Steel pipe column construction method adopting first insertion method

The first-insert steel pipe column construction method uses wireless transmission technology and high-precision control systems to solve the problem of difficult to control the setting time of ultra-retarded concrete, achieve high-precision installation and one-time pouring of steel pipe columns, and improve construction efficiency and safety. , reducing costs.

CN118774110APending Publication Date: 2024-10-15BEIJING INT CONSTR GRP +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202410929452.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

In the cover-and-cut reverse method, the setting time of super-retarded concrete is difficult to control, resulting in the steel pipe column being unable to be inserted into the column base, increasing installation risks and construction difficulty, and affecting construction efficiency and cost.

Method used

The first-insert steel pipe column construction method is adopted, and wireless transmission technology and high-precision control systems are used to ensure the precise hoisting and position adjustment of the steel cage and steel pipe columns. The use of super-retarded concrete is eliminated, one-time pouring is achieved, and the construction process is simplified.

Benefits of technology

It improves the installation accuracy and construction efficiency of steel pipe columns, reduces costs, avoids installation risks caused by the difficulty in controlling the setting time of ultra-retarded concrete, and ensures the safety and quality of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774110A_ABST
    Figure CN118774110A_ABST
Patent Text Reader

Abstract

The invention relates to the field of high-precision installation of steel pipe columns, in particular to a first insertion method steel pipe column construction method, which comprises the following steps of: paying off and positioning, and embedding a pile casing; after positioning, pile hole forming is determined, and a bottom reaming drill bit is used for reaming; erecting a reinforcement cage and adjusting the position of the reinforcement cage; a reinforcement cage is placed in the pile hole; the verticality adjusting machine is hoisted and moved to the position above the pile hole, the verticality adjusting machine is moved to the measuring position, and the verticality adjusting machine is kept horizontal; hoisting the steel pipe column, hoisting the steel pipe column into a verticality adjusting machine, and adjusting the horizontal elevation and the verticality of the steel pipe column through a control system; a guide pipe is embedded in the pile hole, and pile foundation concrete is poured; and concrete is replaced, and pouring is continuously conducted in the steel pipe column. The method has the effect that the installation risk that the steel pipe column cannot be inserted into the column foundation due to the fact that the setting time of the super-retarding concrete is difficult to control is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of high-precision installation of steel pipe columns, and in particular to a pre-insertion steel pipe column construction method. Background Art

[0002] During the construction of the project, when encountering problems such as the foundation pit being too long, too wide, huge in size, too deep, poor in geological conditions, and prominent groundwater problems, in order to solve the problems, the cover-excavation reverse construction method is generally used. This method uses the structure as a support, has considerable rigidity, and greatly improves the safety of the ultra-deep foundation pit. After the cover-excavation top plate is completed, a strong internal support is formed to prevent the retaining structure from deforming into the foundation pit. The underground structure is carried out under the cover of the top plate, and the main structure is excavated layer by layer from top to bottom until the bottom plate.

[0003] The pile column includes the pile foundation and the steel pipe column. The important part of the reverse construction method is to implement the vertical pile column system to form a vertical support to bear the structure and construction load of the entire building and ensure that the differential settlement meets the structural safety requirements. According to the practice of this method, the vertical support system involves the quality of hole formation and the verticality control of pile column installation. The more construction layers, the stronger the required vertical bearing capacity, the greater the construction difficulty, and the higher the quality control requirements. The construction quality of the pile column directly affects the vertical bearing capacity and even affects whether the reverse construction method can be realized and the overall safety and stability of the structure.

[0004] There are a large number of actual engineering cases in China regarding the research on the installation process of steel pipe columns in the cover-excavation reverse construction method. The post-insertion installation process of steel pipe columns, which is mainly based on HPE, uses a full-casing full-rotation drilling rig to insert the steel pipe into the super-slow-setting concrete, and monitors the verticality of the steel pipe column during the process. It has a large market share. The post-insertion method uses a full-casing full-rotation drilling rig to insert the steel pipe into the super-slow-setting concrete. The initial and final setting of the super-slow-setting concrete are highly discrete, resulting in the initial setting of the concrete during the insertion of the steel pipe column. The steel pipe column cannot be installed, and secondary drilling and concrete pouring are required to reinstall the steel pipe column, but it still cannot make up for the defect of broken piles at the column foundation. Summary of the invention

[0005] In order to avoid the installation risk that the steel pipe column cannot be inserted into the column base due to the difficulty in controlling the solidification time of the super-slow setting concrete, the present application provides a pre-insertion steel pipe column construction method.

[0006] The present application provides a method for constructing a steel pipe column by inserting the steel pipe first, which adopts the following technical solution: A method for constructing a steel pipe column by inserting first, comprising the steps of: Laying out wires, positioning and burying casing; After positioning, confirm that the pile hole is formed and use a bottom expansion drill bit to expand the hole; Set up steel cage and adjust its position; Lower the steel cage into the pile hole; Lift the vertical adjustment machine to the top of the pile hole, move the vertical adjustment machine to the measurement position, and keep the vertical adjustment machine level; Lift the steel pipe column and place it in the vertical adjustment machine. Adjust the horizontal elevation and verticality of the steel pipe column through the control system. Bury the guide tube in the pile hole and pour the pile foundation concrete. Replace the concrete and continue pouring inside the steel pipe column.

[0007] By adopting the above technical scheme, the method is used during the construction process, the control system adopts wireless transmission technology, and high-precision installation operations are performed through wireless transmission, so that the steel cage and steel pipe column can be hoisted and installed through high-precision operations to ensure construction accuracy. When this method is used for pouring, it can be completed in one time, which is simple and convenient, improves construction efficiency, and saves the total construction period. The one-time pouring eliminates the use of super-slow-setting concrete, avoids the installation risk of the steel pipe column being unable to be inserted into the column base due to the difficulty in controlling the solidification time of the super-slow-setting concrete, improves work efficiency, and reduces costs.

[0008] Preferably, in the step, the vertical adjustment machine is hoisted and moved to the top of the pile hole, and the vertical adjustment machine is moved to the measurement position to keep the vertical adjustment machine horizontal, wherein the vertical adjustment machine includes a clamp and hydraulic legs; The step of moving the vertical adjustment machine to the measuring position comprises the steps of aligning the clamping center of the vertical adjustment machine with the center of the pile hole, and adjusting the hydraulic legs to control the vertical adjustment machine to be level.

[0009] By adopting the above technical solution, the vertical adjustment machine adjusts the position of the steel pipe column by adjusting the center position of the clamp. The hydraulic legs are first used to adjust the level of the vertical adjustment machine itself. Further, the horizontal elevation and verticality of the steel pipe column are adjusted by the hydraulic legs to improve the position accuracy of the steel pipe column.

[0010] Preferably, when the position of the steel pipe column is adjusted by a control system, the control system includes a wireless transmitter, a sensor, and an information center; The steel pipe column is controlled by the control system to determine the horizontal elevation and verticality of the steel pipe column, the position of the steel pipe column is determined by the sensor, and the position information is transmitted to the information center through a wireless transmitter. The information center adjusts the position of the steel pipe column after processing the position information data.

[0011] By adopting the above technical solution, the sensor is used to sense the position of the component to be hoisted, and transmits the position information to the information center through a wireless transmitter. After obtaining the information, the information center processes and calculates it, and can issue control commands to the equipment to accurately locate the position through multiple adjustments.

[0012] Preferably, when the steel pipe column is installed, the installation site is provided with the plumb adjustment machine, a high-precision inclination sensor is placed on the top of the steel pipe column, the clamp holds the steel pipe column tightly, the midline of the length direction of the steel pipe column is aligned with the center of the clamp, and the plumb adjustment machine adjusts the verticality of the steel pipe column, wherein the verticality of the steel pipe column is adjusted by a relative plumb adjustment method, and the relative plumb adjustment method includes initial zeroing and fine zeroing stages.

[0013] By adopting the above technical solution, after the control system scans the steel pipe column, it can confirm the three-dimensional position of the steel pipe column, adjust the front, back, left, and right directions of the steel pipe column, determine the verticality of the steel pipe column, ensure the installation accuracy of the steel pipe column, meet construction requirements, and achieve the optimal standard.

[0014] Preferably, the tool section is engraved with scales, and after the steel pipe column is horizontally positioned, the horizontal elevation of the steel pipe column is remeasured using a total station.

[0015] By adopting the above technical solution, the height position of the steel pipe column is confirmed by the scale on the tool section, and the height of the steel pipe column is quickly adjusted. Before determining the height position of the steel pipe column, it is necessary to calculate in advance the position of the steel pipe column and the required installation elevation of the top of the tool section according to the parameters given in the design, and then install the steel pipe column. During installation, the steel pipe column is fixed by a plumbing machine.

[0016] Preferably, the vertical adjustment machine adjusts the verticality of the steel pipe column, including: Detecting the verticality of the steel pipe column by means of the high-precision inclination sensor; Observe the verticality of the steel pipe column through the vertical adjustment machine and the digital display device of the high-precision sensor; After the vertical adjustment machine adjusts the verticality of the steel pipe column, the method further comprises: The verticality of the steel pipe column is remeasured from different angles by using the straight line scanning function of the total station.

[0017] By adopting the above technical solution, the straight line scanning function of the total station can re-measure the verticality of the steel pipe column from different angles. If the verticality of the steel pipe column does not meet the requirements, it will be adjusted immediately. Multi-angle confirmation can make the error of the steel pipe column smaller during installation and ensure the installation accuracy. The plumb adjustment machine and the high-precision inclination sensor monitor the horizontal inclination of the top of the steel pipe column to confirm whether the steel pipe column is in a vertical state within the error range. The total station scanning, plumb adjustment machine and high-precision inclination sensor work together to improve the installation accuracy of the steel pipe column.

[0018] Preferably, observing the verticality of the steel pipe column through the vertical adjustment machine and the digital display device of the high-precision sensor includes: A plurality of clamping cylinders are used to adjust the tool section in a plurality of directions, so as to regulate and control the verticality of the top of the tool section.

[0019] By adopting the above technical solution, the tool section can be adjusted in multiple directions through four clamping cylinders, specifically including six directions: up, down, left, right, front, and back.

[0020] Preferably, burying a conduit in the pile hole and pouring pile foundation concrete comprises the steps of: Removing sediment from the bottom of the pile hole to make the pile hole meet the construction requirements; burying a conduit in the pile hole; Pour the first type of underwater concrete until the designed elevation of the pile foundation top; The first type of underwater concrete overfilling is 0.8-1.0 meters.

[0021] By adopting the above technical solution, the first pouring is carried out through the conduit after cleaning. The over-pouring is to ensure the strength of the pile head and ensure that the bearing capacity of the pile foundation meets the requirements.

[0022] Preferably, the conduit is buried in the first underwater concrete at a height ranging from 2 to 6 meters.

[0023] By adopting the above technical solution, the underwater concrete can be poured with better effect and the occurrence of hollowing and the like can be avoided.

[0024] Preferably, the replacing of concrete and continuing pouring in the steel pipe column comprises: Replacing the first underwater concrete with a second underwater concrete of a higher grade; Casting inside the steel pipe column; During the pouring process, a chute machine and a filling machine are used between the steel pipe columns to evenly and continuously backfill the pile hole with crushed stone; Setting measuring ropes to monitor the concrete elevation and the height of the gravel surface between the piles; The second type of underwater concrete is overfilled by 0.8-1.0 m.

[0025] By adopting the above technical solution, during the concrete pouring process, in order to ensure that the height of the concrete outside the steel pipe column does not rise, a chute machine and a filler machine are used between the steel pipe columns to evenly and continuously backfill gravel into the hole to ensure that the pressure difference between the concrete inside the steel pipe column and the concrete outside the steel pipe column is consistent, and a measuring rope is used to monitor the concrete elevation and the height of the gravel surface of the steel pipe column. Over-pouring of concrete is to ensure that the bearing capacity of the steel pipe column can meet the demand.

[0026] In summary, the present application includes at least one of the following beneficial technical effects: 1. The control system adopts wireless transmission technology and performs high-precision installation operations through wireless transmission, so that the steel cage and steel pipe column can be hoisted and installed through high-precision operations to ensure construction accuracy. When this method is used for pouring, it can be completed in one time, which is simple and convenient, improves construction efficiency, and saves the total construction period. The one-time pouring eliminates the use of super-slow-setting concrete, avoids the installation risk of the steel pipe column being unable to be inserted into the column base due to the difficulty in controlling the solidification time of the super-slow-setting concrete, improves work efficiency, and reduces costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a flow chart of the steel pipe column construction method using the pre-insertion method in the embodiment of the present application. DETAILED DESCRIPTION

[0028] The following is combined with Figure 1 This application is described in further detail.

[0029] The present application embodiment discloses a method for constructing a steel pipe column by inserting the steel pipe first. Figure 1 The first insertion method of the steel pipe column construction method includes the following steps.

[0030] S1: Laying out wires, positioning and burying casing.

[0031] In step S1, the line positioning specifically includes the following steps: (1) Plane control measurement In accordance with the requirements of the specifications, planar encrypted control conductor points are laid out on site based on the qualified precision conductor points delivered by Party A's entrusted unit.

[0032] (2) The elevation control measurement is to arrange four leveling points on the basis of the verified qualified on-site leveling base points. All the leveling points form a leveling line for level II leveling measurement.

[0033] (3) Additional leveling points Due to the high requirements for working leveling control points, the additional leveling points adopt the fourth-class leveling measurement standard specified in the "Engineering Survey Standard" technical standard, adopt the combined measurement, use the level instrument to measure once, and the level rod is a double-sided rod.

[0034] S2: After positioning, make sure the pile hole is formed and use a bottom expansion drill to expand the hole.

[0035] S3: Set up the steel cage and adjust its position.

[0036] S4: Lower the steel cage into the pile hole.

[0037] S5: Hoist the vertical adjustment machine to the top of the pile hole, move the vertical adjustment machine to the measurement position, and keep the vertical adjustment machine level.

[0038] In the step, the vertical adjustment machine is hoisted and moved to the top of the pile hole, the vertical adjustment machine is moved to the measuring position, and the vertical adjustment machine is kept horizontal, and the vertical adjustment machine includes a clamp and a hydraulic leg; Moving the vertical adjustment machine to the measurement position includes the following steps: aligning the clamp center of the vertical adjustment machine with the center of the pile hole, and adjusting the hydraulic outriggers to control the level of the vertical adjustment machine; the vertical adjustment machine adjusts the position of the steel pipe column by adjusting the clamp center position, and the hydraulic outriggers are first used to adjust the level of the vertical adjustment machine itself, and further, the horizontal elevation of the steel pipe column is adjusted by the hydraulic outriggers to improve the position accuracy of the steel pipe column.

[0039] S6: Hoist the steel pipe column and place it into the vertical adjustment machine, and adjust the horizontal elevation and verticality of the steel pipe column through the control system.

[0040] When the steel pipe column is installed, the installation site is provided with the plumb adjustment machine, a high-precision inclination sensor is placed on the top of the steel pipe column, the clamp holds the steel pipe column tightly, the center line of the steel pipe column in the length direction is aligned with the center of the clamp, and the plumb adjustment machine adjusts the verticality of the steel pipe column, wherein the relative plumb adjustment method is used to adjust the verticality of the steel pipe column, and the relative plumb adjustment method includes initial zeroing and fine zeroing stages to ensure the installation accuracy of the steel pipe column, meet construction requirements, and achieve the optimal standard.

[0041] Before the steel pipe column is hoisted, the following steps are included: Assembling tool section and steel pipe column; The tool section and the steel pipe column are assembled using the on-site processing frame platform of the steel pipe column.

[0042] The tool section and the steel pipe column are connected by flanges; flange bolts are used on site to meet construction requirements. When connecting, the steel pipe column and the tool section are spliced ​​using a steel pipe column welding frame, and the frame must be installed stably; after the steel pipe column and the tool section are aligned, they must be inspected with a level ruler and caliper, and they can be bolted only when they meet the requirements; the bolts must be tightened diagonally when connected; after docking, the straightening recorder is installed on the upper flange of the tool section and fixed firmly; after assembly, reference lines are set on the side and top of the column. The reference lines are made of steel wire to control the verticality deviation of the splicing of the tool section and the steel pipe column to no more than 3mm, and measurement marks are affixed on the tool section for verticality and elevation control during the installation of the steel pipe column; after the bolt connection is tightened, the gap at the connection between the tool section and the steel pipe column is filled with sealant to prevent mud from entering the steel pipe column.

[0043] Adjust the position of the steel pipe column. When adjusting the position of the steel pipe column through the control system, the control system includes a wireless transmitter, a sensor, and an information center; the steel pipe column is controlled by the control system to determine the horizontal elevation and verticality of the steel pipe column, the position of the steel pipe column is determined by the sensor, and the position information is transmitted to the information center through the wireless transmitter. The information center adjusts the position of the steel pipe column after processing the position information data; the sensor is used to sense the position of the component to be hoisted, and transmits the position information to the information center through the wireless transmitter. After obtaining the information, the information center processes and calculates it, and can issue control commands to the equipment to accurately locate the position through multiple adjustments.

[0044] In an optional embodiment, the control system is adjusted by means of plane coordinates to quickly position the steel pipe column. In a preferred embodiment, the control system is positioned and adjusted by means of polar coordinates.

[0045] In an optional embodiment, the vertical adjustment machine is adjusted by means of plane coordinates to quickly position the steel cage; in a preferred embodiment, the vertical adjustment machine is positioned and adjusted by means of polar coordinates, and can quickly position the center coordinates to achieve millimeter-level control accuracy; preferably, the elevation and verticality of the steel pipe column are adjusted, with the elevation control level being at the millimeter level and the verticality control accuracy being 1 / 1000.

[0046] There are scales engraved on the tool section. After the steel pipe column is horizontally positioned, the horizontal elevation of the steel pipe column is remeasured through the scale section on the tool section, and the height of the steel pipe column is quickly adjusted. Before determining the height position of the steel pipe column, it is necessary to calculate in advance the position of the steel pipe column and the required installation elevation of the top of the tool section according to the parameters given in the design, and then install the steel pipe column. During installation, the steel pipe column is fixed by a plumbing machine.

[0047] Among them, the vertical adjustment machine adjusts the verticality of the steel pipe column, including: The verticality of the steel pipe column is detected by a high-precision inclination sensor; Observe the verticality of the steel pipe column through the digital display device of the vertical adjustment machine and the high-precision sensor; After the vertical adjustment machine adjusts the verticality of the steel pipe column, it also includes: The verticality of the steel pipe column is remeasured from different angles using the straight line scanning function of the total station.

[0048] The straight line scanning function of the total station can confirm the verticality of the steel pipe column from different angles. If the verticality of the steel pipe column does not meet the requirements, it will be adjusted immediately. Multi-angle confirmation can make the error of the steel pipe column smaller during installation and ensure the installation accuracy. The vertical adjustment machine and high-precision inclination sensor monitor the horizontal inclination of the top of the steel pipe column to confirm whether the steel pipe column is in a vertical state within the error range. The total station scanning and high-precision inclination sensor work together to improve the installation accuracy of the steel pipe column.

[0049] The actual verticality of the steel pipe column is observed through the vertical adjustment machine and the digital display device of the high-precision sensor, including: The tool section is adjusted in multiple directions by multiple clamping cylinders to adjust and control the verticality of the top of the tool section. The tool section is adjusted in multiple directions by four clamping cylinders, specifically including six directions of up, down, left, right, front and back.

[0050] S7: bury the conduit in the pile hole and pour the pile foundation concrete. The method comprises burying a conduit in the pile hole and pouring pile foundation concrete, comprising the following steps: Remove the sediment at the bottom of the pile hole to make the pile hole meet the construction requirements; burying a conduit in the pile hole; Pour the first type of underwater concrete until the designed elevation of the pile foundation top; Overfill the first type of underwater concrete by 0.8-1.0 m.

[0051] After cleaning, the first pouring is carried out through the conduit. Over-pouring is to ensure that the bearing capacity of the pile foundation can meet the requirements. Optionally, the first type of underwater concrete can be C35 underwater concrete.

[0052] In a preferred embodiment, the buried height of the conduit in the first underwater concrete is maintained in the range of 2-6 meters, so as to achieve a better effect during the pouring of the underwater concrete and avoid the occurrence of hollowing and the like.

[0053] Specifically, before pouring concrete, preparations must be made, the hole inspection must be passed, and it must be confirmed that the steel cage, steel pipe column, etc. have been installed before the concrete pouring work can begin. Before pouring, the pouring volume must be calculated in advance, and communication must be done with the mixing station to ensure an uninterrupted supply of concrete during the pouring period.

[0054] Optional, the conduit trial assembly and water tightness test, pouring concrete using Φ300mm thick wall 5mm conduit, before and after a period of use, in addition to the specification, quality and splicing structure of the conduit should be carefully checked, it is also necessary to do splicing, ball and water pressure test, the pressure during the water pressure test should not be less than 1.3 times the maximum pressure that the conduit may withstand when pouring concrete. Specifically, the test method includes: first fill the assembled conduit with 70% water, close both ends, weld the air pipe joint at one end, and input the calculated wind pressure. The conduit must be rolled several times, and it is qualified if it does not leak after 15 minutes. The ball should be unobstructed in the conduit. After meeting the requirements, the outer wall of the conduit is clearly marked and numbered section by section and the scale is indicated. The total number of conduits should be equipped with 20% to 30% of spare casings. In a preferred embodiment, the water pressure control value is 1.0MPa.

[0055] Specifically, the conduit can be pre-assembled in sections beside the drill hole, and then assembled section by section when it is hoisted. When assembling in sections, first check the conduit to avoid deformation and wear of the conduit. At the same time, clean the mortar and mud on the inner wall of the conduit. After the steel cage and steel pipe column are installed, they are inspected, and underwater concrete is poured after they are qualified. In an optional embodiment, pull-out piles, test piles, and anchor piles with a diameter of 1.0 meters are selected to use a conduit with a diameter of 250; reverse piles with a diameter of more than 2.0 meters are poured with a conduit with a diameter of 300mm; the minimum aperture at the node partition in the steel pipe column is 700mm; it can meet the smooth lowering and extraction of the 300 conduit.

[0056] Specifically, first use a crane to hang the conduit fixing platform to the position of the pile hole, and the center of the conduit fixing platform coincides with the pile. When hanging the conduit, make sure it is in the center of the hole, with a straight axis, and sink it steadily to prevent it from getting stuck on the partitions or steel skeletons in the steel pipe column and colliding with the hole wall. Mark the conduit with paint. After the conduit is installed, insert it into the bottom of the hole, then lift it 30cm away from the bottom of the hole to check the actual length of the conduit.

[0057] S8: Replace the concrete and continue pouring inside the steel pipe column.

[0058] Among them, replacement concrete is used between steel pipe columns, and pouring inside the steel pipe columns continues, including: Replace the first type of underwater concrete used between steel pipe columns with a second type of underwater concrete with a higher grade; Casting inside the steel pipe column; During the pouring process, chute machines and fillers are used between steel pipe columns to evenly and continuously backfill gravel into the pile holes between steel pipe columns; measuring ropes are set to monitor the concrete elevation between steel pipe columns and the height of the gravel surface between piles; Use the second type of underwater concrete to overfill the steel pipe columns by 0.8-1.0 meters.

[0059] During the pouring of concrete, in order to ensure that the height of the concrete outside the steel pipe column does not rise, a chute machine and a filler machine are used between the steel pipe columns to evenly and continuously backfill gravel into the hole to ensure that the pressure difference between the concrete inside the steel pipe column and the outside of the steel pipe column is constant, and a measuring rope is used to monitor the concrete elevation and the height of the gravel surface of the steel pipe column. Over-pouring concrete is also to ensure that the bearing capacity of the steel pipe column can meet the requirements. In an optional embodiment, the second underwater concrete can be selected as C50 or C60 underwater concrete.

[0060] The implementation principle of the embodiment of the present application is as follows: the control system adopts wireless transmission technology, and performs high-precision installation operations through wireless transmission, so that the steel cage and steel pipe column can be hoisted and installed through high-precision operations to ensure construction accuracy. When this method is used for pouring, it can be completed in one time, which is simple and convenient, improves construction efficiency, and saves the total construction period. The one-time pouring eliminates the use of super-slow-setting concrete, avoids the installation risk of the steel pipe column being unable to be inserted into the column base due to the difficulty in controlling the solidification time of the super-slow-setting concrete, improves work efficiency, and reduces costs.

[0061] In a specific application scenario, the specific application steps of the pre-insertion steel pipe column construction method are as follows.

[0062] Step S1.1.1 Line positioning Level the site, lay out the lines according to the dimensions measured on site, determine the horizontal elevation line, and draw a cross line to control the center position of the pile.

[0063] Step S1.1.2 Casing laying In step S1.1.2, after the drilling rig is in place, first drill a hole slightly larger than the diameter of the casing and 50 cm shallower than the casing. Then, the casing is hoisted into the hole and pressed into the hole using a rotary drilling rig. The center position of the casing is controlled according to the cross line. The center line of the casing should not be greater than 50 mm from the center line of the pile position, and the casing should be perpendicular to the surrounding area. Clay should be used to fill the area around the casing.

[0064] The length and burial depth of the casing should be determined according to the actual geological conditions on site. The burial depth of the casing should not be less than 4.0m to achieve the purpose of stabilizing the soil at the hole. To ensure the circulation of slurry, the diameter of the casing should be more than 200mm larger than the diameter of the cast-in-place pile; The top of the buried casing should be flush with the original ground to facilitate the fixing of the steel cage suspension bars on the concrete ground.

[0065] Step S1.1.3 Hole Formation This step specifically includes the following steps: a. After the casing is buried, a drilling rig is used to drill holes. During the drilling process, in order to ensure the stability of the trench hole, a mud pump is used to continuously add fresh mud into the hole. The mud plays the role of wall protection, slag carrying, machine cooling, and soil cutting lubrication; b. During drilling, the drilling speed is reasonably adjusted according to different geological conditions. Generally, the fastest speed does not exceed 10m / h, and the sand layer stratum is controlled at 3m / h; c. After the hole reaches the designed elevation, replace the bottom expansion drill bit to carry out the bottom expansion and hole forming operation.

[0066] Among them, during the bottom expansion construction, the operator first sets the bottom expansion parameters on the computer, and carries out the bottom expansion construction work under the command of the computer automatic management center, and timely monitors the hole expansion situation through the image monitoring system to ensure the quality of the bottom expansion hole; while the rotary bottom expansion drill bit is rotating, the inverted titanium alloy inlaid on the drill bit is evenly divided into two parts for cutting and excavating sand and soil, and horizontal mechanical hole expansion and advancement operations are implemented. The original soil produced by the bottom expansion operation is accommodated by the drill bit, and the drill bit is retracted to bring the original soil out of the ground.

[0067] When the hole depth reaches the depth specified in the drawing, use the sand drill bit to clean the hole for the first time to remove the sediment. When cleaning the hole, the water level in the hole should be kept 0.4m above the lower end of the casing and 1m above the groundwater level to prevent the hole from collapsing.

[0068] After the hole is cleaned, the quality inspector will check the hole quality. The hole depth is measured with a measuring rope. The hole diameter is checked by ultrasonic testing. The thickness of the sediment at the bottom of the hole is measured with a standard hydrological measuring rope. The verticality of the hole is checked with a total station and a drill rod before and during construction.

[0069] Step S1.1.4 Fabrication and hoisting of steel cage In this step, the steel cage is made on site, and the frame assembly platform is made of steel pipes with a diameter of 150. The spacing between steel pipes is 2.0 meters. The length of the processing platform is determined according to the actual situation on site.

[0070] The reinforcement ribs are made using a reinforcement rib mould. The reinforcement ribs are welded on one side with a lap length of 10d.

[0071] According to the design calculation, the cutting length of various types of steel bars is fixed by spot welding at the intersection of the main bar and the reinforcing bar. If the length of the steel cage exceeds the maximum lifting height of the crawler crane. The steel cage needs to be hoisted in sections, and a double-sleeve straight threaded first-level joint is used for connection at the hole, and the joint position spacing is 300-500mm. The straight thread connections in other parts are all greater than 35d.

[0072] The production of spiral reinforcement of steel cage includes the following steps: Fix the steel cage frame on the rolling cage machine and start installing the spiral reinforcement. The intersection of the spiral reinforcement and the main reinforcement is fixed by "plum blossom" spot welding. The top and tail of the spiral reinforcement should be horizontally wound for no less than one and a half turns, and bend 135 degrees to extend into the main reinforcement. After assembly, the steel cage is lifted off the rolling cage machine in time and placed flat on the pads.

[0073] Place grouting pipes, ultrasonic testing pipes and other testing materials according to the requirements of the drawings.

[0074] After the spiral reinforcement is completed, protective layer gaskets need to be welded on the main reinforcement of the steel cage to ensure that the thickness of the protective layer meets the requirements.

[0075] The auxiliary cage of the steel cage is installed to assist the installation of the steel cage and reinforce the acoustic detection pipe and grouting pipe. The diameter of the auxiliary cage is the same as that of the steel cage. It is welded to the main cage at the opening, and the single-sided welding length is 10d.

[0076] The top of the cage is welded with hanging rods according to the column top elevation and the ground elevation. The hanging rods are made of round steel and the top is set as a hanging ring. The number of hanging points is calculated according to the weight and length of the steel cage.

[0077] The steel cage is hoisted by double-clicking method. After the steel cage is hoisted to the specified elevation, the steel pipe column is kept stable and vertical by passing two pre-prepared channel steels through the hoisting rods set on the top of the steel cage.

[0078] Step S1.1.5: Steel pipe column splicing In this step, flanges are used to assemble the steel pipe column and the tool section before the steel pipe column is formally hoisted.

[0079] After the docking is completed, install the straightening recorder on the upper flange of the tool section and fix it firmly.

[0080] After the assembly is completed, reference lines are set on the side and top of the column. The reference lines are made of steel wire to control the verticality deviation of the tool column and the steel pipe column to be no more than 3mm. Measurement marks are affixed to the tool column to control the verticality and elevation during the installation of the steel pipe column.

[0081] After the bolt connection is tightened, the gap between the tool section and the steel pipe column is filled with sealant to prevent mud from entering the steel pipe column.

[0082] Step S1.1.6: Hoisting of steel pipe columns In this step, after the steel cage is lowered, the vertical adjustment machine is hoisted and moved above the pile hole, and the center of the vertical adjustment machine clamp is aligned with the center of the pile hole. The vertical adjustment machine equipment is kept horizontal by adjusting the hydraulic legs of the vertical adjustment machine. The steel pipe column is then hoisted into the vertical adjustment machine. According to the parameters given in the design, the required installation elevation position of the top of the steel pipe column and the tool section is calculated in advance. During the installation of the steel pipe column, the clamp of the vertical adjustment machine is used to hold the steel pipe column tightly. The verticality of the steel pipe column is measured from different angles through the straight line scanning function of the total station. The surveyors and operators work closely together to ensure the accuracy of the top section of the steel pipe column. A high-precision inclination sensor is placed on the top of the steel pipe column to monitor the verticality of the steel pipe column in real time. The actual verticality of the steel pipe column is observed through the digital display device of the vertical adjustment machine and the high-precision sensor.

[0083] During the process, the verticality of the top of the tool section can be controlled by adjusting the four clamping cylinders (up, down, left, right, front, and back). After the adjustment is completed, the cylinder is locked. The measurement team remeasures the positioning of the steel pipe column to ensure that the verticality of the top section of the steel pipe column is less than 1‰H. H is the height of the steel pipe column. There is a scale made in advance on the tool section. After the steel pipe column is positioned, the total station is used to accurately locate the height of the steel pipe column.

[0084] The verticality control of the steel pipe column adopts the relative vertical adjustment method, which is divided into the initial zero adjustment and fine zero adjustment stages; a. Fix the inclination sensor on the steel pipe column, hoist it into the air, and measure the verticality of the steel pipe column in different directions through the measuring instrument; b. When the verticality meets the requirements, set the inclination sensor to zero, open the equipment clamp, and lower the steel pipe column to near the design elevation. At this time, the inclination sensor with the tilt angle is adjusted to zero degrees using the vertical adjustment equipment, proving that the state in the air coincides with the state in the hole (that is, the verticality meets the design requirements).

[0085] Step S1.1.7 Catheter installation In this step, the appropriate conduit diameter is determined based on the pile diameter.

[0086] Before the duct is officially used, it is necessary to conduct a trial assembly and water tightness test. Fill the assembled duct with 70% water, seal both ends, weld the air pipe joint at one end, and input the calculated wind pressure. The duct must be rolled several times, and it is qualified if it does not leak after 15 minutes. The ball in the duct should be unobstructed. After meeting the requirements, the outer wall of the duct should be clearly marked and numbered section by section and indicate the size. The total number of ducts should be equipped with 20% to 30% of spare casings.

[0087] The conduit can be pre-assembled in sections next to the drill hole and then assembled section by section when it is hoisted.

[0088] After the conduit is assembled, a crane is used to lower the conduit fixing platform to the position of the pile hole, and the center of the conduit fixing platform coincides with the center of the pile.

[0089] When hanging the conduit, it should be positioned in the center of the hole with a straight axis and lowered steadily to prevent it from getting stuck on the node partitions or steel skeleton inside the steel pipe column and colliding with the hole wall.

[0090] Mark the conduit with paint. After the conduit is installed, insert it into the bottom of the hole, then lift it 30cm from the bottom of the hole to check the actual length of the conduit. The conduit should always be buried at a height of 2 to 6 meters in the concrete. Step S1.1.8: Underwater concrete pouring After the installation of the steel cage and steel pipe columns is completed, hidden engineering acceptance should be carried out, and underwater concrete should be poured immediately after passing the acceptance.

[0091] The one-time pouring of pile foundation and steel pipe column concrete is mainly divided into two stages: Phase 1: Before the formal pouring of concrete, the sediment at the bottom of the hole must be removed. When the conditions in the hole meet the requirements, the conduit can be buried and the pile foundation concrete (generally C35 underwater concrete) can be poured until the top of the pile foundation is at the designed elevation (the conduit is always buried in the concrete at a height of 2 to 6 meters), and over-poured by 0.8 to 1.0 meters.

[0092] The second stage: After the concrete is poured to the designed elevation of the top of the pile foundation and exceeds the tank appropriately, high-grade underwater concrete (generally C50 and C60 underwater concrete) is used to replace the C35 underwater concrete, and the steel pipe column is continued to be poured. In the process of pouring concrete, in order to ensure that the height of the concrete outside the steel pipe column does not rise, a chute machine and a filler machine are required to evenly and continuously backfill gravel into the hole between the piles and columns to ensure that the pressure difference between the concrete inside the column and the outside of the column is consistent, and a measuring rope is used to monitor the concrete elevation and the height of the gravel surface between the piles and columns. The measuring rope is placed on the backfilled gravel surface outside the steel pipe. If the measuring rope is found to rise, the pouring is stopped immediately and the gravel backfilling is started. In order to ensure that the bearing capacity of the steel pipe column meets the requirements, when pouring the concrete inside the steel pipe column to the designed elevation of the concrete surface of the steel pipe column, it is also necessary to overfill by 0.8 to 1.0 meters.

[0093] Through the steel pipe column construction method of the present application, when pouring is carried out using this method, the pouring can be completed in one time, which is simple and convenient, improves the construction efficiency, and saves the total construction period. The one-time pouring eliminates the use of super-slow-setting concrete, avoids the installation risk of the steel pipe column being unable to be inserted into the column base due to the difficulty in controlling the solidification time of the super-slow-setting concrete, improves work efficiency, and reduces costs.

[0094] The following diagrams provide a detailed description of the advantages of the first insertion method over the last insertion method.

[0095] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A method for constructing a steel pipe column by inserting first, characterized in that: Includes steps: Laying out wires, positioning and burying casing; After positioning, confirm that the pile hole is formed and use a bottom expansion drill bit to expand the hole; Set up steel cage and adjust its position; Lower the steel cage into the pile hole; Lift the vertical adjustment machine to the top of the pile hole, move the vertical adjustment machine to the measurement position, and keep the vertical adjustment machine level; Hoist the steel pipe column, place it in the vertical adjustment machine, and adjust the horizontal elevation and verticality of the steel pipe column through the control system; Bury the conduit in the pile hole and pour the pile foundation concrete; Replace the concrete and continue pouring inside the steel pipe column.

2. The method for constructing a steel pipe column by inserting first according to claim 1, characterized in that: In the steps, the vertical adjustment machine is hoisted and moved to the top of the pile hole, and the vertical adjustment machine is moved to the measuring position to keep the vertical adjustment machine horizontal, wherein the vertical adjustment machine includes a clamp and hydraulic legs; The step of moving the vertical adjustment machine to the measuring position comprises the steps of aligning the clamping center of the vertical adjustment machine with the center of the pile hole, and adjusting the hydraulic legs to control the vertical adjustment machine to be level.

3. The method for constructing a steel pipe column by inserting first according to claim 1, characterized in that: When the steel pipe column is hoisted and the position of the steel pipe column is adjusted by a control system, the control system includes a wireless transmitter, a sensor, and an information center; The steel pipe column is controlled by the control system to determine the horizontal elevation and verticality of the steel pipe column, the position of the steel pipe column is determined by the sensor, and the position information is transmitted to the information center through a wireless transmitter. The information center adjusts the position of the steel pipe column after processing the position information data.

4. The method for constructing a steel pipe column by inserting first according to claim 3, characterized in that: When the steel pipe column is installed, the installation site is provided with the plumb adjusting machine, a high-precision inclination sensor is placed on the top of the steel pipe column, the clamp holds the steel pipe column tightly, the center line of the steel pipe column in the length direction is aligned with the center of the clamp, and the plumb adjusting machine adjusts the verticality of the steel pipe column, wherein the verticality of the steel pipe column is adjusted by the relative plumb adjusting method, and the relative plumb adjusting method includes initial zeroing and fine zeroing stages.

5. The method for constructing a steel pipe column by inserting first according to claim 4 is characterized in that: The steel pipe column comprises a tool section on which scales are engraved. After the steel pipe column is horizontally positioned, the horizontal elevation of the steel pipe column is remeasured using a total station.

6. The method for constructing a steel pipe column by inserting first according to claim 4, characterized in that: The vertical adjustment machine adjusts the verticality of the steel pipe column, including: Detecting the verticality of the steel pipe column by means of the high-precision inclination sensor; Observe the verticality of the steel pipe column through the vertical adjustment machine and the digital display device of the high-precision sensor; After the vertical adjustment machine adjusts the verticality of the steel pipe column, the method further comprises: The verticality of the steel pipe column is remeasured from different angles by using the straight line scanning function of the total station.

7. The method for constructing a steel pipe column by inserting first according to claim 6, characterized in that: The verticality of the steel pipe column is observed through the vertical adjustment machine and the digital display device of the high-precision sensor, including: A plurality of clamping cylinders are used to adjust the tool section in a plurality of directions, so as to regulate and control the verticality of the top of the tool section.

8. The method for constructing a steel pipe column by inserting first according to claim 1, characterized in that: The method of burying a conduit in the pile hole and pouring pile foundation concrete comprises the following steps: Removing sediment from the bottom of the pile hole to make the pile hole meet the construction requirements; burying a conduit in the pile hole; Pour the first type of underwater concrete until the designed elevation of the pile foundation top; The first type of underwater concrete is overfilled by 0.8-1.0 meters.

9. The method for constructing a steel pipe column by inserting first according to claim 8, characterized in that: The conduit is buried in the first underwater concrete at a height ranging from 2 to 6 meters.

10. The method for constructing a steel pipe column by inserting first according to claim 8, characterized in that: The replacement of concrete and continued pouring in the steel pipe column include: Replacing the first underwater concrete with a second underwater concrete of a higher grade; Casting inside the steel pipe column; During the pouring process, a chute machine and a filling machine are used between the steel pipe columns to evenly and continuously backfill the pile hole with crushed stone; Setting measuring ropes to monitor the concrete elevation and the height of the gravel surface between the piles; The second type of underwater concrete is overfilled by 0.8-1.0 m.

Citation Information

Cited By

  • Intelligent positioning and pouring integrated platform for pile foundation reinforcement cage construction

    CN119442439A

  • An integrated platform for intelligent positioning and pouring of pile foundation reinforcement cage construction

    CN119442439B