Information processing method and information processing system

The information processing system optimizes voltage adjustment work timing based on charging/discharging information and cost analysis to minimize long-term battery costs by balancing cell deterioration and adjustment expenses.

JP7607236B2Active Publication Date: 2024-12-27PANASONIC INTELLECTUAL PROPERTY MANAGEMENT CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2022535031
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Priority Date
2020-07-10
Filing Date
2021-06-28
Publication Date
2024-12-27
Estimated Expiration
2041-06-28

AI Technical Summary

Technical Problem

Existing battery management systems fail to determine the optimal time for performing voltage adjustment work on battery cells to minimize long-term costs, leading to increased costs due to premature battery replacement or inefficient cell balancing.

Method used

An information processing system that acquires charging/discharging information, relationship information between cell deterioration and voltage difference, and cost information to determine the optimal time for performing voltage adjustment work based on total cost considerations.

Benefits of technology

This system enables determining the optimal timing for voltage adjustment work to minimize long-term total costs by balancing the costs of battery deterioration and adjustment work, thereby extending battery life and reducing overall ownership costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007607236000001
    Figure 0007607236000001
  • Figure 0007607236000002
    Figure 0007607236000002
  • Figure 0007607236000003
    Figure 0007607236000003
Patent Text Reader

Abstract

This information processing device: acquires charging / discharging information representing information corresponding to an amount of charging or discharging per unit period for a battery including a plurality of cells; acquires first relationship information representing a relationship between the information corresponding to the amount of charging or discharging per unit period and a degree of degradation of the battery; acquires second relationship information representing a relationship between elapsed time or the amount of charging or discharging, and a voltage difference arising between the plurality of cells; acquires first cost information representing a first cost arising due to degradation of the battery, and second cost information representing a second cost required for work to reduce the voltage difference; and, on the basis of the charging / discharging information, the first relationship information, the second relationship information, the first cost information, and the second cost information, determines a work timing, which is a timing for performing the work in a charge / discharge plan, and which is a timing at which the sum of the first cost and the second cost satisfies a prescribed requirement.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to an information processing method and an information processing system. [Background technology]

[0002] Patent Document 1 listed below discloses a technique for determining whether or not to rebalance a plurality of cells in a battery pack based on the number of times the battery pack has been charged.

[0003] In the technology disclosed in Patent Document 1, rebalancing is performed every predetermined number of charging operations, so the timing of rebalancing may not be appropriate from the viewpoint of battery costs. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Special Publication No. 2018-515054 Summary of the Invention

[0005] The present disclosure aims to provide a technology that makes it possible to determine the appropriate time to perform work to reduce the voltage difference occurring between multiple cells of a battery, from the perspective of battery cost.

[0006] An information processing method according to one embodiment of the present disclosure includes an information processing device that acquires charge and discharge information indicating information corresponding to a charge and discharge amount per unit period of a battery provided in an electrical device powered by a battery, the battery having a plurality of cells, the charge and discharge amount including at least one of a charge amount and a discharge amount of the battery, acquires first relationship information indicating a relationship between the information corresponding to the charge and discharge amount per unit period and a deterioration degree of the battery, acquires second relationship information indicating a relationship between an elapsed time or the charge and discharge amount and a voltage difference occurring between the plurality of cells, acquires first cost information indicating a first cost incurred due to deterioration of the battery and second cost information indicating a second cost required for an operation to reduce the voltage difference, and determines a work time for performing the operation in a charge and discharge plan, the work time being a time when the sum of the first cost and the second cost satisfies a predetermined requirement, based on the charge and discharge information, the first relationship information, the second relationship information, the first cost information, and the second cost information, and causes a presentation device to present information indicating the work time. [Brief description of the drawings]

[0007] [Figure 1] 1 is a block diagram showing a configuration of an information processing system according to a first embodiment of the present disclosure. [Diagram 2] FIG. 2 is a diagram showing a simplified configuration of a battery. [Diagram 3] FIG. 2 is a block diagram showing functions of a data processing unit. [Figure 4] FIG. 1 is a diagram showing an example of a long-term business plan for a certain business establishment. [Diagram 5] FIG. 1 is a diagram showing an example of a current business situation in a certain establishment. [Figure 6] FIG. 1 is a diagram showing an example of business costs in a certain establishment. [Figure 7] FIG. 4 is a diagram showing an example of deterioration characteristics indicating a degree of deterioration of a battery with respect to a traveling distance of a vehicle. [Figure 8] FIG. 4 is a diagram showing an example of a voltage difference characteristic showing a voltage difference between cells of a battery with respect to a total travel distance of a vehicle. [Figure 9] 10 is a flowchart showing the flow of processing executed by a data processing unit. [Figure 10] FIG. 4 is a diagram showing an example of a deterioration degree of a battery with respect to a total traveling distance of a vehicle. [Figure 11] FIG. 13 is a simplified diagram showing an example of a presented planned quantity. [Figure 12] FIG. 13 is a simplified diagram showing an example of a presented planned travel distance. [Figure 13] FIG. 11 is a block diagram showing a configuration of an information processing system according to a second embodiment of the present disclosure. [Figure 14] 10 is a flowchart showing the flow of processing executed by a data processing unit. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0008] (Findings on which this disclosure is based) Products purchased through mail order sales over the Internet, etc., are delivered to customers' homes, etc. by delivery companies. Delivery companies use multiple trucks to deliver packages within their assigned delivery area. In the future, electric vehicles (EVs) equipped with battery-powered driving motors are expected to become more widespread, and the number of delivery companies using EV trucks to deliver packages is expected to increase.

[0009] EV batteries are often configured as battery packs with multiple cells (battery cells) connected in series. When an EV is used for many years, differences in remaining capacity occur among the multiple cells, resulting in an imbalance in cell voltage (cell imbalance). In a battery with cell imbalance, when charging is complete, some cells have a remaining capacity of 100% and others have a remaining capacity of less than 100%. When the EV starts and the battery begins to discharge, discharging is stopped when the remaining capacity of the latter cells reaches the lower allowable limit. As a result, the overall battery capacity is effectively reduced.

[0010] It is possible to resolve cell imbalance by implementing a known cell balancing circuit in the battery pack. The cell balancing circuit selects only cells with a large remaining capacity and connects them to a resistance element in the circuit, thereby forcibly discharging the selected cells. The cell imbalance can be resolved by stopping the forced discharge when the cell voltages of all the cells are equal. However, implementing a cell balancing circuit in the battery pack increases the cost of the battery pack, which in turn increases the manufacturing cost of the EV.

[0011] To avoid increasing the cost of EVs, instead of implementing a cell balancing circuit in the battery pack, a possible method is to take an EV with cell imbalance to a repair shop or the like and have the battery voltage adjusted. Similar to the cell balancing circuit described above, this voltage adjustment process resolves the cell imbalance in the battery by forcibly discharging cells with a large remaining capacity to make the cell voltages of all cells uniform.

[0012] However, voltage adjustment work at repair shops and the like is a paid task. Therefore, if voltage adjustment work is performed when the degree of cell imbalance is low, the battery capacity recovered by the work is small, so the cost-effectiveness is low. In addition, even if voltage adjustment work is performed on a battery that has deteriorated to the point of reaching the end of its life, the EV will need to be replaced some time after the work, so the cost-effectiveness is also low. On the other hand, if voltage adjustment work is never performed and the EV is replaced every time the battery performance deteriorates, the replacement cycle will be shortened and the vehicle purchase cost will increase. Therefore, if it is more cost-effective in the long term to perform voltage adjustment work rather than replace the EV, the replacement time should be postponed and the voltage adjustment work should be performed. Thus, when operating a delivery business using EVs, it is important to formulate a business plan that minimizes the long-term (e.g., 10-year) total cost of ownership (TCO), which includes not only the vehicle purchase cost associated with replacing vehicles with deteriorated batteries but also the cost of voltage adjustment work to resolve cell imbalance.

[0013] The battery pack charging / discharging system disclosed in the above-mentioned Patent Document 1 includes a charging station for charging / discharging a battery pack having multiple cells. The charging station includes a processor circuit that determines when to perform rebalancing of the multiple cells based on a predetermined rebalancing criterion and battery pack charging / discharging data stored in a battery pack memory.

[0014] However, the above-mentioned Patent Document 1 does not disclose anything about determining the timing of voltage adjustment work from the viewpoint of minimizing long-term total costs.

[0015] In order to solve the above problems, the present inventor has discovered that by using long-term planning information, cost information, relationship information between mileage and battery deterioration degree, and relationship information between mileage and cell imbalance, it is possible to determine the optimal timing to perform voltage adjustment work so as to minimize long-term total costs, and has arrived at the present disclosure.

[0016] Next, each aspect of the present disclosure will be described.

[0017] An information processing method according to one embodiment of the present disclosure includes an information processing device that acquires charge and discharge information indicating information corresponding to a charge and discharge amount per unit period of a battery provided in an electrical device powered by a battery, the battery having a plurality of cells, the charge and discharge amount including at least one of a charge amount and a discharge amount of the battery, acquires first relationship information indicating a relationship between the information corresponding to the charge and discharge amount per unit period and a deterioration degree of the battery, acquires second relationship information indicating a relationship between an elapsed time or the charge and discharge amount and a voltage difference occurring between the plurality of cells, acquires first cost information indicating a first cost incurred due to deterioration of the battery and second cost information indicating a second cost required for an operation to reduce the voltage difference, and determines a work time for performing the operation in a charge and discharge plan, the work time being a time when the sum of the first cost and the second cost satisfies a predetermined requirement, based on the charge and discharge information, the first relationship information, the second relationship information, the first cost information, and the second cost information, and causes a presentation device to present information indicating the work time.

[0018] According to this configuration, the information processing device determines the timing of performing work to reduce the voltage difference occurring between the multiple cells of the battery based on the charge / discharge information, the first relationship information, the second relationship information, the first cost information, and the second cost information so that the total of the first cost and the second cost satisfies a predetermined requirement. In this way, by determining the timing of work based on the total cost of the first cost and the second cost, the timing of work can be determined to be appropriate in terms of the cost of the battery. For example, it is possible to determine the optimal timing of work that minimizes the long-term total cost.

[0019] In the above aspect, the charge / discharge information is plan information or history information regarding charge / discharge.

[0020] According to this configuration, the timing of work can be determined before starting to use the electrical appliance by using the plan information, and the timing of work can be determined while taking into account the usage status of the electrical appliance during its use by using the past history information.

[0021] In the above aspect, the electrical equipment is a moving body, the information corresponding to the charge and discharge amount is a travel distance of the moving body, the charge and discharge information is travel information including a travel distance of the moving body per unit period, the battery is a mobile battery mounted on the moving body, the first relationship information indicates a relationship between a travel distance of the moving body per unit period and a deterioration degree of the battery, the second relationship information indicates a relationship between the elapsed time or the travel distance of the moving body and a voltage difference occurring between the multiple cells, the charge and discharge plan is a travel plan for the moving body, and the work time is a time when the work used in the travel plan is performed and a time when the sum of the first cost and the second cost satisfies a specified requirement.

[0022] With this configuration, it is possible to determine the optimal timing for performing work to reduce the voltage difference occurring between multiple cells of a battery mounted on a mobile object.

[0023] In the above aspect, the information processing device further determines a planning time, which is the time for purchasing, selling, or disposing of the moving body or the battery installed in the moving body used in the driving plan, based on the driving plan information, the first relationship information, the second relationship information, the first cost information, and the second cost information, and causes the presentation device to present information indicating the planning time.

[0024] According to this configuration, the information processing device determines a planning timing for the purchase, sale, or disposal of a mobile object or a battery such that the sum of the first cost and the second cost satisfies a predetermined requirement. In this way, by determining the planning timing based on the total cost of the first cost and the second cost, the planning timing can be determined to be appropriate in terms of the cost of the battery. For example, it is possible to determine an optimal planning timing for a mobile object or a battery that minimizes the long-term total cost.

[0025] In the above aspect, the first cost includes a cost required for purchasing, selling, or disposing of the battery or the mobile object equipped with the battery whose deterioration level has reached a threshold value or higher.

[0026] According to this configuration, the cost required for purchasing, selling, or disposing of a battery or a mobile body equipped with the battery whose deterioration level is equal to or greater than a threshold value is included in the first cost, so that the lifespan of the battery or the mobile body can be controlled using the threshold value. Therefore, it is possible to improve the accuracy of the first cost, which is the deterioration-linked cost.

[0027] In the above aspect, the information processing device causes the presentation device to present information indicating the implementation time a predetermined period before the implementation time arrives.

[0028] According to this configuration, by presenting information a predetermined period of time before the time for performing the work arrives, arrangements such as work reservations can be made smoothly.

[0029] In the above aspect, the electrical equipment is a power storage device, the information corresponding to the charge / discharge amount is the charge / discharge amount of the power storage device, the first relationship information indicates the relationship between the charge / discharge amount per unit period of the power storage device and the degree of deterioration of the battery, the second relationship information indicates the relationship between the elapsed time or the charge / discharge amount of the power storage device and the voltage difference occurring between the multiple cells, the charge / discharge plan is a charge / discharge plan for the power storage device, and the work timing is the time to perform the work used in the charge / discharge plan and is the time when the sum of the first cost and the second cost satisfies a specified requirement.

[0030] With this configuration, it is possible to determine the optimal timing for carrying out work to reduce the voltage difference occurring between multiple cells of a battery mounted in an electricity storage device.

[0031] An information processing system according to one embodiment of the present disclosure includes a first acquisition unit that acquires charge / discharge information indicating information corresponding to a charge / discharge amount per unit period of a battery provided in an electrical device driven by the battery; a second acquisition unit that acquires first relationship information indicating a relationship between the information corresponding to the charge / discharge amount per unit period and a deterioration level of the battery, the battery having a plurality of cells, the charge / discharge amount including at least one of a charge amount and a discharge amount of the battery; a third acquisition unit that acquires second relationship information indicating a relationship between an elapsed time or the charge / discharge amount and a voltage difference generated between the plurality of cells; a fourth acquisition unit that acquires first cost information indicating a first cost incurred due to deterioration of the battery and second cost information indicating a second cost required for an operation to reduce the voltage difference; a determination unit that determines a work timing for performing the operation in a charge / discharge plan based on the charge / discharge information, the first relationship information, the second relationship information, the first cost information, and the second cost information, the work timing being a time when the sum of the first cost and the second cost satisfies a predetermined requirement; and a presentation unit that presents information indicating the work timing.

[0032] According to this configuration, the determination unit determines the timing of work to reduce the voltage difference occurring between the multiple cells of the battery based on the charge / discharge information, the first relationship information, the second relationship information, the first cost information, and the second cost information so that the sum of the first cost and the second cost satisfies a predetermined requirement. In this way, by determining the timing of work based on the total cost of the first cost and the second cost, the timing of work can be determined to be appropriate in terms of the cost of the battery. For example, it is possible to determine the optimal timing of work that minimizes the long-term total cost.

[0033] The above-mentioned general or specific aspects of the present disclosure can be realized as a system, an apparatus, a method, an integrated circuit, a computer program, or any combination thereof. It goes without saying that such a computer program can be distributed as a computer-readable non-volatile recording medium such as a CD-ROM, or distributed via a communication network such as the Internet.

[0034] Each of the embodiments described below shows a specific example of the present disclosure. The numerical values, shapes, components, steps, order of steps, etc. shown in the following embodiments are merely examples and are not intended to limit the present disclosure. Furthermore, among the components in the following embodiments, components that are not described in an independent claim showing a top concept are described as optional components. Furthermore, in all embodiments, the contents of each component can be combined.

[0035] Hereinafter, embodiments of the present disclosure will be described in detail with reference to the drawings. In addition, elements with the same reference numerals in different drawings indicate the same or corresponding elements.

[0036] (First embodiment) FIG. 1 is a block diagram showing a configuration of an information processing system 1 according to a first embodiment of the present disclosure. In the example of this embodiment, the information processing system 1 is constructed as a management system of a delivery company that delivers packages to customers' homes or the like using electric vehicles (EVs). As an example, this delivery company has multiple business offices in charge of each delivery area and a head office that manages these multiple business offices. A local PC 12 is installed in the head office and each business office and is connected to a cloud server 11. In addition, multiple vehicles 13 for delivering packages are deployed in each business office. The cloud server 11, the local PC 12, and the vehicle 13 can communicate with each other via an arbitrary communication network 14 such as an IP network. In this embodiment, the moving body is a vehicle, but is not limited to this. For example, the moving body may be an aircraft such as a drone, a ship, or a mobile robot.

[0037] The cloud server 11 includes a data processing unit 22, a storage unit 23, and a communication unit 24. The local PC 12 includes a display unit 31, a data processing unit 32, a storage unit 33, a communication unit 34, and an input unit 35. The display unit 31 is a liquid crystal display or an organic EL display, etc. The data processing units 22, 32 are processors such as a CPU. The storage units 23, 33 are HDDs or SSDs, etc. The communication units 24, 34 are communication modules that perform data communication according to a predetermined communication standard such as IP. The input unit 35 is a mouse, a keyboard, etc.

[0038] The vehicle 13 is an EV truck or the like, and includes a battery 41, a control unit 42, and a communication unit 43. The battery 41 is a secondary battery such as a lithium ion battery for driving a driving motor mounted on the vehicle 13. The control unit 42 is a BMS (Battery Management System) for controlling the operation and managing the state of the battery 41. The communication unit 43 is a communication module that performs data communication according to a predetermined communication standard such as IP.

[0039] The application of the information processing system 1 according to this embodiment is not limited to delivery businesses, but may also be any business that uses multiple EVs, such as a taxi business, a rental car business, a car sharing business, or a designated driving business.

[0040] 2 is a diagram showing a simplified configuration of the battery 41. The battery 41 includes a plurality of cells (battery cells) C1 to C4 connected in series. In other words, the battery 41 is configured as a battery pack including a plurality of cells C1 to C4 connected in series. Note that the number of cells is not limited to four, and may be any number.

[0041] Fig. 3 is a block diagram showing functions of the data processing unit 22 of the cloud server 11. As shown in Fig. 3, the data processing unit 22 has a plan information acquisition unit 51, a current information acquisition unit 52, a deterioration characteristic acquisition unit 53, a cost information acquisition unit 54, a voltage difference characteristic acquisition unit 55, and an optimum value calculation unit 56. These functions may be realized in software by a CPU executing a program read from a ROM or the like.

[0042] FIG. 4 is a diagram showing an example of a long-term business plan for a certain establishment, FIG. 5 is a diagram showing an example of the current business situation at that establishment, and FIG. 6 is a diagram showing an example of business costs at that establishment.

[0043] Currently (0 years later), this business establishment is in charge of a predetermined delivery area using four EVs (vehicles A to D). The total distance traveled by the four EVs per day is 200 km. This business establishment plans to expand its business scale in line with the increase in the amount of packages, and as shown in FIG. 4, plans to increase the total distance traveled per day to 500 km in 10 years' time. Plan information indicating this long-term business plan is input from the input unit 35 of the local PC 12 installed in the business establishment. Input of plan information into the local PC 12 is performed when a new long-term business plan is formulated and when an existing long-term business plan is changed due to the occurrence of a special event such as a disaster. The input plan information is transmitted from the local PC 12 to the cloud server 11 via the communication network 14 and stored in the storage unit 23. Referring to FIG. 3, the plan information acquisition unit 51 acquires the plan information received from the local PC 12.

[0044] As shown in FIG. 5, the current business status includes the purchase date, the total mileage from when the vehicle was new to the present, the current SoH, the current setting value of the mileage per day, the maximum cell voltage, and the minimum cell voltage for each of the four EVs. The SoH is an index indicating the degree of deterioration of the battery 41. The maximum cell voltage is the maximum value of the cell voltages of the cells C1 to C4. The minimum cell voltage is the minimum value of the cell voltages of the cells C1 to C4. This current information indicating the current business status is input from the input unit 35 of the local PC 12 installed in the business establishment. The current information is input to the local PC 12 when a new long-term business plan is formulated, when an existing long-term business plan is changed, and periodically (for example, once every six months). The input current information is transmitted from the local PC 12 to the cloud server 11 via the communication network 14 and stored in the storage unit 23. When a new business establishment is established using only new EVs, the batteries 41 of none of the vehicles 13 are deteriorated, so transmission of the current information to the cloud server 11 may be omitted. 3, the current information acquisition unit 52 acquires the current information received from the local PC 12. Note that the information relating to the maximum cell voltage and the minimum cell voltage may be transmitted to the cloud server 11 from the vehicle 13 via the communication network 14, instead of from the local PC 12.

[0045] As shown in FIG. 6, the business costs at the business are classified into costs that vary according to the number of vehicles 13 deployed at the business (vehicle number-linked costs), costs that vary according to the deterioration level of the batteries 41 (deterioration-linked costs), and costs that do not vary according to the number of vehicles and the deterioration level of the batteries (fixed costs). The vehicle number-linked costs include the personnel costs of the drivers, and vehicle maintenance costs such as maintenance costs and insurance premiums. Although not shown in FIG. 6, the vehicle number-linked costs include the electricity costs of the vehicles 13, and lease costs when the vehicles 13 are leased. The deterioration-linked costs include the vehicle purchase costs (first cost) and voltage adjustment work costs (second cost) of the vehicles 13. When selling an old vehicle when purchasing a new vehicle, the profit from the sale is recorded as a negative vehicle purchase cost.

[0046] When an EV is used for many years, a difference in remaining capacity occurs among the cells C1 to C4, resulting in a state where the balance of the cell voltages is lost (cell imbalance). In the battery 41 where cell imbalance occurs, when charging is completed, some cells have a remaining capacity of 100% and some have a remaining capacity of less than 100%. When the EV starts discharging the battery 41, discharging is stopped when the remaining capacity of the latter cell reaches a lower limit allowable value. As a result, the battery capacity of the battery 41 as a whole is substantially reduced. In this embodiment, in order to avoid an increase in the cost of the EV, the above-mentioned cell balancing circuit is not implemented in the battery pack, but a method is adopted in which an EV where cell imbalance occurs is carried into a repair shop or the like and a voltage adjustment work is performed on the battery 41. This voltage adjustment work is performed to cancel the cell imbalance of the battery 41 by forcibly discharging a cell with a large remaining capacity to equalize the cell voltages of all the cells, as in the case of the cell balancing circuit. The voltage adjustment work cost shown in FIG. 6 is the cost required for this voltage adjustment work at the repair shop or the like.

[0047] Although not shown in Fig. 6, the deterioration-linked costs include the cost of scrapping the vehicle 13 when it reaches the end of its life. The fixed costs include operating costs such as rent, warehouse costs, and personnel costs other than the driver. The cost information of the business establishment shows the unit cost corresponding to each cost item such as the driver personnel costs and vehicle maintenance costs.

[0048] Cost information of a business establishment is input from an input unit 35 of a local PC 12 installed in the business establishment. Input of cost information into the local PC 12 is performed when a new long-term business plan is formulated, when an existing long-term business plan is changed, and periodically (for example, once every six months). The input cost information is transmitted from the local PC 12 to the cloud server 11 via the communication network 14 and stored in the storage unit 23. Referring to FIG. 3, a cost information acquisition unit 54 acquires the cost information received from the local PC 12.

[0049] FIG. 7 is a diagram showing an example of deterioration characteristics indicating the deterioration degree of the battery 41 with respect to the mileage of the vehicle 13. The horizontal axis of the graph indicates the mileage per day (km / day). The vertical axis of the graph indicates the SoH value (%) one year later when the mileage indicated on the horizontal axis is continued for one year. The value on the vertical axis when the horizontal axis is 0 is the current SoH of the battery 41. For example, if the battery 41 with a current SoH of 90% is used continuously with a mileage of 50 km per day, the SoH of the battery 41 will drop to 80% one year later. When the SoH of the battery 41 drops below a predetermined value (e.g., 80%) (in other words, when the degree of deterioration of the battery 41 becomes equal to or greater than a threshold), the battery 41 or the vehicle 13 equipped with the battery 41 reaches the end of its life (i.e., the remaining life is zero).

[0050] Although FIG. 7 shows only three patterns of deterioration characteristics with the current SoH of 90, 95, and 100%, many deterioration characteristics may be created with finer intervals (for example, 1% intervals). Furthermore, the deterioration characteristics may be shown in the form of a function formula, a look-up table, or the like, instead of the graph format shown in FIG. 7. Referring to FIG. 3, the deterioration characteristics acquisition unit 53 acquires the deterioration characteristics of the battery 41 by reading out deterioration characteristics created in advance for each type of battery from the storage unit 23. The deterioration characteristics acquisition unit 53 may acquire the deterioration characteristics of the battery 41 by obtaining information on the deterioration characteristics from the manufacturer or analysis manufacturer of the battery 41. If the deterioration characteristics of the battery 41 are not created in advance and cannot be obtained from the manufacturer, the deterioration characteristics acquisition unit 53 acquires the deterioration characteristics of the battery 41 by creating the deterioration characteristics by itself through analysis of vehicle information (including charge / discharge information of the battery 41) acquired from many vehicles 13.

[0051] FIG. 8 is a diagram showing an example of a voltage difference characteristic showing the inter-cell voltage difference of the battery 41 with respect to the total mileage of the vehicle 13. The horizontal axis of the graph shows the total mileage (km) of the vehicle 13 from when it was new. The total mileage of the vehicle 13 corresponds to the total charge / discharge amount of the battery 41. The charge / discharge amount includes at least one of the charge amount and the discharge amount. The vertical axis of the graph shows the inter-cell voltage difference, which is the difference between the maximum cell voltage and the minimum cell voltage among all the cells C1 to C4. It can be seen that the inter-cell voltage difference increases approximately in proportion to the total mileage. Note that the inter-cell voltage difference is approximately proportional not only to the total mileage of the vehicle 13 but also to the elapsed time since the manufacture of the battery 41. Therefore, the horizontal axis of the graph may be the elapsed time instead of the total mileage.

[0052] The voltage difference characteristic may be represented in the form of a function formula or a look-up table, instead of the graph form shown in Fig. 8. Referring to Fig. 3, the voltage difference characteristic acquisition unit 55 acquires the voltage difference characteristic of the battery 41 by reading out the voltage difference characteristic created in advance for each type of battery from the storage unit 23. The voltage difference characteristic acquisition unit 55 may acquire the voltage difference characteristic of the battery 41 by acquiring information on the voltage difference characteristic from the manufacturer or analysis manufacturer of the battery 41. When the voltage difference characteristic of the battery 41 has not been created in advance and cannot be acquired from the manufacturer, the voltage difference characteristic acquisition unit 55 acquires the voltage difference characteristic of the battery 41 by creating the voltage difference characteristic by itself through analysis of vehicle information (including charge / discharge information of the battery 41) acquired from a large number of vehicles 13.

[0053] 4 to 8, the cloud server 11 determines the optimum number (planned number) of vehicles 13 to be deployed at each business establishment, the optimum travel distance (planned travel distance) of each vehicle 13, and the optimum timing (work timing) of voltage adjustment work for each vehicle 13 so as to minimize the long-term (e.g., 10-year) total cost of ownership (TCO) at each business establishment. At the same time, the timing (planned timing) of purchasing, selling, or disposing of the vehicles 13 or the batteries 41 mounted on the vehicles 13 may also be determined.

[0054] FIG. 9 is a flowchart showing the flow of processing executed by the data processing unit 22 of the cloud server 11 to determine the planned number of vehicles, the planned travel distance, and the work timing for the target establishment.

[0055] When a request for determining the planned number of vehicles, planned mileage, and work timing for a certain business establishment is input to cloud server 11, first in step S01, degradation characteristic acquisition unit 53 and voltage difference characteristic acquisition unit 55 respectively determine whether or not it is possible to acquire the degradation characteristic shown in Fig. 7 and the voltage difference characteristic shown in Fig. 8. If a degradation characteristic and a voltage difference characteristic created in advance are stored in memory unit 23, or if information on the degradation characteristic and the voltage difference characteristic is available from the manufacturer of battery 41, etc., degradation characteristic acquisition unit 53 and voltage difference characteristic acquisition unit 55 determine that the degradation characteristic and the voltage difference characteristic can be acquired.

[0056] If the deterioration characteristic and voltage difference characteristic can be acquired (step S01: YES), then in step S02, the deterioration characteristic acquisition unit 53 and the voltage difference characteristic acquisition unit 55 acquire the deterioration characteristic and voltage difference characteristic of the battery 41 by reading the deterioration characteristic and voltage difference characteristic from the storage unit 23, or by accessing a database of the manufacturer of the battery 41 or the like and downloading information on the deterioration characteristic and voltage difference characteristic. The deterioration characteristic acquisition unit 53 and the voltage difference characteristic acquisition unit 55 input the acquired deterioration characteristic and voltage difference characteristic to the optimum value calculation unit 56 as data D3 and D5.

[0057] If the deterioration characteristic or voltage difference characteristic cannot be acquired (step S01: NO), then in step S03, the cloud server 11 acquires vehicle information from a large number of vehicles 13 via the communication network 14. The vehicle information includes charge / discharge information of the battery 41 of each vehicle 13. The vehicle information also includes mileage information of each vehicle 13. The acquired vehicle information is stored in the storage unit 23.

[0058] Next, in step S04, the deterioration characteristic acquisition unit 53 or the voltage difference characteristic acquisition unit 55 determines whether or not a sufficient amount of vehicle information for creating the deterioration characteristic or the voltage difference characteristic has been accumulated in the storage unit 23. If a sufficient amount of vehicle information has not been accumulated (step S04: NO), the processes of steps S03 and S04 are repeatedly executed until a sufficient amount of vehicle information is accumulated.

[0059] If a sufficient amount of vehicle information has been accumulated (step S04: YES), then in step S05, the degradation characteristic acquisition unit 53 or the voltage difference characteristic acquisition unit 55 creates the degradation characteristic or the voltage difference characteristic of the battery 41 based on the vehicle information accumulated in the storage unit 23. The vehicle information includes charge / discharge information (including information on the maximum cell voltage and the minimum cell voltage) and mileage information of the battery 41 for each vehicle 13. Therefore, the degradation characteristic acquisition unit 53 can analyze these pieces of information to create the degradation characteristic indicating the relationship between the mileage of the vehicle 13 and the degradation level (SoH) of the battery 41 for each type of battery 41. In addition, the voltage difference characteristic acquisition unit 55 can analyze these pieces of information to create the voltage difference characteristic indicating the relationship between the mileage of the vehicle 13 and the inter-cell voltage difference of the battery 41 for each type of battery 41. The degradation characteristic acquisition unit 53 or the voltage difference characteristic acquisition unit 55 inputs the created degradation characteristic or the voltage difference characteristic to the optimum value calculation unit 56 as data D3 and D5.

[0060] Following step S02 or step S05, in step S06, the plan information acquisition unit 51 acquires plan information indicating a long-term business plan of the target establishment by reading out from the storage unit 23 the plan information received from the local PC 12 and stored in the storage unit 23. As shown in Fig. 4, the plan information indicates the total travel distance per day (km / day) by the multiple vehicles 13 deployed at the establishment on an annual basis. The plan information acquisition unit 51 inputs the acquired plan information to the optimum value calculation unit 56 as data D1.

[0061] Next, in step S07, the current information acquisition unit 52 acquires current information (see FIG. 5) indicating the current business situation of the target establishment by reading out the current information received from the local PC 12 and stored in the storage unit 23 from the storage unit 23. The current information acquisition unit 52 inputs the acquired current information to the optimum value calculation unit 56 as data D2.

[0062] Next, in step S08, the cost information acquisition unit 54 acquires cost information of the target establishment by reading from the storage unit 23 the cost information received from the local PC 12 and stored in the storage unit 23. As shown in Fig. 6, the cost information includes a vehicle number-linked cost item that varies according to the number of vehicles 13 and a unit price for calculating the vehicle number-linked cost item, a deterioration-linked cost item that varies according to the deterioration degree of the battery 41 and a unit price for calculating the deterioration cost item, and a fixed cost item and a unit price for calculating the deterioration cost item. The cost information acquisition unit 54 inputs the acquired cost information to the optimum value calculation unit 56 as data D4.

[0063] Next, in step S09, the optimal value calculation unit 56 determines the planned number of vehicles 13 for the target business establishment, the planned mileage of each vehicle 13, and the work timing for each vehicle 13 based on the planned information indicated by data D1, the current information indicated by data D2, the deterioration characteristics indicated by data D3, the cost information indicated by data D4, and the voltage difference characteristics indicated by data D5.

[0064] A prediction model for predicting objective variables (planned number of vehicles, planned mileage, work timing) from explanatory variables (deterioration characteristics, voltage difference characteristics, planning information, current information, cost information) can be derived by machine learning using artificial intelligence. As an algorithm for the prediction model, route optimization by linear programming, neural network, multiple regression analysis, etc. can be used. A combination of the number of vehicles and the mileage of each vehicle to achieve the total mileage for each year specified in the planning information, and a combination of vehicle purchase and voltage adjustment work are variously changed to search for a combination that satisfies a predetermined requirement for TCO. As the predetermined requirement, for example, one combination that minimizes TCO, or one or more combinations that make TCO less than a target value are searched for. The optimal value calculation unit 56 outputs the determined planned number of vehicles as data D11, outputs the determined planned mileage as data D12, and outputs the determined work timing as data D13.

[0065] Next, in step S10, the cloud server 11 transmits the data D11 to D13 to the local PC 12 of the head office or the target business establishment via the communication network 14. The display unit 31 of the local PC 12 displays (presents) the planned number of vehicles, planned mileage, and work timing for its own business establishment based on the received data D11 to D13.

[0066] FIG. 10 is a diagram showing an example of the deterioration degree of the battery 41 with respect to the total mileage of the vehicle 13. In FIG. 10, the deterioration of the battery 41 progresses as the total mileage of the vehicle 13 increases. However, if a voltage adjustment operation is performed at the operation timing calculated as described above, the deterioration degree of the battery 41 is restored. Since such a voltage adjustment operation is determined based on the sum of the first cost and the second cost, it is possible to continue using the battery 41 while suppressing costs. Note that the horizontal axis of FIG. 10 may represent elapsed time or date instead of the total mileage.

[0067] FIG. 11 is a simplified diagram showing an example of the proposed planned number of vehicles, and FIG. 12 is a simplified diagram showing an example of the proposed planned mileage and planned period. In FIG. 11, characteristic K1 shows a graph in which the number of vehicles 13 is simply increased in response to an increase in the total mileage. The number of vehicles 13 after 10 years is 10. Characteristic K2 shows the transition of the planned number of vehicles determined by the optimal value calculation unit 56. The number of vehicles 13 increases by one each after 3 years, 6 years, and 8 years, and the number of vehicles 13 after 10 years is 7.

[0068] With reference to FIG. 12, it can be seen that the planned mileage increases and decreases significantly from year to year even for the same vehicle 13 (for example, vehicle E). For example, the graph for vehicle A disappears after six years. This indicates that the optimal time to sell (or scrap) vehicle A is six years from now. The graph for vehicle E appears after three years. This indicates that the optimal time to purchase vehicle E is three years from now. Point P1 is set for vehicle A one year from now, and point P2 is set for vehicle E eight years from now. Points P1 and P2 correspond to the time to perform voltage adjustment work on battery 41. In other words, this indicates that the optimal time to perform voltage adjustment work on vehicle A is one year from now, and the optimal time to perform voltage adjustment work on vehicle E is eight years from now.

[0069] Based on the data D13, the data processing unit 22 may cause the display units 21, 31 to display information indicating the target vehicles and the timing of the voltage adjustment work a predetermined period of time (e.g., one to several months) before the time for the voltage adjustment work to be performed for each vehicle A, E.

[0070] In addition, in the case of the vehicle 13 in which the battery 41 can be replaced, the time to replace the battery 41 may be presented. For example, by replacing the battery 41 of the vehicle A after six years, the graph of the vehicle F is taken over by the vehicle A after the battery replacement.

[0071] According to this embodiment, the data processing unit 22 of the cloud server 11 (information processing device) acquires long-term planning information (charge / discharge information or movement information) of the establishment, deterioration characteristics (first relationship information) of the battery 41, voltage difference characteristics (second relationship information) of the battery 41, and cost information including a unit price (first cost) of the vehicle purchase cost (first cost) and a unit price (second cost information) of the voltage adjustment work cost (second cost). Then, based on the acquired information, the work timing for performing the work to reduce the voltage difference occurring among the multiple cells C1 to C4 of the battery 41 is determined so that the total of the first cost and the second cost meets a predetermined requirement. In this way, by determining the work timing based on the total of the vehicle purchase cost and the voltage adjustment work cost, the work timing can be determined as an appropriate timing from the viewpoint of the cost of the battery 41. For example, it is possible to determine an optimal work timing at which the long-term total cost TCO is minimized.

[0072] Furthermore, according to this embodiment, the data processing unit 22 of the cloud server 11 determines the planning timing for purchasing, selling, or disposing of the vehicle 13 or the battery 41 so that the total of the vehicle purchase cost and the voltage adjustment work cost meets a predetermined requirement. In this way, by determining the planning timing based on the total of the vehicle purchase cost and the voltage adjustment work cost, it is possible to determine the optimal planning timing for the vehicle 13 or the battery 41 that minimizes the long-term total cost TCO.

[0073] Furthermore, according to the present embodiment, the cost required for purchasing, selling, or disposing of the battery 41 whose degradation level is equal to or greater than the threshold value or the vehicle 13 equipped with the battery 41 is included in the first cost, so that the lifespan of the battery 41 or the vehicle 13 can be controlled using the threshold value. Therefore, it is possible to improve the accuracy of the first cost, which is the degradation-linked cost.

[0074] Furthermore, according to this embodiment, by having the display units 21, 31, etc. display information such as the timing of the voltage adjustment work on the battery 41 a predetermined period of time before the time for the work to be performed arrives, the manager, etc. can smoothly make arrangements for work reservations, etc.

[0075] Second embodiment In the first embodiment, the cloud server 11 determines the timing of the voltage adjustment work of the battery based on the driving plan information of the EV, which is a battery-powered EV as an example of an electric device, but is not limited to this example. The cloud server 11 may determine the timing of the voltage adjustment work of the battery based on the usage plan information of the electric device, which is an arbitrary electric device driven by a battery having a plurality of cells. The electric device is, for example, a power storage device. The power storage device may have a power generation function. The usage plan information of the electric device can be formulated as charge and discharge information indicating the charge and discharge amount (at least one of the charge amount and the discharge amount) of the battery. When the charge and discharge plan information is unknown, the plan information acquisition unit 51 may estimate the plan information from the tendency based on the history information indicating the past usage status of the electric device or the battery.

[0076] Fig. 13 is a block diagram showing a configuration of an information processing system 1 according to a second embodiment of the present disclosure. The vehicle 13 shown in Fig. 1 is replaced with an electric device 113. The electric device 113 has a battery 141, a control unit 142, and a communication unit 143. The battery 141, the control unit 142, and the communication unit 143 correspond to the battery 41, the control unit 42, and the communication unit 43 shown in Fig. 1, respectively.

[0077] In this embodiment, the cloud server 11 determines the optimal number of electrical devices 113 (planned number), the optimal charge / discharge amount (planned charge / discharge amount) of each electrical device 113, and the optimal timing (work timing) for performing voltage adjustment work for each electrical device 113 so as to minimize the long-term (e.g., 10 years) total cost of ownership (TCO).

[0078] FIG. 14 is a flowchart showing the flow of processing executed by the data processing unit 22 of the cloud server 11 to determine the planned number of vehicles, the planned charge / discharge amount, and the work timing.

[0079] When a request to determine the planned number of units, the planned charging / discharging amount, and the work timing is input to the cloud server 11, first, in step S01, the deterioration characteristic acquisition unit 53 and the voltage difference characteristic acquisition unit 55 respectively determine whether or not it is possible to acquire the deterioration characteristic and the voltage difference characteristic.

[0080] If the deterioration characteristics and voltage difference characteristics can be acquired (step S01: YES), then in step S02, the deterioration characteristics acquisition unit 53 and the voltage difference characteristics acquisition unit 55 acquire the deterioration characteristics and voltage difference characteristics of the battery 41, and input the acquired deterioration characteristics and voltage difference characteristics to the optimal value calculation unit 56 as data D3 and D5.

[0081] If the deterioration characteristic or the voltage difference characteristic cannot be acquired (step S01: NO), then in step S103, the cloud server 11 acquires log information from a large number of electric devices 113 via the communication network 14. The log information includes charge / discharge information of the battery 41 of each electric device 113. The acquired log information is accumulated in the storage unit 23.

[0082] Next, in step S04, the deterioration characteristic acquisition unit 53 or the voltage difference characteristic acquisition unit 55 determines whether or not a sufficient amount of log information for creating the deterioration characteristic or the voltage difference characteristic has been accumulated in the storage unit 23. If a sufficient amount of log information has not been accumulated (step S04: NO), the processes of steps S03 and S04 are repeatedly executed until a sufficient amount of log information is accumulated.

[0083] If a sufficient amount of log information has been accumulated (step S04: YES), next, in step S05, the deterioration characteristic acquisition unit 53 or the voltage difference characteristic acquisition unit 55 creates the deterioration characteristic or the voltage difference characteristic of the battery 41 based on the log information accumulated in the storage unit 23. The log information includes charge / discharge information (including information on the maximum cell voltage and the minimum cell voltage) of the battery 41 related to each electric device 113. Therefore, the deterioration characteristic acquisition unit 53 can analyze this information to create the deterioration characteristic indicating the relationship between the total usage time of the electric device 113 (or the total charge / discharge amount of the battery 41) and the deterioration level (SoH) of the battery 41 for each type of battery 41. In addition, the voltage difference characteristic acquisition unit 55 can analyze this information to create the voltage difference characteristic indicating the relationship between the total usage time of the electric device 113 (or the total charge / discharge amount of the battery 41) and the inter-cell voltage difference of the battery 41 for each type of battery 41. The degradation characteristic acquisition unit 53 or the voltage difference characteristic acquisition unit 55 inputs the created degradation characteristic or voltage difference characteristic to the optimum value calculation unit 56 as data D3, D5.

[0084] Thereafter, as in the first embodiment described above, the data processing unit 22 sequentially executes the processes of steps S06 to S10 to determine the optimal number of electrical appliances 113 (planned number), the optimal charge / discharge amount (planned charge / discharge amount) of each electrical appliance 113, and the optimal timing (work timing) for performing voltage adjustment work for each electrical appliance 113 so as to minimize the total cost TCO, and presents this information.

[0085] According to this embodiment, the data processing unit 22 of the cloud server 11 (information processing device) acquires the usage plan information (charging and discharging information of the battery 41) of the electric device 113, the deterioration characteristic (first relationship information) of the battery 41, the voltage difference characteristic (second relationship information) of the battery 41, and cost information including the unit price (first cost) of the purchase cost (first cost) of the electric device 113 and the unit price (second cost information) of the voltage adjustment work cost (second cost). Then, based on the acquired information, the work timing for performing the work to reduce the voltage difference occurring among the multiple cells C1 to C4 of the battery 41 is determined so that the total of the first cost and the second cost meets a predetermined requirement. In this way, by determining the work timing based on the total of the equipment purchase cost and the voltage adjustment work cost, the work timing can be determined as an appropriate timing from the viewpoint of the cost of the battery 41. For example, it is possible to determine the optimal work timing at which the long-term total cost TCO is minimized.

[0086] According to the present embodiment, the charge / discharge information of the battery 41 is plan information or history information of the charge / discharge of the battery 41. By using the plan information, the timing of the work can be determined before starting to use the electric device. Furthermore, by using the past history information, the timing of the work can be determined while taking into account the usage status during the use of the electric device. [Industrial Applicability]

[0087] The technology disclosed herein is particularly useful for formulating long-term business plans for home delivery businesses that use multiple EVs.

Claims

1. An information processing device, acquiring charge / discharge information indicating information corresponding to a charge / discharge amount per unit period of a battery included in an electrical device driven by the battery; the battery having a plurality of cells; the charge / discharge amount includes at least one of a charge amount and a discharge amount of the battery, acquiring first relationship information indicating a relationship between information corresponding to the charge / discharge amount per unit period and a deterioration level of the battery; acquiring second relationship information indicating a relationship between an elapsed time or the charge / discharge amount and a voltage difference occurring among the plurality of cells; acquiring first cost information indicating a first cost incurred due to deterioration of the battery and second cost information indicating a second cost required for an operation to reduce the voltage difference; determining a work time for performing the work in the charge / discharge plan based on the charge / discharge information, the first relationship information, the second relationship information, the first cost information, and the second cost information, the work time being a time when the sum of the first cost and the second cost satisfies a predetermined requirement; causing a presentation device to present information indicating the work time; Information processing methods.

2. The information processing method according to claim 1 , wherein the charge / discharge information is plan information or history information regarding charge / discharge.

3. the electrical device is a moving object, the information corresponding to the charge / discharge amount is a travel distance of the moving object, the charge / discharge information is movement information including a movement distance of the moving object per unit period, the battery is a battery for transportation mounted on the moving body, the first relationship information indicates a relationship between a moving distance of the moving object per unit period and a deterioration level of the battery, the second relationship information indicates a relationship between the elapsed time or the moving distance of the moving object and a voltage difference occurring among the plurality of cells, The charge / discharge plan is a movement plan of the moving body, The work time is a time when the work used in the movement plan is performed, and the sum of the first cost and the second cost satisfies a predetermined requirement.

3. The information processing method according to claim 1 or 2.

4. The information processing device further comprises: determining a planning time for purchasing, selling, or disposing of the moving object or the battery mounted on the moving object used in a moving plan based on the movement information, the first relationship information, the second relationship information, the first cost information, and the second cost information, the planning time being a time when the sum of the first cost and the second cost satisfies the predetermined requirement; causing the presentation device to present information indicating the planned time period; The information processing method according to claim 3.

5. The first cost includes a cost required for purchasing, selling, or disposing of the battery or the mobile body equipped with the battery, the deterioration level of which is equal to or greater than a threshold value.

5. The information processing method according to claim 3.

6. the information processing device causes the presentation device to present information indicating the implementation time a predetermined period before the implementation time arrives; The information processing method according to any one of claims 1 to 5.

7. the electrical device is a power storage device, the information corresponding to the charge / discharge amount is a charge / discharge amount of the power storage device, the first relationship information indicates a relationship between a charge / discharge amount per unit period of the power storage device and a deterioration level of the battery, the second relationship information indicates a relationship between the elapsed time or a charge / discharge amount of the power storage device and a voltage difference occurring among the plurality of cells, the charge / discharge plan is a charge / discharge plan for the power storage device, The work time is a time when the work to be used in the charge / discharge plan is performed, and the sum of the first cost and the second cost satisfies a predetermined requirement. The information processing method according to claim 1 .

8. a first acquisition unit that acquires charge / discharge information indicating information corresponding to a charge / discharge amount per unit period of a battery included in an electrical device driven by the battery; the battery having a plurality of cells; the charge / discharge amount includes at least one of a charge amount and a discharge amount of the battery, a second acquisition unit that acquires first relationship information indicating a relationship between information corresponding to the charge / discharge amount per unit period and a deterioration level of the battery; a third acquisition unit that acquires second relationship information indicating a relationship between an elapsed time or the charge / discharge amount and a voltage difference generated among the plurality of cells; a fourth acquisition unit that acquires first cost information indicating a first cost incurred due to deterioration of the battery and second cost information indicating a second cost required for an operation to reduce the voltage difference; a determination unit that determines a time to perform the work in the charge / discharge plan based on the charge / discharge information, the first relationship information, the second relationship information, the first cost information, and the second cost information, and that is a time when a sum of the first cost and the second cost satisfies a predetermined requirement; A presentation unit that presents information indicating the work time; An information processing system comprising:

Citation Information

Patent Citations

  • Charging controller for storage battery

    JP1989099441A

  • JP1992035635U

  • A surgical charging system for charging and / or conditioning one or more batteries

    JP2018515054A