Temporary scaffolding forming tool

The temporary scaffold forming jig addresses inefficiencies in supporting temporary scaffolding by distributing reaction forces between frames, enhancing installation/removal efficiency and reducing resident inconvenience.

JP7573392B2Active Publication Date: 2024-10-25HASEKO CORP
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2020145470
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-08-31
Publication Date
2024-10-25
Estimated Expiration
2040-08-31

AI Technical Summary

Technical Problem

Existing methods for supporting temporary scaffolding in apartment complexes during construction or repair require specialized installation and cause inefficiencies and inconvenience due to the need for direct fixation to building frames, which can disrupt resident life and increase installation/removal time.

Method used

A temporary scaffold forming jig that includes a support bracket, fixing part, and reaction force transmission section, allowing the reaction force to be distributed between the support bracket and an upper frame without direct fixation, using a detachable and slidable design.

Benefits of technology

The jig reduces installation and removal time by distributing the reaction force, minimizing disruptions to resident life and improving work efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007573392000001
    Figure 0007573392000001
  • Figure 0007573392000002
    Figure 0007573392000002
Patent Text Reader

Abstract

To provide a temporary scaffold forming jig capable of dispersing the suppression of reaction force to a load of a temporary scaffold added to a support bracket and avoiding the deterioration of workability at the time of installation and removal of the temporary scaffold and inconvenience in the life of a resident at the time of repair.SOLUTION: A temporary scaffold forming jig is provided with a support bracket 1 for supporting a temporary scaffold S, a fixing part 2 for fixing the support bracket 1 to a skeleton C1, and a reaction force transmitting part 3 for transmitting a reaction force against a load of the temporary scaffold S applied to the supporting bracket 1, and the reaction force transmitting part 3 is arranged between the support bracket 1 and another skeleton C2 on the upper layer of the skeleton C1, and transmits the reaction force to the other skeleton C2.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a temporary scaffolding forming jig that supports temporary scaffolding that is installed when constructing or repairing a building such as an apartment building. [Background technology]

[0002] Conventionally, for example, when constructing or repairing an apartment building, a temporary scaffolding was set up on the ground to carry out construction work from the outside. However, an apartment building with a seismic isolation structure shakes differently from the ground during an earthquake, so there was a risk that it would collide with and damage the temporary scaffolding, or that the temporary scaffolding would be knocked down. Therefore, it was necessary for the apartment building to support the temporary scaffolding so that it was raised above the ground.

[0003] In view of this, when the end of the balcony of an apartment building is made of a thick concrete structure, a technique has been disclosed that can avoid collisions between the apartment building and the temporary scaffolding by using a support bracket fixed to the structure to raise the scaffolding (see, for example, Patent Document 1). According to this technique, it is possible to effectively use the space below around the structure under construction as a passageway or material storage area by dismantling and removing the lower part of the temporary scaffolding according to the progress of the work. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2001-323654 A Summary of the Invention [Problem to be solved by the invention]

[0005] However, in Patent Document 1, in order to fix the support bracket to the structure, a fastening insert is inserted into the side of the structure. In other words, since the reaction force of the load of the temporary scaffolding that the support bracket receives is suppressed only by the fastening insert, the installation of the fastening insert is extremely important, and therefore, it takes time to assign construction work to specialized workers or experienced personnel, which may result in a decrease in workability when setting up the temporary scaffolding.

[0006] Similarly to the above-mentioned fastening inserts, there is a method in which a chemical anchor is inserted vertically into the surface of a balcony to secure the support brackets of the temporary scaffolding, and the reaction force is suppressed solely by the pull-out strength of the chemical anchor. However, this not only reduces the ease of work when setting up and removing the temporary scaffolding and requires restoration work to the balcony after the chemical anchor is removed, but also poses the risk of causing inconvenience to the occupants of the rooms on the balcony when repairs are made.

[0007] In other words, rather than both fixing the support bracket and suppressing the reaction force using only a single component such as the fastening insert or the chemical anchor, by using at least the suppression of the reaction force using a different component, the load applied to each component can be distributed, and there is no need to directly insert the fastening insert or the chemical anchor into the main body. Overall, the inventors came up with the idea of ​​avoiding both the aforementioned decrease in workability and inconvenience in the lives of residents.

[0008] Therefore, the object of the present invention is to provide a temporary scaffolding formation tool that distributes the suppression of the reaction force against the load of the temporary scaffolding applied to the support bracket, thereby avoiding a decrease in workability when setting up and removing the temporary scaffolding, and inconvenience to the residents' lives when repairing it. [Means for solving the problem]

[0009] That is, the temporary scaffolding forming jig in the present invention includes a support bracket that supports the temporary scaffolding, a fixing part that fixes the support bracket to the framework of a building, and a reaction force transmission part that transmits a reaction force against the load of the temporary scaffolding applied to the support bracket, and the reaction force transmission part is Without support from directly below The support bracket is disposed between the support bracket and another structure located on an upper layer of the structure, and transmits the reaction force to the other structure.

[0010] It is desirable that one end of the reaction force transmission portion is detachably fixed to the support bracket, and the other end of the reaction force transmission portion is detachably fixed to the rear surface of the separate body.

[0011] It is desirable that one end and / or the other end of the reaction force transmission portion have a jack structure that is slidable in the longitudinal direction.

[0012] The fixing portion is preferably a pressing bolt that is detachably attached to the support bracket and presses the body. Effect of the Invention

[0013] According to the present invention, the reaction force against the load of the temporary scaffolding received by the support bracket is distributed between the fixed part and the reaction force transmission part, thereby it is expected that the reduction in workability when setting up and removing the temporary scaffolding and the inconvenience to the residents' lives when repairing it can be avoided. [Brief description of the drawings]

[0014] [Figure 1] FIG. 1 is a perspective view showing a state in which a temporary scaffolding forming jig is used in one embodiment of the present invention. [Diagram 2] FIG. 13 is a conceptual diagram showing the operating status of the temporary scaffolding forming jig. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0015] Hereinafter, a temporary scaffolding forming jig in one embodiment of the present invention (hereinafter, also referred to as "this temporary scaffolding forming jig") will be described with reference to Figs. 1 and 2. In these drawings, when there are multiple identical parts, only one part is numbered. For ease of explanation, certain parts and lines leading to these parts are shown with hidden lines (dashed lines) or imaginary lines (two-dot chain lines). In the explanation, terms indicating orientation such as up, down, length, width, vertical, and horizontal are basically based on the building.

[0016] First, the structure of the temporary scaffolding forming jig will be described with reference to FIG.

[0017] As shown in Figure 1, this temporary scaffolding forming jig is used to form temporary scaffolding S that is installed when constructing or repairing an apartment building M that is made up of two or more floors. The apartment building M has a structure C1 that protrudes outward and corresponds to the veranda or balcony of the rooms on each floor or the common corridor. The structure C1 has a structure tip part Ca that rises vertically from its tip. The structure tip part Ca is a part where a handrail made of, for example, a glass or aluminum plate is installed, and there is no limit to the thickness.

[0018] The temporary scaffolding S may have a known structure, and is basically composed of a plurality of building sites T arranged vertically and scaffolding boards P arranged at a predetermined height on the building sites T. There is no limit to the height, but the scaffolding S is supported by the temporary scaffolding forming tool as one set for the height of the 3rd to 5th floors of the apartment building M. Only the bottom end of the temporary scaffolding S is supported by the temporary scaffolding forming tool, and the part above the bottom end is connected by a wall joint that is not numbered. In other words, the second set of temporary scaffolding located above the first set of temporary scaffolding S is supported by another temporary scaffolding forming tool.

[0019] In detail, this temporary scaffolding forming jig comprises a support bracket 1 that supports the temporary scaffolding S, a fixing part 2 that fixes the support bracket 1 to a tip part Ca of the skeleton C1 of the housing complex M, and a reaction force transmission part 3 that transmits a reaction force against the load of the temporary scaffolding S applied to the support bracket 1, and the reaction force transmission part 3 is disposed between the support bracket 1 and another skeleton C2 on the upper layer of the skeleton C1, and transmits the reaction force to the other skeleton C2. At least two of this temporary scaffolding forming jigs are attached at a predetermined building pitch, in other words, two or more may be attached according to the total width of the temporary scaffolding S.

[0020] According to this configuration, the reaction force transmission part 3 is pushed upward in response to the reaction force against the load of the temporary scaffolding S and is pressed against the back surface of another structure C2, thereby transmitting the reaction force to the other structure C2. In other words, the reaction force is borne by the other structure C2 via the reaction force transmission part 3, so that the reaction force applied to the support bracket can be suppressed in a distributed manner, and the temporary scaffolding S can be stably supported without having to insert the fixing part 2 into the surface or side of the structure C1.

[0021] The support bracket 1 is a roughly triangular jig comprising a first rod 11, a second rod 12 attached by welding or the like roughly perpendicular to the first rod 11, and a third rod 13 attached by welding or the like at an angle to the first rod 11 and the second rod 12, and may be made of a known material, shape, dimensions, and weight. When attached to the main body C, the first rod 11 protrudes roughly horizontally beyond the main body tip Ca to the inside and outside of the apartment building M, and the second rod 12 faces the outer surface of the main body tip Ca.

[0022] The first bar 11 has cylindrical first sockets 11a, 11a protruding upward for insertion of the building site T. The vertical dimension of the first bar 11 may be lower than the height of the gap between the lower end surface of the glass or aluminum handrail and the top surface of the body tip portion Ca, and the height may be about 40 mm.

[0023] The fixing portion 2 is located inside the apartment building M from the tip portion Ca of the main body when the support bracket 1 is attached to the tip portion Ca of the main body, and is detachable from the first rod material 11 of the support bracket 1. The fixing portion 2 is equipped with a cylindrical slide portion 21 that allows the first rod material 11 to slide freely by inserting it, a push bolt 22 that presses the tip portion Ca of the main body toward the outside of the apartment building M via an unnumbered protrusion that protrudes downward from the slide portion 21, and a second socket 23 that protrudes upward from the slide portion 21 for inserting the reaction force transmission portion 3.

[0024] The slide portion 21 slides according to the degree of pressure of the pressing bolt 22 against the body tip portion Ca. The pressing bolt 22 presses the body tip portion Ca and sandwiches the body tip portion Ca together with the second bar material 12 of the support bracket 1, thereby fixing the support bracket 1. The second socket 23 is cylindrical, and the inner surface may be formed into a female thread shape.

[0025] With this configuration, even if a glass or aluminum handrail is attached to the tip portion Ca of the structure, the support bracket 1 can be easily fixed to the structure C by inserting the first bar 11 from the outside of the apartment building M through the gap between the lower end surface of the handrail and the top surface of the tip portion Ca of the structure, then inserting the sliding portion 21 of the fixing part 2 into the first bar 11 from the inside of the apartment building M and sliding it to the specified position, and finally pressing the tip portion Ca of the structure with the push bolt 22.

[0026] The reaction force transmission part 3 is a bar material such as a steel pipe, but may also be an iron plate, and the size, shape, and weight are not limited. One end of the reaction force transmission part 3 is detachably fixed to the support bracket 1, and specifically, it may be fixed by simply being inserted into the second socket 23 of the fixing part 2, or may be formed in a male thread shape and screwed into the female thread shape of the second socket 23. The other end of the reaction force transmission part 3 is detachably fixed to the back surface of another structure C2, and specifically, it may be fixed by simply being pressed against the back surface of another structure C2 by the reaction force against the load of the temporary scaffolding S applied to the support bracket 1, or an anti-slip member for the back surface may be attached to the end surface.

[0027] The total length of the reaction force transmission part 3 may be approximately equal to the height dimension from the top surface of the tip part Ca of the body to the back surface of another body C2, or may be shorter than the above height dimension.If it is shorter, the height may be adjusted by providing a predetermined underlay member on one end side and / or the other end side of the reaction force transmission part 3.

[0028] According to this configuration, after the supporting bracket 1 is attached to the body C1, the reaction force transmission part 3 can be easily installed between the supporting bracket 1 and another body C2. That is, one end of the reaction force transmission part 3 can be easily fixed and positioned to the supporting bracket 1 by the second socket 23 of the fixing part 2, and then the other end of the reaction force transmission part 3 can be fixed to the back surface of the other body C2, so that the reaction force against the load of the temporary scaffolding S applied to the supporting bracket 1 can be reliably transmitted to the other body C2.

[0029] One end and / or the other end of the reaction force transmission part 3 may have a jack structure that is slidable in the longitudinal direction. Specifically, one end and the other end of the reaction force transmission part 3 have a screw-type jack (not shown) that can be inserted and removed in the longitudinal direction from each end face, and in this case, the total length of the reaction force transmission part 3 may be shorter than the height dimension from the top face of the body tip part Ca to the back face of another body C2. In other words, the reaction force transmission part 3 may have a structure that is detachable by raising and lowering the jack.

[0030] According to this configuration, regardless of the specifications of the apartment building M or the support bracket 1, the reaction force against the load of the temporary scaffolding S applied to the support bracket 1 can be transmitted to another structure C2 via the reaction force transmission part 3. In other words, it is not necessary to design the reaction force transmission part 3 in strict consideration of the height dimension from the top surface of the structure tip part Ca to the back surface of the other structure C2 or the height dimension of the first bar 11 of the support bracket 1, and it can be expected that both the manufacture and installation of the reaction force transmission part 3 can be easily performed.

[0031] Next, the operation of the present temporary scaffolding forming jig will be described with reference to FIG.

[0032] As shown in Figure 2, when the load of the temporary scaffolding S is applied in the direction of arrow L1 to the support bracket 1 attached to the body C1, the outside of the support bracket 1 tries to move in the direction of arrow R1 with the tip Ca of the body as the fulcrum, and the inside of the support bracket 1 tries to move in the direction of arrow R2. In other words, a reaction force in the direction of arrow R2 is generated on the inside of the support bracket 1 against the load of the temporary scaffolding S in the direction of arrow L1.

[0033] The fixing part 2 bears the reaction force in the direction of the arrow R2 while fixing the support bracket 1 to the tip part Ca of the structure. The reaction force transmission part 3 is fixed to the back surface of the support bracket 1 and another structure C2, and is pushed up by the reaction force. Therefore, the reaction force is generated in the direction of the arrow L2 and is transmitted to the other structure C2. In other words, since the fixing part 2 and the reaction force transmission part 3 bear the reaction force in a distributed manner, the reaction force can be suppressed without having to pierce the fixing part 2 into the structure C1 like a chemical anchor.

[0034] The temporary scaffolding forming jig shown in this embodiment is not limited to the above-mentioned contents, and includes the positions, shapes, and dimensions of all parts and the relationships between parts as long as the same effect is obtained. [Explanation of symbols]

[0035] 1 Support bracket, 11 First bar, 11a First socket, 12 Second bar, 13 Third bar, 2 Fixing part, 21 Slide part, 22 Push bolt, 23 Second socket, 3 Reaction force transmission part, S Temporary scaffolding, T Building site, P Scaffolding board, C Structure (C1 Structure, Ca Structure tip, C2 Another structure), M Apartment building

Claims

1. A support bracket for supporting the temporary scaffolding; A fixing portion for fixing the support bracket to a building frame; A reaction force transmission unit that transmits a reaction force against the load of the temporary scaffolding applied to the support bracket, The reaction force transmission unit is disposed between the support bracket and another body on an upper layer of the body without being supported by the body from directly below, and transmits the reaction force to the other body. A temporary scaffolding forming jig characterized by the above.

2. One end of the reaction force transmission portion is detachably fixed to the support bracket, The other end of the reaction force transmission part is detachably fixed to the back surface of the other body.

2. The temporary scaffolding forming jig according to claim 1.

3. One end and / or the other end of the reaction force transmission part has a jack structure that is slidable in the longitudinal direction.

3. A temporary scaffolding forming jig according to claim 1 or 2.

4. The fixing portion is a pressing bolt that is detachable from the support bracket and presses the body. A temporary scaffolding forming jig according to any one of claims 1 to 3.

Citation Information

Patent Citations

  • Simple scaffold

    JP2000038837A

  • Setting method for external strut

    JP2000073561A

  • Installation method for temporary scaffold and its support changing device

    JP2001323654A

  • Scaffold support jig

    JP2003206627A

  • scaffold assembly equipment

    JP3116907U