A method for measuring downhole tensor resistivity

By setting up multi-directional electrodes and inspection mechanisms on the underground rock layer, the problem of inaccurate downhole tensor resistivity measurement is solved, and accurate prediction and real-time monitoring of geological disasters are achieved.

CN114355460BActive Publication Date: 2024-11-22ANHUI UNIV OF TECH SCI & TECH PARK CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111630510.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-28
Publication Date
2024-11-22
Estimated Expiration
2041-12-28

AI Technical Summary

Technical Problem

The existing downhole tensor resistivity measurement methods cannot comprehensively measure the resistivity along the direction, tendency and vertical direction of the rock formation, resulting in inaccurate measurement results and difficult to accurately predict geological disasters.

Method used

Substation nodes are set at intervals along the tunnel construction direction on the underground rock layer, and each substation node is set with transmitting electrodes and acquisition electrodes along the three directions of X, Y and Z. The main station equipment summarizes and calculates the resistivity, and works through the substation nodes. Status inspection and acquisition status inspection screen out faulty nodes to ensure data accuracy.

Benefits of technology

Accurate prediction and real-time monitoring of geological disasters are achieved, and avant-garde data can be collected in a timely manner, predict stress peaks, and the accuracy and reliability of measurement results are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114355460B_ABST
    Figure CN114355460B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for measuring underground tensor resistivity, which belongs to the field of geological exploration. It has the following steps: 1. n substation nodes are arranged at intervals along the tunnel construction direction on the underground rock layer, and each substation node is respectively arranged with three transmitting electrodes and three collecting electrodes along the three directions of X, Y and Z; 2. The main station device sends a collection command to the substation device, the transmitting electrode of the substation node transmits a signal, the collecting electrode receives the signal and records the potential difference between the transmitting electrode and the collecting electrode, and then the substation device uploads the collected potential difference to the main station device; 3. The main station device summarizes the collected data and uploads it to the background device, and the background device calculates the resistivity according to the collected potential difference data between each node. The present invention can comprehensively measure the resistivity along the strike, inclination and vertical direction of the rock layer, improve the accuracy of the final measurement result, and thus accurately predict geological disasters.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of geological exploration, and more specifically, relates to a method for measuring underground tensor resistivity. Background Art

[0002] Research has shown that the process of coal and gas outbursts, rock bursts and other dynamic disasters from their conception, development to occurrence undergoes complex nonlinear processes such as stress transfer, coal and rock deformation and destruction, and fluid migration. The most significant physical property feature in this process is the regular spatiotemporal evolution of the electrical anisotropy of coal and rock masses. The macroscopic conductivity difference shown by water and gas in the cracks provides a physical basis for the identification of water-filled or gas-rich states in the cracks. Therefore, electrical detection can effectively predict some geological disasters.

[0003] Traditional underground electrical detection generally uses direct current method for measurement. The direct current method assumes that the earth is electrically isotropic, so the resistivity value is only measured in one direction each time. However, due to the heterogeneity of rock composition and structure, especially layered coal rocks and sedimentary minerals, the resistivity values ​​measured along the strike, dip and vertical directions of the rock formations are generally different, resulting in the results of measurements by direct current method often not being comprehensive and accurate enough. When conducting geological interpretation, it only observes the resistivity scalar, but does not specifically reflect the differences in geological structure. Therefore, direct current method measurements cannot objectively and comprehensively reflect the anisotropic characteristics and temporal and spatial evolution laws of the mined rock mass, which is not conducive to the precise positioning of electrical anomaly areas, and also misses the precious opportunity to provide precursor information for the "advanced prediction and advanced crisis resolution" of coal and rock dynamic disasters.

[0004] With the in-depth understanding of electrical anisotropy characteristics and the successful application of tensor measurement in many fields, tensor resistivity measurement has become a development trend. The tensor resistivity method can timely collect precursor data of the development of coal mine dynamic disasters, conduct real-time analysis, and predict stress peaks to achieve early warning, and timely release the reversible stress of dynamic disasters, and realize full-space real-time monitoring of the anisotropic characteristics of coal and rock masses.

[0005] After searching, a Chinese patent, a method for advanced detection of apparent resistivity in three directions in a tunnel (application publication date: September 11, 2020; application number: CN 202010694683.0). The patent discloses a method for advanced detection of apparent resistivity in three directions in a tunnel, which is suitable for the detection of hidden disaster geological bodies and their water-bearing properties in front of the tunnel during the construction of underground projects such as tunnels: first, an electrical survey line is designed in the tunnel, s power supply points and n measurement points are arranged in sequence on the survey line, and power supply electrodes and three-directional measurement electrode groups are constructed; the power supply cable and the receiving cable are connected to the electrical instrument to complete the data collection of the power supply current I of different power supply points and the potential differences ΔUx, ΔUy and ΔUz in three directions of the measurement points. Although the patent calculates the measurement electrodes in three directions of the tunnel and measures the potential differences in three directions, the three aspects of XYZ are not measured in pairs, and the full-space measurement of the tensor resistivity of nine potential differences is not achieved. The measurement results are not comprehensive and accurate, and errors may occur in the prediction of geological disasters.

[0006] After searching, the Chinese patent, coal rock forming experimental device and method for testing three-dimensional apparent resistivity changes (application publication date: August 25, 2020; application number: CN 202010489891.7). The patent discloses a coal rock forming experimental device and a method for testing three-dimensional apparent resistivity changes. The outer periphery of the forming mold of the coal rock forming experimental device is vertically fixed with at least two symmetrical columns, and a pressurizing mechanism is fixed above the columns. The water pump is connected to the interior of the forming mold through the upper water pipe and the lower water pipe. An air inlet pipe is opened on the side wall of the forming mold; there are three pairs of electrodes on the top surface of the cover plate of the forming mold connected to the corresponding apparent resistivity tester, and the electrode plates connected to each pair of electrodes are arranged in the horizontal, longitudinal and vertical directions according to the size of the coal rock sample. In the sample preparation process of this test method, three apparent resistivity testers are turned on for testing in turn, with an interval of less than 1 second. When the next apparent resistivity tester is turned on, the current apparent resistivity tester is turned off, and the test is cyclically tested and the data is recorded. This patent also arranges electrodes in three directions and measures the apparent resistivity through three apparent resistivity testers, but does not take into account the superposition effect of the three directions, does not implement two-by-two cross-measurements, and cannot cyclically transform the transmitting and collecting nodes and electrodes, resulting in unsatisfactory measurement accuracy, making it difficult to achieve online real-time monitoring and control of coal and rock formations, and possible errors in the prediction of geological disasters. Summary of the invention

[0007] 1. Problems to be solved

[0008] In view of the fact that the existing underground tensor resistivity measurement method is not comprehensive, it is difficult to ensure the accuracy and comprehensiveness of the final measurement results, and the prediction of geological disasters may have errors, the present invention provides an underground tensor resistivity measurement method, which can comprehensively measure the resistivity along the strike, dip and vertical direction of the rock formation, improves the accuracy of the final measurement results, and thus accurately predicts geological disasters.

[0009] 2. Technical solution

[0010] To solve the above problems, the present invention adopts the following technical solutions.

[0011] A method for measuring downhole tensor resistivity, the method comprising the following steps:

[0012] 1. n substation nodes are set at intervals along the tunnel construction direction on the underground rock layer, and each substation node is respectively set with three transmitting electrodes and three collecting electrodes along the three directions of X, Y and Z;

[0013] 2. The master station sends a collection command to the slave station. The transmitting electrode of the slave station transmits a signal, and the collecting electrode receives the signal and records the potential difference between the transmitting electrode and the collecting electrode. Then, the slave station uploads the collected potential difference to the master station.

[0014] 3. The master station equipment summarizes the collected data and uploads it to the background equipment, which calculates the resistivity based on the collected potential difference data between each node.

[0015] As a further improvement of the technical solution, it also includes substation node working status inspection, the specific process is as follows:

[0016] S1. Inspection queue classification: number the substation nodes along the tunnel construction direction and set the uninspected queue and inspected queue;

[0017] S2. Node status determination: inspect each substation node, add the inspected substation nodes to the inspected queue, and add the uninspected substation nodes to the uninspected queue; then conduct the next inspection, if a substation node in the uninspected queue is inspected, transfer the substation node to the inspected queue; after multiple inspections, list the substation nodes in the uninspected queue as faulty nodes, and list the substation nodes in the inspected queue as valid nodes.

[0018] As a further improvement of the technical solution, the substation node working status inspection further includes:

[0019] S3. Calculate the mapping relationship between the logical and physical addresses: pair the logical address of the substation node that has been inspected in the queue with the physical address, where the logical address is the sorting number of the substation node in the inspected queue, and the physical address is the number of the substation node in step S1.

[0020] As a further improvement of the technical solution, it also includes substation node collection status inspection, the specific process is as follows:

[0021] S1. Collection status queue classification: set three status queues: collection completed, not collected, and error. At the beginning, all substation nodes are added to the not collected queue;

[0022] S2, data collection: take out the substation nodes in the uncollected queue for data collection, add the substation nodes whose collected data are within the set range to the collection completed queue, and add the substation nodes whose collected data are not within the set range to the error queue;

[0023] S3, Error Node Inspection: Collect data from the substation nodes in the error queue. If the collected data is within the set range, add the substation node to the uncollected queue and collect again. If the recollected data is still within the set range, add the substation node to the collection completed queue.

[0024] S4. Repeat steps S1 to S3 to obtain the collection status of all substation nodes.

[0025] As a further improvement of the technical solution, in step 2, the specific collection process is as follows:

[0026] S1. Designate a substation node as a transmitting node;

[0027] S2, turning on a transmitting electrode in the transmitting node;

[0028] S3, taking the remaining substation nodes as collection nodes, and cyclically connecting the collection electrodes in each collection node to collect data;

[0029] S4, turn on the remaining transmitting electrodes in the transmitting node in sequence and repeat step S3;

[0030] S5. Designate all substation nodes as transmitting nodes in sequence and repeat steps S2 to S4 until all substation nodes are used as transmitting nodes.

[0031] As a further improvement of the technical solution, if there are substation nodes in the error queue, the substation nodes in the error queue are not used as transmitting nodes and collecting nodes during the collection process.

[0032] As a further improvement of the technical solution, the acquisition process further includes:

[0033] S6. Convert the format of the collected data into a protocol-defined data format that meets the communication transmission requirements.

[0034] As a further improvement of the technical solution, the step 2 also includes the processing of the collected data:

[0035] S1, inputting the data acquired by the collection electrode of each collection node in each collection process into the waveform generator respectively, and inputting the set DC level into the waveform generator to generate the potential difference waveform of the positive level, zero level and negative level of the set pulse width;

[0036] S2, setting the number of signal transmissions in one acquisition process to N, the generated waveform includes N cycles, each cycle includes a potential difference waveform of a positive level, a zero level, and a negative level;

[0037] S3. Collect 5-20 data points in the positive level waveform in each cycle and take the average value as the positive level measurement value HV i ;

[0038] S4. Collect 5-20 data in the negative level waveform in each cycle and take the average value as the negative level measurement value LV i ;

[0039] S5. Obtain HV within N cycles i The average value is taken as the positive level result value HV AVG , find the LV within N cycles i The average value of the negative level result value HV AVG ;

[0040] S6. Calculate the potential difference between the transmitting electrode and the collecting electrode as U = (|HV AVG |+|HL AVG |) / 2.

[0041] As a further improvement of the technical solution, in step 3, the tensor resistivity is calculated using the following formula:

[0042] E = U / d;

[0043] ρ = E / J;

[0044] Where E is the electric field intensity, d is the distance from the transmitting electrode to the collecting electrode, J is the current density, and ρ is the tensor resistivity.

[0045] As a further improvement of the technical solution, if the amount of substation node data collected by the master station device exceeds the set value, the data will be sub-packeted for transmission:

[0046]

[0047] Among them, TransData is the transmission volume, ALLDatas is the collected data, and K is the number of subpackets.

[0048] 3. Beneficial effects

[0049] Compared with the prior art, the present invention has the following beneficial effects:

[0050] (1) The present invention provides a method for measuring underground tensor resistivity, which can comprehensively measure the resistivity along the strike, dip and vertical direction of the rock formation, thereby improving the accuracy of the final measurement result, thereby accurately predicting and real-time monitoring geological disasters, and timely collecting precursor data of the development of geological disasters, real-time analysis, and predicting stress peaks to achieve early warning, and timely release the reversible stress of dynamic disasters;

[0051] (2) The present invention provides a method for measuring downhole tensor resistivity. By setting up substation node working status inspection and substation node acquisition status inspection, the faulty nodes and nodes with abnormal data acquisition can be effectively screened out, so that the faulty nodes and nodes with abnormal data acquisition can be excluded during actual data acquisition, and valid data can be retained to ensure the accuracy of the final calculation result. In addition, by matching the sequence number of the detected working substation node with the actual physical address number of the substation node, the staff can clearly grasp the calculation results corresponding to each substation node to avoid confusion.

[0052] (3) The present invention provides a method for measuring underground tensor resistivity. The collected data is used to generate a potential difference waveform through a waveform generator, and the average of the positive and negative levels is then calculated. The component potential difference between the transmitting electrode and the collecting electrode is obtained by calculation, which effectively improves the accuracy of the tensor resistivity finally calculated, thereby enabling accurate prediction and real-time monitoring of geological disasters. BRIEF DESCRIPTION OF THE DRAWINGS

[0053] Figure 1 The design principle of the transmitting and collecting electrodes of the tensor resistivity device of the present invention;

[0054] Figure 2 The electromagnetic wave waveform diagram representing the potential difference of the present invention;

[0055] Figure 3 It is a flow chart of the substation node working status inspection of the present invention;

[0056] Figure 4 A flow chart of the substation node acquisition status inspection of the present invention;

[0057] Figure 5 It is a flow chart of the substation potential difference acquisition process of the present invention;

[0058] Figure 6 This is the monitoring system architecture of the present invention. DETAILED DESCRIPTION

[0059] The present invention is further described below in conjunction with specific embodiments and drawings.

[0060] Example 1

[0061] A method for measuring underground tensor resistivity is used in underground mines, especially in coal mining. By measuring and calculating the tensor resistivity of each direction of the rock layer, geological disasters such as coal mine dynamic disasters can be predicted in time to ensure the normal progress of underground mining and the safety of personnel. The specific process is described in detail below.

[0062] The method adopts a complete set of tensor resistivity equipment, which mainly includes a master station device, a substation device, an industrial computer, and a matching communication interface and communication device. Among them, the master station device includes a power supply, a control chip, a CAN interface circuit, a W5500 chip Ethernet communication interface circuit and an RJ45 network port module. The substation device includes a power supply, a multi-channel transmitting power output, three-channel transmitting electrodes, three-channel collecting electrodes, a control chip ARM and a CAN interface circuit. The industrial computer has an industrial Ethernet and Internet interface, which is used to receive data transmitted by the master station device and control the operation of the master station device and the substation device.

[0063] like Figure 6 As shown, the method constructs an overall monitoring system for address disasters, controls the main station equipment and substation equipment through industrial computers, collects the component potential difference of each substation node, and uploads the collected data to the main station equipment for aggregation. The background equipment calculates the tensor resistivity based on the collected data, and the staff predicts the geological disasters based on the calculation results, realizing real-time monitoring of geological disasters such as coal mine power disasters. Specifically, the following steps are included:

[0064] 1. Set n substation nodes at intervals along the tunnel construction direction on the underground rock layer, and number each substation node in sequence. In this embodiment, 32 substation nodes are set. In general, the spacing between substation nodes is kept consistent as much as possible, and the specific number of substation nodes is set according to the tunnel length. Each substation node is equipped with a substation device, and three transmitting electrodes and three collecting electrodes are respectively set along the X, Y and Z directions. Specifically, the X, Y and Z directions are respectively along the strike, dip and vertical directions of the rock layer. Figure 1As shown in the figure, it is the working principle diagram of the substation node. Between two substation nodes, the three transmitting electrodes of one substation transmit signals respectively, and the three collecting electrodes of the other substation node receive signals respectively. Then, the three transmitting electrodes and the three collecting electrodes can measure the 9 component potential differences between the two substation nodes in different directions, namely {XX, YX, ZX}, {XY, YY, ZY}, {XZ, YZ, ZZ}.

[0065] For example, in a certain detection and collection, the node number of the substation as the transmitting node is 3, the node number of the substation as the collecting node is 12, and the collected component potential difference is:

[0066] {{7.9112361E-02,8.5602672E-02,8.3562645E-02},{6.4245701E-03,6.10997 85E-03,5.8294712E-03},{3.5230172E-03,3.0151256E-03,3.2260576E-03}}.

[0067] 2. The master station device sends a collection command to the substation device. The transmitting electrode of the substation node transmits a signal, and the collection electrode receives the signal and records the potential difference between the transmitting electrode and the collection electrode. Then, the substation device uploads the collected potential difference to the master station device.

[0068] Before the collection begins, it is necessary to inspect the working status of the substation nodes, that is, to determine whether the substation equipment of all substation nodes has any faults, such as Figure 3 As shown, the specific process is as follows:

[0069] S1. Inspection queue classification: number the substation nodes along the tunnel construction direction and set the unPollingQueue and pollingQueue queues.

[0070] S2, node status determination: inspect each substation node, add the inspected substation nodes to the inspected queue, and add the uninspected substation nodes to the uninspected queue; then conduct the next inspection, if the uninspected substation node is inspected, transfer the substation node to the inspected queue; after multiple inspections, list the uninspected substation nodes as faulty nodes, and list the inspected substation nodes as valid nodes. The number saved at this time is the physical address number of the substation node in S1.

[0071] For example, in this step of a certain inspection:

[0072] unPollingQueue = {3, 12}

[0073] pollingQueue={1,2,4,5,6,7,8,9,10,11,13,14,15,16,17,18,19,20,21,22,23,24,25,26,27,28,29,30,31,32}

[0074] S3, calculate the mapping relationship between the logical and physical addresses: pair the logical address and physical address of the substation node that has been inspected in the queue to form the corresponding relationship between the logical and physical addresses of all substation nodes, addrMapping<logical address, physical address>. The logical address is the sequence number of the substation node in the inspected queue, and the physical address is the number of the substation node in step S1.

[0075] addrMapping={<1,1>,<2,4>,<3,5>,<4,6>,<5,7>,<6,8>,<7,9>,<8,10>,<9,11>,<10,13>,<11,14>,<12,15>,<13,16>,<14,17>,<15,18>,<1 6,19>,<17,20>,<18,21>,<19,22>,<20,23>,<21,24>,<22,25>,<23,2 6>,<24,27>,<25,28>,<26,29>,<27,30>,<28,31>,<29,32>,<30,33>}.

[0076] That is, during this inspection, the substation devices with physical address numbers 3 and 12 failed.

[0077] Then, if Figure 4 As shown, the collection status of the working substation nodes is inspected to determine whether there is any abnormality in the collection process. The inspection process is as follows:

[0078] S1. Classification of collection status queues: set three status queues: finishedQueue, unFinishedQueue and errorQueue. At the beginning, all substation nodes are added to the unfinished queue. During a certain inspection process, the substation node with physical address number 1 is used as the transmitting node.

[0079] Then unFinishedQueue 开始 ={2,4,5,6,7,8,9,10,11,13,14,15,16,17,18,19,20,21,22,23,24,25,26,27,28,29,30,31,32}

[0080] S2. Data collection: Take out the substation nodes in the uncollected queue for data collection, add the substation nodes whose collected data are within the set range to the collection completed queue, and add the substation nodes whose collected data are not within the set range to the error queue.

[0081] S3. Error node inspection: collect data from the substation nodes in the error queue. If the collected data is within the set range, the substation node is added to the uncollected queue and collected again. If the recollected data is still within the set range, the substation node is added to the collection completed queue.

[0082] S4, repeat steps S1 to S3 to obtain the collection status of all substation nodes. The number of repetitions of this inspection is 6, and finally the following is obtained:

[0083] unFinishedQueue 结束 ={20}

[0084] finishedQueue={2,4,5,6,7,8,9,10,11,13,14,15,16,17,18,19,21,22,23,24,25,26,27,28,29,30,31,32}

[0085] errorQueue = {}

[0086] That is, the substation node with physical address number 20 still does not meet the requirements after 6 polls, so it is set as an unfinished node. The data will still be uploaded to the industrial computer. Further analysis of the reasons may include unstable operation, undervoltage, poor grounding, etc.

[0087] By setting up substation node working status inspection and substation node collection status inspection, it is possible to effectively screen out faulty nodes and nodes with abnormal data collection, thereby eliminating faulty nodes during actual data collection and excluding nodes with abnormal data collection during calculation, retaining valid data and ensuring the accuracy of the final calculation results. In addition, by matching the sequence number of the detected working substation node with the actual physical address number of the substation node, the staff can clearly grasp the calculation results corresponding to each substation node to avoid confusion.

[0088] like Figure 5 As shown in the figure, the specific collection process is as follows:

[0089] S1. Designate a substation node as the transmitting node.

[0090] S2. Turn on one transmitting electrode in the transmitting node.

[0091] S3. Use the remaining substation nodes as collection nodes, and cyclically connect the collection electrodes in each collection node to collect data.

[0092] S4. Turn on the remaining transmitting electrodes in the transmitting node in sequence and repeat step S3.

[0093] S5. Designate all substation nodes as transmitting nodes in sequence and repeat steps S2 to S4 until all substation nodes are used as transmitting nodes.

[0094] S6. Convert the format of the collected data into a protocol-defined data format that meets the communication transmission requirements.

[0095] It should be noted that if there are substation nodes in the error queue, the substation nodes in the error queue will not be used as transmitting nodes and collecting nodes during the collection process.

[0096] To give a specific example, one substation node is selected from the 32 substation nodes as the transmitting node i, and one transmitting electrode in the transmitting node i is connected as the transmitting electrode h for this time. Then the remaining substation nodes are sequentially used as the collecting nodes j, and the three collecting electrodes in the collecting node j are sequentially connected as the collecting electrodes k for this time. When all the substation nodes except i are used as collecting nodes, and the collecting electrodes of these substation nodes have collected the potential difference data, the transmitting electrode h is cyclically switched in i and the collecting steps of the remaining substation nodes are repeated until the three transmitting electrodes have completed a signal transmission. Then the substation nodes are switched and the above steps are repeated until all the substation nodes are used as the transmitting nodes once, and a complete data collection process is completed.

[0097] It should be noted that not every acquisition process must be complete. It is also possible to collect the potential difference data of certain substation nodes separately. Therefore, there are many situations in the acquisition process as follows:

[0098] Case 1: When not specified, it is in automatic mode, i, h, j, k are collected in a full cycle, which is a complete collection process.

[0099] Case 2: When the transmitting node i is specified, h, j, and k are collected in a full cycle.

[0100] Case 3: When the transmitting node i and the transmitting electrode h are specified, j and k are fully collected in a cycle.

[0101] Case 4: When the transmitting node i and the transmitting electrode h, and the collecting node j are specified, k is collected in a full cycle.

[0102] Case 5: When the transmitting node i and the transmitting electrode h, and the collecting node j and the collecting electrode k are specified, only the component potential difference between the transmitting electrode h and the collecting electrode k is collected.

[0103] In order to improve the accuracy of the tensor resistivity finally calculated, so as to accurately predict and monitor geological disasters in real time, this embodiment also includes a process for processing the collected data, such as Figure 2 As shown, the specific process is as follows:

[0104] S1. Input the data acquired by the collection electrode of each collection node in each collection process into the waveform generator respectively, and input the set DC level into the waveform generator to generate the potential difference waveform of the positive level, zero level and negative level of the set pulse width.

[0105] S2. Set the number of signal transmissions in one acquisition process to N, then the generated waveform includes N cycles, and each cycle includes a potential difference waveform of a positive level, a zero level, and a negative level.

[0106] S3. Collect 5-20 data points in the positive level waveform in each cycle and take the average value as the positive level measurement value HV i .

[0107] S4. Collect 5-20 data in the negative level waveform in each cycle and take the average value as the negative level measurement value LV i .

[0108] It should be noted that the positive and negative level pulses within the period T respectively include three time stages: start time, measurement time, and end time. The data within the measurement time is generally more accurate. Therefore, the data taken in steps S3 and S4 are the data under the measurement time.

[0109] S5. Obtain HV within N cycles i The average value is taken as the positive level result value HV AVG , find the LV within N cycles i The average value of the negative level result value HV AVG .

[0110] S6. Calculate the potential difference between the transmitting electrode and the collecting electrode as U = (|HV AVG |+|HL AVG |) / 2.

[0111] Finally, the tensor resistivity was calculated using the following formula;

[0112] E = U / d;

[0113] ρ = E / J;

[0114] Where E is the electric field intensity, d is the distance from the transmitting electrode to the collecting electrode, J is the current density, and ρ is the tensor resistivity.

[0115] It is worth mentioning that if the amount of substation node data collected by the master station device exceeds the set value, the data needs to be transmitted in packets, otherwise packet loss will occur, resulting in inaccurate final calculation results.

[0116]

[0117] Among them, TransData is the transmission volume at one time, ALLDatas is the collected data, K is the number of subpackets, and the calculation result is not an integer, so take a larger integer value.

[0118] For example, the data ALLDatas collected in a certain detection is 720 bytes, and the transmission amount TransData is 512 bytes, then K=|720 / 512|=2.

[0119] To sum up, the method for measuring underground tensor resistivity in the present embodiment can comprehensively measure the resistivity along the strike, dip and vertical direction of the rock formation, thereby improving the accuracy of the final measurement results, thereby accurately predicting geological disasters, and can timely collect precursor data of the gestation and development of geological disasters, analyze in real time, and predict stress peaks to achieve early warning and timely release the reversible stress of dynamic disasters.

[0120] The examples described in the present invention are merely descriptions of the preferred implementation modes of the present invention, and are not intended to limit the concept and scope of the present invention. Without departing from the design concept of the present invention, various modifications and improvements made to the technical solutions of the present invention by engineers and technicians in this field should all fall within the protection scope of the present invention.

Claims

1. A method for measuring downhole tensor resistivity, Features: The method comprises the following steps:

1. n substation nodes are set at intervals along the tunnel construction direction on the underground rock layer, and each substation node is respectively set with three transmitting electrodes and three collecting electrodes along the three directions of X, Y and Z; 2. The master station device sends a collection command to the substation device. The transmitting electrode of the substation node transmits a signal, and the collecting electrode receives the signal and records the potential difference between the transmitting electrode and the collecting electrode. Then, the substation device uploads the collected potential difference to the master station device. Between two substation nodes, the three transmitting electrodes of one substation transmit signals respectively, and the three collecting electrodes of the other substation node receive signals respectively. Then, the three transmitting electrodes and the three collecting electrodes can measure the 9 component potential differences between the two substation nodes in different directions.

3. The master station device summarizes the collected data and uploads it to the background device, which calculates the resistivity based on the collected potential difference data between each node; The step 2 also includes the process of processing the collected data: S1, inputting the data acquired by the collection electrode of each collection node in each collection process into the waveform generator respectively, and inputting the set DC level into the waveform generator to generate the potential difference waveform of the positive level, zero level and negative level of the set pulse width; S2, setting the number of signal transmissions in one acquisition process to N, the generated waveform includes N cycles, each cycle includes a potential difference waveform of a positive level, a zero level, and a negative level; S3. Collect 5-20 data in the positive level waveform in each cycle and take the average value as the positive level measurement value HV i ; S4. Collect 5-20 data in the negative level waveform in each cycle and take the average value as the negative level measurement value LV i ; S5. Find the number of cycles within N HV i The average value of the positive level result is HV AVG , find the LV i The average value of the negative level result HV AVG ; S6. Calculate the component potential difference between the transmitting electrode and the collecting electrode: ; In the step 3, the tensor resistivity is calculated using the following formula: E = U / d; =E / J; Where, E is the electric field intensity, d is the distance from the transmitting electrode to the collecting electrode, J is the current density, is the tensor resistivity; If the amount of substation node data collected by the master device exceeds the set value, the data will be transmitted in packets: ; in, is the amount of transmission at one time, To collect data, K is the number of sub-packets.

2. A method for measuring downhole tensor resistivity according to claim 1, Features: It also includes substation node working status inspection, the specific process is as follows: S1. Inspection queue classification: number the substation nodes along the tunnel construction direction and set the uninspected queue and inspected queue; S2, node status determination: inspect each substation node, add the inspected substation nodes to the inspected queue, and add the uninspected substation nodes to the uninspected queue; then conduct the next inspection, if the inspected substation node is in the uninspected queue, transfer the substation node to the inspected queue; After multiple inspections, the substation nodes that have not been inspected in the queue are listed as faulty nodes, and the substation nodes that have been inspected in the queue are listed as valid nodes.

3. A method for measuring downhole tensor resistivity according to claim 2, Features: The substation node working status inspection also includes: S3. Calculate the mapping relationship between the logical and physical addresses: pair the logical address of the substation node that has been inspected in the queue with the physical address, where the logical address is the sorting number of the substation node in the inspected queue, and the physical address is the number of the substation node in step S1.

4. A method for measuring downhole tensor resistivity according to claim 2, Features: It also includes substation node collection status inspection, the specific process is as follows: S1. Collection status queue classification: set three status queues: collection completed, not collected, and error. At the beginning, all substation nodes are added to the not collected queue; S2, data collection: take out the substation nodes in the uncollected queue for data collection, add the substation nodes whose collected data are within the set range to the collection completed queue, and add the substation nodes whose collected data are not within the set range to the error queue; S3, Error Node Inspection: Collect data from the substation nodes in the error queue. If the collected data is within the set range, add the substation node to the uncollected queue and collect again. If the recollected data is still within the set range, add the substation node to the collection completed queue. S4. Repeat steps S1 to S3 to obtain the collection status of all substation nodes.

5. A method for measuring downhole tensor resistivity according to claim 4, Features: In step 2, the specific collection process is as follows: S1. Designate a substation node as a transmitting node; S2, turning on a transmitting electrode in the transmitting node; S3, taking the remaining substation nodes as collection nodes, and cyclically connecting the collection electrodes in each collection node to collect data; S4, turn on the remaining transmitting electrodes in the transmitting node in sequence and repeat step S3; S5. Designate all substation nodes as transmitting nodes in sequence and repeat steps S2 to S4 until all substation nodes are used as transmitting nodes.

6. A method for measuring downhole tensor resistivity according to claim 5, Features: If there are substation nodes in the error queue, the substation nodes in the error queue will not be used as transmitting nodes and collecting nodes during the collection process.

7. A method for measuring downhole tensor resistivity according to claim 6, Features: The collection process also includes: S6. Convert the format of the collected data into a protocol-defined data format that meets the communication transmission requirements.