Shear reinforcement construction management method
The construction management method using IC tags in spacers for reinforcing bars in concrete structures addresses the challenge of ensuring correct placement and specification, providing reliable verification and detection of errors, thus improving the shear reinforcement process.
Patent Information
- Application Number
- JP2021146632
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-09-09
- Publication Date
- 2024-11-21
- Estimated Expiration
- 2041-09-09
AI Technical Summary
Conventional shear reinforcement methods in existing concrete structures face challenges in ensuring that reinforcing bars with appropriate specifications are correctly inserted and buried at all locations, as they rely on drawings and electromagnetic radar which may not accurately detect existing reinforcing bars, leading to erroneously drilled holes and lack of verification for fraud.
A construction management method using IC tags embedded in spacers for ensuring cover thickness, which record and verify the position and specifications of reinforcing bars, allowing for remote confirmation and authentication through a reader/writer system, ensuring accurate placement and preventing unauthorized information writing.
This method guarantees that reinforcing bars are correctly placed with appropriate specifications and cover thickness, enabling efficient management and detection of erroneously drilled holes, thereby enhancing the reliability and integrity of the shear reinforcement process.
Smart Images

Figure 0007588056000001 
Figure 0007588056000002 
Figure 0007588056000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a construction management method for a shear reinforcement method performed on an existing concrete structure. [Background technology]
[0002] Conventionally, a shear reinforcement method has been known as a method for seismic reinforcement of existing concrete structures. The shear reinforcement method is a method for increasing shear stress by forming holes in the surface of an existing structure and embedding steel materials inside the holes (see, for example, Patent Document 1 and Patent Document 2). [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2014-181473 A [Patent Document 2] JP 2015-218465 A Summary of the Invention [Problem to be solved by the invention]
[0004] When implementing the shear reinforcement method, reinforcing bars are inserted as reinforcing steel into holes drilled in an existing concrete structure, and then the holes are backfilled. Although it depends on the scale of the existing concrete structure, shear reinforcement bars are usually buried in 500 to 1000 places in the same structure.
[0005] In the shear reinforcement method, the specifications of the reinforcing bars used are set according to the reinforcement points. In other words, it is necessary to embed shear reinforcement bars of appropriate specifications in 500 to 1,000 places in the existing concrete structure.
[0006] When drilling holes for embedding shear reinforcement bars in existing concrete structures, it is checked in advance using drawings and electromagnetic radar whether there are existing reinforcing bars such as main reinforcement bars or distribution bars at the drilling hole formation location. However, the actual condition of the existing concrete structure may differ from the drawing, and there may be existing reinforcing bars that were not detected by the electromagnetic radar. In such cases, the drilled holes are backfilled as mis-drilled holes because the shear reinforcement bars cannot be embedded due to interference with the existing reinforcing bars.
[0007] After the shear reinforcement method is applied, a completion inspection is generally conducted at a specified time. During this completion inspection, it is necessary to check whether the rebars of the specified specifications have been properly inserted in each location of the existing concrete structure, and whether the traces of backfilling indicate correct rebar insertion locations or incorrect drilling locations.
[0008] In the conventional method, only representative points are photographed and recorded, and it is not possible to completely guarantee that the appropriate rebars are used in all reinforcement points. Moreover, these photographs are usually taken before the shear reinforcement bars are inserted, so there is currently no way to check whether or not there has been any fraud.
[0009] In view of the above problems, the present invention aims to provide a method for easily managing construction details, such as whether appropriate reinforcing bars are used in each location where shear reinforcement construction methods have been implemented. [Means for solving the problem]
[0010] The construction management method for shear reinforcement of an existing concrete structure according to the present invention comprises the steps of: A step (a) of backfilling the first drilled hole portion formed by cutting in a depth direction from the surface to the center of the existing concrete structure, with a shear reinforcement bar embedded in the first drilled hole portion together with a spacer for ensuring a cover thickness having an IC tag embedded therein; A step (b) of writing first information including information on the embedded position of the cover thickness securing spacer and information on the specification of the shear reinforcement bar to the IC tag before or after the step (a); (c) a step of recording information corresponding to the first information in a management storage unit; After the steps (b) and (c) are performed, a step (d) of communicating with the IC tag from a reader or a reader / writer from outside the surface of the existing concrete structure to read the first information recorded in the IC tag; The method further comprises a step (e) of comparing the first information read in the step (d) with the first information recorded in the memory unit.
[0011] According to the above method, the first information including information on the buried position of the cover thickness securing spacer and information on the specification of the shear reinforcement is written on the IC tag buried in each cover thickness securing spacer, so that it is possible to confirm that the appropriate shear reinforcement is buried in the location by comparing the information written on the IC tag with information previously recorded in the management memory unit. When confirming, the first information can be read by simply communicating with the IC tag at the buried location from the outside of the existing concrete structure using a reader or reader / writer. That is, the specification of the shear reinforcement buried in the location can be detected by the read first information. Furthermore, it is possible to confirm whether the read first information is correct by comparing the read first information with the first information recorded in the memory unit.
[0012] Among the first information, the information on the buried position of the cover thickness securing spacer is information indicating at what position in the existing concrete structure the cover thickness securing spacer is buried. For example, Fig. 1 is a drawing showing a schematic diagram of the surface state of an existing concrete structure after a shear reinforcement method is applied. Backfilling marks remain at a number of points on the surface of the existing concrete structure 1. Fig. 1 shows a schematic diagram of the situation where backfilling marks remain at points A1-A5, B1-B5, and C1-C5 on the surface of the existing concrete structure 1.
[0013] The information for identifying the points A1, A2, etc. on the surface of the existing concrete structure 1 in Fig. 1 corresponds to the information on the buried position. In other words, the information on the buried position is information for distinguishing between buried positions formed in the existing concrete structure. Note that Fig. 1 will be described later.
[0014] The information on the specifications of the shear reinforcement bar among the first information is information that allows the physical properties of the shear reinforcement bar to be recognized. Specific examples include material (type of reinforcing bar, presence or absence of plating, type of plating material, type of coating material, etc.), length, diameter, etc.
[0015] However, if the shear reinforcement is exposed to the outside air, it will corrode due to rust, etc. For this reason, the entire reinforcement is positioned completely within the cut hole so that the end of the reinforcement is not exposed, and then the repair material is filled in. At this time, if the shear reinforcement is too close to the surface, it cannot be denied that corrosion may progress little by little over time, so it is preferable to bury the shear reinforcement with a certain degree of cover thickness.
[0016] As mentioned above, with the conventional method, photographic records were only kept for representative locations, so it was not possible to guarantee that appropriate cover thickness had been secured in all locations where shear reinforcement bars were buried.
[0017] According to the above method, since the spacer for ensuring the cover thickness is buried together with the shear reinforcement bar, it is guaranteed that the shear reinforcement bar is buried with the cover thickness secured for at least the length of the spacer.
[0018] However, since it is expected that the size of this spacer will differ depending on the existing concrete structure and the buried location, from the standpoint of accurately guaranteeing the actual value of the cover thickness, it is preferable for information regarding the cover thickness of the shear reinforcement bar within the first drilled hole section to be included in the first information.
[0019] In other words, the first information may include information regarding the cover thickness of the shear reinforcement bar within the first drilled hole portion.
[0020] According to the above method, since the information on the cover thickness is included in the first information, the cover thickness of the shear reinforcement buried in the location can be easily confirmed by reading the first information from the IC tag with a reader or a reader / writer. Also, by comparing this information with the information recorded in the management storage unit, it is possible to ensure that the cover thickness is an appropriate value.
[0021] In the above method, the step (b) is a step carried out before the step (a), The step (a) may include a step of embedding the cover thickness securing spacer, which includes the IC tag with the first information written therein, in the first drilled hole.
[0022] The storage unit is a storage area in a server, The step (c) includes a step of reading the first information written in the IC tag that is built into the spacer for ensuring the covering thickness by communicating with the reader or reader / writer, and transmitting the read first information to the server via a telecommunication line; The step (e) may include a step of reading the first information recorded in the server via the telecommunications line, and may involve comparing the first information read from the server with the first information read in the step (d).
[0023] In this case, in step (c), the first information may be transmitted to the server by a reader or reader / writer equipped with a function for connecting to a telecommunications line (such as the Internet), or may be transmitted to the server by a communication device separate from the reader or reader / writer.
[0024] The construction management method for shear reinforcement further includes a step (f) of transporting the cover thickness securing spacer having the IC tag with the first information written therein to a target location where the existing concrete structure exists before the step (a), The step (a) may include a step of embedding the cover thickness securing spacer transported in the step (f) in the first drilled hole portion.
[0025] In the above method, the step (b) is a step of writing, in addition to the first information, second information related to authentication for accessing information recorded in the server to the IC tag; the step (c) includes a step of reading the second information in addition to the first information using the reader or reader / writer, and transmitting the first information to the server after performing an authentication process for connection to the server based on the second information; the step (d) is a step of reading the second information in addition to the first information by using the reader or reader / writer; The step (e) may include a step of reading the first information recorded in the server after performing an authentication process for connection to the server based on the second information.
[0026] According to the above method, unauthorized writing of information to the server is prevented, so that the degree of assurance of information such as the specifications of the shear reinforcement bars embedded in each location can be further increased.
[0027] The construction management method for shear reinforcement includes, before the step (a), a step (f) of transporting the cover thickness securing spacer incorporating the IC tag before the first information is written to a target location where the existing concrete structure exists; and (g) attaching a two-dimensional code having at least the first information written thereon to the shear reinforcement bar; Step (b) may include a step of reading the two-dimensional code affixed to the shear reinforcement bar using a two-dimensional code reader, and writing the first information contained in the two-dimensional code to the IC tag built into the cover thickness spacer transported in step (f) using a reader / writer.
[0028] the step (b) is a step of writing, in addition to the first information, second information related to authentication for accessing information recorded in the server to the IC tag using the reader / writer; the step (c) includes a step of transmitting the first information to the server after performing an authentication process for connection to the server based on the second information; the step (d) is a step of reading the second information in addition to the first information by using the reader or reader / writer; The step (e) may include a step of reading the first information recorded in the server after performing an authentication process for connection to the server based on the second information.
[0029] In the above method, the second information recorded in the reader / writer may be written to the IC tag. Also, in step (c), the second information may be recorded in advance on a device that transmits the information to a server, and the second information may be transmitted to the server to perform access authentication, or the reader or reader / writer may be used to read the second information in addition to the first information from the IC tag, and then the second information may be transmitted to the server to perform access authentication.
[0030] According to the above method, unauthorized writing of information to the server is prevented, so that the degree of assurance of information such as the specifications of the shear reinforcement bars embedded in each location can be further increased.
[0031] The construction management method for shear reinforcement includes the steps of: A process (h1) of backfilling the second drilled hole portion resulting from an erroneous drilling, which is formed by cutting in a depth direction from the surface to the center of the existing concrete structure, without embedding the shear reinforcement bar, and in a state in which the cover thickness securing spacer having the IC tag built in is embedded, (h2) a step of writing third information regarding erroneous drilling to the IC tag before or after the step (a); and (h3) recording information corresponding to the third information in the storage unit, The step (d) is a step of reading the third information in addition to the first information recorded in the IC tag, The step (e) includes a step of comparing the third information read in the step (d) with the third information recorded in the memory unit, and if the information read in the step (d) and the information recorded in the memory unit are mutually corresponding third information, it may be possible to detect that the cover thickness ensuring spacer is embedded in the second drilled portion resulting from an erroneous drilling.
[0032] The following description will be given with reference to Figure 1. Backfilling traces (2a, 2b) remain on the surface of an existing concrete structure 1 in multiple locations (here, A1-A5, B1-B5, C1-C5). When backfilling, the cut holes are filled with a repair material such as mortar. This repair material is not always the same color as the existing concrete structure, so the backfilling traces can be confirmed by visual inspection.
[0033] Here, if the hole is drilled incorrectly and backfilled due to the risk of interference with existing rebars, etc., it is common to drill a hole again in an appropriate nearby location and then bury the shear reinforcement. In the example of Figure 1, points A1, A3, and C1, for example, are diagrammatically shown as such a situation.
[0034] However, it is not possible to distinguish between the backfill trace 2a after shear reinforcement and the backfill trace 2b of an incorrectly excavated hole just by looking from the outside. In other words, with the conventional method, it is not possible to distinguish between the backfill trace 2a after shear reinforcement and the backfill trace 2b of an incorrectly excavated hole, particularly at points A1, A3, and C1. Also, even if it is possible that the backfill trace 2b is formed at point C3, with the conventional method it is not possible to detect whether point C3 is the backfill trace 2a after shear reinforcement or the backfill trace 2b of an incorrectly excavated hole.
[0035] In contrast, according to the above method, if the backfilling trace is due to backfilling the second drilled portion resulting from erroneous drilling, the IC tag built into the cover thickness securing spacer embedded in the second drilled portion has third information written therein indicating that the hole is erroneously drilled. Therefore, by having the reader or reader / writer notify the IC tag in step (d) during the completion inspection, if the read information includes the third information, it is possible to recognize that the backfilling trace at that location is due to erroneous drilling. Furthermore, by comparing this third information with the information recorded in the memory unit in step (e), the accuracy of the information can be guaranteed.
[0036] In addition, in the step (c), in addition to the information corresponding to the first information, fourth information including at least one of image information of the location corresponding to the first hole drilling portion or the second hole drilling portion and information on the construction date and time may be recorded in the storage unit. In this case, in the step (e), when the first information or the third information is collated, the fourth information may also be read out from the storage unit. Effect of the Invention
[0037] According to the present invention, it is possible to easily manage the details of construction work, such as whether appropriate reinforcing bars are used at each location where shear reinforcement construction method is implemented. [Brief description of the drawings]
[0038] [Figure 1] 1 is a drawing showing a schematic diagram of the surface condition of an existing concrete structure after a shear reinforcement method has been applied. [Diagram 2] 1 is a flowchart illustrating a schematic diagram of an overall processing procedure of a construction management method for shear reinforcement. [Diagram 3] 11 is a part of a flowchart illustrating an example of a detailed processing procedure of a shear reinforcement construction step S1 in the first embodiment. [Figure 4] FIG. 1 is a conceptual diagram showing a procedure for performing shear reinforcement on an existing concrete structure. [Diagram 5] FIG. 1 is a conceptual diagram showing a procedure for performing shear reinforcement on an existing concrete structure. [Figure 6A] 1 is a diagram showing a schematic view of a shear reinforcement bar with an anchoring jig attached thereto, together with a spacer. [Figure 6B] 1 is a schematic diagram showing a shear reinforcement bar without an anchoring jig attached thereto, together with a spacer. [Figure 7A] 1 is a diagram showing a schematic diagram of an example of a method for manufacturing a spacer having an IC tag built in. [Figure 7B] 1 is a diagram showing a schematic diagram of an example of a method for manufacturing a spacer having an IC tag built in. [Figure 8] 1 is a drawing for explaining the cover thickness of shear reinforcement bars. [Figure 9] FIG. 11 is a block diagram showing a schematic diagram of the processing carried out in step S19. [Figure 10] 11 is a part of a flowchart illustrating an example of a detailed processing procedure of a shear reinforcement construction step S1 in the first embodiment. [Figure 11] FIG. 11 is a block diagram showing a schematic diagram of the process carried out in step S13b. [Figure 12] FIG. 11 is a block diagram showing a schematic diagram of the process carried out in step S19a. [Figure 13] 11 is a part of a flowchart showing a schematic example of a detailed processing procedure of the completion inspection process S2. [Figure 14A] This is a block diagram showing the processing contents in the completion inspection process S2. [Figure 14B] This is another block diagram showing the processing contents in the completion inspection process S2. [Figure 15] 13 is a part of a flowchart showing an example of a detailed processing procedure of a shear reinforcement construction step S1 in the second embodiment. [Figure 16] FIG. 11 is a block diagram showing a schematic diagram of the processing carried out in step S14. [Figure 17] FIG. 11 is a block diagram showing a schematic diagram of the processing carried out in step S15. [Figure 18] 13 is a part of a flowchart showing an example of a detailed processing procedure of a shear reinforcement construction step S1 in the second embodiment. [Figure 19] FIG. 11 is a block diagram showing a schematic diagram of the process carried out in step S13b in the second embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0039] The embodiment of the method for managing construction of shear reinforcement according to the present invention will be described with reference to the drawings as appropriate. However, the drawings are schematic illustrations, and the actual dimensional ratios do not necessarily match the dimensional ratios in the drawings, and the dimensional ratios do not necessarily match between the drawings.
[0040] [First embodiment] 2 is a flow chart showing a schematic diagram of the overall procedure of the construction management method for shear reinforcement according to the present embodiment. The management method is divided into two steps: a shear reinforcement construction process S1 and a completion inspection process S2.
[0041] The shear reinforcement work process S1 corresponds to a process of actually performing shear reinforcement work on the existing concrete structure 1. On the other hand, the completion inspection process S2 is carried out after the completion of the shear reinforcement work process S1, and corresponds to a process of checking and inspecting whether the shear reinforcement work on the existing concrete structure 1 has been properly performed. The timing of the completion inspection process S2 varies depending on various circumstances, but as a typical example, it is carried out within a few days after the completion of the shear reinforcement work process S1.
[0042] <Shear reinforcement construction process S1> 3 is a flow chart showing an example of a detailed procedure of the shear reinforcement construction step S1. The reference numerals of steps S11 to S13 and S16 to S19 below correspond to the reference numerals in the flow chart of FIG.
[0043] (Step S11) As shown in Fig. 4, a bottomed hole 3 is formed in an existing concrete structure 1 (hereinafter, abbreviated as "existing structure 1") on which shear reinforcement work is to be performed. When forming the hole 3, a drilling device such as a core drill or a high-pressure water injection device such as a water jet can be used.
[0044] This hole drilling section 3 is provided in order to secure a space for inserting the shear reinforcement bars 5 in the later step S16. Therefore, it is necessary to form the hole drilling section 3 in a location that avoids existing reinforcing bars such as main bars and distribution bars that are provided in the existing structure 1. Therefore, before forming the hole drilling section 3, it is preferable to determine in advance the installation locations of the main bars and distribution bars using a reinforcing bar detection device that uses electromagnetic waves, such as an RC radar.
[0045] When forming the hole drilling portion 3, a widening process may be performed to widen the inner diameter of the hole drilling portion 3 at a position close to the wall surface 1a, i.e., at a position close to the opening surface. After the hole drilling portion 3 is formed, pressurized air may be sent into the hole drilling portion 3 using an air compressor or the like as necessary to remove foreign matter such as drilling chips from the hole drilling portion 3.
[0046] In Fig. 4, the insertion direction of the shear reinforcement bars 5 is the X direction, and the height direction (typically the vertical direction) of the existing structure 1 is the Y direction. In the following drawings, the coordinate axes are set in a similar manner unless otherwise noted.
[0047] (Step S12) During the execution of step S11, the formed hole drilling section 3 may interfere with main reinforcement or distribution reinforcement already placed in the existing structure 1. Even if it is confirmed based on the drawing or radar detection results before the execution of step S11 that there are no main reinforcement or distribution reinforcement in the planned location for forming the hole drilling section 3, it is possible that such an incident may occur due to circumstances such as the drawing and the actual position of the rebar being different, or the radar being unable to detect them correctly.
[0048] This step S12 is a process for confirming that the formed hole drilling section 3 does not interfere with the main reinforcement or distribution reinforcement already placed in the existing structure 1, i.e., that the hole has not been drilled erroneously.
[0049] (Step S13, Step S16) If the hole drilling section 3 is not erroneously drilled (Yes in step S12), the shear reinforcement bar 5 is embedded in the hole drilling section 3 (see FIG. 5). If the hole drilling section 3 is not erroneously drilled, the hole drilling section 3 formed in step S11 corresponds to the "first hole drilling section" (step S13).
[0050] Specifically, first, an amount of fixing material (grout material) 7 is injected into the drilled portion 3 so that it will not overflow out through the opening of the drilled portion 3 even when the shear reinforcement steel bar 5 is inserted later as a shear reinforcement member. Through this process, the fixing material 7 is filled into a predetermined area including the inner bottom 3a of the drilled portion 3. As the fixing material 7, mortar, cement milk (a mixture of cement and water), or resin can be suitably used, and among these, mortar is particularly preferred. After this, in order to insert the shear reinforcement steel bar 5 into the drilled portion 3 with the fixing material 7 injected inside, the fixing material 7 is made of a material that has high fluidity before hardening and hardens over time.
[0051] Next, as shown in Fig. 5, the shear reinforcement bar 5 is inserted in the +X direction into the drilled hole 3. The shear reinforcement bar 5 enters the drilled hole 3 in the +X direction while pushing aside the anchorage material 7 that has already been injected.
[0052] In the example of Fig. 5, a structure in which fixing jigs (5a, 5b) are attached to both ends of the shear reinforcement 5 in the longitudinal direction is shown, but as described later with reference to Figs. 6A to 6B, the presence or absence of these jigs (5a, 5b) is optional. The shear reinforcement 5 is inserted to a position where the end on the -X side (jig 5a if jig 5a is attached) is completely housed in the drilled hole 3. More specifically, in the next step S17, the shear reinforcement 5 is inserted in the depth direction (+X direction) to a position where a space can be secured for completely embedding the spacer 10 at a position adjacent to the -X side of the shear reinforcement 5.
[0053] (Step S17) Next, as shown in Fig. 5, a spacer 10 for ensuring the cover thickness of the shear reinforcement (hereinafter simply abbreviated as "spacer 10") is inserted into the drilled hole 3. As shown in Fig. 9 described later, this spacer 10 has an internal IC tag 30 capable of communicating with a reader or reader / writer (hereinafter collectively referred to as "reader / writer 40"). This IC tag 30 may be present completely embedded inside the spacer 10.
[0054] In this embodiment, first information i1 including information on the embedding position of the spacer 10 and information on the specifications of the shear reinforcement 5 to be embedded in the embedding position is written in advance in the IC tag 30. For example, for the spacer 10 to be embedded in the position A2 in the existing structure 1 in Fig. 1, the first information i1 includes information on the specifications (material, length, diameter, etc.) of the shear reinforcement 5 to be embedded in the position A2 and information for identifying this "position A2". Note that the first information i1 may also include information on the cover thickness L5 of the shear reinforcement 5 (see Fig. 8 described later).
[0055] Furthermore, in addition to the first information i1, second information i2 related to authentication for connecting to a server 50 shown in Fig. 9 described later may be written in the IC tag 30. The second information i2 may be the same information for the same existing structure 1, for example, or may be different information for each buried location. Since the second information i2 is used for authentication of connection to the server 50 described later, the contents of the information are arbitrary as long as the function is fulfilled.
[0056] The spacer 10 is inserted until it abuts against the end of the -X side of the shear reinforcement bar 5 (the jig 5a if the jig 5a is attached). The spacer 10 is inserted so that the end of the -X side is not exposed on the wall surface 1a side of the existing structure 1.
[0057] As shown in Fig. 6A, when the jigs (5a, 5b) are attached to the shear reinforcement bar 5, the end face (first surface 11) on the +X side of the spacer 10 abuts against the jig 5a. Also, as shown in Fig. 6B, when the jigs (5a, 5b) are not attached to the shear reinforcement bar 5, the end face (first surface 11) on the +X side of the spacer 10 abuts against the end of the shear reinforcement bar 5 on the -X side.
[0058] 7A and 7B are diagrams illustrating an example of a method for manufacturing a spacer 10 incorporating an IC tag 30. In FIG.
[0059] The body of the spacer 10 is made of mortar, ceramics, plastic, or the like, and is preferably made of mortar or ceramics. When the body of the spacer 10 is made of mortar, high-strength mortar is preferably used. When the body of the spacer 10 is made of ceramics, Al2O3 or ZrO2 is preferably used.
[0060] The shape of the spacer 10 may be a columnar body, a shape in which a columnar body and a frustum are combined, etc. The present invention is not limited to the shape of the spacer 10.
[0061] When manufacturing the spacer 10, for example, a method of bonding two partial spacers (10A, 10B) as shown in Fig. 7A can be used. For example, a hole 31 for embedding an IC tag 30 is provided on one surface 10a of one partial spacer 10A, and the IC tag 30 is embedded in this hole 31. Thereafter, the surface 10b of the other partial spacer 10B and the surface 10a of the partial spacer 10A are bonded together, for example, via mortar. This results in a spacer 10 with the IC tag 30 embedded therein, as shown in Fig. 7B.
[0062] Any known IC tag can be used as the IC tag 30, as long as it can be powered and written to and read from the memory at the same time using a reader / writer 40 (see FIG. 9, described later). The frequency band of radio waves transmitted and received by the IC tag 30 can be a general range of several hundred kHz to 3 GHz.
[0063] The IC tag 30 is provided with an antenna (not shown), and receives radio waves from the reader / writer 40 by this antenna. As will be described later when explaining the completion inspection process S2, the IC tag 30 incorporated in the spacer 10 receives radio waves from the reader / writer 40 located outside the wall surface 1a of the existing structure 1. Therefore, from the viewpoint of ensuring the radio wave sensitivity required for reception, the embedding depth d30 of the IC tag 30 from the side closer to the wall surface 1a of the existing structure 1, that is, from the second surface 12 in FIG. 7B, is restricted within a certain range. Preferably, assuming the length of the spacer 10 in the direction parallel to the depth direction (i.e., the X direction) of the drilled hole 3 is d10, the embedding depth d30 of the IC tag 30 is preferably set to d30 < 0.6×d10. Also, when d30 < 0.2×d10, there is a possibility that the strength of the spacer 10 itself becomes small. Therefore, the embedding depth d30 of the IC tag 30 is preferably set to 0.2×d10 < d30 < 0.6×d10.
[0064] Also, from the viewpoint of enhancing the reception sensitivity, the reception surface of the IC tag 30 is preferably installed so as to be substantially parallel to the opening surface of the drilled hole 3 (see FIG. 5). More specifically, it is preferable that the spacer 10 in a state where the IC tag 30 is embedded on a surface substantially parallel to the first surface 11 or the second surface 12 is inserted into the drilled hole 3 along the direction orthogonal to the first surface 11 or the second surface 12.
[0065] For example, the spacer 10 incorporating the IC tag 30 manufactured by the above method is transported to the site of the existing structure 1 and embedded in the drilled hole 3 in step S17.
[0066] In this embodiment, as described above, the necessary information (i1, i2) is written in advance to the IC tag 30 built into the spacer 10. The information (i1, i2) may be written to the IC tag 30 before it is embedded in the spacer 10, or may be written after it is embedded in the spacer 10. In this embodiment, the process of writing this information corresponds to process (b). Note that the process of transporting the spacer 10, which includes the IC tag 30 with the information (i1, i2) written therein, to the site of the existing structure 1 corresponds to process (f).
[0067] (Step S18) 5, the remaining space in the drilled portion 3 is filled with repair material 8, and the opening surface of the drilled portion 3 is connected to the wall surface 1a of the existing structure 1, thereby closing the opening surface. This step backfills the drilled portion 3 (first drilled portion).
[0068] The repair material 8 may be the same material as the fixing material 7 or may be different. However, unlike the fixing material 7, the repair material 8 is injected for the purpose of ensuring continuity with the wall surface 1a of the existing structure 1, and therefore a part of the repair material 8 is exposed to the outside. From this viewpoint, it is preferable that the repair material 8 is a material that exhibits stable properties even when exposed to the air. Mortar or cement milk is preferably used.
[0069] In particular, when the repair material 8 is made of the same material as the fixing material 7, the repair material 8 and the fixing material 7 may be regarded as being integrated in FIG.
[0070] The order of step S17 for embedding the spacer 10 and step S18 for injecting the repair material 8 may be reversed. That is, the repair material 8 may be injected first, and then the spacer 10 may be embedded in the hole drilling section 3. In this case, by intruding the spacer 10 in the depth direction (X direction), a part of the repair material 8 is pushed out and moves toward the wall surface 1a side of the existing structure 1 (i.e., the opening surface side of the hole drilling section 3) through the space between the spacer 10 and the hole drilling section 3. As a result, the repair material 8 covers the opening surface of the hole drilling section 3, thereby repairing it. Note that a part of the repair material 8 attached to the wall surface 1a of the existing structure 1 located outside the hole drilling section 3 may be appropriately removed depending on the amount of exposure.
[0071] Through the above steps S11 to S13 and S16 to S18, the shear reinforcement bars 5 are inserted into the existing structure 1 in a direction (here, the X direction) different from the vertical direction (the Y direction), thereby increasing the shear resistance of the existing structure 1 and improving earthquake resistance. Also, since the spacers 10 are embedded in step S17, the covering thickness of the shear reinforcement bars 5 is reliably ensured at least for the length of the spacers 10 in the X direction.
[0072] The cover thickness of the shear reinforcement bar 5 is the distance L5 between the end of the shear reinforcement bar 5 on the side (-X side) close to the wall surface 1a of the existing structure 1 after construction and the wall surface 1a of the existing structure 1 (see FIG. 8). As shown in FIG. 8, when a jig (5a, 5b) is attached to the end of the shear reinforcement bar 5, the distance L5 between the end face on the -X side of this jig and the wall surface 1a of the existing structure 1 may be taken as the cover thickness of the shear reinforcement bar 5. When a jig (5a, 5b) is not attached to the end of the shear reinforcement bar 5, the distance L5 between the end face on the -X side of the shear reinforcement bar 5 itself and the wall surface 1a of the existing structure 1 may be taken as the cover thickness of the shear reinforcement bar 5.
[0073] Through the above steps S11, and S16 to S18, the drilled hole 3 in the existing structure 1 is backfilled with the shear reinforcement bar 5 and the spacer 10 incorporating the IC tag 30 with at least the first information i1 written therein. That is, steps S11, and S16 to S18 shown in Fig. 3 correspond to the process (a).
[0074] (Step S19) 9, the worker uses the reader / writer 40 to read the information (i1, i2) written in the IC tag 30 in the spacer 10, and uses the communication device 41 to transmit the information (i1, i2) to the server 50 via the electric communication line NW. After authentication processing based on the second information i2, the server 50 stores the received first information i1 in a predetermined storage area. This step S19 corresponds to the process (c).
[0075] In step S19, the identification information i30 of the IC tag 30 may be read by the reader / writer 40. In this case, the identification information i30 may be transmitted by the communication device 41 to the server 50 together with the first information i1, and may be stored therein.
[0076] For example, a general-purpose smartphone or a portable computer can be used as the communication device 41. In the case of the former, it may be configured to be integrated with the reader / writer 40.
[0077] This step S19 is preferably performed after the target spacer 10 is embedded in the drilled portion 3, but it does not exclude the step S19 being performed before embedding in the drilled portion 3. In the former case, the step S19 may be performed before or after backfilling the drilled portion 3.
[0078] When step S19 is executed, other information (corresponding to the "fourth information") such as a photograph of the hole-drilling section 3 and the date and time of construction may also be transmitted to the server 50. In this case, the server 50 stores the fourth information together with the first information i1 in the storage area.
[0079] (Step S13a, Step S13b) Next, a case where the hole drilling section 3 has erroneously drilled a hole (No in step S12) will be described. Fig. 10 is a flow chart showing an example of a detailed processing procedure of the shear reinforcement construction process S1 when the hole drilling section 3 has erroneously drilled a hole. The reference numerals of the following steps S13a, S13b, S17a, S18a, and S19a correspond to the reference numerals in the flow chart of Fig. 10.
[0080] When the hole-drilled portion 3 is an erroneous hole-drilled portion, the hole-drilled portion 3 formed in step S11 corresponds to the "second hole-drilled portion" (step S13a: see FIG. 10).
[0081] When the hole drilling portion 3 is improperly drilled, the shear reinforcement bar 5 is not embedded in the hole drilled portion 3. On the other hand, in this embodiment, the spacer 10 is embedded in the hole drilled portion 3.
[0082] In this embodiment, if the hole drilling unit 3 has erroneously drilled a hole, the worker uses the reader / writer 40 to write third information i3 indicating that the hole has been erroneously drilled into the IC tag 30 (step S13b: see FIG. 11). This step S13b corresponds to process (h2).
[0083] (Step S17a) The spacer 10 with the third information i3 written in the IC tag 30 is embedded in the drilled hole 3. In this step, similarly to the above-mentioned step S17, it is preferable to position the spacer 10 somewhat close to the wall surface 1a so that radio waves can be received between the spacer 10 and the reader / writer 40 positioned outside the wall surface 1a of the existing structure 1 in the completion inspection process S2 described later.
[0084] (Step S18a) The drilled portion 3 (second drilled portion) is backfilled in the same manner as in step S18. That is, through the above-mentioned steps S11, S17a, and S18, the drilled portion 3 is backfilled in a state in which the spacer 10 incorporating the IC tag 30 in which at least the third information i3 is written is embedded in the drilled portion 3 in the existing structure 1. That is, the above-mentioned steps S11, S17a, and S18 correspond to the process (h1).
[0085] (Step S19a) 12, in a similar manner to step S19, the worker uses the reader / writer 40 to read the information (i1, i2, i3) written in the IC tag 30 in the spacer 10, and uses the communication device 41 to transmit the information (i1, i2, i3) to the server 50 via the electric communication line NW. After authentication processing based on the second information i2, the server 50 stores the received first information i1 and third information i3 in a predetermined area. This step S19a corresponds to process (h3).
[0086] According to this step S19a, it is recorded in the storage area of the server 50 that the position corresponding to the buried location described in the first information i1 is an erroneous hole drilling based on the third information i3.
[0087] This step S19a may be performed before or after embedding the target spacer 10 in the hole 3.
[0088] In addition, in step S19a, as in step S19, the identification information i30 of the IC tag 30 read by the reader / writer 40, the photograph of the hole-drilling section 3, the construction date and time, etc., may be transmitted to the server 50 together with the third information i3 and recorded in the memory area of the server 50.
[0089] Completion inspection process S2 13 is a flow chart showing an example of a detailed procedure of the completion inspection process S2. The reference numerals of steps S21 to S23 and S23a below correspond to the reference numerals in the flow chart of FIG.
[0090] (Steps S21 to S23) When the inspector arrives at the location of the existing structure 1 to be inspected, as shown in FIG. 14A, he brings the reader / writer 40 close to the wall surface 1a of the existing structure 1 and communicates with the IC tag 30 embedded in the buried spacer 10 (step S21). As described above with reference to FIG. 1, the backfilling traces (2a, 2b) have a different color from the surroundings on the surface of the existing structure 1, so the worker can recognize from the outside the position to which the reader / writer 40 should be brought. In step S21, the reader / writer 40 reads the information written on the IC tag 30. Step S21 corresponds to process (d).
[0091] Among the backfilled areas (2a, 2b), the backfilled area 2a after shear reinforcement is not an erroneously drilled hole but a backfilled area of the drilled hole section 3 (first drilled hole section) in which the shear reinforcement bar 5 and the spacer 10 were buried, and is a trace left after step S18 was performed. Also, the backfilled area 2b of the erroneously drilled hole is a backfilled area of the drilled hole section 3 (second drilled hole section) in which the shear reinforcement bar 5 was not buried and only the spacer 10 was buried, and is a trace left after step S18a was performed.
[0092] As described above, according to the shear reinforcement construction step S1 of this embodiment, the spacer 10 incorporating the IC tag 30 is embedded in the drilled hole portion 3, whether it is the first drilled hole portion in which the shear reinforcement steel bar 5 is embedded or the second drilled hole portion due to erroneous drilling. Therefore, in this step S21, by bringing the reader / writer 40 close, communication with the IC tag 30 can be performed and the information written in the IC tag 30 can be read.
[0093] If the information read from the IC tag 30 does not include the third information i3 (No in step S22), the reader / writer 40 reads from the IC tag 30 the first information i1 including information on the embedded position of the spacer 10 and the specifications of the shear reinforcement bar 5, and the second information i2 for authentication. In addition, preferably, the identification information i30 of the IC tag 30 itself is also read.
[0094] The inspector uses the communication device 41 to connect to the server 50 via the electric communication line NW to check whether the information written on the IC tag 30 is accurate, and compares it with the information stored in the server 50 (step S23). At this time, authentication processing may be performed based on the second information i2 read from the IC tag 30. This step S23 corresponds to the process (e).
[0095] When the server 50 receives the first information i1 from the communication device 41, it recognizes information about the embedded position of the spacer 10 from the received first information i1 and identifies a storage area in which the information about the embedded position is stored. Then, the information stored in the identified storage area, i.e., the first information i1 recorded in the server 50 in step S19 of the shear reinforcement construction process S1, is compared with the first information i1 transmitted from the communication device 41. Note that, when identifying the storage area in the server 50, the IC tag identification information i30 read from the IC tag 30 may be used.
[0096] Since the first information i1 of both of them includes at least information on the specifications of the shear reinforcement bars 5 buried in the relevant location, if it is confirmed that they match, it can be confirmed that the shear reinforcement work was carried out correctly. In addition, if the fourth information on site photos and construction date and time is stored in the server 50, the inspector can read this information from the server 50 and check it.
[0097] (Step S23a) On the other hand, if the information read from the IC tag 30 includes the third information i3 (Yes in step S22), the reader / writer 40 reads from the IC tag 30 the first information i1 including information about the embedded position of the spacer 10, the second information i2 for authentication, and the third information i3 indicating that the hole has been drilled incorrectly (see FIG. 14B). The inspector uses the communication device 41 to connect to the server 50 via the electric communication line NW to check whether the information written on the IC tag 30 is accurate, and compares it with the information stored in the server 50 (step S23a). At this time, authentication processing may be performed based on the second information i2 read from the IC tag 30. This step S23a corresponds to the process (e).
[0098] When the server 50 receives the first information i1 and the third information i3 from the communication device 41, the server 50 recognizes information about the embedded position of the spacer 10 from the received first information i1, and identifies a storage area in which the information about the embedded position is stored. Then, the information stored in the identified storage area, i.e., the third information i3 stored in the server 50 in step S19a of the shear reinforcement construction process S1, is compared with the third information i3 transmitted from the communication device 41. Note that, when identifying the storage area in the server 50, the IC tag identification information i30 read from the IC tag 30 may be used.
[0099] If the two pieces of information match, the worker will know that the hole in question has been drilled incorrectly.
[0100] [Second embodiment] A second embodiment of the construction management method for shear reinforcement will be described below, focusing only on the differences from the first embodiment. Fig. 15 is a flow chart that shows a schematic diagram of the processing procedure of the construction management method for shear reinforcement of this embodiment. The reference numerals of steps S11 to S19 below correspond to the reference numerals in the flow charts of Figs. 3 and 15.
[0101] In this embodiment, the content of the shear reinforcement construction step S1 is different from that of the first embodiment. Note that the completion inspection step S2 is the same as in the first embodiment, so a description thereof will be omitted.
[0102] This embodiment differs from the first embodiment in that a two-dimensional code 35 (see Figure 16) is attached to the shear reinforcement bar 5 and that the first information i1 is not written in advance to the IC tag 30 built into the spacer 10.
[0103] That is, in this embodiment, the spacer 10 incorporating the IC tag 30 in which the first information i1 has not been written is transported to the site of the existing structure 1. This transport step corresponds to step (f).
[0104] The two-dimensional code 35 is typically a sticker on which the two-dimensional code is printed. At least the first information i1 related to the specifications of the shear reinforcement bar 5 is written in this two-dimensional code 35. As an example, the shear reinforcement bar 5 is transported to the site of the target existing structure 1 with a sticker on which the two-dimensional code 35 is printed attached in advance. The first information i1 written in the two-dimensional code 35 is information related to the specifications of the shear reinforcement bar 5, and therefore can be realized only with information known by, for example, the rebar manufacturer. Therefore, it is possible to attach the two-dimensional code 35 at the time of shipping the shear reinforcement bar 5. The process of attaching the two-dimensional code 35 to the shear reinforcement bar 5 corresponds to the process (g).
[0105] (Steps S11 to S13) This is common to the first embodiment. That is, if the hole-drilling portion 3 is not an erroneous hole-drilling portion (Yes in step S12), the hole-drilling portion 3 formed in step S11 corresponds to the "first hole-drilling portion."
[0106] (Step S14) As described above, in this embodiment, the two-dimensional code 35 is attached in advance to the shear reinforcement bar 5 (see FIG. 16). A worker reads the two-dimensional code 35 using the two-dimensional code reader 42. As a result, the first information i1 written on the two-dimensional code 35 is expanded in the two-dimensional code reader 42.
[0107] (Step S15) The worker uses the reader / writer 40 to write the first information i1, including the information read by the two-dimensional code reader 42, to the IC tag 30 built into the spacer 10 (see FIG. 17). At this time, the worker also writes information (first information i1) relating to the position where the spacer 10 is to be embedded into the IC tag 30. Furthermore, at this time, second information i2 relating to authentication may also be written to the IC tag 30. Information previously stored in the reader / writer 40 may be used as the second information i2 to be written.
[0108] The reader / writer 40 and the two-dimensional code reader 42 may be integrated together.
[0109] Through steps S14 to S15, the spacer 10 having the IC tag 30 with predetermined information written therein is prepared. In other words, the same situation as in the first embodiment is obtained.
[0110] Steps S14 and S15 correspond to the process (b).
[0111] (After step S16) Since this is common to the first embodiment, the description will be omitted.
[0112] (Steps S13a and S13b) Next, a case where the hole drilling section 3 has erroneously drilled a hole (No in step S12) will be described. Fig. 18 is a flow chart showing an example of a detailed processing procedure of the shear reinforcement construction process S1 of this embodiment when the hole drilling section 3 has erroneously drilled a hole. The reference numerals of the following steps S13a, S13b, S17a, S18a, and S19a correspond to the reference numerals in the flow chart of Fig. 18.
[0113] If the hole drilling portion 3 is an erroneous hole drilling portion (No in step S12), the hole drilling portion 3 formed in step S11 corresponds to the "second hole drilling portion" (step S13a: see FIG. 18).
[0114] If the hole-drilling section 3 is an erroneous hole-drilling, the worker uses the reader / writer 40 to write third information i3 indicating that the hole-drilling is an erroneous hole-drilling to the IC tag 30 (step S13b). At this time, first information i1 regarding the position of the hole-drilling section 3, i.e., the embedding position of the spacer 10 incorporating the IC tag 30, is also written (see FIG. 19). This step S13b differs from the first embodiment in that information regarding the embedding position is written. This step S13b corresponds to process (h2).
[0115] (Step S17a and after) Since this is common to the first embodiment, the description will be omitted.
[0116] In this embodiment, the second information i2 may be written in advance in the IC tag 30 embedded in the spacer 10 that is transported to the site where the existing structure 1 exists.
[0117] [Another embodiment] In the above embodiment, in steps S19 and S19a, the information (i1, i3, etc.) written in the IC tag 30 is transmitted to the server 50 and recorded in a storage area in the server 50. However, the present invention does not exclude the case where the management information database is constructed in a storage area of a stand-alone device, rather than in the server 50. In this case, when executing the method according to the present invention, the above-mentioned "server 50" is replaced with "said stand-alone device", and the same processing procedure is followed. [Explanation of symbols]
[0118] 1: Existing concrete structure 1a: Wall of an existing concrete structure 2a, 2b: Backfilled areas 3: Drilling section 3a: Bottom of drilled hole 5: Shear reinforcement bars 5a, 5b: Jig 7: Fixing agent 8: Repair materials 10: Spacer for securing cover thickness 10A, 10B: Partial spacer 30: IC tag 31: Hole 35: 2D code 40: Reader / writer 41: Communication equipment 42: 2D code reader 50: Server
Claims
1. A construction management method for shear reinforcement of an existing concrete structure, comprising: A step (a) of backfilling the first drilled hole portion formed by cutting in a depth direction from the surface to the center of the existing concrete structure, in a state in which a shear reinforcement steel bar is embedded together with a spacer for ensuring a cover thickness having an IC tag embedded therein; A step (b) of writing first information including information on the embedding position of the cover thickness securing spacer and information on the specification of the shear reinforcement bar to the IC tag before or after the step (a); (c) a step of recording information corresponding to the first information in a management storage unit; After the steps (b) and (c) are performed, a step (d) of communicating with the IC tag from outside the surface of the existing concrete structure using a reader or a reader / writer to read the first information recorded in the IC tag; A construction management method for shear reinforcement, characterized by comprising a step (e) of comparing the first information read in the step (d) with the first information recorded in the memory unit.
2. The step (b) is a step carried out before the step (a), The construction management method for shear reinforcement as described in claim 1, characterized in that the step (a) includes a step of burying the cover thickness ensuring spacer, which has an IC tag with the first information written therein, in the first drilled hole portion.
3. The storage unit is a storage area in a server, The step (c) includes a step of reading the first information by causing the reader or reader / writer to communicate with the IC tag, in which the first information is written and which is built into the spacer for ensuring the covering thickness, and transmitting the read first information to the server via a telecommunication line; The construction management method for shear reinforcement as described in claim 2, characterized in that the step (e) includes a step of reading the first information recorded in the server via the telecommunications line, and the first information read from the server is compared with the first information read in the step (d).
4. The method further includes a step (f) of transporting the cover thickness ensuring spacer having the IC tag with the first information written therein to a target location where the existing concrete structure exists before the step (a), The construction management method for shear reinforcement as described in claim 3, characterized in that the step (a) includes a step of embedding the cover thickness ensuring spacer transported in the step (f) into the first drilled hole portion.
5. the step (b) is a step of writing, in addition to the first information, second information related to authentication for accessing information recorded in the server to the IC tag; the step (c) includes a step of reading the second information in addition to the first information using the reader or reader / writer, and transmitting the first information to the server after performing an authentication process for connection to the server based on the second information; the step (d) is a step of reading the second information in addition to the first information by using the reader or reader / writer; The construction management method for shear reinforcement as described in claim 4, characterized in that the step (e) includes a step of reading the first information recorded in the server after performing authentication processing for connection to the server based on the second information.
6. a step (f) of transporting the cover thickness ensuring spacer incorporating the IC tag before the first information is written to a target location where the existing concrete structure exists before the step (a) is performed; and (g) attaching a two-dimensional code having at least the first information written thereon to the shear reinforcement bar; The construction management method for shear reinforcement as described in claim 3, characterized in that the step (b) includes a step of reading the two-dimensional code affixed to the shear reinforcement bar using a two-dimensional code reader, and writing the first information contained in the two-dimensional code to the IC tag built into the cover thickness securing spacer transported in the step (f) using a reader / writer.
7. the step (b) is a step of writing, in addition to the first information, second information related to authentication for accessing information recorded in the server to the IC tag using the reader / writer; the step (c) includes a step of transmitting the first information to the server after performing an authentication process for connection to the server based on the second information; the step (d) is a step of reading the second information in addition to the first information by using the reader or reader / writer; The construction management method for shear reinforcement as described in claim 6, characterized in that the step (e) includes a step of reading the first information recorded in the server after performing authentication processing for connection to the server based on the second information.
8. The construction management method for shear reinforcement described in any one of claims 1 to 7, characterized in that the first information includes information regarding the cover thickness of the shear reinforcement steel bar within the first drilled hole section.
9. A step (h1) of backfilling the second drilled hole portion resulting from an erroneous drilling, which is formed by cutting in a depth direction from the surface to the center of the existing concrete structure, without embedding the shear reinforcement bar, and in a state in which the cover thickness securing spacer having the IC tag built in is embedded; A step (h2) of writing third information regarding erroneous drilling to the IC tag before or after the step (a); and (h3) recording information corresponding to the third information in the storage unit; The step (d) is a step of reading the third information in addition to the first information recorded in the IC tag, The step (e) includes a step of comparing the third information read in the step (d) with the third information recorded in the memory unit, and when the information read in the step (d) and the information recorded in the memory unit are the third information corresponding to each other, it is detected that the cover thickness ensuring spacer is buried in the second drilled portion resulting from an erroneous drilling, which is a construction management method for shear reinforcement described in any one of claims 1 to 8.
Citation Information
Patent Citations
Structure of embedding radio IC tag in concrete, method of embedding the same, and concrete information control system
JP2007224654A
System for notifying position of buried object, and RFID tag
JP2010164353A
Buried object
JP2012112982A
IC chip and arrangement method of IC chip
JP2013045286A
Shear reinforcement method of existing concrete construction
JP2014181473A