Bridge end transition slab suitable for deep soft soil area and construction method

By designing bridge head trays and specific construction methods for articulated and longitudinal joints in deep soft soil areas, the problem of bridge head trays is solved, achieving better deformation coordination and extending the life of boarding.

CN119041257APending Publication Date: 2024-11-29ZHUHAI PLANNING&DESIGNING INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411248009.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-06
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In deep soft soil areas, conventional bridgehead trays cannot effectively alleviate the problem of jumping from the bridgehead, resulting in uneven vehicles passing through and safety hazards.

Method used

A bridge head placing plate including a first pillow beam, a second pillow beam, a first pillow plate and a second pillow plate are designed. The pillow plate is connected through hinges and longitudinal seams, and a grouting hole is reserved, and the pillow plate is mounted. The length is 6 meters or more, and rigid concrete materials are used, combined with specific construction methods such as foundation pit excavation, base treatment, formwork installation, steel bar processing and concrete pouring, to ensure the stability and durability of the board.

Benefits of technology

By extending the length of the plate and strengthening the structural rigidity, the impact of roadbed settlement on the plate angle is reduced, the risk of jumping from the bridge head is reduced, and the exposure time of the stripping area is reduced by reserved grouting holes, which improves the use of the plate Coordinate life and deformation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041257A_ABST
    Figure CN119041257A_ABST
Patent Text Reader

Abstract

The invention discloses a bridgehead transition slab suitable for a deep soft soil area and a construction method, relates to the technical field of bridge construction, and can effectively relieve the problem of bumping at a bridgehead in the deep soft soil area. A bridgehead transition slab suitable for a deep soft soil area comprises a first sleeper beam, a second sleeper beam, a first transition slab and a second transition slab. The transition slab is a rigid concrete slab, the deformation of the transition slab can be ignored, after the transition slab is lengthened, the length of the transition slab is lengthened, and for the same subgrade settlement amount, the longitudinal slope reflected to the road surface is reduced, so that a better deformation coordination effect is achieved. The grouting hole site is reserved before the transition slab is poured, after settlement of the roadbed below the transition slab occurs, grouting treatment is conducted on the void area in time through the reserved hole site, the exposure time of the void area below the transition slab is shortened, the damage risk of the transition slab is reduced, and the service life of the transition slab is prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a bridge head slab suitable for deep soft soil areas and a construction method. Background Art

[0002] Bridgehead slab design is an important and common technology in municipal road and bridge design. Bridgehead slab is usually used to coordinate the differential settlement between bridge and roadbed. The settlement control of bridge structure is often at the millimeter level, while the roadbed at the end of the bridge is affected by compaction or geology, and its settlement often reaches the centimeter level or even greater. By setting up a bridgehead slab, the bridge and roadbed are connected through the slab, and the slab can rotate with the settlement of the roadbed to achieve the purpose of coordinating the differential settlement of the bridge and roadbed, so that vehicles can pass the bridgehead relatively smoothly. The conventional bridgehead slab is set to a length of 3 to 6 meters. In deep soft soil areas, the settlement of the roadbed often exceeds 50cm, and even reaches more than 1m. Many projects continue to use conventional bridgehead slabs in deep soft soil areas, resulting in frequent hazards such as bridgehead jumping. Summary of the invention

[0003] The purpose of the present invention is to solve at least one of the technical problems existing in the prior art, and to provide a bridge head cladding and construction method suitable for deep soft soil areas, which can effectively alleviate the problem of bridge head jumping in deep soft soil areas.

[0004] According to a first aspect of the present invention, there is provided a bridgehead slab suitable for use in deep soft soil areas, comprising a first bolster, a second bolster, a first slab and a second slab, wherein one end of the first slab is overlapped on the first bolster, and the other end is overlapped on the second bolster, one end of a pavement structure is overlapped on the first bolster and butt-jointed with the first slab, one end of the second slab is overlapped on the second bolster, and the other end is overlapped on the abutment, and the second slab is hinged to the first slab.

[0005] According to the bridgehead slab suitable for deep soft soil areas described in the first aspect of the present invention, the second slab is hinged to the first slab via hinged steel bars.

[0006] According to the first aspect of the present invention, a bridgehead slab suitable for use in thick soft soil areas further includes longitudinal seam connecting steel bars, wherein the first slabs arranged side by side are connected by the longitudinal seam connecting steel bars, and the second slabs arranged side by side are connected by the longitudinal seam connecting steel bars.

[0007] According to the first aspect of the present invention, a bridgehead slab suitable for deep soft soil areas is provided, wherein the length of the first slab is 6 meters.

[0008] According to the bridgehead slab suitable for deep soft soil areas described in the first aspect of the present invention, the length of the second slab is not less than 8 meters.

[0009] According to the bridgehead slab applicable to deep soft soil areas described in the first aspect of the present invention, the first slab and the second slab are rigid concrete slabs.

[0010] According to the bridge head slab suitable for deep soft soil areas in the first aspect of the present invention, grouting holes are reserved on the first slab and the second slab.

[0011] According to a second aspect of the present invention, there is provided a construction method for bridgehead slabs in deep soft soil areas, comprising the following steps:

[0012] Foundation pit excavation: excavate the foundation pit according to the design requirements, and the width and depth of the foundation pit must meet the design requirements;

[0013] Base treatment: After the foundation pit is excavated, base treatment is carried out to ensure the density of the foundation. If necessary, foundation reinforcement can be carried out, such as laying a gravel cushion or compaction treatment;

[0014] Formwork installation: Install the formwork according to the design size of the slab. The strength and rigidity of the formwork must meet the construction requirements to ensure that it does not deform during concrete pouring.

[0015] Support system: The formwork support system of the slab should be strong to prevent the formwork from shifting during the concrete pouring process;

[0016] Steel bar processing: Process and shape steel bars according to design drawings;

[0017] Rebar binding: Bind the rebars according to the design requirements, pay attention to the spacing between the rebars and the thickness of the protective layer, and conduct self-inspection after binding to ensure that there are no missing or loose phenomena;

[0018] Pouring concrete: Pour concrete in layers, with each layer thickness controlled at 25-30cm. Avoid voids or segregation during pouring;

[0019] Vibration and leveling: Use a vibrator to vibrate to ensure that the concrete is dense. After the vibration is completed, the concrete surface is leveled;

[0020] Concrete curing: After the initial setting of concrete, water curing is carried out for 7-14 days. During the curing period, the concrete surface should be kept moist.

[0021] Formwork removal: After the concrete reaches the designed strength, the formwork is removed, and attention is paid to the order of formwork removal to avoid damage to the structure;

[0022] Backfill: After removing the formwork, backfill the earth on both sides of the scaffolding. The backfill material should be compacted layer by layer to avoid settlement at the connection between the scaffolding and the roadbed.

[0023] According to a second aspect of the present invention, a construction method for a bridgehead slab in a deep soft soil area is described, grouting holes are reserved before the slab is cast, and after settlement of the roadbed below the slab occurs, grouting treatment is promptly performed on the void area through the grouting holes.

[0024] According to the present invention, at least the following beneficial effects are achieved: the slab is a rigid concrete slab, and its own deformation can be ignored. After the slab is lengthened, the longitudinal slope of the road surface will be reduced for the same roadbed settlement by lengthening the slab, thereby achieving a better deformation coordination effect. Grouting holes are reserved before the slab is cast. After the roadbed settlement occurs under the slab, the empty area is grouted in time through the reserved holes, reducing the exposure time of the empty area under the slab, which is conducive to reducing the risk of damage to the slab and increasing the service life of the slab.

[0025] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The present invention is further described below in conjunction with the accompanying drawings and embodiments;

[0027] Figure 1 A top view of a preferred embodiment of the present invention;

[0028] Figure 2 It is a cross-sectional view of a preferred embodiment of the present invention.

[0029] Reference numerals: first bolster 10 , second bolster 20 , first lap plate 30 , second lap plate 40 , hinged steel bar 50 , longitudinal seam connecting steel bar 60 . DETAILED DESCRIPTION

[0030] This section will describe in detail the specific embodiments of the present invention. The preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present invention, but it cannot be understood as a limitation on the scope of protection of the present invention.

[0031] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., and orientations or positional relationships indicated are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0032] In the description of the present invention, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0033] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.

[0034] Reference Figure 1 and Figure 2 A bridgehead slab suitable for deep soft soil areas comprises a first bolster 10, a second bolster 20, a first slab 30 and a second slab 40. One end of the first slab 30 is overlapped on the first bolster 10, and the other end is overlapped on the second bolster 20. One end of the pavement structure is overlapped on the first bolster 10 and butted with the first slab 30. One end of the second slab 40 is overlapped on the second bolster 20, and the other end is overlapped on the abutment. The second slab 40 is hinged to the first slab 30.

[0035] Reference Figure 1 and Figure 2 The second strap 40 is hinged to the first strap 30 via a hinged steel bar 50 .

[0036] Reference Figure 1 and Figure 2 A bridgehead slab suitable for deep soft soil areas also includes a longitudinal seam connecting steel bar 60, the parallel first slabs 30 are connected by the longitudinal seam connecting steel bar 60, and the parallel second slabs 40 are connected by the longitudinal seam connecting steel bar 60.

[0037] In some embodiments of the present invention, the length of the first strap 30 is 6 meters, and the length of the second strap 40 is not less than 8 meters.

[0038] It is understandable that, compared with the existing technology, extending the length of the scaffolding can significantly reduce the changes in the scaffolding angle caused by the settlement of the bridge structure and avoid vehicle jumping at the bridge head.

[0039] It is worth noting that, in some embodiments of the present invention, the first butt plate 30 and the second butt plate 40 are rigid concrete butt plates.

[0040] It is worth noting that the rigid concrete slab has excellent structural rigidity and produces very little deformation.

[0041] It is worth noting that, in some embodiments of the present invention, grouting holes are reserved on the first strap 30 and the second strap 40 .

[0042] Grouting holes are reserved before pouring the scaffolding. After the roadbed below the scaffolding settles, the void area is promptly grouted through the grouting holes. This can reduce the exposure time of the void area below the scaffolding, help reduce the risk of scaffolding damage, and increase the service life of the scaffolding.

[0043] A bridgehead slab construction method suitable for deep soft soil areas comprises the following steps:

[0044] Foundation pit excavation: excavate the foundation pit according to the design requirements, and the width and depth of the foundation pit must meet the design requirements;

[0045] Base treatment: After the foundation pit is excavated, base treatment is carried out to ensure the density of the foundation. If necessary, foundation reinforcement can be carried out, such as laying a gravel cushion or compaction treatment;

[0046] Formwork installation: Install the formwork according to the design size of the slab. The strength and rigidity of the formwork must meet the construction requirements to ensure that it does not deform during concrete pouring.

[0047] Support system: The formwork support system of the slab should be strong to prevent the formwork from shifting during the concrete pouring process;

[0048] Rebar processing: Process and shape the rebar according to the design drawings.

[0049] Rebar binding: Bind the rebars according to the design requirements, paying attention to the spacing between the rebars and the thickness of the protective layer. After binding, conduct a self-inspection to ensure that there are no missing or loose bindings;

[0050] Concrete pouring: pour concrete in layers, with each layer thickness controlled at 25-30cm. Avoid voids or segregation during pouring;

[0051] Vibration and leveling: Use a vibrator to vibrate to ensure that the concrete is dense. After vibration, level the concrete surface;

[0052] Concrete curing: After the initial setting of concrete, water curing is carried out for 7-14 days. During the curing period, the concrete surface should be kept moist.

[0053] Formwork removal: After the concrete reaches the designed strength, the formwork is removed, and attention is paid to the order of formwork removal to avoid damage to the structure;

[0054] Backfill: After removing the formwork, backfill the earth on both sides of the scaffolding. The backfill material should be compacted layer by layer to avoid settlement at the connection between the scaffolding and the roadbed.

[0055] It is worth noting that, in some embodiments of the present invention, grouting holes are reserved before casting the slab, and after settlement of the roadbed under the slab occurs, grouting treatment is promptly performed on the void area through the grouting holes.

[0056] The embodiments of the present invention are described in detail above with reference to the accompanying drawings. However, the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.

Claims

1. A bridgehead slab suitable for deep soft soil areas. It is characterized in that include: A first bolster, a second bolster, a first lap plate and a second lap plate, wherein one end of the first lap plate is overlapped on the first bolster, and the other end is overlapped on the second bolster, one end of the pavement structure is overlapped on the first bolster and connected to the first lap plate, one end of the second lap plate is overlapped on the second bolster, and the other end is overlapped on the abutment, and the second lap plate is hinged to the first lap plate.

2. The bridgehead slab suitable for deep soft soil areas according to claim 1, It is characterized in that The second butt plate is hinged to the first butt plate via hinged steel bars.

3. The bridgehead slab suitable for deep soft soil areas according to claim 1, It is characterized in that It also includes longitudinal seam connecting steel bars, and the first lap boards arranged side by side are connected by the longitudinal seam connecting steel bars, and the second lap boards arranged side by side are connected by the longitudinal seam connecting steel bars.

4. The bridgehead slab suitable for deep soft soil areas according to claim 1, It is characterized in that The length of the first butt board is 6 meters.

5. The bridgehead slab suitable for deep soft soil areas according to claim 1, It is characterized in that The length of the second butt board is not less than 8 meters.

6. The bridgehead slab suitable for deep soft soil areas according to claim 1, It is characterized in that The first butt plate and the second butt plate are rigid concrete butt plates.

7. The bridgehead slab suitable for deep soft soil areas according to claim 1, It is characterized in that Grouting holes are reserved on the first butt plate and the second butt plate.

8. A bridgehead slab construction method suitable for deep soft soil areas. It is characterized in that The following steps are involved: Foundation pit excavation: excavate the foundation pit according to the design requirements, and the width and depth of the foundation pit must meet the design requirements; Base treatment: After the foundation pit is excavated, base treatment is carried out; Formwork installation: Install the formwork according to the design dimensions of the slab. The strength and rigidity of the formwork must meet the construction requirements. Support system: The formwork support system of the slab should be strong to prevent the formwork from shifting during the concrete pouring process; Steel bar processing: Process and shape steel bars according to design drawings; Rebar binding: Bind the rebars according to the design requirements, pay attention to the spacing between the rebars and the thickness of the protective layer, and conduct self-inspection after binding to ensure that there are no missing or loose phenomena; Pouring concrete: Pour concrete in layers, with each layer thickness controlled at 25-30cm. Avoid voids or segregation during pouring; Vibration and leveling: Use a vibrator to vibrate to ensure that the concrete is dense. After the vibration is completed, the concrete surface is leveled; Concrete curing: After the initial setting of concrete, water curing is carried out for 7-14 days. During the curing period, the concrete surface should be kept moist. Formwork removal: After the concrete reaches the designed strength, the formwork is removed, and attention is paid to the order of formwork removal to avoid damage to the structure; Backfill: After removing the formwork, backfill the earth on both sides of the scaffolding. The backfill material should be compacted layer by layer to avoid settlement at the connection between the scaffolding and the roadbed.

9. A bridgehead slab construction method applicable to deep soft soil areas according to claim 8, It is characterized in that Grouting holes are reserved before pouring the slab. After settlement of the roadbed under the slab occurs, grouting treatment is carried out in time to the void area through the grouting holes.