Superimposed beam and connecting method thereof

By setting up uniform array of nails and through holes in a modular building and connecting them with concrete and grouting materials, the problem of insufficient connection stiffness and integrity between modules is solved, and reliable connection and coordinated stress between modules is achieved. Improves the overall performance and construction efficiency of the building.

CN118958588APending Publication Date: 2024-11-15UNIV OF SCI & TECH BEIJING

Patent Information

Application Number
CN202411185009.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The connection stiffness and integrity between modules in existing modular buildings are insufficient, especially the connection between horizontally adjacent module beams is not effectively considered, resulting in poor structural stability and seismic resistance.

Method used

By setting up uniform arrays of pegs and through holes on the ceiling beams and floor beams, and connecting them with concrete and grouting materials, the horizontal and vertical connection between the ceiling beams and the floor beams is achieved, increasing the stiffness and integrity between the modules.

Benefits of technology

Reliable connection between modules is achieved, the integrity, stiffness and stress performance of modular buildings are improved, the coordinated stress capacity between modules is enhanced, and the construction efficiency and overall performance are significantly improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958588A_ABST
    Figure CN118958588A_ABST
Patent Text Reader

Abstract

The invention provides a superposed beam which is characterized in that the superposed beam comprises ceiling beams and floor beams, every two adjacent ceiling beams are horizontally connected, every two adjacent floor beams are horizontally connected, and the ceiling beams and the floor beams are vertically connected; first studs are uniformly arranged on the inner wall of a lower flange of the ceiling beam, second studs are uniformly arranged on the top of the ceiling beam, and first through holes are uniformly formed in a web plate of the ceiling beam; third studs are uniformly arranged on the inner wall of an upper flange of the floor beam, second through holes are uniformly formed in a lower flange of the floor beam, and third through holes are uniformly formed in a web plate of the floor beam; horizontal and vertical connection of the combined modules can be achieved, cooperative stress of multiple beams can be achieved, the integrity and stress performance of a modular building are improved, the assembling efficiency is high, and construction is rapid and convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction engineering, in particular to a composite beam and a connection method thereof. Background Art

[0002] The core idea of ​​modular construction is to divide the building into several independent spatial units, namely modules, which are pre-manufactured in the factory and then assembled as a whole on the construction site. Since modular buildings are composed of multiple independent modular units, the stable connection between modules becomes the key to ensure its structural integrity and earthquake resistance.

[0003] In existing modular buildings, vertical connections between modules are mostly corner connections. Research results show that simply improving the bearing capacity and stiffness of corner connections between modules to strengthen the integrity of steel structure modular buildings is not ideal. In response to the problem of insufficient corner connection, Yang Chao proposed a new modular structure, that is, on the basis of corner connection, the ceiling beam and the floor beam are connected by bolts, but the structural stiffness and integrity are still insufficient. A plywood bolt connection method in the prior art connects adjacent independent double beams between upper and lower modules to form a composite beam, but does not consider the connection between horizontally adjacent module beams, and the stiffness of pure steel beams is still insufficient. Summary of the invention

[0004] In order to solve the technical problems existing in the prior art, an embodiment of the present invention provides a composite beam and a connection method thereof.

[0005] The technical solution is as follows:

[0006] A composite beam, comprising a ceiling beam and a floor beam, wherein two adjacent ceiling beams are horizontally connected, two adjacent floor beams are horizontally connected, and the ceiling beam is vertically connected to the floor beam;

[0007] A first stud is evenly arranged in an array on the inner wall of the lower flange of the ceiling beam and along the length direction of the ceiling beam, a second stud is evenly arranged in an array on the top of the ceiling beam and along the length direction of the ceiling beam, and a first through hole is evenly arranged in an array on the web of the ceiling beam and along the length direction of the ceiling beam;

[0008] A third bolt is evenly arranged in an array on the inner wall of the upper flange of the floor beam and along the length direction of the floor beam, a second through hole is evenly arranged in an array on the lower flange of the floor beam and along the length direction of the floor beam, and a third through hole is evenly arranged in an array on the web of the floor beam and along the length direction of the floor beam;

[0009] The length of the ceiling beam is equal to the length of the floor beam, the number of the second studs is equal to the number of the second through holes, and the position of each second stud corresponds to the position of each second through hole one by one.

[0010] Optionally, in the two horizontally connected ceiling beams, each of the first through holes of one ceiling beam is aligned with each of the first through holes of the other ceiling beam, and first horizontal connecting steel bars are provided in two adjacent and aligned first through holes; and the two ceiling beams are filled with concrete.

[0011] Optionally, in the two horizontally connected floor beams, each of the third through holes of one of the floor beams is aligned with each of the third through holes of the other floor beam, and second horizontal connecting steel bars are provided in two adjacent and aligned third through holes; and grouting material is filled in the two floor beams.

[0012] Optionally, in the vertically connected ceiling beams and floor beams, the floor beams are located above the ceiling beams, the lower flanges of the floor beams are aligned with the top surfaces of the ceiling beams, each of the second bolts passes through each of the second through holes respectively, concrete is set in the ceiling beams, grouting material is set in the floor beams, and grouting material is set between the ceiling beams and the floor beams.

[0013] Optionally, the ceiling beam is a C-beam, a U-beam or a rectangular beam, and the floor beam is a C-beam or a rectangular beam.

[0014] Optionally, when the ceiling beam is a U-shaped beam, the number of the first through holes respectively arranged on the webs on both sides of the ceiling beam is equal, and the position of each of the first through holes on the web on one side of the ceiling beam corresponds one to one with the position of each of the first through holes on the web on the other side of the ceiling beam;

[0015] The top ends of the webs on both sides of the ceiling beam are bent inward to obtain the top surface of the ceiling beam, and the bending angle is a right angle. Connecting plates are evenly arrayed on the top surfaces of the webs on both sides of the ceiling beam and along the length direction of the ceiling beam, and each of the second bolts is correspondingly arranged on each of the connecting plates.

[0016] Optionally, when the ceiling beam is a rectangular beam, the number of the first through holes respectively arranged on the webs on both sides of the ceiling beam is equal, and the position of each of the first through holes on the web on one side of the ceiling beam corresponds one to one with the position of each of the first through holes on the web on the other side of the ceiling beam;

[0017] A plurality of fourth through holes are arranged on the upper flange of the ceiling beam and along the length direction of the ceiling beam, and one second bolt is arranged between two adjacent fourth through holes.

[0018] Optionally, when the floor beam is a rectangular beam, the number of the third through holes respectively arranged on the webs on both sides of the floor beam is equal, and the position of each of the third through holes on the web on one side of the floor beam corresponds one-to-one to the position of each of the third through holes on the web on the other side of the floor beam.

[0019] A method for connecting a composite beam, comprising the composite beam, the method comprising:

[0020] S1. Prefabricate the ceiling beams and the floor beams;

[0021] S2: connecting the ceiling beams to the ceiling beams, connecting the floor beams to the floor beams, and / or connecting the ceiling beams to the floor beams;

[0022] The ceiling beams are poured with concrete, and the floor beams are poured with grouting material.

[0023] Optionally,

[0024] The step of connecting the ceiling beams to the ceiling beams, connecting the floor beams to the floor beams, and / or connecting the ceiling beams to the floor beams in S2 includes:

[0025] When the ceiling beams are horizontally connected to each other, each of the first through holes of one of the ceiling beams is aligned with each of the first through holes of another of the ceiling beams, and the first horizontal connecting steel bars are inserted into two adjacent and aligned first through holes;

[0026] When the floor beams are horizontally connected, each of the third through holes of one floor beam is aligned with each of the third through holes of another floor beam, and second horizontal connecting steel bars are arranged in two adjacent and aligned third through holes;

[0027] When the ceiling beam is vertically connected to the floor beam, the lower flange of the floor beam is aligned with the top surface of the ceiling beam, and each of the second bolts passes through each of the second through holes to connect the ceiling beam to the floor beam;

[0028] The pouring of concrete on the ceiling beams and pouring grouting material on the floor beams in S2 comprises:

[0029] When the ceiling beam is a C-shaped beam, concrete is filled into the ceiling beam from the side opening of the ceiling beam; when the ceiling beam is a U-shaped beam, concrete is filled into the ceiling beam from the top opening of the ceiling beam; when the ceiling beam is a rectangular beam, concrete is filled into the ceiling beam from the fourth through hole;

[0030] When the floor beam is a C-shaped beam, the grouting material is poured into the floor beam from the side opening of the floor beam, and after the grouting material fills the floor beam, it flows out from the second through hole to fill the gap between the ceiling beam and the floor beam;

[0031] When the floor beam is a rectangular beam, the grouting material is poured into the floor beam from the third through hole. After the grouting material fills up the floor beam, it flows out from the second through hole to fill up the gap between the ceiling beam and the floor beam.

[0032] The beneficial effects brought about by the technical solution provided by the embodiment of the present invention include at least:

[0033] The present invention can realize reliable horizontal and vertical connection of combined modules. The second bolt is welded to the upper flange of the module ceiling beam. After grouting, it is used together with the concrete tenon in the opening of the flange of the upper module floor beam to combine the upper and lower steel beams to realize the vertical connection between modules. The ceiling beam web and the floor beam web are both opened with holes to place horizontal connecting steel bars. The steel bars and the concrete tenon in the opening are used together to combine the left and right module beams to realize the horizontal connection of the left and right module beams, and finally realize the coordinated force of multiple beams to improve the integrity, rigidity and force performance of modular buildings, realize the horizontal connection and vertical connection between modules, and make adjacent modules bear force in a coordinated manner. This composite structural module composite beam has the advantages of high assembly efficiency, quick and convenient construction, good force performance, rigidity and integrity, and can freely connect modules vertically and horizontally. It has broad application prospects and is suitable for promotion and use in the field of modular buildings. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0035] Figure 1 A schematic diagram of the structure of horizontal connection of two ceiling beams in the composite beam provided by the present invention;

[0036] Figure 2 A schematic diagram of a ceiling beam horizontally connected in a composite beam provided by the present invention after pouring concrete;

[0037] Figure 3 A schematic diagram of the connection between the ceiling beam and the floor beam in the composite beam provided by the present invention;

[0038] Figure 4 A schematic diagram of horizontal connection of floor beams in a composite beam provided by the present invention;

[0039] Figure 5 It is a schematic diagram of a horizontally connected floor beam in a composite beam provided by the present invention after grouting material is poured into the floor beam;

[0040] Figure 6 A schematic diagram of the structure when the ceiling beam in the composite beam provided by the present invention is a C-shaped beam;

[0041] Figure 7 A schematic diagram of the structure when the ceiling beam in the composite beam provided by the present invention is a U-shaped beam;

[0042] Figure 8 A schematic diagram of the structure when the ceiling beam in the composite beam provided by the present invention is a rectangular beam;

[0043] Fig. 9 A schematic diagram of a C-shaped ceiling beam and a C-shaped floor beam in a composite beam provided by the present invention after being connected;

[0044] Fig.10 A schematic diagram of a U-shaped ceiling beam and a rectangular floor beam in a composite beam provided by the present invention after being connected;

[0045] Fig.11 This is a schematic diagram of the connection between the rectangular ceiling beam and the rectangular floor beam in the composite beam provided by the present invention.

[0046] Reference numerals:

[0047] 1. Floor beam; 11. Third bolt; 12. Second horizontal connecting steel bar; 13. Grouting material; 14. Second through hole; 15. Third through hole; 2. Ceiling beam; 21. First horizontal connecting steel bar; 22. Concrete; 23. Second bolt; 24. First bolt; 25. First through hole; 3. Connecting plate; 4. Fourth through hole. DETAILED DESCRIPTION

[0048] In order to make the purpose, technical solution and advantages of the embodiment of the present invention clearer, the technical solution of the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings of the embodiment of the present invention. Obviously, the described embodiment is a part of the embodiment of the present invention, not all of the embodiments. Based on the described embodiment of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0049] Unless otherwise defined, the technical terms or scientific terms used in the present invention should be understood by people with ordinary skills in the field to which the present invention belongs. The words "first", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. Similarly, words such as "one", "one" or "the" do not indicate a quantitative limitation, but indicate the existence of at least one. Words such as "include" or "comprise" mean that the elements or objects appearing before the word include the elements or objects listed after the word and their equivalents, without excluding other elements or objects. Words such as "connect" or "connected" are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect.

[0050] It should be noted that the terms "up", "down", "left", "right", "front", "back", etc. used in the present invention are only used to indicate relative position relationships. When the absolute position of the object being described changes, the relative position relationship may also change accordingly.

[0051] like Figure 1-Figure 11 As shown, this embodiment provides a composite beam, including a ceiling beam 2 and a floor beam 1, first bolts 24 are arranged in a uniform array on the inner wall of the lower flange of the ceiling beam 2 and along the length direction of the ceiling beam 2, second bolts 23 are arranged in a uniform array on the top of the ceiling beam 2 and along the length direction of the ceiling beam 2, and first through holes 25 are arranged in a uniform array on the web of the ceiling beam 2 and along the length direction of the ceiling beam 2.

[0052] Third bolts 11 are arranged in a uniform array on the inner wall of the upper flange of the floor beam 1 and along the length direction of the floor beam 1, second through holes 14 are arranged in a uniform array on the lower flange of the floor beam 1 and along the length direction of the floor beam 1, and third through holes 15 are arranged in a uniform array on the web of the floor beam 1 and along the length direction of the floor beam 1.

[0053] The length of the ceiling beam 2 is equal to that of the floor beam 1 , the number of the second bolts 23 is equal to the number of the second through holes 14 , and the position of each second bolt 23 corresponds to the position of each second through hole 14 .

[0054] The ceiling beam 2 is a C-beam, a U-beam or a rectangular beam, and the floor beam 1 is a C-beam or a rectangular beam; the C-beam, U-beam or a rectangular beam is a C-shaped steel, a U-shaped steel and a rectangular steel, which are prior arts and will not be described here. The difference between the C-beam and the U-beam is that the C-beam has a C-shaped cross section with an opening facing both sides, while the U-beam has an opening facing upwards, and the top ends of the two side walls of the U-beam are bent inwards at a right angle.

[0055] like Figure 1-Figure 6 , Fig. 9As shown, in the composite beam, two adjacent ceiling beams 2 are horizontally connected, two adjacent floor beams 1 are horizontally connected, and the ceiling beam 2 is vertically connected to the floor beam 1; in the two horizontally connected ceiling beams 2, each first through hole 25 of one ceiling beam 2 is aligned with each first through hole 25 of the other ceiling beam 2, and the first horizontal connecting steel bars 21 are arranged in the two adjacent and aligned first through holes 25; the two ceiling beams 2 are filled with concrete 22. In the two horizontally connected floor beams 1, each third through hole 15 of one floor beam 1 is aligned with each third through hole 15 of the other floor beam 1, and the second horizontal connecting steel bars 12 are arranged in the two adjacent and aligned third through holes 15; the two floor beams 1 are filled with grouting material 13. In the vertically connected ceiling beam 2 and floor beam 1, the floor beam 1 is located above the ceiling beam 2, the lower flange of the floor beam 1 is aligned with the top surface of the ceiling beam 2, each second bolt 23 passes through each second through hole 14 respectively, concrete 22 is set in the ceiling beam 2, grouting material 13 is set in the floor beam 1, and grouting material 13 is set between the ceiling beam 2 and the floor beam 1.

[0056] like Figure 7 , Fig.10 As shown, when the ceiling beam 2 is a U-shaped beam, the number of the first through holes 25 respectively arranged on the webs on both sides of the ceiling beam 2 is equal, and the position of each first through hole 25 on the web on one side of the ceiling beam 2 corresponds to the position of each first through hole 25 on the web on the other side of the ceiling beam 2;

[0057] The top ends of the webs on both sides of the ceiling beam 2 are bent inward to obtain the top surface of the ceiling beam 2, and the bending angle is a right angle. A plurality of connecting plates 3 are evenly arrayed on the top surfaces of the webs on both sides of the ceiling beam 2 and along the length direction of the ceiling beam 2, and each second bolt 23 is respectively arranged on each connecting plate 3.

[0058] like Figure 8 , Fig.11 As shown, when the ceiling beam 2 is a rectangular beam, the number of first through holes 25 respectively arranged on the webs on both sides of the ceiling beam 2 is equal, and the position of each first through hole 25 on the web on one side of the ceiling beam 2 corresponds to the position of each first through hole 25 on the web on the other side of the ceiling beam 2;

[0059] A plurality of fourth through holes 4 are arranged on the upper flange of the ceiling beam 2 and along the length direction of the ceiling beam 2 , and a second bolt 23 is arranged between two adjacent fourth through holes 4 .

[0060] When the floor beam 1 is a rectangular beam, the number of the third through holes 15 respectively arranged on the webs on both sides of the floor beam 1 is equal, and the position of each third through hole 15 on the web on one side of the floor beam 1 corresponds one to one to the position of each third through hole 15 on the web on the other side of the floor beam 1.

[0061] like Figure 1-Figure 11 A method for connecting composite beams is shown in FIG.

[0062] The method comprises:

[0063] S1, prefabricate ceiling beams 2 and floor beams 1 in the factory according to regulations;

[0064] S2: connecting the ceiling beams to the ceiling beams, connecting the floor beams to the floor beams, and / or connecting the ceiling beams to the floor beams;

[0065] When the ceiling beams 2 are horizontally connected to the ceiling beams 2, each first through hole 25 of one ceiling beam 2 is aligned with each first through hole 25 of another ceiling beam 2, and the first horizontal connecting steel bars 21 are inserted into two adjacent and aligned first through holes 25;

[0066] When the floor beams 1 are horizontally connected to each other, each third through hole 15 of one floor beam 1 is aligned with each third through hole 15 of another floor beam 1, and the second horizontal connecting steel bars 12 are arranged in two adjacent and aligned third through holes 15;

[0067] When the ceiling beam 2 is vertically connected to the floor beam 1, the lower flange of the floor beam 1 is aligned with the top surface of the ceiling beam 2, and each second bolt 23 passes through each second through hole 14 to connect the ceiling beam 2 to the floor beam 1;

[0068] The ceiling beams are poured with concrete, and the floor beams are poured with grouting material.

[0069] When the ceiling beam 2 is a C-shaped beam, concrete 22 is filled into the ceiling beam 2 from the side opening of the ceiling beam 2; when the ceiling beam 2 is a U-shaped beam, concrete 22 is filled into the ceiling beam 2 from the top opening of the ceiling beam 2; when the ceiling beam 2 is a rectangular beam, concrete 22 is filled into the ceiling beam 2 from the fourth through hole 4;

[0070] When the floor beam 1 is a C-shaped beam, the grouting material 13 is poured into the floor beam 1 from the side opening of the floor beam 1. After the grouting material 13 fills the floor beam 1, it flows out from the second through hole 14 to fill the gap between the ceiling beam 2 and the floor beam 1.

[0071] When the floor beam 1 is a rectangular beam, the grouting material 13 is poured into the floor beam 1 from the third through hole 15 . After the grouting material 13 fills the floor beam 1 , it flows out from the second through hole 14 to fill the gap between the ceiling beam 2 and the floor beam 1 .

[0072] This solution can achieve reliable horizontal and vertical connection of the combined modules. The second bolt is welded to the upper flange of the module ceiling beam. After grouting, it is used together with the concrete tenon in the opening of the flange of the upper module floor beam to combine the upper and lower steel beams to achieve vertical connection between modules. Holes are opened in the webs of the ceiling beam and the webs of the floor beam to place horizontal connecting steel bars. The steel bars and the concrete tenon in the opening are used to combine the left and right module beams to achieve horizontal connection of the left and right module beams, and finally multiple beams are coordinated to bear force, so as to improve the integrity, rigidity and stress performance of modular buildings, realize horizontal and vertical connection between modules, and make adjacent modules bear force synergistically. This composite structural module composite beam has the advantages of high assembly efficiency, quick and convenient construction, good stress performance, rigidity and integrity, and can freely connect modules vertically and horizontally. It has broad application prospects and is suitable for promotion and use in the field of modular buildings.

[0073] The following points need to be explained:

[0074] (1) The drawings of the embodiments of the present invention only involve structures related to the embodiments of the present invention. Other structures may refer to conventional designs.

[0075] (2) For the sake of clarity, in the drawings used to describe the embodiments of the present invention, the thickness of layers or regions is exaggerated or reduced, that is, these drawings are not drawn according to the actual scale. It is understood that when an element such as a layer, film, region or substrate is referred to as being "on" or "under" another element, the element may be "directly" "on" or "under" the other element or there may be intermediate elements.

[0076] (3) In the absence of conflict, the embodiments of the present invention and the features therein may be combined with each other to obtain new embodiments.

[0077] The above are only specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. The protection scope of the present invention shall be based on the protection scope of the claims.

Claims

1. A composite beam, characterized in that: It comprises a ceiling beam and a floor beam, wherein two adjacent ceiling beams are horizontally connected, two adjacent floor beams are horizontally connected, and the ceiling beam is vertically connected to the floor beam; A first stud is evenly arranged in an array on the inner wall of the lower flange of the ceiling beam and along the length direction of the ceiling beam, a second stud is evenly arranged in an array on the top of the ceiling beam and along the length direction of the ceiling beam, and a first through hole is evenly arranged in an array on the web of the ceiling beam and along the length direction of the ceiling beam; A third bolt is evenly arranged in an array on the inner wall of the upper flange of the floor beam and along the length direction of the floor beam, a second through hole is evenly arranged in an array on the lower flange of the floor beam and along the length direction of the floor beam, and a third through hole is evenly arranged in an array on the web of the floor beam and along the length direction of the floor beam; The length of the ceiling beam is equal to the length of the floor beam, the number of the second studs is equal to the number of the second through holes, and the position of each second stud corresponds to the position of each second through hole one by one.

2. The composite beam according to claim 1, characterized in that: In the two horizontally connected ceiling beams, each of the first through holes of one ceiling beam is aligned with each of the first through holes of the other ceiling beam, and first horizontal connecting steel bars are arranged in two adjacent and aligned first through holes; the two ceiling beams are filled with concrete.

3. The composite beam according to claim 1, characterized in that: In the two horizontally connected floor beams, each of the third through holes of one floor beam is aligned with each of the third through holes of the other floor beam, and second horizontal connecting steel bars are arranged in two adjacent and aligned third through holes; and grouting material is filled in the two floor beams.

4. The composite beam according to claim 1, characterized in that: Among the vertically connected ceiling beams and floor beams, the floor beam is located above the ceiling beam, the lower flange of the floor beam is aligned with the top surface of the ceiling beam, each of the second bolts passes through each of the second through holes respectively, concrete is set in the ceiling beam, grouting material is set in the floor beam, and grouting material is set between the ceiling beam and the floor beam.

5. The composite beam according to claim 1, characterized in that: The ceiling beam is a C-shaped beam, a U-shaped beam or a rectangular beam, and the floor beam is a C-shaped beam or a rectangular beam.

6. The composite beam according to claim 5, characterized in that: When the ceiling beam is a U-shaped beam, the number of the first through holes respectively arranged on the webs on both sides of the ceiling beam is equal, and the position of each of the first through holes on the web on one side of the ceiling beam corresponds one to one with the position of each of the first through holes on the web on the other side of the ceiling beam; The top ends of the webs on both sides of the ceiling beam are bent inward to obtain the top surface of the ceiling beam, and the bending angle is a right angle. Connecting plates are evenly arrayed on the top surfaces of the webs on both sides of the ceiling beam and along the length direction of the ceiling beam, and each of the second bolts is correspondingly arranged on each of the connecting plates.

7. The composite beam according to claim 5, characterized in that: When the ceiling beam is a rectangular beam, the number of the first through holes respectively arranged on the webs on both sides of the ceiling beam is equal, and the position of each of the first through holes on the web on one side of the ceiling beam corresponds one to one with the position of each of the first through holes on the web on the other side of the ceiling beam; A plurality of fourth through holes are arranged on the upper flange of the ceiling beam and along the length direction of the ceiling beam, and one second bolt is arranged between two adjacent fourth through holes.

8. The composite beam according to claim 5, characterized in that: When the floor beam is a rectangular beam, the number of the third through holes respectively arranged on the webs on both sides of the floor beam is equal, and the position of each of the third through holes on the web on one side of the floor beam corresponds one to one with the position of each of the third through holes on the web on the other side of the floor beam.

9. A method for connecting composite beams, characterized in that: The composite beam comprising any one of claims 1 to 8, wherein the method comprises: S1. Prefabricate the ceiling beams and the floor beams; S2: connecting the ceiling beams to the ceiling beams, connecting the floor beams to the floor beams, and / or connecting the ceiling beams to the floor beams; The ceiling beams are poured with concrete, and the floor beams are poured with grouting material.

10. The method for connecting composite beams according to claim 9, characterized in that: The step of connecting the ceiling beams to the ceiling beams, connecting the floor beams to the floor beams, and / or connecting the ceiling beams to the floor beams in S2 includes: When the ceiling beams are horizontally connected to each other, each of the first through holes of one of the ceiling beams is aligned with each of the first through holes of another of the ceiling beams, and the first horizontal connecting steel bars are inserted into two adjacent and aligned first through holes; When the floor beams are horizontally connected, each of the third through holes of one floor beam is aligned with each of the third through holes of another floor beam, and second horizontal connecting steel bars are arranged in two adjacent and aligned third through holes; When the ceiling beam is vertically connected to the floor beam, the lower flange of the floor beam is aligned with the top surface of the ceiling beam, and each of the second bolts passes through each of the second through holes to connect the ceiling beam to the floor beam; The pouring of concrete on the ceiling beams and pouring of grouting material on the floor beams in S2 comprises: When the ceiling beam is a C-shaped beam, concrete is filled into the ceiling beam from the side opening of the ceiling beam; when the ceiling beam is a U-shaped beam, concrete is filled into the ceiling beam from the top opening of the ceiling beam; when the ceiling beam is a rectangular beam, concrete is filled into the ceiling beam from the fourth through hole; When the floor beam is a C-shaped beam, the grouting material is poured into the floor beam from the side opening of the floor beam, and after the grouting material fills the floor beam, it flows out from the second through hole to fill the gap between the ceiling beam and the floor beam; When the floor beam is a rectangular beam, the grouting material is poured into the floor beam from the third through hole. After the grouting material fills up the floor beam, it flows out from the second through hole to fill up the gap between the ceiling beam and the floor beam.

Citation Information

Patent Citations

  • Modularized steel frame structure and inter-module connecting device

    CN113187096A

  • Web embedded type composite shear key and construction method

    CN116427260A

  • Corrugated -steel -web combined box girder

    CN205115992U

  • Be applied to composite floor slab unit of modularization building

    CN206128290U

  • Combined beam with T-shaped steel piece connecting prefabricated slab partially wrapped by honeycomb steel

    CN213296879U

Cited By

  • Prestress composite structure modular building system and construction method

    CN119553786A

  • Modular anti-seismic composite beam structure, modular building structure and construction method

    CN119914000A

  • Modular seismic-resistant composite beam structure, modular building structure and construction method

    CN119914000B