Carbon dioxide capture tower
By setting up pre-washing, absorption and washing sections in the same tower, combining mist capture and liquid spraying technology, the high cost and large land occupation problems caused by the dual tower setup are solved, and efficient carbon dioxide capture and Intercepting harmful components improves the load adaptability and energy consumption efficiency of the system.
Patent Information
- Application Number
- PCT/CN2024/096380
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-05-31
- Filing Date
- 2024-05-30
- Publication Date
- 2024-12-05
AI Technical Summary
The existing carbon dioxide capture system has high manufacturing costs, large operation and maintenance, large footprint, poor load adaptability, and high energy consumption under low load conditions.
Design a carbon dioxide capture tower, and carry out pre-washing and decompression sections, carbon dioxide absorption sections and flue gas washing sections in the same tower, adopting a vertical segment structure, including gas distributors, liquid collection sections, and lean The liquid absorption segmentation, cooling absorption segmentation and washing segmentation are used to achieve uniform distribution and multiple interception of flue gas through mist capture, liquid spraying and washing liquid circulation systems, thereby reducing carbon dioxide residues and harmful components emissions.
Reduces the manufacturing cost and operation and maintenance workload of the carbon dioxide capture system, reduces the footprint, improves load adaptability and energy consumption efficiency under low load conditions, and achieves efficient removal of carbon dioxide in flue gas and harmful components. interception.
Smart Images

Figure CN2024096380_05122024_PF_FP_ABST
Abstract
Description
Carbon dioxide capture tower Technical Field
[0001] The present application relates to the technical field of carbon dioxide capture, and in particular to a carbon dioxide capture tower. Background Art
[0002] The basic process flow for flue gas CO2 capture consists of three main components: an absorption tower as the core, supplemented by pre-washing, gas-water separation, and boosting equipment; a regeneration tower and reboiler as the core, supplemented by regenerated gas, cooling gas, separators, and a reflux system; and the intermediate components, consisting primarily of a heat exchange system for the CO2-rich absorbent, the regenerated absorbent, and the filtration system. The pre-washing process is performed by a dedicated pre-washing tower, with flue gas piping connecting the pre-washing tower and the absorption tower, and a booster fan installed in the flue gas piping to overcome the resistance encountered by the flue gas during transmission. This system, which uses a pre-washing tower and an absorption tower to perform the pre-washing and CO2 absorption processes separately, requires corresponding auxiliary systems for each tower, as well as additional flue gas piping and booster fans to transport the flue gas between the pre-washing tower and the absorption tower. This results in high manufacturing costs for the flue gas CO2 capture system and significant operational maintenance. Furthermore, the dual-tower setup of the pre-washing tower and the absorption tower occupies a large area, subject to significant site constraints. Summary of the Invention
[0003] The purpose of this application is to provide a carbon dioxide capture tower to address at least one technical problem raised in the background technology.
[0004] In order to achieve the above objectives, this application adopts the following technical solutions:
[0005] One aspect of the present application provides a carbon dioxide capture tower, comprising a pre-wash and impurity removal section, a carbon dioxide absorption section and a flue gas scrubbing section arranged in sequence from bottom to top in a vertical direction, so that flue gas can flow through the pre-wash and impurity removal section, the carbon dioxide absorption section and the flue gas scrubbing section in sequence, a carbon dioxide capture tower flue gas inlet being provided on the pre-wash and impurity removal section, and a carbon dioxide capture tower flue gas outlet being provided on the scrubbing section.
[0006] Optionally, the pre-wash and impurity removal section includes a gas distributor, a first liquid collector, an impurity removal filler, a pre-wash liquid distributor and a pre-wash liquid feed pipe arranged in sequence from bottom to top, and the pre-wash liquid feed pipe is connected to the pre-wash liquid distributor to supply pre-wash liquid for pre-washing flue gas to the pre-wash liquid distributor through the pre-wash liquid feed pipe.
[0007] The beneficial effect of this technical solution is that after the flue gas enters the pre-wash and impurity removal section through the gas distributor, it can be relatively evenly distributed in the pre-wash and impurity removal section, the pre-wash liquid enters the pre-wash liquid distributor from the pre-wash liquid feed pipe, and is relatively evenly distributed through the pre-wash liquid distributor, the pre-wash liquid is fully in contact with the flue gas in the impurity removal filler, and trace impurities such as gypsum are removed. The pre-wash liquid that has completed impurity removal falls into the first liquid collector for collection.
[0008] Optionally, the carbon dioxide absorption section includes a plurality of segments arranged in a vertical direction, one of the segments is a liquid collection segment, the liquid collection segment is located at the bottom of the segments, the liquid collection segment includes a liquid collector, and the liquid collector includes a mist capture member.
[0009] The beneficial effect of this technical solution is that the mist capture element is used to effectively prevent the lean liquid from leaking into the pre-wash and impurity removal section.
[0010] Optionally, one of the segments is a lean liquid absorption segment, and the lean liquid absorption segment includes a second liquid collector, a first absorption filler, a lean liquid distributor and a lean liquid feed pipe arranged in sequence from bottom to top, the second liquid collector is used for allowing flue gas to pass through, and the lean liquid feed pipe is connected to the lean liquid distributor.
[0011] The beneficial effect of this technical solution is that the flue gas flows through the second liquid collector and the first absorption filler in the lean liquid absorption section, the lean liquid flows into the lean liquid distributor through the feed pipe, and is evenly sprayed onto the first absorption filler. In the first absorption filler, the flue gas and the lean liquid are fully in contact, so that the lean liquid absorbs carbon dioxide in the flue gas.
[0012] Optionally, one of the sections is a cooling absorption section, the liquid collection section, the cooling absorption section and the lean liquid absorption section are arranged in sequence from bottom to top, and the cooling absorption section is used to cool the flue gas and absorb carbon dioxide in the flue gas.
[0013] The beneficial effect of this technical solution is that, in this way, carbon dioxide can be removed from the flue gas in both the cooling absorption section and the lean liquid absorption section, which greatly reduces the carbon dioxide residue that may appear in the flue gas. When an absorption filler is set in the liquid collection section, the lean liquid can also absorb carbon dioxide in the flue gas in the liquid collection section.
[0014] Optionally, the cooling absorption segment includes a third liquid collector, a second absorption filler, an absorption cooling liquid distributor and an absorption cooling liquid feed pipe arranged in sequence from bottom to top, the third liquid collector is used for flue gas to pass through, and the absorption cooling liquid feed pipe is connected to the absorption cooling liquid distributor.
[0015] The beneficial effect of this technical solution is that, in the process of successively passing through the cooling absorption section and the lean liquid absorption section, the flue gas is fully in contact with the lean liquid, and the lean liquid absorbs the carbon dioxide in the flue gas. At the same time, the lean liquid also cools the flue gas, which greatly reduces the carbon dioxide residue that may exist in the flue gas finally discharged from the carbon dioxide capture tower and greatly reduces the temperature of the flue gas before it is discharged from the carbon dioxide capture tower.
[0016] Optionally, the flue gas scrubbing section includes a scrubbing section and a defoaming section, and the scrubbing section is located below the defoaming section.
[0017] The beneficial effect of this technical solution is that by re-washing the flue gas, the harmful components that may exist in the flue gas can be reduced to a large extent, making it difficult for these harmful components to be discharged from the carbon dioxide capture tower. By setting up a defoaming section, the harmful substances in the carbon dioxide capture tower are not easily discharged from the tower in the form of foam.
[0018] Optionally, the defoaming segment includes a fourth liquid collector, a first washing filler, a first washing liquid distributor, a first washing liquid feed pipe and a wire mesh demister arranged in sequence from bottom to top, the first washing liquid feed pipe is connected to the first washing liquid distributor, and the fourth liquid collector is used for flue gas to pass through.
[0019] The beneficial effect of this technical solution is that: in the defoaming section, the flue gas flows through the fourth liquid collector and the first washing filler in sequence, and the washing liquid enters the first washing liquid distributor through the first washing liquid feed pipe and is distributed more evenly on the first washing filler. In the first washing filler, the flue gas and the washing liquid are fully in contact to absorb the solution components in the flue gas, making it difficult for the solution components to escape with the flue gas and cause losses and secondary pollution. The wire mesh demister makes it difficult for the solution components in the flue gas to flow out of the carbon dioxide capture tower in the form of foam, further reducing the possibility of solution component escape and secondary pollution.
[0020] Optionally, the washing section includes a fifth liquid collector, a second washing filler, a second washing liquid distributor and a second washing liquid feed pipe, the second washing liquid distributor is connected to the second washing liquid feed pipe, and the fifth liquid collector is used for allowing flue gas to pass through.
[0021] The beneficial effects of this technical solution are: in the washing section, the flue gas flows through the fifth liquid collector and the second washing filler in sequence, the washing liquid enters the second washing liquid distributor through the second washing liquid feed pipe, and is more evenly distributed on the second washing filler. In the second washing filler, the flue gas is fully in contact with the washing liquid to absorb the solution components in the flue gas, so that the solution is not easy to escape with the flue gas to cause loss and secondary pollution; through the two washing and one defoaming of the flue gas by the washing section and the defoaming section, a triple interception is formed for the solution components that may be carried by the flue gas, making it more difficult for the solution components to escape with the flue gas. In some ideal cases, the flue gas washing section can intercept all the solution components carried by the flue gas.
[0022] Optionally, a washing liquid circulation system is also included, and the washing section and the defoaming section are both connected to the washing liquid circulation system. The washing liquid circulation system is used to supply washing liquid to the washing section and the defoaming section, and the washing liquid circulation system is used to receive washing liquid flowing out from the washing section and the defoaming section.
[0023] The beneficial effect of this technical solution is that the washing liquid can be recycled through the washing liquid circulation system, saving costs.
[0024] The technical solution provided by this application can achieve the following beneficial effects:
[0025] The carbon dioxide capture tower provided by the present application arranges the pre-wash impurity removal section, the carbon dioxide absorption section and the flue gas washing section in the same tower, so that the pre-wash process and the carbon dioxide absorption process are carried out in the same tower. Only one set of auxiliary systems is required for one tower, and the flue gas pipeline and the booster fan previously provided for connecting the pre-wash tower and the absorption tower are removed, thereby reducing the manufacturing cost of the carbon dioxide capture system, making the initial investment of the project lower and the control requirements also lowered. At the same time, compared with maintaining the two towers of the pre-wash tower and the absorption tower and the corresponding auxiliary systems, maintaining only the carbon dioxide capture tower and the corresponding auxiliary systems reduces the workload of later operation and maintenance. In addition, compared with the traditional use of A carbon dioxide capture system in which a pre-washing tower and an absorption tower complete the two processes of pre-washing and carbon dioxide absorption uses a carbon dioxide capture system that uses the carbon dioxide capture tower provided in an embodiment of the present application. The two processes of pre-washing and carbon dioxide absorption can be completed by one tower, which effectively reduces the footprint of the carbon dioxide capture system and makes the layout of the carbon dioxide capture system relatively flexible and less restricted by the site. Moreover, the use of the pre-washing tower and the absorption tower to complete the two processes of pre-washing and carbon dioxide has poor load adaptability and high energy consumption under low-load conditions. However, the carbon dioxide capture tower provided in the present application is easy to operate, has high load adaptability, and has low energy consumption under low-load conditions.
[0026] In order to make the above and other objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0028] FIG1 is a schematic structural diagram of an embodiment of a carbon dioxide capture tower provided in an embodiment of the present application;
[0029] FIG2 is a partial structural schematic diagram of an embodiment of a carbon dioxide capture tower provided in an example of the present application;
[0030] FIG3 is a schematic diagram of a liquid collector with a mist capture device provided in an embodiment of the present application;
[0031] FIG4 is a schematic diagram of a liquid collector with a mist capture device provided in an embodiment of the present application.
[0032] Reference numerals:
[0033] 01-Flue gas scrubbing section; 02-Carbon dioxide absorption section;
[0034] 03- pre-wash liquid distributor; 04- pre-wash impurity removal section;
[0035] 05-second washing liquid distributor; 06-second liquid collector;
[0036] 07-Absorption coolant distributor; 08-Third liquid collector;
[0037] 09-Liquid collector; 10-Impurity removal filler;
[0038] 11-support beam; 12-first liquid collector;
[0039] 13-gas distributor; 14-support grid;
[0040] 15-pressing plate; 16-pre-wash liquid feeding pipe;
[0041] 17-absorbent filler; 18-second absorbent filler;
[0042] 19-absorption coolant feed pipe; 20-first absorption filler;
[0043] 21-lean liquid distributor; 22-second washing liquid feed pipe;
[0044] 23-first washing liquid distributor; 24-first washing liquid feed pipe;
[0045] 25-wire mesh demister; 26-lean liquid feed pipe;
[0046] 27- fourth liquid collector; 28- first washing filler;
[0047] 29-fifth liquid collector; 30-second washing filler;
[0048] 1-base plate; 2-ascending air pipe;
[0049] 3-Liter gas cap; 5-Flange;
[0050] 4-Mist capture device. DETAILED DESCRIPTION
[0051] The following will clearly and completely describe the technical solution of this application in conjunction with the accompanying drawings. Obviously, the embodiments described are only part of the embodiments of this application, not all of them. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making any creative efforts are within the scope of protection of this application.
[0052] In the description of this application, it should be noted that the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," and "outer," etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings and are intended solely to facilitate the description of this application and simplify the description. They do not indicate or imply that the devices or components referred to must have a specific orientation, be constructed, or operate in a specific orientation. Therefore, they should not be construed as limitations on this application. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.
[0053] In the description of this application, it should be noted that, unless otherwise expressly specified or limited, the terms "mounted," "connected," and "connected" should be understood in a broad sense. For example, they can refer to fixed connections, detachable connections, or integral connections; mechanical connections or electrical connections; direct connections or indirect connections through an intermediate medium; and internal connections between two components. Those skilled in the art will understand the specific meanings of the above terms in this application based on the specific circumstances.
[0054] As shown in Figures 1 and 2, one aspect of the present application provides a carbon dioxide capture tower, including a pre-wash and impurity removal section 04, a carbon dioxide absorption section 02 and a flue gas scrubbing section 01 arranged in sequence from bottom to top in the vertical direction, so that the flue gas can flow through the pre-wash and impurity removal section 04, the carbon dioxide absorption section 02 and the flue gas scrubbing section 01 in sequence, and a carbon dioxide capture tower flue gas inlet is provided on the pre-wash and impurity removal section 04, and a carbon dioxide capture tower flue gas outlet is provided on the scrubbing section.
[0055] During use, the flue gas after desulfurization enters the pre-wash and impurity removal section 04 from the flue gas inlet of the carbon dioxide capture tower, flows through the pre-wash and impurity removal section 04, the carbon dioxide absorption section 02 and the flue gas washing section 01 in sequence, and finally flows out of the carbon dioxide capture tower from the flue gas outlet of the carbon dioxide capture tower. In the pre-wash and impurity removal section 04, the flue gas is pretreated to remove trace impurities such as gypsum carried in the flue gas. The flue gas flows from bottom to top in the carbon dioxide absorption section 02 and contacts the lean liquid sprayed into the tower from the top in countercurrent, so that the carbon dioxide is removed. The flue gas enters the flue gas washing section 01. In the flue gas washing section 01, it is directly sprayed with water to wash and recover the solution components carried by the flue gas, so that the solution is not easily lost and secondary pollution is caused by escaping with the flue gas. Finally, decarbonized flue gas is discharged from the carbon dioxide capture tower. In the embodiment of the present application, the amine solution that has not absorbed carbon dioxide is called lean liquid, and the amine solution after absorbing carbon dioxide is called rich liquid. The lean liquid can also be called carbon capture absorption solution.
[0056] The carbon dioxide capture tower provided by the present application arranges the pre-wash and impurity removal section 04, the carbon dioxide absorption section 02 and the flue gas washing section 01 in the same tower, so that the pre-wash process and the carbon dioxide absorption process are carried out in the same tower. One tower only requires one set of auxiliary systems (including but not limited to the bottom support system), and the flue gas pipeline and the booster fan previously provided for connecting the pre-wash tower and the absorption tower are removed, thereby reducing the manufacturing cost of the carbon dioxide capture system, making the initial investment of the project lower and the control requirements also reduced. At the same time, compared with maintaining the two towers of the pre-wash tower and the absorption tower and the corresponding auxiliary systems, maintaining only the carbon dioxide capture tower and the corresponding auxiliary systems reduces the workload of later operation, overhaul and maintenance. In addition, compared with the traditional carbon dioxide capture system that uses a pre-wash tower and an absorption tower to complete the two processes of pre-washing and carbon dioxide absorption, the carbon dioxide capture system using the carbon dioxide capture tower provided in the embodiment of the present application can complete the two processes of pre-washing and carbon dioxide absorption with one tower, which effectively reduces the footprint of the carbon dioxide capture system and makes the layout of the carbon dioxide capture system relatively flexible and less restricted by the site; moreover, the use of a pre-wash tower and an absorption tower to complete the two processes of pre-washing and carbon dioxide has poor load adaptability and high energy consumption under low-load conditions, but the carbon dioxide capture tower provided by the present application is easy to operate, has high load adaptability, and has low energy consumption under low-load conditions.
[0057] Optionally, the pre-wash and impurity removal section 04 includes a gas distributor 13, a first liquid collector 12, an impurity removal filler 10, a pre-wash liquid distributor 03, and a pre-wash liquid feed pipe 16, which are arranged in sequence from bottom to top. The pre-wash liquid feed pipe 16 is connected to the pre-wash liquid distributor 03 to supply pre-wash liquid for pre-washing the flue gas to the pre-wash liquid distributor 03 through the pre-wash liquid feed pipe 16. After the flue gas enters the pre-wash and impurity removal section 04 through the gas distributor 13, it can be relatively evenly distributed in the pre-wash and impurity removal section 04. The pre-wash liquid enters the pre-wash liquid distributor 03 from the pre-wash liquid feed pipe 16 and is relatively evenly distributed through the pre-wash liquid distributor 03. The pre-wash liquid fully contacts the flue gas in the impurity removal filler 10, thereby removing impurities such as trace gypsum. The pre-wash liquid that has completed impurity removal falls into the first liquid collector 12 for collection. The pre-wash liquid distributor 03 is preferably a liquid spraying device.
[0058] Optionally, the carbon dioxide absorption section 02 includes a plurality of segments arranged in the vertical direction, one of the segments being a liquid collection segment, the liquid collection segment being located at the bottom of the segments, and the liquid collection segment including a liquid collector 09, and the liquid collector 09 including a mist capture piece. The mist capture piece described in the embodiment of the present application is a mist capture piece or other mist capture device; by adopting the mist capture piece, the lean liquid is effectively prevented from leaking into the pre-washing and impurity removal section 04. Preferably, the liquid collection segment also includes an absorption filler 17, which is arranged above the liquid collector 09. The flue gas in the liquid collection segment flows through the liquid collector 09 and the absorption filler 17 in sequence. The lean liquid flowing into the liquid collection segment from above is in full contact with the flue gas in the absorption filler 17, so that the lean liquid can absorb the carbon dioxide in the flue gas.
[0059] As shown in Figures 3 and 4, a liquid collector with a mist collection device provided in an embodiment of the present application includes a bottom plate 1, an air riser 2, an air riser cap 3, the air riser cap includes a top plate and a flange 5, and the flange 5 of the air riser cap is downward, and the mist collection device 4 is arranged in the space formed between the air riser and the flange of the air riser cap 5.
[0060] The present invention prevents back-mixing of liquid above and below the liquid collector by arranging the mist capture device 4 between the air riser 2 and the flange 5 of the air riser cap.
[0061] Optionally, one of the sections is a lean liquid absorption section, which includes a second liquid collector 06, a first absorption filler 20, a lean liquid distributor 21, and a lean liquid feed pipe 26, arranged in sequence from bottom to top. The second liquid collector 06 is used to allow flue gas to pass through, and the lean liquid feed pipe 26 is connected to the lean liquid distributor 21. It can be understood that the lean liquid absorption section and the liquid collection section are not the same section; the second liquid collector 06 is preferably a gas cap liquid collector; in the lean liquid absorption section, the flue gas flows through the second liquid collector 06 and the first absorption filler 20, and the lean liquid flows into the lean liquid distributor 21 through the feed pipe and is evenly sprayed onto the first absorption filler 20. In the first absorption filler 20, the flue gas and the lean liquid are fully in contact, so that the lean liquid absorbs carbon dioxide in the flue gas; the lean liquid distributor 21 is preferably a liquid spraying device.
[0062] Optionally, one of the segments is a cooling absorption segment, and the liquid collection segment, the cooling absorption segment, and the lean liquid absorption segment are arranged sequentially from bottom to top. The cooling absorption segment is used to cool the flue gas and absorb carbon dioxide from the flue gas. In this way, carbon dioxide can be removed from the flue gas in both the cooling absorption segment and the lean liquid absorption segment, significantly reducing the potential for residual carbon dioxide in the flue gas. When the absorbent filler 17 is provided in the liquid collection segment, the lean liquid can also absorb carbon dioxide from the flue gas in the liquid collection segment.
[0063] Optionally, the cooling absorption section includes a third liquid collector 08, a second absorption filler 18, an absorption coolant distributor 07, and an absorption coolant feed pipe 19, arranged sequentially from bottom to top. The third liquid collector 08 is used to allow flue gas to pass through, and the absorption coolant feed pipe 19 is connected to the absorption coolant distributor 07. In the embodiment of the present application, an amine solution, which also serves as a lean liquid, is preferably used as the absorption coolant. In this way, the flue gas is fully contacted with the lean liquid during its flow through the cooling absorption section and the lean liquid absorption section. The lean liquid absorbs carbon dioxide in the flue gas and also cools the flue gas. This greatly reduces the carbon dioxide residue that may be present in the flue gas that is finally discharged from the carbon dioxide capture tower and greatly reduces the temperature of the flue gas before it is discharged from the carbon dioxide capture tower. The third liquid collector 08 is preferably a gas cap liquid collector; the absorption coolant distributor 07 is preferably a liquid spray device.
[0064] Optionally, the flue gas scrubbing section 01 includes a scrubbing section and a defoaming section, with the scrubbing section located below the defoaming section. Re-scrubbing the flue gas can minimize any harmful components that may be present in the flue gas, making them less likely to be discharged from the CO2 capture tower. The defoaming section also prevents harmful substances from being discharged from the CO2 capture tower as foam.
[0065] Optionally, the defoaming section includes, arranged from bottom to top, a fourth liquid collector 27, a first washing filler 28, a first washing liquid distributor 23, a first washing liquid feed pipe 24, and a wire mesh demister 25. The first washing liquid feed pipe 24 is connected to the first washing liquid distributor 23. The fourth liquid collector 27 is used to allow flue gas to pass through. In this embodiment of the present application, the fourth liquid collector 27 is preferably a rising gas cap liquid collector, and the first washing liquid distributor 23 is preferably a liquid spray device. In the defoaming section, the flue gas flows through the fourth liquid collector 27 and the first washing filler 28 in sequence. The washing liquid enters the first washing liquid distributor 23 through the first washing liquid feed pipe 24 and is evenly distributed on the first washing filler 28. In the first washing filler 28, the flue gas and the washing liquid are fully in contact to absorb the solution components in the flue gas, making it difficult for the solution components to escape with the flue gas and cause loss and secondary pollution. The wire mesh demister 25 makes it difficult for the solution components in the flue gas to flow out of the carbon dioxide capture tower in the form of foam, further reducing the possibility of solution component escape and secondary pollution.
[0066] Optionally, the scrubbing section includes a fifth liquid collector 29, a second scrubbing filler 30, a second scrubbing liquid distributor 05, and a second scrubbing liquid feed pipe 22. The second scrubbing liquid distributor 05 is connected to the second scrubbing liquid feed pipe 22. The fifth liquid collector 29 is used to allow flue gas to pass through. In this embodiment of the present application, the fifth liquid collector 29 is preferably a gas cap collector, and the second scrubbing liquid distributor 05 is preferably a liquid spray device. In the washing section, the flue gas flows through the fifth liquid collector 29 and the second washing filler 30 in sequence, and the washing liquid enters the second washing liquid distributor 05 through the second washing liquid feed pipe 22 and is evenly distributed on the second washing filler 30. In the second washing filler 30, the flue gas is fully in contact with the washing liquid to absorb the solution components in the flue gas, so that the solution is not easy to escape with the flue gas to cause loss and secondary pollution; through the two washing and one defoaming of the flue gas by the washing section and the defoaming section, a triple interception is formed for the solution components that may be carried by the flue gas, making it more difficult for the solution components to escape with the flue gas. In some ideal cases, the flue gas washing section 01 can intercept all the solution components carried by the flue gas.
[0067] Optionally, the carbon dioxide capture tower provided in the embodiments of the present application further includes a washing liquid circulation system, to which the washing segment and the defoaming segment are both connected, the washing liquid circulation system being used to supply washing liquid to the washing segment and the defoaming segment, and the washing liquid circulation system being used to receive washing liquid flowing out of the washing segment and the defoaming segment. In this way, the washing liquid circulation system can be used to recycle and reuse the washing liquid, saving costs; preferably, the washing liquid circulation system has a water replenishment function, so that when washing liquid is lost, desalted water can be added as washing liquid.
[0068] Preferably, each filler in the embodiment of the present application is provided with an auxiliary component for supporting and fixing the filler, and the auxiliary component may include a support beam 11, a support grid 14, a pressure plate 15, etc. For example, in the embodiment of the present application, the pre-wash and impurity removal section 04 also includes a support beam 11, a support grid 14, and a pressure plate 15, and the gas distributor 13, the first liquid collector 12, the support beam 11, the support grid 14, the impurity removal filler 10, the pressure plate 15, the pre-wash liquid distributor 03, and the pre-wash liquid feed pipe 16 are arranged in sequence from bottom to top, the support beam 11 and the support grid 14 are used to support the impurity removal filler 10, and the pressure plate 15 is used to press the impurity removal filler 10. In the embodiment of the present application, the filler used in the flue gas scrubbing section 01 and the pre-wash and impurity removal section 04 is preferably PP (Chinese name: polypropylene) material, and the filler used in the carbon dioxide absorption section 02 is preferably 304 stainless steel, such as 304 stainless steel structured corrugated filler, 304 stainless steel structured filler, or 304 metal honeycomb inclined plate filler. In the embodiment of the present application, the pre-wash liquid is preferably a low-concentration sodium hydroxide aqueous solution, i.e., alkaline solution.
[0069] To better illustrate the carbon dioxide capture tower provided in this application, this application also provides an application example of the carbon dioxide capture tower. In this application example, the pre-wash and impurity removal section 04 is also referred to as the pre-wash section, the carbon dioxide absorption section 02 is also referred to as the absorption section, the flue gas scrubbing section 01 is also referred to as the scrubbing section, the support beam 11 is also referred to as the packing support beam, and the carbon dioxide capture tower is also referred to as the composite absorption tower. The application example is as follows:
[0070] This application example involves a new composite absorption tower for carbon dioxide capture, which combines the functions of a pre-wash tower and an absorption tower in traditional processes. That is, the flue gas is washed, cooled, and CO2 is recovered in the CO2 composite absorption tower, and then discharged from the top of the CO2 composite absorption tower after further washing and cooling.
[0071] The basic process flow of flue gas CO2 capture mainly consists of three parts: the absorption tower as the center, supplemented by pre-washing, gas-water separation and boosting equipment; the regeneration tower and reboiler as the center, supplemented by regeneration gas, cooling gas, separator and reflux system; the part between the above two mainly includes CO2-rich absorption liquid, regeneration absorption liquid heat exchange system and filtration system.
[0072] The flue gas temperature at the outlet is approximately 48°C, which is within the ideal absorption temperature range for amine solutions. The flue gas is pretreated in the pre-wash tower to remove trace impurities such as gypsum. A booster fan is used to overcome resistance as the gas passes through the pre-treatment system and absorption tower.
[0073] In the absorption tower, flue gas flows upward, countercurrently contacting the amine solution sprayed into the tower from above, removing CO2. The exhaust gas is then discharged into the atmosphere through the top of the tower. To prevent the solution from escaping with the flue gas and causing losses and secondary pollution, an exhaust gas scrubber is installed at the top of the absorption tower. This scrubber recovers the solution components carried by the flue gas through direct water spraying. The scrubbing water is recycled. When the capture system needs to be replenished, the scrubbing water is first used to replenish the system, and any lost scrubbing water is replaced with demineralized water.
[0074] The rich liquid after CO2 absorption is pumped from the bottom of the tower into the lean-rich liquid heat exchanger, sprayed into the upper part of the regeneration tower, and partially desorbed by steam stripping. The semi-lean liquid after steam stripping and desorption enters the reboiler for further CO2 desorption. The lean liquid after CO2 desorption in the reboiler flows out of the bottom of the regeneration tower, is cooled in the lean-rich liquid heat exchanger and lean liquid cooler, and then enters the absorption tower for recycling. This back-and-forth solvent circulation constitutes a continuous CO2 absorption and desorption process.
[0075] The desorbed CO2, along with the water vapor, is cooled and separated to remove the water, resulting in high-purity CO2 gas that is then fed into the subsequent compression system. The condensed water separated from the regenerated gas is pumped to the regeneration tower to regulate the temperature inside the tower.
[0076] In order to keep the solution clean, about 10-15% of the lean liquid is filtered through an activated carbon filter; in order to treat the degradation products of the system, a solution purification and recovery system is set up. When necessary, part of the lean liquid is sent to the purification and recovery system and a prescribed alkaline solution is added for purification and recovery.
[0077] In the above process, the pre-wash tower and the absorption tower are set separately, which has the following problems: 1) The dual towers and their relatively complete auxiliary system configuration make the system process relatively complex, with high control requirements, high initial project investment, and a large workload for later operation, inspection and maintenance; 2) Due to the installation of two towers, the floor area is larger than that of a single tower, and the application is obviously restricted by the site; 3) The load adaptability is poor, and the energy consumption is high under low-load conditions.
[0078] The composite absorption tower proposed in this application example combines a pre-washer and absorption tower into one. Flue gas from the unit's desulfurization system first enters the pre-wash section of the composite absorption tower, where it undergoes pretreatment to remove trace impurities such as gypsum. It then enters the absorption section of the composite absorption tower for decarbonization. Finally, the flue gas enters the scrubbing section to recover the solution components carried by the flue gas. In other words, the flue gas is scrubbed, cooled, and CO2 is recovered in the CO2 composite absorption tower. After further scrubbing and cooling, it is discharged from the top of the CO2 composite absorption tower.
[0079] Compared with the double towers (pre-wash tower and absorption tower), the advantages of the composite absorption tower are: 1) The two towers are combined into one, the carbon capture system process is relatively simple, the initial investment of the project is low, and the workload of later operation inspection and maintenance is small; 2) The floor area is smaller than that of a single tower, and the application is less restricted by the site; 3) It is easy to operate, has high load adaptability, and has low energy consumption under low-load conditions.
[0080] The composite absorption tower consists of a pre-wash section, an absorption section, and a washing section from bottom to top. Flue gas enters the composite absorption tower from the bottom of the tower. The functions of each section are as follows:
[0081] (1) In the pre-washing section, the flue gas is pretreated to remove trace impurities such as gypsum carried by the flue gas.
[0082] (2) In the absorption section, the flue gas flows from bottom to top and contacts the carbon capture absorption solution sprayed into the tower from the top in countercurrent, so that CO2 is removed and the tail gas enters the washing section.
[0083] (3) A liquid collector with a mist capture device is installed in the pre-wash section and the absorption section to prevent the captured solution from leaking into the pre-wash section.
[0084] (4) In the washing section, the solution components carried by the flue gas are recovered by direct spraying water to avoid the loss and secondary pollution caused by the escape of the solution with the flue gas. The washing water can be recycled. When the capture system needs to be replenished with water, the washing water is first used to replenish the system. The lost washing water is replenished with desalted water.
[0085] The detailed scheme of the composite absorption tower and the specific structure of each section are as follows:
[0086] (1) Pre-wash section (Bed6): The structural layout from bottom to top should be gas distributor, liquid collector, packing support beam, support grid, packing, pressure plate, liquid distributor, and feed pipe;
[0087] (2) Absorption section (Bed3-5): The structural layout of Bed5 from bottom to top should be liquid collector, filler and its auxiliary components; the structural layout of Bed4 should be liquid collector, filler and its auxiliary components, liquid distributor, intermediate absorption cooling feed pipe; the structural layout of Bed3 should be liquid collector, filler and its auxiliary components, liquid distributor, lean liquid feed pipe;
[0088] (3) Tail gas washing section (Bed1-2): The structural layout of Bed2 should be liquid collector, packing and its accessories, liquid distributor, lower section washing liquid feed pipe; the structural layout of Bed1 should be liquid collector, packing and its accessories, liquid distributor, upper section washing liquid feed pipe, wire mesh demister and its accessories.
[0089] The composite absorption tower proposed in this application example combines a pre-washer and an absorption tower into one. Flue gas from the unit's desulfurization system first enters the pre-wash section of the composite absorption tower, where it undergoes pretreatment to remove trace impurities such as gypsum. It then enters the absorption tower for decarbonization. Finally, the flue gas enters the scrubbing section to recover the solution components carried by the flue gas. In other words, the flue gas is scrubbed, cooled, and CO2 recovered in the CO2 composite absorption tower. After further scrubbing and cooling, it is discharged from the top of the CO2 composite absorption tower.
[0090] Compared with the double towers (pre-wash tower and absorption tower), the advantages of the composite absorption tower are: 1) The two towers are combined into one, the carbon capture system process is relatively simple, the initial investment of the project is low, and the workload of later operation inspection and maintenance is small; 2) The floor area is smaller than that of a single tower, and the application is less restricted by the site; 3) It is easy to operate, has high load adaptability, and has low energy consumption under low-load conditions.
[0091] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some or all of the technical features therein. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present application.
Claims
1. Carbon dioxide capture tower, It is characterized in that The invention comprises a pre-washing and impurity removal section, a carbon dioxide absorption section and a flue gas washing section which are arranged in sequence from bottom to top in the vertical direction, so that the flue gas can flow through the pre-washing and impurity removal section, the carbon dioxide absorption section and the flue gas washing section in sequence, a carbon dioxide capture tower flue gas inlet is arranged on the pre-washing and impurity removal section, and a carbon dioxide capture tower flue gas outlet is arranged on the washing section.
2. The carbon dioxide capture tower according to claim 1, It is characterized in that The pre-wash and impurity removal section includes a gas distributor, a first liquid collector, an impurity removal filler, a pre-wash liquid distributor and a pre-wash liquid feed pipe arranged in sequence from bottom to top. The pre-wash liquid feed pipe is connected to the pre-wash liquid distributor to supply pre-wash liquid for pre-washing flue gas to the pre-wash liquid distributor through the pre-wash liquid feed pipe.
3. The carbon dioxide capture tower according to claim 1, It is characterized in that The carbon dioxide absorption section includes a plurality of segments arranged in a vertical direction, one of the segments is a liquid collection segment, and the liquid collection segment is located at the bottom of the segments. The liquid collection segment includes a liquid collector, and the liquid collector includes a mist capture member.
4. The carbon dioxide capture tower according to claim 3, It is characterized in that One of the sections is a lean liquid absorption section, which includes a second liquid collector, a first absorption filler, a lean liquid distributor and a lean liquid feed pipe arranged in sequence from bottom to top. The second liquid collector is used for flue gas to pass through, and the lean liquid feed pipe is connected to the lean liquid distributor.
5. The carbon dioxide capture tower according to claim 4, It is characterized in that One of the sections is a cooling absorption section. The liquid collecting section, the cooling absorption section and the lean liquid absorption section are arranged in sequence from bottom to top. The cooling absorption section is used to cool the flue gas and absorb carbon dioxide in the flue gas.
6. The carbon dioxide capture tower according to claim 5, It is characterized in that The cooling absorption section includes a third liquid collector, a second absorption filler, an absorption cooling liquid distributor and an absorption cooling liquid feed pipe which are arranged in sequence from bottom to top. The third liquid collector is used for flue gas to pass through, and the absorption cooling liquid feed pipe is connected to the absorption cooling liquid distributor.
7. The carbon dioxide capture tower according to any one of claims 1 to 6, It is characterized in that The flue gas scrubbing section comprises a scrubbing section and a defoaming section, and the scrubbing section is located below the defoaming section.
8. The carbon dioxide capture tower according to claim 7, It is characterized in that The defoaming section includes a fourth liquid collector, a first washing filler, a first washing liquid distributor, a first washing liquid feed pipe and a wire mesh defoamer arranged in sequence from bottom to top, the first washing liquid feed pipe is connected to the first washing liquid distributor, and the fourth liquid collector is used for flue gas to pass through.
9. The carbon dioxide capture tower according to claim 7, It is characterized in that The washing section comprises a fifth liquid collector, a second washing filler, a second washing liquid distributor and a second washing liquid feed pipe, wherein the second washing liquid distributor is connected to the second washing liquid feed pipe, and the fifth liquid collector is used for allowing flue gas to pass through.
10. The carbon dioxide capture tower according to claim 7, It is characterized in that It also includes a washing liquid circulation system, the washing section and the defoaming section are both connected to the washing liquid circulation system, the washing liquid circulation system is used to supply washing liquid to the washing section and the defoaming section, and the washing liquid circulation system is used to receive the washing liquid flowing out from the washing section and the defoaming section.
Citation Information
Patent Citations
Apparatus for gas scrubbing
CN104797321A
Waste heat driving based boiler smoke exhaust total component treatment and resource recycling mode
CN110131742A
Partitioned multi-stage circulating CO2 trapping and concentrating method based on mass transfer-reaction regulation and control
CN113521966A
Device and method for capturing and absorbing carbon dioxide in flue gas
CN115999336A
Carbon dioxide trapping tower
CN116510469A
Cited By
Integrated flue gas purification tower
CN119819100A