A visualization device for simulating shield excavation and monitoring tunnel and soil deformation, and a shield simulation test method

By designing a visual device, using model box and fiber optic strain sensing technology, the problem of soil and pipe sheet deformation monitoring in shield tunnel construction is solved, and the precise monitoring of soil and pipe sheet deformation during shield tunnel excavation is realized. Improves the safety of construction and operation and provides emergency response measures.

CN113586070BActive Publication Date: 2024-11-19ZHEJIANG UNIV OF TECH
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202110606291.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-06-01
Publication Date
2024-11-19
Estimated Expiration
2041-06-01

AI Technical Summary

Technical Problem

During the construction and operation of shield tunnels, it is difficult to effectively monitor and analyze the deformation of soil and pipe sheets, especially when crossing dense areas of buildings or facing severe weather, which leads to threatening the safety of the tunnel and lack of effective simulation and monitoring. means.

Method used

A visualization device was designed, including a model box, a tunnel excavation device, a support adjustment system and a monitoring system. The principle of geometric similarity ratio is used to simulate soil layer distribution, combined with 3D printing technology and fiber strain sensing technology to monitor soil and pipes in real time deformation of the slice and data analysis is provided through computer automation processing.

Benefits of technology

Accurate monitoring of soil and pipe sheet deformation during shield tunnel excavation process, simplifies the construction and operation process, provides reference for safety optimization and emergency response measures, reduces test interference factors, and improves construction and operation security.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113586070B_ABST
    Figure CN113586070B_ABST
Patent Text Reader

Abstract

The present invention discloses a visualization device for simulating shield excavation and monitoring tunnel and soil deformation, and a shield simulation test method implemented by the visualization device. The visualization device includes: a model box, a tunnel excavation device, a support adjustment system, and a monitoring system. The tunnel excavation device adopts 3D printing technology to scale down and assemble segments, and the support adjustment system adopts a support platform and a jack to simulate shield excavation. The hole digging device and the segment lining are assembled to simulate shield excavation. The monitoring system in the device of the present invention adopts optical fiber strain sensing technology to realize wireless transmission, automatic processing and visualization of monitoring data. It also realizes the simulation of shield crossing process and tunnel operation process under various working conditions such as different natural environments, geological conditions and construction conditions by adopting an adjustment plate and a combination of different functional modules, providing a reference for shield crossing optimization construction and tunnel operation safety and emergency response measures.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of tunnels and underground engineering, and in particular to a visualization device for simulating shield excavation and monitoring deformation of tunnels and soil. The present invention also relates to a shield simulation test method implemented by using the visualization device for simulating shield excavation and monitoring deformation of tunnels and soil. Background Art

[0002] With the acceleration of my country's urbanization process and the rapid development of urban rail transit, the scale of shield tunnels has continued to expand. The construction of shield tunnels is restricted by surrounding buildings and environmental factors. For example, tunnels inevitably pass through densely built areas or existing underground pipelines, and the impact of tunnel construction on surrounding buildings and structures needs to be fully considered. For example, during the construction and operation of tunnels, they will be affected by severe weather such as heavy rain and high temperature, which can easily cause deformation of the surrounding soil, posing a challenge to tunnel safety. Shield tunnels play a significant role in transportation, and their construction and operation safety affect the safety of people's lives and property and the normal progress of social and economic activities. In order to improve the safety of shield tunnel projects during construction and operation, it is necessary to conduct indoor model tests of shield tunnels before the project is carried out, simulate the conditions of tunnels passing through existing buildings, underground pipelines, rivers, etc. during construction, and simulate various disasters during tunnel construction and operation. At the same time, the deformation of soil and pipe segments is monitored in real time, and corresponding solutions are provided for the actual project through data analysis. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a visualization device for simulating shield excavation and monitoring tunnel and soil deformation, which can be used to analyze soil displacement changes and the strain state of tunnel segments during shield crossing construction, and to study the mechanism of stratum disturbance and the development law of uneven surface settlement. The technical problem to be solved by the present invention also includes providing a shield simulation test method implemented by using the visualization device for simulating shield excavation and monitoring tunnel and soil deformation.

[0004] To this end, the present invention provides a visualization device for simulating shield excavation and monitoring tunnel and soil deformation, comprising: a model box, a tunnel excavation device, a support adjustment system, and a monitoring system;

[0005] The model box is filled with soil samples collected during on-site construction, and the soil samples are buried in layers based on the principle of geometric similarity ratio to simulate the distribution of soil layers on site. The front and rear sides of the model box are composed of detachable plug-in plates with holes.

[0006] The tunnel excavation device is composed of a hole digging device and a segment lining. The front end of the hole digging device is a truncated cone-shaped smooth and sharp ring cutter, and the rear end is a hollow cylinder for filling soil. The segment lining is obtained by 3D printing technology and is formed by a combination of multiple segments. There is no gap between the truncated cone-shaped smooth and sharp ring cutter, the cylinder for filling soil and the segment lining, and the cylinder is provided with a thread to be connected with the segment lining to form a whole. The segments are connected by bolts, and a thread shape is provided on the segment at one end of the segment lining to be threadedly connected with the cylinder.

[0007] A support adjustment system is provided below the excavation device, and the support adjustment system includes a tunnel support platform, a reset spring, a jack, a jack support platform, a jack base, a push plate, and a jack reaction platform; the tunnel support platforms are connected as a whole by reset springs, and the distance between the tunnel support platforms is adjusted by reset springs; the excavation of the tunnel is realized by the jack, and the push plate is placed between the jack and the tunnel excavation device, and the tunnel is pushed forward by the jack onto the push plate;

[0008] The monitoring system uses optical fiber strain sensing technology to monitor the deformation of soil and segment lining. The strain sensing optical fiber is installed in the soil of the model box and on the segment lining. The optical fiber demodulator can collect and wirelessly transmit data. The monitoring data is displayed in real time on the computer screen, and the corresponding deformation information is obtained through computer automatic processing.

[0009] Preferably, a plurality of card slots are vertically arranged on the front and rear sides and the upper and lower sides of the model box, and the card slots are separated by vertical frame bars. A plurality of height adjustment baffles and a hollow baffle are arranged in the middle card slot, and a plurality of height adjustment baffles are arranged in the card slots on both sides; the card slots, height adjustment baffles and hollow baffles are arranged symmetrically on the acrylic plate on the rear side of the model box and the front side of the model box, the height adjustment baffles in the card slots can move up and down, the height and width of the height adjustment plates at the bottom of both sides are consistent with those of the hollow baffles, and the height and width of the remaining height adjustment plates are consistent.

[0010] Preferably, the deformation monitoring system for soil and segment lining is composed of a strain sensing optical fiber, an optical fiber demodulator, and a computer. The strain sensing optical fiber is installed in the soil of the model box and on the segment lining, and the deformation of the soil and segment lining is monitored by using the optical fiber demodulator. The data collected by the optical fiber demodulator can be transmitted to the computer wirelessly. The strain sensing optical fiber is installed in parallel with a temperature compensation optical fiber. The monitoring data of the temperature compensation optical fiber is subtracted from the monitoring data of the strain sensing optical fiber to obtain the deformation information of the soil and segment lining. The strain sensing optical fiber is composed of a core and a reinforced sheath from the inside to the outside to prevent the optical fiber from being damaged during installation.

[0011] Preferably, a water spray device is arranged above the model box, and the water spray device is supported by a water spray device bracket fixed on the model box. The water spray device includes a water spray pipe network, and the water spray pipe network has water spray outlets densely opened downward, and nozzles are installed at the water spray outlets. The main pipe of the water spray pipe network is connected to the water inlet pipe through an external pipe, and the water inlet pipe is connected to the water pump.

[0012] Preferably, a radiation lamp bracket is fixed on the model box, and a thermal radiation lamp is fixed on the radiation lamp bracket. The thermal radiation lamp irradiates the soil sample in a direction to simulate the temperature rise caused by sunlight. The water spraying device bracket is fixed on both sides of the model box, and the radiation lamp bracket is arranged between the frames on both sides of the model box. The radiation lamp bracket is equipped with a motor to drive it to move up and down. When the water spraying network sprays water, the motor drives the radiation lamp bracket to move up with the thermal radiation lamp and is above the water spraying network. When the thermal radiation lamp is used to radiate heat, the motor drives the thermal radiation lamp bracket to move down with the thermal radiation lamp and is below the water spraying network.

[0013] The present invention also provides a shield simulation test method implemented by using the above-mentioned visualization device for simulating shield excavation and monitoring tunnel and soil deformation, comprising the following steps:

[0014] A. Based on the survey data, fill the model box soil based on the similarity ratio theory to simulate the actual soil layer distribution;

[0015] B. Install the strain sensing optical fiber in the soil of the model box, and use the optical fiber demodulator to monitor the deformation of the soil. The data collected by the optical fiber demodulator can be transmitted to the computer by wireless. The strain sensing optical fiber is installed with a temperature compensation optical fiber in parallel. The monitoring data of the strain sensing optical fiber is subtracted from the monitoring data of the temperature compensation optical fiber to obtain the deformation information of the soil. The strain sensing optical fiber is composed of a core and a reinforced sheath from the inside to the outside, so as to avoid damage to the optical fiber during the installation process.

[0016] C. Install the strain sensing optical fiber on the segment lining, and use the optical fiber demodulator to monitor the deformation of the segment lining; the data collected by the optical fiber demodulator can be transmitted to the computer by wireless, and the strain sensing optical fiber is installed with a temperature compensation optical fiber in parallel, and the monitoring data of the temperature compensation optical fiber is subtracted from the monitoring data of the strain sensing optical fiber to obtain the deformation information of the segment lining; the strain sensing optical fiber is composed of a core and a reinforced sheath from the inside to the outside, so as to avoid damage to the optical fiber during installation;

[0017] D. The tunnel excavation device is composed of a hole digging device and a segment lining. The front end of the hole digging device is a truncated cone-shaped smooth and sharp ring cutter, and the rear end is a hollow cylinder for filling soil. The segment lining is obtained by 3D printing technology and is formed by combining multiple segments. The segment lining and the cylinder for filling soil are connected as a whole through threads.

[0018] E. A support adjustment system is provided below the excavation device, the tunnel support platforms are connected as a whole by reset springs, and the distance between the tunnel support platforms is adjusted by reset springs; the excavation of the tunnel is realized by the jack, and the push plate is placed between the jack and the tunnel excavation device, and the jack is used to push the push plate to control the advancement of the tunnel;

[0019] F. The monitoring system uses optical fiber strain sensing technology to monitor the deformation of soil and segment lining. The strain sensing optical fiber is installed in the soil of the model box and on the segment lining. The data can be collected and wirelessly transmitted through the optical fiber demodulator; the monitoring data is displayed in real time on the computer screen, and the corresponding deformation information is obtained through computer automated processing.

[0020] Preferably, the segments are connected by bolts, and a threaded shape is provided on the segment at one end of the segment lining, which is threadedly connected to the cylinder.

[0021] Technical effects of the present invention:

[0022] 1) The shield tunnel excavation model of the present invention is an improvement on the traditional shield test model, which is specifically manifested in that: the model of the present invention adopts 3D printing technology to scale down and assemble the segments in equal proportions, restoring the actual state of the segment lining; after assembling the hole-digging device and the segment lining, tunnel excavation is simulated, simplifying the complex process of shield construction excavation and segment assembly. The device solves the problems existing in the current test device to a certain extent and eliminates other test interference factors.

[0023] 2) The device of the present invention utilizes optical fiber strain sensing technology to establish a monitoring system for soil and segment lining deformation. The optical fiber sensor used in the system has the advantages of high sensitivity, good stability, corrosion resistance, and resistance to electromagnetic interference, and can realize wireless transmission, automatic processing, and visualization of monitoring data. Based on the monitoring data, the development and progress of disasters such as soil and segment lining deformation, uneven surface settlement, etc. during shield crossing and tunnel operation can be further analyzed.

[0024] 3) The device of the present invention can simulate natural factors such as heavy rainfall, high temperature weather, underground caves, etc. It can simulate the excavation of tunnels of different depths, the excavation of multiple tunnels, and the impact of tunnel excavation on existing tunnels. It can also simulate the impact of tunnel excavation on upper buildings by arranging buildings on the surface soil of the model. Therefore, with the help of this device, the safety of the tunnel and its surrounding environment during the shield crossing process and tunnel operation under the above working conditions can be explored, providing a reference for the optimization of shield crossing construction and emergency response measures for tunnel operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 A schematic diagram of the three-dimensional structure of a visualization device for simulating shield excavation and monitoring tunnel and soil deformation provided by the present invention;

[0026] Figure 2 for Figure 1 Schematic diagram of the structure of the model box in ;

[0027] Figure 3 for Figure 1 Schematic diagram of the connection structure of the shield tunnel support seat and jack;

[0028] Figure 4 for Figure 1 Schematic diagram of the structure of the hole-digging device and the segment lining;

[0029] Figure 5 for Figure 1 A schematic diagram of the insertion structure of the height adjustment baffle and the hollowed-out baffle and the card slot;

[0030] Figure 6 for Figure 3 Schematic diagram of the tunnel support platform and jacking plate structure;

[0031] Figure 7 for Figure 1 Strain sensing optical fiber arrangement in the model box and on the segment lining;

[0032] Figure 8 for Figure 1 Schematic diagram of the structure of the visualization device used to simulate shield excavation and monitor tunnel and soil deformation;

[0033] Fig. 9 for Figure 8 Schematic diagram of the top view of the model box in . DETAILED DESCRIPTION

[0034] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. The same parts are represented by the same reference numerals. It should be noted that the words "front", "rear", "left", "right", "upper" and "lower" used in the following description refer to directions in the accompanying drawings, and the words "bottom surface" and "top surface", "inner" and "outer" refer to directions toward or away from the geometric center of a specific component, respectively.

[0035] Reference Figure 1-5 As shown, the present invention provides a visualization device for simulating shield excavation and monitoring tunnel and soil deformation, comprising: a model box 1, a tunnel excavation device, a support adjustment system, and a monitoring system;

[0036] The model box 1 is filled with soil samples collected during on-site construction. The soil samples are buried in layers based on the principle of geometric similarity ratio to simulate the distribution of soil layers on site. The front and rear side plates of the model box 1 are provided with shield plug holes 2.

[0037] The tunnel excavation device is composed of a hole digging device and a segment lining 5. The front end of the hole digging device is a truncated cone-shaped smooth and sharp ring cutter 3, and the rear end is a hollow cylinder 6 for filling soil. The segment lining 5 is formed by a combination of multiple segments 4. There is no gap between the truncated cone-shaped smooth and sharp ring cutter 3, the cylinder 6 for filling soil, and the segment lining 5. At the same time, a thread 25 is provided on the cylinder 6 to connect with the segment 4 at one end of the segment lining 5 to form a whole; the segments 4 are connected by bolts, and at the same time, a thread 25 is provided on the segment 4 at one end of the segment lining 5 to connect with the cylinder 6 by thread 25;

[0038] A support adjustment system is provided below the tunnel excavation device, and the support adjustment system includes a tunnel support platform 7, a reset spring 8, a jack 9, a jack support platform 10, a jack base 11, a push plate 12, and a jack reaction platform 24; the tunnel support platform 7 is connected as a whole by the reset spring 8, the tunnel support platform 7 is sleeved on the reset spring 8 and can slide relatively, and the distance between the tunnel support platforms 7 is adjusted by the reset spring 8; the excavation of the tunnel is realized by the jack 9, the push plate 12 is placed between the jack 9 and the tunnel, and the jack 9 is used to push the push plate 12 to control the advancement of the tunnel, and the jack reaction platform 24 provides a reaction force for the jack 9;

[0039] The monitoring system uses strain sensing optical fiber 16 to monitor the deformation of soil and segment lining 5. The strain sensing optical fiber 16 is buried in the soil of the model box 1 and on the segment lining 5. The data can be collected and wirelessly transmitted through the optical fiber demodulator, and the data can be displayed in real time on the computer screen, and the corresponding deformation information can be obtained through automatic processing.

[0040] Reference Figure 1 , Figure 2 and Figure 5 As shown, the front side of the model box 1 is vertically arranged with multiple slots 13, each slot 13 is separated by a vertical frame bar 14, a plurality of height adjustment baffles 22 and a hollow baffle 15 are arranged in the middle slot 13, and a plurality of height adjustment baffles 22 are arranged in the slots 13 on both sides; the slots 13, the height adjustment baffles 22, and the hollow baffles 15 are arranged symmetrically on the acrylic plate on the rear side of the model box 1 and the front side of the model box 1, the height adjustment baffles 22 in the slots 13 can move up and down, the height and width of the height adjustment plates 22 at the bottom of both sides are consistent with the hollow baffles 15, and the height and width of the remaining height adjustment plates 22 are consistent. This structure can flexibly select the position of the hollow baffle 15 and the shield plug hole 2.

[0041] Reference Figure 6As shown, the above-mentioned tunnel excavation device can be suspended and fixed on the top push plate 12, so that during shield excavation, the conical smooth and sharp ring cutter 3, the cylinder 6 and the segment lining 5 can be maintained in the same central position; at the same time, when the tunnel excavation is carried out to the point where most of the hollow cylinder 6 for filling soil enters the soil, the tunnel support platform 7 can be disassembled to allow the hollow cylinder 6 for filling soil to completely enter the soil, and the segment lining 5 can be completely buried in the soil, wherein the tunnel support platform 7 can be assembled and combined by wedges.

[0042] Reference Figure 7 As shown, the above-mentioned soil and segment lining 5 deformation monitoring system is composed of a strain sensing optical fiber 16, an optical fiber demodulator and a computer. The strain sensing optical fiber 16 is installed in the soil of the model box and on the segment lining 5, and the optical fiber demodulator is used to monitor the deformation of the soil and segment lining 5; the data collected by the optical fiber demodulator can be transmitted to the computer by wireless, and the strain sensing optical fiber 16 is installed in parallel with a temperature compensation optical fiber, and the monitoring data of the temperature compensation optical fiber is subtracted from the monitoring data of the strain sensing optical fiber 16 to obtain the deformation information of the soil and segment lining 5; the strain sensing optical fiber 16 is composed of a core and a reinforced sheath from the inside to the outside, so as to avoid damage to the optical fiber during installation.

[0043] Reference Figure 1-9 As shown, the present invention also provides a shield simulation test method implemented by using the above-mentioned visualization device for simulating shield excavation and monitoring tunnel and soil deformation, comprising the following steps:

[0044] A. Based on the survey data, fill the model box soil based on the similarity ratio theory to simulate the actual soil layer distribution;

[0045] B. Install the strain sensing optical fiber 16 in the soil of the model box, and use the optical fiber demodulator to monitor the deformation of the soil. The data collected by the optical fiber demodulator can be transmitted to the computer by wireless. The strain sensing optical fiber 16 is installed with a temperature compensation optical fiber in parallel. The monitoring data of the strain sensing optical fiber 16 is subtracted from the monitoring data of the temperature compensation optical fiber to obtain the deformation information of the soil. The strain sensing optical fiber 16 is composed of a core and a reinforced sheath from the inside to the outside, so as to avoid damage to the optical fiber during the installation process.

[0046] C. Install the strain sensing optical fiber 16 on the segment lining, and use the optical fiber demodulator to monitor the deformation of the segment lining; the data collected by the optical fiber demodulator can be transmitted to the computer by wireless, and the strain sensing optical fiber 16 is installed with a temperature compensation optical fiber in parallel, and the monitoring data of the temperature compensation optical fiber is subtracted from the monitoring data of the strain sensing optical fiber 16 to obtain the deformation information of the segment lining; the strain sensing optical fiber 16 is composed of a fiber core and a reinforced sheath from the inside to the outside, so as to prevent the optical fiber from being damaged during the installation process;

[0047] D. The tunnel excavation device is composed of a hole digging device and a segment lining 5. The front end of the hole digging device is a truncated cone-shaped smooth and sharp ring cutter 3, and the rear end is a hollow cylinder 6 for filling soil. The segment lining 5 is formed by a combination of multiple segments 4. There is no gap between the truncated cone-shaped smooth and sharp ring cutter 3, the cylinder 6 for filling soil, and the segment lining 5. At the same time, a thread 25 is provided on the cylinder 6 to connect with the segment 4 at one end of the segment lining 5 to form a whole; the segments 4 are connected by bolts, and at the same time, a thread 25 is provided on the segment 4 at one end of the segment lining 5 to connect with the cylinder 6 by thread 25;

[0048] E. A support adjustment system is provided below the tunnel excavation device. The tunnel support platforms 7 are connected as a whole by reset springs 8. The distance between the tunnel support platforms 7 is adjusted by reset springs 8. The excavation of the tunnel is realized by the jacks 9. The push plate 12 is placed between the jacks 9 and the tunnel. The tunnel is simulated by the segments 4 and the cylinder 6. The jacks 9 push the push plate 12 to control the advancement of the tunnel.

[0049] F. The monitoring system uses optical fiber strain sensing technology to monitor the deformation of soil and segment lining. The strain sensing optical fiber 16 is installed in the soil of the model box 1 and on the segment lining 5. The data can be collected and wirelessly transmitted through the optical fiber demodulator; the monitoring data is displayed in real time on the computer screen, and the corresponding deformation information is obtained through computer automated processing.

[0050] Reference Figure 8-9 As shown, on the basis of the above technical solution, in order to facilitate the simulation of rain and temperature change environment and realize the efficient switching of each simulation mechanism, the present invention adds the following structure: a water spray device is arranged above the above model box 1, and the water spray device is supported by a water spray device bracket 17 fixed on the model box, and the water spray device includes a water spray pipe network 18, and the water spray pipe network 18 has water spray ports 19 densely arranged downward, and a nozzle is installed at the water spray port 19. The main pipe of the water spray pipe network 18 is connected to the water inlet pipe through an external pipe, and the water inlet pipe is connected to the water pump; a radiation lamp bracket 20 is fixed on the model box 1, and a heat radiation lamp 21 is fixed on the radiation lamp bracket 20. The heat radiation lamp 21 The spotlight 21 irradiates the soil sample in a direction to simulate the temperature rise caused by sunlight. The water spray device bracket 17 is fixedly arranged on both sides of the model box 1. The radiation lamp bracket 20 is arranged between the frames on both sides of the model box 1. The radiation lamp bracket 20 is configured with a motor to drive it to move up and down. When the water spray network 18 sprays water, the motor drives the radiation lamp bracket 20 to move up with the thermal radiation lamp 21 and is located above the water spray network 18. When the thermal radiation lamp 21 radiates heat, the motor drives the thermal radiation lamp bracket 20 to move down with the thermal radiation lamp 21 and is located below the water spray network 18. This structure is conducive to the switching of thermal radiation and water spraying. Thermal radiation simulates sunlight and controls temperature, and water spraying can simulate rainfall.

[0051] Reference Figure 8As shown, in order to enable the tunnel support platform 7 to slide more smoothly, a pulley 23 is set at the bottom of the tunnel support platform 7, and a reset spring 8 is set between the tunnel support platforms 7. When pushing, the tunnel support platform 7 will be relatively retracted after sliding, thereby pushing into the soil. When withdrawing, the tunnel support platform 7 will automatically open under the action of the reset spring 8.

[0052] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.

Claims

1. A shield simulation test method implemented by a visualization device, characterized in that: The visualization device is used to simulate shield excavation and monitor the deformation of tunnels and soil. The visualization device for simulating shield excavation and monitoring the deformation of tunnels and soil includes a model box, a tunnel excavation device, a support adjustment system, and a monitoring system; The model box is filled with soil samples collected during on-site construction, and the soil samples are buried in layers based on the principle of geometric similarity ratio to simulate the distribution of soil layers on site. The front and rear sides of the model box are composed of detachable plug-in plates with holes. The tunnel excavation device is composed of a hole digging device and a segment lining. The front end of the hole digging device is a truncated cone-shaped smooth and sharp ring cutter, and the rear end is a hollow cylinder for filling soil. The segment lining is obtained by 3D printing technology and is formed by a combination of multiple segments. There is no gap between the truncated cone-shaped smooth and sharp ring cutter, the cylinder for filling soil and the segment lining, and the cylinder is provided with a thread to be connected with the segment lining to form a whole. The segments are connected by bolts, and a thread shape is provided on the segment at one end of the segment lining to be threadedly connected with the cylinder. A support adjustment system is provided below the excavation device, and the support adjustment system includes a tunnel support platform, a reset spring, a jack, a jack support platform, a jack base, a push plate, and a jack reaction platform; the tunnel support platforms are connected as a whole by reset springs, the distance between the tunnel support platforms is adjusted by reset springs, and a pulley is provided at the bottom of the tunnel support platform; the excavation of the tunnel is realized by the jack, and the push plate is placed between the jack and the tunnel excavation device, and the tunnel is pushed forward by the jack onto the push plate; The monitoring system uses optical fiber strain sensing technology to monitor the deformation of soil and segment lining. The strain sensing optical fiber and temperature compensation optical fiber are installed in the soil of the model box and on the segment lining. The optical fiber demodulator can collect and wirelessly transmit data. The monitoring data is displayed on the computer screen in real time, and the corresponding deformation information is obtained through computer automatic processing. A plurality of card slots are vertically arranged on the front and rear sides of the model box, and the card slots are separated by vertical frame bars. A plurality of height adjustment baffles and a hollow baffle are arranged in the middle card slot, and a plurality of height adjustment baffles are arranged in the card slots on both sides. The card slots, the height adjustment baffles, and the hollow baffles are arranged symmetrically on the acrylic plate on the rear side of the model box and the front side of the model box. The height adjustment baffles in the card slots can move up and down, and the height and width of the height adjustment baffles at the bottom of both sides are consistent with the hollow baffles, and the height and width of the remaining height adjustment baffles are consistent; The deformation monitoring system of the soil and the segment lining is composed of a strain sensing optical fiber, an optical fiber demodulator, and a computer. The strain sensing optical fiber is installed in the soil of the model box and on the segment lining, and the deformation of the soil and the segment lining is monitored by the optical fiber demodulator; the data collected by the optical fiber demodulator can be transmitted to the computer by wireless, and the strain sensing optical fiber is installed in parallel with a temperature compensation optical fiber, and the monitoring data of the temperature compensation optical fiber is subtracted from the monitoring data of the strain sensing optical fiber to obtain the deformation information of the soil and the segment lining; The strain sensing optical fiber is composed of a fiber core and a reinforced sheath from the inside to the outside, so as to prevent the optical fiber from being damaged during installation; A water spray device is arranged above the model box, and the water spray device is supported by a water spray device bracket fixed on the model box. The water spray device comprises a water spray pipe network, and the water spray pipe network has water spray outlets densely arranged downward, and a nozzle is installed at the water spray outlet. The main pipe of the water spray pipe network is connected to the water inlet pipe through an external pipe, and the water inlet pipe is connected to the water pump; The model box is fixed with a radiation lamp bracket, on which a heat radiation lamp is fixedly arranged, and the heat radiation lamp irradiates the soil sample in a direction to simulate the temperature rise caused by the sun, the water spraying device bracket is fixedly arranged on both sides of the model box, the radiation lamp bracket is arranged between the frames on both sides of the model box, and the radiation lamp bracket is equipped with a motor to drive it to move up and down. When the water spraying network sprays water, the motor drives the radiation lamp bracket to move up with the heat radiation lamp and is located above the water spraying network. When the heat radiation lamp is used to radiate heat, the motor drives the heat radiation lamp bracket to move down with the heat radiation lamp and is located below the water spraying network; The test method comprises the following steps: A. Based on the survey data, fill the model box soil based on the similarity ratio theory to simulate the actual soil layer distribution; B. Install the strain sensing optical fiber in the soil of the model box, and use the optical fiber demodulator to monitor the deformation of the soil. The data collected by the optical fiber demodulator can be transmitted to the computer by wireless. The strain sensing optical fiber is installed with a temperature compensation optical fiber in parallel. The monitoring data of the strain sensing optical fiber is subtracted from the monitoring data of the temperature compensation optical fiber to obtain the deformation information of the soil. The strain sensing optical fiber is composed of a core and a reinforced sheath from the inside to the outside, so as to avoid damage to the optical fiber during the installation process. C. Install the strain sensing optical fiber on the segment lining, and use the optical fiber demodulator to monitor the deformation of the segment lining; the data collected by the optical fiber demodulator can be transmitted to the computer by wireless, and the strain sensing optical fiber is installed with a temperature compensation optical fiber in parallel, and the monitoring data of the temperature compensation optical fiber is subtracted from the monitoring data of the strain sensing optical fiber to obtain the deformation information of the segment lining; the strain sensing optical fiber is composed of a core and a reinforced sheath from the inside to the outside, so as to avoid damage to the optical fiber during installation; D. The tunnel excavation device is composed of a hole digging device and a segment lining. The front end of the hole digging device is a truncated cone-shaped smooth and sharp ring cutter, and the rear end is a hollow cylinder for filling soil. The segment lining is obtained by 3D printing technology and is formed by combining multiple segments. The segment lining and the cylinder for filling soil are connected as a whole through threads. E. A support adjustment system is provided below the excavation device, the tunnel support platforms are connected as a whole by reset springs, and the distance between the tunnel support platforms is adjusted by reset springs; the excavation of the tunnel is realized by the jack, and the push plate is placed between the jack and the tunnel excavation device, and the jack is used to push the push plate to control the advancement of the tunnel; F. The monitoring system uses optical fiber strain sensing technology to monitor the deformation of soil and segment lining. The strain sensing optical fiber is installed in the soil of the model box and on the segment lining. The data can be collected and wirelessly transmitted through the optical fiber demodulator; the monitoring data is displayed in real time on the computer screen, and the corresponding deformation information is obtained through computer automated processing.

2. The shield simulation test method using a visualization device according to claim 1 is characterized in that: The segments are connected by bolts, and a threaded shape is provided on the segment at one end of the segment lining to be threadedly connected with the cylinder.

Citation Information

Patent Citations

  • Tunnel structure monitoring system and tunnel structure monitoring method based on distributed long-gauge fiber bragg grating

    CN104374433A

  • System and method capable of achieving large-scale high-precision on-line monitoring of faulting of slab ends of shield tunnel

    CN105089702A

  • Soft rock slaking test system for simulating natural environments

    CN106370545A

  • Noncontact tunnel excavation physical model capable of simulating rainfall and test method

    CN110275008A

  • Test device for erecting shield tunnel excavation model and working method thereof

    CN110530788A