Wideband oscillation risk assessment method and system for new energy grid-connected system, and device and medium
By constructing impedance external characteristic models for new energy power plants and AC power grids, the accuracy and adaptability issues of broadband oscillation risk assessment in new energy grid-connected systems were resolved, achieving more accurate risk assessment.
Patent Information
- Application Number
- PCT/CN2025/118203
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2025-05-07
- Filing Date
- 2025-09-01
- Publication Date
- 2026-11-12
AI Technical Summary
Existing technologies cannot fully consider various operating conditions in new energy grid-connected systems, resulting in low accuracy and poor adaptability in broadband oscillation risk assessment.
Impedance external characteristic models of new energy power plants and AC power grids are constructed. By comparing the impedance external characteristic curves of new energy power plants and AC power grids, broadband oscillation risk is assessed, taking into account the impact of topology and operating conditions.
It improves the accuracy and adaptability of broadband oscillation risk assessment for new energy grid-connected systems, and can handle oscillation risks in different frequency bands more flexibly.
Smart Images

Figure CN2025118203_12112026_PF_FP_ABST
Abstract
Description
A method, system, equipment, and medium for assessing broadband oscillation risk in a new energy grid-connected system.
[0001] This application claims priority to Chinese Patent Application No. 202510578590.4, filed on May 7, 2025, entitled "A Method, System, Device and Medium for Broadband Oscillation Risk Assessment of New Energy Grid-Connected Systems", the entire contents of which are incorporated herein by reference. Technical Field
[0002] This invention relates to the field of power system technology, and in particular to a method, system, equipment and medium for assessing broadband oscillation risk in new energy grid-connected systems. Background Technology
[0003] In recent years, new energy sources, represented by offshore wind power and photovoltaics, have experienced explosive growth. It is estimated that by 2030, the total installed capacity of new energy in my country will account for nearly 50%. New energy power plant AC grid-connected systems contain a large number of power electronic conversion devices such as new energy converters and static var generators (SVG). These devices interact with high-frequency filter circuits, the ground capacitance of bus cables / overhead lines, and grid impedance, leading to an increased risk of resonance in the AC grid-connected system of new energy power plants.
[0004] In large-scale renewable energy grid connection projects, the occurrence of multiple broadband oscillation events may greatly threaten the stability of the power grid project.
[0005] Therefore, it is evident that broadband oscillations in power electronic device-connected systems pose a high risk, characterized by wide resonant frequency ranges, diverse types, and complex mechanisms, seriously threatening the safe and stable operation of grid-connected equipment and the power system. Thus, it is necessary to conduct an assessment of the broadband oscillation risk in new energy grid-connected systems.
[0006] Currently, the broadband oscillation risk assessment methods for new energy grid-connected systems are difficult to consider various operating conditions of the system, which easily leads to low accuracy and poor adaptability in the broadband oscillation risk assessment of new energy grid-connected systems. Summary of the Invention
[0007] In view of this, the present invention provides a method, system, device and medium for assessing broadband oscillation risk in new energy grid-connected systems, which solves the technical problem that broadband oscillation risk assessment methods for new energy grid-connected systems are difficult to consider various operating conditions of the system, which easily leads to low accuracy and poor adaptability in the assessment of broadband oscillation risk of new energy grid-connected systems.
[0008] In this invention, a first aspect provides a method for assessing broadband oscillation risk in a new energy grid-connected system. This method is applied to assess the broadband oscillation risk of a new energy grid-connected system in different broadband oscillation risk assessment frequency bands, including mid-to-high frequency bands and sub-supersynchronous frequency bands; comprising:
[0009] Based on the multiple electrical units of the new energy power station, an impedance external characteristic model of each electrical unit is established;
[0010] Based on the impedance external characteristic model and wiring structure of each electrical unit of the new energy power station, the electrical units are connected, and based on the impedance series and parallel relationship of each electrical unit, the impedance external characteristic model of the new energy power station corresponding to the broadband oscillation risk assessment frequency band is obtained.
[0011] Based on different broadband oscillation risk assessment frequency bands, determine the impedance external characteristic model of the AC power grid corresponding to the broadband oscillation risk assessment frequency band;
[0012] Based on the impedance external characteristic model of the new energy power station and the impedance external characteristic model of the AC power grid, the impedance external characteristic curves of the new energy power station and the AC power grid are determined.
[0013] A broadband oscillation risk assessment is conducted on the new energy grid-connected system based on the comparison results between the impedance external characteristic curves of the new energy power station and the AC power grid.
[0014] Preferably, the electrical unit includes a feeder, a transformer, a reactive power compensation device, and an energy storage unit. The feeder comprises multiple new energy generators and multiple AC lines, which are connected in series and parallel to form the feeder.
[0015] Preferably, the process of constructing the impedance external characteristic model of the feeder is as follows:
[0016] Based on different broadband oscillation risk assessment frequency bands, construct the voltage and current small-signal phasors at the common coupling point of a single new energy unit under three-phase symmetrical operating conditions;
[0017] Based on the voltage and current small-signal phasors, the AC side admittance matrix is obtained by performing a Laplace transform on the control process of the single new energy unit; wherein, the AC side admittance matrix of the sub-supersynchronous frequency band incorporates the phase-locked loop control coefficient matrix affected by the AC side power operation level.
[0018] The impedance characteristic model of a single new energy unit is determined based on the AC side admittance matrix.
[0019] The equivalent impedance model of the AC line between the two new energy units was obtained by using the Bergeron model to simulate the AC line.
[0020] Based on the connection relationship between the multiple new energy generating units on the feeder and the AC line, the impedance characteristic model of the single new energy generating unit and the equivalent impedance model of the AC line are connected in series and parallel to obtain the impedance external characteristic model of the feeder.
[0021] Based on the primary structure and control structure of the reactive power compensation device, an impedance external characteristic model of the reactive power compensation device is constructed using the impedance modeling method.
[0022] Based on the primary structure and control structure of the energy storage unit, an impedance external characteristic model of the energy storage unit is constructed using the impedance modeling method.
[0023] The transformer is modeled using a T-shaped or π-shaped equivalent circuit to obtain the transformer's impedance external characteristic model.
[0024] The impedance external characteristic model of the new energy power station is formed by connecting the impedance external characteristic models of the feeder, the reactive power compensation device, the energy storage unit, and the transformer in series and parallel.
[0025] Preferably, the broadband oscillation risk assessment frequency band is a mid-to-high frequency band or a sub-supersynchronous frequency band; the construction process of the impedance external characteristic model of the AC power grid is as follows:
[0026] The outgoing terminals of the AC power grid after passing through multiple stages of lines or transformers are determined by using multiple ideal voltage sources and lumped parameter impedances.
[0027] Starting from the common coupling point between the new energy power station and the AC power grid, looking towards the AC power grid to the outgoing end, the impedance external characteristic model of the AC power grid is obtained based on the series and parallel connections of the AC lines, transformers, and other primary equipment in the AC power grid.
[0028] Preferably, the broadband oscillation risk assessment frequency band is the sub-supersynchronous frequency band; the construction process of the impedance external characteristic model of the AC power grid is as follows: based on the short-circuit ratio equivalent method, it is constructed according to the equivalent short-circuit ratio of the AC power grid.
[0029] Preferably, the new energy grid-connected system corresponding to the sub-supersynchronous frequency band adopts an operating mode under different power operating levels; the new energy grid-connected system corresponding to the mid-to-high frequency band adopts an operating mode under rated operating power levels; wherein, the operating mode adopts one of the following methods, wherein the operating mode includes:
[0030] Black start, full wiring, all reactive power compensation devices are shut down, reactive power compensation devices are put into operation separately, some new energy generator sets are shut down, some new energy feeders are shut down, some AC busbars are shut down, some transformers are shut down, some reactive power compensation devices are shut down, and some energy storage is shut down.
[0031] Preferably, the step of conducting a broadband oscillation risk assessment of the renewable energy grid-connected system based on the comparison results of the impedance external characteristic curves of the renewable energy power plant and the AC power grid includes:
[0032] Based on the impedance external characteristic curve of the new energy power station and the impedance external characteristic curve of the AC power grid, the frequency range in which the impedance amplitude of the AC power grid is greater than that of the new energy power station under the same broadband oscillation risk assessment frequency band is determined.
[0033] Determine whether the phase difference between the impedance external characteristic curve of the AC power grid and the impedance external characteristic curve of the new energy power station within the frequency range is greater than a preset phase difference threshold.
[0034] If the phase difference is determined to be greater than the preset phase difference threshold, then the new energy grid-connected system is determined to have a broadband oscillation risk.
[0035] If the phase difference is determined to be no greater than the preset phase difference threshold, then it is determined that the new energy grid-connected system does not have the risk of broadband oscillation.
[0036] Secondly, this invention provides a broadband oscillation risk assessment system for new energy grid-connected systems, applied to assess the broadband oscillation risk of new energy grid-connected systems in different broadband oscillation risk assessment frequency bands, wherein the broadband oscillation risk assessment frequency bands include mid-to-high frequency bands and sub-supersynchronous frequency bands; including:
[0037] The impedance model construction module is used to establish the impedance external characteristic model of each electrical unit based on multiple electrical units in the new energy power station.
[0038] The power station model construction module is used to connect each electrical unit according to the impedance external characteristic model and wiring structure of each electrical unit of the new energy power station, and obtain the impedance external characteristic model of the new energy power station corresponding to the broadband oscillation risk assessment frequency band according to the impedance series-parallel relationship of each electrical unit.
[0039] The grid-side model construction module is used to determine the impedance external characteristic model of the AC power grid corresponding to the broadband oscillation risk assessment frequency band based on different broadband oscillation risk assessment frequency bands.
[0040] The impedance curve determination module is used to determine the impedance external characteristic curve of the new energy power station and the impedance external characteristic curve of the AC power grid based on the impedance external characteristic model of the new energy power station and the impedance external characteristic model of the AC power grid.
[0041] The risk assessment module is used to conduct a broadband oscillation risk assessment of the new energy grid-connected system based on the comparison results between the impedance external characteristic curve of the new energy power station and the impedance external characteristic curve of the AC power grid.
[0042] Thirdly, the present invention also provides an electronic device, the electronic device including a memory and a processor, the memory storing a computer program, the computer program being executed by the processor causing the processor to perform the steps of the broadband oscillation risk assessment method for new energy grid-connected systems as described in the first aspect.
[0043] Fourthly, the present invention also provides a computer-readable storage medium having a computer program stored thereon, wherein the computer program, when executed, implements the steps of the broadband oscillation risk assessment method for new energy grid-connected systems as described in the first aspect.
[0044] As can be seen from the above technical solutions, this invention constructs an impedance external characteristic model of a new energy power station and an impedance external characteristic model of an AC power grid for different broadband oscillation risk assessment frequency bands. This allows for flexible processing of different broadband oscillation risk assessment frequency bands. The impedance external characteristic curves of the new energy power station and the AC power grid are determined using the impedance external characteristic models of the new energy power station and the AC power grid. The comparison results between these two curves are used to conduct broadband oscillation risk assessment of the new energy grid-connected system. Furthermore, the impact of topology and operating conditions on broadband oscillation risk is fully considered, thus improving the accuracy and adaptability of broadband oscillation risk assessment for the new energy grid-connected system. Attached Figure Description
[0045] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0046] Figure 1 shows the application environment of a broadband oscillation risk assessment method for a new energy grid-connected system provided by an embodiment of the present invention.
[0047] Figure 2 is a flowchart of a broadband oscillation risk assessment method for a new energy grid-connected system provided by an embodiment of the present invention;
[0048] Figure 3 is a schematic diagram of a typical AC power grid structure for a new energy grid-connected system.
[0049] Figure 4 is a schematic diagram of the forward-sequence subsystem of the new energy grid connection system;
[0050] Figure 5 is a schematic diagram of the negative sequence subsystem of the new energy grid connection system;
[0051] Figure 6 is a typical wind turbine topology diagram;
[0052] Figure 7 shows a typical wind turbine control block diagram;
[0053] Figure 8 is a schematic diagram of the impedance scanning system structure;
[0054] Figure 9 is the equivalent diagram of the AC circuit;
[0055] Figure 10 shows the equivalent model of the feeder;
[0056] Figure 11 is the electrical wiring diagram of the reactive power compensation device;
[0057] Figure 12 is a control architecture diagram of the reactive power compensation device;
[0058] Figure 13 is a topology diagram of the AC power transmission and grid connection system of an offshore wind farm.
[0059] Figures 14 and 15 show the impedance modeling and verification diagrams for a single wind turbine in the medium and high frequency band.
[0060] Figures 16 and 17 show the modeling and verification diagrams of the AC submarine cable.
[0061] Figures 18 and 19 show the high-frequency impedance characteristic curves of offshore wind farms.
[0062] Figures 20 and 21 show the impedance characteristic curves after considering the impact of the booster station on the new energy power station;
[0063] Figures 22 and 23 show the impedance characteristic curves of offshore wind farms after considering the influence of long-distance AC transmission lines.
[0064] Figures 24 and 25 show the impedance characteristic curves of the reactive power compensation parallel branch in the medium and high frequency range.
[0065] Figures 26 and 27 are comparison curves of impedance characteristics between reactive power compensation parallel branches and new energy power stations.
[0066] Figures 28 and 29 show the impedance characteristic curves of new energy power stations after considering reactive power compensation parallel branches in the medium and high frequency ranges.
[0067] Figures 30 and 31 show the impedance characteristic curves of typical reactive power compensation parallel branches and new energy power station wiring methods in medium and high frequency applications.
[0068] Figures 32 and 33 are comparison charts of the theoretical values and actual frequency scan values of the impedance model of a single wind turbine in the sub-supersynchronous frequency band.
[0069] Figures 34 and 35 show the impedance characteristic curves of a single wind turbine in the sub-supersynchronous frequency band under operating condition 1.
[0070] Figures 36 and 37 show the impedance characteristic curves of a single wind turbine in the sub-supersynchronous frequency band under operating condition 2.
[0071] Figures 38 and 39 show the modeling and verification results of AC submarine cables after the equivalent of the Bergeron model;
[0072] Figures 40 and 41 show the impedance characteristic curves of the sub-supersynchronous frequency band of the offshore wind farm after considering multiple feeders.
[0073] Figures 42 and 43 show the impedance characteristic curves of the sub-supersynchronous frequency band offshore wind farm after considering the influence of the sea-level riser transformer.
[0074] Figures 44 and 45 show the impedance characteristic curves of the sub-supersynchronous frequency band offshore wind farm as seen from the onshore grid connection point of the AC submarine cable.
[0075] Figures 46 and 47 show the impedance characteristic curves of the reactive power compensation parallel branch in the sub-supersynchronous frequency band.
[0076] Figures 48 and 49 are comparison curves of the impedance characteristics of the reactive power compensation parallel branch and the new energy power station in the sub-supersynchronous frequency band.
[0077] Figures 50 and 51 show the impedance characteristic curves of new energy power stations after considering reactive power compensation parallel branches in the sub-supersynchronous frequency band.
[0078] Figures 52 and 53 are diagrams for assessing the oscillation risk of the AC grid equivalent impedance to the sub-supersynchronous frequency band of the new energy transmission system under operating condition 1.
[0079] Figures 54 and 55 are diagrams for assessing the oscillation risk of the AC grid equivalent impedance to the sub-supersynchronous frequency band of the new energy transmission system under operating condition 2.
[0080] Figure 56 is a schematic diagram of a broadband oscillation risk assessment system for a new energy grid-connected system;
[0081] Figure 57 is a schematic diagram of the structure of an electronic device. Detailed Implementation
[0082] To enable those skilled in the art to better understand the present invention, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0083] The broadband oscillation risk assessment method for new energy grid-connected systems provided in this application embodiment can be applied to the application environment shown in Figure 1. In this system, each device node communicates with server 102 via a network. A data storage system can store the data that server 102 needs to process. The data storage system can be integrated onto server 102, or it can be located in the cloud or on other network servers. Server 102 can be a standalone physical server, a server cluster or distributed system composed of multiple physical servers, or a cloud server providing cloud computing services.
[0084] This application provides a method for assessing broadband oscillation risk in a new energy grid-connected system. It is applied to assess the broadband oscillation risk of a new energy grid-connected system in different broadband oscillation risk assessment frequency bands, including the mid-high frequency band and the sub-supersynchronous frequency band.
[0085] In this application, the embodiments establish the impedance models of the new energy power station side and the AC power grid for different broadband oscillation risk assessment frequency bands of new energy grid-connected systems. The broadband oscillation risk assessment frequency bands include the mid-high frequency band (greater than 200Hz) and the sub-supersynchronous frequency band (1-200Hz).
[0086] Meanwhile, this application embodiment adaptively adjusts the impedance external characteristic model of new energy power plants and the impedance external characteristic model of AC power grid according to different broadband oscillation risk assessment frequency bands to ensure the accuracy and effectiveness of the impedance model.
[0087] As shown in Figure 2, this application provides a method for assessing the broadband oscillation risk of a new energy grid-connected system. Using server 102 in Figure 1 as an example, the method includes the following steps S1 to S5:
[0088] Step S1: Based on the multiple electrical units of the new energy power station, establish the impedance external characteristic model of each electrical unit.
[0089] In this system, the new energy grid connection system connects the new energy power plants and the AC grid at the PCC (Point of Common Coupling) as the dividing point, as shown in Figure 3. The onshore AC grid outputs its lines after passing through multiple transformer stages. Considering two transformer stages, an ideal voltage source and lumped parameter impedance can be used to characterize the end of the onshore AC grid.
[0090] The electrical unit includes feeders, transformers, reactive power compensation devices, and energy storage units. The feeders consist of multiple new energy generating units and multiple AC lines, which are connected in series and parallel to form the feeders.
[0091] Step S2: Based on the impedance external characteristic model and wiring structure of each electrical unit of the new energy power station, connect each electrical unit, and obtain the impedance external characteristic model of the new energy power station corresponding to the broadband oscillation risk assessment frequency band according to the series and parallel impedance relationship of each electrical unit.
[0092] The impedance external characteristic model of a new energy power station is determined by the impedance external characteristic models of multiple electrical units, as well as their wiring structures and impedance series-parallel relationships. These electrical units in a new energy power station include feeders, transformers, reactive power compensation devices, and energy storage units.
[0093] The impedance external characteristic models of each electrical unit are connected according to the wiring structure of each electrical unit in the new energy power station, and the impedance external characteristic model of the new energy power station is obtained according to the series and parallel impedance relationship of each electrical unit.
[0094] Step S3: Determine the impedance external characteristic model of the AC power grid corresponding to the different broadband oscillation risk assessment frequency bands.
[0095] For mid-to-high frequency bands, an impedance model of the AC power grid is established based on the series and parallel connections of AC lines, transformers, and other primary equipment. Modeling the AC power grid for new energy grid-connected systems requires considering outgoing lines with two or more transformer stages. The portion after two transformer stages can be characterized using ideal voltage sources and lumped parameter impedances at the end of the AC power grid. Different operating conditions, such as full AC grid connection, single equipment disconnection, and single line disconnection, are considered to obtain AC power grid impedance models under different operating conditions. The equivalent impedance of the AC power grid changes according to the outgoing line operating conditions. The impact of changes in the AC power grid topology and operating conditions on the impedance external characteristic model can also be considered. For example, when a ring network structure exists in the AC power grid, equivalent modeling of these structures is required to obtain a more accurate impedance external characteristic model. It should be noted that the impedance models of AC lines, transformers, and other primary equipment in the AC power grid can be referenced from the impedance modeling of corresponding equipment in new energy power plants.
[0096] In some embodiments, the equivalent impedance of the AC power grid can be considered for the sub-supersynchronous frequency band using the short-circuit ratio equivalent method. That is, the impedance external characteristic model of the AC power grid is based on the short-circuit ratio equivalent method and is constructed according to the equivalent short-circuit ratio of the AC power grid.
[0097] For example, assuming the equivalent short-circuit ratio (SCR) of the AC power grid under a certain outgoing line operating condition is known (if the AC power grid has multiple feed-in renewable energy stations, the SCR should be the equivalent short-circuit ratio of the multiple feed-in renewable energy stations), the equivalent impedance model of the AC side is as follows:
[0098] In the formula, U base P base Let f be the rated voltage and rated power of the AC power grid, respectively, and ω = 2πf. By taking different frequencies f, the equivalent impedance of the AC power grid under the subsynchronous frequency band can be obtained.
[0099] Step S4: Based on the impedance external characteristic model of the new energy power station and the impedance external characteristic model of the AC power grid, determine the impedance external characteristic curve of the new energy power station and the impedance external characteristic curve of the AC power grid.
[0100] Specifically, based on the impedance external characteristic model of the new energy power plant, the amplitude and phase are obtained, and the impedance external characteristic curve of the new energy power plant can be plotted. Similarly, based on the impedance external characteristic model of the AC power grid, a Fast Fourier Transform is performed to obtain the amplitude and phase, and the impedance external characteristic curve of the AC power grid can be plotted.
[0101] Step S5: Based on the comparison results of the impedance external characteristic curves of the new energy power station and the AC power grid, conduct a broadband oscillation risk assessment of the new energy grid-connected system.
[0102] It should be noted that this invention constructs an impedance external characteristic model for new energy power plants and an impedance external characteristic model for AC power grids in different broadband oscillation risk assessment frequency bands. This allows for flexible processing of different broadband oscillation risk assessment frequency bands. The impedance external characteristic curves of the new energy power plants and the AC power grid are determined using these two models. The comparison between these two curves is then used to conduct broadband oscillation risk assessment of the new energy grid-connected system. Furthermore, the impact of topology and operating conditions on broadband oscillation risk is fully considered, thus improving the accuracy and adaptability of broadband oscillation risk assessment for new energy grid-connected systems.
[0103] In some embodiments, a broadband oscillation risk assessment of the renewable energy grid-connected system is performed based on a comparison of the impedance external characteristic curves of the renewable energy power plant and the AC power grid, including:
[0104] Step S501: Based on the impedance external characteristic curves of the new energy power station and the AC power grid, determine the frequency range in which the impedance amplitude of the AC power grid is greater than that of the new energy power station under the same broadband oscillation risk assessment frequency band.
[0105] Specifically, in the mid-to-high frequency band, the phase difference between the impedance amplitude of the AC power grid (above 200Hz) and that of the impedance amplitude of the new energy power station is determined. In the sub-supersynchronous frequency band, the phase difference between the impedance amplitude of the AC power grid (1-200Hz) and that of the impedance amplitude of the new energy power station is determined.
[0106] Step S502: Determine whether the phase difference between the impedance external characteristic curve of the AC power grid and the impedance external characteristic curve of the new energy power station within the frequency range is greater than the preset phase difference threshold.
[0107] Step S503: If the phase difference is determined to be greater than the preset phase difference threshold, then it is determined that the new energy grid-connected system has a risk of broadband oscillation.
[0108] Step S504: If the phase difference is determined to be no greater than the preset phase difference threshold, then it is determined that there is no risk of broadband oscillation in the new energy grid-connected system.
[0109] Among them, as shown in Figures 4 and 5, the new energy grid-connected system has a positive sequence subsystem and a negative sequence subsystem, where Z Rp I Rp Z represents the positive sequence impedance and equivalent current source of the new energy source, respectively; Mp V Mp These represent the positive sequence impedance and equivalent voltage source of the flexible DC converter station, respectively; V outp I outp These represent the AC bus voltage and current of the new energy power station, respectively. Rn I Rn Z represents the negative sequence impedance and equivalent current source of the new energy source, respectively; Rn I Rn Z represents the negative sequence impedance and equivalent current source of the new energy source, respectively; Mn V Mn V represents the negative sequence impedance and equivalent voltage source of the AC power grid, respectively; outn I outn These represent the AC bus voltage and current at the grid connection point of the new energy power station, respectively.
[0110] Taking the positive sequence subsystem as an example, according to Figure 4, the voltage V of the AC bus of the new energy power station in the positive sequence subsystem can be solved. outp Current I outpThey are respectively:
[0111] Assuming that both the renewable energy power plant and the AC power grid are in a stable state when operating independently, then I Rp V Mp Both are stable. Therefore, when the new energy power station is interconnected with the AC power grid, the stability of the positive sequence subsystem depends on the term 1 / (1+Z) in equations (2) and (3). Mp (s) / Z Rp Is (s) stable?
[0112] The system does not satisfy the stability criterion and oscillates if and only if the following two conditions are met: ① There exists Z Mp (s) Impedance magnitude is greater than Z Rp (s) Frequency range of impedance amplitude; ② In Z Mp (s) Impedance magnitude is greater than Z Rp (s) Within the frequency range of impedance amplitude, Z Mp (s) and Z Rp (s) The phase-frequency response curves differ by more than 180°.
[0113] In some embodiments, the process of constructing the impedance external characteristic model of a new energy power station is as follows:
[0114] Step S201: Construct the voltage and current small-signal phasors at the common coupling point of a single new energy unit under three-phase symmetrical operating conditions based on different broadband oscillation risk assessment frequency bands;
[0115] Step S202: Based on the small-signal phasors of voltage and current, the AC side admittance matrix is obtained by performing a Laplace transform on the control process of a single new energy unit; wherein, the AC side admittance matrix of the sub-supersynchronous frequency band introduces the phase-locked loop control link coefficient matrix affected by the AC side power operation level.
[0116] Taking a wind turbine as an example, in the phase-locked loop (PLL) control of a single new energy unit, the input of the coefficient matrix of the voltage variables in the PLL control loop is the AC side voltage. The output phase θ is greatly affected by the AC side power operation level. The PLL control frequency band is located in the sub-supersynchronous band. The influence of PLL control in the mid-to-high frequency band decays rapidly. Therefore, the impedance characteristic curve of the wind turbine in the mid-to-high frequency band can ignore the influence of the system power operation level caused by the PLL on the impedance characteristics. However, due to the PLL control, the sub-supersynchronous impedance characteristic of the wind turbine is affected by the system power level. When conducting the sub-supersynchronous band oscillation risk assessment, it is necessary to consider the influence of the power level on the sub-supersynchronous impedance characteristics of a single wind turbine (examples of wind turbines with different power levels are shown in Table 1).
[0117] Table 1 Examples of operating conditions for wind turbines at different power levels (Applicable operating conditions of the invention include, but are not limited to, those in this table).
[0118] A typical wind turbine topology and control block diagram are shown in Figures 6 and 7. Due to the frequency coupling effect caused by the asymmetric control of the DC bus dynamic characteristics and the converter's dq axis, each signal quantity in the system needs to be described using two-dimensional phasors. By linearizing at the steady-state point, small-signal phasors for each dynamic quantity can be constructed; these phasors consist of Fourier coefficients of the dynamic quantity at different frequencies.
[0119] In Figure 6, Z t For commutation transformer leakage reactance, Y c For AC side filter bank admittance, Z f For the passive branch impedance on the AC side, Z G The AC impedance of a single wind turbine as seen from the high-voltage side, Z g I represents the AC impedance of a single wind turbine as seen from the low-pressure side. source It serves as a controlled current source for components such as the converter station on the simulator side.
[0120] In Figure 7, P in Injecting active power to the DC side, u dc C dc These represent the DC-side voltage and the DC-side equivalent capacitance, respectively. mabc L represents the three-phase voltage (a, b, c) at the fan outlet. f For filter inductance, u gabc i gabc q g These represent the voltage, current, and reactive power at the common coupling point, respectively, R. f C f These are the filter resistor and filter capacitor, respectively, L t1 For commutation leakage inductance, k t1 The transformer ratio is θ. PLL is a phase-locked loop. PLL The phase angle is the output phase angle of the phase-locked loop, abc / dq represents the Park transformation process, and H... f For the filtering stage, i gdq u gdq These are the dq-axis current and voltage after Park transformation, respectively, each containing the dq-axis current i. gd i gq and dq axis voltage u gd u gq U dc ref Q ref These are the DC voltage reference value and the reactive power reference value at the AC side common coupling point, respectively. V G Q G I K dThese are the voltage outer loop, reactive power outer loop, current inner loop PI control stage and decoupling stage, and dq / abc is the Park inverse transform stage. D The system's equivalent control link delay is represented by PWM, which is a modulation process that generates a three-phase modulated wave m. abc .
[0121] The voltage and current small-signal phasors constructed at the wind turbine port are as follows. Since this is for a three-phase symmetrical operating condition, the voltage and current phasors at the common coupling point of any one phase are denoted as follows.
[0122] In the formula, The voltages at frequencies p and p-2 are respectively. The currents are at frequencies p and p-2, respectively.
[0123] The AC side admittance matrix of a single wind turbine can be written as follows:
[0124] In the formula, Y 11 Y 22 All are wind turbine self-admittance, Y 12 Y 21 All are wind turbine coupling admittance, Y G (s) represents the wind turbine admittance matrix.
[0125] The impedance matrix of the wind turbine can be defined according to Z=Y. -1 The impedance matrix can be obtained. An equivalent system model is established using the state-space averaging method. By performing Laplace transform and linearization on the voltage and current small-signal phasors, the AC-side admittance matrix, and the control process, the AC-side admittance matrix, considering the AC-side passive branch, AC-side filter, and transformer, can be obtained from the perspective of the fan at the point of common coupling (PCC). Its specific form is as follows:
[0126] In the formula, Z G (s) is the AC side admittance matrix, s is the Laplace operator, H D (s) is the system control link delay matrix, Z f (s), Z t (s), Y c (s) are 2×2 matrices related to the AC passive branch, converter transformer leakage inductance, and AC measurement filter, respectively. I,i G(s) and GV,i(s) are coefficient matrices related to the DC voltage outer loop voltage and current variables, respectively. Q,v (s) is the correlation coefficient matrix of the reactive power outer loop voltage variable, G Q,i (s), G PLL,v(s) is the coefficient matrix of the voltage variables in the phase-locked loop control loop, G I,v (s), G V,v (s) are coefficient matrices related to the DC voltage inner loop voltage and current variables, respectively, E is a 2×2 identity matrix, and G is a coefficient matrix. Q,i (s) is the correlation coefficient matrix of the reactive outer loop current variable.
[0127] Among them, for the mid-to-high frequency band G PLL,v (s) can be ignored, i.e., G PLL,v (s) is zero, and the AC side admittance matrix can be further simplified. For G in the sub-supersynchronous band PLL,v (s) Since the input is AC side voltage, its output reference phase θ is greatly affected by the AC side power operating level, therefore it is necessary to adjust G... PLL,v (s) is retained.
[0128] Step S203: Determine the impedance characteristic model of a single new energy unit based on the AC side admittance matrix;
[0129] In this invention, the AC side admittance matrix of the common coupling point is used as the impedance characteristic model of a single wind turbine. In some embodiments, verification is required to support the risk assessment of wide-band AC transmission oscillations in new energy power plants. Considering that this invention focuses on the external impedance characteristics of the model, this invention adopts an impedance scanning-based modeling verification method to verify the correctness of the single wind turbine impedance characteristic model, as shown in the impedance scanning system structure in Figure 8, where the device to be scanned is a single wind turbine.
[0130] Specifically, the process of verifying the correctness of the impedance characteristic model of a single wind turbine using the impedance sweep modeling verification method includes:
[0131] 1) Apply disturbance voltages at multiple measurement frequency points to the AC side of a single wind turbine under steady-state operation, and obtain grid connection point voltage and current data of the AC side of the single wind turbine.
[0132] In this process, while the device under test is operating stably, small disturbance voltages (or small disturbance currents) of different measurement frequencies are applied to the AC side, and impedance scanning modules are used on the AC side to acquire grid connection point voltage and current data.
[0133] 2) Perform Fast Fourier Transform on the voltage and current data at the grid connection point to obtain voltage FFT complex variables and current FFT complex variables at multiple measurement frequency points;
[0134] 3) Determine the complex value of impedance based on the complex variables of voltage FFT and current FFT at multiple different measurement frequency points;
[0135] 4) Determine the impedance external characteristic curve of a single fan based on the amplitude and phase of the complex impedance value;
[0136] 5) Compare the similarity between the impedance external characteristic curve and the impedance external characteristic curve determined by the single wind turbine impedance characteristic model;
[0137] 6) Verify the correctness of the impedance characteristic model of a single wind turbine based on the similarity comparison results;
[0138] 7) If the impedance characteristic model of a single wind turbine is found to be incorrect, update the parameters of the single wind turbine impedance characteristic model until the single wind turbine impedance characteristic model is found to be correct.
[0139] When updating the parameters of the impedance characteristic model of a single wind turbine, it is possible to consider updating parameters such as voltage and current small-signal phasors, and then re-derive the impedance characteristic model of the single wind turbine.
[0140] Step S204: Use the Begeron model to perform an equivalent simulation of the AC line between the two new energy units to obtain the equivalent impedance model of the AC line.
[0141] The equivalent diagram of the AC line is shown in Figure 9. The equivalent impedance and equivalent admittance expressions of the Bergeron model are as follows:
[0142] In the formula, γ is the propagation constant of the line. Z C It is wave impedance. Z line For the equivalent impedance of the Bergeron model, Y line Let the equivalent admittance of the Bergeron model be l0, and the equivalent AC cable length be l0, and the impedance and admittance per unit length be z0 and y0, respectively.
[0143] Step S205: Based on the connection relationship between multiple new energy generating units and AC lines on the feeder, the impedance characteristic model of a single new energy generating unit and the equivalent impedance model of the AC line are connected in series and parallel to obtain the external impedance characteristic model of the feeder.
[0144] One of the feeders in a wind farm consists of multiple wind turbines and multiple AC lines connected in series and parallel. The impedance model of a single feeder in a new energy power station is obtained by using the series and parallel relationship of the equivalent impedance models of the wind turbines and the collecting lines.
[0145] Specifically, starting from the first wind turbine, the turbine admittance is connected in parallel with the equivalent admittance of the Begeron model, then in series with the equivalent impedance of the Begeron model, and then in parallel with the equivalent admittance of the Begeron model to obtain the equivalent impedance looking from the next wind turbine towards the first turbine. Based on the feeder topology, i.e., the Begeron model parameters, series and parallel connections are made to obtain the equivalent model of the entire feeder, as shown in Figure 10 (the process of this invention applies to single feeder topologies, including but not limited to Figure 10). Assume the impedance of a single wind turbine is Z. Gij Admittance is Y Gij (Each wind turbine can have different power operating levels, control parameters, and control structures), and the equivalent impedance of the AC submarine cable between wind turbines using the Bergeron model is Z. aij The equivalent admittance is Y aij .
[0146] Based on Figure 9, the impedance characteristic model of a single feeder can be obtained, denoted as:
[0147] Let the impedance at the end of a single feeder be Z. Fi Then Z Fi =1 / Y Eij This refers to the impedance of a single feeder line. Assume the impedance and admittance of a single wind turbine are Z... Gij Y Gij The equivalent impedance and admittance of the j-th segment of the feeder line in the Begeron model are Z. aij Y bij The equivalent impedance and admittance viewed from the outlet of a certain wind turbine towards the head end are Z. pij Y pij The equivalent impedance and admittance viewed from the beginning of the Bergeron line are Z. cij Y cij The equivalent impedance and admittance viewed from the end of the Bergeron line towards the beginning of the line are Z. hij Y hij Based on Figure 10, by modeling the impedance characteristics of a single wind turbine and the Bergeron model, and considering the topology of a single feeder, the impedance characteristic curve Z of a single feeder can be established through the series and parallel impedance relationships. Fi Impedance scanning can be used to verify the impedance characteristic curve of a single feeder. Since wind farm feeders vary in turbine type, control parameters, and feeder topology, the modeling and verification results of AC submarine cables using the Bergeron model are presented here.
[0148] Step S206: Based on the primary structure and control structure of the reactive power compensation device, construct the impedance external characteristic model of the reactive power compensation device using the impedance modeling method;
[0149] By performing a Laplace transform on the control process of the reactive power compensation device, the impedance external characteristic model of the reactive power compensation device is obtained.
[0150] In order to establish the branch impedance model of the parallel reactive power compensation device, the electrical wiring diagram and control architecture of the reactive power compensation device are shown in Figures 11 and 12.
[0151] In Figure 11, the 35KV high-voltage busbar is connected to the 35KV user switch cabinet. The 35KV user switch cabinet is equipped with a circuit breaker QF1, which is connected to the outdoor section. The outdoor section includes a switch K1, a circuit breaker QF2, and an inductor L. The outdoor section is also connected to the SVG power cabinet.
[0152] In Figure 12, U A i A The values represent the AC phase A voltage and current, and the PLL is a phase-locked loop. θ a The phase angle is the output phase angle of the phase-locked loop, Delay is the delay, and 3s / 2r is the Park transformation process. The three-phase voltage and current on the AC side are transformed by Park to generate the dq-axis voltage and current u. d u q i d i q U dca_ref U dcam The reference DC-side voltage value and the actual DC-side voltage value are respectively added or subtracted, and then the d-axis current reference value i is generated through a PI control circuit. dref ; I in the outer loop of AC voltage s For alternating current, passing through the slope coefficient k slope The ramp voltage U is then generated. slope , and the AC voltage reference value U ref and the actual value of AC voltage U rms After addition and subtraction operations, the q-axis current reference value i is generated by the PI control circuit. qref1 The reactive power reference value Q in the outer loop of reactive power. ref The actual reactive power value Q is added or subtracted, and then passed through a PI control loop to obtain the q-axis current reference value i. qref2 K d For decoupling, u dref u qref These are the dq-axis voltage reference values, and 2r / 3s represents the inverse Park transformation process, generating the AC voltage reference value u. aref u bref u cref .
[0153] Under typical control, the SVG adopts phase-separated control in the dq axis coordinate system. First, virtual dq axis components are constructed. Using the harmonic linearization method, the frequency domain expression of the modulation wave is obtained from the SVG control system. Further considering the effects of control link delay and discrete control, combined with the primary loop structure of the SVG, the SVG converter impedance and system impedance are obtained as shown in Equation (9).
[0154] In the formula, L is the AC side impedance of the SVG, and G i For the transfer function of the current inner loop controller, K d G is the decoupling coefficient for the dq axis. d To control the link delay transfer function, G o For the zero-order hold transfer function, G sv Let R be the transfer function of the voltage feedforward low-pass filter. ed Let T be the equivalent resistance of the SVG, and T be the power frequency period. The impedance characteristic curve of the SVG is affected by the power operating conditions. Considering the influence of different power operating conditions, different impedance characteristic curves of the SVG are obtained.
[0155] Step S207: Based on the primary structure and control structure of the energy storage unit, construct the impedance external characteristic model of the energy storage unit using the impedance modeling method;
[0156] Step S208: Use a T-shaped equivalent circuit or a π-shaped equivalent circuit to perform equivalent modeling of the transformer to obtain the impedance external characteristic model of the transformer;
[0157] Among them, the transformers in the new energy power station include new energy unit transformers and main step-up transformers of the power station. Taking the double-winding transformer as an example, a T-type equivalent circuit or a π-type equivalent circuit can be selected.
[0158] Step S209: The impedance external characteristic model of the new energy power station is formed by connecting the impedance external characteristic models of the feeder, the reactive power compensation device, the energy storage unit, and the transformer through series and parallel connections.
[0159] Based on the determined primary structure, control structure and parameters of the energy storage unit, an accurate model for obtaining the external characteristic curve of the impedance of a single energy storage unit is established using the impedance modeling method, and verified using the electromagnetic transient simulation frequency scanning method.
[0160] In some embodiments, the broadband oscillation risk assessment frequency band is the mid-to-high frequency band or the sub-supersynchronous frequency band; the process of constructing the impedance external characteristic model of the AC power grid is as follows:
[0161] Step S301: Determine the outgoing terminals of the AC power grid after passing through multiple stages of lines or transformers by using multiple ideal voltage sources and lumped parameter impedances;
[0162] The outgoing terminals of the AC power grid after passing through multiple lines or transformers are determined by using multiple ideal voltage sources and lumped parameter impedances. Specifically, the power grid structure, transformer ratio, line impedance, and other parameters can be determined based on the electrical wiring diagram of the AC power grid. Then, based on these parameters, multiple ideal voltage sources and lumped parameter impedances are used to equivalently represent the AC power grid, thereby determining the outgoing terminals of the AC power grid after passing through multiple lines or transformers.
[0163] Step S302: Starting from the common coupling point between the new energy power station and the AC power grid, looking towards the AC power grid to the end of the outgoing line, based on the series and parallel connections of the AC lines, transformers and other primary equipment in the AC power grid, obtain the impedance external characteristic model of the AC power grid.
[0164] In some embodiments, the broadband oscillation risk assessment frequency band is the sub-supersynchronous frequency band; the process of constructing the impedance external characteristic model of the AC power grid is as follows: based on the short-circuit ratio equivalent method, it is constructed according to the equivalent short-circuit ratio of the AC power grid.
[0165] The system is constructed based on the equivalent short-circuit ratio of the AC power grid. Specifically, the AC power grid is regarded as an ideal voltage source connected in series with an equivalent impedance. This equivalent impedance is the impedance external characteristic of the AC power grid. The equivalent short-circuit ratio is defined as the ratio of the system short-circuit capacity to the rated capacity of the new energy power station.
[0166] In some embodiments, the new energy grid-connected system corresponding to the sub-supersynchronous frequency band adopts the operation mode under different power operation levels; the new energy grid-connected system corresponding to the mid-to-high frequency band adopts the operation mode under the rated operating power level; wherein, the operation mode adopts one of the following methods, wherein the operation mode includes: black start, full connection, all reactive power compensation devices are turned off, reactive power compensation devices are turned on separately, some new energy generator sets are turned off, some new energy feeders are turned off, some AC buses are turned off, some transformers are turned off, some reactive power compensation devices are turned off, and some energy storage is turned off.
[0167] Specifically, because the impedance model of power electronic components in the sub-supersynchronous frequency band is affected by the power operating level, the impact on sub-supersynchronous frequency band oscillations can be observed by simulating the state of the renewable energy grid-connected system under different power operating levels. This approach can take into account the dynamic characteristics of the system under different load conditions, thus more accurately assessing the oscillation risk. For example, when the system is at a low power operating level, certain specific operating conditions may trigger sub-supersynchronous oscillations; while when the system is at a high power operating level, power fluctuations and distribution issues may increase the oscillation risk. Specific power operating levels include: maximum capacitive reactive power output at 100% active power, maximum inductive reactive power output at 100% active power, zero reactive power output at 100% active power, maximum capacitive reactive power output at 10% active power, maximum inductive reactive power output at 10% active power, and zero reactive power output at 10% active power, etc.
[0168] The grid-connected new energy systems operating at mid-to-high frequency bands adopt the operation mode at rated power level. The impedance model of the grid-connected new energy systems operating at mid-to-high frequency bands is not affected by the power operation level. Therefore, under the rated power operation mode, it can ensure accurate assessment of oscillation risk under various operating conditions.
[0169] Black start is a special operating mode for restoring power after a complete system power outage. In renewable energy grid-connected systems, black start typically means gradually restoring power to the entire system by starting specific renewable energy generator sets or energy storage devices without any external power support. Considering black start when assessing broadband oscillation risks helps analyze the system's stability and oscillation characteristics under extreme conditions. This aids in developing more effective emergency measures and oscillation control strategies.
[0170] Fully connected operation mode refers to the operation of a new energy grid-connected system where all lines and equipment are connected. In this mode, the system structure and parameters are relatively fixed, facilitating accurate oscillation risk assessment. By simulating system operation under fully connected conditions, the impact of each line and device on oscillations can be evaluated, thereby identifying critical nodes and weak points.
[0171] Operating modes, such as all reactive power compensation devices being disabled and only one reactive power compensation device being activated, are used to analyze the impact of reactive power compensation devices and reactive power on system oscillations. Reactive power compensation devices and reactive power have a significant impact on system stability and oscillation characteristics. By adjusting the operating status of the reactive power compensation devices, the oscillation of the system under different reactive power levels can be observed, providing a basis for formulating reactive power control strategies.
[0172] Operating modes such as partial shutdown of renewable energy generator units and partial shutdown of renewable energy feeders are used to analyze the contribution of each component in the renewable energy grid-connected system to the overall oscillation characteristics. By simulating different shutdown scenarios, the impact of each component on system oscillation can be assessed, thereby identifying areas and equipment requiring focused attention.
[0173] Operating modes such as partial AC bus shutdown, partial transformer shutdown, partial reactive power compensation device shutdown, and partial energy storage shutdown are used to analyze the oscillation characteristics of the system under different structural conditions. By simulating these shutdown scenarios, the impact of system structural changes on oscillations can be observed, providing guidance for optimizing system structure and improving stability.
[0174] In this application embodiment, the risk of broadband oscillation exists in the new energy grid-connected system.
[0175] Different suppression measures for new energy grid-connected systems corresponding to different broadband oscillation risk assessment frequency bands are proposed until the broadband oscillation risk disappears.
[0176] Specifically, the measures to mitigate the risk of broadband oscillations in the mid-to-high frequency range are as follows:
[0177] If there is a risk of medium-to-high frequency oscillation in the renewable energy grid-connected system, measures will be taken to change the impedance of the renewable energy power station or the AC grid impedance. Measures to change the impedance of the renewable energy power station include changing the control structure or parameters of the renewable energy power generation unit, changing the control structure or parameters of the SVG, changing the primary circuit of the renewable energy power station, installing passive equipment, and installing active equipment. Measures to change the impedance of the AC grid include restricting specific AC grid operation modes, installing passive equipment, and installing active equipment.
[0178] The measures to mitigate the risk of broadband oscillations in the sub-supersynchronous frequency band are as follows:
[0179] Measures shall be taken to change the impedance of new energy power plants or the impedance of the AC power grid. Measures to change the impedance of new energy power plants include: changing the control structure or parameters of new energy power generation units, changing the control structure or parameters of SVG, changing the primary circuit of new energy power plants, installing passive equipment, installing active equipment, and limiting the operating power level of new energy units or energy storage units or SVG. Measures to change the impedance of the AC power grid include restricting specific AC power grid operation modes.
[0180] The following is a calculation example of the broadband oscillation risk assessment method for new energy grid-connected systems proposed in this invention.
[0181] In this example, the AC grid-connected power transmission structure of an offshore wind farm is taken as an example. The topology of the AC grid-connected power transmission system of an offshore wind farm is shown in Figure 13. Among them, multiple wind turbine units P 11 ~P 1nEach wind turbine is equipped with a wind turbine, a converter, and a step-up transformer. The converter converts the alternating current generated by the wind turbine into a form of electrical energy suitable for subsequent transmission. The electrical energy is then collected into a collector line via connecting cables. The resistance of different branches in the collector line is l... 11 ~l 1n These collection lines gather the electricity from the dispersed wind turbines and send it to the offshore substation. The substation's step-up transformers boost the voltage, and the high-voltage electricity is then transmitted to land via submarine cables, ensuring stable power delivery. From there, it is transmitted to the onshore control center via submarine cables. Upon arrival on land, the electricity first enters the converter station. The converter station contains converter transformers (C and P) to transform the electricity to meet the requirements for grid connection. Simultaneously, the system is equipped with SVG (Static Var Generator) for reactive power compensation, improving the power factor, stabilizing voltage, and ensuring power quality. After processing at the converter station, the electricity passes through a high-voltage reactor, which limits short-circuit current and reduces operational overvoltages. Finally, the electrical energy reaches the point of common coupling (PCC), where the electrical energy generated by offshore wind power is connected to the grid's equivalent voltage source and then connected to the onshore power grid through the grid's equivalent impedance, thereby enabling the transmission of offshore wind power to the user end.
[0182] It should be noted that this application applies to AC grid-connected transmission systems for new energy sources such as offshore wind power and photovoltaics, and is not limited to the topology shown in Figure 13.
[0183] The following experiment was conducted in the risk assessment of mid-to-high frequency oscillations:
[0184] 1) Establish and verify the impedance characteristic model of a single wind turbine: As shown in Figures 14 and 15, the theoretical value of the single wind turbine impedance model established in this application matches the actual value of the scan well, and can be used for risk assessment of medium and high frequency oscillations.
[0185] 2) Establishing and Verifying a Single Feeder Impedance Model: Due to the different types of wind turbines and control parameters, as well as the varying feeder topologies, the modeling and verification results of the AC submarine cable using the Bergeron model are presented here, as shown in Figures 16 and 17. After verification of the single wind turbine and AC submarine cable impedance models, the impedance characteristic curve model of a single feeder can be obtained through the series and parallel relationships of the single feeder topology.
[0186] 3) Impedance characteristic modeling of offshore wind farm: The high-frequency impedance characteristic curves of the offshore wind farm after multiple feeders are shown in Figures 18 and 19, where Degree represents the phase.
[0187] 4) Considering the impact of the substation on the impedance of the new energy power plant, the impedance characteristics of the offshore wind farm are calculated from the high-voltage side of the offshore substation, as shown in Figures 20 and 21. The offshore substation mainly affects the high-frequency impedance of the wind farm. Due to the inductive effect of the transformer in the high-frequency band, the wind farm mainly exhibits inductive characteristics in the high-frequency band.
[0188] 5) Considering the impact of long-distance AC transmission lines on the impedance of new energy power plants, the impedance characteristics of offshore wind farms are calculated from the perspective of the onshore grid connection point of the AC submarine cable, as shown in Figures 22 and 23. It can be seen that due to the influence of the AC submarine cable, the impedance of the wind farm exhibits positive damping over a large range in the mid-to-high frequency band, but the impedance phase angle is around ±90°, indicating relatively weak system damping.
[0189] 6) Considering the impact of parallel branches such as SVG on the impedance of new energy power plants, the impedance characteristic curves of the reactive power compensation parallel branches under a specific operating condition are shown in Figures 24 and 25. Taking a specific operating condition as an example, the impedance characteristics of the offshore wind farm seen from the grid connection point on the parallel branches and the AC submarine cable are compared in Figures 26 and 27.
[0190] In the mid-to-high frequency band, the impedance amplitude of the reactive power compensation parallel branch is much larger than that of the new energy power station. Therefore, the reactive power compensation parallel branch has little impact on the impedance of the wind farm. The impedance characteristics of the new energy power station after considering the reactive power compensation parallel branch are shown in Figures 28 to 29.
[0191] 7) Considering the input of the reactive power compensation parallel branch and the wiring method of the new energy power station, the impedance characteristic curves of the new energy power station side under the typical input of the reactive power compensation parallel branch and the wiring method of the new energy power station are shown in Figures 30 and 31 (taking a certain working condition as an example).
[0192] 8) Risk assessment of oscillation in medium- and high-frequency renewable energy grid-connected transmission systems. As shown in Figures 30 and 31, offshore wind farms exhibit medium- and high-frequency negative damping under operating conditions, with the negative damping frequency band mainly distributed in the range of 1500–4200 Hz. Typically, short-circuit faults in the AC grid causing line disconnection (such as N-1, N-2, N-3, etc.) will cause the AC grid impedance phase angle to approach +90° or -90° over a wider range, thus increasing the risk of medium- and high-frequency resonance in the system. However, if it can be ensured that there is no medium- and high-frequency negative damping in the offshore wind farm, regardless of the type of fault in the AC grid causing changes in the AC grid impedance, medium- and high-frequency resonance will not be actively triggered.
[0193] The following experiment was conducted in the risk assessment of subsynchronous frequency band oscillations:
[0194] 1) Taking the rated power as an example, the modeling verification was carried out. The theoretical value of the impedance model of a single wind turbine in the sub-supersynchronous frequency band and the actual frequency scan value are compared with those in Figures 32 and 33. The theoretical value and the actual frequency scan value are in good agreement. The established model can be used to assess the oscillation risk in the sub-supersynchronous frequency band.
[0195] Figures 34, 35, 36, and 37 show the sub-supersynchronous frequency bands of a single wind turbine under different power levels (taking two power levels as examples). It can be seen that the power level has a significant impact on the sub-supersynchronous frequency band impedance of power electronic devices.
[0196] 2) Due to the different types of wind turbines and control parameters, as well as the varying feeder topologies, the modeling and verification results of the AC submarine cable using the Bergeron model are presented here, as shown in Figures 38 and 39. After verification of the impedance model of a single wind turbine and AC submarine cable, the impedance characteristic curve model of a single feeder can be obtained through the series and parallel relationships of the single feeder topology.
[0197] 3) Impedance characteristic modeling of offshore wind farms. The impedance characteristic curves of the sub-supersynchronous frequency band of offshore wind farms after multiple feeders are considered are shown in Figures 40-41.
[0198] 4) Considering the impact of the booster station on the impedance of the new energy power station, the impedance characteristics of the offshore wind farm are calculated from the high-voltage side of the offshore booster station, as shown in Figures 42-43.
[0199] 5) Considering the impact of long-distance AC transmission lines on the impedance of new energy power plants, the impedance characteristics of offshore wind farms are calculated from the perspective of the onshore grid connection point of the AC submarine cable, as shown in Figures 44-45.
[0200] 6) Considering the impact of parallel branches such as SVG on the impedance of new energy power plants, the impedance characteristic curves of reactive power compensation parallel branches at a certain power level are shown in Figures 46-47. Taking a specific operating condition as an example, the impedance characteristics of the offshore wind farm seen from the grid connection point on the parallel branch and the AC submarine cable are compared in Figures 48-49.
[0201] In the sub-supersynchronous frequency band, the impedance amplitude of the reactive power compensation parallel branch is similar to that of the new energy power station. Therefore, the reactive power compensation parallel branch has a significant impact on the impedance of the wind farm. The impedance characteristics of the new energy power station after considering the reactive power compensation parallel branch are shown in Figures 50-51.
[0202] 7) AC power grid modeling and oscillation risk assessment of the new energy grid-connected transmission system in the sub-supersynchronous frequency band: The equivalent impedance of the AC power grid is established by using SCR, the operating power level of the wind turbine is limited, and the equivalent impedance of the AC power grid under two operating conditions is selected to conduct an oscillation risk assessment of the new energy grid-connected transmission system in the sub-supersynchronous frequency band. The impedance analysis method is used for analysis, as shown in Figures 52, 53, 54, and 55.
[0203] Within a frequency range where the impedance amplitude of the AC power grid is greater than that of the offshore wind farm, the impedance phase angle difference is less than 180°, indicating that the risk of subsynchronous oscillation in the system is low.
[0204] Based on the same inventive concept, this application also provides a new energy grid-connected system broadband oscillation risk assessment system for implementing the above-mentioned new energy grid-connected system broadband oscillation risk assessment method.
[0205] The solution provided by this system is similar to the solution described in the above method. Therefore, the specific limitations of one or more embodiments of the broadband oscillation risk assessment system for new energy grid-connected systems provided below can be found in the limitations of the broadband oscillation risk assessment method for new energy grid-connected systems described above, and will not be repeated here.
[0206] As shown in Figure 56, this embodiment of the invention provides a broadband oscillation risk assessment system for new energy grid-connected systems, including:
[0207] Impedance model construction module 100 is used to establish the impedance external characteristic model of each electrical unit based on multiple electrical units of the new energy power station.
[0208] The power station model construction module 200 is used to connect each electrical unit according to the impedance external characteristic model and wiring structure of each electrical unit of the new energy power station, and obtain the impedance external characteristic model of the new energy power station corresponding to the broadband oscillation risk assessment frequency band according to the impedance series and parallel relationship of each electrical unit.
[0209] The grid-side model construction module 300 is used to determine the impedance external characteristic model of the AC power grid corresponding to different broadband oscillation risk assessment frequency bands.
[0210] Impedance curve determination module 400 is used to determine the impedance external characteristic curves of the new energy power station and the AC power grid based on the impedance external characteristic model of the new energy power station and the impedance external characteristic model of the AC power grid.
[0211] The risk assessment module 500 is used to conduct broadband oscillation risk assessment of the new energy grid-connected system based on the comparison results of the impedance external characteristic curves of the new energy power plant and the AC power grid.
[0212] In some embodiments, the electrical unit includes a feeder, a transformer, a reactive power compensation device, and an energy storage unit. The feeder includes multiple new energy generators and multiple AC lines, which are connected in series and parallel to form the feeder.
[0213] In some embodiments, the process of constructing the impedance external characteristic model of a new energy power station is as follows:
[0214] Based on different broadband oscillation risk assessment frequency bands, construct the voltage and current small-signal phasors at the common coupling point of a single new energy unit under three-phase symmetrical operating conditions;
[0215] Based on voltage and current small-signal phasors, the AC side admittance matrix is obtained by performing a Laplace transform on the control process of a single new energy unit; among them, the AC side admittance matrix of the sub-supersynchronous frequency band introduces the phase-locked loop control coefficient matrix affected by the AC side power operation level.
[0216] The impedance characteristic model of a single new energy unit is determined based on the AC side admittance matrix.
[0217] The equivalent impedance model of the AC line between the two new energy units was obtained by using the Bergeron model to simulate the AC line.
[0218] Based on the connection relationship between multiple new energy generating units and AC lines on the feeder, the impedance characteristic model of a single new energy generating unit and the equivalent impedance model of the AC line are connected in series and parallel to obtain the external impedance characteristic model of the feeder.
[0219] Based on the primary structure and control structure of the reactive power compensation device, an impedance external characteristic model of the reactive power compensation device is constructed using the impedance modeling method.
[0220] Based on the primary structure and control structure of the energy storage unit, an impedance external characteristic model of the energy storage unit is constructed using the impedance modeling method.
[0221] The transformer is modeled using a T-shaped or π-shaped equivalent circuit to obtain the transformer's impedance external characteristic model.
[0222] The impedance external characteristic model of a new energy power station is formed by connecting the impedance external characteristic models of the feeder, the reactive power compensation device, the energy storage unit, and the transformer through series and parallel connections.
[0223] In some embodiments, the broadband oscillation risk assessment frequency band is the mid-to-high frequency band or the sub-supersynchronous frequency band; the process of constructing the impedance external characteristic model of the AC power grid is as follows:
[0224] The outgoing terminals of the AC power grid after passing through multiple stages of lines or transformers are determined by using multiple ideal voltage sources and lumped parameter impedances.
[0225] Starting from the common coupling point between the new energy power station and the AC power grid, looking towards the AC power grid to the end of the outgoing line, the impedance external characteristic model of the AC power grid is obtained based on the series and parallel connections of the AC lines, transformers, and other primary equipment in the AC power grid.
[0226] In some embodiments, the broadband oscillation risk assessment frequency band is the sub-supersynchronous frequency band; the process of constructing the impedance external characteristic model of the AC power grid is as follows: based on the short-circuit ratio equivalent method, it is constructed according to the equivalent short-circuit ratio of the AC power grid.
[0227] In some embodiments, the new energy grid-connected system corresponding to the sub-supersynchronous frequency band adopts the operation mode under different power operation levels; the new energy grid-connected system corresponding to the mid-to-high frequency band adopts the operation mode under the rated operating power level; wherein, the operation mode adopts one of the following methods, wherein the operation mode includes: black start, full connection, all reactive power compensation devices are turned off, reactive power compensation devices are turned on separately, some new energy generator sets are turned off, some new energy feeders are turned off, some AC buses are turned off, some transformers are turned off, some reactive power compensation devices are turned off, and some energy storage is turned off.
[0228] In some embodiments, the risk assessment module 500 is used for:
[0229] Based on the impedance external characteristic curves of the new energy power station and the AC power grid, the frequency range in which the impedance amplitude of the AC power grid is greater than that of the new energy power station under the same broadband oscillation risk assessment frequency band is determined.
[0230] Determine whether the phase difference between the impedance external characteristic curve of the AC power grid and the impedance external characteristic curve of the new energy power station within the frequency range is greater than a preset phase difference threshold.
[0231] If the phase difference is determined to be greater than the preset phase difference threshold, then the new energy grid-connected system is determined to have a risk of broadband oscillation.
[0232] If the phase difference is determined to be no greater than the preset phase difference threshold, then it is determined that the new energy grid-connected system does not have the risk of broadband oscillation.
[0233] As shown in Figure 57, this application embodiment also provides an electronic device. The electronic device 10 includes a memory 20 and a processor 30. The memory 20 stores a computer program. When the computer program is executed by the processor 30, the processor 30 performs the steps of the broadband oscillation risk assessment method for new energy grid-connected systems as described above.
[0234] This application also provides a computer-readable storage medium storing a computer program thereon, which, when executed, implements the steps of the broadband oscillation risk assessment method for new energy grid-connected systems as described above.
[0235] Those skilled in the art will clearly understand that, for the sake of convenience and brevity, the specific working processes of the systems, electronic devices, and computer storage media described above can be referred to the corresponding processes in the foregoing method embodiments, and will not be repeated here.
[0236] It should be noted that the terms "comprising" and "having" and any variations thereof in the specification, claims and accompanying drawings of this invention are intended to cover non-exclusive inclusion. For example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are explicitly listed, but may include other steps or units that are not explicitly listed or that are inherent to such processes, methods, products or devices.
[0237] In the several embodiments provided by this invention, it will be understood that each block in the flowchart or block diagram may represent a module, segment, or portion of code, which contains one or more executable instructions for implementing a specified logical function. It should also be noted that in some alternative implementations, the functions marked in the blocks may occur in a different order than those shown in the figures. For example, two consecutive blocks may actually be executed substantially in parallel, and they may sometimes be executed in reverse order, depending on the functions involved.
[0238] In the embodiments provided by this invention, it should be understood that the disclosed systems, electronic devices, computer storage media, and methods can be implemented in other ways. For example, the device embodiments described above are merely illustrative; for instance, the division of units is only a logical functional division, and in actual implementation, there may be other division methods. For example, multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed. Furthermore, the coupling or direct coupling or communication connection shown or discussed may be through some interfaces; the indirect coupling or communication connection between devices or units may be electrical, mechanical, or other forms.
[0239] The units described as separate components may or may not be physically separate. The components shown as units may or may not be physical units; that is, they may be located in one place or distributed across multiple network units. Some or all of the units can be selected to achieve the purpose of this embodiment according to actual needs.
[0240] Furthermore, the functional units in the various embodiments of the present invention can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The integrated unit can be implemented in hardware or as a software functional unit.
[0241] If the integrated unit is implemented as a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions for executing all or part of the steps of the methods described in the various embodiments of the present invention through a computer device (which may be a personal computer, server, or network device, etc.). The aforementioned storage medium includes: USB flash drives, portable hard drives, read-only memory (ROM), random access memory (RAM), magnetic disks, optical disks, and other media capable of storing program code.
[0242] The above embodiments are only used to illustrate the technical solutions of the present invention, and are not intended to limit it. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for assessing broadband oscillation risk in a new energy grid-connected system, applied to assess the broadband oscillation risk of a new energy grid-connected system in different broadband oscillation risk assessment frequency bands, wherein the broadband oscillation risk assessment frequency bands include mid-to-high frequency bands and sub-supersynchronous frequency bands; characterized in that, The method includes: Based on the multiple electrical units of the new energy power station, an impedance external characteristic model of each electrical unit is established; Based on the impedance external characteristic model and wiring structure of each electrical unit of the new energy power station, the electrical units are connected, and based on the impedance series and parallel relationship of each electrical unit, the impedance external characteristic model of the new energy power station corresponding to the broadband oscillation risk assessment frequency band is obtained. Based on different broadband oscillation risk assessment frequency bands, determine the impedance external characteristic model of the AC power grid corresponding to the broadband oscillation risk assessment frequency band; Based on the impedance external characteristic model of the new energy power station and the impedance external characteristic model of the AC power grid, the impedance external characteristic curves of the new energy power station and the AC power grid are determined. A broadband oscillation risk assessment is conducted on the new energy grid-connected system based on the comparison results between the impedance external characteristic curves of the new energy power station and the AC power grid.
2. The method for assessing the broadband oscillation risk of a new energy grid-connected system according to claim 1, characterized in that, The electrical unit includes a feeder, a transformer, a reactive power compensation device, and an energy storage unit. The feeder comprises multiple new energy generators and multiple AC lines, which are connected in series and parallel to form the feeder.
3. The method for assessing the broadband oscillation risk of a new energy grid-connected system according to claim 2, characterized in that, The process of constructing the impedance external characteristic model of the new energy power station is as follows: Based on different broadband oscillation risk assessment frequency bands, construct the voltage and current small-signal phasors at the common coupling point of a single new energy unit under three-phase symmetrical operating conditions; Based on the voltage and current small-signal phasors, the AC side admittance matrix is obtained by performing a Laplace transform on the control process of the single new energy unit; wherein, the AC side admittance matrix of the sub-supersynchronous frequency band incorporates the phase-locked loop control coefficient matrix affected by the AC side power operation level. The impedance characteristic model of a single new energy unit is determined based on the AC side admittance matrix. The equivalent impedance model of the AC line between the two new energy units was obtained by using the Bergeron model to simulate the AC line. Based on the connection relationship between the multiple new energy generating units on the feeder and the AC line, the impedance characteristic model of the single new energy generating unit and the equivalent impedance model of the AC line are connected in series and parallel to obtain the impedance external characteristic model of the feeder. Based on the primary structure and control structure of the reactive power compensation device, an impedance external characteristic model of the reactive power compensation device is constructed using the impedance modeling method. Based on the primary structure and control structure of the energy storage unit, an impedance external characteristic model of the energy storage unit is constructed using the impedance modeling method. The transformer is modeled using a T-shaped or π-shaped equivalent circuit to obtain the transformer's impedance external characteristic model. The impedance external characteristic model of the new energy power station is formed by connecting the impedance external characteristic models of the feeder, the reactive power compensation device, the energy storage unit, and the transformer in series and parallel.
4. The method for assessing the broadband oscillation risk of a new energy grid-connected system according to claim 1, characterized in that, The broadband oscillation risk assessment frequency band is the mid-to-high frequency band or the sub-supersynchronous frequency band; the construction process of the impedance external characteristic model of the AC power grid is as follows: The outgoing terminals of the AC power grid after passing through multiple stages of lines or transformers are determined by using multiple ideal voltage sources and lumped parameter impedances. Starting from the common coupling point between the new energy power station and the AC power grid, looking towards the AC power grid to the outgoing end, the impedance external characteristic model of the AC power grid is obtained based on the series and parallel connections of the AC lines, transformers, and other primary equipment in the AC power grid.
5. The method for assessing the broadband oscillation risk of a new energy grid-connected system according to claim 1, characterized in that, The broadband oscillation risk assessment frequency band is the sub-supersynchronous frequency band; the construction process of the impedance external characteristic model of the AC power grid is as follows: based on the short-circuit ratio equivalent method, it is constructed according to the equivalent short-circuit ratio of the AC power grid.
6. The method for assessing the broadband oscillation risk of a new energy grid-connected system according to claim 1, characterized in that, The new energy grid-connected system corresponding to the sub-supersynchronous frequency band adopts the operation mode under different power operation levels; the new energy grid-connected system corresponding to the mid-to-high frequency band adopts the operation mode under the rated operating power level; wherein, the operation mode adopts one of the following methods, wherein the operation mode includes: black start, full connection, all reactive power compensation devices are turned off, reactive power compensation devices are turned on separately, some new energy generator sets are turned off, some new energy feeders are turned off, some AC busbars are turned off, some transformers are turned off, some reactive power compensation devices are turned off, and some energy storage is turned off.
7. The method for assessing the risk of broadband oscillation in a new energy grid-connected system according to claim 1, characterized in that, The broadband oscillation risk assessment of the renewable energy grid-connected system based on the comparison results of the impedance external characteristic curves of the renewable energy power plant and the AC power grid includes: Based on the impedance external characteristic curve of the new energy power station and the impedance external characteristic curve of the AC power grid, the frequency range in which the impedance amplitude of the AC power grid is greater than that of the new energy power station under the same broadband oscillation risk assessment frequency band is determined. Determine whether the phase difference between the impedance external characteristic curve of the AC power grid and the impedance external characteristic curve of the new energy power station within the frequency range is greater than a preset phase difference threshold. If the phase difference is determined to be greater than the preset phase difference threshold, then the new energy grid-connected system is determined to have a broadband oscillation risk. If the phase difference is determined to be no greater than the preset phase difference threshold, then it is determined that the new energy grid-connected system does not have the risk of broadband oscillation.
8. A broadband oscillation risk assessment system for a new energy grid-connected system, used to assess the broadband oscillation risk of the new energy grid-connected system in different broadband oscillation risk assessment frequency bands, wherein the broadband oscillation risk assessment frequency bands include mid-high frequency bands and sub-supersynchronous frequency bands; characterized in that, include: The impedance model construction module is used to establish the impedance external characteristic model of each electrical unit based on multiple electrical units in the new energy power station. The power station model construction module is used to connect each electrical unit according to the impedance external characteristic model and wiring structure of each electrical unit of the new energy power station, and obtain the impedance external characteristic model of the new energy power station corresponding to the broadband oscillation risk assessment frequency band according to the impedance series-parallel relationship of each electrical unit. The grid-side model construction module is used to determine the impedance external characteristic model of the AC power grid corresponding to the broadband oscillation risk assessment frequency band based on different broadband oscillation risk assessment frequency bands. The impedance curve determination module is used to determine the impedance external characteristic curve of the new energy power station and the impedance external characteristic curve of the AC power grid based on the impedance external characteristic model of the new energy power station and the impedance external characteristic model of the AC power grid. The risk assessment module is used to conduct a broadband oscillation risk assessment of the new energy grid-connected system based on the comparison results between the impedance external characteristic curve of the new energy power station and the impedance external characteristic curve of the AC power grid.
9. An electronic device, characterized in that, The electronic device includes a memory and a processor. The memory stores a computer program. When the computer program is executed by the processor, the processor performs the steps of the broadband oscillation risk assessment method for new energy grid-connected systems as described in any one of claims 1-7.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed, it implements the steps of the broadband oscillation risk assessment method for new energy grid-connected systems as described in any one of claims 1-7.