Automatic lowering method and system for crane

The automatic crane lowering method and system address manual operation challenges by using positional reference points and automated controls to ensure safe and efficient movement of suspended loads, reducing errors and optimizing the lowering process.

JP7565790B2Active Publication Date: 2024-10-11KITAGAWA IRON WORKS CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2020217084
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-12-25
Publication Date
2024-10-11
Estimated Expiration
2040-12-25

AI Technical Summary

Technical Problem

Existing crane operations for moving suspended loads from a lowering start point to a lowering end point are prone to errors due to manual operation, leading to issues like load swinging, sudden stops, cargo collapse, collisions, and inefficiencies, especially when performed by inexperienced workers.

Method used

An automatic crane lowering method and system that uses positional information comparison with pre-stored reference points to automatically control the lowering process, ensuring safe and efficient movement of suspended loads by integrating sensors, encoders, and a control device to manage motors based on pass/fail criteria.

Benefits of technology

Ensures safe and efficient crane operation by reducing human error, preventing collisions, and optimizing the lowering process without relying on worker judgment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007565790000001
    Figure 0007565790000001
  • Figure 0007565790000002
    Figure 0007565790000002
  • Figure 0007565790000003
    Figure 0007565790000003
Patent Text Reader

Abstract

To provide an automatic crane lowering method that ensures safety and automatic operation in lowering a crane, thereby enabling efficient operation without depending on operators.SOLUTION: There is provided an automatic crane lowering method that automatically moves a suspended load from a start point of lowering to an end point of lowering. The crane has a jib that can be raised and lowered, and the load is suspended from an end of the jib by a wire. The automatic crane lowering method sequentially performs: a step a of comparing position information as of when the suspended load is moved to near the start point of lowering, with first reference position information stored in advance; a step b of automatically lowering the suspended load when the comparison result satisfies a pre-stored start point acceptance criterion; a step c of comparing position information as of when the suspended load is moved to near the end point of lowering, with second reference position information stored in advance; and a step d of automatically stop lowering the suspended load when the comparison result satisfies a pre-stored end point acceptance criterion.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a method and system for automatically lowering a crane. [Background technology]

[0002] Conventionally, there are cranes known as climbing cranes that rotate a load via a jib (also called a boom) that can be raised and lowered (see, for example, Patent Document 1). With this type of crane, the operator repeatedly lowers the lifted load from the start point of lowering to the end point of lowering, mainly manually.

[0003] Specifically, the load to be lifted is moved to the start point of lowering by driving the raising and lowering motor to raise and lower the jib, and the slewing motor to rotate via the jib, and then the lowering motor is driven to move the load to the end point of lowering while appropriately changing the lowering speed at the operator's discretion depending on the load of the load, etc. Such work often requires operators to manually move the same type or weight of suspended load repeatedly all day long. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2018-184269 A Summary of the Invention [Problem to be solved by the invention]

[0005] However, there are various ways to move (lower) a suspended load from the lowering start point to the lowering end point, depending on the worker. Specifically, the load may swing due to the worker going too fast, starting suddenly, or stopping suddenly. This may also lead to the load collapsing, collision, or damage to the inside of the crane body. In addition, since the work is simple and repetitive, workers may make mistakes due to lack of concentration. Furthermore, inexperienced workers may take longer to work than experienced workers, and may be less efficient.

[0006] The present invention has been made in consideration of the above circumstances, and has an object to provide a method for automatically lowering a crane, which ensures safety and allows the work to be done efficiently without relying on an operator. [Means for solving the problem]

[0007] According to the present invention, there is provided an automatic lowering method for a crane that automatically moves a load from a lowering start point to a lowering end point, comprising the steps of: The crane is equipped with a retractable jib. The load is suspended by a wire from the tip of the jib. There is provided a method for automatically lowering a crane, which comprises sequentially carrying out the following steps a to d. Step a: comparing position information when the load is moved to the vicinity of the lowering start point with first reference position information stored in advance; Step b: If the start point is within the pre-stored pass / fail criteria, the load is automatically lowered. Step c: comparing the position information when the load is moved to the vicinity of the end point of lowering with pre-stored second reference position information; Step d: If the pre-stored end point pass / fail criteria are met, the automatic lowering of the load is completed.

[0008] According to another aspect of the present invention, there is provided an automatic lowering system for a crane that automatically moves a load from a lowering start point to a lowering end point, the system comprising a lowering start point acquisition means, a lowering end point acquisition means, and a control device, the crane comprising a lowering device, the lowering start point acquisition means being configured to be able to acquire position information in the vicinity of the lowering start point, the lowering end point acquisition means being configured to acquire position information in the vicinity of the lowering end point, the control device comprising a memory unit and a control unit, the memory unit storing first reference position information serving as a reference for the position information of the lowering start point, second reference position information serving as a reference for the position information of the lowering end point, and the position information by the lowering start point acquisition means. In one embodiment, a control unit stores in advance a start point pass / fail criterion which is the pass / fail criterion for the start of lowering and an end point pass / fail criterion which is the pass / fail criterion for the position information by the lowering end point acquisition means, and generates a lowering start signal when the position information by the lowering start point acquisition means for a suspended load that has moved to the lowering start point falls within the start point pass / fail criterion, and generates a lowering end signal when the position information by the lowering end point acquisition means during automatic lowering falls within the end point pass / fail criterion, and controls the lowering device to drive when the crane receives the lowering start signal and to stop when the crane receives the lowering end signal.

[0009] The method and system for automatically lowering a crane according to the present invention can provide a method and system that can perform the work efficiently without relying on an operator by performing the work automatically while ensuring safety. [Brief description of the drawings]

[0010] [Figure 1] Schematic overall configuration diagram of the automatic lowering system. [Diagram 2] FIG. 2 is a front view showing an example of a crane. [Diagram 3] Flow diagram of the preliminary stages during implantation. [Figure 4] Flow diagram of automatic lowering when landing. [Diagram 5] Flow diagram of the preliminary stage when hollow. [Figure 6] Flow diagram of automatic lowering when hollow. [Figure 7]FIG. 2 is a schematic overall configuration diagram showing a modified example of FIG. 1. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described with reference to the drawings. Various characteristic features shown in the following embodiments can be combined with each other.

[0012] 1. Overall structure In Section 1, we will explain the overall configuration of an automatic lowering system 1 for a crane that automatically moves a load from a lowering start point to a lowering end point. Figure 1 is a schematic overall configuration diagram of the automatic lowering system 1. In the figure, solid arrows indicate signals sent to a control device 40, and dashed arrows indicate signals sent from the control device 40. The automatic lowering system 1 is a system that comprises a crane 10, a control device 40, an input device that transmits information obtained to the control device 40, and an output device that executes commands output from the control device 40, all of which are electrically connected. In this automatic lowering system 1, the operation of the crane 10 is controlled by processing a signal received by the control device 40 in the control unit 41. For example, the input devices include the operator operation unit 20, which is a device operated by the operator, and sensors and devices that acquire or monitor the status of the crane, such as a load cell 26, a lowering start point acquisition means 50, and a lowering end point acquisition means 51.

[0013] <Worker operation section> The operator operation unit 20 generates signals to be sent to the control device through operation by the operator, and includes an operation device 21, a start point memory button 22, an end point memory button 23, an automatic operation button 24, an input device 25, and the like. Furthermore, the operator operation unit 20 may employ interfaces such as a mouse, keyboard, touch panel, voice input device, etc. as needed, as well as button switches, lever switches, etc. that are typically used on the crane 10.

[0014] <Operating device> The operation device 21 corresponds to an operation lever or the like, and an operator arbitrarily issues a speed command to the control device 40 by using the operation lever or the like.

[0015] <Start point memory button> When an operator presses the start point memory button 22, the input information is transmitted to the control device 40. In this embodiment, when the load is at a position that is a reference for the suspension start point, pressing the start point memory button 22 causes the position to be stored in the memory unit 41 as first reference position information.

[0016] <End point memory button> When an operator presses the end point memory button 23, the input information is transmitted to the control device 40. In this embodiment, when the load is at a position that is a reference for the suspension end point, pressing the end point memory button 23 causes the position to be stored in the memory unit 41 as second reference position information.

[0017] <Automatic operation execution button> The automatic operation execution button 24 is a button that, when pressed by an operator, automatically moves the load from the lowering start point to the lowering end point.

[0018] Input Device The input device 25 corresponds to a touch panel or the like, and upon receiving input information (commands) from an operator, transmits the input information to the control device 40.

[0019] <Load cell> The load cell 26 measures the load of the suspended load. For example, the load cell 26 is attached to the jib top, detects the magnitude of the load of the suspended load suspended from the jib top, and transmits a corresponding control signal to the control device 40.

[0020] <Method of obtaining lowering start point> The lowering start point acquisition means 50 is configured to be able to receive information on the current position of the load. Specifically, this is the count number of pulses transmitted from the hoisting encoder 33 attached to the hoisting motor 32 and the rotation encoder 35 attached to the rotation motor 34. This makes it possible to obtain detailed position information.

[0021] <Method of obtaining end point of lowering> The lowering end point acquisition means 51 is configured to be able to receive current position information of the load L. Specifically, it is the number of pulse counts transmitted from a lowering encoder 31 attached to a lowering motor 30 (an example of a lowering device). This makes it possible to obtain detailed position information. Preferably, the number of counts of pulses sent from the elevation and rotation encoders 33, 35 may be included.

[0022] <Lowering, raising and lowering, and turning motor> The lowering, hoisting, and swinging motors 30, 32, and 34 operate and drive the crane 10 by driving the motors. Strictly speaking, it should be noted that power of a given voltage and frequency is transmitted to each motor via an inverter (not shown). This concept is also included in the outline of the description. Note that although an operator can transmit a desired value to each motor via the operating device 21, in the automatic lowering system 1 of this embodiment, this is realized by transmitting a desired value to each motor by pressing the automatic operation execution button 24.

[0023] <crane> The form of the crane 10 is not particularly limited, but for example, a climbing crane as shown in Fig. 2 may be adopted. Fig. 2 is a front view showing an example of a crane. Specifically, the crane 10 has a mast body 12 attached to the top of a base frame 11, and a crane body 13 installed on the top of the mast body 12. Preferably, the mast body 12 is made up of a plurality of masts, which are removably connected together in a vertically upward direction.

[0024] The crane body 13 is mainly composed of a rotating body 14, a jib 15, a hook 16, etc. The rotating body 14 is rotatably supported by a rotating bearing (not shown) provided at the top of the mast body 12 via a rotating motor 34. The jib 15 is supported on the rotating body 14 so as to be capable of being raised and lowered by a raising and lowering motor 32 . The hook 16 is attached to one end of a wire r that hangs down from the tip 15a of the jib 15. The wire r is used to hoist or lower the hook 16 or the load suspended therefrom by a lowering motor 30 fixed to the rotating body 14. Specifically, the other end of the wire r is attached to a lowering drum (not shown) and hangs down vertically from the tip 15a of the jib 15 via a relay sheave 17 from the lowering drum, and the wire r is wound onto or unwound from the lowering drum by the drive of the lowering motor 30.

[0025] Control Device The control device 40 has a storage unit 41 and a control unit 42, and these components are electrically connected inside the control device 40. Each component will be described in further detail below.

[0026] <Storage section 41> The storage unit 41 is a volatile or non-volatile storage medium that stores various information. It may be implemented as a storage device such as a solid state drive (SSD), or as a memory such as a random access memory (RAM) that stores temporarily required information (arguments, arrays, etc.) related to program operations, or may be a combination of these.

[0027] In particular, the storage unit 41 stores information transmitted from the input devices, such as information received from the load cell 26, the lowering encoder 31, the elevation encoder 33, and the rotation encoder 35.

[0028] In addition, when the operator presses the start point memory button 22 at a position that serves as the reference for the position information of the lowering start point, the pulse count numbers of the elevation encoder 33 and the rotation encoder 35 at that time are stored as the first reference position information.

[0029] Similarly, when the operator presses the end point memory button 23 at a position that serves as the reference for the position information of the lowering end point, the number of pulses counted by the lowering encoder 31 at that time is stored as second reference position information.

[0030] Furthermore, it should be noted that the start point pass / fail criterion G1 and the end point pass / fail criterion G2 are stored in advance in the memory unit 41. The start point pass / fail criterion G1 and the end point pass / fail criterion G2 can be changed as appropriate depending on the size of the crane, the operating speed, or the surrounding conditions (for example, if the site is narrow, the start point pass / fail criterion needs to be stricter).

[0031] As an example, the start point pass / fail criterion G1 in this embodiment is a criterion used to determine whether the difference between the first reference position information and the current position information when the load moves to the start point of lowering through repeated work is within a specified value, and the specified value is within ±3000 pulses.

[0032] Similarly, the end point pass / fail criterion G2 is a criterion used to determine whether the difference between the current position information and the second reference position information when the load moves to the end point of lowering through repetitive work is within a specified value, the specified value being 10,000 pulses.

[0033] <Control Unit> The control unit 42 processes and controls the overall operations related to the control device 40, and is, for example, a central processing unit (CPU) (not shown). The control unit 42 realizes various functions related to the control device 40 by reading out predetermined programs stored in the storage unit 41.

[0034] Specifically, the control unit 42 calculates the difference between the pulse counts of the hoisting and slewing encoders 33, 35, which are the first reference position information, and the current pulse counts of the hoisting and slewing encoders 33, 35 when the load has moved to the lowering start point, and if the differences are within a range of ±3000 pulses each, it makes a pass judgment and generates a control signal for controlling the drive of the lowering motor 30. On the other hand, if they are outside the ±3000 pulse range, it makes a fail judgment and generates an error signal.

[0035] The control unit 42 also calculates a value obtained by subtracting the second reference position information pulse count number of the lowering encoder 33 from the current pulse count number of the lowering encoder 33 when the load has moved to the lowering end point, and if the value is 10,000 pulses or less, it makes a pass judgment and generates a control signal to stop driving the lowering motor 30. On the other hand, if the value is more than 10,000 pulses, it makes a fail judgment and generates a signal to hoist the load by the lowering motor 30.

[0036] 2. Automatic lowering method of the crane In Section 2, we explain the automatic lowering method of the crane to automatically move the load from the lowering start point to the lowering end point. Figure 3 is a flow chart of the pre-stage at the time of landing. In this case, lowering refers to lowering the suspended load in the first embodiment until it hits the ground. Below, each step in FIG. 3 will be explained.

[0037] [start] (Step S101) The worker operates the operating device 21 (driving the lowering, raising and lowering, and turning motors 30, 32, and 34) to move the lifted load to the lowering start point (continue to step S102).

[0038] (Step S102) Next, the worker presses the start point memory button 22 at that position (continue to step S103).

[0039] (Step S103) Next, the memory unit 41 stores the count number of pulses of the elevation and rotation encoders 33, 35 (first reference position information) and the load of the suspended load (continue to step S104).

[0040] (Step S104) Next, the worker presses the automatic lowering button (continues to step S105). At this time, the driving of the hoisting and swinging motors 32, 34 is stopped, and the lowering motor 30 is driven to lower the load. Here, it is preferable that the worker sets the speed in advance using the input device 25 to a low speed.

[0041] (Step S105) Next, it is determined whether the load has come off during lowering. Whether the load has come off may be determined based on the value acquired from the load cell 26. If the value acquired from the load cell 26 is equal to or less than the reference value (Yes), the process proceeds to step S6. On the other hand, if the load has not come off (No), it is determined that the load has not yet touched the ground, and lowering continues. Here, by making the determination based on the load, it is possible to adjust how much slack the wire of the suspended load is to be allowed to be when the load touches the ground.

[0042] (Step S106) Then, it is determined that the machine has reached the bottom, the lowering ends, and the drive of the lowering motor 30 is stopped. This position is also determined as the lowering end point, and the memory unit 41 stores the number of pulse counts of the lowering encoder 31 (second position information).

[0043] After going through this previous process, the operation of automatically driving the load that has been repeatedly hoisted up to the start point of lowering to the end point of lowering will be explained using Figure 4. Figure 4 is a flow chart of automatic lowering when the load lands on the floor. Here, the means for moving the load to the lowering start point may be manual work by an operator or automatic operation. However, when moving the load to the lowering start point, whether manual or automatic, it is difficult to repeatedly move it to the same position due to the weight of the load and external disturbances, and some error occurs. This error is expressed as "near" and is sometimes called "near the lowering start point."

[0044] [start] (Step S111) The worker operates the operating device 21 (driving the lowering, raising and lowering, and turning motors 30, 32, and 34) to move the lifted load to the vicinity of the lowering start point (continued in step S112).

[0045] (Step S112) Next, it is determined whether the current position near the lowering start point is within the start point pass / fail criteria. Specifically, the difference between the pulse count number of the hoisting and slewing encoders 33, 35, which is the first reference position information, and the current pulse count number of the hoisting and slewing encoders 33, 35 when the load moves to the lowering start point is calculated, and if the difference is within the start point pass / fail criteria (for example, within a range of ±3000 pulses each), a pass is determined (Yes) and the process proceeds to step S113. On the other hand, if it is outside the ±3000 pulse range, a fail is determined (No), and the process is returned to step S111 by manual correction by the operator in step S114.

[0046] (Step S113) Next, the worker presses the automatic operation execution button (continues to step S115). At this time, the driving of the hoisting and swinging motors 32, 34 is stopped, and the lowering motor 30 is driven to lower the load. Here, it is preferable that the worker determines the lowering speed in advance using the input device 25. It is also preferable to set the speed so that it is gradually reduced when a predetermined distance is reached.

[0047] The process of step S113 is divided into two routes. Route A is a route in which a determination is made based on the load (step S115), and route B is a route in which a determination is made as to whether the second position information has been reached (step S118). The following will explain each in order.

[0048] Route A (Step S115) Next, it is determined whether the load has come off during lowering. Whether the load has come off may be determined based on the value acquired from the load cell 26. If the value acquired from the load cell 26 is equal to or less than the reference value (Yes), the process proceeds to step S116. On the other hand, if the load has not come off (No), it is determined that the load has not yet touched the ground, and lowering continues. Here, by making the determination based on the load, it is possible to adjust how much slack the wire of the suspended load is to be when the load touches the ground.

[0049] (Step S116) Next, it is determined whether the current position during lowering is within the end point pass / fail criteria. Specifically, a value is calculated by subtracting the number of pulses counted by the lowering encoder 33, which is the second reference position information, from the current number of pulses counted by the lowering encoder 33 when the load moves to the lowering end point, and if the value is within the end point pass / fail criteria (for example, 10,000 pulses or less), a pass determination is made (Yes), and the process proceeds to step S117. On the other hand, if the value is greater than 10,000 pulses, a fail determination is made (No), and the process of step S119 is performed. Specifically, the lowering is temporarily stopped, and the operation of winding up is performed. Here, the 10,000 pulses can determine whether the load is caught at a position different from the lowering end point position (landing position). If a large pulse value is set, it is not possible to determine whether the load is different from the landing position, and on the other hand, if a small pulse value is set, it may be determined that the load is erroneously landed even though it is the landing position. Therefore, it is preferable to appropriately change the set pulse value in consideration of the surrounding environment (whether there is anything around the load that may get caught, etc.). Then, following step S120, it is determined whether the load is normal or not. Here, if the difference between the current load and the load of the suspended load stored in step S103 is within ±0.2t, it is deemed normal (YES), and the process returns to step S113. On the other hand, if the difference is outside ±0.2t, it is still not deemed normal (No), and the process returns to step S119 for hoisting. This allows for an accurate determination to be made even if the crane sways during operation.

[0050] (Step S117) Then, it is determined that the lifter has reached the floor, the lowering operation is completed, and the drive of the lowering motor 30 is stopped.

[0051] Route B Route B is a route to avoid the danger of continuing to lower the load when it cannot be released for some reason. Specifically, it is designed not to lower the load below a set position. (Step S118) Next, it is determined whether the current position during lowering is within the end point pass / fail criteria. Specifically, a value is calculated by subtracting the pulse count number of the lowering encoder 33, which is the second reference position information, from the current pulse count number of the lowering encoder 33 when the load moves to the lowering end point, and if the value is within the end point pass / fail criteria (for example, 3000 pulses or less), a pass judgment is made (Yes) and the process continues to step S117. On the other hand, if the value is greater than 3000 pulses, a fail judgment is made (No) and the process returns to step S113. It should be noted here that in step S116, the judgment value is 10000, whereas in step S118, the judgment value is 3000. This allows for accurate judgment without judging it as erroneous implantation.

[0052] 3. Second embodiment In the third section, a method for controlling the crane 10 according to the second embodiment will be described. Note that a description of the common points with the method for controlling the crane 10 according to the first embodiment will be omitted. Fig. 5 is a flow chart of the first stage when the crane is empty. Note that lowering here refers to lowering the load to a predetermined position in the air, as opposed to the first embodiment, in which the load is lowered until it hits the ground. Below, each step in FIG. 5 will be explained.

[0053] [start] (Step S201) The worker operates the operating device 21 (driving the lowering, raising and lowering, and turning motors 30, 32, and 34) to move the lifted load to the lowering start point (continue to step S202).

[0054] (Step S202) Next, the worker presses the start point memory button 22 at that position (continue to step S203).

[0055] (Step S203) Next, the storage unit 41 stores the count numbers (first reference position information) of the pulses of the elevation and rotation encoders 33, 35 (continue to step S204).

[0056] (Step S204) Next, the worker presses the automatic lowering button (continues to step S205). At this time, the driving of the hoisting and swinging motors 32, 34 is stopped, and the lowering motor 30 is driven to lower the load. Here, it is preferable that the worker sets a low speed in advance using the input device 25. This allows the worker to safely lower the load while checking the surroundings and whether there are any problems such as obstacles on the route.

[0057] (Step S205) Next, it is determined whether or not the target position for transferring the suspended load in midair has been reached. If the target position has been reached (Yes), the process proceeds to step S206. On the other hand, if the target position has not been reached (No), the process returns to step S204.

[0058] (Step S206) Next, it is deemed that the target position in the air has been reached, lowering ends, and driving of the lowering motor 30 is stopped. This position is also regarded as the lowering end point, and the memory unit 41 stores the number of pulse counts of the lowering encoder (second position information).

[0059] After going through this previous process, the operation of automatically driving the load that has been repeatedly hoisted up to the start point of lowering to the end point of lowering will be explained using Figure 6. Figure 6 is a flow chart of automatic lowering when the load lands on the floor. Here, the means for moving the load to the lowering start point may be manual work by an operator or automatic operation. However, when moving the load to the lowering start point, whether manual or automatic, it is difficult to repeatedly move it to the same position due to the weight of the load and external disturbances, and some error occurs. This error is expressed as "near" and is sometimes called "near the lowering start point."

[0060] [start] (Step S211) The worker operates the operating device 21 (driving the lowering, raising and lowering, and turning motors 30, 32, and 34) to move the lifted load to the vicinity of the lowering start point (continued in step S212).

[0061] (Step S212) Next, it is determined whether the current position near the lowering start point is within the start point pass / fail criteria. Specifically, the difference between the pulse count number of the hoisting and slewing encoders 33, 35, which is the first reference position information, and the current pulse count number of the hoisting and slewing encoders 33, 35 when the load moves to the lowering start point is calculated, and if the difference is within the start point pass / fail criteria (for example, within a range of ±3000 pulses each), a pass is determined (Yes) and the process proceeds to step S213. On the other hand, if it is outside the ±3000 pulse range, a fail is determined (No), and the process is returned to step S211 by manual correction by the operator in step S214.

[0062] (Step S213) Next, the operator presses the automatic operation execution button (continues to step S215). At this time, the driving of the elevation and rotation motors 32, 34 is stopped, and the lowering motor 30 is driven to lower the load. Here, it is preferable for the operator to determine the lowering speed in advance using the input device 25. It is also preferable to set the speed so that it is gradually reduced when a predetermined distance is reached. This makes it possible to suppress vibration when the target position is reached, and to safely reach the target position.

[0063] (Step S215) Next, it is determined whether the current position during lowering is within the end point pass / fail criteria. Specifically, a value is calculated by subtracting the pulse count number of the lowering encoder 33, which is the second reference position information, from the current pulse count number of the lowering encoder 33 when the load moves to the lowering end point, and if this value is within the end point pass / fail criteria (for example, 3000 pulses or less), a pass judgment is made (Yes) and the process continues to step S216. On the other hand, if the value is greater than 3000 pulses, a fail judgment is made (No) and the process returns to step S213.

[0064] (Step S216) Then, it is determined that the target position in the air has been reached, the lowering is completed, and the driving of the lowering motor 30 is stopped.

[0065] 4. Variations In Section 4, a modified example of the schematic overall configuration diagram of the automatic lowering system 1 in Fig. 1 will be described. Note that a description of the common parts with the automatic lowering system 1 according to the present embodiment will be omitted. In the automatic lowering system 1 of FIG. 1, a lowering start point acquisition means 50 and a lowering end point acquisition means 51 are provided as input devices. The lowering start point acquisition means 50, for example, counts the number of pulses transmitted from the hoisting encoder 33 attached to the hoisting motor 32 and the rotation encoder 35 attached to the rotation motor . On the other hand, the lowering end point acquisition means 51 is, for example, the count number of pulses transmitted from the lowering encoder 31 attached to the lowering motor 30. In contrast, Fig. 7 shows a modified example of Fig. 1. The difference is that the lowering start point acquisition means 50 and the lowering end point acquisition means 51 are other examples, and specifically, while the lowering start point acquisition means 50 in Fig. 1 is the count number of each pulse from the hoisting and rotation encoders 33, 35, in Fig. 7 it is composed of position information from the GNSS receiver 27 or position information from the jib hoisting angle meter 28 and the jib rotation angle clock 29. In addition, while in Figure 1 the lowering end point acquisition means 51 is the number of pulses counted from the lowering encoder 31, in Figure 7 it is composed of position information from the GNSS receiver 27, or position information from the jib hoisting angle meter 28 and the jib rotation angle clock 29.

[0066] 4. Conclusion As described above, according to the present embodiment, in a method and system for automatically lowering a crane, it is possible to provide a method and system for automatically lowering a crane, which ensures safety and allows work to be performed efficiently without relying on an operator.

[0067] A method for automatically lowering a crane may be provided in the following manner. A method for automatically lowering a crane, the method comprising: first reference position information being position information that serves as a reference for a lowering start point; and second reference position information being position information that serves as a reference for a lowering end point. A method for automatically lowering a crane, comprising the steps of: during the automatic lowering in step b, determining the load of a suspended load; and, if the load is equal to or less than a predetermined value, executing step c. A method for automatically lowering a crane, wherein the automatic lowering in step b is performed by gradually decreasing the speed. A method for automatically lowering a crane, the method comprising: position information near a start point of lowering being a pulse count number of a hoisting and rotation encoder; and position information during the automatic lowering and near an end point of lowering being a pulse count number of a lowering encoder. Of course, this is not the case.

[0068] Finally, although various embodiments of the present invention have been described, these are presented as examples and are not intended to limit the scope of the invention. The novel embodiments can be implemented in various other forms, and various omissions, substitutions, and modifications can be made without departing from the spirit of the invention. The embodiments and their modifications are included within the scope and spirit of the invention, and are included in the scope of the invention and its equivalents described in the claims. [Explanation of symbols]

[0069] 1 Automatic unwinding system 10. Crane 15 Jib 15a Jib tip 21 Operating device 24 Automatic operation execution button 26 Load Cell 30 Lowering motor (lowering device) 31 Lower Encoder 32 Elevation motor 33 Elevation Encoder 34 Swing motor 35 Rotation Encoder 40 Control device 41 Storage section 42 Control section r Wire

Claims

1. A method for automatically lowering a load of a crane, which automatically moves a load from a lowering start point to a lowering end point, comprising the steps of: The crane has a retractable jib, The load is suspended by a wire from the tip of the jib, A method for automatically lowering a crane, comprising the steps of: Step a: comparing position information when the load is moved to the vicinity of the lowering start point with first reference position information stored in advance; Step b: If the start point pass / fail criteria stored in advance are met, the load is automatically lowered; Step c: comparing the position information when the load is moved to the vicinity of the end point of the lowering with pre-stored second reference position information; Step d: If the pre-stored end point pass / fail criteria are met, the automatic lowering of the load is completed.

2. The first reference position information is position information that serves as a reference for the lowering start point, The second reference position information is position information serving as a reference for the end point of the lowering.

2. The method for automatically lowering a crane according to claim 1.

3. During the automatic lowering in step b, the load of the suspended load is judged, and if it is equal to or less than a predetermined value, step c is executed.

3. A method for automatically lowering a crane according to claim 1 or 2.

4. The automatic lowering in step b is performed by gradually decreasing the speed. A method for automatically lowering a crane according to any one of claims 1 to 3.

5. The position information in the vicinity of the lowering start point is the number of pulse counts of the elevation and rotation encoders. During automatic lowering and near the end point of lowering, position information is the number of pulse counts of the lowering encoder. A method for automatically lowering a crane according to any one of claims 1 to 4.

6. An automatic lowering system for a crane that automatically moves a load from a lowering start point to a lowering end point, The system includes a lowering start point acquisition means, a lowering end point acquisition means, and a control device, The crane includes a hoisting device, The lowering start point acquisition means is configured to be capable of acquiring position information in the vicinity of the lowering start point, The lowering end point acquisition means is configured to be capable of acquiring position information in the vicinity of the lowering end point, The control device includes a storage unit and a control unit. the storage unit pre-stores first reference position information serving as a reference for the position information of the lowering start point, second reference position information serving as a reference for the position information of the lowering end point, a start point pass / fail criterion serving as a pass / fail criterion for the position information obtained by the lowering start point acquisition means, and an end point pass / fail criterion serving as a pass / fail criterion for the position information obtained by the lowering end point acquisition means, the control unit generates a lowering start signal when position information obtained by the lowering start point acquisition means for the suspended load that has moved to the lowering start point falls within a start point pass / fail criterion, and generates a lowering end signal when position information obtained by the lowering end point acquisition means during automatic lowering falls within an end point pass / fail criterion; When the crane receives a lowering start signal, the lowering device is driven, and when the crane receives a lowering end signal, the lowering device is controlled to stop. Automatic crane lowering system.

Citation Information

Patent Citations

  • Load elevating device

    JP1993229794A

  • Lifting controller for boom work machine