Hot water supply equipment
The water heater system addresses false failure detections by determining external disturbances during a pre-purge process and confirms fan failure using initial or reference data, ensuring timely maintenance and preventing operational disruptions.
Patent Information
- Application Number
- JP2020212283
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-12-22
- Publication Date
- 2024-10-17
- Estimated Expiration
- 2040-12-22
AI Technical Summary
Existing combustion fan failure detection systems in water heaters are prone to false positives due to external disturbances, such as windy weather, leading to erroneous failure detections.
A water heater system that includes a control section to determine the presence of external disturbances during a pre-purge process, setting the combustion fan to a scavenging rotation speed, and then performing an ignition process only if no disturbance is detected, using initial data or failure reference data to confirm fan failure.
Prevents erroneous failure detections caused by disturbances and ensures timely detection of actual fan failures, allowing for proactive maintenance before the heater becomes inoperable.
Smart Images

Figure 0007568918000001 
Figure 0007568918000002 
Figure 0007568918000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a combustion type hot water heater, and more particularly to a hot water heater configured to detect a sign of failure of a combustion fan that supplies air for combustion before the failure occurs. [Background technology]
[0002] Conventionally, there are known techniques for detecting signs of failure due to deterioration of a combustion fan based on the rotational responsiveness and deviation from the target rotation speed of the combustion fan, such as the water heater in Patent Document 1. As the usable period (lifespan) of the water heater is predicted based on the progression of deterioration of the combustion fan, this is useful for considering countermeasures such as replacing parts or purchasing a new water heater. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2002-149865 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, the rotational responsiveness and deviation from the target rotational speed of the combustion fan are easily affected by external disturbance factors, such as outside air blowing back into the exhaust port when it is windy, which may result in erroneous detection of a malfunction.
[0005] An object of the present invention is to provide a water heating apparatus that can prevent erroneous detection of a malfunction symptom of a combustion fan and can detect a malfunction symptom before a malfunction occurs to prompt inspection. [Means for solving the problem]
[0006] The hot water heater of the invention of claim 1 comprises a combustion section, a combustion fan for supplying combustion air to the combustion section, a heat exchange section, a water supply section, a hot water outlet section, and a control section, and is configured to perform a heating operation in which hot water supplied from the water supply section is heated in the heat exchange section by combustion heat generated in the combustion section, and to supply hot water to the hot water outlet section, and the control section detects and notifies of a failure sign of the combustion fan based on a rotational response and deviation of the combustion fan from a target rotational speed, the heating operation includes a pre-purge process in which the target rotational speed is set to a predetermined scavenging rotational speed and the combustion fan is driven for a predetermined time, and an ignition process in which the target rotational speed is set to a predetermined ignition rotational speed after the pre-purge process and the combustion fan is driven and an ignition operation is performed, and the control section determines the presence or absence of an external disturbance factor based on the rotational response and deviation of the combustion fan from the scavenging rotational speed in the pre-purge process. Then, the ignition process begins. When it is determined that there is no disturbance factor, the failure sign is detected based on the rotation response and deviation of the combustion fan with respect to the ignition rotation speed in the ignition process. and when it is determined that the disturbance factor exists, the failure sign detection is not performed in the ignition process. It is characterized by the following.
[0007] According to the above configuration, the presence or absence of a disturbance factor is determined in the pre-purge process based on the rotation response and deviation of the combustion fan from the target rotation speed during heating operation. Then, the process proceeds to the ignition process, and the ignition operation is performed. When there are no disturbance factors teeth Detects signs of combustion fan failure during the ignition process In addition, when there is a disturbance factor, the failure sign detection is not performed in the ignition process. Therefore, Since the presence or absence of disturbance factors is judged, it is possible to prevent false detection of failure signs caused by disturbances and perform heating operation. Since the combustion fan failure warning is performed every time heating operation is performed, it is difficult to overlook the failure warning. can be .
[0008] The water heating device of the invention of claim 2 is characterized in that, in the invention of claim 1, the control unit stores initial data regarding the rotational response and deviation of the combustion fan at the time of installation, and detects the signs of failure by comparing the current rotational response and deviation of the combustion fan with the initial data. According to the above configuration, since the failure sign of the combustion fan is detected by comparing with the initial data when the hot water heater was first installed, it is possible to detect the failure sign caused by aging of the combustion fan. Therefore, it is possible to prompt an inspection before the hot water heater becomes unable to operate due to a failure of the combustion fan.
[0009] The water heating apparatus of the invention of claim 3 is characterized in that, in the invention of claim 1, the control unit pre-stores failure standard data regarding the rotational responsiveness and deviation of the combustion fan that is judged to be a failure, and detects the signs of failure by comparing the current rotational responsiveness and deviation of the combustion fan with the failure standard data. According to the above configuration, since the malfunction indication of the combustion fan is detected based on the comparison with the malfunction reference data for judging the combustion fan to be malfunctioning, the malfunction indication can be detected before it is judged to be malfunctioning, and therefore, an inspection can be prompted before the hot water supply device becomes unable to operate due to the malfunction of the combustion fan. Effect of the Invention
[0010] According to the water heater of the present invention, erroneous detection of a malfunction symptom of the combustion fan caused by an external disturbance can be prevented, and a malfunction symptom can be detected before a malfunction occurs, and an alert can be issued to prompt inspection. [Brief description of the drawings]
[0011] [Figure 1] 1 is an explanatory diagram of a combustion type hot water supply device according to the present invention. [Diagram 2] 2 is an explanatory diagram of a configuration and communication paths of a control unit of the water heating apparatus; FIG. [Diagram 3] FIG. 4 is a process explanatory diagram of the heating operation of the water heater. [Figure 4] 4 is a flowchart of a combustion fan failure sign detection control according to the first embodiment. [Diagram 5] 10 is a flowchart of a combustion fan failure sign detection control according to the second embodiment. [Figure 6] 13 is a flowchart of a combustion fan failure sign detection control according to the third embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0012] Hereinafter, the mode for carrying out the present invention will be described based on examples. EXAMPLES
[0013] Combustion type hot water heater 1 is usually installed outdoors. As shown in Fig. 1, hot water heater 1 has a combustion section 2, a heat exchange section 3, a water supply section 4, and a hot water outlet section 5, and is configured to perform a heating operation in which clean water supplied from the water supply section 4 is heated in heat exchange section 3 using the combustion heat generated in combustion section 2, and the clean water is output to the hot water outlet section 5. A fuel supply section 6 for supplying fuel gas (natural gas or propane gas) is connected to combustion section 2.
[0014] A combustion fan 8 is provided near the combustion section 2 to supply combustion air to the combustion section 2 and to send the combustion gas, which is a medium for the combustion heat generated by combustion, to the heat exchange section 3 and exhaust it to the outside from the exhaust port 7. The combustion section 2 is divided into a plurality of combustion regions, for example, first to fourth combustion regions 2a to 2d, in which the fuel gas supplied from the fuel supply section 6 is mixed with the combustion air and combusted, and the region in which combustion is performed is changed according to the required combustion amount to generate the required amount of heat.
[0015] The fuel supply unit 6 has first to fourth gas electromagnetic valves 6a to 6d corresponding to the first to fourth combustion regions 2a to 2d, and a fuel flow rate adjustment valve 6e that adjusts the flow rate of fuel supplied to the combustion unit 2. The fuel supply unit 6 adjusts the fuel flow rate and is configured to be able to individually switch between supplying and stopping the fuel gas to these first to fourth combustion regions 2a to 2d.
[0016] The heat exchange section 3 has a first heat exchanger 3a of a fin-and-tube type and a second heat exchanger 3b consisting of multiple hot and cold water passages. The first heat exchanger 3a recovers the sensible heat of the high-temperature combustion gas immediately after combustion to heat hot and cold water. The second heat exchanger 3b recovers the latent heat of the combustion gas whose temperature has been reduced by recovering the sensible heat to heat the clean water.
[0017] In the second heat exchanger 3b, the moisture contained in the combustion gas condenses to produce condensed water. This condensed water contains components of the combustion gas and is highly acidic. Therefore, it is inappropriate to drain it as is, so it is introduced into a neutralization tank 9a that contains, for example, calcium carbonate granules as a neutralizing agent, and is neutralized before being drained. The combustion gas whose temperature has been reduced by recovering latent heat in the second heat exchanger 3b is exhausted to the outside from an exhaust port 7.
[0018] An introduction passage 9b that introduces condensed water that has fallen into a drain pan 3c disposed below the second heat exchanger 3b to the neutralization tank 9a, and a drain passage 9c that drains the neutralized condensed water to the outside of the hot water supply device 1 are connected to the neutralization tank 9a to form a neutralization section 9. A pair of electrodes 9d is provided at the upper end of the neutralization tank 9a as a water level detection means for detecting the water level of the condensed water (predetermined water level). A voltage is applied between the pair of electrodes 9d, and when the water level reaches the predetermined level, a current flows between the pair of electrodes 9d through the condensed water, thereby detecting the predetermined water level.
[0019] The water supply section 4 has a water supply passage 4a that supplies clean water supplied from a clean water source to the second heat exchanger 3b, and a water supply branch passage 4b that branches off from the water supply passage 4a and is equipped with a flow rate adjustment valve 10. The hot water heated in the second heat exchanger 3b is introduced into the first heat exchanger 3a and is further heated to a high temperature. The hot water heated in the first heat exchanger 3a is supplied to the hot water outlet passage 5a. In the hot water outlet section 5 formed by connecting the hot water outlet passage 5a to the water supply branch passage 4b, the heated hot water and clean water are mixed and the temperature is adjusted, and the hot water is supplied to a hot water supply destination, such as a hot water tap 11.
[0020] The first combustion region 2a of the combustion section 2 is the region that is ignited and burned first when the heating operation is started. An ignition device 14 that generates sparks by discharge and a first flame rod 15a that detects the flame of the first combustion region 2a to confirm ignition are disposed at a position corresponding to the first combustion region 2a.
[0021] The second combustion area 2b adjacent to the first combustion area 2a is a flame-transfer area that first expands the combustion area from the first combustion area 2a in order to increase the amount of combustion and increase the generation of combustion heat. A second flame rod 15b for detecting the flame in the second combustion area 2b is disposed at a position corresponding to this second combustion area 2b. The amount of combustion can be increased by expanding the combustion area to the third and fourth combustion areas 2c and 2d. Note that flame rods corresponding to the third and fourth combustion areas 2c and 2d may be disposed in order to detect the flames in the third and fourth combustion areas 2c and 2d.
[0022] A water supply flow rate sensor 4c that detects the flow rate of clean water supplied to the heat exchange section 3, and a water supply temperature sensor 4d that detects the water supply temperature are disposed in the water supply passage 4a. A hot water outlet temperature sensor 5b that detects the outlet temperature of hot water heated in the heat exchange section 3 is disposed in the hot water outlet passage 5a. A hot water temperature sensor 5c that detects the supply temperature of hot water whose temperature has been adjusted by mixing with the clean water is disposed downstream of the connection of the hot water outlet passage 5a with the water supply branch passage 4b.
[0023] The hot water supply device 1 includes a control unit 16 that controls a heating operation to supply hot water at a set hot water supply temperature based on the water supply flow rate, the water supply temperature, and the hot water outlet temperature. The set hot water supply temperature is set by operating an operation terminal 17 connected to the control unit 16. In the heating operation, the control unit 16 calculates the required combustion amount (required heat amount) based on, for example, the set hot water supply temperature, the water supply flow rate, and the water supply temperature. Then, in order to generate the required heat amount, the control unit 16 sets the combustion area to be burned by the combustion unit 2, the target rotation speed of the combustion fan 8, and the fuel flow rate of the fuel supply unit 6. The control unit 16 also adjusts the opening of the flow rate adjustment valve 10 so that the hot water supply temperature approaches the set hot water supply temperature, and adjusts the mixing ratio of the clean water and the heated hot water.
[0024] 2, control unit 16 has calculation unit 16a that executes various control programs, storage unit 16b that stores various control programs, control parameters, etc., and communication unit 16c. Calculation unit 16a controls flow rate control valve 10, valves of fuel supply unit 6, and combustion fan 8 via communication unit 16c that communicates with built-in devices of water heating apparatus 1 and operation terminal 17, and receives detection signals from sensors such as water supply temperature sensor 4d and operation details of operation terminal 17.
[0025] Operation terminal 17 is connected to an external communication network 19 (Internet) via a communication gateway 18 equipped with, for example, a home network construction function. A management server 20 installed by a service shop that installs and maintains water heating apparatus 1 or a manufacturer is connected to this communication network 19 in order to manage information relating to currently installed water heating apparatuses including water heating apparatus 1 and other devices. This enables control unit 16 to communicate with management server 20. Note that communication unit 16c or operation terminal 17 may be directly connected to communication network 19.
[0026] When the water supply flow rate detected by the water supply flow rate sensor 4c becomes equal to or exceeds a predetermined minimum flow rate due to the start of hot water supply use, heating operation is started. As shown in Fig. 3, the heating operation is divided into a pre-purge process, an ignition process, a combustion process, and a post-purge process. In the pre-purge process, the target rotation speed of the combustion fan 8 is set to the scavenging rotation speed (e.g., 3000 rpm), and the combustion fan 8 is driven at the scavenging rotation speed for a predetermined time, the pre-purge time (e.g., 5 seconds). As a result, air remaining in the combustion section 2 and the heat exchange section 3 is exhausted from the exhaust port 7, and the rotation speed of the combustion fan 8, which was stopped, is increased to about the scavenging rotation speed.
[0027] When the target rotation speed is changed in this way, the difference between the actual rotation speed and the target rotation speed is the deviation from the target rotation speed of the combustion fan 8. The larger the deviation is, and the longer the state of a large deviation continues, including the case where the actual rotation speed is not stable, the greater the deterioration in the rotation response of the combustion fan 8.
[0028] Next, the process moves to the ignition process, in which the first gas solenoid valve 12a corresponding to the first combustion region 2a (ignition region) is opened, the target rotation speed is set to the ignition rotation speed (e.g., 2500 rpm), and the combustion fan 8 is driven at the ignition rotation speed. Then, the ignition device 14 is driven to ignite the first combustion region 2a as an ignition operation. When the flame in the first combustion region 2a is detected (ignition is confirmed) by the first flame rod 15a, the process moves to the combustion process.
[0029] Next, in the combustion process, the combustion region of the combustion unit 2, the target rotation speed of the combustion fan 8, and the fuel flow rate of the fuel supply unit 6 are set so that the calculated required heat amount can be supplied. Then, the combustion fan 8 is driven at the target rotation speed, and the fuel gas solenoid valve corresponding to the combustion region is opened to supply fuel at the set fuel flow rate, generating the required heat amount and supplying hot water at the set hot water supply temperature.
[0030] When the water supply flow rate falls below a predetermined minimum flow rate due to the end of hot water supply use, the system transitions to the post-purge process. In the post-purge process, all open gas solenoid valves are closed to stop combustion in the combustion section 2, the target rotation speed is set to the scavenging rotation speed, and the combustion fan 8 is driven at the scavenging rotation speed for the post-purge time (e.g., 10 seconds). This exhausts the combustion gas so that it does not remain in the combustion section 2 and the heat exchange section 3. Finally, the combustion fan 8 is stopped, and the heating operation ends.
[0031] When hot water heating apparatus 1 is installed, a trial run is performed to confirm that hot water heating apparatus 1 operates normally. Control unit 16 stores heating operation data from the trial run in storage unit 16b or a storage area of management server 20 as initial data at the time of installation.
[0032] In heating operation, combustion fan 8 can usually be controlled to roughly match the target rotation speed when hot water supply device 1 is first installed, but aging makes it gradually impossible to adjust the rotation speed to the target speed. When a failure criterion is reached that determines a failure, control unit 16 prohibits heating operation and notifies the user of the failure of combustion fan 8, for example, via operation terminal 17, and notifies the construction and maintenance company of the failure of combustion fan 8 via management server 20. The user or construction and maintenance company that learns of the failure will arrange for inspection and repair.
[0033] Simply notifying that combustion fan 8 has failed would be inconvenient as water heating apparatus 1 cannot be used from the time the failure occurred until inspection and repair are completed, so this system detects signs of failure before combustion fan 8 fails and notifies management server 20 of the presence of signs of failure. This failure sign detection will be explained based on the flowchart of combustion fan failure sign detection control in Figure 4. In the figure, Si (i=1, 2,...) represents a step.
[0034] When the combustion fan failure sign detection control is started together with the start of the heating operation, in S1, the target rotation speed of the combustion fan 8 is set to the scavenging rotation speed, and the process proceeds to S2. In S2, the combustion fan 8 is driven for a pre-purge time (e.g., 5 seconds) so as to reach the target rotation speed, and the actual rotation speed during that time is obtained, and the process proceeds to S3.
[0035] In S3, it is determined whether the difference between the target rotation speed and the actual rotation speed (absolute value of the deviation) is equal to or less than a predetermined reference value (e.g., 200 rpm). For example, when the weather is windy, there is a risk that wind will blow in from the outside into the exhaust port 7 and cause a backflow, hindering the rotation of the combustion fan 8 and causing a disturbance that reduces the actual rotation speed. If such a disturbance factor exists, there is a risk that a sign of failure in the combustion fan 8 will be erroneously detected. S3 is a step for eliminating the risk of this erroneous detection.
[0036] If the determination in S3 is Yes, it is assumed that there is no disturbance factor and the process proceeds to S4. If the determination in S3 is No, it is assumed that there is a disturbance factor, the combustion fan failure sign detection control is terminated, and heating operation is continued. This corresponds to the pre-purge process, and the process proceeds to the next ignition process.
[0037] In S4, the target rotation speed of the combustion fan 8 is set to the ignition rotation speed, and the process proceeds to S5. Because the area in which combustion is performed is limited to the first combustion area 2a (ignition area), and because ignition becomes difficult when the air flow rate is large, the ignition rotation speed is set to a lower rotation speed than the scavenging rotation speed. Then, in S5, the combustion fan 8 is driven for a predetermined time (e.g., 7 seconds) so that the ignition rotation speed becomes the target rotation speed, and the actual rotation speed during that time is obtained, and the process proceeds to S6.
[0038] In S6, it is determined whether the state in which the difference between the target rotation speed and the actual rotation speed exceeds 200 rpm continues for A seconds (e.g., 5 seconds) or more. Since it has already been determined in S3 that there is no disturbance factor, the state in which the deviation from the target rotation speed is large and the duration of that state indicate the current degree of deterioration of the combustion fan 8, whose rotation response has decreased.
[0039] If the determination in S6 is Yes, the process proceeds to S7. In this case, since the deterioration of the combustion fan 8 has progressed to a certain extent, the detection of a failure sign of the combustion fan 8 is notified in S7, the combustion fan failure sign detection control is terminated, and the process proceeds to the combustion process to continue the heating operation. At this time, the detection of a failure sign is notified to, for example, a service shop via the management server 20 to prompt an inspection, but the user can also be notified by, for example, lighting up a lamp on the operation terminal 17.
[0040] On the other hand, if the determination in S6 is No, the deterioration of the combustion fan 8 has not progressed so that it is determined that no signs of failure of the combustion fan 8 have been detected, and the combustion fan failure sign detection control is terminated, and the system proceeds to the combustion process to continue the heating operation. As described above, since the detection of signs of failure of the combustion fan 8 is performed every time the heating operation is performed, it is difficult to overlook the signs of failure of the combustion fan 8. In addition, since the presence or absence of a disturbance factor is determined, and the failure sign detection is performed when there is no disturbance factor, it is possible to prevent erroneous detection of a failure sign due to a disturbance, and the transmission of erroneous detection information of a failure sign to the management server 20 can be prevented, thereby reducing the amount of communication. EXAMPLES
[0041] An example in which the above-mentioned first embodiment is partially modified will be described with reference to the flowchart of Fig. 5. Portions common to the first embodiment will be given the same reference numerals as the first embodiment, and description thereof will be omitted. The configuration of water heater 1 is the same as in Example 1. In the pre-purge step of the heating operation of water heater 1, the presence or absence of a disturbance factor that inhibits the rotation of combustion fan 8 is determined as in S1 to S3, and if there is no disturbance factor and the determination is Yes, the process moves to the ignition step and proceeds to S4. If there is a disturbance factor and the determination is No, the combustion fan failure sign detection control is ended, and the process moves to the ignition step to continue the heating operation.
[0042] In S4, the target rotation speed of the combustion fan 8 is set to the ignition rotation speed, and the process proceeds to S5. Then, in S5, the combustion fan 8 is driven for a predetermined time (e.g., 7 seconds) so that the ignition rotation speed becomes the target rotation speed, and the actual rotation speed during that time is obtained, and the process proceeds to S16.
[0043] In S16, a comparison is made with the initial data to determine whether the duration B seconds during which the difference between the target rotation speed and the actual rotation speed exceeds 200 rpm is longer than X times (e.g., 10 times) the initial data when water heating apparatus 1 was first installed. The initial data is data collected during a trial run of water heating apparatus 1 and stored in control unit 16 (memory unit 16b) or management server 20, and the duration of the state during which the difference between the target rotation speed and the actual rotation speed exceeds 200 rpm in the initial data is, for example, about 0.3 seconds. Because it has already been determined in the pre-purge process that there are no disturbance factors, the state in which the deviation from the target rotation speed is large and its duration represent the current degree of deterioration of combustion fan 8, whose rotational responsiveness has decreased.
[0044] If the determination in S16 is Yes, the process proceeds to S7. In this case, since the combustion fan 8 has deteriorated to a certain extent, the detection of a failure sign of the combustion fan 8 is notified in S7, the combustion fan failure sign detection control is terminated, and the process proceeds to the combustion process to continue the heating operation. At this time, the detection of a failure sign is notified to, for example, a service shop via the management server 20 to prompt an inspection, but the user can also be notified by, for example, lighting up a lamp on the operation terminal 17.
[0045] On the other hand, if the determination in S16 is No, the deterioration of the combustion fan 8 has not progressed so much that it is determined that no signs of failure of the combustion fan 8 have been detected, and the combustion fan failure sign detection control is terminated, and the system transitions to the combustion process to continue the heating operation. As described above, since the failure sign detection of the combustion fan 8 is performed every time the heating operation is performed, it is difficult to overlook the failure sign of the combustion fan 8. In addition, since the presence or absence of a disturbance factor is determined, and failure sign detection is performed when there is no disturbance factor, it is possible to prevent erroneous detection of a failure sign due to a disturbance, and it is possible to reduce the amount of communication by preventing transmission and reception of initial data and erroneous detection information of a failure sign between the management server 20 and the management server 20. EXAMPLES
[0046] An example in which the above-mentioned first embodiment is partially modified will be described with reference to the flowchart of Fig. 6. Portions common to the first embodiment will be given the same reference numerals as the first embodiment, and description thereof will be omitted. The configuration of water heater 1 is the same as in Example 1. In the pre-purge step of the heating operation of water heater 1, the presence or absence of a disturbance factor that inhibits the rotation of combustion fan 8 is determined as in S1 to S3, and if there is no disturbance factor and the determination is Yes, the process moves to the ignition step and proceeds to S4. If there is a disturbance factor and the determination is No, the combustion fan failure sign detection control ends, the process moves to the ignition step, and the heating operation continues.
[0047] In S4, the target rotation speed of the combustion fan 8 is set to the ignition rotation speed, and the process proceeds to S5. Then, in S5, the combustion fan 8 is driven for a predetermined time (e.g., 7 seconds) so that the ignition rotation speed becomes the target rotation speed, and the actual rotation speed during that time is obtained, and the process proceeds to S26.
[0048] In S26, it is determined whether the state where the difference between the failure reference rotation speed and the actual rotation speed is less than 200 rpm continues for C seconds (e.g., 5 seconds) or more as a comparison with the failure reference data. The failure reference rotation speed is preset as the upper and lower limit rotation speeds at which normal ignition and combustion can be performed based on combustion experiments of the combustion unit 2, and is stored in advance in the control unit 16 (storage unit 16b) as, for example, + / - 500 rpm for the ignition rotation speed. Since it has already been determined in the pre-purge process that there is no disturbance factor, the state where the difference between the failure reference rotation speed and the actual rotation speed is small, i.e., the state where the difference between the target rotation speed and the actual rotation speed is large, and the duration of this state represent the current deterioration degree of the combustion fan 8 with reduced rotation response.
[0049] If the duration of the state in which the actual rotation speed is within the range of the upper limit rotation speed and the rotation speed 200 rpm lower than the upper limit, or within the range of the lower limit rotation speed and the rotation speed 200 rpm higher than the lower limit, is C seconds or more, i.e., if the judgment in S26 is Yes, proceed to S7. In this case, since the deterioration of the combustion fan 8 has progressed to a certain extent, the detection of a failure sign of the combustion fan 8 is notified in S7, the combustion fan failure sign detection control is terminated, and the process proceeds to the combustion process to continue the heating operation. At this time, the detection of a failure sign is notified to, for example, a service shop via the management server 20 to encourage inspection, but the user can also be notified by, for example, lighting a lamp on the operation terminal 17.
[0050] On the other hand, if the determination in S26 is No, the deterioration of the combustion fan 8 has not progressed so that it is determined that no signs of failure of the combustion fan 8 have been detected, and the combustion fan failure sign detection control is terminated, and the process proceeds to the combustion step to continue the heating operation. As described above, since signs of failure of the combustion fan 8 are detected every time the heating operation is performed, it is difficult to overlook the signs of failure. In addition, since the presence or absence of a disturbance factor is determined, and the signs of failure are detected when there is no disturbance factor, it is possible to prevent erroneous detection of signs of failure due to disturbance, and it is possible to prevent the transmission of erroneous detection information of signs of failure to the management server 20, thereby reducing the amount of communication.
[0051] The operation and effect of the hot water supply device 1 will be described. Control unit 16 of water heating apparatus 1 determines the presence or absence of a disturbance factor in the pre-purge process based on the rotation response and deviation from the target rotation speed of combustion fan 8 during heating operation, and detects signs of failure of combustion fan 8 in the ignition process if no disturbance factor is present. Therefore, since detection of signs of failure of combustion fan 8 is performed every time heating operation is performed, it becomes difficult to overlook signs of failure, and since the presence or absence of a disturbance factor is determined, erroneous detection of signs of failure due to disturbance can be prevented.
[0052] Furthermore, when detecting signs of failure of combustion fan 8 by comparing with initial data at the time of installation of water heating apparatus 1, it is possible to detect signs of failure due to aging of combustion fan 8. Therefore, an inspection can be encouraged before a failure of combustion fan 8 renders water heating apparatus 1 unable to operate.
[0053] On the other hand, when a failure sign of the combustion fan 8 is detected based on a comparison with failure reference data that indicates a failure of the combustion fan 8, the failure sign can be detected before a failure is determined. Therefore, an inspection can be prompted before a failure of the combustion fan 8 makes it impossible to operate the water heater 1.
[0054] Although the above description is given by taking an example in which the disturbance factor is determined in the pre-purge process and the failure sign is detected in the ignition process, for example, in the post-purge process, after the disturbance factor is determined, the target rotation speed may be changed during the post-purge process to detect the failure sign. Also, the failure sign may be detected based on the number of times the actual rotation speed deviates from the standard during a specified driving time (fluctuation of the actual rotation speed). When the current for driving the combustion fan 8 is increased or decreased so that the actual rotation speed becomes the target rotation speed, the failure sign may be detected based on a comparison of this current value with initial data at the time of installation or with the failure standard.
[0055] In addition, a person skilled in the art can implement the present invention in a form in which various modifications are added to the above-described embodiment without departing from the spirit of the present invention, and the present invention includes such modifications. [Explanation of symbols]
[0056] 1: Hot water supply equipment 2: Combustion section 2a: 1st combustion area (ignition area) 2b: Secondary combustion zone (fire spread zone) 2c: Third combustion zone 2d: 4th combustion zone 3:Heat exchange section 3a: 1st heat exchanger 3b:Second heat exchanger 3c: Drain pan 4: Water supply section 4a: Water supply passage 4b: Water supply branch passage 4c: Water supply flow sensor 4d: Water supply temperature sensor 5: Tap area 5a: Hot water passage 5b: Outlet water temperature sensor 5c: Hot water temperature sensor 6:Fuel supply section 6a to 6d: 1st to 4th gas solenoid valves 6e: Fuel flow control valve 7: Exhaust port 8: Combustion fan 9: Neutralization section 9a: Neutralization tank 9b: Entry passage 9c: Drain passage 10: Flow control valve 11: Hot water tap 14:Ignition device 15a: First frame rod 15b: 2nd frame rod 16: Control section 16a: Arithmetic section 16b: Storage section 16c: Communications Department 17: Operation terminal 18: Communication Gateway 19: Communication network 20: Management server
Claims
1. A hot water supply device comprising a combustion section, a combustion fan for supplying combustion air to the combustion section, a heat exchange section, a water supply section, a hot water outlet section, and a control section, configured to perform a heating operation in which hot water supplied from the water supply section is heated in the heat exchange section by the combustion heat generated in the combustion section, and to supply hot water to the hot water outlet section, and the control section detects and notifies of signs of failure of the combustion fan based on the rotational responsiveness and deviation from a target rotational speed of the combustion fan, The heating operation includes a pre-purge process in which the target rotation speed is set to a predetermined scavenging rotation speed and the combustion fan is driven for a predetermined time, and an ignition process in which the target rotation speed is set to a predetermined ignition rotation speed after the pre-purge process and the combustion fan is driven while an ignition operation is performed, The control unit is configured to determine whether or not there is an external disturbance factor based on the rotational responsiveness and deviation of the combustion fan relative to the scavenging rotation speed in the pre-purge process, and to transition to the ignition process; if it is determined that there is no external disturbance factor, it detects the failure sign in the ignition process based on the rotational responsiveness and deviation of the combustion fan relative to the ignition rotation speed; and if it is determined that there is an external disturbance factor, it does not detect the failure sign in the ignition process.
2. The hot water supply device according to claim 1, characterized in that the control unit stores initial data regarding the rotational response and deviation of the combustion fan at the time of installation, and detects the signs of failure by comparing the current rotational response and deviation of the combustion fan with the initial data.
3. The hot water supply device according to claim 1, characterized in that the control unit pre-stores failure criteria data regarding the rotational response and deviation of the combustion fan that are judged to be faulty, and detects the signs of failure by comparing the current rotational response and deviation of the combustion fan with the failure criteria data.