, the pattern extraction unit 32 extracts any of a plurality of usage state prediction patterns based on the occurrence probability from among the plurality of usage state prediction patterns generated by the vehicle usage state prediction unit 31. For example, the plurality of usage state prediction patterns are extracted in descending order of occurrence probability. The consumption prediction value calculation unit 33 calculates a prediction value of the power consumption of the in-vehicle storage battery 113 at each time of the prediction target period for each of the plurality of usage state prediction patterns extracted by the pattern extraction unit 32, based on the usage state prediction pattern and the actual value of the past power consumption of the in-vehicle storage battery 113.
[0107] In this configuration, the consumption prediction error calculation unit 3C calculates one or more consumption prediction errors for each of the multiple consumption prediction values, and the separate consumption prediction value calculation unit 3D calculates a separate consumption prediction value using the consumption prediction errors. As an example, m (m≧2) usage state prediction patterns are extracted in descending order of occurrence probability, and n1, n2, . . . n are selected from the extracted m usage state prediction patterns. m pieces (total n1+n2+...+n m Here, n1>n2>...>n may be calculated according to the occurrence probability of the usage state prediction pattern. m It is also possible to use the following.
[0108] Alternatively, the consumption prediction error calculation unit 3C and the separate consumption prediction value calculation unit 3D may be omitted, and the charge / discharge plan creation unit 5 may be configured as follows: That is, under constraint conditions set for the power generation prediction value, the demand prediction value, and the state of the storage batteries 113, 114, the charge / discharge plan creation unit 5 creates a charge / discharge plan for the storage batteries 113, 114 by performing an optimization calculation that reduces the power procurement fee without causing a shortage of the amount of storage required for use as the mobility of the vehicle, while satisfying the constraint conditions among the multiple power generation prediction values obtained by the power generation prediction unit 1B and the separate power generation prediction value calculation unit 1D, the multiple demand prediction values obtained by the power demand prediction unit 2B and the separate demand prediction value calculation unit 2D, the multiple consumption prediction values obtained by the consumption prediction value calculation unit 33 from each of the multiple usage state prediction patterns extracted by the pattern extraction unit 32, and the state of the storage batteries 113, 114.
[0109] In the above embodiment, an example has been described in which the fee data acquisition unit 4 acquires data on the electricity fee system by time period in the prediction target period from the electricity fee providing server 200, stores the data in the fee table storage unit 14, and performs optimization calculations using the data on the electricity fee system, but the present invention is not limited to this. For example, as with the power generation prediction value and the demand prediction value, one or more separate electricity fees may be calculated using a prediction error in the electricity fee, and then the optimization calculations may be performed using the multiple electricity fees thus obtained.
[0110] Fig. 13 is a diagram showing an example of the functional configuration of a power management device 100' in this case. In Fig. 13, blocks having the same reference numerals as those shown in Fig. 2 include the same functions as the functional blocks shown in Fig. 2, and are shown in a simplified manner. The power management device 100' shown in Fig. 13 includes an electricity rate actual data recording unit 4A, a rate data acquisition unit 4B, an electricity rate prediction error calculation unit 4C, a separate electricity rate prediction value calculation unit 4D, an electricity rate actual data storage unit 14', and a charge / discharge plan creation unit 5', instead of the rate data acquisition unit 4, the rate table storage unit 14, and the charge / discharge plan creation unit 5 shown in Fig. 2.
[0111] The electricity rate actual data recording unit 4A acquires actual data of the electricity rate system by time period from the electricity rate providing server 200 via the communication network, and stores the data in the electricity rate actual data storage unit 14'. The actual data of the electricity rate system acquired here is, for example, data of transaction prices (contract prices) previously determined by JEPX.
[0112] The price data acquisition unit 4B corresponds to the electricity price prediction unit in the claims, and similarly to the price data acquisition unit 4 shown in Fig. 2, acquires electricity price data at each time of the prediction target period from the electricity price providing server 200 via a communication network. As described above, the electricity price data acquired here is the next day's transaction price data provided by JEPX, and this can be treated as a predicted value for the prediction target period (hereinafter referred to as an electricity price prediction value).
[0113] The electricity rate prediction error calculation unit 4C calculates the prediction error of the electricity rate expected at each time of the prediction period (hereinafter referred to as the electricity rate prediction error) based on the past electricity rate actual values stored in the electricity rate actual data storage unit 14'. That is, the electricity rate prediction error calculation unit 4C calculates the electricity rate prediction error for each of the times t1 to t48, which are 30 minutes apart during the prediction period. The electricity rate prediction error calculation unit 4C calculates at least one, and preferably multiple, electricity rate prediction errors for each time.
[0114] The separate electricity price prediction value calculation unit 4D calculates separate electricity price prediction values at each time of the prediction target period using the electricity price prediction value acquired by the price data acquisition unit 4B and the electricity price prediction error calculated by the electricity price prediction error calculation unit 4C. The separate electricity price prediction value calculation unit 4D calculates at least one, and preferably multiple, separate electricity price prediction values for each time.
[0115] The charge / discharge plan creation unit 5' uses multiple electricity fee prediction values obtained by the fee data acquisition unit 4B and the separate electricity fee prediction value calculation unit 4D to perform optimization calculations under constraint conditions set for the power generation prediction value, demand prediction value, and state of the storage batteries 113, 114, such that each predicted value calculated by the power generation prediction unit 1B, separate power generation prediction value calculation unit 1D, power demand prediction unit 2B, separate demand prediction value calculation unit 2D, vehicle state prediction unit 3B, and separate consumption prediction value calculation unit 3D and the state of the storage batteries 113, 114 satisfy the constraint conditions, while reducing the power procurement fee for purchasing electricity without causing a shortage of the amount of storage electricity required for use as vehicle mobility.
[0116] In the above embodiment, regarding the battery deterioration-related constraint condition of (Equation 10) and (Equation 11) that the stored power of the storage batteries 113, 114 is kept above a predetermined lower limit value and below a predetermined upper limit value, the lower limit value set in a predetermined time period in the prediction target period may be set to be larger than the lower limit values set in other time periods. The predetermined time period is set to be a time period in the latter half of the prediction target period. In this way, it is possible to prevent the creation of an unnatural charge / discharge plan that reduces the objective function by discharging in the latter half of the prediction target period. In addition, it is also possible to have a role of a safety margin, such as increasing the stored power of the in-vehicle storage battery 113 before the time when the vehicle starts to be used as a mobility.
[0117] Furthermore, in the above embodiment, when the charge / discharge plan creation unit 5 performs optimization calculations, with regard to the battery deterioration-related constraint conditions of (Equation 10) and (Equation 11) that the retained power of the storage batteries 113, 114 is kept above a predetermined lower limit value and below a predetermined upper limit value, even if the retained power of the storage batteries 113, 114 falls below the lower limit value, if the period during which it is below the lower limit value is within a predetermined time period, the current retained power may be treated as the lower limit value during the predetermined time period.
[0118] In the above embodiment, the batch processing is executed at the start of the prediction period, but the present invention is not limited to this. For example, the batch processing may be executed at a timing a predetermined time before the start of the prediction period. In addition, the timing of the batch processing may be arbitrarily specified by the user.
[0119] In the above embodiment, a Home Energy Management System (HEMS) is used as an example of the EMS 101, and an example of predicting whether a vehicle is at home or away is described, but the present invention is not limited to this. For example, the present invention can be similarly applied to an xEMS such as a Building Energy Management System (BEMS) or a Factory Energy Management System (FEMS).
[0120] In addition, the above-mentioned embodiments are merely examples of the implementation of the present invention, and the technical scope of the present invention should not be interpreted as being limited thereby. In other words, the present invention can be implemented in various forms without departing from the gist or main characteristics thereof. [Explanation of symbols]
[0121] 1A Power generation performance data recording section 1B Power Generation Prediction Section 1C Power generation forecast error calculation section 1D power generation forecast calculation section 2A Demand performance data recording section 2B Power Demand Forecasting Department 2C Demand forecast error calculation part 2D demand forecast calculation section 3A Vehicle usage data recording section 3B Vehicle state prediction unit 3C Consumption prediction error calculation section 3D consumption forecast calculation section 4. Fee Data Acquisition Section 4A Electricity charge data recording section 4B Fee data acquisition section 4C Electricity price prediction error calculation section 4D Electricity Charge Forecast Calculation Section 5,5' Charging and discharging planning department 6. Charge / discharge control unit 31 Vehicle usage status prediction unit 32 Pattern Extraction Section 33 Consumption forecast value calculation unit 100,100' power management equipment 101 EMS 102 V2H System 111 Solar power generation equipment 112 Power load 113 Vehicle storage battery 114 Residential storage batteries
Claims
1. A power management system that creates a charge / discharge plan for a storage battery based on a predicted power generation by a power generation device, a predicted power demand by a power load, a charge / discharge amount of a storage battery including an on-board storage battery mounted on a vehicle, and a time-of-day electricity rate system, a power generation prediction unit for acquiring a predicted value of a power generation amount at each time of a prediction target period; a power generation prediction error calculation unit that calculates a prediction error of the amount of power generation expected at each time of the prediction target period based on a past actual value of the amount of power generation; a separate power generation forecast value calculation unit that calculates a separate power generation forecast value at each time of the prediction target period by using the power generation forecast value acquired by the power generation power prediction unit and the power generation forecast error calculated by the power generation forecast error calculation unit; an electricity demand prediction unit that obtains a predicted value of an electricity demand amount at each time of the prediction target period; a demand forecast error calculation unit that calculates a forecast error of the amount of energy demand expected at each time of the forecast target period based on an actual value of the amount of energy demand in the past; a separate demand forecast value calculation unit that calculates a separate demand forecast value at each time of the prediction period by using the demand forecast value acquired by the power demand forecasting unit and the demand forecast error calculated by the demand forecast error calculation unit; and a vehicle state prediction unit that obtains a predicted value of a usage state of the vehicle as a mobility and a predicted value of a power consumption amount of the vehicle-mounted storage battery at each time of the prediction target period; a consumption prediction error calculation unit that calculates a prediction error of the power consumption expected at each time point during the prediction target period based on a past actual value of the power consumption of the vehicle-mounted storage battery; a separate consumption prediction value calculation unit that calculates a separate consumption prediction value at each time of the prediction target period by using the consumption prediction value acquired by the vehicle state prediction unit and the consumption prediction error calculated by the consumption prediction error calculation unit; and a charge / discharge plan creation unit that creates a charge / discharge plan for the storage battery by performing an optimization calculation to reduce a power procurement fee for purchasing power without causing a shortage of a storage amount required for use as mobility of the vehicle, under constraint conditions set for the power generation forecast value, the demand forecast value, and a state of the storage battery, while the plurality of power generation forecast values obtained by the power generation forecast unit and the separate power generation forecast value calculation unit, the plurality of demand forecast values obtained by the power demand forecast unit and the separate demand forecast value calculation unit, the plurality of consumption forecast values obtained by the vehicle state prediction unit and the separate consumption forecast value calculation unit, and the state of the storage battery satisfy the constraint conditions, using information on the electricity rate system by time period in the prediction period. A power management system comprising:
2. The vehicle state prediction unit is a vehicle usage state prediction unit that predicts a plurality of patterns of usage states of the vehicle as a form of mobility at each time of the prediction target period and calculates an occurrence probability indicating a likelihood of each pattern occurring; a pattern extraction unit that extracts one usage state prediction pattern from the plurality of usage state prediction patterns generated by the vehicle usage state prediction unit based on the occurrence probability; a consumption prediction value calculation unit that calculates a prediction value of the power consumption of the vehicle-mounted storage battery at each time of the prediction target period based on the usage state prediction pattern extracted by the pattern extraction unit and an actual value of the power consumption of the vehicle-mounted storage battery in the past. The power management system according to claim 1 .
3. The vehicle state prediction unit is a vehicle usage state prediction unit that predicts a plurality of patterns of usage states of the vehicle as a form of mobility at each time of the prediction target period and calculates an occurrence probability indicating a likelihood of each pattern occurring; a pattern extraction unit that extracts a plurality of usage state prediction patterns based on the occurrence probability from the plurality of usage state prediction patterns generated by the vehicle usage state prediction unit; and a consumption prediction value calculation unit that calculates a predicted value of the power consumption of the vehicle-mounted storage battery at each time of the prediction target period for each of a plurality of usage state prediction patterns extracted by the pattern extraction unit, based on the usage state prediction pattern and a past actual value of the power consumption of the vehicle-mounted storage battery. The power management system according to claim 1 .
4. A power management system that creates a charge / discharge plan for a storage battery based on a predicted power generation by a power generation device, a predicted power demand by a power load, a charge / discharge amount of the storage battery, and a time-of-day electricity rate system, a power generation prediction unit for acquiring a predicted value of a power generation amount at each time of a prediction target period; a power generation prediction error calculation unit that calculates a prediction error of the amount of power generation expected at each time of the prediction target period based on a past actual value of the amount of power generation; a separate power generation forecast value calculation unit that calculates a separate power generation forecast value at each time of the prediction target period by using the power generation forecast value acquired by the power generation power prediction unit and the power generation forecast error calculated by the power generation forecast error calculation unit; an electricity demand prediction unit that obtains a predicted value of an electricity demand amount at each time of the prediction target period; a demand forecast error calculation unit that calculates a forecast error of the amount of energy demand expected at each time of the forecast target period based on an actual value of the amount of energy demand in the past; a separate demand forecast value calculation unit that calculates a separate demand forecast value at each time of the prediction period by using the demand forecast value acquired by the power demand forecasting unit and the demand forecast error calculated by the demand forecast error calculation unit; and an electricity rate prediction unit that obtains a predicted value of the electricity rate at each time of the prediction target period; an electricity price prediction error calculation unit that calculates a prediction error of the electricity price expected at each time of the prediction target period based on actual values of past electricity prices; A separate electricity price prediction value calculation unit that calculates a separate electricity price prediction value at each time of the prediction target period using the electricity price prediction value acquired by the electricity price prediction unit and the electricity price prediction error calculated by the electricity price prediction error calculation unit; and a charge / discharge plan creation unit that creates a charge / discharge plan for the storage battery by performing an optimization calculation using the plurality of electricity rate prediction values obtained by the electricity rate prediction unit and the separate electricity rate prediction value calculation unit under constraint conditions set for the power generation prediction value, the demand prediction value, and the state of the storage battery to reduce a power procurement fee for purchasing power while the plurality of power generation prediction values obtained by the power generation prediction unit and the separate power generation prediction value calculation unit, the plurality of demand prediction values obtained by the power demand prediction unit and the separate demand prediction value calculation unit, and the state of the storage battery satisfy the constraint conditions. A power management system comprising:
5. an electricity rate prediction unit that obtains a predicted value of the electricity rate at each time of the prediction target period; an electricity price prediction error calculation unit that calculates a prediction error of the electricity price expected at each time of the prediction target period based on actual values of past electricity prices; Further, a separate electricity price prediction value calculation unit calculates a separate electricity price prediction value at each time of the prediction target period using the electricity price prediction value acquired by the electricity price prediction unit and the electricity price prediction error calculated by the electricity price prediction error calculation unit, The charge / discharge plan creation unit uses the plurality of electricity fee prediction values obtained by the electricity fee prediction unit and the separate electricity fee prediction value calculation unit to perform an optimization calculation for reducing the electricity procurement fee without causing a shortage of the amount of storage required for use as mobility of the vehicle, under constraint conditions set for the power generation prediction value, the demand prediction value, and the state of the storage battery, while the plurality of power generation prediction values obtained by the power generation prediction unit and the separate power generation prediction value calculation unit, the plurality of demand prediction values obtained by the power demand prediction unit and the separate demand prediction value calculation unit, the plurality of consumption prediction values obtained by the vehicle state prediction unit and the separate consumption prediction value calculation unit, and the state of the storage battery satisfy the constraint conditions, thereby creating a charge / discharge plan for the storage battery. The power management system according to claim 1 .
6. A power management system that creates a charge / discharge plan for a storage battery based on a predicted power generation by a power generation device, a predicted power demand by a power load, a charge / discharge amount of a storage battery including an on-board storage battery mounted on a vehicle, and a time-of-day electricity rate system, a power generation prediction unit for acquiring a predicted value of a power generation amount at each time of a prediction target period; a power generation prediction error calculation unit that calculates a prediction error of the amount of power generation expected at each time of the prediction target period based on a past actual value of the amount of power generation; a separate power generation forecast value calculation unit that calculates a separate power generation forecast value at each time of the prediction target period by using the power generation forecast value acquired by the power generation power prediction unit and the power generation forecast error calculated by the power generation forecast error calculation unit; an electricity demand prediction unit that obtains a predicted value of an electricity demand amount at each time of the prediction target period; a demand forecast error calculation unit that calculates a forecast error of the amount of energy demand expected at each time of the forecast target period based on an actual value of the amount of energy demand in the past; a separate demand forecast value calculation unit that calculates a separate demand forecast value at each time of the prediction period by using the demand forecast value acquired by the power demand forecasting unit and the demand forecast error calculated by the demand forecast error calculation unit; and a vehicle usage state prediction unit that predicts a plurality of patterns of usage states of the vehicle as a form of mobility at each time of the prediction target period and calculates an occurrence probability indicating a likelihood of each pattern occurring; a pattern extraction unit that extracts a plurality of usage state prediction patterns based on the occurrence probability from the plurality of usage state prediction patterns generated by the vehicle usage state prediction unit; a consumption prediction value calculation unit that calculates a prediction value of the power consumption of the on-board storage battery at each time of the prediction target period for each of a plurality of usage state prediction patterns extracted by the pattern extraction unit, based on the usage state prediction pattern and a past actual value of the power consumption of the on-board storage battery; and a charge / discharge plan creation unit that creates a charge / discharge plan for the storage battery by performing an optimization calculation to reduce a power procurement fee for purchasing power without causing a shortage of a storage amount required for use as mobility of the vehicle, under constraint conditions set for the power generation forecast value, the demand forecast value, and a state of the storage battery, while the multiple power generation forecast values obtained by the power generation forecast unit and the separate power generation forecast value calculation unit, the multiple demand forecast values obtained by the power demand forecast unit and the separate demand forecast value calculation unit, the multiple consumption forecast values obtained by the consumption forecast value calculation unit, and the state of the storage battery satisfy the constraint conditions, using information on the electricity rate system by time period in the prediction period. A power management system comprising:
7. The power management system described in any one of claims 1 to 6, characterized in that the charge / discharge plan creation unit performs an optimization calculation to reduce the power procurement fee under a plurality of constraint conditions set with respect to the power generation forecast value, the demand forecast value, and the state of the storage battery, and if a solution that satisfies all of the plurality of constraint conditions is not obtained, relaxes at least one of the plurality of constraint conditions and performs an optimization calculation again to reduce the power procurement fee under the relaxed constraint condition.
8. the plurality of constraint conditions include a peak value-related constraint condition for keeping a peak value of the amount of power usage due to the purchased power equal to or less than a target peak value, and a battery deterioration-related constraint condition for suppressing deterioration of the storage battery due to charging and discharging; The charge / discharge plan creation unit assigns a higher priority to the peak value-related constraint condition than to the battery deterioration-related constraint condition, and repeats the optimization calculation while gradually relaxing the multiple constraint conditions according to the priority until a solution that satisfies the constraint conditions is obtained. The power management system according to claim 7 .
9. The power management system described in claim 8, characterized in that the battery deterioration-related constraint condition includes a constraint condition that the stored power of the storage battery is kept above a predetermined lower limit value and below a predetermined upper limit value, and the lower limit value set for a predetermined time period within the prediction period is set to be larger than the lower limit values set for other time periods.
10. The power management system described in claim 8, characterized in that the battery deterioration-related constraint condition includes a constraint condition that the stored power of the storage battery be kept above a predetermined lower limit value and below a predetermined upper limit value, and even if the stored power of the storage battery falls below the lower limit value, if the period during which it is below the lower limit value is within a predetermined time, the current stored power is treated as the lower limit value during the predetermined time period.
11. A charge / discharge plan creation method for creating a charge / discharge plan for a storage battery based on a predicted power generation by a power generation device, a predicted power demand by a power load, a charge / discharge amount of a storage battery including an on-board storage battery mounted on a vehicle, and a time-of-day electricity rate system, comprising: A step in which a power generation prediction unit of a power management device obtains a predicted value of a power generation amount at each time of a prediction target period; A step in which a power generation prediction error calculation unit of the power management device calculates a prediction error of the amount of power generation expected at each time of the prediction target period based on an actual value of the amount of power generation in the past; a step of a separate power generation forecast value calculation unit of the power management device calculating a separate power generation forecast value at each time of the prediction target period using the power generation forecast value acquired by the power generation forecast unit and the power generation forecast error calculated by the power generation forecast error calculation unit; A step in which a power demand prediction unit of the power management device obtains a predicted value of the power demand at each time of the prediction target period; A step in which a demand prediction error calculation unit of the power management device calculates a prediction error of the amount of power demand expected at each time of the prediction target period based on an actual value of the amount of power demand in the past; A step in which a separate demand forecast value calculation unit of the power management device calculates a separate demand forecast value at each time of the prediction target period using the demand forecast value acquired by the power demand forecasting unit and the demand forecast error calculated by the demand forecast error calculation unit; A step in which a vehicle state prediction unit of the power management device acquires a predicted value of a usage state of the vehicle as a mobility and a predicted value of a power consumption amount of the in-vehicle storage battery at each time of the prediction target period; A consumption prediction error calculation unit of the power management device calculates a prediction error of the power consumption expected at each time of the prediction target period based on an actual value of the power consumption of the vehicle-mounted storage battery in the past; A step in which a separate consumption prediction value calculation unit of the power management device calculates a separate consumption prediction value at each time of the prediction target period using the consumption prediction value acquired by the vehicle state prediction unit and the consumption prediction error calculated by the consumption prediction error calculation unit; and a charge / discharge plan creation unit of the power management device performs an optimization calculation to create a charge / discharge plan for the storage battery by using information on the time-of-day electricity rate system in the prediction period under constraint conditions set for the power generation forecast value, the demand forecast value, and the state of the storage battery, whereby a plurality of the power generation forecast values obtained by the power generation forecast unit and the separate power generation forecast value calculation unit, a plurality of the demand forecast values obtained by the power demand forecast unit and the separate demand forecast value calculation unit, a plurality of the consumption forecast values obtained by the vehicle state prediction unit and the separate consumption forecast value calculation unit, and the state of the storage battery satisfy the constraint conditions, without causing a shortage of the amount of stored power required for use as mobility of the vehicle. A charge and discharge plan creation method comprising:
12. A method for creating a charge / discharge plan for a storage battery based on a predicted power generation by a power generation device, a predicted power demand by a power load, a charge / discharge amount of the storage battery, and a time-of-day electricity rate system, comprising: A step in which a power generation prediction unit of a power management device obtains a predicted value of a power generation amount at each time of a prediction target period; A step in which a power generation prediction error calculation unit of the power management device calculates a prediction error of the amount of power generation expected at each time of the prediction target period based on an actual value of the amount of power generation in the past; a step of a separate power generation forecast value calculation unit of the power management device calculating a separate power generation forecast value at each time of the prediction target period using the power generation forecast value acquired by the power generation forecast unit and the power generation forecast error calculated by the power generation forecast error calculation unit; A step in which a power demand prediction unit of the power management device obtains a predicted value of the power demand at each time of the prediction target period; A step in which a demand prediction error calculation unit of the power management device calculates a prediction error of the amount of power demand expected at each time of the prediction target period based on an actual value of the amount of power demand in the past; A step in which a separate demand forecast value calculation unit of the power management device calculates a separate demand forecast value at each time of the prediction target period using the demand forecast value acquired by the power demand forecasting unit and the demand forecast error calculated by the demand forecast error calculation unit; An electricity rate prediction unit of the power management device acquires a predicted value of an electricity rate at each time of the prediction target period; A step in which an electricity rate prediction error calculation unit of the power management device calculates a prediction error of the electricity rate expected at each time of the prediction target period based on actual values of past electricity rates; A step in which a separate electricity price prediction value calculation unit of the power management device calculates a separate electricity price prediction value at each time of the prediction target period using the electricity price prediction value acquired by the electricity price prediction unit and the electricity price prediction error calculated by the electricity price prediction error calculation unit; and a charge / discharge plan creation unit of the power management device performs an optimization calculation using the plurality of electricity price prediction values obtained by the electricity price prediction unit and the separate electricity price prediction value calculation unit under constraint conditions set for the power generation prediction value, the demand prediction value, and the state of the storage battery, in which the plurality of power generation prediction values obtained by the power generation prediction unit and the separate power generation prediction value calculation unit, the plurality of demand prediction values obtained by the power demand prediction unit and the separate demand prediction value calculation unit, and the state of the storage battery satisfy the constraint conditions, thereby reducing a power procurement fee for purchasing power. A charge and discharge plan creation method comprising:
13. A method for creating a charge / discharge plan for a storage battery based on a predicted power generation by a power generation device, a predicted power demand by a power load, a charge / discharge amount of a storage battery including an on-board storage battery mounted on a vehicle, and a time-of-day electricity rate system, comprising: A step in which a power generation prediction unit of a power management device obtains a predicted value of a power generation amount at each time of a prediction target period; A step in which a power generation prediction error calculation unit of the power management device calculates a prediction error of the amount of power generation expected at each time of the prediction target period based on an actual value of the amount of power generation in the past; a step of a separate power generation forecast value calculation unit of the power management device calculating a separate power generation forecast value at each time of the prediction target period using the power generation forecast value acquired by the power generation forecast unit and the power generation forecast error calculated by the power generation forecast error calculation unit; A step in which a power demand prediction unit of the power management device obtains a predicted value of the power demand at each time of the prediction target period; A step in which a demand prediction error calculation unit of the power management device calculates a prediction error of the amount of power demand expected at each time of the prediction target period based on an actual value of the amount of power demand in the past; A step in which a separate demand forecast value calculation unit of the power management device calculates a separate demand forecast value at each time of the prediction target period using the demand forecast value acquired by the power demand forecasting unit and the demand forecast error calculated by the demand forecast error calculation unit; a step in which a vehicle usage state prediction unit of the power management device predicts a plurality of patterns of usage states of the vehicle as a mobility at each time of the prediction target period, and calculates an occurrence probability indicating a likelihood of each usage state pattern occurring; a pattern extraction unit of the power management device extracting any one of a plurality of usage state prediction patterns from a plurality of usage state prediction patterns generated by the vehicle usage state prediction unit based on the occurrence probability; a consumption prediction value calculation unit of the power management device calculating a prediction value of the power consumption of the on-board storage battery at each time of the prediction target period for each of a plurality of usage state prediction patterns extracted by the pattern extraction unit, based on the usage state prediction pattern and an actual value of past power consumption of the on-board storage battery; and a charge / discharge plan creation unit of the power management device performs an optimization calculation to create a charge / discharge plan for the storage battery by using information on the time-of-day electricity rate system in the prediction period, under constraint conditions set for the power generation forecast value, the demand forecast value, and the state of the storage battery, so that the multiple power generation forecast values obtained by the power generation forecast unit and the separate power generation forecast value calculation unit, the multiple demand forecast values obtained by the power demand forecast unit and the separate demand forecast value calculation unit, the multiple consumption forecast values obtained by the consumption forecast value calculation unit, and the state of the storage battery satisfy the constraint conditions, and reduce a power procurement fee for purchasing power without causing a shortage of the amount of storage required for use as mobility of the vehicle. A charge and discharge plan creation method comprising:
Citation Information
Patent Citations
Crevice corrosion preventing method for titanium structure
JP1981072186A
Polyphenylene ether composition
JP1985053554A
Charge / discharge control program, charge / discharge control method, and charge / discharge control device
JP2016073113A
Power load leveling device
JP2016116401A
Power generation plan creation apparatus, power generation plan creation program, and power generation plan creation method
JP2017050972A