Supporting device and joint construction method using same

The support device and method allow for precise leveling of poured concrete by using a top level adjustment jig with a holding member and coupling members, addressing uneven joint lines in floor slab construction and achieving a neat finish.

JP7587265B2Active Publication Date: 2024-11-20AIRTEC AG
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2021014168
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-02-01
Publication Date
2024-11-20
Estimated Expiration
2041-02-01

AI Technical Summary

Technical Problem

Existing construction methods for large floor slabs result in uneven joint lines due to height differences, leading to an unattractive finished product.

Method used

A support device and method that uses a top level adjustment jig with a holding member and coupling members to adjust the position of a leveling member, allowing for precise and easy leveling of poured concrete by sandwiching the support member and changing the joining positions of the coupling members.

Benefits of technology

Enables accurate and easy adjustment of the top level of poured concrete, ensuring a neat finish by supporting the jig and facilitating uniform joint lines in floor slab construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007587265000001
    Figure 0007587265000001
  • Figure 0007587265000002
    Figure 0007587265000002
  • Figure 0007587265000003
    Figure 0007587265000003
Patent Text Reader

Abstract

To provide a support tool which contributes to facilitation of adjustment of a top end level of placed concrete for constructing a floor slab etc., and a construction joint method using the same.SOLUTION: In a support tool 20 for supporting a top end level adjusting jig 4 capable of holding a leveling member 10, a screw hole 25 for screwing a bolt 24 capable of advancing / retreating to / from a notched groove 21 is provided on one of two opposed pieces 22 and 23 opposed to each other across the notched groove 21, and insertion parts 30 and 31 are provided through which a male screw part of a support member 5 of the top end level adjusting jig 4 is inserted.SELECTED DRAWING: Figure 6
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a support suitable for use in supporting a jig for adjusting the top level of poured concrete, for example, when pouring concrete to construct a floor slab, and a joint construction method using this support. [Background technology]

[0002] A known construction method that is used when constructing relatively large floor slabs, etc., is to divide the space into multiple sections based on the amount of concrete that can be poured per day and other conditions, and pour the concrete sequentially in sections (see, for example, Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2010-1662 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, if a large unevenness (difference in height) occurs at the joint line (the boundary between adjacent sections) of the concrete poured using the above-mentioned joint construction method, the finished product will not be beautiful. In view of this problem, there is a demand for a method that allows the top level of poured concrete to be adjusted accurately and easily over the entire section.

[0005] The present invention has been made with the above-mentioned considerations in mind, and its object is to provide a support device that facilitates adjustment of the top level of poured concrete for constructing floor slabs, etc., and a joint construction method using the same. [Means for solving the problem]

[0006] In order to achieve the above object, the support device according to the present invention comprises: The base of the holding member that is passed through the support member and holds the leveling member is sandwiched between two connecting members that are connected to the support member, so that the holding member can be connected and fixed to the support member. In addition, the position of the holding member that is connected and fixed to the support member can be changed by changing the connecting positions of the two connecting members to the support member.A support for supporting a top end level adjustment jig, comprising two opposing pieces facing each other across a notched groove, one of which has a screw hole for screwing in a bolt that can be advanced and retreated into the notched groove; The two opposing pieces have longitudinally extending edges connected to each other by a pair of parallel side plates, and the pair of side plates are each roughly U-shaped in front view so as to form the notch groove, The male thread of the support member of the top end level adjustment jig is inserted The two insertion directions are different from each other. Provide a through hole One of the two insertion parts is formed by a through hole provided in each of the two opposing pieces, and the other is formed by a through hole provided in the pair of side panels. The support tool supports the support member by sandwiching the insertion part inserted into the support member with a connecting member connected to the support member, so that the support member is connected and fixed to the insertion part. (Claim 1).

[0007] The above support In the notch groove, a receiving piece protrudes outward from an edge of the opposing piece on the side where the screw hole for screwing the bolt is not provided, of the two opposing pieces. This is also possible (Claim 2).

[0008] On the other hand, in order to achieve the above object, the joint construction method according to the present invention is characterized in that a plurality of supports according to claim 1 or 2 are installed at intervals along the boundary where concrete is to be jointed. The method according to claim 1 A pouring method in which a top level adjustment jig is supported, leveling members are held using multiple top level adjustment jigs, and concrete is poured using the leveling members as a guide, wherein the support is installed by accepting rod-shaped members such as rebar or studs fixedly positioned in the area where the concrete is poured into the cutout groove and abutting the bolt against the rod-shaped member (Claim 3). In the joint construction method, the holding member of the top end level adjustment jig has a plate-shaped base in which a through hole is formed to pass through the support member, and a holding portion extending from one end of the base in two forks for holding the leveling member, and the holding portion has a screw support piece in which a female thread is formed to which the spacing adjustment screw is screwed, and a pressure-receiving piece arranged in a position opposite the tip of the spacing adjustment screw screwed into the female thread, and may be configured so that the leveling member can be held by the holding portion when the spacing adjustment screw is tightened so that it firmly abuts against the leveling member inserted into the holding portion (Claim 4). Effect of the Invention

[0009] The present invention provides a support device that facilitates adjustment of the top level of poured concrete for constructing a floor slab, etc., and a joint construction method using the same.

[0010] In other words, with the support device of the invention according to each claim of this application, a rod-shaped member such as a rebar or stud that is normally present in a fixed position in the area where concrete is about to be poured is received into the cutout groove, and the bolt is abutted against the rod-shaped member, thereby allowing the support device to be attached to the rod-shaped member.Furthermore, by inserting the male threaded portion of the support member of the top level adjustment jig into the insertion portion and appropriately connecting a connecting member such as a nut to this male threaded portion, the top level adjustment jig can be supported by the support device, which makes it possible to easily install the top level adjustment jig and, in turn, facilitates the adjustment of the top level of poured concrete for constructing a floor slab, etc.

[0011] Claim Item 1 With the support of the present invention, for example, a single type of support can be used in both cases where the rod-shaped member to which the support is attached is a horizontally extending rebar and where the rod-shaped member is a vertically extending stud.

[0012] In the joint construction method of the invention according to claim 3, the top level adjustment jig can be easily supported using the above-mentioned support device, and if this top level adjustment jig makes it easy to adjust the position of the leveling member, the top level and joint line of poured concrete for constructing floor slabs, etc. can be accurately and easily adjusted, thereby resulting in a neat finish. [Brief description of the drawings]

[0013] [Figure 1] FIG. 1A is a perspective view showing an example of construction using a joint construction method using a support device according to one embodiment of the present invention, and FIG. 1B is a perspective view showing an example of construction using a joint construction method according to a modified example of the present invention. [Diagram 2] 2A to 2D are explanatory diagrams illustrating a schematic configuration of the top end level adjusting jig shown in FIG. 1A. [Diagram 3] 2A to 2D are explanatory diagrams that illustrate a method of using the top end level adjusting jig shown in FIG. 1A. [Figure 4]1(A) to 1(B) and 1(C) to 1(F) are explanatory diagrams that illustrate the configuration and usage of the top end level adjusting jig shown in FIG. 1(B). [Diagram 5] 4A and 4B are a perspective view and a front view of the support. [Figure 6] FIG. 4 is a perspective view showing an example of a method of using the support tool. [Figure 7] 11 is a perspective view showing another example of a method of using the support tool. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0014] An embodiment of the present invention will be described below.

[0015] In the pouring joint method shown in Figure 1(A), for example, a deck plate 1 with a corrugated cross section (shown simply in Figure 1(A)) is laid on top of a steel beam (not shown) as a bottom formwork, and concrete is poured on top of this deck plate 1 to construct a floor slab. The concrete pouring space is divided into multiple sections, and the concrete is poured sequentially in sections.

[0016] In order to pour concrete in sections in sequence, multiple joint frames 2 are arranged closely together as formwork on the boundary (joint line) between the target section where concrete is to be poured and the non-target section where concrete has not yet been poured. In the example of Fig. 1(A), the first section S1 on the left side of the joint frames 2 lined up in a row from the front side to the back right side of the drawing is the target section, and the second section S2 on the right side is the non-target section.

[0017] The joint frame material 2 is constructed by containing a rectangular columnar elastic body (e.g., a porous elastic body such as a urethane material) in a bottomed box-shaped (bag-shaped) container (e.g., a resin film with a smooth surface such as a polyethylene material with a thickness of approximately 0.1 mm).

[0018] Here, after the concrete poured in the first section S1 has hardened, in order to pour concrete in the second section S2 and perform the joint, it is necessary to remove each of the joint frame materials 2, but during this removal, the concrete that has hardened in the first section S1 is in a state of adhering to the outer surface of the joint frame material 2. If the outer surface of the joint frame material 2 after removal is damaged due to this adhesion, it may be difficult to reuse it. Therefore, it is preferable to make the container that constitutes the outer surface of the joint frame material 2 out of a material that can be easily peeled off from the concrete, or to coat the outer surface of the joint frame material 2 with an appropriate release agent, etc., so that the joint frame material 2 can be easily peeled off from the concrete adhering thereto.

[0019] As described above, when arranging a plurality of joint frame materials 2 at the boundary between the first section S1 and the second section S2, in this example, in order to prevent the arrangement of the joint frame materials 2 from becoming disorganized due to the lateral pressure of the concrete poured in the first section S1, the joint frame materials 2 are appropriately arranged by abutting them against the reinforcing bars 3 arranged in a mesh pattern in a plan view throughout the entire concrete pouring space (target section and non-target section). Therefore, no special tools are required to arrange the joint frame materials 2.

[0020] When pouring concrete into the first section S1 with multiple joint frame materials 2 lined up at the boundary between the first section S1 and the second section S2, in this example, a top level adjustment jig (hereinafter referred to as the "jig") 4 is used to enable accurate and easy adjustment of the top level of the poured concrete.

[0021] As shown in Figure 2(B), the jig 4 includes a support member 5, a retaining member 6 which penetrates the support member 5, and a first connecting member 7 (see also Figure 2(A)) and a second connecting member 8 which are connected to the support member 5.

[0022] Here, the support member 5 is a fully threaded bolt, and the first connecting member 7 and the second connecting member 8 are nuts that are screwed onto this fully threaded bolt.

[0023] On the other hand, the holding member 6 has a plate-shaped base 9 having a through hole formed therein to be inserted into the support member 5, and a holding portion 11 extending from one end of the base 9 in two directions for holding a leveling member (an angle iron in this example) 10 as shown in FIG. 2(D) etc.

[0024] The retaining portion 11 has a screw support piece 14 having a female threaded portion 13 into which the gap adjustment screw 12 (see FIG. 2(D)) is screwed, and a pressure-receiving piece 15 arranged in a position opposite to the tip of the gap adjustment screw 12 screwed into the female threaded portion 13.

[0025] In such a jig 4, as shown in Figure 2 (B), the base 9 of the retaining member 6, which penetrates the support member 5, can be sandwiched between two connecting members 7, 8 connected to the support member 5, thereby connecting and fixing the retaining member 6 to the support member 5.

[0026] 2(D), when the interval adjusting screw 12 is tightened so as to strongly abut against the leveling member 10 inserted into the holding portion 11, the leveling member 10 can be held by the holding portion 11. When the interval adjusting screw 12 lightly abuts against the leveling member 10 inserted into the holding portion 11, the insertion depth of the leveling member 10 into the holding portion 11 can be adjusted, that is, the position of the leveling member 10 held by the holding portion 11 can be adjusted in a direction perpendicular to the axial direction of the support member 5 (a direction approaching or moving away from the base 9).

[0027] In addition, in order to ensure the adjustment range of the leveling member 10 held by the holding portion 11 (the adjustment range in the direction toward or away from the base 9), the female thread portion 13 of the screw support piece 14 needs to be provided at a position on the screw support piece 14 that is some distance away from the base 9, and it is preferable to provide it at a position near the tip of the screw support piece 14 (opposite the base 9).

[0028] 2(B), the holding member 6 is connected and fixed to the support member 5. However, if the two connecting members 7, 8 are separated from the base 9 while maintaining the base 9 penetrated by the support member 5, and the base 9 is no longer sandwiched between the two connecting members 7, 8, the holding member 6 can move in the penetration direction (axial direction of the support member 5) relative to the support member 5. Needless to say, the connecting positions of the two connecting members 7, 8 to the support member 5 can be changed, and the two connecting members 7, 8 can be stopped at any position of the support member 5, which is a fully threaded bolt. Therefore, by changing the connecting positions of the two connecting members 7, 8 to the support member 5, the position of the holding member 6 connected and fixed to the support member 5 can be changed, which means that the position of the leveling member 10 held by the holding member 6 can be adjusted in the axial direction of the support member 5.

[0029] Hereinafter, a description will be given of a joint construction method of this example using the jig 4, together with an explanation of how to use the jig 4. In the joint construction method of this example, the concrete pouring space is divided into a plurality of sections, and the concrete is poured in each section in sequence by repeating the following steps (1) to (6) once or a plurality of times (one less than the number of sections).

[0030] (1) First, a plurality of support members 5 are erected (planted) at intervals along the boundary (joint line) between the first section S1 (target section) and the second section S2 (non-target section) shown in Fig. 1(A). This erection can be performed, for example, by supporting the support members 5 with supports 20 (details of which will be described later).

[0031] (2) Next, as shown in Fig. 2(A), the first connecting member 7 is screwed to the support member 5, and then, as shown in Fig. 2(B), the support member 5 is passed through the through hole in the base 9 of the retaining member 6, the retaining member 6 is placed on the first connecting member 7, and the second connecting member 8 is screwed to the support member 5 from above. Then, the positions of the two connecting members 7, 8 are adjusted, and the height position of the retaining member 6 is provisionally adjusted so that it approximately matches the target top level of the poured concrete.

[0032] (3) After each jig 4 has been provisionally adjusted in this manner, the leveling member 10 is held by the holding portion 11 of each jig 4, as shown in Figures 2(C) and (D). Since accurate position adjustment (vertical and horizontal position adjustment) of the leveling member 10 will be performed in a later process, the positioning of the leveling member 10 at this stage does not need to be precise.

[0033] (4) A number of joint frame materials 2 are placed on the deck plate 1 without any space between them along the boundary (joint line) between the first section S1 and the second section S2 shown in Fig. 1(A) (see also Figs. 3(A)-(D)). At this time, the side of each joint frame material 2 on the second section S2 side, which is lined up in a row, is abutted against the reinforcing bar 3 extending parallel to this row, so that each joint frame material 2, which receives the lateral pressure of the concrete poured in the first section S1 in a later process, does not move toward the second section S2 side.

[0034] Each jig 4 is erected in a position where it is sandwiched between adjacent joint frame materials 2, and the two joint frame materials 2 that sandwich the jig 4 each elastically deform so as to adhere closely to the jig 4, thereby preventing the formation of a large gap between the two joint frame materials 2 that sandwich the jig 4.

[0035] (5) The level (height) and front-to-rear direction (front-to-rear direction when the first section S1 is the front and the second section S2 is the rear) position of the leveling member 10 held by each jig 4 are confirmed and adjusted.

[0036] Here, the vertical position adjustment (final adjustment) of the leveling member 10 can be performed by adjusting the joining positions of the two joining members 7, 8 relative to the support member 5. Also, the front-rear position adjustment of the leveling member 10 can be performed by bringing the spacing adjustment screw 12 into light contact with the leveling member 10 inserted into the holding portion 11, making the final adjustment in this state, and then tightening the spacing adjustment screw 12 so that it is in strong contact with the leveling member 10.

[0037] (6) Concrete is poured into the first section S1 using the leveling members 10 as a guide (reference point), and after an appropriate curing period has elapsed, the joint frame material 2 is removed for reuse, the leveling members 10 are detached from each jigs 4, and each jigs 4 and the supports 20 supporting them are also recovered.

[0038] The above steps (1) to (6) are carried out once or repeatedly a number of times. When pouring concrete into the last section, since this last section is surrounded by a normal, general formwork and the concrete already poured in the section adjacent to this section, there is no need to install a joint frame material 2. Furthermore, since pouring concrete into the last section can be performed to match the level of the concrete in the adjacent section, there is no need to install a jig 4.

[0039] In the joint construction method of this example described above, the use of the jig 4 makes it easy to adjust the position of the leveling member 10 in the vertical and front-to-back directions, so that the top level and joint line of poured concrete for constructing floor slabs, etc. can be accurately and easily adjusted, thereby resulting in a neat finish.

[0040] In this example, as shown in Fig. 1(A), the jig 4 (the support member 5 thereof) is supported in an upright state by a support 20. As shown in Fig. 5(A), this support 20 has a screw hole 25 into which a bolt 24 that can advance and retract into the notched groove 21 is screwed in one of two parallel opposing pieces 22, 23 that face each other across the notched groove 21.

[0041] 5(A), the two opposing pieces 22, 23 have their front and rear edges (edges extending in the longitudinal direction) connected to each other by a pair of parallel side plates 26, 27, and the side plates 26, 27 are each roughly U-shaped when viewed from the front so as to form the notched groove 21. Then, receiving pieces 28, 29 protrude outward from the edge of the notched groove 21 on the opposing piece 23 side.

[0042] Furthermore, as shown in FIG. 5(A), the support 20 is provided with two (one example of multiple) insertion portions 30, 31 through which the male threaded portion of the support member 5 of the jig 4 (in this example, the entire support member 5 from one end to the other end is a male threaded portion) is inserted.

[0043] In this example, the directions in which the support member 5 is inserted are different for the two insertion parts 30, 31. That is, as shown in Fig. 5(A), the insertion part 30 is provided so as to enable the support member 5 to penetrate the support 20 in its longitudinal direction, and specifically, is constituted by through holes 30a, 30b provided in the two opposing pieces 22, 23, respectively. The insertion part 31 is provided so as to enable the support member 5 to penetrate the support 20 in its thickness direction, and specifically, is constituted by through holes 31a, 31b provided in the pair of side panels 26, 27.

[0044] 1(A) and 6, when the jig 4 is fixed using a horizontally extending reinforcing bar (an example of a rod-shaped member fixedly arranged in an area where concrete is poured) 3, the support 20 can be attached to the reinforcing bar 3. Specifically, as shown in Fig. 6, the reinforcing bar 3 is received in the notched groove 21, and in this state, the bolt 24 is inserted into the notched groove 21 and strongly abuts (locks) against the reinforcing bar 3. At this time, as shown in Fig. 5(B), in order to prevent the support 20 from easily moving (to increase stability), the tip of the bolt 24 and the edge of the notched groove 21 are brought into close contact with the outer surface of the reinforcing bar 3.

[0045] On the other hand, as shown in Figure 7, when fixing the jig 4 using a stud (another example of a rod-shaped member fixedly positioned in the area where concrete is poured) 32 (see also Figure 1 (A)) that is welded to the upper surface of the deck plate 1 and extends vertically, the support 20 can be attached to this stud 32. Specifically, as shown in Figure 7, the stud 32 is received in the notch groove 21, and in that state, the bolt 24 is inserted into the notch groove 21 and firmly abuts (engages) against the stud 32.

[0046] In both the examples of Figures 6 and 7, when the bolt 24 is abutted against the reinforcing bar 3 or stud 32, as shown in Figure 5(B), in order to prevent the support 20 from moving easily (to increase stability), it is preferable that the tip of the bolt 24 and the edge of the notch groove 21 are brought into close contact with the outer surface of the reinforcing bar 3 or stud 32, and that the reinforcing bar 3 or stud 32 is prevented from slipping out of the gap between the tip of the bolt 24 and the notch groove 21.

[0047] 6 and 7, the support tool 20 supports the pole member 5 by clamping the insertion portion 30 or 31 inserted into the pole member 5 with connecting members 33, 34 such as nuts connected to the pole member 5, so that the pole member 5 is connected and fixed to the insertion portion 30 or 31. The connecting members 33, 34 may be the same as the first and second connecting members 7, 8.

[0048] In this example, which uses the support 20 described above, rod-shaped members such as reinforcing bars 3 and studs 32 that are normally positioned in a fixed state in the area where concrete is to be poured are received into the notch groove 21, and the bolt 24 is abutted against the rod-shaped member, thereby allowing the support 20 to be attached to the rod-shaped member.Furthermore, by inserting the support member 5 of the jig 4 into the insertion portions 30, 31 and appropriately connecting members such as nuts to this support member 5, the jig 4 can be supported by the support 20, which makes it possible to easily install the jig 4 and, in turn, facilitates the adjustment of the top level of poured concrete to construct a floor slab, etc.

[0049] Furthermore, as described above, the orientation of the support member 5 through which the insertion portions 30, 31 are inserted is different from each other (90 degree difference), so that one type of support 20 can be used in both cases where the rod-shaped member to which the support 20 is attached is a reinforcing bar 3 extending horizontally, and where the rod-shaped member is a stud 32 extending vertically.

[0050] It is to be noted that the present invention is not limited to the above-described embodiment, and can be modified in various ways without departing from the spirit and scope of the present invention. For example, the following modifications can be mentioned.

[0051] The support member 5 is not limited to a fully threaded bolt, but may be, for example, a bolt having a partial thread.

[0052] 1(A), the support member 5 is erected within the row of the joint frame members 2 (at a position sandwiched by the joint frame members 2), but this is not limiting, and the support member 5 may be erected outside the row of the joint frame members 2 (on the first section S1 side or the second section S2 side). For example, when the support member 5 is provided on the second section S2 side of the joint frame members 2, the holding member 6 may be extended so that the leveling member 10 can be held at a position on the first section S1 side of the joint frame members 2.

[0053] 2(B), the retaining member 6 is attached to the support member 5 so that the screw support piece 14 is located above the pressure-receiving piece 15, but this is not limiting, and the retaining member 6 may be attached to the support member 5 so that the screw support piece 14 is located below the pressure-receiving piece 15. However, there is an advantage in that it is easier to perform tasks such as tightening the gap adjustment screw 12 when the screw support piece 14 is located on the upper side.

[0054] In the example of Figure 2 (B), the base 9 and the screw support piece 15 of the retaining member 6 are continuously connected to form a single plate, and the screw support piece 14 is provided in a state where it protrudes upward from the plate, but this is not limited to the above. For example, the base 9 and the screw support piece 14 may be continuously connected to form a single plate, and the pressure receiving piece 15 may be provided in a state where it protrudes downward from the plate.

[0055] In the above embodiment, the leveling member 10 is an angle iron, but the leveling member 10 may be a flat bar, as shown in Fig. 1(B). In this case, it is possible to use a jig 16 (a jig for adjusting the top level) instead of the jig 4.

[0056] As shown in Figure 4(B), jig 16 has a first support portion 17a, which is a portion corresponding to support member 5 of jig 4, and a second support portion 17b extending in a direction perpendicular to first support portion 17a, and is equipped with support member 17 formed in an L-shaped rod shape overall, a retaining member 6 which is penetrated by support member 17 (first support portion 17a), and a first connecting member 7 (see also Figure 4(A)) and a second connecting member 8 which are connected to support member 17 (first support portion 17a).

[0057] That is, the jig 16 differs from the jig 4 in that the support member 5 is replaced with a support member 17, but is common in that the other components 6, 7, and 8 are used.

[0058] And, the jig 4, which is set upright on the deck plate 1 by the supports 20, enables the position of the leveling member 10 held by the holding member 6 to be adjusted in the up-down and front-to-back directions, and this is the same for the jig 16. However, as is clear from a comparison of Fig. 2(B) with Fig. 4(B), the attitude (horizontal) of the first support portion 17a, which is the portion of the jig 16 that corresponds to the support member 5, is rotated 90 degrees from the attitude (vertical) of the support member 5 in the jig 4, and therefore the members responsible for adjusting the position of the leveling member 10 in the up-down and front-to-back directions are different between the jig 4, 16.

[0059] That is, in the jig 4, the position of the leveling member 10 in the front-rear direction can be adjusted by adjusting the insertion depth of the leveling member 10 into the holding portion 11, but in the jig 16, the position can be adjusted in the up-down direction. Also, in the jig 4, the position of the leveling member 10 in the up-down direction can be adjusted by adjusting the joining positions of the two joining members 7, 8 to the support member 5, but in the jig 16, the position of the leveling member 10 in the front-rear direction can be adjusted by adjusting the joining positions of the two joining members 7, 8 to the first support portion 17a, which is the portion corresponding to the support member 5.

[0060] Such a jig 16 is used as shown in FIG. 1(B) and FIGS. 4(C) to (F), and the method of use thereof is generally the same as the method of use of the jig 4. As shown in FIG.

[0061] In the above embodiment, the vertical position adjustment of the leveling member 10 is performed only by the jig 4, but since the adjustment of the support height of the pillar member 5 by the support 20 also leads to the adjustment of the vertical position of the leveling member 10, the vertical position adjustment of the leveling member 10 may be performed by adjusting the support height of the pillar member 5 by the support 20 instead of or in addition to the vertical position adjustment by the jig 4.

[0062] Moreover, the support member 5 may be a headed bolt. In this case, for example, the connecting member 34 shown in FIG. 5(B) may be eliminated, and a head may be provided in place of the connecting member 34.

[0063] Needless to say, the modified examples given in this specification may be combined as appropriate. [Explanation of symbols]

[0064] 1 Deck plate 2. Joint frame material 3. Steel Bars 4 Top level adjustment jig 5 Support members 6 Retaining member 7 First connecting member 8 Second connecting member 9 base 10 Leveling materials 11 Holding part 12 Spacing adjustment screw 13 Female thread 14 Screw support piece 15 Pressure receiving piece 16 Top level adjustment jig 17 Support member 17a 1st pillar part 17b 2nd pillar part 20 Supports 21 Notch groove 22 Opposing piece 23 Opposing piece 24 Volts 25 screw hole 26 Side plate 27 Side plate 28 Support piece 29 Support piece 30 Insertion part 30a, 30b through hole 31 Insertion part 31a, 31b through hole 32 Stud 33 Connecting members 34 Connecting members S1 1st Section S2 2nd Section

Claims

1. A support for supporting a top end level adjustment jig, in which the base of a holding member that is inserted into a support member and holds a leveling member can be clamped between two connecting members connected to the support member, thereby connecting and fixing the holding member to the support member, and the position of the holding member that is connected and fixed to the support member can be changed by changing the connecting positions of the two connecting members relative to the support member, a screw hole for screwing a bolt capable of moving in and out of the notched groove is provided in one of the two opposing pieces that face each other across the notched groove; The two opposing pieces have longitudinally extending edges connected to each other by a pair of parallel side plates, and the pair of side plates are each roughly U-shaped in front view so as to form the notch groove, The male thread portion of the support member of the top end level adjustment jig is inserted into two insertion portions having different insertion directions, One of the two insertion portions is formed by a through hole provided in each of the two opposing pieces, and the other is formed by a through hole provided in the pair of side panels, The support device supports the support member by clamping the insertion portion inserted into the support member with a connecting member connected to the support member, so that the support member is connected and fixed to the insertion portion.

2. A support device as described in claim 1, in which a receiving piece protrudes outward from the edge of the opposing piece in the cutout groove that does not have a screw hole for screwing the bolt into.

3. A joint construction method in which the top end level adjustment jig according to claim 1 is supported by a plurality of supports according to claim 1 or 2 installed at intervals along the boundary where concrete is to be jointed, a leveling member is held using a plurality of top end level adjustment jigs, and concrete is poured using the leveling member as a guide, The support is installed by receiving a rod-shaped member such as a reinforcing bar or stud fixed in the area where concrete is poured into the notched groove and abutting the bolt against the rod-shaped member.

4. The holding member of the top end level adjustment jig has a plate-shaped base having a through hole formed therein to be inserted into the support member, and a holding portion extending from one end side of the base in two branches for holding a leveling member; the holding portion has a screw support piece having a female thread portion into which the gap adjustment screw is screwed, and a pressure-receiving piece disposed at a position opposite to a tip of the gap adjustment screw screwed to the female thread portion, 4. The joint construction method according to claim 3, wherein the leveling member can be held by the holding portion by tightening the interval adjustment screw so that the interval adjustment screw abuts firmly against the leveling member inserted into the holding portion.

Citation Information

Patent Citations

  • Floor concrete ceiling indicator

    JP1992092950U

  • Indication tool for top end of cast-in-place concete in half-precast floor slab

    JP1999182045A

  • Top end indicator for slab concrete, its extension hardware, and method of forming concrete slab using the indicator and the hardware

    JP2007224572A

  • Construction joint frame member

    JP2010001662A

  • Top end pointer

    JP2019027229A