Method for controlling load increase rate of fuel cell, and vehicle

By detecting the fuel cell voltage drop rate and adjusting the load-raising rate, the problem of failure of the fuel cell when the rapid load rises is solved, effectively controlling the load-raising rate of the fuel cell is achieved, and the risk of failure is reduced.

WO2024239451A1PCT designated stage expired Publication Date: 2024-11-28SHANGHAI H RISE NEW ENERGY TECH CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2023/110319
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-05-22
Filing Date
2023-07-31
Publication Date
2024-11-28

AI Technical Summary

Technical Problem

When the vehicle is loading rapidly increases, the load-raising rate of fuel cells is likely to exceed its own tolerance limit, resulting in an increase in the possibility of failure.

Method used

By obtaining the vehicle load-up request, the voltage drop rate of each battery cell in the instantaneous load-up experiment is detected, and whether the load-up rate is allowed is determined based on the voltage drop rate and the preset boundary value. If it exceeds the load-up rate, it will be adjusted to be lower than the original rate. The second liter load rate is to avoid failure.

Benefits of technology

Effectively control the load-raising rate of the fuel cell, reduce the possibility of failure, and ensure the stable operation of the battery when the load is raised.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023110319_28112024_PF_FP_ABST
    Figure CN2023110319_28112024_PF_FP_ABST
Patent Text Reader

Abstract

A method for controlling a load increase rate of a fuel cell, and a vehicle. The method comprises: acquiring a vehicle load increase request, the vehicle load increase request comprising a load increase rate; when the load increase rate is greater than a preset threshold, detecting a voltage drop rate of each battery cell of the fuel cell in an instantaneous load increase experiment, the instantaneous load increase experiment comprising a step of performing instantaneous load increase on the fuel cell at the load increase rate; and according to the voltage drop rate of each battery cell and a voltage drop rate boundary value corresponding to the load increase rate, determining whether to perform load increase on the fuel cell at the load increase rate.
Need to check novelty before this filing date? Find Prior Art

Description

Fuel cell loading rate control method and vehicle

[0001] CROSS-REFERENCE TO RELATED APPLICATIONS

[0002] This application claims priority to Chinese patent application number 202310572910.6 filed with the State Intellectual Property Office of China on May 22, 2023, entitled “Fuel Cell Loading Rate Control Method and Vehicle,” the entire contents of which are incorporated by reference into this application. Technical Field

[0003] The present application relates to the field of fuel cell technology, and in particular to a fuel cell loading rate control method and a vehicle. Background Art

[0004] When a vehicle is started and driving, it usually experiences an increase in load, such as when the vehicle suddenly accelerates or turns on the air conditioner. The increase in vehicle load will prompt the fuel cell in the vehicle to increase its load to support the increased vehicle load.

[0005] However, in practical applications, fuel cells are often limited by factors such as their hydrothermal state and rated power, resulting in a load-bearing limit. Therefore, when increasing vehicle load, especially rapidly, the fuel cell's load rate must be controlled to avoid exceeding its load limit, which could lead to failure.

[0006] Summary of the Invention

[0007] The purpose of the embodiments of the present application is to provide a fuel cell loading rate control method and a vehicle to solve the problems of the prior art.

[0008] A first aspect of an embodiment of the present application provides a fuel cell loading rate control method, comprising:

[0009] Obtaining a vehicle load increase request, wherein the vehicle load increase request includes a load increase rate;

[0010] When the load rate is greater than a preset threshold, detecting the voltage drop rate of each battery cell of the fuel cell in the instantaneous load test; wherein the instantaneous load test includes the step of instantaneously increasing the load of the fuel cell at the load rate;

[0011] Whether to increase the load on the fuel cell at the increasing rate is determined according to the voltage decrease rate of each battery cell and the voltage decrease rate boundary value corresponding to the increasing rate.

[0012] In one embodiment, the method further includes:

[0013] Using the ramp-up rate to query a preset corresponding relationship table or a preset corresponding relationship diagram to determine a voltage drop rate boundary value corresponding to the ramp-up rate; or,

[0014] Substitute the load increase rate into the corresponding relationship calculation formula to determine the voltage drop rate boundary value corresponding to the load increase rate.

[0015] In one embodiment, the method further includes: pre-generating a preset correspondence diagram.

[0016] In one embodiment, determining whether to increase the load on the fuel cell at the increasing rate according to the voltage decrease rate of each battery cell and the voltage decrease rate boundary value corresponding to the increasing rate specifically includes:

[0017] Determining whether the voltage drop rate of each battery cell is less than the voltage drop rate boundary value;

[0018] If so, the fuel cell is loaded at the loading rate; or

[0019] If not, the fuel cell is loaded at a second loading rate that is lower than the loading rate.

[0020] In one embodiment, determining whether the voltage drop rate of each battery cell is less than the voltage drop rate boundary value specifically includes:

[0021] Obtain the maximum value of the voltage drop rate of each battery cell;

[0022] Determining whether the maximum value is less than the voltage drop rate boundary value;

[0023] Among them, if the maximum value is less than the voltage drop rate boundary value, the voltage drop rate of each battery cell is less than the voltage drop rate boundary value; or, if the maximum value is greater than or equal to the voltage drop rate boundary value, the voltage drop rate of at least one battery cell is greater than or equal to the voltage drop rate boundary value.

[0024] In one embodiment, the method further includes: calculating the second loading rate by multiplying the loading rate by a coefficient less than 1.

[0025] In one embodiment, the method further includes: calculating the coefficient according to a difference or ratio between the maximum value and the voltage drop rate boundary value.

[0026] In one embodiment, the vehicle load increase request further includes a target load; and

[0027] Increasing the loading of the fuel cell at the increasing loading rate specifically includes:

[0028] The load of the fuel cell is increased to the target load at the increase rate.

[0029] In one embodiment, the transient load test includes the steps of transiently increasing the load on the fuel cell at the load rate for multiple times; and

[0030] Detecting the voltage drop rate of each battery cell of the fuel cell in the instantaneous load increase experiment specifically includes:

[0031] In each instantaneous load increase step, the voltage drop rate of each battery cell is detected respectively;

[0032] For each battery cell, an average value of the voltage drop rates detected each time is determined as the voltage drop rate of the battery cell.

[0033] A second aspect of an embodiment of the present application provides a vehicle, and the loading rate of a fuel cell in the vehicle is controlled by the method provided in the embodiment of the present application.

[0034] The fuel cell loading rate control method provided in an embodiment of the present application includes obtaining a vehicle loading request, which includes a loading rate, then determining whether the loading rate is greater than a preset threshold. If the loading rate is greater than the preset threshold, the method detects the voltage drop rate of each cell of the fuel cell during an instantaneous loading test. Based on the voltage drop rate of each cell and the voltage drop rate boundary value corresponding to the loading rate, the method determines whether to load the fuel cell at the loading rate. Therefore, this method can control the loading rate of the fuel cell, thereby preventing the loading rate from exceeding the fuel cell's inherent tolerance limit and reducing the possibility of failure. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the following is a brief introduction to the drawings required for use in the embodiments of the present application. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without creative work.

[0036] FIG1 is a schematic diagram of a specific flow chart of a fuel cell loading rate control method provided by an embodiment of the present application;

[0037] FIG2 is a schematic diagram of the specific structure of a fuel cell loading rate control device provided by another embodiment of the present application;

[0038] FIG3 is a schematic diagram of the specific structure of an electronic device for a vehicle provided in one embodiment of the present application. DETAILED DESCRIPTION

[0039] The technical solutions in the embodiments of the present application will be described below in conjunction with the accompanying drawings. In the description of the present application, terms such as "first," "second," and "third" are used only to distinguish descriptions and should not be understood as indicating or implying relative importance or order.

[0040] As mentioned above, fuel cells are often limited by factors such as their hydrothermal state and rated power, resulting in a load-bearing limit. Therefore, when increasing the vehicle's load, especially rapidly, the fuel cell's load rate must be controlled to avoid exceeding its load limit, which could lead to failure.

[0041] Based on this, an embodiment of the present application provides a fuel cell ramp-up rate control method that can be used to control the ramp-up rate of a fuel cell. The fuel cell is disposed in a vehicle, and the electricity generated by the fuel cell can be used to power the vehicle to support the vehicle's travel, etc.

[0042] In addition, the fuel cell may include a plurality of fuel cell monomers (hereinafter referred to as battery monomers), which may be combined in series and / or in parallel to form the fuel cell. For example, the battery monomers may be connected in series in sequence to form the fuel cell.

[0043] FIG1 is a schematic diagram of a specific flow chart of the fuel cell loading rate control method. The method can be executed by a fuel cell control system provided in a vehicle. The method includes the following steps:

[0044] Step S11: obtaining a vehicle loading request, which includes a loading rate.

[0045] During vehicle startup, acceleration, air conditioning, or other situations where the vehicle needs to increase its load, the vehicle's load will increase. For example, when the driver steps on the accelerator or turns on the air conditioning, the vehicle's load will increase, which in turn will prompt the fuel cell in the vehicle to increase its load. At this time, during the fuel cell load increase process, a vehicle load increase request will be obtained.

[0046] Therefore, when the driver steps on the accelerator, turns on the air conditioner, or performs other operations that may increase the vehicle load, the vehicle's central control system can calculate the fuel cell loading rate, the fuel cell's target load and other parameters based on the increased load, and send a vehicle loading request to the fuel cell control system. The vehicle loading request carries these parameters, and the fuel cell control system can then control the fuel cell loading rate based on these parameters in the vehicle loading request.

[0047] Therefore, in step S11, the fuel cell control system can obtain the vehicle load increase request sent by the vehicle central control system. The vehicle load increase request can include a load increase rate and, of course, a target load, etc. The greater the load increase rate, the greater the rate at which the fuel cell load needs to be increased to meet the increase in vehicle load. Conversely, the smaller the load increase rate, the smaller the rate at which the fuel cell load can be increased to meet the increase in vehicle load. The load increase rate carried in the vehicle load increase request can be represented by g. The unit of the load increase rate can be amperes per second (A / s), watts per second (W / s), or other units that can describe the load rate.

[0048] The target load is the load to which the fuel cell needs to be increased in order to meet the increase in vehicle load. The larger the target load, the larger the load to which the fuel cell needs to be increased in order to meet the increase in vehicle load, and vice versa.

[0049] For ease of explanation, the current fuel cell load is represented by X1, and the target load is represented by X2. Specifically, the fuel cell load needs to be increased from the current load X1 to the target load X2, and the fuel cell load increase rate is controlled during this increase. The units of X1 and X2 can be amperes, watts, or other units that can describe the load.

[0050] Step S12: Determine whether the loading rate in the vehicle loading request is greater than a preset threshold. If not, execute step S13; if so, execute steps S14 and S15.

[0051] Step S13: increasing the load of the fuel cell to the target load at the increasing rate.

[0052] Step S14: detecting the voltage drop rate of each battery cell of the fuel cell during the instantaneous load increase experiment.

[0053] Here, the above steps S12 to S14 can be collectively explained.

[0054] In step S12, it is first determined whether the loading rate in the vehicle loading request is greater than a preset threshold. The value of the preset threshold can be preset according to actual conditions. For example, the preset threshold can be set according to the rated power of the fuel cell. At this time, when the loading rate is less than or equal to the preset threshold, it means that the fuel cell will be loaded at this loading rate, and the risk of fuel cell failure is relatively low. Therefore, step S13 is executed, that is, the load of the fuel cell is increased to the target load at this loading rate; and when the loading rate is greater than the preset threshold, it means that the fuel cell will be loaded at this loading rate, and there may be certain risks, and further testing of the fuel cell's loading capacity is required.

[0055] It should be noted that in the embodiment of the present application, the load-raising capacity of the fuel cell is measured by the voltage drop rate of each battery cell. For example, during the load-raising process, if the voltage drop rate of the battery cell is greater, it reflects that the load-raising capacity of the fuel cell is relatively poor; if the voltage drop rate of the battery cell is smaller, it reflects that the load-raising capacity of the fuel cell is relatively strong.

[0056] However, since the fuel cell is already installed in the vehicle, detecting the voltage drop rate of each cell in the fuel cell during normal vehicle use presents certain difficulties. For example, if the fuel cell load is increased to detect the voltage drop rate of each cell, this would affect the vehicle load increase process and could also increase the fuel cell load rate too quickly, making it more susceptible to failure. Therefore, in step S13 of the present embodiment, a transient load increase test is performed to detect the voltage drop rate of each cell.

[0057] The instantaneous load increase test includes the step of instantaneously increasing the fuel cell load at the load increase rate specified in the vehicle load increase request. For example, the instantaneous load increase refers to a load increase within a very short time (e.g., 0.1 to 1 second). Such a short load increase generally does not affect the increase in vehicle load and is unlikely to cause fuel cell failure.

[0058] For example, the instantaneous load increase test may include the step of increasing the fuel cell load from the current load X1 to (X1+g / a) at the load increase rate g, wherein the preset parameter a may be any value in the range of 1 to 10. In this way, the instantaneous load increase takes 1 / a seconds, thereby enabling the instantaneous load increase to be performed in a very short time of 0.1 to 1 second. For example, when a is 5, the instantaneous load increase from X1 to (X1+g / a) at the load increase rate g takes 0.2 seconds; when a is 10, the instantaneous load increase from X1 to (X1+g / a) at the load increase rate g takes 0.1 seconds; and when a is 1, the instantaneous load increase from X1 to (X1+g / a) at the load increase rate g takes 1 second.

[0059] Thus, since the instantaneous load increase experiment includes the step of instantaneously increasing the load of the fuel cell at the load increase rate in the vehicle load increase request, the voltage drop rate of each battery cell of the fuel cell can be detected during the instantaneous load increase process. For example, during the instantaneous load increase process, the fuel cell voltage patrol controller CVM can be used to detect the voltage V1 of each battery cell before the load increase and the voltage V2 after the load increase, thereby calculating the voltage drop rate of each battery cell respectively. The voltage drop rate of each battery cell can be expressed as dV / dt, where dV / dt = (V2-V1) / t, where t is the time taken for the fuel cell load to increase from X1 to (X1+g / a) during the instantaneous load increase, and thus t = 1 / a second.

[0060] Therefore, the V1 and V2 of each battery cell can be detected by the CVM, and the voltage drop rate of each battery cell can be calculated based on the V1 and V2 of each battery cell.

[0061] It should be further explained that in order to more accurately evaluate the load-raising capacity of the fuel cell, the instantaneous load-raising test may also include the step of instantaneously raising the fuel cell at the load-raising rate in the vehicle load-raising request multiple times. In this way, in the instantaneous load-raising test, the instantaneous load-raising step is performed multiple times, so that the voltage drop rate of each battery cell is detected in each instantaneous load-raising step. In this way, the voltage drop rate of each battery cell can be detected multiple times, and then, for each battery cell, the average value of the voltage drop rates detected each time is further used as the voltage drop rate of the battery cell, so that the voltage drop rate of each battery cell detected by the instantaneous load-raising test is more accurate.

[0062] Step S15: determining whether to increase the load on the fuel cell at the increasing rate according to the voltage decrease rate of each battery cell and the voltage decrease rate boundary value corresponding to the increasing rate.

[0063] As mentioned above, in the embodiment of the present application, the voltage drop rate of each battery cell is used to measure the load-increasing capacity of the fuel cell. Therefore, after detecting the voltage drop rate of each battery cell in the fuel cell through the above-mentioned step S14, it is further determined whether to load the fuel cell at the load-increasing rate based on the voltage drop rate of each battery cell and the voltage drop rate boundary value corresponding to the load-increasing rate.

[0064] Among them, the voltage drop rate boundary value corresponding to the loading rate reflects the boundary condition of the voltage drop rate when the fuel cell is loaded at the loading rate. That is to say, if the voltage drop rate is less than the voltage drop rate boundary value, it means that the loading capacity of the fuel cell is insufficient to support the loading at the loading rate.

[0065] Therefore, in step S15, it can be specifically determined whether the voltage drop rate of each battery cell is less than the voltage drop rate boundary value. If so, it means that the load-raising capacity of the fuel cell can support loading at this loading rate. At this time, if the fuel cell is loaded at this loading rate, the voltage drop rate of each battery cell does not exceed the boundary condition. Accordingly, the loading rate can be adjusted, and the fuel cell can be loaded at this loading rate, for example, the load of the fuel cell is increased from the current load to the target load at this loading rate; conversely, if the voltage drop rate of one or more battery cells is greater than or equal to the voltage drop rate boundary value, it means that the load-raising capacity of the fuel cell is insufficient to support loading at this loading rate, and the fuel cell can be loaded at a second loading rate lower than the loading rate, for example, the load of the fuel cell is increased from the current load to the target load at the second loading rate.

[0066] To facilitate determining whether the voltage drop rate of each battery cell is less than the voltage drop rate boundary value, the maximum value of the voltage drop rates of each battery cell can be first obtained, and then a determination can be made as to whether the maximum value is less than the voltage drop rate boundary value. If the maximum value is less than the voltage drop rate boundary value, it indicates that the voltage drop rate of each battery cell is less than the voltage drop rate boundary value; or if the maximum value is greater than or equal to the voltage drop rate boundary value, it indicates that the voltage drop rate of at least one battery cell is greater than or equal to the voltage drop rate boundary value. The battery cell corresponding to the maximum value has the largest voltage drop rate, indicating that the performance of the battery cell corresponding to the maximum value is relatively poor among the battery cells of the fuel cell, reflecting the weakest plate of the fuel cell. Therefore, the maximum value is compared with the voltage drop rate boundary value.

[0067] Furthermore, since the second loading rate is less than the loading rate in the vehicle loading request, the second loading rate can be calculated by multiplying the loading rate by a coefficient P less than 1. Specifically, the coefficient P less than 1 can have a value in the range of 0.50-0.99. For example, the coefficient P can be 0.50, 0.52, 0.55, 0.6, 0.65, 0.7, 0.75, 0.8, 0.85, 0.9, 0.95, 0.99, or other values ​​between 0.50 and 0.99. Of course, the second loading rate can also be calculated by subtracting a set value from the loading rate.

[0068] It should be noted that when the second loading rate is calculated by multiplying the loading rate by a coefficient P, the coefficient P may be a pre-set fixed value. For example, based on statistical analysis, a fixed value may be pre-selected from 0.50-0.99 as the value of the coefficient P, and then the second loading rate may be calculated by multiplying the loading rate by the coefficient P.

[0069] However, considering the diversity of the fuel cell's own state and vehicle operating conditions, the parameter P can also be set dynamically. For example, the parameter P can be determined based on the voltage drop rate boundary value (called dVb / dt) and the maximum value of the voltage drop rate of each battery cell (called dVm / dt). For example, a functional relationship between the parameter P and the difference between dVm / dt and dVb / dt can be pre-generated. In this functional relationship, the difference between dVm / dt and dVb / dt is the independent variable, and the parameter P is the dependent variable. Thus, the parameter P can be calculated by the difference between dVm / dt and dVb / dt and the functional relationship. For example, the functional relationship can be a piecewise function. In this case, the difference between dVm / dt and dVb / dt can be calculated first, and then the value of the coefficient P can be determined based on the interval to which the difference belongs.

[0070] Of course, a second functional relationship between the parameter P and the ratio of dVm / dt to dVb / dt can also be pre-generated. In this second functional relationship, the ratio of dVm / dt to dVb / dt is the independent variable, and the parameter P is the dependent variable. The parameter P can then be calculated based on the ratio of dVm / dt to dVb / dt and this second functional relationship. For example, a larger ratio indicates a larger dVm / dt relative to dVb / dt, and the value of the parameter P is smaller. Conversely, a smaller ratio indicates a larger value of the parameter P.

[0071] The fuel cell loading rate control method provided in an embodiment of the present application includes obtaining a vehicle loading request, which includes a loading rate, then determining whether the loading rate is greater than a preset threshold. If the loading rate is greater than the preset threshold, the method detects the voltage drop rate of each cell of the fuel cell during an instantaneous loading test. Based on the voltage drop rate of each cell and the voltage drop rate boundary value corresponding to the loading rate, the method determines whether to load the fuel cell at the loading rate. Therefore, this method can control the loading rate of the fuel cell, thereby preventing the loading rate from exceeding the fuel cell's inherent tolerance limit and reducing the possibility of failure.

[0072] In the above-mentioned step S15, the voltage drop rate boundary value corresponding to the load increase rate is mentioned. Therefore, the method may further include the step of determining the voltage drop rate boundary value, including using the load increase rate to query a preset correspondence table or a preset correspondence diagram to determine the voltage drop rate boundary value corresponding to the load increase rate; or, substituting the load increase rate into the correspondence calculation formula to determine the voltage drop rate boundary value corresponding to the load increase rate.

[0073] For example, the preset correspondence table, the preset correspondence diagram or the correspondence calculation formula can be established in advance, and then the preset correspondence table, the preset correspondence diagram can be queried using the load rate, or the load rate can be substituted into the correspondence calculation formula to determine the voltage drop rate boundary value corresponding to the load rate.

[0074] Among them, for the specific method of pre-generating the preset correspondence table and the preset correspondence diagram, for example, one method may be to perform simulation calculations by establishing a model to obtain the preset correspondence table or the preset correspondence diagram, wherein the simulation calculation method is more efficient; another method may be to perform calibration through a calibration experiment, wherein the calibration experiment method has higher accuracy. Among them, the steps of the calibration experiment are as follows: Step 1, for the battery cell used as the experimental sample (the battery cell may be a randomly selected battery cell), the battery cell is loaded from the electrical density point A1 to the electrical density point A2 at a loading rate of L1; Step 2, during the loading process, monitor whether the lowest voltage of the battery cell is lower than the preset lowest value (usually set to about 0.3V). If so, it is determined that the loading has failed, and the load is stopped urgently and the battery stack is protected for safety. At this time, it means that the loading rate L1 is too large, and then the loading rate can be reduced (for example, from L1 to L2) and the experiment can be repeated; if the lowest voltage of the battery cell is higher than the preset lowest value, the calculation Calculate and record the initial voltage drop rate of the battery cell, that is, the voltage drop rate within 1 second after the start of the loading process (within 0-1 second of loading); step 3, adjust the working conditions of the load density point A1 (such as lowering the temperature, increasing the humidity, etc.) until the loading fails, and then record the voltage drop rate boundary value corresponding to the loading rate L1; step 4, adjust the loading rate from L1 to L3, and load the battery cell from the load density point A1 to the load density point A2 again at the loading rate L3, and then repeat the above corresponding steps, and finally determine the voltage drop rate boundary value corresponding to each loading rate, and use this to draw the preset corresponding relationship diagram or the preset corresponding relationship table.

[0075] It should be further explained that, as mentioned in the above step S15, if the voltage drop rate of each battery cell is less than the voltage drop rate boundary value (in this case, dVm / dt must also be less than dVb / dt), the fuel cell load can be increased from the current load to the target load at the increase rate in the vehicle load increase request. At this time, since the increase rate is determined to be greater than the preset threshold in the above step S12, there is still a certain risk in increasing the load at this increase rate. Therefore, steps S14 and S15 can be periodically performed to periodically detect the voltage drop rate of each battery cell and further determine whether the periodically detected dVm / dt is less than dVb / dt. If the dVm / dt detected in a certain cycle is greater than or equal to dVb / dt, it indicates that the load-increasing capacity of the fuel cell has decreased. In this case, the fuel cell can be increased at the second increase rate. Of course, if the dVm / dt detected in each cycle is less than dVb / dt, the fuel cell can still be increased at this increase rate.

[0076] In addition, the above step S15 also mentions that if the voltage drop rate of one or more battery cells is greater than or equal to the voltage drop rate boundary value (at this time, dVm / dt must be greater than or equal to dVb / dt), the fuel cell can be loaded at a second loading rate. At this time, loading the fuel cell at the second loading rate may still exceed the loading capacity of the fuel cell. Therefore, in the process of loading the fuel cell at the second loading rate, the method can further include: detecting the voltage drop rate of each battery cell of the fuel cell in the second instantaneous loading experiment, wherein the second instantaneous loading experiment is The test includes the step of instantaneously loading the fuel cell at the second loading rate. The difference between the second instantaneous loading test and the instantaneous loading test mentioned in the above step S14 is that the instantaneous loading test includes the step of instantaneously loading the fuel cell at the loading rate, while the second instantaneous loading test includes the step of instantaneously loading the fuel cell at the second loading rate. Other contents between the two may be the same. Therefore, for the specific content of detecting the voltage drop rate of each battery cell of the fuel cell in the second instantaneous loading test, reference may be made to the content in the above step S14, which will not be repeated here.

[0077] Of course, after detecting the voltage drop rate of each cell of the fuel cell in the second instantaneous load test, it is possible to further determine whether the voltage drop rate of each cell is less than the voltage drop rate boundary value corresponding to the second load rate, and then determine whether to continue to load the fuel cell at the second load rate. For example, if the voltage drop rate of each cell is less than the voltage drop rate boundary value corresponding to the second load rate, the fuel cell will continue to be loaded at the second load rate; or if the voltage drop rate of one or more cells is greater than or equal to the voltage drop rate boundary value corresponding to the second load rate, the fuel cell will be loaded at a third load rate that is less than the second load rate.

[0078] The third increasing rate can be calculated based on the same principle as that for determining the second increasing rate, by multiplying the second increasing rate by the coefficient P, which will not be described in detail here.

[0079] Of course, in the process of loading the fuel cell at the third loading rate, based on the same principle, a new instantaneous loading experiment can still be carried out to determine whether the loading capacity of the fuel cell is exceeded when loading at the third loading rate, and thus ultimately achieve control of the fuel cell loading rate in this way.

[0080] Using the same inventive concept as the fuel cell loading rate control method provided in the embodiment of the present application, the embodiment of the present application also provides a fuel cell loading rate control device. For any unclear details about the specific description of the device, please refer to the corresponding content of the method. Figure 2 shows a schematic diagram of the specific structure of the device 20. The device 20 includes: an acquisition unit 201, a detection unit 202, and a loading rate control unit 203, wherein:

[0081] An acquiring unit 201 is configured to acquire a vehicle loading request, wherein the vehicle loading request includes a loading rate;

[0082] The detection unit 202 is configured to detect a voltage drop rate of each battery cell of the fuel cell in a transient load increase test when the load increase rate is greater than a preset threshold; wherein the transient load increase test includes a step of transiently increasing the load of the fuel cell at the load increase rate;

[0083] The loading rate control unit 203 is configured to determine whether to load the fuel cell at the loading rate according to the voltage drop rate of each battery cell and a voltage drop rate boundary value corresponding to the loading rate.

[0084] The device 20 provided in the embodiment of the present application is used. Since the device 20 adopts the same inventive concept as the fuel cell loading rate control method provided in the embodiment of the present application, on the premise that the method can solve the technical problem, the device 20 can also solve the technical problem, which will not be repeated here.

[0085] In addition, in actual applications, the technical effects achieved by combining the device 20 with specific hardware equipment such as vehicles, cloud technology, etc. are also within the scope of protection of this application. For example, different units in the device 20 are deployed in different nodes in the distributed cluster in a distributed cluster manner, or some units are deployed in cloud servers, etc., to improve efficiency and reduce costs.

[0086] The present application also provides a storage medium, including a program, which, when executed on an electronic device on a vehicle, enables the electronic device to execute all or part of the process of the method in the above embodiment. The storage medium may be a magnetic disk, an optical disk, a read-only memory (ROM), a random access memory (RAM), a flash memory, a hard disk drive (HDD), or a solid-state drive (SSD). The storage medium may also include a combination of the above types of memory.

[0087] The embodiment of the present application also provides an electronic device for use in a vehicle. FIG3 is a schematic diagram of the specific structure of the electronic device 3. The electronic device 3 includes: at least one processor 31 and a memory 32. FIG3 takes one processor as an example. The processor 31 and the memory 32 can be connected via a bus 30. The memory 32 stores instructions that can be executed by the processor 31. The instructions are executed by the processor 31 so that the electronic device 3 can execute all or part of the process of the method in the embodiment of the present application. For example, the electronic device 3 is set on a vehicle, and then the electronic device 3 is used to execute all or part of the process of the method in the embodiment of the present application.

[0088] An embodiment of the present application further provides a vehicle, in which a fuel cell is provided. The fuel cell loading rate control method provided in the embodiment of the present application is used to control the loading rate of the fuel cell in the vehicle.

[0089] Although the embodiments of the present application have been described with reference to the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present application, and such modifications and variations shall fall within the scope defined by the appended claims.

Claims

1. A fuel cell loading rate control method, It is characterized in that include: Obtaining a vehicle load increase request, wherein the vehicle load increase request includes a load increase rate; When the load rate is greater than a preset threshold, detecting the voltage drop rate of each battery cell of the fuel cell in the instantaneous load test; wherein the instantaneous load test includes the step of instantaneously loading the fuel cell at the load rate; According to the voltage drop rate of each battery cell and the voltage drop rate boundary value corresponding to the load increase rate, it is determined whether to increase the load of the fuel cell at the load increase rate.

2. The method according to claim 1, It is characterized in that The method further comprises: Using the load increase rate to query a preset corresponding relationship table or a preset corresponding relationship diagram to determine the voltage drop rate boundary value corresponding to the load increase rate; or, Substitute the load increase rate into the corresponding relationship calculation formula to determine the voltage drop rate boundary value corresponding to the load increase rate.

3. The method according to claim 2, It is characterized in that The method further includes: pre-generating a preset corresponding relationship diagram.

4. The method according to claim 1, It is characterized in that Determining whether to load the fuel cell at the loading rate according to the voltage drop rate of each battery cell and the voltage drop rate boundary value corresponding to the loading rate specifically includes: Determine whether the voltage drop rate of each battery cell is less than the voltage drop rate boundary value; If so, the fuel cell is loaded at the loading rate; or, If not, the fuel cell is loaded at a second loading rate that is lower than the loading rate.

5. The method according to claim 4, It is characterized in that Determining whether the voltage drop rate of each battery cell is less than the voltage drop rate boundary value specifically includes: Obtaining the maximum value of the voltage drop rate of each battery cell; Determining whether the maximum value is less than the voltage drop rate boundary value; Among them, if the maximum value is less than the voltage drop rate boundary value, the voltage drop rate of each battery cell is less than the voltage drop rate boundary value; or, if the maximum value is greater than or equal to the voltage drop rate boundary value, the voltage drop rate of at least one battery cell is greater than or equal to the voltage drop rate boundary value.

6. The method according to claim 5, It is characterized in that The method further includes: calculating the second loading rate by multiplying the loading rate by a coefficient less than 1.

7. The method according to claim 6, It is characterized in that The method further includes calculating the coefficient according to a difference or a ratio between the maximum value and the voltage drop rate boundary value.

8. The method according to claim 4, It is characterized in that The vehicle load increase request also includes a target load; and, Loading the fuel cell at the loading rate specifically includes: The load of the fuel cell is increased to the target load at the load increase rate.

9. The method according to claim 1, It is characterized in that The instantaneous load increase test includes the steps of performing instantaneous load increase on the fuel cell at the load increase rate for multiple times; as well as, Detecting the voltage drop rate of each battery cell of the fuel cell in the instantaneous load increase experiment specifically includes: In each instantaneous load increase step, the voltage drop rate of each battery cell is detected respectively; For each battery cell, an average value of the voltage drop rates detected each time is determined as the voltage drop rate of the battery cell.

10. A vehicle, It is characterized in that By using the method according to any one of claims 1 to 9, the loading rate of the fuel cell in the vehicle is controlled.

Citation Information

Patent Citations

  • Vehicle power boundary flexible control method and system

    CN112248878A

  • Vehicle-mounted fuel cell boost DCDC control method and system

    CN114094145A

  • Fuel cell engine loading control method, device and equipment

    CN114683969A

  • Fuel cell engine power control method, system, equipment and medium

    CN115991122A

  • Fuel cell lift rate control method and vehicle

    CN116278988A