Manufacturing line process planning device and method

The process planning device optimizes manufacturing line operations by accounting for raw material status and equipment constraints, enhancing production capacity and reducing operational losses, thus achieving efficient allocation of resources.

JP7574761B2Active Publication Date: 2024-10-29SUMCO CORP
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
JP2021131600
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-08-12
Publication Date
2024-10-29
Estimated Expiration
2041-08-12

AI Technical Summary

Technical Problem

Conventional process planning systems fail to account for the in-process status of raw materials, leading to deviations from actual line operations and suboptimal process plans.

Method used

A process planning device and method that considers daily operation information, in-process quantity of raw materials, and equipment constraints to optimize production capacity by minimizing product changes and raw material waiting times, using a combination extraction unit to identify the most efficient allocation of manufacturing equipment and products.

Benefits of technology

Enables the creation of an optimal process plan that maximizes production capacity and minimizes operational losses due to raw material shortages and equipment changes, thereby improving manufacturing efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007574761000001
    Figure 0007574761000001
  • Figure 0007574761000002
    Figure 0007574761000002
  • Figure 0007574761000003
    Figure 0007574761000003
Patent Text Reader

Abstract

To provide a wafer production line process plan drafting apparatus and method capable of obtaining an optimum process plan.SOLUTION: In a production line 1 for manufacturing multiple types of wafer products 13 using multiple CVD apparatuses 12 that operate in parallel, a process plan drafting device 2 drafts a process plan for assigning a target manufacturing quantity of each wafer for each manufacturing date of the current month to each of the multiple CVD apparatuses. The process plan drafting device includes: a conditional information input unit 21 for inputting conditional information as a prerequisite for drafting the process plan; an operation information input unit 22 for inputting daily operation information of the production line; a production capacity determination unit 23 for obtaining predicted values of production capacity including the number of product type changes and operation loss due to waiting for raw materials by round-robin simulation for all combinations of multiple manufacturing apparatuses and the multiple wafer products; and a combination extraction unit 24 for extracting a combination of a manufacturing apparatus and a wafer that maximizes the predicted values of the production capacity.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an apparatus and method for creating a process plan for various manufacturing lines such as silicon epitaxial wafers. [Background technology]

[0002] A process planning system is known that uses a database that accumulates the quality records of silicon wafers and process routes (route information consisting of the combination of production equipment used in each process) and the like to statistically estimate the quality of silicon wafers obtained by combining production equipment across multiple processes (e.g., processes such as polishing and cleaning), predicts the yield for each combination of silicon wafer products and production equipment based on the quality standards of a given silicon wafer, selects a combination of production equipment for each silicon wafer product that maximizes the overall yield of the target silicon wafer products, and presents a process plan for each process (see Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2017-45143 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, in the above-mentioned conventional technology, the in-process state of the raw materials is not taken into consideration, so there is a deviation from the operating state of the actual line, and an optimal process plan cannot necessarily be obtained.

[0005] An object of the present invention is to provide an apparatus and method for creating a process plan for a manufacturing line, which is capable of obtaining an optimal process plan. [Means for solving the problem]

[0006] The present invention relates to a process planning device that creates a process plan in which a target production quantity of each product is assigned to each of the manufacturing devices for each production date of the current month in a process of a manufacturing line that manufactures a plurality of products using a plurality of manufacturing devices that operate in parallel, a condition information input unit for inputting condition information that is a premise for creating the process plan; an operation information input unit for inputting daily operation information of the manufacturing line; For all combinations of the plurality of manufacturing apparatuses and the plurality of products, Depending on the type of product, replacement of members or parts included in the manufacturing equipment is required. Number of product changes and 、 Operational loss due to waiting for raw materials and A production capacity determination unit that determines a predicted value of the production capacity including the above through a brute force simulation; The above problem is solved by a manufacturing line process planning device including a combination extraction unit that extracts a combination of manufacturing equipment and products that maximizes the predicted value of the production capacity.

[0007] The present invention also provides a process plan creation method for creating a process plan for a manufacturing line in which a plurality of products are manufactured using a plurality of manufacturing devices operating in parallel, the process plan including a target production quantity for each product on each manufacturing date of a current month for each of the plurality of manufacturing devices, the process plan being created by a computer running a program, the process plan comprising: The computer includes: Input condition information that is the premise for planning the process plan, inputting daily operating information of said production line; For all combinations of the plurality of manufacturing apparatuses and the plurality of products, Depending on the type of product, replacement of members or parts included in the manufacturing equipment is required. Number of product changes and 、 Operational loss due to waiting for raw materials and The predicted value of production capacity including the above was calculated by brute force simulation. The above problem is solved by a method for creating a process plan for a manufacturing line, which extracts a combination of manufacturing equipment and products that maximizes the predicted value of the production capacity.

[0008] In the above invention, it is more preferable that the condition information includes quality standard information for each of the products, target shipping volume information for the current month for each of the products, manufacturing equipment constraint information for each of the products, and quality inspection result information for each of the products, and the operation information includes information on the in-process quantity of raw materials, remaining production volume information for the current month, production capacity information for each of the products, setting condition information for the manufacturing equipment, and maintenance plan information for the manufacturing equipment.

[0009] In the above invention, it is more preferable to calculate a yield rate for each product from the target shipping volume information for each product for the current month, calculate a target production volume for each product for the current month from the calculated yield rate and the target shipping volume information for each product for the current month, and calculate the number of days required to achieve the target production volume for the current month from the calculated target production volume and the production capacity information for each product.

[0010] In the above invention, the process plan determination unit determines whether or not the combination of the manufacturing equipment and the product extracted by the combination extraction unit is feasible in light of the manufacturing equipment constraint information input to the condition information input unit, If the process plan determination unit determines that the combination of the extracted manufacturing equipment and product is not feasible, it is more preferable that the process plan determination unit excludes the extracted combination of manufacturing equipment and product and then has the production capacity determination unit re-calculate the predicted production capacity value.

[0011] In the above invention, it is more preferable to apply a wafer as the product. Effect of the Invention

[0012] According to the present invention, it is possible to provide a manufacturing line process planning apparatus and method capable of obtaining an optimal process plan. [Brief description of the drawings]

[0013] [Figure 1] 1 is a block diagram showing an entire wafer manufacturing line including a process planning device according to the present invention; [Diagram 2] 1 is a block diagram showing an embodiment of a process planning device according to the present invention; [Diagram 3] 3 is a flowchart showing information processing of the process planning device of FIG. 2. [Figure 4] 1. FIG. 4 is a diagram showing an example of quality constraint information by product according to the embodiment in FIG. [Diagram 5] 1. FIG. 4 is a diagram showing an example of product-by-product current month target shipment amount information according to the embodiment of FIG. [Figure 6] FIG. 2 is a diagram showing an example of information on the in-process quantity of raw materials according to the embodiment of FIG. 1. [Figure 7] 1. FIG. 4 is a diagram showing an example of current month production remaining information according to the embodiment of FIG. [Figure 8] FIG. 2 is a diagram showing an example of production capacity by product according to the embodiment of FIG. 1. [Figure 9A] 2 is a diagram showing an example of setting condition information of the manufacturing apparatus according to the embodiment of FIG. 1; [Figure 9B] FIG. 2 is a diagram showing an example of the shape of a member A and the shape of a member B currently set in a CVD apparatus. [Figure 10] 2 shows an example of maintenance plan information for the manufacturing apparatus according to the embodiment of FIG. 1. [Figure 11A] 4 is a Gantt chart (part 1) illustrating an example of the process of step S3 in FIG. 3. [Figure 11B] 4 is a Gantt chart (part 2) illustrating an example of the process of step S3 in FIG. 3. [Figure 11C] 4 is a Gantt chart (part 3) illustrating an example of the process of step S3 in FIG. 3. [Figure 11D] 4 is a fourth Gantt chart illustrating an example of the process in step S3 of FIG. 3. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0014] FIG. 1 is a block diagram showing an entire wafer manufacturing line 1 including a process planning device according to the present invention. The manufacturing line 1 of the illustrated embodiment is a manufacturing line in which mirror-polished silicon wafers are used as raw material 11, and a silicon epitaxial layer is formed on the surface of the silicon wafer using a CVD device 12 to obtain a silicon epitaxial wafer product 13, and includes a plurality of CVD devices 12, from No. 1 to No. n, which operate in parallel. In general, when manufacturing silicon epitaxial wafers, the mirror-polished wafers, which are raw material 11, are placed in an epitaxial furnace of the CVD device 12 and heated to about 1150° C., and a raw material gas such as vaporized silane dichloride or silane trichloride is flowed into the furnace to vapor-grow (epitaxially grow) a single crystal silicon film on the wafer surface. This is a high-quality silicon wafer that can be used when perfection of silicon crystals is required or when a multilayer structure with different resistivities is required.

[0015] The CVD equipment 12 has replaceable parts or components (see parts A and B described below) depending on the type of wafer, and when a type of wafer that cannot use the same parts or components is manufactured in the CVD equipment 12, a type change operation is required to replace the parts or components with those appropriate for that type. Since the type change operation takes a certain amount of time, the operation rate decreases. Therefore, it is desirable to allocate the process in a way that avoids type change operation as much as possible.

[0016] Furthermore, if the raw material, mirror-polished wafers, run out of stock, at least some of the CVD apparatuses 12 will not be able to operate, i.e., will have to wait for a raw material shortage. A shortage of mirror-polished wafers, which is the upstream process, will occur due to delays or defects in the mirror-polished wafer manufacturing process, which will cause the epitaxial wafer manufacturing line to stop. Therefore, it is desirable to allocate the process so that such operational losses due to waiting for raw materials do not occur.

[0017] As described above, an allocation that minimizes the amount of product type change work and the waiting time due to raw material shortages will result in a process plan that maximizes the operating rate. The process plan creation device 2 of this embodiment inputs condition information that is the premise for creating a process plan and daily operation information of the actual manufacturing line, and calculates a combination of allocations to wafer manufacturing equipment that minimizes the number of product type changes and operation losses due to waiting for raw materials, as shown in FIG. 2. For this reason, the process plan creation device 2 of this embodiment includes a condition information input unit 21 that inputs condition information, an operation information input unit 22 that inputs operation information, a production capacity determination unit 23 that calculates a predicted value of production capacity, a combination extraction unit 24 that extracts optimal combinations, and a process plan determination unit 25 that determines whether or not a process is feasible. Note that the process plan creation device 2 can be configured by a computer including hardware and software, and the condition information input unit 21, operation information input unit 22, production capacity judgment unit 23, combination extraction unit 24 and process plan determination unit 25 can be realized as individual software programs.

[0018] The condition information to be input to the condition information input unit 21 is a non-variable condition that is determined in advance regardless of the operating state, and includes quality constraint information for each wafer product, current month target shipping volume information for each wafer product, and manufacturing equipment constraint information for each wafer product.

[0019] The quality constraint information for each wafer product is information on which CVD apparatus 12 can satisfy the quality required for the wafer. FIG. 4 is a diagram showing an example of the quality constraint information for each wafer product according to the present embodiment. The qualities required for the wafer products A, B, and C include quality 1, quality 2, and quality 3 (for example, flatness, film thickness, resistance value, etc.), and it is assumed that the quality inspection results of the wafer products 13 manufactured by each of the current CVD apparatuses 12 No. 1 to No. 5 in the actual manufacturing line 1 are as shown in FIG. 4. In FIG. 4, "◯" indicates a result that the quality is satisfied, and a blank indicates a result that the quality is not satisfied. If the quality inspection results of the current CVD apparatuses 12 No. 1 to No. 5 are as shown in FIG. 4, for example, when quality 1 is required for product A, the No. 2 apparatus cannot be used, and when quality 2 or quality 3 is required, the No. 5 apparatus cannot be used. Such constraint conditions for the CVD apparatus 12 are called quality constraint information.

[0020] The target shipment volume information for each wafer product for the current month includes the target shipment volume for each wafer product for the month for which the process plan should be created. Figure 5 shows the shipment volume for a certain month, and in this example, the wafer product A is 1200 pieces, product B is 1400 pieces, product C is 2500 pieces, product D is 1000 pieces, and product E is 1200 pieces.

[0021] The manufacturing equipment constraint information for each wafer product is information on wafer products that cannot be handled by each CVD equipment 12, and includes information such as that the product can only be produced by the CVD equipment 12 specified by the customer.

[0022] The operational information to be input to the operational information input unit 22 is a variable condition that varies depending on the operational state of the manufacturing line 1, and includes information on the in-process quantity of raw materials, actual production information for the current month by wafer product, production capacity information by wafer product, setting condition information for the manufacturing equipment, and maintenance plan information for the manufacturing equipment.

[0023] The raw material in-process quantity information is the number of wafers that are in the middle of raw material production. FIG. 6 shows an example of raw material in-process quantity information. Processes 1 to 9 in FIG. 6 show the manufacturing process of mirror-polished wafers, specifically, manufacturing processes 1 to 9 of mirror-polished wafers from slicing into wafers to the epitaxial process. The information is about the in-process quantities of wafer products A to E in process at each of processes 1 to 9, along with the processing capacity per hour of each process. The information is used to minimize operational losses due to shortages of mirror-polished wafers when planning the epitaxial process.

[0024] Current month production performance information for wafer products is information on the quantity of wafer products actually produced in the current month. The yield rate (= number of good products / production volume) can be calculated from the current month's production volume (including defective products) and the actual quantity of good products. In addition, the target production volume for the current month can be calculated by dividing the target shipment volume for the current month in Figure 5 by the yield rate. An example of current month production performance information is shown in Figure 7.

[0025] The production capacity information for each wafer product is the maximum production volume per day determined for that wafer manufacturing line 1, and is a known value for each wafer product. An example of production capacity for each wafer product is shown in Figure 8. The number of days required to achieve the target production volume for that month can be calculated by subtracting the amount of non-defective products for that month from the target production volume for that month, and then dividing the result by the maximum production volume per day in Figure 8.

[0026] The setting condition information of the manufacturing equipment is information about dedicated members or parts currently set in each CVD equipment 12. As described above, the shape of member A and the shape of member B used for each wafer product are fixed, and if the type of wafer product changes and it becomes necessary to replace members A and B, time is required for the replacement work. Therefore, in order to create a production plan that does not require the replacement work of members A and B when such a product type is changed, the setting condition information of the manufacturing equipment is grasped.

[0027] Fig. 9A shows an example of the components A and B used for each wafer product. Fig. 9B shows an example of the shapes of components A and B currently set in the CVD apparatus 12. For instance, in the example shown in Fig. 9A, when manufacturing wafer product A, component A must be shape 1 and component B must be shape 1. In the example shown in Fig. 9A, since no wafer products A to E use components A and B of the same shape, when the type of wafer products A to E changes, replacement work for components A and B is always required.

[0028] The maintenance plan information for the manufacturing equipment is plan information for maintenance work required for each CVD equipment 12, and is determined in advance, for example, to perform three days of maintenance work once a year for each equipment. An example of the maintenance plan information for the manufacturing equipment is shown in FIG.

[0029] For example, when target production volumes for each wafer product in a certain month are allocated to multiple CVD equipment 12 to manufacture all of them, production capacity determination unit 23 performs a brute force simulation to obtain a predicted value of production capacity including the number of product changeovers and operation losses due to waiting for raw materials for combinations of each product wafer and CVD equipment 12. If the calculation time by computer is long, an upper limit time may be set in advance, and combinations obtained within that time range may be used.

[0030] The combination extraction unit 24 extracts a combination of the wafer products and the CVD equipment 12 that maximizes the predicted value of the production capacity, including the number of product type changes and the operation loss due to waiting for raw materials, from among the combinations obtained by the production capacity determination unit 23. In other words, it extracts a combination that minimizes the number of product type changes and the operation loss.

[0031] The process plan determination unit 25 judges whether or not the combination of the wafer type and CVD equipment 12 extracted by the combination extraction unit 24 is feasible in light of the condition information, i.e., the quality constraint information and the manufacturing equipment constraint information, input to the condition information input unit 21. If it is judged to be feasible, the process plan determination unit 25 excludes the combination of the extracted wafer type and CVD equipment 12 and re-calculates the predicted value of production capacity by the production capacity judgment unit 23.

[0032] Next, a method for formulating a process plan according to this embodiment will be described. Fig. 3 is a flow chart showing information processing of the process plan formulating device. First, in step S1, condition information including quality constraint information for each wafer product, shipping amount information for each wafer type for the current month, and constraint information for the CVD device for each wafer type is input to the condition information input unit 21. Next, in step S2, operation information including in-process quantity information for raw materials, quality inspection result information for wafer products, remaining production amount information for the current month, production capacity information for each wafer type, setting condition information for the CVD device, and maintenance plan information for the CVD device is input to the operation information input unit 22.

[0033] Next, in step S3, the yield rate, target production volume, and the number of days to achieve the target production volume are calculated from the information entered in steps S1 and S2. Specifically, the yield rate by product is calculated from the number of non-defective items and the number of defective items in the product-specific target shipping volume information for the current month, the product-specific target production volume for the current month is calculated from the calculated yield rate and the product-specific target shipping volume information for the current month, and the number of days to achieve the product-specific target production volume for the current month is calculated from the calculated target production volume and the product-specific production capacity information.

[0034] Next, in step S4, the production capacity determination unit 23 performs a round-robin simulation to obtain a predicted value of the production capacity, including the number of product type changes and the operation loss due to waiting for raw materials, for all combinations of the multiple CVD devices 12 and the multiple types of wafer products, based on the condition information and operation information input in steps S1 and S2, and the yield rate and target production volume calculated in step S3. An example of this calculation will be described with reference to the Gantt charts in Figures 11A to 11D. As a premise of this example, as shown in FIG. 11A, the number of days to achieve the wafer products to be manufactured and their target production volumes are 13 days for product A, 6 days for product B, 2 days for product C, and 7 days for product D, the horizontal axis indicates the production days (6 days), five CVD equipments 12 are used, No. 1 (#1) to No. 5 (#5), each CVD equipment has a production capacity of 1 wafer / day, the current equipment setting conditions are as follows: No. 1 corresponds to product A, No. 2 corresponds to product B, No. 3 corresponds to product C, No. 4 corresponds to product D, and No. 5 corresponds to product B, and No. 3 is scheduled for maintenance for 2 days.

[0035] Under the above conditions, first, in order to avoid any type changeover work, product A is assigned to machine 1 for 6 days, product B to machine 2 for 6 days, product C to machine 3 for 2 days, and product D to machine 4 for 6 days. This is shown in Figure 11B. The number of days to achieve the production volume after this assignment is 7 days for product A, 0 days for products B and C, and 1 day for product D, and the number of days for the unassigned CVD equipment 12 is 2 days for machine 3 and 6 days for machine 5.

[0036] For machine 5, product B is the equipment setting condition, so product changeover work will occur for both the remaining products A and D. Also, for machine 3, since it has just undergone maintenance work, product changeover work can be carried out during the maintenance work, so product changeover work will not occur regardless of whether product A or D is assigned. However, if product D is assigned to machine 5, product changeover work will occur after the end of day 2, so as shown in Figure 11C, 6 days of product A are assigned to machine 5, and the remaining one sheet of product A and one day of product D are assigned to machine 3, as shown in Figure 11D. By programming the above processing and conducting a brute-force simulation, the predicted production capacity, including the number of product changeovers and operational losses due to waiting for raw materials, was found to be the most accurate. Get bigger A combination of the wafer product and the CVD apparatus 12 is obtained.

[0037] Next, in step S5, the combination extraction unit 24 extracts a combination of the CVD equipment 12 and the wafers that maximizes the predicted value of the production capacity obtained in step S4. In the following step S6, the process plan determination unit 25 judges whether the combination of the CVD equipment 12 and the wafer products extracted by the combination extraction unit 24 is feasible in light of the constraint information of the CVD equipment input to the condition information input unit 21. If the result of this judgment is that the combination is feasible, the process proceeds to step S7, the process plan of the combination is output, and the planning process is terminated. On the other hand, if the result of the judgment in step S6 is that the combination is not feasible, the process proceeds to step S8, the combination of the extracted CVD equipment 12 and the wafer products is excluded, and then the process proceeds to step S4, where the production capacity judgment unit 23 re-obtains the predicted value of the production capacity under the excluded conditions. Then, steps S4 → S5 → S6 → S8 → S4 are repeated until a feasible combination is determined in step S6. This makes it possible to find a combination that satisfies the constraint information of the CVD equipment 12 and minimizes the number of product type changes and operational losses due to waiting for raw materials.

[0038] In the present invention, the epitaxial process in the silicon epitaxial wafer manufacturing process is given as an example, but the present invention is not limited thereto and can be applied to, for example, a wafer polishing process in the silicon wafer manufacturing process. Moreover, the present invention can be applied not only to the silicon wafer manufacturing process but also to a process in a manufacturing line that manufactures multiple products using multiple manufacturing devices operating in parallel, such as a film formation process in a semiconductor device manufacturing process. [Explanation of symbols]

[0039] 1. Wafer production line 11...Raw materials 12...CVD equipment 13...Product (epitaxial wafer) 2...Process planning device 21...Condition information input section 22...Operation information input section 23…Production Capacity Assessment Department 24…Combination judgment section 25...Process planning department 3. Database D1…Condition information D2…Operational information D3…Operational information D4…Operational information

Claims

1. A process planning device that creates a process plan in which a target production quantity of each product is assigned to each of the manufacturing devices for each production date of a current month in a process of a manufacturing line in which a plurality of products are manufactured using a plurality of manufacturing devices operating in parallel, a condition information input unit for inputting condition information that is a premise for creating the process plan; an operation information input unit for inputting daily operation information of the manufacturing line; a production capacity determination unit that performs a brute force simulation to determine a predicted value of production capacity, including a number of product type changes that require replacement work of members or parts included in the manufacturing equipment according to the product type, and an operation loss due to waiting for raw materials, for all combinations of the plurality of manufacturing equipment and the plurality of products; A process planning device for a manufacturing line comprising: a combination extraction unit that extracts a combination of manufacturing equipment and products that maximizes the predicted value of the production capacity.

2. The condition information includes quality constraint information for each product, target shipping volume information for each product for the current month, and manufacturing equipment constraint information for each product, 2. The manufacturing line process planning device according to claim 1, wherein the operation information includes information on the in-process quantity of raw materials, production performance information for the product in the current month, production capacity information for the product, setting condition information for the manufacturing equipment, and maintenance plan information for the manufacturing equipment.

3. The production capacity determination unit is Calculating a yield rate for each product from the target shipping volume information for each product for the current month; Calculating the target production volume for each product for the current month from the calculated yield rate and the target shipping volume information for each product for the current month; 3. The manufacturing line process planning device according to claim 1, further comprising: a step of calculating a number of days required to achieve the target production volume for the current month from the calculated target production volume and the production capacity information for each product.

4. a process plan determination unit that determines whether or not the combination of the manufacturing equipment and the product extracted by the combination extraction unit is feasible in light of the condition information input to the condition information input unit, 4. The manufacturing line process planning device according to claim 1, wherein, when the process plan determination unit determines that the process plan is not feasible, the process plan determination unit excludes the extracted combination of manufacturing equipment and product and re-calculates the predicted value of the production capacity by the production capacity determination unit.

5. 5. The manufacturing line process planning device according to claim 1, wherein the product is a wafer product.

6. A process planning method for a manufacturing line in which a plurality of products are manufactured using a plurality of manufacturing devices operating in parallel, the process planning being performed by a computer running a program to allocate a target production quantity of each product for each of the plurality of manufacturing devices on each manufacturing date of a current month, the method comprising: The computer includes: Input condition information that is the premise for planning the process plan, inputting daily operating information of said production line; For all combinations of the plurality of manufacturing equipment and the plurality of products, a predicted value of production capacity including the number of product type changes that require replacement work of members or parts included in the manufacturing equipment according to the product type and an operation loss due to waiting for raw materials is obtained by brute-force simulation; A method for creating a process plan for a manufacturing line, which extracts a combination of manufacturing equipment and products that maximizes the predicted value of the production capacity.

7. The condition information includes quality constraint information for each product, target shipping volume information for each product for the current month, and manufacturing equipment constraint information for each product, 7. The method for creating a process plan for a manufacturing line according to claim 6, wherein the operation information includes information on the in-process quantity of raw materials, production performance information for the product in the current month, production capacity information for the product, setting condition information for the manufacturing equipment, and maintenance plan information for the manufacturing equipment.

8. Calculating a yield rate for each product from the target shipping volume information for each product for the current month; Calculating the target production volume for each product for the current month from the calculated yield rate and the target shipping volume information for each product for the current month; 8. The method for creating a process plan for a manufacturing line according to claim 6, further comprising the step of calculating the number of days required to achieve the target production volume for the current month from the calculated target production volume and the production capacity information for each product.

9. determining whether the extracted combination of the manufacturing equipment and the product is feasible in light of the input condition information; A method for creating a process plan for a manufacturing line according to any one of claims 6 to 8, further comprising the steps of: excluding the extracted combination of manufacturing equipment and product when it is determined that the combination is not practicable; and then re-calculating the predicted value of the production capacity.

10. 10. The method for creating a process plan for a manufacturing line according to claim 6, wherein the product is a wafer product.

Citation Information

Patent Citations

  • Manufacturing method and device

    JP1988232921A

  • Date of delivery calculating device

    JP2001325018A

  • Bottleneck formation avoidance method and system in manufacturing of semiconductor device

    JP2005190031A

  • Optimal index generation device, optimal index generation method, optimal index generation program, and optical index generation server

    JP2013033466A

  • Process planning system, apparatus, method, and program for silicon wafers

    JP2017045143A