A multi-agent joint dosing control method for water treatment system
Through the combination of multi-agent joint dosing control method and online experimental equipment, the dosage of reagents is dynamically adjusted, which solves the problems of lag and poor accuracy in reagent dosing control in water treatment, and achieves the balance between water quality and cost and the accuracy of intelligent control. promote.
Patent Information
- Application Number
- CN202311314857.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-12
- Publication Date
- 2024-09-24
- Estimated Expiration
- 2043-10-12
AI Technical Summary
During the water treatment process, the existing technology is difficult to dynamically adjust the dosage of chemicals, resulting in lag in control and poor accuracy. It is unable to effectively respond to changes in water quality and affects the balance between water quality and cost.
Using a multi-agent joint dosing control method, through online water quality monitoring and database analysis, dynamically adjust the dosage of chemicals based on multiple production data and test data of source water and submerged water, and conduct orthogonal design and simulation in conjunction with online experimental equipment Experiment and optimize the chemical ratio.
It achieves the dynamic determination of the optimal dosage of chemicals based on changes in source water quality, improves the balance between water quality and cost, and enhances the accuracy and speed of intelligent control.
Smart Images

Figure CN117130336B
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of adding turbid water purification treatment agents in the process of tap water intake and sewage drainage, and in particular to a multi-agent joint addition control method applied to a water treatment system. Background Art
[0002] my country is a water-scarce country, with per capita water resources only 1 / 4 of the world's per capita water resources. Moreover, the uneven distribution of water resources in my country in terms of time, space and region has aggravated the actual water shortage. Therefore, in recent years, my country's urban water resources have become more and more tense, and many cities are seriously short of water. At the same time, water pollution is becoming increasingly serious, so many factories have established their own tap water treatment plants to change the current situation of water shortage and pollution. Environmental protection issues are increasingly becoming one of the factors that affect and restrict the development of human society. Therefore, water treatment companies are needed to solve the water supply problem.
[0003] In the process of water treatment, it is often necessary to add chemicals to the tap water to be treated or various industrial discharge water and domestic sewage waiting to be treated. For enterprises in the water treatment industry, most of them rely on manual sampling and analysis of source water, rely on "experience" to control the amount of chemicals added, or directly add them in proportion. However, there are problems such as control lag and poor control accuracy, and inability to adjust control strategies according to sudden changes in water quality.
[0004] Therefore, there is an urgent need to provide a multi-agent combined dosing control method for water treatment systems, which can dynamically determine the optimal agent dosage, especially the ratio of multiple agents, according to changes in source water quality, so as to achieve a balance between water quality and cost. Summary of the invention
[0005] The technical problem to be solved by the present invention is to provide a multi-agent combined dosing control method applied to a water treatment system.
[0006] To solve the above problems, the technical solution adopted by the present invention is:
[0007] A multi-agent combined dosing control method applied to a water treatment system, the method comprising:
[0008] Step S1, using an online water quality monitor and a dosing acquisition device to collect multiple production data of the water treatment process; wherein each piece of the production data includes production source water information, production over-sinking water information and dosing data of each production agent; the production source water information includes: source water pH value, source water turbidity, source water COD, source water residual chlorine; the production over-sinking water information includes: over-sinking pH control value, over-sinking turbidity control value, over-sinking COD control value, over-sinking residual chlorine control value, and over-sinking chromaticity value;
[0009] Step S2, receiving a plurality of test data sent by the online experimental equipment, each of which is obtained based on the initial production source water information and the preset addition amount range of each production agent;
[0010] Step S3, saving the plurality of production data and the plurality of test data into a database;
[0011] Step S4, after obtaining the current production source water information and the current production sink water information, adjust the dosage of each agent based on the current production source water information and the current production sink water information, as well as the multiple production data and the multiple test data in the database.
[0012] As an implementation mode of the invention, after determining that the number of data strips in the database reaches a first preset number threshold but does not reach a second preset number threshold, step four includes:
[0013] Step S401, after obtaining the current production source water information and the current production sink water information, obtain the corresponding parameter difference between the current production source water information and the current production sink water information, and obtain the adjustment value of each reagent dosage based on each parameter difference;
[0014] Step S402: save the current production source water information, the current production sink water information and the adjustment value of each reagent dosage into the database as a new production data.
[0015] As an embodiment of the invention, in step S401, the method of obtaining the dosage adjustment value of each agent based on the difference of each parameter includes:
[0016] Step S4011: for any parameter difference, search the database for an approximate value corresponding to the parameter difference, and when at least one approximate value is found, take the average value of the drug dosage parameters corresponding to all the approximate values as the drug dosage adjustment value; or
[0017] Step S4012: When the approximate value cannot be found, the corresponding reagent addition amount is searched only according to the current production source water information, and after the search, the reagent addition amount adjustment value is obtained according to a preset formula.
[0018] As an implementation mode of the invention, when it is determined that the number of data strips in the database reaches a second preset number threshold, the step four includes:
[0019] Step S403, after obtaining the current production source water information and the current production sink water information, obtain the corresponding parameter difference in the current production source water information and the current production sink water information, search the database for the approximate value corresponding to each parameter difference, and use the amount of reagent added corresponding to the approximate value as the reagent dosage adjustment value.
[0020] As an embodiment of the invention, the parameter difference includes: a first parameter difference between the source water pH value and the over-sedimentation pH control value, a second parameter difference between the source water turbidity and the over-sedimentation turbidity control value, a third parameter difference between the source water COD and the over-sedimentation COD control value, and a fourth parameter difference between the source water residual chlorine and the over-sedimentation residual chlorine control value;
[0021] The first parameter difference corresponds to CO2 agent, the second parameter difference corresponds to PAC agent, the third parameter difference corresponds to KMnO4 agent, and the fourth parameter difference corresponds to NaClO agent.
[0022] As an implementation mode of the invention, in step S4011:
[0023] For the first parameter difference, search for an approximate value that differs from the first parameter difference by ±0.1; for the second parameter difference, search for an approximate value that differs from the second parameter difference by ±0.2; for the third parameter difference, search for an approximate value that differs from the third parameter difference by ±10; for the fourth parameter difference, search for an approximate value that differs from the fourth parameter difference by ±0.1.
[0024] As an implementation mode of the invention, step 2 includes:
[0025] Step S201, sending the production source water information to an online test device;
[0026] Step S202, receiving a plurality of test data sent by the online test equipment, each of which is obtained after the online test equipment conducts a test based on the production source water information and a preset addition amount range of each production agent.
[0027] As an embodiment of the invention, the online test equipment generates test data in the following manner:
[0028] The online test equipment automatically performs orthogonal design based on the production source water information and the preset addition range of each production agent, and automatically conducts tests according to each orthogonal design data to generate test sinking information; and, after determining that the requirements are met, sends the test sinking information, its corresponding production source water information and orthogonal design data as one test data.
[0029] As an embodiment of the invention, the online experimental equipment comprises: a vortex reaction zone, a horizontal flow sedimentation zone, an inclined tube sedimentation zone and a detection zone;
[0030] The vortex reaction zone includes a first flow channel formed by a vortex-shaped flow guide plate, water is injected into the inner end of the first flow channel and water is discharged from the outer end, a plurality of baffles are arranged in the first flow channel along the water flow direction, a first flow guide hole is opened in the upper or lower part of the baffle, and the first flow guide holes on adjacent baffles are opened at opposite positions, and the upper part of the inner end of the first flow channel corresponds to the liquid outlet of the injection pipe;
[0031] The horizontal flow sedimentation area includes a box body whose one end is connected to the water outlet end of the first flow channel, and the other end of the box body is provided with an inclined tube sedimentation area, and the inclined tube sedimentation area includes an inclined tube sedimentation cavity, a second flow guide hole is opened at the lower part of the side wall of the inclined tube sedimentation cavity, and a plurality of inclined tubes are evenly arranged at the upper part of the inclined tube sedimentation cavity;
[0032] A detection area is provided outside the inclined tube sedimentation chamber, and the detection area includes a detection box fixedly installed with the inclined tube sedimentation chamber. The upper part of the side wall of the inclined tube sedimentation chamber is connected to the detection box through a third guide hole, and a detection device is provided at the detection box;
[0033] Mud discharge pipelines are arranged at the bottom of the vortex reaction zone, the advection sedimentation zone and the inclined tube sedimentation zone.
[0034] The beneficial effects of adopting the above technical solution are:
[0035] The multi-agent combined dosing control method for a water treatment system provided by the present invention can dynamically determine the optimal dosage of the agent, especially the ratio of the multi-agent, according to the change of the water quality of the source water, so as to achieve a balance between water quality and cost. In addition, after determining the dosage of the agent, the data will also be stored in the database, increasing the amount of data in the database, thereby improving the accuracy of the intelligent control.
[0036] In addition, the online experimental equipment provided by the present invention can simulate a "real-time simulation experiment" of adding multiple reagents through multiple dosing tubes. After the reagents and water enter the vortex reaction zone from the mixer, they move forward in a vortex manner, and turn upside down under the action of the partition and the first guide hole, which plays a role of full mixing; during precipitation, a combination of a horizontal flow precipitation zone and an inclined tube precipitation zone is adopted, and the S-shaped second flow channel and the vortex-shaped first flow channel in the vortex reaction zone realize the real simulation of production in the smallest possible space;
[0037] The PLC control device controls the dosage of the reagents and receives the detection data of the detection device, and performs data storage, processing and algorithm calculation, builds and optimizes the data model. The feedback control has high accuracy and fast speed. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 It is a flow chart of the present invention.
[0039] Figure 2 It is a structural schematic diagram of the present invention.
[0040] Figure 3 It is a structural schematic diagram from another angle of the present invention.
[0041] Figure 4 It is another perspective structural schematic diagram of the present invention.
[0042] Figure 5 It is a schematic diagram of the internal structure of the present invention.
[0043] Figure 6 It is a schematic diagram of the top structure of the present invention.
[0044] Figure 7 It is a structural schematic diagram of the partition in the present invention.
[0045] Figure 8 It is a structural schematic diagram of the mud discharge pipeline in the present invention.
[0046] Fig. 9 It is a structural schematic diagram of the liquid adding device in the present invention.
[0047] Among them: 100 first flow channel, 200 second flow channel, 1 guide plate, 2 partition, 3 first guide hole, 4 baffle, 5 box, 7 blocking plate, 8 second guide hole, 9 third guide hole, 10 inclined tube sedimentation chamber, 11 inclined tube, 12 detection box, 13 overflow port, 14 water inlet pipe, 15 metering pump, 16 connecting pipe, 1601 dosing pipe, 17 mixer, 18 injection pipe, 19 detection device, 20 PLC control device, 21 first mud suction branch pipeline, 22 second mud suction branch pipeline, 23 mud suction main pipeline, 24 mud discharge pump. DETAILED DESCRIPTION
[0048] In order to make the objectives, technical solutions and advantages of the present invention more clear, the present invention is clearly and completely described below in conjunction with specific embodiments.
[0049] The embodiment of the present invention provides a multi-agent joint addition control method applied to a water treatment system. The water treatment process currently used is: source water - adding CO2 to adjust pH - adding KMnO4 for pre-oxidation - adding NaClO for disinfection - adding flocculant PAC (polyaluminium chloride) - entering the reaction zone for reaction - entering the sedimentation zone, mud sediment sinks and is discharged, and clear water is discharged from the upper layer and enters the filtration link. The method provided by the present invention includes:
[0050] Step S1, using an online water quality monitor and a dosing amount acquisition device to collect multiple production data of the water treatment process.
[0051] Among them, each piece of production data includes production source water information, production sedimentation water information and dosing data of each production agent, and the dosing data of each production agent is obtained based on the production source water information and production sedimentation water information; the production source water information includes: source water pH value, source water turbidity (over-sedimentation turbidity of production water), source water COD (over-sedimentation COD of production water), source water residual chlorine (over-sedimentation residual chlorine value of production water); the production sedimentation water information includes: over-sedimentation pH control value, over-sedimentation turbidity control value, over-sedimentation COD control value, over-sedimentation residual chlorine control value, and over-sedimentation color value.
[0052] Online water quality monitors obtain production source water information and production sink water information, including: 2 sets of pH meters, 2 sets of COD Mn , 1 set of residual chlorine meter, 1 set of colorimeter, 2 sets of turbidity meters. Among them, when 2 sets are designed, one set is used to monitor the water quality of the front-end incoming water (production source water), and the other set is used to monitor the water quality of the production sedimentation water.
[0053] The dosing amount acquisition device acquires the dosing amount of each production agent, which is connected to the dosing pump. In this step, the dosing data of each production agent are all empirical values obtained manually based on the production source water information and the production sink water information. The empirical values are input through the human-computer interaction interface, and the system control computer sends instructions to the dosing pumps of each production agent for execution, as follows:
[0054] 1. When the pH value of the source water is lower than the over-settling pH control value for 5 consecutive minutes, the CO2 addition is suspended; when the pH value of the source water is higher than the over-settling pH control value for 5 consecutive minutes, the CO2 addition is started. Every 40 minutes, the CO2 addition parameters are adjusted according to the difference between the over-settling pH value of the produced water and the over-settling pH control value (input through the human-computer interaction interface), and the ratio is: pH difference 0.1 corresponds to CO2 addition value change ±600:3.
[0055] Among them, 600:3 is the flow unit, and the raw water flow is 600m 3 / h, the carbon dioxide flow rate is 3L / min. For example, the pH value changes from 8.31 to 8.41. If the CO2 dosage is 600:18 when the pH is 8.31, when the pH becomes 8.41, the CO2 dosage is changed to 600:21.
[0056] 2. Every 40 minutes, adjust the PAC dosing parameters according to the difference between the source water turbidity and the over-settlement turbidity control value (input through the human-computer interaction interface), the ratio is: turbidity difference 0.2 corresponds to PAC dosing value change ±1;
[0057] 3. Every 40 minutes, according to the difference between the source water COD and the over-sedimentation COD control value (input through the human-computer interaction interface), adjust the KMnO4 addition parameters. If the over-sedimentation chromaticity value does not exceed the standard, the adjustment ratio is: COD difference 10 corresponds to KMnO4 addition value change ±0.005; if the over-sedimentation chromaticity value exceeds the standard, KMnO4 will not be adjusted, but NaClO will be adjusted instead, and the ratio is: COD difference 10 corresponds to NaClO addition value change ±0.1.
[0058] 4. Every 40 minutes, adjust the NaClO addition parameters according to the difference between the residual chlorine in the source water and the residual chlorine control value (input through the human-computer interaction interface). The ratio is: the residual chlorine difference of 0.1 corresponds to the change of NaClO addition value ±0.2.
[0059] In this step, a complete data is as follows:
[0060]
[0061] Step S2: receiving a plurality of test data sent by the online test equipment.
[0062] Among them, each test data is obtained based on the initial production source water information and the pre-set addition range of each production agent.
[0063] This step includes:
[0064] Step S201, sending production source water information to online testing equipment;
[0065] Step S202, receiving a plurality of test data sent by the online test equipment, each of which is obtained after the online test equipment conducts a test based on the production source water information and a preset addition amount range of each production agent.
[0066] Among them, the way in which the online test equipment generates test data is as follows:
[0067] The online test equipment automatically performs orthogonal design based on the production source water information and the preset addition range of each production agent, and automatically conducts tests according to each orthogonal design data to generate tested sinking information; and, after determining that the requirements are met, sends the tested sinking information, its corresponding production source water information and orthogonal design data as one test data.
[0068] The online test equipment runs 24 hours a day, automatically performs orthogonal design on the four dosing agents (CO2, KMnO4, NaClO, PAC), automatically conducts experiments according to the design results, and stores the experimental data in the database system.
[0069] This system adopts L9 (3 4) Orthogonal experimental table, each experiment uses three levels and four factors. The experimental values start from low, and after the experiment, the values jump up. For example, the first experimental design is as follows:
[0070]
[0071]
[0072] After completing this group of orthogonal experiments, the next group of orthogonal experiments will be started. The design is as follows: the value of factor 4 (PAC) in this group of orthogonal experiment table 1 (factor and level value table) will be jumped to 4, 5, and 6, and the others will remain unchanged. And so on, multiple experiments will be carried out.
[0073] After all the values of factor 4 are taken through orthogonal experiment, the value of factor 3 is jumped to 1.3, 1.4, 1.5, and factor 4 returns to the minimum value of 4, 5, 6, and the others remain unchanged. And so on, multiple experiments are carried out.
[0074] After all the factors 3 have been selected through orthogonal experiments, the same process can be repeated until all the factors have been iterated.
[0075] Because the experimental results are closely related to the season, the data stored in the database include the experimental date. The results may be different for completely identical raw water parameters and dosing parameters. Therefore, after completing all factor level iterations, this orthogonal experiment will continue the experiment and enter the next round of iteration.
[0076] The experiment is completed once every hour, and then the parameter values of the four agents are jumped, re-valued, and then the orthogonal design is automatically performed to start the next pilot test. This is repeated, and the coverage experiment is performed within the allowable extreme value range of the four agents. The extreme value and jump point design of the four agents are shown in Table 4:
[0077]
[0078] The structure of the online testing equipment is described below.
[0079] like Figure 2-Figure 6 As shown, the online test equipment includes a vortex reaction zone, a horizontal flow sedimentation zone, an inclined tube sedimentation zone and a detection zone. The vortex reaction zone includes a first flow channel 100 formed by a vortex-shaped guide plate 1. A bottom plate is fixedly provided at the bottom of the guide plate 1. Water is injected into the inner end of the first flow channel 100 and water is discharged from the outer end. A plurality of partitions 2 are arranged in the first flow channel 100 along the water flow direction. A first guide hole 3 is opened at the upper or lower part of the partition 2, and the opening positions of the first guide holes 3 on adjacent partitions 2 are opposite to each other. In this embodiment, the first guide hole 3 is opened at the upper or lower end of the partition 2, and the upper part of the inner end of the first flow channel 100 corresponds to the liquid outlet of the injection pipe 18.
[0080] The horizontal flow sedimentation area includes a box body 5 connected to the water outlet end of the first flow channel 100 at one end, and an inclined tube sedimentation area is arranged at the other end of the box body 5. The inclined tube sedimentation area includes an inclined tube sedimentation chamber 10, and a second guide hole 8 is opened at the lower part of the side wall of the inclined tube sedimentation chamber 10. A plurality of inclined tubes 11 are evenly arranged at the upper part of the inclined tube sedimentation chamber 10, and the lower end of the inclined tube 11 is above the second guide hole 8, and the upper end of the inclined tube 11 is below the third guide hole 9. The plurality of inclined tubes 11 in the inclined tube sedimentation area are arranged together obliquely, and the water flows from bottom to top, and the silt will stick to the tube wall. When there is too much silt, it will fall to the bottom under the action of its own weight and be sucked away by the mud discharge pipeline;
[0081] A detection area is provided outside the oblique tube sedimentation chamber 10, and the detection area includes a detection box 12 fixedly installed with the oblique tube sedimentation chamber 10. The upper part of the side wall of the oblique tube sedimentation chamber 10 is connected to the detection box 12 through the third guide hole 9. A detection device 19 is provided at the detection box 12 for performing water quality detection on the supernatant on the upper part of the detection box 12. An overflow port 13 is provided at the upper part of the side wall of the detection box 12, so that the supernatant is discharged from the overflow port 13;
[0082] Mud discharge pipelines are arranged at the bottom of the vortex reaction zone, the advection sedimentation zone and the inclined tube sedimentation zone.
[0083] The source water flows into the online test equipment through the water inlet pipe 14, and a "real-time simulation experiment" of simulating the addition of multiple agents is performed through multiple dosing pipes 1601 (orthogonal design can be automatically performed to determine the dosage of each agent). After the agents and water enter the vortex reaction zone from the mixer 17, they move forward in a vortex manner, and are turned upside down by the action of the partition 2 and the first guide hole 3, which plays a role in sufficient mixing; during sedimentation, a combination of a horizontal flow sedimentation zone and an inclined tube sedimentation zone is adopted, and the S-shaped second flow channel 200 and the vortex-shaped first flow channel 100 in the vortex reaction zone realize a true simulation of production in the smallest possible space.
[0084] In addition, baffles 4 are arranged alternately on the front and rear inner walls of the box 5, and an S-shaped second flow channel 200 is formed between adjacent baffles 4 and between the free ends of the baffles 4 and the inner wall of the box 5. When the sediment in the water flows in the second flow channel 200, it will sink to the bottom under the action of its own weight. Figure 8 As shown, the mud discharge pipeline includes a first mud suction branch pipeline 21 arranged at the bottom of the first flow channel 100, a second mud suction branch pipeline 22 arranged between the bottoms of adjacent baffles 4 in the second flow channel 100, and a second mud suction branch pipeline 22 arranged at the bottom of the inclined tube sedimentation chamber 10. The first mud suction branch pipeline 21 and the second mud suction branch pipeline 22 are connected to the mud suction main pipeline 23, and the mud suction main pipeline 23 is connected to the mud discharge pump 24.
[0085] like Fig. 9As shown, the injection pipe 18 is connected to the mixer 17, and the mixer 17 is respectively connected to the water inlet pipe 14 and a plurality of dosing pipes 1601, and a metering pump 15 is provided on the water inlet pipe 14 and the dosing pipe 1601. Specifically, the mixer 17 is connected to the water inlet pipe 14 through a connecting pipe 16, and a plurality of dosing pipes 1601 are respectively connected to the connecting pipe 16, and the metering pump 15 is provided on the water inlet pipe 14 and the dosing pipe 1601.
[0086] The detection device 19 is a multi-parameter water quality online analyzer, which can detect the pH, turbidity and residual chlorine of the water quality in real time online.
[0087] like Figure 2 , Figure 6 and Figure 7 As shown, in this embodiment, the center lines of the partition plates 2 and the guide plates 1 are in the same plane, and the angle between adjacent partition plates 2 is 90°.
[0088] In this embodiment, a sealing plate 7 is fixedly provided between the outermost baffle 4 in the box body 5 and the inner wall of the box body 5, and an inclined tube sedimentation chamber 10 is formed between the outermost baffle 4, the sealing plate 7 and the box body 5, and the second guide hole 8 is opened at the lower end of the sealing plate 7.
[0089] There are 3 to 6 dosing pipes 1601. According to the preset dosing amount range of each production agent, an orthogonal design is automatically performed to determine the dosing amount of CO2 agent, PAC agent, KMnO4 agent and NaClO agent.
[0090] Of course, the online water quality monitor also includes a PLC control device 20, which is electrically connected to the sludge pump 24, the detection device 19 and each metering pump 15. The PLC control device 20 controls the addition of reagents and receives the detection data of the detection device 19, and performs data storage, processing and algorithm calculation to build and optimize the data model. After determining that the test sinking information meets the requirements, the test sinking information, its corresponding production source water information and orthogonal design data are sent as a test data, and its feedback control is high in accuracy and speed.
[0091] Step S3: save the multiple production data and multiple test data into a database.
[0092] In step 1, all data from source water to sinking water are stored in the database system as raw data accumulation (if the sinking water data is unqualified, the data will be discarded).
[0093] All experimental data in step 2 are stored in the database system (if the experimental results show that the data is unqualified, the data will be discarded).
[0094] Step S4, after obtaining the current production source water information and the current production sink water information, adjust the dosage of each agent based on the current production source water information and the current production sink water information, as well as multiple production data and multiple test data in the database.
[0095] Specifically, this step includes two cases:
[0096] Case 1: After determining that the number of data items in the database reaches a first preset number threshold but does not reach a second preset number threshold, the step includes:
[0097] Step S401, after obtaining the current production source water information and the current production sink water information, obtain the corresponding parameter difference between the current production source water information and the current production sink water information, and obtain the adjustment value of each reagent dosage based on each parameter difference;
[0098] This step includes:
[0099] Step S4011: for any parameter difference, search the database for the approximate value corresponding to the parameter difference, and when at least one approximate value is found, take the average value of the drug dosage parameters corresponding to all the approximate values as the drug dosage adjustment value; or
[0100] Step S4012: When no approximate value can be found, the corresponding reagent addition amount is searched only according to the current production source water information, and after the search, the reagent addition amount adjustment value is obtained according to the preset formula.
[0101] In the present invention, the parameter difference includes: a first parameter difference between the source water pH value and the over-precipitation pH control value, a second parameter difference between the source water turbidity and the over-precipitation turbidity control value, a third parameter difference between the source water COD and the over-precipitation COD control value, and a fourth parameter difference between the source water residual chlorine and the over-precipitation residual chlorine control value. To achieve adjustment, the first parameter difference corresponds to the CO2 agent, the second parameter difference corresponds to the PAC agent, the third parameter difference corresponds to the KMnO4 agent, and the fourth parameter difference corresponds to the NaClO agent.
[0102] For the first parameter difference, search for an approximate value that differs from the first parameter difference by ±0.1; for the second parameter difference, search for an approximate value that differs from the second parameter difference by ±0.2; for the third parameter difference, search for an approximate value that differs from the third parameter difference by ±10; for the fourth parameter difference, search for an approximate value that differs from the fourth parameter difference by ±0.1.
[0103] The steps are as follows:
[0104] 1. When the pH value of the source water is lower than the over-settling pH control value for 5 consecutive minutes, the CO2 addition is suspended; when the pH value of the source water is higher than the over-settling pH control value for 5 consecutive minutes, the CO2 addition is started. According to the first parameter difference, search the corresponding approximate value (±0.1) of the first parameter difference in the database system, and take the CO2 addition parameter in the data strip (if there are multiple records, take the average value) as the CO2 control parameter for this time;
[0105] If the search is unsuccessful, only search based on the production "source water pH value"; if the corresponding data in the database still cannot be searched, take the closest data to the "source water pH value" in the database, and take the CO2 addition parameter value ±30x in its data strip (x is the difference between the source water pH value and the source water pH value in the data strip) as the CO2 control parameter this time.
[0106] 2. According to the source water turbidity and over-sedimentation turbidity control values, search for the corresponding approximate value (±0.2) of the second parameter difference in the database system, and take the PAC dosing parameter in the data strip (if there are multiple records, take the average value) as the PAC control parameter for this time;
[0107] If the search is unsuccessful, only search based on the "source water turbidity value of production water"; if the corresponding data in the database still cannot be searched, take the closest data to the "source water turbidity value of production water" in the database, and take the PAC dosage parameter value ±0.5 x in its data strip (x is the difference between the source water turbidity and the source water turbidity in the data strip) as the PAC control parameter this time.
[0108] 3. According to the source water COD and over-settled COD control values, search for the corresponding approximate value (±10) of the third parameter difference in the database system, and take the KMnO4 addition parameter in the data strip (if there are multiple records, take the average value) as the KMnO4 control parameter for this time;
[0109] If the search is unsuccessful, only search based on the production "source water COD"; if the corresponding data in the database still cannot be searched, take the closest data of "source water COD" in the database, and take the KMnO4 addition parameter value ±0.0005 x in its data strip (x is the difference between the source water COD and the source water COD in the data strip) as the KMnO4 control parameter this time.
[0110] 4. According to the control values of residual chlorine in source water and residual chlorine in sedimentation, search for the corresponding approximate value (±0.1) of the fourth parameter difference in the database system, and take the NaClO addition parameter in the data strip (if there are multiple records, take the average value) as the NaClO control parameter for this time;
[0111] If the search is unsuccessful, take the closest data to "source water residual chlorine" in the database, and take the NaClO addition parameter value ±2 x (x is the difference between the source water residual chlorine and the source water residual chlorine in the data strip) in its data strip as the NaClO control parameter this time.
[0112] Step S402: save the current production source water information, the current production sink water information and the adjustment value of each reagent dosage into the database as a new production data.
[0113] All data from source water to sedimentation (pond) water are stored in the database system (if the data of sedimentation water is unqualified, the data will be discarded) and accumulated as original data.
[0114] Case 2: When it is determined that the number of data items in the database reaches a second preset number threshold, the step includes:
[0115] Step S403, after obtaining the current production source water information and the current production sink water information, obtain the corresponding parameter difference in the current production source water information and the current production sink water information, search the database for the approximate value corresponding to each parameter difference, and use the amount of reagent added corresponding to the approximate value as the reagent dosage adjustment value.
[0116] According to the parameter values of the production source water and the control values of the sedimentation parameters, the corresponding approximate values (pH±0.1, turbidity±0.2, COD±10, residual chlorine±0.1, date<not considering the year>±30 days) are searched in the database system, and the PAC addition parameters in the data strip are taken (if there are multiple records, take the average value) as the PAC control parameters for this time.
[0117] All data from source water to sedimentation (sedimentation pond) water are stored in the database system (if the sedimentation water data is unqualified, the data will be discarded) as raw data accumulation. This ensures that the big data in the database system becomes more and more abundant with production operation, making the intelligent control more and more accurate.
[0118] The multi-agent combined dosing control method for a water treatment system provided by the present invention can dynamically determine the optimal dosage of the agent, especially the ratio of the multi-agent, according to the change of the water quality of the source water, so as to achieve a balance between water quality and cost. In addition, after determining the dosage of the agent, the data will also be stored in the database, increasing the amount of data in the database, thereby improving the accuracy of the intelligent control.
[0119] In addition, the online experimental equipment provided by the present invention can simulate a "real-time simulation experiment" of adding multiple reagents through multiple dosing tubes. After the reagents and water enter the vortex reaction zone from the mixer, they move forward in a vortex manner, and turn upside down under the action of the partition and the first guide hole, which plays a role of full mixing; during precipitation, a combination of a horizontal flow precipitation zone and an inclined tube precipitation zone is adopted, and the S-shaped second flow channel and the vortex-shaped first flow channel in the vortex reaction zone realize the real simulation of production in the smallest possible space;
[0120] The PLC control device controls the dosage of the reagents and receives the detection data of the detection device, and performs data storage, processing and algorithm calculation, builds and optimizes the data model. The feedback control has high accuracy and fast speed.
Claims
1. A multi-agent joint dosing control method applied to a water treatment system, characterized in that: The method comprises: Step S1, using an online water quality monitor and a dosing amount acquisition device to collect multiple production data of the water treatment process; wherein each piece of the production data includes production source water information, production over-sinking water information and dosing data of each production agent; the production source water information includes: source water pH value, source water turbidity, source water COD, source water residual chlorine; the production over-sinking water information includes: over-sinking pH control value, over-sinking turbidity control value, over-sinking COD control value, over-sinking residual chlorine control value, and over-sinking chromaticity value; the dosing data of each production agent are all empirical values obtained manually based on the production source water information and the production over-sinking water information by experience, and the empirical values are input through the human-computer interaction interface, and the system control computer sends instructions to the dosing pumps of each production agent for execution; Step S2, receiving a plurality of test data sent by the online experimental equipment, each of which is obtained based on the initial production source water information and the preset addition amount range of each production agent; Step S3, saving the plurality of production data and the plurality of test data into a database; Step S4, after obtaining the current production source water information and the current production past water information, based on the current production source water information and the current production past water information, as well as the multiple production data and the multiple test data in the database, adjusting the dosage of each agent; Step S2 includes: Step S201, sending the production source water information to an online test device; Step S202, receiving a plurality of test data sent by the online test equipment, each of which is obtained by the online test equipment after testing based on the production source water information and the preset addition amount range of each production agent; The online experimental equipment comprises: a vortex reaction area, a horizontal flow sedimentation area, an inclined tube sedimentation area and a detection area; The vortex reaction zone includes a first flow channel formed by a vortex-shaped flow guide plate, water is injected into the inner end of the first flow channel and water is discharged from the outer end, a plurality of baffles are arranged in the first flow channel along the water flow direction, a first flow guide hole is opened in the upper or lower part of the baffle, and the first flow guide holes on adjacent baffles are opened at opposite positions, and the upper part of the inner end of the first flow channel corresponds to the liquid outlet of the injection pipe; The horizontal flow sedimentation area includes a box body whose one end is connected to the water outlet end of the first flow channel, baffles are arranged alternately on the front and rear inner walls of the box body, and an S-shaped second flow channel is formed between adjacent baffles and between the free ends of the baffles and the inner wall of the box body; a blocking plate is fixed between the outermost baffle in the box body and the inner wall of the box body, and the outermost baffle, the blocking plate and the box body form the inclined tube sedimentation chamber, and the second guide hole is opened at the lower part of the blocking plate; The other end of the box body is provided with an inclined tube sedimentation area, the inclined tube sedimentation area includes an inclined tube sedimentation cavity, a second guide hole is opened at the lower part of the side wall of the inclined tube sedimentation cavity, and a plurality of inclined tubes are evenly arranged at the upper part of the inclined tube sedimentation cavity; A detection area is provided outside the inclined tube sedimentation chamber, and the detection area includes a detection box fixedly installed with the inclined tube sedimentation chamber. The upper part of the side wall of the inclined tube sedimentation chamber is connected to the detection box through a third guide hole, and a detection device is provided at the detection box; A mud discharge pipeline is arranged at the bottom of the vortex reaction zone, the horizontal flow sedimentation zone and the inclined tube sedimentation zone; the mud discharge pipeline includes a first mud suction branch pipeline arranged at the bottom of the first flow channel, a second mud suction branch pipeline arranged between the bottoms of adjacent baffles in the second flow channel, and a second mud suction branch pipeline arranged at the bottom of the inclined tube sedimentation chamber, the first mud suction branch pipeline and the second mud suction branch pipeline are connected to the mud suction main pipeline, and the mud suction main pipeline is connected to the mud discharge pump.
2. A multi-agent combined dosing control method for a water treatment system according to claim 1, characterized in that: When it is determined that the number of data strips in the database reaches the first preset number threshold but does not reach the second preset number threshold, step S4 includes: Step S401, after obtaining the current production source water information and the current production sink water information, obtain the corresponding parameter difference between the current production source water information and the current production sink water information, and obtain the adjustment value of each reagent dosage based on each parameter difference; Step S402: save the current production source water information, the current production sink water information and the adjustment value of each reagent dosage into the database as a new production data.
3. A multi-agent combined dosing control method for a water treatment system according to claim 2, characterized in that: In step S401, the method of obtaining the dosage adjustment value of each agent based on the difference of each parameter includes: Step S4011: for any parameter difference, search the database for an approximate value corresponding to the parameter difference, and when at least one approximate value is found, take the average value of the drug dosage parameters corresponding to all the approximate values as the drug dosage adjustment value; or Step S4012: When the approximate value cannot be found, the corresponding reagent addition amount is searched only according to the current production source water information, and after the search, the reagent addition amount adjustment value is obtained according to a preset formula.
4. A multi-agent combined dosing control method for a water treatment system according to claim 2 or 3, characterized in that: When it is determined that the number of data strips in the database reaches a second preset number threshold, step S4 includes: Step S403, after obtaining the current production source water information and the current production sink water information, obtain the corresponding parameter difference in the current production source water information and the current production sink water information, search the database for the approximate value corresponding to each parameter difference, and use the amount of reagent added corresponding to the approximate value as the reagent dosage adjustment value.
5. A multi-agent combined dosing control method for a water treatment system according to any one of claim 2, characterized in that: The parameter differences include: a first parameter difference between the source water pH value and the over-sedimentation pH control value, a second parameter difference between the source water turbidity and the over-sedimentation turbidity control value, a third parameter difference between the source water COD and the over-sedimentation COD control value, and a fourth parameter difference between the source water residual chlorine and the over-sedimentation residual chlorine control value; The first parameter difference corresponds to CO2 agent, the second parameter difference corresponds to PAC agent, the third parameter difference corresponds to KMnO4 agent, and the fourth parameter difference corresponds to NaClO agent.
6. A multi-agent combined dosing control method for a water treatment system according to claim 5, characterized in that: In step S4011: For the first parameter difference, search for an approximate value that differs from the first parameter difference by ±0.1; for the second parameter difference, search for an approximate value that differs from the second parameter difference by ±0.2; for the third parameter difference, search for an approximate value that differs from the third parameter difference by ±10; for the fourth parameter difference, search for an approximate value that differs from the fourth parameter difference by ±0.
1.
7. A multi-agent combined dosing control method for a water treatment system according to claim 6, characterized in that: The online test equipment generates test data in the following way: The online test equipment automatically performs orthogonal design based on the production source water information and the preset addition amount range of each production agent, and automatically performs the test according to each orthogonal design data to generate the test sinking water information; And, after it is determined that the requirements are met, the test sinking water information, its corresponding production source water information and orthogonal design data are sent as a test data.