Device and method for removing turbidity and reducing hardness of coal gasification black water

By designing suitable mixing tanks, flocculation tanks and electrochemical precipitation tanks in the gasified black water treatment system, combined with the magnetic scraper drive structure, the scale problem of gasified black water is solved, and the flocculation efficiency and equipment stability are improved. , extends the service life.

CN118993468AInactive Publication Date: 2024-11-22ANHUI CARBON XIN TECH CO LTD

Patent Information

Application Number
CN202411493998.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-24
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Gasified black water is prone to fouling during operation, causing congestion of pipelines and equipment, affecting the service life and operation efficiency of equipment, and it is difficult for the existing technology to effectively solve this problem.

Method used

Design a gasified black water turbidity-reducing device. By setting up mutually adapted mixing tanks and flocculation tanks, multiple precipitation tanks are set up in the flocculation tanks, and combined with electrochemical effects, the magnetic scraper and driving structure are used to realize mud Efficient discharge of slag shortens flocculation time.

Benefits of technology

It effectively improves the flocculation and precipitation effect, reduces the hardness and turbidity of water quality, extends the service cycle of the gasification device, and ensures the long-term and stable operation of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118993468A_ABST
    Figure CN118993468A_ABST
Patent Text Reader

Abstract

The invention discloses a turbidity-removing and hardness-reducing device and method for coal gasification black water, and belongs to the technical field of coal gasification black water treatment.The turbidity-removing and hardness-reducing device is characterized in that a mixing tank and a flocculation tank which are matched with each other are arranged, a plurality of precipitation tanks which are communicated and isolated from the mixing tank are arranged in the flocculation tank, and after black water and a flocculating agent are put into the mixing tank, stirring and mixing are conducted firstly; the two actions do not interfere with each other, it is guaranteed that black water mixed with a flocculating agent is continuously injected into the precipitation tank in a small amount in batches for independent flocculation and precipitation, the flocculation action time is shortened, the flocculation and precipitation effect is further improved in cooperation with the electrochemical action, and after one-time flocculation work is completed, the flocculation and precipitation efficiency is improved. The driving structure is used for driving the magnetic mud scraping plate to push mud slag at the upper end of the connecting plate out of the slag discharging opening, the emptied precipitation tank is used for flocculation and precipitation next time, the operation is cycled, the turbidity removal and hardness reduction effects of gasified ash water are improved, and long-period stable work of the gasification device is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of coal gasification black water treatment, and more specifically, to a device and method for removing turbidity and reducing hardness of coal gasification black water. Background Art

[0002] The process of producing methanol by using coal through a pulverized coal gasification furnace can achieve the production of methanol. It uses pulverized coal as raw material, oxygen and sub-high pressure steam as gasification agents, and produces CO 2 and H 2 The crude synthesis gas with effective ingredients, under the high-temperature gasification reaction or quenching conditions of the gasifier, the substances produced by the side reactions are dissolved in the water system and enter the black water system for flash evaporation. Black water is high-temperature and high-pressure circulating water with high hardness. It is easy to produce scaling during operation. The scaling substances are easily adsorbed together and adhere to the pipe wall and will be deposited in the pipes and equipment, resulting in serious scaling of the pipes and equipment, affecting the service life of the pipes and equipment, and causing serious impact on the operation and maintenance of the gasification device.

[0003] At present, after a series of treatments such as high-pressure flash evaporation, low-pressure flash evaporation and vacuum flash evaporation, the coal gasification ash water / black water system adds flocculants to the water inlet pipe of the sedimentation tank to remove most of the suspended matter in the water, and adds dispersants to the inlet of the ash water tank pipeline when the clear liquid overflows from the upper part of the sedimentation tank to prevent scaling ions from scaling inside the equipment and affecting the normal operation of the equipment. The water is then returned to the system for recycling.

[0004] Since the flocculation reaction is a slow process in which the floccules gradually increase in size, especially for the black water discharge process with large volume, a certain flocculation time needs to be guaranteed. Mechanical stirring is a better measure to improve the efficiency of co-directional flocculation. However, when mechanical stirring is configured, the upper clear liquid is easily affected by the agitation, causing the flocculated particles to enter the gray water tank together with the upper clear liquid; in addition, if the mud residue at the bottom is not discharged in time, the subsequent flocculation work will be affected.

[0005] To this end, we propose a device and method for removing turbidity and reducing hardness of coal gasification black water in response to the above problems. Summary of the invention

[0006] The purpose of the present invention is to solve the existing practical problems. Compared with the existing technology, a device and method for removing turbidity and reducing hardness of coal gasification black water is provided. The method is to set a mixing tank and a flocculation tank that are compatible with each other. A plurality of sedimentation tanks that are connected to and isolated from the mixing tank are arranged in the flocculation tank. After the black water and the flocculant are put into the mixing tank, they are first stirred and mixed, and then the mixture is injected into the sedimentation tank for flocculation and sedimentation, so as to ensure that the black water mixed with the flocculant is continuously injected into the sedimentation tank in small batches for independent flocculation and sedimentation, shortening the flocculation time, and cooperating with the electrochemical action to further improve the flocculation and sedimentation effect. After one flocculation work is completed, the driving structure is used to drive the magnetic scraper plate to push the mud residue on the upper end of the connecting plate to the slag discharge port, and the emptied sedimentation tank is prepared for the next flocculation and sedimentation. Such a cycle operation is carried out to improve the effect of removing turbidity and reducing hardness of gasification ash water.

[0007] The purpose of the present invention can be achieved through the following technical solutions:

[0008] A coal gasification black water turbidity removal and hardness reduction device, comprising a flocculation tank fixedly mounted on an operating table, a mixing tank sleeved and mounted in a hollow shaft core of the flocculation tank, a stirring shaft installed in the mixing tank for rotational driving, a black water inlet pipe and a flocculant dosing tank connected to the top of the stirring shaft through a fixedly mounted rotating joint, a plurality of groups of partitions are annularly distributed in the flocculation tank, the plurality of groups of partitions divide the interior of the flocculation tank into a plurality of annularly staggered sedimentation tanks and sewage tanks, a connection plate is fixedly connected to the sedimentation tank near the bottom end, the bottom end of the mixing tank is connected to the interior of a plurality of sedimentation tanks one by one through a plurality of shunt pipes, and a gray water discharge pipe extending to the outside of the flocculation tank is externally connected to the upper end of the sedimentation tank;

[0009] An anode rod and a cathode rod connected to a power supply are fixedly installed inside each of the sedimentation tanks, a magnetic scraper plate located above a connecting plate is movably installed on the inner wall of the flocculation tank, a driving structure for driving the magnetic scraper plate to rotate along the axis of the flocculation tank is installed at the bottom of the sedimentation tank, a slag discharge port corresponding to the position of the magnetic scraper plate is provided on the end of each of the partitions, and a magnetic valve plate is movably connected to the slag discharge port, a plurality of sewage outlets connected to sewage troughs are annularly provided on the bottom end wall of the flocculation tank, and a sewage hopper connected to the plurality of sewage outlets is fixed at the bottom end of the flocculation tank.

[0010] Furthermore, the mixing tank is a hollow cylindrical structure with its top exposed above the flocculation tank, a plurality of stirring rods connected to the interior of the stirring shaft are distributed on the end wall of the stirring shaft, and the rotary joint is fixed to the top of the mixing tank and is connected to the interior of the stirring shaft.

[0011] Furthermore, a gear 1 which rotates on the top of the mixing tank is fixedly installed on the upper end of the stirring shaft, a gear 2 which meshes with the gear 1 and is rotatably installed on the operating table, and a driving motor which drives the gear 2 is fixedly installed on the operating table. Black water and flocculant are respectively injected into the stirring shaft through the black water inlet pipe and the flocculant addition tank. The flocculant is appropriately proportioned according to the injection amount of black water. The black water and flocculant are mixed and injected into the mixing tank by multiple stirring rods. During the injection process, the stirring shaft continuously rotates to achieve sufficient mixing of the black water and the flocculant.

[0012] Furthermore, the diverter pipe is located above the magnetic scraper plate, and the inner wall of the flocculation tank is provided with an arc groove for the magnetic scraper plate to rotate along its end wall.

[0013] Furthermore, the driving structure includes an annular guide rail embedded in the inner wall of the flocculation tank, the annular guide rail is located below the connecting plate, and a magnetic push plate corresponding to the position of the magnetic scraper plate and magnetically attracted to the magnetic scraper plate is installed on the annular guide rail. A sliding groove for rotating and sliding the magnetic push plate is provided at the bottom end of the connecting plate. By utilizing the magnetic attraction force between the magnetic push plate and the magnetic scraper plate, when the annular guide rail drives the magnetic push plate to rotate along the axis of the flocculation tank, the magnetic push plate drives the magnetic scraper plate located above the connecting plate to rotate synchronously, so as to push the sludge accumulated in the sedimentation tank to the side.

[0014] Furthermore, a hollow cavity is formed on the inner wall of the partition above the slag discharge port, and an electromagnetic strip for magnetically positioning the magnetic valve plate is embedded and installed at the top of the hollow cavity.

[0015] Furthermore, the height of the magnetic valve plate is greater than the height of the slag discharge port, and the end of the magnetic valve plate embedded in the hollow cavity is made of a magnetic material that is magnetically attracted to the electromagnetic strip. In the initial state, the electromagnetic strip is in a closed state, and the magnetic valve plate is sealed at the slag discharge port. The black water that is fully stirred and mixed with the flocculant is introduced into the sedimentation tank through the diversion pipe, and the slag is flocculated and precipitated at the upper end of the connecting plate. When the flocculation stage is completed, the gray water discharge pipe is opened to discharge the gray water at the upper end of the sedimentation tank, and the mud residue below is pushed to the open slag discharge port by the magnetic scraper plate that reciprocates left and right, and is finally discharged through the slag discharge port, the sewage outlet, and the sewage bucket.

[0016] Furthermore, a dispersion plate with a discharge pipe and located below a plurality of gray water discharge pipes is fixedly mounted on the outer end wall of the flocculation tank, and a dispersant dosing tank for dosing dispersant into the dispersing plate is provided on one side of the dispersing plate.

[0017] Furthermore, a vibration plate is installed on the bottom end wall of the dispersion plate, and the vibration plate is externally connected to an ultrasonic generator through a power supply.

[0018] A method for removing turbidity and reducing hardness of coal gasification black water comprises the following steps:

[0019] Step 1: First, inject black water into the mixing tank through the black water inlet pipe, and at the same time inject a certain proportion of flocculant into the mixing tank through the flocculant addition tank. The black water and flocculant are fully mixed and stirred in the mixing tank through the stirring shaft;

[0020] Step 2: Introduce the black water into the sedimentation tank through the diversion pipe for flocculation and sedimentation, repeatedly introduce the black water and flocculant into the mixing tank through the black water inlet pipe and the flocculant adding tank for stirring, and inject the stirred black water into multiple sedimentation tanks one by one for static sedimentation;

[0021] Step 3: After the black water is introduced into the sedimentation tank, the anode rod and the cathode rod are started to electrochemically react with the sewage. The impurities in the black water form small, light, and non-sinking floccules. The sedimentation tank is stratified, and the sludge flocculates and precipitates at the upper end of the connecting plate. When the flocculation stage is completed, the gray water discharge pipe is opened to discharge the gray water at the upper end, and the sludge at the bottom is pushed to the opened slag discharge port by the magnetic scraper plate that reciprocates left and right, and finally discharged through the slag discharge port, sewage discharge port, and sewage discharge bucket. The empty sedimentation tank is prepared for the next flocculation and sedimentation.

[0022] Step 4: While the gray water is introduced into the dispersion plate through the gray water discharge pipe, a certain proportion of dispersant is injected into the dispersion plate through the dispersant addition tank. With the cooperation of the vibration plate and the ultrasonic generator, the dispersant fully acts on the gray water to reduce the precipitation of the gray water. The treated gray water is discharged from the discharge pipe.

[0023] Compared with the prior art, the advantages of the present invention are:

[0024] (1) This scheme is to set up a mixing tank and a flocculation tank that are compatible with each other. The flocculation tank is divided into multiple sedimentation tanks connected to the mixing tank by multiple groups of partitions. The mixing tank and the sedimentation tank are isolated from each other. Therefore, after the black water and flocculant are put into the mixing tank, they are first stirred and mixed, and then the mixture is injected into the sedimentation tank for flocculation and sedimentation. The two actions do not interfere with each other, and multiple sedimentation tanks are distributed in a ring outside the mixing tank to ensure that the black water mixed with the flocculant is continuously injected into the sedimentation tank in batches in small quantities for independent flocculation and sedimentation, shortening the flocculation time. In addition, the electrochemical action is combined to further improve the flocculation and sedimentation effect, so that the water quality of the gasification ash water circulation system is improved, the water hardness and turbidity are reduced, and it is conducive to the long-term stable operation of the gasification device.

[0025] (2) This scheme adds a magnetic scraper plate and a driving structure compatible with it at the bottom of the sedimentation tank, and adds a magnetic valve plate movably installed at the slag discharge port at the partitions on both sides of the sedimentation tank. When the flocculation work in the sedimentation tank is completed, the upper layer of ash water is discharged through the ash water discharge pipe. At this time, the magnetic valve plates on both sides are opened again, and the magnetic push plate and the magnetic scraper plate are magnetically attracted. When the annular guide rail drives the magnetic push plate to rotate along the axis of the flocculation tank, the magnetic push plate drives the magnetic scraper plate located above the connecting plate to rotate synchronously, so as to push the sludge accumulated in the sedimentation tank to the side, and finally discharge it through the slag discharge port, sewage discharge port, and sewage discharge bucket. The empty sedimentation tank is ready for the next flocculation sedimentation. This cycle is repeated, effectively shortening the flocculation time each time. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a structural schematic diagram of the present invention;

[0027] Figure 2 It is a structural schematic diagram of another perspective of the present invention;

[0028] Figure 3 It is a partial cross-sectional view of the present invention;

[0029] Figure 4 It is an internal cross-sectional view of the mixing tank of the present invention;

[0030] Figure 5 It is a top view of the junction of the flocculation tank and the mixing tank of the present invention;

[0031] Figure 6 The cross-sectional view of the flocculation tank of the present invention Figure 1 ;

[0032] Figure 7 The cross-sectional view of the flocculation tank of the present invention Figure 2 ;

[0033] Figure 8 It is a structural schematic diagram of the flocculation tank and the sewage hopper of the present invention when they are separated;

[0034] Fig. 9 It is a structural schematic diagram of the magnetic scraper and the driving structure of the present invention;

[0035] Fig.10 It is a schematic structural diagram of the present invention when using a magnetic scraper to scrape away mud residue at a slag discharge port.

[0036] Description of the numbers in the figure:

[0037] 1. Flocculation tank; 101. Sedimentation tank; 102. Drain trough; 103. Grey water discharge pipe; 104. Drain port; 2. Mixing tank; 201. Diverter pipe; 3. Stirring shaft; 301. Stirring rod; 4. Rotary joint; 5. Black water inlet pipe; 6. Flocculant dosing tank; 7. Partition; 8. Anode rod; 9. Cathode rod; 10. Dispersant dosing tank; 11. Dispersing disc; 111. Drain pipe; 12. Connecting plate; 13. Magnetic scraper; 14. Magnetic push plate; 15. Annular guide rail; 16. Magnetic valve plate; 17. Electromagnetic strip; 18. Drain hopper; 19. Vibrating plate. DETAILED DESCRIPTION

[0038] The following will combine the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all the embodiments. All other embodiments obtained by ordinary technicians in this field without creative work based on the embodiments of the present invention belong to the scope of protection of the present invention.

[0039] Embodiment 1:

[0040] The present invention discloses a device for removing turbidity and reducing hardness of coal gasification black water. Figure 1-Figure 4 , comprising a flocculation tank 1 fixedly mounted on an operating table, the flocculation tank 1 being an annular sleeve structure with an upper end opening, a mixing tank 2 fixed on the operating table being sleeved and mounted in a hollow axial portion of the flocculation tank 1, a stirring shaft 3 being installed for rotational drive inside the mixing tank 2, and a black water inlet pipe 5 and a flocculant dosing tank 6 being connected to the top of the stirring shaft 3 through a fixedly mounted rotating joint 4;

[0041] The mixing tank 2 is a hollow cylindrical structure with its top exposed above the flocculation tank 1. A plurality of stirring rods 301 connected to the interior of the stirring shaft 3 are distributed on the end wall. The rotary joint 4 is fixed to the top of the mixing tank 2 and is connected to the interior of the stirring shaft 3. A gear 1 that rotates on the top of the mixing tank 2 is fixedly installed on the upper end of the stirring shaft 3. A gear 2 that meshes with the gear 1 is rotatably installed on the operating table, and a driving motor that drives the gear 2 is fixedly installed on the operating table. Black water and flocculant are respectively injected into the stirring shaft 3 through the black water inlet pipe 5 and the flocculant addition tank 6. The flocculant is appropriately proportioned according to the amount of black water injected. The black water and the flocculant are mixed and injected into the mixing tank 2 by the plurality of stirring rods 301. During the injection process, the stirring shaft 3 continuously rotates to achieve sufficient mixing of the black water and the flocculant.

[0042] See also Figure 5-Figure 6There are multiple groups of partitions 7 distributed in an annular manner inside the flocculation tank 1, and the multiple groups of partitions 7 divide the interior of the flocculation tank 1 into multiple annularly staggered sedimentation tanks 101 and sewage tanks 102. The internal volume of the sedimentation tank 101 is larger than the internal volume of the sewage tank 102. A connecting plate 12 is fixedly connected to the sedimentation tank 101 near the bottom end. The bottom end of the mixing tank 2 is connected to the inner walls of the lower ends of the multiple sedimentation tanks 101 one by one through multiple diversion pipes 201. Each diversion pipe 201 is installed with a solenoid valve. There are multiple gray water discharge pipes 103 extending to the inner wall of the upper end of the sedimentation tank 101 distributed in an annular manner on the outer end wall of the flocculation tank 1.

[0043] After the black water and flocculant in the mixing tank 2 are fully mixed, the mixed black water is discharged into the sedimentation tank 101 through the diversion pipe 201 for flocculation and sedimentation. After the black water in the mixing tank 2 is introduced into the sedimentation tank 101, the black water and flocculant are repeatedly introduced into the mixing tank 2 through the black water inlet pipe 5 and the flocculant adding tank 6 for stirring, and the stirred black water is injected into multiple sedimentation tanks 101 one by one for static sedimentation. According to actual needs, the mixed and stirred black water mixture is injected into multiple groups of sedimentation tanks 101 in batches, and each group of sedimentation tanks 101 is provided with one or more, that is, the black water mixture in the mixing tank 2 can be injected into one sedimentation tank 101 at a time, or can be injected into multiple sedimentation tanks 101 at a time. The two actions of stirring and flocculation do not interfere with each other, ensuring that the black water mixture is continuously injected into the sedimentation tank 101 in batches in small quantities for independent flocculation and sedimentation, shortening the flocculation time, and effectively solving the disadvantages of traditional stirring and flocculation in one tank body.

[0044] See also Figure 2-Figure 3 Each sedimentation tank 101 is fixedly installed with an anode rod 8 and a cathode rod 9 connected to an external power supply. After the black water is introduced into the sedimentation tank 101, the anode rod 8 and the cathode rod 9 are started to perform an electrochemical reaction on the sewage. The impurities in the black water form small, light, and non-sinking floccules, causing stratification in the sedimentation tank 101. The mud residue flocculates and settles at the upper end of the connecting plate 12. When the flocculation stage is completed, the gray water discharge pipe 103 is opened to discharge the gray water at the upper end of the sedimentation tank 101.

[0045] A dispersion plate 11 with a discharge pipe 111 and located below a plurality of gray water discharge pipes 103 is fixedly mounted on the outer end wall of the flocculation tank 1. A dispersant dosing tank 10 is installed on one side of the dispersion plate 11 for adding dispersant therein. A vibration plate 19 is mounted on the bottom end wall of the dispersion plate 11. The vibration plate 19 is externally connected to an ultrasonic generator via a power supply.

[0046] When the gray water is introduced into the dispersion plate 11 by the gray water discharge pipe 103, a certain proportion of dispersant is injected into the dispersion plate 11 by the dispersant addition tank 10. With the cooperation of the vibration plate 19 and the ultrasonic generator, the dispersant fully acts on the gray water to reduce the precipitation of the gray water. The treated gray water is discharged outwardly from the discharge pipe 111.

[0047] Embodiment 2: Based on Embodiment 1, this embodiment adds a slag discharge structure at the bottom of the sedimentation tank 101 for discharging the sludge. The slag discharge structure is composed of a magnetic scraper 13, a driving structure, and a movable magnetic valve plate 16, as shown below:

[0048] See also Figure 3 and Figure 5-Figure 8 A magnetic scraper 13 is movably mounted on the inner wall of the flocculation tank 1 and is located above the connecting plate 12. The diverter pipe 201 is located above the magnetic scraper 13. An arc groove is provided on the inner wall of the flocculation tank 1 for the magnetic scraper 13 to rotate along its end wall.

[0049] A driving structure for rotating the magnetic scraper 13 along the axis of the flocculation tank 1 is installed at the bottom of the sedimentation tank 101, and a slag discharge port corresponding to the position of the magnetic scraper 13 is opened at the end of each partition 7, and a magnetic valve plate 16 is movably connected to the slag discharge port, and a plurality of sewage outlets 104 connected to the sewage trough 102 are annularly opened on the bottom end wall of the flocculation tank 1, and a sewage hopper 18 connected to the plurality of sewage outlets 104 is fixed to the bottom end of the flocculation tank 1.

[0050] See also Figure 9-10 The driving structure includes an annular guide rail 15 embedded on the inner wall of the flocculation tank 1, the annular guide rail 15 is located below the connecting plate 12, and a magnetic push plate 14 corresponding to the position of the magnetic scraper plate 13 and magnetically attracted to the magnetic scraper plate 13 is installed on the annular guide rail 15. A sliding groove for the magnetic push plate 14 to rotate and slide is provided at the bottom of the connecting plate 12. The magnetic push plate 14 and the magnetic scraper plate 13 are magnetically attracted to each other. When the annular guide rail 15 drives the magnetic push plate 14 to rotate along the axis of the flocculation tank 1, the magnetic push plate 14 drives the magnetic scraper plate 13 located above the connecting plate 12 to rotate synchronously, so as to push the sludge accumulated in the sedimentation tank 101 toward the slag discharge port;

[0051] The inner wall of the partition 7 above the slag discharge port is provided with a hollow cavity, and an electromagnetic strip 17 for magnetically positioning the magnetic valve plate 16 is embedded at the top of the hollow cavity of the partition 7, and the height of the magnetic valve plate 16 is greater than the height of the slag discharge port, and the end of the magnetic valve plate 16 embedded in the hollow cavity is made of a magnetic material that is magnetically attracted to the electromagnetic strip 17;

[0052] In the initial state, the electromagnetic strip 17 is in a closed state, and the magnetic valve plate 16 is closed at the slag discharge port under the action of gravity. The black water fully stirred and mixed with the flocculant is introduced into the sedimentation tank 101 through the diversion pipe 201 for flocculation and sedimentation. In this process, the mud residue is flocculated and precipitated at the upper end of the connecting plate 12. When the flocculation stage is completed, the gray water discharge pipe 103 is opened to discharge the gray water at the upper end of the sedimentation tank 101. The gray water is directly discharged into the dispersion plate 11, and the mud residue below is removed by the magnetic scraper that reciprocates left and right. The mud plate 13 is pushed toward the opened slag discharge port, and the magnetic valve plate 16 at the slag discharge port is reset upward and stored in the hollow cavity under the activation of the electromagnetic bar 17, exposing the slag discharge port, and the mud is discharged through the slag discharge port, the sewage outlet 104, and the sewage bucket 18. In addition to using magnetic suction to open the magnetic valve plate 16, the opening and closing of the magnetic valve plate 16 can also be achieved by setting an existing electric pushing structure. This is a prior art. The emptied sedimentation tank 101 is prepared for the next flocculation sedimentation to prevent the mud from affecting the subsequent flocculation sedimentation.

[0053] Embodiment 3: A method for removing turbidity and reducing hardness of coal gasification black water, comprising the following steps:

[0054] Step 1: First, inject black water into the mixing tank 2 through the black water inlet pipe 5, and at the same time inject a certain proportion of flocculant into the mixing tank 2 through the flocculant adding tank 6, and the black water and the flocculant are fully mixed and stirred in the mixing tank 2 through the stirring shaft 3;

[0055] Step 2: Introduce the black water into the sedimentation tank 101 through the diversion pipe 201 for flocculation and sedimentation. After the black water in the mixing tank 2 is introduced into the sedimentation tank 101, the black water and flocculant are repeatedly introduced into the mixing tank 2 through the black water inlet pipe 5 and the flocculant addition tank 6 for stirring, and the stirred black water is successively injected into multiple sedimentation tanks 101 for static sedimentation;

[0056] Step 3: After the black water is introduced into the sedimentation tank 101, the anode rod 8 and the cathode rod 9 are started to perform an electrochemical reaction on the sewage. The impurities in the black water form small, light, and non-sinking floccules, so that stratification occurs in the sedimentation tank 101. The mud residue flocculates and settles at the upper end of the connecting plate 12. When the flocculation stage is completed, the gray water discharge pipe 103 is opened to discharge the gray water at the upper end of the sedimentation tank 101. The gray water is directly discharged into the dispersion plate 11, and the mud residue below is pushed to the opened slag discharge port by the magnetic scraper 13 that reciprocates left and right, and finally discharged through the slag discharge port, the sewage discharge port 104, and the sewage discharge bucket 18. The empty sedimentation tank 101 is ready for the next flocculation and sedimentation.

[0057] Step 4: While the gray water is introduced into the dispersion plate 11 by the gray water discharge pipe 103, a certain proportion of dispersant is injected into the dispersion plate 11 by the dispersant addition tank 10. With the cooperation of the vibration plate 19 and the ultrasonic generator, the dispersant fully acts on the gray water to reduce the precipitation of the gray water. The treated gray water is discharged outward from the discharge pipe 111.

[0058] In summary, the present invention is to set a mixing tank 2 and a flocculation tank 1 that are adapted to each other, and the flocculation tank 1 is divided into a plurality of sedimentation tanks 101 connected to the mixing tank 2 by a plurality of partitions 7, and the mixing tank 2 and the sedimentation tank 101 are isolated from each other. Therefore, after the black water and the flocculant are put into the mixing tank 2, they are first stirred and mixed, and then the mixture is injected into the sedimentation tank 101 for flocculation and sedimentation. The two actions do not interfere with each other, ensuring that the black water mixed with the flocculant is continuously injected into the sedimentation tank 101 in batches in small quantities for independent flocculation and sedimentation, shortening the flocculation time, and cooperating with the electrochemical action to further improve the flocculation and sedimentation effect;

[0059] After a flocculation work is completed, the upper layer of ash water is discharged through the ash water discharge pipe 103. At this time, the magnetic valve plates 16 on both sides are opened to expose the slag discharge port at the sedimentation tank 101. The magnetic scraper plate 13 is used in conjunction with the drive structure to push the mud residue on the upper end of the connecting plate 12 to the slag discharge port. The emptied sedimentation tank 101 is prepared for the next flocculation sedimentation. Such a cyclic operation enhances the flocculation effect, reduces the hardness and turbidity of the gasified ash water, and is conducive to the long-term stable operation of the gasification device.

[0060] The above are only preferred specific implementation modes of the present invention; however, the protection scope of the present invention is not limited thereto; any technician familiar with the technical field within the technical scope disclosed by the present invention; any equivalent replacement or change based on the technical solution and improved concept of the present invention shall be covered within the protection scope of the present invention.

Claims

1. A device for removing turbidity and reducing hardness of coal gasification black water, comprising a flocculation tank (1) fixedly mounted on an operating table, Features: The flocculation tank (1) is sleeved with a mixing tank (2) in the hollow shaft center portion, and a stirring shaft (3) is installed inside the mixing tank (2) for rotational driving. The top end of the stirring shaft (3) is connected to a black water inlet pipe (5) and a flocculant dosing tank (6) via a fixedly installed rotating joint (4). The inside of the flocculation tank (1) is divided into a plurality of staggered sedimentation tanks (101) and sewage tanks (102) by a plurality of groups of partitions (7) distributed in an annular manner. The bottom end of the sedimentation tank (101) is fixedly connected to a connecting plate (12). The bottom end of the mixing tank (2) is connected to the inside of the plurality of sedimentation tanks (101) one by one via a plurality of diversion pipes (201), and the upper end of the sedimentation tank (101) is externally connected to a gray water discharge pipe (103) extending to the outside of the flocculation tank (1); Each of the sedimentation tanks (101) is fixedly provided with an anode rod (8) and a cathode rod (9) connected to a power supply; a magnetic scraper (13) is movably provided on the inner wall of the flocculation tank (1) and is located above the connection plate (12); a driving structure for driving the magnetic scraper (13) to rotate along the axis of the flocculation tank (1) is provided at the bottom of the sedimentation tank (101); a slag discharge port corresponding to the position of the magnetic scraper (13) is provided at the end of each partition plate (7); and a magnetic valve plate (16) is movably connected to the slag discharge port; a plurality of sewage discharge ports (104) connected to the sewage discharge tank (102) are provided in an annular manner on the bottom end wall of the flocculation tank (1); and a sewage discharge bucket (18) connected to the plurality of sewage discharge ports (104) is fixed at the bottom end of the flocculation tank (1); The driving structure comprises an annular guide rail (15) embedded and installed on the inner wall of the flocculation tank (1), the annular guide rail (15) being located below the connecting plate (12), and a magnetic push plate (14) corresponding to the position of the magnetic scraper plate (13) and magnetically attracted to the magnetic scraper plate (13) being installed on the annular guide rail (15), a sliding groove for rotating and sliding the magnetic push plate (14) being provided at the bottom end of the connecting plate (12), a hollow cavity being provided on the inner wall of the partition plate (7) located above the slag discharge port, and an electromagnetic strip (17) for magnetically attracting and positioning the magnetic valve plate (16) being embedded and installed at the top of the hollow cavity of the partition plate (7); A dispersion plate (11) with a discharge pipe (111) is fixedly mounted on the outer end wall of the flocculation tank (1), and is located below the plurality of grey water discharge pipes (103). A dispersant dosing tank (10) for dosing dispersant into the dispersion plate (11) is provided on one side of the dispersion plate (11). A vibration plate (19) is mounted on the bottom end wall of the dispersion plate (11). The vibration plate (19) is externally connected to an ultrasonic generator via a power source.

2. A device for removing turbidity and reducing hardness of coal gasification black water according to claim 1, Features: The mixing tank (2) is a hollow cylindrical structure with its top exposed above the flocculation tank (1); a plurality of stirring rods (301) are distributed on the end wall of the stirring shaft (3) and are connected to the interior thereof; and the rotary joint (4) is fixed to the top end of the mixing tank (2) and is connected to the interior of the stirring shaft (3).

3. The device for removing turbidity and reducing hardness of coal gasification black water according to claim 1, Features: The height of the magnetic valve plate (16) is greater than the height of the slag discharge port, and the end of the magnetic valve plate (16) embedded in the hollow cavity is made of a magnetic material that is magnetically attracted to the electromagnetic strip (17).

4. A method for removing turbidity and reducing hardness of coal gasification black water, using a coal gasification black water removal turbidity and reducing hardness device as claimed in any one of claims 1 to 3, Features: The following steps are involved: Step 1: first, inject black water into the mixing tank (2) through the black water inlet pipe (5), and at the same time inject a certain proportion of flocculant into the mixing tank (2) through the flocculant addition tank (6), and the black water and the flocculant are fully mixed and stirred in the mixing tank (2) through the stirring shaft (3); Step 2: introducing the black water into the sedimentation tank (101) through the diversion pipe (201) for flocculation and sedimentation, repeatedly introducing the black water and flocculant into the mixing tank (2) through the black water inlet pipe (5) and the flocculant addition tank (6) for stirring, and injecting the stirred black water into multiple sedimentation tanks (101) one by one for static sedimentation; Step 3: After the black water is introduced into the sedimentation tank (101), the anode rod (8) and the cathode rod (9) are started to perform an electrochemical reaction on the sewage. The impurities in the black water form fine, light, and non-sinking floccules. A stratification phenomenon occurs in the sedimentation tank (101). The sludge flocculates and settles at the upper end of the connecting plate (12). When the flocculation stage is completed, the gray water discharge pipe (103) is opened to discharge the gray water at the upper end, while the sludge at the lower end is pushed to the opened slag discharge port by the magnetic scraper (13) that reciprocates left and right, and finally discharged through the slag discharge port, the sewage discharge port (104), and the sewage discharge bucket (18). The empty sedimentation tank (101) is prepared for the next flocculation and sedimentation. Step 4: While the grey water is introduced into the dispersion plate (11) via the grey water discharge pipe (103), a dispersant of a certain proportion is injected into the dispersion plate (11) via the dispersant dosing tank (10). With the cooperation of the vibration plate (19) and the ultrasonic generator, the dispersant fully acts on the grey water to reduce the precipitation of the grey water. The treated grey water is discharged from the discharge pipe (111).

Citation Information

Patent Citations

  • Entrained-flow coal gasification black ash water settling and dispersing system and black ash water settling method thereof

    CN110665260A

  • Electrochemical flocculation precipitation device and method

    CN116354463A

  • Precipitation device for domestic sewage

    CN210313668U

  • Zinc sulfate heptahydrate flocculent precipitation device

    CN219709223U

  • Efficient treatment system for heavy metal sewage

    CN220537639U

Cited By

  • Waste plastic cleaning wastewater treatment system

    CN120646994A

  • Waste plastic cleaning wastewater treatment system

    CN120646994B