Railway vehicle test device and test method

The power supply device with synchronized control of multiple power sources and a central system replicates actual railway vehicle power dynamics, addressing the challenge of simulating complex power fluctuations and transitions, ensuring accurate testing of railway vehicle drive systems.

JP7572925B2Active Publication Date: 2024-10-24HITACHI LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2021145126
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-09-07
Publication Date
2024-10-24
Estimated Expiration
2041-09-07

AI Technical Summary

Technical Problem

Existing railway vehicle test devices struggle to simulate the dynamic power fluctuations and transitions that occur when multiple trains operate on the same feeder section, such as sudden power cuts, voltage fluctuations during acceleration and deceleration, and changes in electrification methods, which are crucial for evaluating the impact on vehicle driving.

Method used

A power supply device with multiple power supplies and a central control system that simulates the voltage patterns of overhead contact lines, allowing for synchronized control of power fluctuations and transitions between DC and AC electrification, as well as regenerative braking scenarios, to replicate actual railway vehicle operating conditions.

Benefits of technology

The solution enables realistic simulation of power supply dynamics, including sudden voltage changes and regenerative braking, accurately testing the railway vehicle drive system under various operational conditions, thereby enhancing the reliability and efficiency of railway vehicle drive systems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007572925000001
    Figure 0007572925000001
  • Figure 0007572925000002
    Figure 0007572925000002
  • Figure 0007572925000003
    Figure 0007572925000003
Patent Text Reader

Abstract

To provide a test device for a railway vehicle capable of simulating power supply voltage fluctuation due to disconnection of an overhead wire, switching of DC / AC electrification sections, a light-load regenerative state, etc., and realizing power supply fluctuation of a driving system for the railway vehicle of a test target, in the same environment as an actual vehicle traveling state.SOLUTION: A test device for a railway vehicle comprises one or more combinations of: power supply device for supplying power to test machine controllers for controlling respectively test machines being motors each driven by an inverter; and a controller for the power supply device which controls the power supply device. The one or more combinations are provided in accordance with combinations of the test machine and the test machine controller. The one or more controllers for the power supply device controls a voltage outputted by the power supply device to be a voltage suitable to a power supply pattern of an electric railcar line which supplies the power to the railway vehicle to supply the voltage to the test machine controller, executes simulation according to a condition and a state of the electric railcar line, and performs a test corresponding to a route on which the railway vehicle travels.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a railway vehicle testing device and a testing method for testing a railway vehicle drive system, such as an electric motor driven by a converter or inverter. [Background technology]

[0002] In recent years, efforts have been made to make railway vehicle drive systems more compact and more efficient. At the same time, simulators and test devices that mimic the environment in which actual trains run have been disclosed as test devices for evaluating the performance of drive systems.

[0003] For example, Patent Document 1 discloses a simulator that drives a motor by inverter control according to notch information received from a notch command input, reads various information required for calculations such as rail condition input, power supply condition input from the contact line, car body condition input, and substation condition input, and calculates inverter power, train speed, power and energy amount of a power storage device, and current collector voltage. Also proposed is a test stand that uses an inverter to simulate operation in a DC electrified section, operation in an AC electrified section, and fluctuations in car weight due to passengers on board, and is equipped with control devices, measuring devices, etc. to test the propulsion device of a train. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2006-240547 A [Patent Document 2] US Patent Application Publication No. 2004 / 0163451 Summary of the Invention [Problem to be solved by the invention]

[0005] The test equipment described in Patent Documents 1 and 2 simulates vehicle running conditions, but because it uses only one power supply unit that simulates overhead lines, etc., when multiple trains are present in the same power supply section and multiple trains are running within that section, it is difficult to evaluate the impact on vehicle running of fluctuations in power supply voltage when the trains accelerate or decelerate, or a sudden change in power supply when power is temporarily not supplied to the train, such as when the train's current collector comes off the overhead line.

[0006] When actual trains are running, the power supplied to the train from the electric wires via the current collector while the train is running varies depending on the line conditions and the train running conditions, such as the electrification method (DC or AC), voltage, frequency in the case of AC electrification, separation of the train's current collector from the overhead line, and the case where the overhead line voltage rises when regenerative energy generated by regenerative braking when another train set decelerates cannot be consumed by other train sets (trains) or equipment in the same power feed section (light load regeneration state).In order to realize an environment that is the same as the conditions when an actual train is running, it is necessary to simulate the above power supply fluctuations and create a power supply unit that can be tested.

[0007] In view of the above-mentioned problems, the object of the present invention is to provide a railway vehicle testing device that can simulate power supply voltage fluctuations associated with the acceleration and deceleration of multiple formations (cars) when those formations (cars) are present in the same power supply section, for example, by simulating power supply voltage fluctuations caused by overhead line loss, switching between DC and AC electrified sections, and an increase in overhead line voltage during regenerative braking when a car decelerates (light load regenerative state), and can realize an environment for power supply fluctuations in the railway vehicle drive system being tested that is the same as an actual vehicle running state. [Means for solving the problem]

[0008] In order to achieve the above-mentioned objectives, one representative railway vehicle testing device of the present invention combines a power supply unit that supplies power to a test specimen control device that controls a test specimen, which is an inverter-driven electric motor, with a power supply unit controller that controls the power supply unit, and has one or more such combinations according to the combination of the test specimen and the test specimen control device, and the one or more power supply unit controllers control the voltage output by the power supply unit to a voltage that conforms to the power supply pattern of the electric contact line that supplies power to the railway vehicle, and supplies this to the test specimen control device, and performs simulations according to the conditions and state of the electric contact line to perform tests that correspond to the line on which the railway vehicle operates. Effect of the Invention

[0009] According to the present invention, it is possible to realize power supply fluctuations of a railway vehicle drive system under test in an environment that is the same as the actual vehicle running state. This makes it possible to simulate, for example, fluctuations in overhead power supply voltage accompanying acceleration and deceleration of a train (vehicle) by controlling the output of the power supply device. Similarly, it is possible to simulate sudden changes in power supply voltage accompanying loss of contact and voltage increases in a light-load regenerative state by controlling the output voltage of the power supply device.

[0010] Furthermore, by providing multiple power supply units and an integrated control device, fluctuations in the overhead power supply caused by the acceleration, deceleration, or transition to coasting of a certain train (car), can be applied as fluctuations in the overhead power supply of multiple other trains (cars). For example, it is possible to simulate mutual interference of power supply fluctuations between multiple trains (cars) in the same power supply section and have the effect of this on each of the drive systems under test.

[0011] Therefore, the power supply fluctuation of the railcar drive system under test can be realized in an environment that is the same as the actual vehicle running conditions. Problems, configurations and effects other than those described above will become apparent from the description of the following embodiments. [Brief description of the drawings]

[0012] [Figure 1]1 is a diagram showing an overall configuration of a power supply device and a test specimen of a railway vehicle test apparatus according to first and second embodiments of the present invention; [Diagram 2] 2 is a diagram showing the internal configuration of a power supply unit and a power supply device controller constituting the power supply devices of the first and second embodiments. FIG. [Diagram 3] 2 is a diagram showing a method of controlling an output power supply by a power supply unit and a power supply device controller according to the first embodiment. FIG. [Figure 4] FIG. 11 is a diagram showing a method for controlling an output power supply by a power supply unit and a power supply device controller according to the second embodiment. [Diagram 5] FIG. 11 is a diagram showing the overall configuration of a power supply device and a test specimen of a railway vehicle test apparatus according to a third embodiment of the present invention. [Figure 6] FIG. 11 is a diagram illustrating a method of controlling an output power supply by a general control device, a power supply unit, and a power supply device controller according to a third embodiment. [Figure 7] FIG. 11 is a diagram showing the state of a vehicle when an overhead line comes off and the relationship between the overhead line voltage and time. [Figure 8] FIG. 2 is a diagram showing the relationship between the railway vehicle and the overhead line voltage versus time when the railway vehicle travels through an unelectrified section from a DC electrified section to an AC electrified section. [Figure 9] FIG. 11 is a diagram illustrating the operation of a railway vehicle and the state of overhead line voltage when regenerative braking is performed on the railway vehicle according to a fourth embodiment of the present invention. [Figure 10] FIG. 1 is a diagram showing a control method for simulating an overhead line voltage during regenerative braking of a railway vehicle. [Figure 11] FIG. 11 is a diagram showing the overall configuration of a power supply device and a test specimen of a railway vehicle test apparatus according to a fifth embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0013] In the following, with reference to the drawings, examples 1 to 5 will be described as modes for carrying out the present invention. Note that the present invention is not limited to these examples. In addition, in the description of the drawings, the same parts are denoted by the same reference numerals. EXAMPLES

[0014] FIG. 1 is a diagram showing the overall configuration of a power supply device 1 and a test device 2 of a railway vehicle test apparatus according to first and second embodiments of the present invention.

[0015] FIG. 2 is a diagram showing the internal configuration of a power supply unit 20 and a power supply controller 30 that constitute the power supply 1 of the first and second embodiments.

[0016] The power supply device 1 of the railway vehicle test device is composed of a power supply device controller 30 and a power supply section 20, and supplies a power source to the DUT 2 that simulates the voltage of the electric power line.

[0017] As shown in FIG. 2, power supply unit 20 constituting power supply device 1 is made up of one or more power supplies, and shows the following five patterns from (1) to (5). (1) Pattern 1: 1 DC power supply unit (1) 26 (2) Pattern 2: As multiple DC power supplies, the first DC power supply unit (1) 26 to the nth DC power supply unit (n) 27 (3) Pattern 3: One AC power supply unit (1) 28 (4) Pattern 4: As multiple AC power supply units, the first AC power supply unit (1) 28 to the nth AC power supply unit (n) 29 (5) Pattern 5: A combination of one or more DC power supply units (1) 26 and one or more AC power supply units (1)

[0018] As shown in FIG. 2, the power supply device controller 30 constituting the power supply device 1 is also made up of one or more controllers, and corresponds to the above-mentioned power supply unit 20 and falls into the following categories (a) to (d). (a) DC power supply controller (1) 36 that controls DC power supply (1) 26 (b) DC power supply controller (n) 37 that controls DC power supply (n) 27 (c) an AC power supply controller (1) 38 that controls the AC power supply (1) 28 (d) an AC power supply controller (n) 39 that controls an AC power supply (n) 29

[0019] The power supply controllers 30 each pair to control the power supply units 20 . In this manner, the power supply device controller 30 is configured by combining the power supply units 20 according to the five pattern configurations ((1) to (5)) described above.

[0020] On the other hand, the DUT 2 is composed of a DUT 4 and a DUT control device 3. The DUT 4 is an engine, an electric motor, or the like, and the DUT control device 3 is a device that controls the DUT 4.

[0021] FIG. 3 is a diagram showing a method of controlling an output power supply by the power supply unit 20 and the power supply device controller 30 according to the first embodiment of the present invention.

[0022] The power supply device controller 30 is controlled by the power supply pattern 11 , the voltage command value generator 14 , and the voltage controller 17 .

[0023] The power supply pattern 11 is data on the voltage of the electric power line that supplies power to the vehicle. For example, this data is a table of the voltage of the electric power line with respect to time series, distance, etc.

[0024] The voltage command value generating unit 14 generates a voltage command value for outputting a predetermined voltage in accordance with the power supply pattern 11 and outputs it to the power supply control unit 17 .

[0025] The voltage control unit 17 outputs a voltage command for controlling the power supply unit 20 so as to have the same voltage as the power supply pattern 11 based on the voltage command value output by the voltage command value generating unit 14 .

[0026] The power supply section 20 controls the voltage conversion section 21 in accordance with a voltage command from the voltage control section 17 of the power supply device controller 30 to supply the DUT 2 with a power supply voltage having a power supply pattern simulating the electric rail voltage.

[0027] In the present invention, the configurations and control methods of the above-mentioned first embodiment and the second to sixth embodiments described below can simulate the electrification method, voltage, and frequency of AC electrification of the power source supplied by the electric railroad line to railway vehicles that differ depending on the line. This makes it possible to perform testing using the electrification method of the line on which the railway vehicle under test operates. It is also possible to apply the present invention to bi-mode vehicles. EXAMPLES

[0028] FIG. 4 is a diagram showing a method of controlling an output power supply by the power supply unit 20 and the power supply device controller 30 according to the second embodiment of the present invention.

[0029] The second embodiment is structurally similar to the first embodiment shown in FIG. 1, but differs from the control method of the first embodiment shown in FIG. 3 in that the power supply controller 30 has a function of detecting the operating state of the test device 2.

[0030] 3, in the power supply device control device 30, the voltage command value generating unit 14 receives data from the power supply pattern 11. Furthermore, the voltage command value generating unit 14 also receives a detection signal of the operating state of the EUT 2, and outputs a voltage command for supplying the same power supply voltage as the data of the power supply pattern 11 to the EUT 2 by taking into account the operating state of the EUT 2, such as powering or regenerative braking, into the data of the power supply pattern 11.

[0031] The voltage control unit 17 outputs a voltage command for controlling the power supply unit 20 so as to have the same voltage as the power supply pattern 11 based on the voltage command value output by the voltage command value generating unit 14 .

[0032] The power supply section 20 performs voltage conversion 21 in accordance with a voltage command from the voltage control section 17 of the power supply device controller 30, and supplies the DUT 2 with a power supply voltage having a power supply pattern simulating the electric rail voltage.

[0033] In the second embodiment, the above-described configuration and control method make it possible to perform a test that takes into account the state in which the EUT 2 is in powering or regenerative braking operation.

[0034] For large-capacity power sources such as industrial equipment, three-phase AC, the same as the power grid from power plants, is mainly used. On the other hand, for railways, DC power supply DC feeding method is often used to simplify the equipment design on the vehicle side.

[0035] In DC electrified sections, the voltage of the power supplied from the overhead lines drops when a vehicle leaves the substation, and the power voltage supplied from the overhead lines drops further during times when there are many trains traveling, such as during the morning rush hour for commuting to work or school and the evening rush hour for people returning home.

[0036] For this reason, AC power sources (AC electrification) are used for Shinkansen trains, which require a large capacity power source. AC electrification allows for higher voltages, so the intervals between substations can be longer.

[0037] As described above, railways have different power supply methods, such as DC and AC electrification, depending on the line. Also, as mentioned above, there are influences such as a drop in power supply voltage depending on the distance between the train's running point and the substation.

[0038] According to the present invention, when the EUT 2 is in powering operation, the location where the vehicle is traveling is calculated from the rotation speed of the EUT 2, etc., and the location where the vehicle is traveling is compared with the power supply pattern 11, and the voltage command value generating unit 14 outputs a voltage command value to the voltage control unit 17. The voltage control unit 17 controls the power supply unit 20 according to this voltage command value, and simulates the voltage at the location where the vehicle is traveling.

[0039] The power supply unit 20, under the control of the voltage control unit 17, performs voltage conversion 21 on the voltage from the substation, and can supply to the EUT 2 a voltage that simulates the power supply at the point where the vehicle is traveling during powering operation.

[0040] On the other hand, when a railcar performs regenerative braking, it sends regenerative energy to the power feeder section it is traveling in. If there is no equipment or vehicle capable of consuming regenerative energy in the same power feeder section at that time, the regenerative energy has nowhere to go (light-load regenerative state), so the railcar performs light-load regenerative control and performs braking using both regenerative brakes and air brakes.

[0041] Furthermore, in AC electrified sections, if regenerative braking is performed in an area far from a substation, the inductance component of the overhead contact lines becomes large due to the distance from the substation, causing the voltage at the current collector to rise.

[0042] According to the present invention, when the test equipment 2 is performing regenerative braking, the location where the vehicle is traveling is calculated from the rotational speed of the test equipment 2 as described above, and by taking into account the electric line voltage at the actual traveling point, it is possible to simulate the electric line voltage when regenerative energy is sent to the electric line, as well as a light-load regenerative state. EXAMPLES

[0043] Third embodiment FIG. 5 is a diagram showing the overall configuration of a power supply device 1 and a test device 2 of a railway vehicle test apparatus according to a third embodiment of the present invention.

[0044] The third embodiment differs from the configuration of the first embodiment shown in FIG. 1 in that a general control device 10 is added inside the power supply device 1 of the railway vehicle test device.

[0045] The overall control device 10 is connected to each of the DC power supply device controller (1) 36 to the AC power supply device controller (n) 39 in the power supply device controller 30.

[0046] FIG. 6 is a diagram showing a method of controlling an output power supply by the overall control device 10, the power supply unit 20, and the power supply device controller 30 according to the third embodiment.

[0047] The overall control device 10 is composed of a power supply pattern 11 and a voltage command value generating unit 14. The power supply pattern 11 outputs data on the voltage of the electric railroad line that supplies power to the railway vehicle (FIGS. 3 and 4), which was handled by the power supply device controller 30 in the first and second embodiments, to the voltage command value generating unit 14. It also has a function of detecting the operating state of the power supply unit 20 from the power supply device controller 30 having a voltage control unit 17. It is also possible to have the function of the voltage command value generating unit 14 that receives the detection of the operating state of the EUT, as explained in the second embodiment.

[0048] The DC power supply controllers (1) 36 to (n) 37 and the AC power supply controllers (1) 38 to (n) 39 constituting the power supply controller 30 in the first and second embodiments each have a power supply pattern and generate a voltage command. However, with this method, the DC power supply controllers (1) 36 to (n) 37 and the AC power supply controllers (1) 38 to (n) 39 constituting the power supply controller 30 operate separately, making it difficult to synchronize with the operating cycle of the power supply unit 20.

[0049] Therefore, in the third embodiment, the function of the voltage command value generating unit 14, which was performed by the power supply device controller 30 shown in FIG. 1, is provided to the general control device 10, thereby enabling synchronization of power supply commands.

[0050] This allows the DC power supply devices (1) 26 to (n) 27 and the AC power supply devices (1) 28 to (n) 29 that constitute the power supply unit 20 to operate in synchronization with each other. This makes it possible to simulate a sudden change in power supply voltage when the current collector of the vehicle separates from the electric rail and power is temporarily not supplied to the vehicle, and the power supply state of a non-electrical section where the electrification method changes from an AC electrified section to a DC electrified section.

[0051] 7 is a diagram showing the state of a vehicle when an overhead contact breaks and the relationship between the overhead contact voltage and time, in which an overhead contact wire 40 is shown as an example of an electric railcar line.

[0052] The catenary loss is a phenomenon that occurs when the contact between the trolley wire of the catenary 40 and the pantograph 60 is released, causing a temporary loss of power supply from the catenary to the vehicle, resulting in a sudden change in power supply voltage.

[0053] In testing for contact line loss, for example, the power supply is interrupted and then resumed after a few seconds. However, in actual cases, the manner and rate of contact line loss varies depending on the type of contact wire used on each line and the running speed of the railway vehicle.

[0054] When simulating an overhead line breakage, a DUT 2 that will cause an overhead line breakage is selected, and the power supply pattern 11 of the general control device 10 is switched to one for an overhead line breakage to generate a voltage command value.

[0055] The overall control device 10 outputs a voltage command value to the power supply controller 30, and the power supply controller 30 controls the power supply unit 20 using the voltage control unit 17 in accordance with the voltage command, thereby simulating a sudden change in power supply voltage due to a loss of power from the overhead line.

[0056] Next, a simulation example will be described in which the electrification method or the connection point between railway companies is switched via a non-electrified section. FIG. 8 is a diagram showing the relationship between the railway vehicle and the overhead line voltage versus time when the railway vehicle runs from a DC electrified section 70 to an AC electrified section 72 through a non-electrified section 71.

[0057] When traveling through both the DC electrified section 70 and the AC electrified section 72, the train is equipped with an AC / DC electric train that is compatible with each electrification method. Since the non-powered section 71 is an insulated section, no power is supplied to the train from the overhead line 40, and the train coasts through the non-powered section 71.

[0058] When conducting a test assuming that a vehicle will travel from the starting point to the destination point according to route information, if there is a section on the route that switches between a DC electrified section 70 and an AC electrified section 72, simply switching between DC power supply unit 21 and AC power supply unit 22 may result in a difference from the state when the vehicle actually travels on the route, such as the timing of switching.

[0059] In addition, the timing of the switch will vary for each test, making it possible for the tests to be difficult to reproduce the conditions in which a vehicle actually travels through a section where the electrification method switches after passing through an unelectrified section.

[0060] Similarly, it is difficult to simulate switching from the AC electrified section 72 to the DC electrified section 70, or switching the frequency in the AC voltage section, for the same reasons as above.

[0061] A power supply pattern as time-series data similar to the overhead line voltage is set as the power supply pattern 11 of the general control device 10. The power supply pattern 11 outputs a simulated overhead line voltage value to a voltage command value generating unit 14.

[0062] The voltage command value generating unit 14 detects the simulated overhead line voltage value from the power supply pattern 11 and the operating state of the power supply unit 20, selects one of the power supply units 26 to 29 to be operated, and outputs a voltage command value to the power supply unit controller 30. The power supply unit controller 30 operates the selected power supply unit 20 via the voltage control unit 17 according to the voltage command value from the overall control device 10.

[0063] This makes it possible to simulate switching between DC and AC voltage and frequency conversion of AC voltage, and enables tests to be conducted that simulate running from the starting station to the terminal station on a route where the overhead line voltage is switched. EXAMPLES

[0064] Fig. 9 is a diagram showing the operation of a railway vehicle and the state of overhead line voltage when the railway vehicle is in regenerative braking operation according to a fourth embodiment of the present invention. Here, the configuration of the power supply device 1 of the railway vehicle testing device is the same as that of the third embodiment shown in Fig. 5. Also, overhead lines are shown as the electric rails.

[0065] FIG. 9(a) shows the transition of the overhead line voltage over time. FIG. 9(b) shows the operating state of vehicles (two towing cars 43 and one trailer car 44) that make up a single train of multiple vehicles when regenerative energy generated by regenerative braking during deceleration of the railcar is returned to the overhead wires 40. When multiple vehicles perform regenerative braking, not all of them necessarily perform regenerative braking at the same time. In response to a regenerative braking command from the driver's cab, there may be a delay in transmitting the command from the front car where the driver's cab is located to the rearmost car relative to the front car. In this case, regenerative braking is performed, for example, starting with the front car closest to the driver's cab.

[0066] FIG. 9(c) shows the state in which regenerative energy 50 flows to the overhead wire 40 when one train undergoes regenerative braking. When regenerative braking is performed, regenerative energy flows from the pantograph 60 of the railway vehicle to the overhead wire 40. However, if the regenerative energy 50 returned to the overhead wire 40 cannot be consumed by other vehicles or equipment in the same power feeder section, the regenerative energy has nowhere to go. This is called a "light-load regeneration" state. This state can be confirmed as an increase in the overhead wire voltage due to regenerative energy and the overhead wire voltage during light-load regenerative control, as shown in FIG. 9(a). FIG. 9(d) shows the state of multiple vehicles when light-load regenerative control is performed.

[0067] Under light-load regenerative control conditions, the voltage of the filter capacitor built into the test equipment control device 3 shown in Figure 5 rises, so the test equipment control device 3 can suppress the rise in the filter capacitor voltage by performing light-load regenerative control. However, the regenerative braking operation weakens, so the regenerative energy decreases (in Figure 9, the size of the ellipse indicates the magnitude of the energy).

[0068] Fig. 10 is a diagram showing a control method for simulating the overhead line voltage during regenerative braking of a railway vehicle. For this control method, a detector 51 is added to the configuration of the railway vehicle testing device of the third embodiment shown in Fig. 5, between the power supply device 1 and the EUT 2, where a voltage is output from the power supply unit 20 to the EUT 2.

[0069] The overall control device 10 receives a detection signal of the output voltage value of the power supply unit 20 from the detector 51. For example, when the test device (1) 5 performs regenerative braking, the voltage value between the test device (1) 5 and the power supply unit 20 rises. The voltage value at that time is set as a set value and a trigger is issued to the overall control device 10. When the overall control device 10 detects this set value, it recognizes that the test device (1) 5 is performing regenerative braking.

[0070] Next, the integrated control device 10 switches to a power supply pattern for regenerative braking operation. After switching to the power supply pattern for regenerative braking operation, the integrated control device 10 determines the operating state of the power supply unit 20 via the power supply device controller 30, and selects the power supply device controller 30 that outputs a voltage command value.

[0071] The overall control device 10 outputs a voltage command value from the power supply pattern 11 for regenerative braking operation to the selected power supply device controller 30 via the voltage command value generation unit 14. The power supply device controller 30 controls the power supply unit 20 via the voltage control unit 17 in accordance with the voltage command value, and outputs a voltage to the test device (1) 5.

[0072] This makes it possible to simulate the power supply voltage fluctuations of each test device when regenerative braking is performed on multiple vehicles starting from the front vehicle, as well as the power supply voltage fluctuations simulating a light-load regenerative state of multiple vehicles, as the power supply for each test device. EXAMPLES

[0073] 11 is a diagram showing the overall configuration of a power supply device 1 and a test device 2 of a railway vehicle test apparatus according to a fifth embodiment of the present invention. The fifth embodiment is a modified example of the configuration of the power supply device 1 of the railway vehicle test apparatus according to the first embodiment.

[0074] The power supply device 1 is configured with a power supply section 20 and a power supply device controller 30 that controls the power supply section 20, similar to the configuration shown in FIG.

[0075] The power supply unit 20 is similar to the power supply unit 20 of the first embodiment shown in FIG. 2, but is composed of multiple power supplies and has three patterns shown as (2), (4), and (5) in the explanation of the first embodiment (the explanation of the three patterns is the same as in the first embodiment).

[0076] The power supply controller 30 is similar to the power supply controller 30 of the first embodiment shown in FIG. 2, but is composed of multiple controllers, and has four corresponding relationships shown as (a) to (d) in the explanation of the first embodiment (the explanation of the four corresponding relationships is the same as in the first embodiment), and the power supply controller 30 controls the power supply unit 20 in pairs.

[0077] Therefore, the power supply device controller 30 is configured by combining the power supply unit 20 according to the three pattern configurations.

[0078] Furthermore, in the fifth embodiment, a configuration is formed by combining one DC power supply controller (1) 36 to the nth DC power supply controller (n) 37 and one AC power supply controller (1) 38 to the nth AC power supply controller (n) 39, and all of the controllers are connected to each other.

[0079] By connecting all of the controllers, one DC power supply controller (1) 36 through the nth DC power supply controller (n) 37 and one AC power supply controller (1) 38 through the nth AC power supply controller (n) 39 each detect the operating state of the others and take into consideration the detected operating states of the controllers other than themselves, thereby performing coordinated voltage control between the controllers and controlling the power supply unit 20.

[0080] This makes it possible to simulate a power supply under a light-load regenerative condition and to conduct tests by simulating transient power supply operation such as a sudden change in power supply voltage due to a loss of power from the electric line.

[0081] Although the embodiment of the present invention has been described above, the present invention is not limited to the above-described embodiment, and various modifications are possible without departing from the gist of the present invention. [Explanation of symbols]

[0082] 1: Power supply unit for railway vehicle test equipment, 2: Test equipment, 3: Test control device, 4: Test machine, 5: test device (1), 6: test device (n), 10: general control device, 11: power supply pattern, 12: power supply pattern (1), 13: power supply pattern (n), 14: voltage command value generation unit, 15: voltage command value generating unit (1), 16: voltage command value generating unit (n), 17: voltage control unit, 18: voltage control unit (1), 19: voltage control unit (n), 20: power supply unit, 21: voltage conversion, 22: voltage conversion (1), 23: voltage conversion (n), 26: DC power supply (1), 27: DC power supply (n), 28 AC power supply (1), 29: AC power supply (n) 30: Power supply controller, 36: DC power supply controller (1), 37: DC power supply controller (n), 38: AC power supply controller (1), 39: AC power supply controller (n), 40: overhead line, 41: rail, 43: traction vehicle, 44: Trailer car, 50: Regenerative energy, 51: Detector, 60: Pantograph, 70: DC electrified section, 71: non-electric section, 72: AC electrified section

Claims

1. A power supply device that supplies power to a test equipment control device that controls a test equipment that is an inverter-driven motor, and a power supply device controller that controls the power supply device are combined, and one or more combinations are provided according to the combination of the test equipment and the test equipment control device; One or more of the power supply device controllers control the voltage output by the power supply device to a voltage in accordance with the power supply pattern of the electric contact line that supplies power to the railway vehicle, and supplies the voltage to the EUT control device, and performs a simulation in accordance with the conditions and state of the electric contact line to perform a test corresponding to the line on which the railway vehicle runs. A railway vehicle test device comprising:

2. 2. The railway vehicle test device according to claim 1, One or more of the power supply device controllers detect the operating state of the EUT control device, and perform a simulation in response to the detected operating state added to the conditions and state of the electric railway line, thereby performing a test corresponding to the line on which the railway vehicle runs. A railway vehicle test device comprising:

3. 3. The railway vehicle test device according to claim 2, The detected operating state of the test vehicle control device corresponds to the regenerative braking operation of the railcar, including the light load regenerative control. A railway vehicle test device comprising:

4. 2. The railway vehicle test device according to claim 1, A plurality of the power supply controllers are interconnected; Each of the plurality of power supply device controllers detects the operation state of the other power supply device controllers and controls the voltage output by the power supply device in consideration of the operation state of the power supply device controllers other than itself that has been detected. A railway vehicle test device comprising:

5. 5. The railway vehicle test device according to claim 4, The detected operating state of the power supply device controller other than itself corresponds to a light load regeneration state of the railcar or a contact line disconnection state of the railcar. A railway vehicle test device comprising:

6. 3. The railway vehicle test device according to claim 1, A general control device that generalizes the plurality of power supply device controllers, The integrated control device includes: Instead of the power supply device controller, the voltage output by each of the plurality of power supply devices is controlled to a voltage according to each of the power supply patterns and supplied to each of the EUT control devices, and the power supply device controller has a function of detecting an operating state of the power supply device controller or an operating state of the power supply device combined with the power supply device controller from each of the plurality of power supply device controllers; The detected operating state of the power supply device controller or the operating state of the power supply device combined with the detected power supply device controller is simulated according to the conditions and states of the electric railway line or the conditions and states of the electric railway line plus the operating state of the EUT control device, thereby performing a test corresponding to the line on which the railway vehicle runs. A railway vehicle test device comprising:

7. 7. The railway vehicle test device according to claim 6, The detected state of the power supply device controller or the detected state of the power supply device combined with the power supply device controller corresponds to at least one of a contact line disconnection state of the railcar, an AC / DC switching operation in an electrified section in which the railcar operates, and a regenerative braking operation of the railcar including a light-load regenerative control. A railway vehicle test device comprising:

8. A railway vehicle testing method for testing a railway vehicle by supplying a voltage of an electric wire that supplies power to a railway vehicle from a power supply device that supplies power to an EUT control device that controls an EUT, which is an inverter-driven electric motor, A railway vehicle testing method in which the voltage output by the power supply device is controlled to a voltage that conforms to the power supply pattern of the electric railway line and supplied to the test equipment control device, and a simulation is performed in accordance with the conditions and state of the electric railway line, thereby performing a test corresponding to the line on which the railway vehicle operates.

9. 9. A railway vehicle testing method according to claim 8, comprising: A railway vehicle testing method in which the operating state of the EUT control device is detected, and a simulation is performed in accordance with a situation in which the detected operating state is added to the conditions and state of the electric railway line, thereby performing a test corresponding to the line on which the railway vehicle operates.

Citation Information

Patent Citations

  • Train traveling simulator

    JP2006240547A

  • Electricity accumulating unit control system and rolling stock using it

    JP2009159649A

  • Comprehensive test device for railway vehicle

    JP2018174624A

  • Traveling simulation method and device for overhead wire / pantograph system

    JP2020016440A

  • Power test faciIity system of train and testing method of the same

    US20040163451A1