Seismic isolation methods and structures
The seismic isolation method enhances construction efficiency and safety by using facing materials and fastening members to generate frictional force without forming through holes, addressing inefficiencies in existing methods.
Patent Information
- Application Number
- JP2021039257
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-03-11
- Publication Date
- 2024-11-13
- Estimated Expiration
- 2041-03-11
AI Technical Summary
Existing seismic isolation methods require time-consuming processes such as forming through holes in walls and backfilling, which can damage reinforcing bars and are inefficient.
A seismic isolation method involving the installation of a seismic isolation device between upper and lower structures with protruding parts, using facing materials and fastening members to generate frictional force, eliminating the need for through holes and backfilling, and allowing efficient construction.
Facilitates safer and faster construction by maintaining horizontal force resistance through frictional forces, reducing construction time and costs, and minimizing damage to reinforcing bars.
Smart Images

Figure 0007581985000001 
Figure 0007581985000002 
Figure 0007581985000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a seismic isolation method and a seismic isolation structure. [Background technology]
[0002] A seismic isolation method is being implemented in which columns of an existing building are cut and then seismic isolation devices are installed at the cut points to achieve seismic isolation. The existing building is separated into an upper structure and a lower structure with the seismic isolation device in between, and the wall is also separated into a side connected to the upper structure and a side connected to the lower structure. In Patent Document 1, in order to ensure resistance to horizontal external forces (earthquakes, etc.) acting on the building until the installation of the seismic isolation device is completed, the separated upper wall and lower wall are connected with a seismic plate. As disclosed in Patent Document 1, an earthquake-resistant plate 91 (see Figs. 14A and 14B) is generally attached to the walls 51, 52 by fastening members 92 (e.g., anchor bolts, nuts, etc.) inserted into through holes 93 provided in the upper and lower separated walls 51, 52. In this case, resistance to horizontal external forces in a direction along the wall surface can be ensured by the shear strength of the fastening members 92 and the frictional force between the wall surface and the earthquake-resistant plate 91 generated by the fastening members 92. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2001-311314 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, when attaching the earthquake-resistant plate 91 using the above method, it is necessary to form through-holes 93 in each of the upper wall 51 and the lower wall 52, and the through-holes 93 must be backfilled after removing the earthquake-resistant plate 91. Also, it is desirable to inspect the walls 51 and 52 for reinforcing bars before forming the through-holes 93 so as not to damage the reinforcing bars embedded in the walls 51 and 52 when forming the through-holes 93. Thus, the above-mentioned method of installing the earthquake-resistant plate 91 is time-consuming.
[0005] The present invention has been made in consideration of such problems, and its purpose is to facilitate the construction of seismic isolation work while maintaining the building's resistance to horizontal external forces acting on it during construction, thereby enabling the work to be carried out safely. [Means for solving the problem]
[0006] In order to achieve this object, the seismic isolation method of the present invention is a seismic isolation method in which a seismic isolation device is provided between an upper structure and a lower structure, the upper structure having an upper horizontal portion and an upper protruding portion protruding downward from the upper horizontal portion, the lower structure having a lower horizontal portion and a lower protruding portion protruding upward from the lower horizontal portion, a first panel is installed vertically across a gap between the upper protruding portion and the lower protruding portion and along one side surface of the upper protruding portion in the horizontal direction and the one side surface of the lower protruding portion, and the first panel is installed vertically across the gap and along the front side of the lower protruding portion in the horizontal direction. The method includes a panel installation process for installing a second panel along the other side surface of the upper protrusion and the other side surface of the lower protrusion; a pressure bonding process for pressure bonding the first panel and the second panel to the upper protrusion and the lower protrusion using a first fastening member inserted along the horizontal direction into the through hole, the gap, and the through hole of the first panel, and a second fastening member screwed into the first fastening member; and a seismic isolation device installation process for installing the seismic isolation device between the upper structure and the lower structure after the pressure bonding process.
[0007] According to this seismic isolation method, the frictional force generated between the surface material and the upper and lower protrusions can counter horizontal external forces acting on the building. Therefore, even if columns or the like are cut during construction, the positional displacement of the upper structure relative to the lower structure can be suppressed, and construction can be carried out safely. In addition, since the first fastening member is inserted into the gap formed by separating the upper and lower protrusions in order to function the seismic isolation device, there is no need to form holes in the upper and lower protrusions just for inserting the first fastening member, or to backfill the holes after removing the surface material, making construction easier.
[0008] In the seismic isolation method, in the pressure bonding step, a first bonding plate is bonded to the one surface of the first face material in the horizontal direction, and The method is characterized in that, with a second adhesive plate attached to the other side surface of the face material, the first face material and the second face material are pressure-bonded to the upper protrusion and the lower protrusion.
[0009] With this seismic isolation method, the tension of the first fastening member acts evenly over a wide area of the panel, so the panel can be firmly pressure-bonded to the upper and lower protrusions, increasing the frictional force generated between them and enhancing the building's resistance to horizontal external forces.
[0010] In the seismic isolation method, the first splice plate and the second splice plate are a plurality of splice plates. are stacked in the horizontal direction.
[0011] With this seismic isolation method, the horizontal distance from the tightening position of the second fastening member to the panel can be increased, so the tension of the first fastening member acts evenly over a wider area of the panel. This allows the panel to be firmly pressure-bonded to the upper and lower protrusions, increasing the frictional force generated between them and increasing the building's resistance to horizontal external forces.
[0012] In this seismic isolation method, the pressure bonding process is characterized by having a filling process of filling a filler between the first surface material and the upper protrusion and the lower protrusion, and between the second surface material and the upper protrusion and the lower protrusion.
[0013] According to this seismic isolation method, the face material can be tightly attached to the upper and lower protrusions via the filler, without any gaps. This allows the face material to be firmly pressure-bonded to the upper and lower protrusions, increasing the frictional force generated between them and increasing the building's resistance to horizontal external forces.
[0014] This seismic isolation construction method is characterized in that the upper protrusion and the lower protrusion are walls extending in the vertical direction between the upper horizontal portion and the lower horizontal portion, and includes a gap formation process, which cuts the wall to separate it into the upper protrusion and the lower protrusion and forms the gap before the surface material installation process.
[0015] According to this seismic isolation method, the first fastening member can be inserted into the gap formed by separating the wall into upper and lower parts to allow the seismic isolation device to function. In addition, since the wall can be cut before cutting the columns, etc. to install the seismic isolation device, the seismic isolation construction can be carried out efficiently.
[0016] This is a seismic isolation construction method, characterized in that the upper structure has another upper protruding portion protruding downward from the upper horizontal portion, and the lower structure has another lower protruding portion protruding upward from the lower horizontal portion, and in the seismic isolation device installation process, the seismic isolation device is installed between the other upper protruding portion and the other lower protruding portion, and the length of the gap in the vertical direction is shorter than the length of the seismic isolation device in the vertical direction.
[0017] According to this seismic isolation method, by narrowing the gap, the tension of the first fastening member can be received by the upper and lower protrusions rather than by the space of the gap. This makes it possible to efficiently generate friction between the face material and the upper and lower protrusions, and also to suppress bending of the face material.
[0018] Also, a seismic isolation structure having an upper structure having an upper horizontal portion and an upper protruding portion protruding downward from the upper horizontal portion, a lower structure having a lower horizontal portion and a lower protruding portion protruding upward from the lower horizontal portion, and a seismic isolation device installed between the upper structure and the lower structure, comprising: a first panel that vertically spans the gap between the upper protruding portion and the lower protruding portion and is installed along one side surface of the upper protruding portion and the one side surface of the lower protruding portion in the horizontal direction; a second panel that vertically spans the gap and is installed along the other side surface of the upper protruding portion and the other side surface of the lower protruding portion in the horizontal direction; a first fastening member that crimps and joins the first panel and the second panel to the upper protruding portion and the lower protruding portion; and a second fastening member that screws into the first fastening member. The seismic isolation structure is characterized in that the first fastening member is inserted along the horizontal direction through a through hole provided in the first panel, the gap, and a through hole provided in the second panel.
[0019] According to such a seismic isolation structure, the frictional force generated between the face material and the upper and lower protrusions can counter horizontal external forces acting on the building. Therefore, even if a column or the like is cut during construction, the positional deviation of the upper structure relative to the lower structure can be suppressed. In addition, since the first fastening member is inserted into the gap formed by separating the upper and lower protrusions to enable the seismic isolation device to function, there is no need to form holes in the upper and lower protrusions just for inserting the first fastening member, or to backfill the holes after removing the face material, which makes construction easier. Note that such a seismic isolation structure (a structure that has been seismically isolated) includes a structure in the middle of the seismic isolation construction method. Effect of the Invention
[0020] According to the present invention, it is possible to facilitate the construction of seismic isolation works while maintaining the resistance to horizontal external forces acting on the building during construction, thereby allowing the construction to be carried out safely. [Brief description of the drawings]
[0021] [Figure 1] It is a flowchart showing the procedure of the seismic isolation construction method of this embodiment. [Diagram 2] It is an explanatory view of the reinforcing part forming process. [Diagram 3] Figures 3A and 3B are explanatory views of the gap forming process. [Figure 4] Figures 4A and 4B are cross-sectional views explaining the facing material installation process. [Diagram 5] Figures 5A and 5B are views showing the state where the facing materials 61 and 62 are installed. [Figure 6] It is an explanatory view of the space S between the facing material 61 and the shear wall 50. [Figure 7] Figures 7A and 7B are explanatory views of the filling process of the filler 70. [Figure 8] It is a front view of the shear wall 50 after the crimping joining process is completed. [Figure 9] It is an explanatory view of the temporary support member installation process. [Figure 10] It is an explanatory view of the cutting process of the column 2. [Figure 11] It is an explanatory view of the installation process of the seismic isolation device 30. [Figure 12] It is a front view of the existing building 1 after the removal process. [Figure 13] It is a schematic plan view of the existing building 1. [Figure 14] Figures 14A and 14B are explanatory views of the seismic isolation construction method of the comparative example.
Mode for Carrying Out the Invention
[0022] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. ===Embodiment=== <<S01: Reinforcing part forming process>> Figure 1 is a flowchart showing the procedure of the seismic isolation construction method of this embodiment. Figure 2 is an explanatory view of the reinforcing part forming process, and Figure 2 is a front view of the reinforced existing building 1.
[0023] In the seismic isolation construction method of this embodiment, the existing building 1 is separated into an upper structure 10 and a lower structure 20, and a seismic isolation device 30 (for example, a laminated rubber type, a rolling bearing type, a sliding bearing type, etc.) is installed therebetween. Specifically, a part of the column 2 on an intermediate floor of the existing building 1 is cut (here, a part of the column 2 extending in the vertical direction from the floor surface FL1 of the first floor to the floor surface FL2 of the second floor is cut), and the seismic isolation device 30 is installed at the cut portion.
[0024] Hereinafter, two columns 2A and 2B arranged at intervals in the X direction will be described as columns to be constructed with the seismic isolation device 30 installed thereon. Further, the existing building 1 has a shear wall 50 with a wall surface along the X direction between the two columns 2A and 2B. Also, a part of the existing building 1 above the installation position of the seismic isolation device 30 and the cutting position of the shear wall 50 is defined as the upper structure 10, and a part of the existing building 1 below the installation position of the seismic isolation device 30 and the cutting position of the shear wall 50 is defined as the lower structure 20.
[0025] First, in order to compensate for the reduction in the strength and rigidity of the existing building 1 due to separating the existing building 1 vertically, a reinforcement part is formed to reinforce the existing building 1. For example, concrete is placed to raise the floor surface of the floor where the seismic isolation device 30 is installed, thicken the column 2, or thicken the beam 3. However, if there is no need to reinforce the existing building 1, the reinforcement part formation process is unnecessary.
[0026] In this embodiment (FIG. 2), a case is exemplified in which a column upper reinforcement part 41 reinforced by placing concrete on the outer side of the upper part of the columns 2A and 2B to be constructed and a column lower reinforcement part 42 reinforced by placing concrete on the outer side of the lower part of the columns 2A and 2B to be constructed are formed. In addition, when the shear wall 50 is joined integrally with the columns 2A and 2B in the existing building 1, a part of the shear wall 50 may be cut and separated from the columns 2A and 2B to form a space between the columns 2A and 2B and the shear wall 50. By doing so, the column upper reinforcement part 41 and the column lower reinforcement part 42 can be formed for the columns 2A and 2B.
[0027] <<S02: Gap formation process>> Figs. 3A and 3B are explanatory views of the gap forming process. Fig. 3A is a front view of the existing building 1, and Fig. 3B is a cross-sectional view of the shear wall 50 in which the gap 53 is formed.
[0028] Next, after the installation of the seismic isolation device 30, a gap forming process is carried out in which the shear wall 50 is cut along the X direction and separated vertically to form a gap 53 therebetween so that the seismic isolation device 30 functions. As a result, the superstructure 10 has an upper horizontal portion 11 (a portion above the lower surface of the beam 3) and an upper wall 51 (upper protruding portion) that is the upper part of the cut shear wall 50 and protrudes downward from the upper horizontal portion 11. Also, the substructure 20 has a lower horizontal portion 21 (a portion below the floor surface FL1 at the construction stage) and a lower wall 52 (lower protruding portion) that is the lower part of the cut shear wall 50 and protrudes upward from the lower horizontal portion 21.
[0029] Further, by cutting the shear wall 50 along the X direction, a gap 53 (horizontal slit) that is long in the X direction is formed at the cut portion, that is, between the upper wall 51 and the lower wall 52. As shown in Fig. 3B, the gap 53 is a space that penetrates the shear wall 50 in the Y direction orthogonal to the wall surface of the shear wall 50.
[0030] Note that after the installation of the seismic isolation device 30, when the shear wall 50 (upper wall 51 and lower wall 52) is joined to and integrated with the column 2 on which the seismic isolation device 30 is installed, the installation position of the seismic isolation device 30 in the vertical direction is aligned with the cutting position of the shear wall 50 (the position where the gap 53 is formed).
[0031] <<S03: Roughing process>> Next, a roughing process is carried out on the shear wall 50. In the present embodiment, as shown in Fig. 8 described later, the facing unit 60 is installed along the wall surface of the shear wall 50. Therefore, it is preferable to carry out roughing on the region of the wall surface of the shear wall 50 where the facing unit 60 is installed. For example, using a tool such as a grinder, unevenness is formed on the wall surface of the shear wall 50.
[0032] <<S04: Facing installation process>> Figures 4A and 4B are cross-sectional views explaining the panel installation process. Figures 5A and 5B are views showing the state after panel members 61 and 62 have been installed. Figure 5A is a cross-sectional view of bearing wall 50 on which panel members 61 and 62 have been installed, and Figure 5B is a front view of bearing wall 50 on which panel member 61 has been installed. Figure 6 is an explanatory diagram of space S between panel member 61 and bearing wall 50.
[0033] Next, a panel installation process is carried out to install the panel unit 60 on the bearing wall 50. The panel unit 60 has a first panel 61, a second panel 62, a first fastening member 63, a second fastening member 64, a first attachment plate 65, a second attachment plate 66, and a position adjustment bolt 67. In the following description, the first panel 61 and the second panel 62 are collectively referred to simply as the panel members 61, 62.
[0034] The first face material 61 and the second face material 62 may be exemplified by rectangular steel plates. In this embodiment, the steel plate has a thickness of 25 mm and a size of 400 mm×470 mm (X direction×vertical direction). As shown in FIG. 5B, two first fastening members 63 are inserted into the first face material 61 and the second face material 62 with a gap in the horizontal direction (X direction). Therefore, two through holes 611, 621 (for example, holes with a diameter of 39 mm) are formed with a gap in the horizontal direction in the center of the vertical direction (vertical direction) of the first face material 61 and the second face material 62. In addition, nuts 612, 622 are welded and integrally joined to the four corners of the steel plate in the first face material 61 and the second face material 62. In addition, the nuts 612, 622 are joined to the side of the face material 61, 62 that does not abut the wall surface in the thickness direction.
[0035] Examples of the first fastening member 63 include PC steel bars and bolts. In this embodiment, a PC steel bar (round steel bar) of type C No. 1 and diameter 36 mm is used. The second fastening member 64 is a member that screws into the first fastening member 63, and examples of the second fastening member 64 include nuts. In this embodiment, a hexagonal nut 641 and a round washer 642 are used. Examples of the first and second attachment plates 65 and 66 include square washers. In this embodiment, a square washer having a thickness of 38 mm and a size of 190 mm x 190 mm is used.
[0036] Before the facing materials 61, 62 are installed on the bearing wall 50, position adjustment bolts 67 (bolts 671) are screwed into nuts 612 at the four corners of the first facing material 61 and nuts 622 at the four corners of the second facing material 62. In the position adjustment bolts 67, anti-loosening nuts 672 are screwed into the bolts 671. As shown in FIG. 6, the ends of the bolts 671 are protruded from the faces 61b, 62a of the facing materials 61, 62 on the bearing wall 50 side in the Y direction in accordance with a desired width W (for example, 5 to 10 mm) of the space S to be provided between the facing materials 61, 62 and the bearing wall 50. The anti-loosening nuts 672 are in contact with the nuts 612, 622 of the facing materials 61, 62 from the side opposite to the bearing wall 50 side in the Y direction.
[0037] In order to install the face materials 61 and 62, first, as shown in FIG. 4A, the first fastening member 63 is inserted in the gap 53 between the upper wall 51 and the lower wall 52 in the Y direction, and the first fastening member 63 is inserted into the through hole 611 of the first face material 61 from one side in the Y direction of the load-bearing wall 50. Then, the first face material 61 is brought close to the surface 50a of one side of the load-bearing wall 50 in the Y direction. Furthermore, a first attachment plate 65 (two attachment plates 65) and a second fastening member 64 (round washer 642, hexagonal nut 641) are passed through the first fastening member 63 in this order from one side in the Y direction of the first face material 61. In addition, the first face material 61 of this embodiment has two fastening plates 65 arranged in a direction perpendicular to the paper surface of FIG. 4A (X direction). The first fastening members 63 are inserted. To this end, two splice plates 65 and a second fastening member 64 (642, 641) are provided at one end in the Y direction of each of the first fastening members 63. Then, a hexagonal nut 641 is screwed onto the threaded portion of the first fastening member 63 for provisional fastening.
[0038] As a result, the first panel 61 is installed vertically spanning the gap 53 between the upper wall 51 and the lower wall 52, and along one surface 51a of the upper wall 51 and one surface 52a of the lower wall 52 in the Y direction (horizontal direction). However, as shown in Fig. 6, a position adjustment bolt 67 attached to the first panel 61 abuts against the wall surface 50a of the load-bearing wall 50, and a space S (a space S with a width W in the Y direction of, for example, about 5 to 10 mm) is formed between the surface 61b of the first panel 61 and the wall surface 50a of the load-bearing wall 50.
[0039] Similarly, insert the first fastening member 63 that protrudes to the other side in the Y direction from the gap 53 between the upper wall 51 and the lower wall 52 through the through hole 621 of the second facing material 62. Then, bring the second facing material 62 closer to the other side surface 50b of the load-bearing wall 50 in the Y direction. Further, from the other side in the Y direction of the second facing material 62, pass the second abutting plates 66 (two abutting plates 66) and the second fastening member 64 (round washer 642, hexagonal nut 641) through the first fastening member 63 in order. Also, in the second facing material 62 of the present embodiment, in order to insert two first fastening members 63 arranged in the X direction, two abutting plates 66 and the second fastening member 64 (642, 641) are provided at the end of each first fastening member 63 on the other side in the Y direction. Then, temporarily fasten by screwing the hexagonal nut 641 onto the threaded portion of the first fastening member 63.
[0040] Thereby, the second facing material 62 is installed straddling the gap 53 between the upper wall 51 and the lower wall 52 in the vertical direction and along the other side surface 51b of the upper wall 51 and the other side surface 52b of the lower wall 52 in the Y direction (horizontal direction). However, the position adjustment bolt 67 attached to the second facing material 62 abuts against the wall surface 50b of the load-bearing wall 50, and a space S (a space S with a width W in the Y direction of, for example, about 5 to 10 mm) is formed between the surface 62a of the second facing material 62 and the wall surface 50b of the load-bearing wall 50.
[0041] In the facing material installation step, lightly tighten the second fastening member 64 (hexagonal nut 641) on the first fastening member 63 so that the facing material unit 60 does not shift with respect to the load-bearing wall 50.
[0042] <<S05: Crimping and Bonding Step>> Figures 7A and 7B are explanatory diagrams of the filling process of the filler 70. Figure 7A is a front view of the load-bearing wall 50 and the facing material unit 60, and Figure 7B is a cross-sectional view of the load-bearing wall 50 and the facing material unit 60. Figure 8 is a front view of the load-bearing wall 50 after the crimping and bonding step is completed. The crimping and bonding step includes a position adjustment step, a filling step of the filler 70, and a tensioning step.
[0043] First, a position adjustment step is performed in which the position adjustment bolts 67 are used to adjust the width W of the space S between the facing members 61, 62 and the bearing wall 50. The space S is a space for filling with the filler 70, and the width W of the space S is adjusted (for example, to about 5 to 10 mm) in order to fill a desired amount of the filler 70.
[0044] Specifically, as shown in FIG. 6, the bolt 671 of the position adjustment bolt 67 is in contact with the wall surface of the bearing wall 51 with its tip projecting from the face materials 61, 62 by about 5 mm, and nuts 612, 622 provided on the face materials 61, 62 are screwed onto the bolt 671. Furthermore, by fastening the first fastening member 63 and the second fastening member 64, a force is applied to the face materials 61, 62 to approach the bearing wall 50. If the width W of the space S does not reach the desired width (about 5 mm to 10 mm) due to unevenness on the wall surface of the bearing wall 51, the second fastening member 64 is loosened and the bolt 671 is further rotated to adjust the Y-direction position of the nuts 612, 622 (i.e., the face materials 61, 62) screwed onto it. For example, the bolt 671 is rotated in the tightening direction. As a result, the face materials 61, 62 are displaced away from the load-bearing wall 50. This makes it possible to adjust the width W of the space S between the face materials 61, 62 and the load-bearing wall 50 to a desired width. In addition, the anti-loosening nut 672 suppresses misalignment of the nuts 612, 622 (face materials 61, 62) with respect to the bolt 671, and maintains the width of the space S at a desired width.
[0045] 7B, a filling step is performed to fill the space S between the first facing member 61 and the bearing wall 50 (upper wall 51 and lower wall 52) and the space S between the second facing member 62 and the bearing wall 50 (upper wall 51 and lower wall 52) with a filler 70. An example of the filler 70 is a cement-based material such as grout.
[0046] When filling the filler 70, a formwork 71 (such as a backup material) may be provided at the peripheral edge of the space S between the facing materials 61 and 62 and the upper wall 51, and at the peripheral edge of the space S between the facing materials 61 and 62 and the lower wall 52. By doing so, the space S between the facing materials 61 and 62 and the load-bearing wall 50 (51, 52) can be filled with the filler 70 without gaps, and it is possible to prevent the filler 70 from flowing into the gap 53 between the upper wall 51 and the lower wall 52.
[0047] After the filler 70 has hardened, a tensioning process is performed in which the second fastening members 64 (hexagonal nuts 641) fitted to both ends of the two first fastening members 63 inserted through the facing materials 61 and 62 are tightened to apply a tensile force to the first fastening members 64. As a result, the first facing material 61 and the second facing material 62 approach each other in the out-of-plane direction (Y direction) of the load-bearing wall 50 with the load-bearing wall 50 interposed therebetween and are pressure-bonded.
[0048] The pressure-bonding of the facing material unit 60 to the load-bearing wall 50 is completed by the above steps. That is, the first facing material 61 is pressure-bonded to one side surface 50a of the load-bearing wall 50 (upper wall 51 and lower wall 52) in the Y direction via the filler 70. Also, the second facing material 62 is pressure-bonded to the other side surface 50b of the load-bearing wall 50 (upper wall 51 and lower wall 52) in the Y direction via the filler 70.
[0049] In FIG. 8, three facing material units 60 are installed at intervals in the Y direction with respect to one load-bearing wall 50. However, the number of facing material units 60 installed on one load-bearing wall 50 is not limited to three. Also, the number of the first fastening members 63 inserted through the facing materials 61 and 62 is preferably two or three or more as in the present embodiment in order to suppress the inclination (twist) of the facing materials 61 and 62 about the first fastening member 63. Further, through holes 611 and 621 arranged in the direction along the wall surface of the load-bearing wall 50 (here, the X direction) may be formed in the facing materials 61 and 62 so that all of the plurality of first fastening members 63 inserted through the facing materials 61 and 62 pass through the gap 53 between the upper wall 51 and the lower wall 52.
[0050] <<S06: Temporary support member installation process>> Figure 9 is an explanatory diagram of the temporary support member installation process and is a front view of the existing building 1. Next, a temporary support member 80 is installed between the upper structure 10 and the lower structure 20 around the columns 2A and 2B to be constructed. In this embodiment, the temporary support member 80 is installed between the column upper reinforcement part 41 and the column lower reinforcement part 42 formed around each of the columns 2A and 2B. The temporary support member 80 is for temporarily supporting the load of the upper structure 10 after the column 2 is cut and is a member that can expand and contract in the vertical direction (for example, a hydraulic jack, etc.).
[0051] <S07: Column cutting process> Figure 10 is an explanatory diagram of the column 2 cutting process and is a front view of the existing building 1. Next, a part of the columns 2A and 2B to be constructed is cut and removed to form an installation space for the seismic isolation device 30. In this embodiment, the parts of the columns 2A and 2B between the column upper reinforcement part 41 and the column lower reinforcement part 42 are cut. As a result, the upper structure 10 has an upper part 12 of the column protruding downward from the upper horizontal part 11 (other upper protruding parts), and the lower structure 20 has a lower part 22 of the column protruding upward from the lower horizontal part 21 (other lower protruding parts). Also, the load of the upper structure 10 supported by the columns 2A and 2B is transferred to the temporary support member 80.
[0052] <S08: Seismic isolation device installation process> Figure 11 is an explanatory diagram of the seismic isolation device 30 installation process and is a front view of the existing building 1. In the seismic isolation device installation process, first, a lower foundation 31 is formed on the column lower reinforcement part 42 of each of the columns 2A and 2B to be constructed. For example, reinforce bars and a formwork (not shown) are assembled according to the shape of the lower foundation 31, and concrete is placed to form the lower foundation 31. At this time, it is advisable to place the concrete with a base plate (not shown) for installing the seismic isolation device 30 arranged.
[0053] Next, the seismic isolation device 30 is installed on the lower foundation 31. For example, the lower part of the seismic isolation device 30 is fixed to the base plate integrated with the lower foundation 31 with bolts or the like. Then, a base plate is installed on the upper part of the seismic isolation device 30 and fixed with bolts or the like, and an upper foundation 32 including the base plate is formed between the seismic isolation device 30 and the upper column reinforcement part 41. Similar to the lower foundation 31, it is advisable to form the upper foundation 32 by assembling steel bars and formwork according to the shape of the upper foundation 32 and placing concrete with the base plate as the bottom formwork.
[0054] By installing the seismic isolation device 30 in this way between the upper part 12 and the lower part 22 of the columns 2A and 2B, the seismic isolation device 30 can follow the movement of the column 2. Also, the seismic isolation device 30 can transmit the load of the superstructure 10 to the substructure 20 while supporting it.
[0055] <S09: Demolition process> FIG. 12 is a front view of the existing building 1 after the demolition process. After the installation of the seismic isolation device 30, the temporary support member 80 is contracted and removed. Then, the load of the superstructure 10 is transferred from the temporary support member 80 to the seismic isolation device 30. After confirming that the load of the superstructure 10 has been transferred to all the seismic isolation devices 30 of the building and the seismic isolation structure of the entire building functions properly, the facing unit 60 is also removed from the shear wall 50. Note that after the demolition process, a fireproof joint material 54 or the like may be provided in the gap 53 between the upper wall 51 and the lower wall 52 to fill the gap 53 so as to allow displacement of the superstructure 10 with respect to the substructure 20. Further, a wall 55 may be constructed between the upper column reinforcement part 41 and the lower column reinforcement part 42 and the shear wall 50, and a fireproof coating 56 may be installed around the seismic isolation device 30 to form a fireproof compartment.
[0056] <<Regarding the effectiveness of the seismic isolation construction method>> FIG. 13 is a schematic plan view of the existing building 1. FIGS. 14A and 14B are explanatory views of a seismic isolation construction method of a comparative example different from the present embodiment. As described above, in the seismic isolation method of this embodiment, as shown in Fig. 5A, the first face material 61 is installed so as to straddle the gap 53 between the upper wall 51 and the lower wall 52 in the vertical direction and along one face 51a of the upper wall 51 and one face 52a of the lower wall 52 in the Y direction (horizontal direction). In addition, the second face material 62 is installed so as to straddle the gap 53 between the upper wall 51 and the lower wall 52 in the vertical direction and along the other face 51b of the upper wall 51 and the other face 52b of the lower wall 52 in the Y direction (horizontal direction).
[0057] Then, the first and second fastening members 63 are inserted along the Y direction (horizontal direction) into the through-hole 611 of the first face member 61, the gap 53 between the upper wall 51 and the lower wall 52, and the through-hole 621 of the second face member 62, and a second fastening member 64 is screwed into the first and second fastening members 63. Therefore, during construction of the seismic isolation method of this embodiment, a seismic isolation structure (seismic isolated structure) as shown in Fig. 11 is formed, allowing safe construction.
[0058] In other words, the upper wall 51 and the lower wall 52 are constrained and fixed to each other by the frictional force between the facing materials 61, 62 and the bearing wall 50 (upper wall 51 and lower wall 51) generated by the tension of the first fastening member 63. In this state, a part of the column 2 is cut, and the seismic isolation device 30 is installed at the cut site. Therefore, even if an earthquake or a storm occurs during construction when the column 2 etc. is cut, the frictional force between the facing materials 61, 62 and the bearing wall 50 maintains the resistance to horizontal external forces in the X direction (direction along the wall surface, direction perpendicular to the horizontal Y direction) acting on the building, allowing safe construction.
[0059] Specifically, when a horizontal external force in the X direction acts on the upper wall 51, the horizontal external force is transmitted to the lower wall 52 by the frictional force between the facing members 61, 62 and the bearing wall 50. Therefore, the movement (displacement) in the X direction of the upper wall 51 (upper structure 10) relative to the lower wall 52 (lower structure 20) is restricted, allowing safe construction.
[0060] In the seismic isolation method of this embodiment, the bearing wall 50 is cut into a side connected to the superstructure 10 and a side connected to the substructure 20 so that the seismic isolation device 30 can function, and a first fastening member 63 is inserted into the gap 53 formed at that time. Therefore, construction is easier than when a seismic plate 91 (surface material in this embodiment) is installed as in the comparative example shown in Figures 14A and 14B.
[0061] For example, in this embodiment, it is not necessary to form through holes 93 in the upper wall 51 and the lower wall 52 only for inserting the fastening member 92, as in the comparative example. Also, in this embodiment, it is not necessary to perform backfilling of the through holes 93 after removing the earthquake-resistant plate 92 (face material), as in the comparative example. Also, in this embodiment, since the through holes 93 are not formed in the upper wall 51 and the lower wall 52, as in the comparative example, there is no risk of damaging reinforcing bars or the like embedded in the upper wall 51 and the lower wall 52 when forming the through holes 93. Conversely, in this embodiment, it is not necessary to perform reinforcing bar inspection of the upper wall 51 and the lower wall 52 before forming the through holes 93, so that the construction work can be saved.
[0062] Thus, according to the seismic isolation method of this embodiment, the panel units 60 are installed on the load-bearing walls 50 separated into upper and lower parts, so that the load-bearing strength against horizontal external forces acting on the building during construction is maintained and construction can be carried out safely. In addition, compared to the comparative example, the installation of the panel units 60 requires less effort, and the construction of the seismic isolation work can be carried out easily. As a result, the construction period can be shortened and construction costs can be reduced. In addition, since no through holes for installing the panel units 60 are formed in the load-bearing walls 50, damage to the load-bearing walls 50 and reinforcing bars embedded in the load-bearing walls 50 can be reduced.
[0063] Up to this point, an example has been described in which the surface material unit 60 is installed on a bearing wall 50 having a wall surface along the X direction. However, the surface material unit 60 of this embodiment can also be installed on a bearing wall 50 (upper protruding portion and lower protruding portion) having a wall surface along the horizontal direction that intersects with the X direction.
[0064] For example, as shown in Fig. 13, a surface material unit 60 (60Y) can be installed on a bearing wall 50 (50Y) having a wall surface along the Y direction perpendicular to the X direction. This surface material unit 60 (60Y) can suppress misalignment of the superstructure 10 in the Y direction relative to the lower structure 20, even during construction after the columns 2, etc. have been cut. As shown in Fig. 13, by installing the surface material units 60 on the bearing walls 50 along the X direction and the Y direction, respectively, misalignment of the superstructure 10 in the X direction and the Y direction can be suppressed.
[0065] It is not necessary to install the surface material units 60 on all of the cut bearing walls 50, and as long as safe construction is possible, it is also possible not to install the surface material units 60 on some of the cut bearing walls 50. In general, when the strength of the opposing member in the X direction (e.g., bearing wall 50X on which surface material units 60X are installed) and the opposing member in the Y direction (e.g., bearing wall 50Y on which surface material units 60Y are installed) are approximately the same, the same number of opposing members are installed in the X direction and the Y direction. In addition, although not shown, a brace material may be disposed between the columns, and the surface material unit 60 may be used in combination with the brace material to increase the horizontal resistance during construction.
[0066] Furthermore, in the seismic isolation construction method of this embodiment, the seismic isolation devices 30 are installed on the multiple columns 2 on the construction floor, and the seismic isolation device installation process of installing the seismic isolation devices 30 on the columns 2 is performed multiple times. Therefore, it is preferable to perform the face material installation process and the pressure bonding joint process before at least one of the multiple seismic isolation device installation processes. In this way, the seismic isolation device installation process (and the column cutting process) can be safely performed by the bearing wall 50 on which the face material units 60 are installed.
[0067] In addition, in this embodiment, before the panel installation process, a gap formation process is carried out in which the load-bearing wall 50 (wall) extending vertically between the upper horizontal portion 11 and the lower horizontal portion 21 in the existing building 1 is cut to separate it into an upper wall 51 and a lower wall 52, and a gap 53 through which the first fastening member 63 is inserted is formed.
[0068] Therefore, the gaps 53 formed when the existing bearing walls 50 are cut can be used to install the surface material units 60, and seismic isolation work can be carried out efficiently. Also, before cutting the columns 2 etc. to install the seismic isolation devices 30, the existing bearing walls 50 (walls) that the existing building 1 originally had can be cut. This allows for efficient seismic isolation work. For example, if the walls have already been cut, the seismic isolation functions of the building can be demonstrated in a short period of time after the installation of the seismic isolation devices 30 for the entire building has been completed and it has been confirmed that the seismic isolation structure is functioning properly.
[0069] In this embodiment, the surface material unit 60 is installed on the existing load-bearing wall 50 (wall) that the existing building 1 originally had, but this is not limited to the above. The surface material unit 60 may also be installed on a wall (an upper wall and a lower wall that were originally installed in a separate state) that is newly constructed during seismic isolation work. In addition, the wall on which the surface material unit 60 is installed is not limited to a load-bearing wall (for example, a wall of reinforced concrete), and may be any wall that functions as a horizontal counterweight by installing the surface material unit 60 after cutting.
[0070] Furthermore, in this embodiment, in the crimping joining process, as shown in Figure 4A, a first attachment plate 65 is attached to one side surface 61a of the first surface material 61 in the Y direction, and a second attachment plate 66 is attached to the other side surface 62b of the second surface material 62 in the Y direction, and then the first surface material 61 and the second surface material 62 are crimped and joined to the upper wall 51 and the lower wall 52.
[0071] Therefore, the tension of the first fastening member 63 caused by tightening the second fastening member 64 (hexagonal nut 641) can be distributed and applied over a wide range of the face materials 61, 62 via the first and second attachment plates 65 and 66. In other words, it is possible to prevent the tension of the first fastening member 63 from acting locally on a part of the face materials 61, 62, causing deformation or the like of the face materials 61, 62. As a result, the face materials 61, 62 can be pressure-bonded to the wall surface of the bearing wall 50 over a wide range, and the frictional force between the face materials 61, 62 and the bearing wall 50 is increased. This increases the resistance of the bearing wall 50 on which the face material unit 60 is installed against horizontal external forces.
[0072] In addition, the tension of the first fastening member 63 acts in a range that spreads diagonally from the fastening position of the second fastening member 64 (the contact surface between the second fastening member 64 and the first attachment plate 65 or the second attachment plate 66) to the horizontal direction. For this reason, as in this embodiment, it is preferable to use thick square washers as the first attachment plate 65 and the second attachment plate 66, and to lengthen the horizontal distance (here, the Y direction) from the fastening position of the second fastening member 64 to the face materials 61, 62. By doing so, the tension of the first fastening member 63 acts on a wider range of the face materials 61, 62. Therefore, the face materials 61, 62 can be firmly pressure-bonded to the wall surface of the bearing wall 50, the frictional force between the face materials 61, 62 and the bearing wall 50 is increased, and the bearing strength of the bearing wall 50 on which the face material unit 60 is installed against horizontal external forces is increased.
[0073] Furthermore, in this embodiment, a first attachment plate 65 attached to the first surface member 61 and a second surface member 62 The second splice plate 66 that is spliced to the first splice plate 65 is formed by stacking a plurality of splice plates 65, 66 (here, two square washers) in the horizontal direction.
[0074] By doing so, the horizontal distance from the fastening position of the second fastening member 64 to the facing materials 61, 62 becomes longer, and the tensioning force of the first fastening member 63 acts on a wider range of the facing materials 61, 62. Therefore, the facing materials 61, 62 can be firmly pressure-bonded to the wall surface of the bearing wall 50, the frictional force between the facing materials 61, 62 and the bearing wall 50 increases, and the bearing strength of the bearing wall 50 on which the facing unit 60 is installed against horizontal external forces is increased.
[0075] However, without being limited to the above, for example, the first attachment plate 65 and the second attachment plate 66 may be thin members (washers), may be a single member (washer), or may be composed of three or more members (washers) stacked on top of each other.
[0076] In addition, the compression bonding process of this embodiment includes a filling process of filling filler 70 between the first surface material 61 and the upper wall 51 and the lower wall 52, and between the second surface material 62 and the upper wall 51 and the lower wall 52.
[0077] Therefore, the facing materials 61, 62 can be tightly attached to the bearing wall 50 via the filling material 70 without any gaps, and can be firmly pressure-bonded to the wall surface of the bearing wall 50. This increases the frictional force between the facing materials 61, 62 and the bearing wall 50, and increases the resistance of the bearing wall 50 on which the facing unit 60 is installed against horizontal external forces.
[0078] Moreover, in the seismic isolation method of this embodiment, a roughening process of the bearing wall 50 is performed before the face material installation process. The roughening process makes the surface of the bearing wall 50 uneven, thereby increasing the adhesion strength of the filler 70 to the bearing wall 50. Therefore, the face materials 61 and 62 can be firmly pressure-bonded to the bearing wall 50 via the filler 70.
[0079] In addition, after the roughening process, a water absorption regulator (for example, Refretreat manufactured by Sumitomo Osaka Cement Co., Ltd.) may be applied to the area of the bearing wall 50 where the facings 61, 62 are installed and the filler 70 is applied. By doing so, the adhesive strength of the filler 70 to the bearing wall 50 can be further increased.
[0080] However, the present invention is not limited to the above, and the filling material 70 may not be filled between the facing materials 61, 62 and the bearing wall 50, and the facing materials 61, 62 may be directly pressure-bonded to the bearing wall 50. Also, the roughening step may not be provided.
[0081] Furthermore, the seismic isolation device 30 of this embodiment is installed at a location (the cut portion of the column 2) different from the bearing wall 50 on which the surface material unit 60 is installed. In this case, the vertical length H1 (FIG. 3B) of the gap 53 between the upper wall 51 and the lower wall 52 is preferably shorter than the vertical length H2 (FIG. 11) of the seismic isolation device 30. Preferably, the vertical length H1 of the gap 53 is 70 mm or less.
[0082] By doing so, the tension of the first fastening member 63 inserted into the gap 53 can be received by the bearing wall 50 rather than by the space of the gap 53. Therefore, frictional force can be efficiently generated between the face materials 61, 62 and the bearing wall 50, and bending of the face materials 61, 62 can be suppressed. Moreover, since the size and thickness of the face materials 61, 62 can be reduced, construction costs can be reduced.
[0083] The above-mentioned embodiment is intended to facilitate understanding of the present invention, and is not intended to limit the present invention. The present invention can be modified or improved without departing from the spirit of the present invention, and it goes without saying that the present invention includes equivalents thereof. [Explanation of symbols]
[0084] 1 Existing building, 2 pillars, 3 beams, 10 superstructure, 11 upper horizontal part, 12 upper part of column (other upper protruding part), 20 lower structure, 21 lower horizontal part, 22 lower part of column (other lower protruding part), 30 seismic isolation device, 31 lower foundation, 32 upper foundation, 41: Upper column reinforcement part, 42: Lower column reinforcement part, 50 Load-bearing wall, 51 Upper wall (upper protrusion), 52 Lower wall (lower protrusion), 53 Gaps, 54 Joints, 55 Walls, 56 Fireproofing, 60 surface material unit, 61 first surface material, 62 second surface material, 63 first fastening member, 64 second fastening member, 65 first splice plate, 66 second splice plate, 67 position adjustment bolt, 70 Filling materials, 71 Formwork, 80 Temporary support member, 91 earthquake-resistant plate, 92 fastening member, 93 through hole,
Claims
1. A seismic isolation method in which a seismic isolation device is installed between an upper structure and a lower structure, The upper structure has an upper horizontal portion and an upper protruding portion protruding downward from the upper horizontal portion, The lower structure has a lower horizontal portion and a lower protruding portion protruding upward from the lower horizontal portion, a surface material installation process for installing a first surface material so as to straddle a gap between the upper protrusion and the lower protrusion in a vertical direction and along one side surface of the upper protrusion and the one side surface of the lower protrusion in a horizontal direction, and installing a second surface material so as to straddle the gap in the vertical direction and along the other side surface of the upper protrusion and the other side surface of the lower protrusion in the horizontal direction; a pressure-bonding process in which the first face material and the second face material are pressure-bonded to the upper protrusion and the lower protrusion by a first fastening member inserted along the horizontal direction into a through hole and the gap of the first face material and a through hole of the second face material, and a second fastening member screwed into the first fastening member; a seismic isolation device installation process for installing the seismic isolation device between the upper structure and the lower structure after the pressure bonding process; A seismic isolation method comprising the steps of:
2. The seismic isolation method according to claim 1, In the pressure bonding step, a first bonding plate is bonded to the one side surface of the first face material in the horizontal direction, and a second bonding plate is bonded to the other side surface of the second face material in the horizontal direction. A seismic isolation method characterized in that the first panel and the second panel are pressure-bonded to the upper protrusion and the lower protrusion with a splice plate attached.
3. The seismic isolation method according to claim 2, The first and second splice plates are configured by stacking a plurality of splice plates in the horizontal direction. This is a seismic isolation method characterized by the fact that
4. The seismic isolation method according to any one of claims 1 to 3, This is a seismic isolation method characterized in that the pressure bonding process includes a filling process of filling a filler between the first surface material and the upper protrusion and the lower protrusion, and between the second surface material and the upper protrusion and the lower protrusion.
5. The seismic isolation method according to any one of claims 1 to 4, the upper protrusion and the lower protrusion are walls extending in the vertical direction between the upper horizontal portion and the lower horizontal portion, A seismic isolation method characterized by including a gap forming process, which, prior to the panel installation process, cuts the wall to separate it into the upper protrusion and the lower protrusion, and forms the gap.
6. The seismic isolation method according to any one of claims 1 to 5, The upper structure has another upper protruding portion protruding downward from the upper horizontal portion, the lower structure has another lower protruding portion protruding upward from the lower horizontal portion, In the seismic isolation device installation step, the seismic isolation device is installed between the other upper protruding portion and the other lower protruding portion, A seismic isolation method, characterized in that the length of the gap in the vertical direction is shorter than the length of the seismic isolation device in the vertical direction.
7. an upper structure having an upper horizontal portion and an upper protruding portion protruding downward from the upper horizontal portion; a lower structure having a lower horizontal portion and a lower protruding portion protruding upward from the lower horizontal portion; A seismic isolation device installed between the upper structure and the lower structure; A seismic isolation structure having A first surface material that vertically spans the gap between the upper protrusion and the lower protrusion and is installed along one side surface of the upper protrusion and one side surface of the lower protrusion in the horizontal direction; a second surface member that spans the gap in the vertical direction and is installed along the other surface of the upper protrusion and the other surface of the lower protrusion in the horizontal direction; a first fastening member that crimps and joins the first face material and the second face material to the upper protrusion and the lower protrusion; a second fastening member that is screwed into the first fastening member; having A seismic isolation structure characterized in that the first fastening member is inserted along the horizontal direction through a through hole provided in the first panel, the gap, and a through hole provided in the second panel.
Citation Information
Patent Citations
Method for realizing base isolation structure of existing building
JP2001311314A
Shear stop fitting
JP2002021091A
Method for installing base-isolation device in existing column
JP2003161044A
Method for installing temporarily receiving extension member
JP2006083516A
Base isolation construction method for existing building
JP2007308979A