Industrial pipeline bearing hanging bracket
By setting through holes and sliders on the hoisting lugs of the pipe hanger, flexible connection of the hoisting rod is solved, and the problem of the hoisting rod easily deformed when bearing loads is solved. The pipe installation height is achieved through an adjustable hoisting rod structure The flexible adjustment extends the service life of the hanger.
Patent Information
- Application Number
- CN202411770405.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-04
- Publication Date
- 2025-02-07
AI Technical Summary
When the existing pipeline hanger carries carry pipeline loads, the boom is prone to withstand shear stress and torsional stress, resulting in deformation or failure of the connection part, and the boom structure is fixed, making the installation height of the pipe unable to be adjusted.
Design an industrial pipeline load-bearing hanging frame, by setting a through hole on the hanging lug, the first suspender is closed through the through hole through the slider, and has a rotatable degree of freedom to realize the hanging lug and the first suspender. Flexible connection of rods. At the same time, two hanging rods and adjustable connectors are used to achieve height adjustment of the duct support.
The flexible connection reduces the shear stress and torsional stresses that the boom bears, avoids deformation and failure of the hanging frame, extends service life, and achieves convenient adjustment of the pipe installation height.
Smart Images

Figure CN119393593A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pipeline hoisting, and in particular to an industrial pipeline load-bearing hanger. Background Art
[0002] When installing industrial pipelines, special hangers are required to support the pipelines, and the hangers are removed after installation. Pipe hangers are used to bear the load of industrial pipelines and transfer the load to the structural load-bearing components. The structural design of pipe hangers is particularly important for the stability and safety of the overall pipeline system.
[0003] Existing pipe hangers, such as the one disclosed in patent publication number WO2021227485A1, are a kind of high-pressure pipe hanger for the coal chemical industry, which includes a support frame and a connector fixedly connected to the lower surface of the support frame, in which a hanger is installed, and the lower end of the hanger is fixedly connected to the base. The hanger has the following problems: (i) The hanger, the connector and the support frame are rigidly connected. When the pipeline is placed on the base, the hanger is loaded. The rigid connection causes the hanger to be subjected to shear stress and torsional stress, which is easy to cause deformation or failure at the connection between the hanger and the connector, or the connection between the connector and the support frame, affecting the use of the hanger; (ii) The hanger is a single-rod fixed structure, and the base for installing the pipeline cannot be adjusted in height. Summary of the invention
[0004] The object of the present invention is to provide an industrial pipeline load-bearing hanger, which can avoid deformation and failure of the hanger and prolong its service life.
[0005] The technical solution of the present invention is: an industrial pipeline load-bearing hanger, comprising a crossbeam, a lifting lug, a first hanging rod, a fastener, a connecting piece, a second hanging rod and a pipe support for limiting the position of the industrial pipeline; the lifting lug is connected to the lower ends of both sides of the crossbeam in the X direction, the lifting lug is provided with a through hole for the first hanging rod to pass through, the upper end of the first hanging rod is provided with a slider, the slider is in contact with the upper surface of the lifting lug, the through hole passes through in the first direction X, the slider extends in the second direction Y, the first direction X and the second direction Y are perpendicular to each other on the same top projection plane; the lower end of the first hanging rod is connected to the upper end of the connecting piece by a fastener; the upper end of the second hanging rod is connected to the lower end of the connecting piece by a fastener, and the lower ends of the two second hanging rods are connected to the pipe support.
[0006] In the above scheme, a through hole is set on the lifting ear fixedly connected to the crossbeam. After the first hanging rod passes through the through hole, it is limited up and down by a slider and has a rotatable degree of freedom, thereby realizing a flexible connection between the lifting ear and the first hanging rod; when the pipe support is placed on the pipe, the first hanging rod can be adaptively rotated and adjusted due to the load, reducing the shear stress and torsional stress borne by the hanging rod, avoiding deformation and failure of the hanger, and extending its service life.
[0007] Preferably, a plurality of mounting holes are provided in the height direction Z of the connecting member, the first suspension rod is connected to one of the mounting holes on the upper side of the connecting member, and the second suspension rod is connected to one of the mounting holes on the lower side of the connecting member.
[0008] Preferably, the connecting member is provided with an installation groove which passes through from top to bottom, and the first suspension rod and the second suspension rod are connected to the connecting member in the installation groove.
[0009] Preferably, the pipe support includes a base plate, a bracket connected to the base plate, and a support plate connected to the bracket, and the support plate is an arc-shaped plate that is concave in a Z-shape in the height direction.
[0010] Preferably, a polytetrafluoroethylene plate is provided between the slider and the lifting ear.
[0011] Preferably, the crossbeam is an H-shaped steel, and a plurality of lifting ears are arranged in the Y direction of the crossbeam.
[0012] Compared with the related art, the present invention has the following beneficial effects: 1. The present invention sets a through hole on the lifting ear fixedly connected to the crossbeam, and the first hanging rod passes through the through hole and is limited up and down by a slider, and has a rotatable degree of freedom, thereby realizing a flexible connection between the lifting ear and the first hanging rod; when the pipe support is placed on the pipe, the first hanging rod can be adaptively rotated and adjusted due to the load, reducing the shear stress and torsional stress borne by the hanging rod, avoiding deformation and failure of the hanger, and extending its service life; Second, the present invention designs two suspension rods, and the two are connected by a connecting piece, so that the installation height of the pipe support can be adjusted, and more convenient pipeline installation can be achieved; 3. A polytetrafluoroethylene plate is arranged between the slider and the lifting ear to reduce the friction between the two and enhance the stability of the hanger. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 A schematic diagram of the structure of the industrial pipeline load-bearing hanger provided by the present invention; Figure 2 for Figure 1 Schematic diagram of A-direction projection.
[0014] In the attached drawings: 1. cross beam; 2. lifting ear; 21. through hole; 3. slider; 4. polytetrafluoroethylene plate; 5. first hanger; 6. fastener; 7. connector; 71. mounting hole; 72. mounting groove; 8. second hanger; 9. pipe support; 91. bottom plate; 92. bracket; 93. support plate; 10. pipeline. DETAILED DESCRIPTION
[0015] The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments. It should be noted that the embodiments of the present invention and the features in the embodiments can be combined with each other without conflict. For the convenience of description, if the words "upper", "lower", "left" and "right" appear in the following, they only indicate that the upper, lower, left and right directions are consistent with the drawings themselves, and do not limit the structure.
[0016] like Figure 1 , Figure 2 As shown, an industrial pipeline load-bearing hanger provided in this embodiment includes a crossbeam 1, a lifting ear 2, a slider 3, a polytetrafluoroethylene plate 4, a first hanging rod 5, a fastener 6, a connecting piece 7, a second hanging rod 8 and a pipe support 9.
[0017] The cross beam 1 is an H-shaped steel and is an integral load-bearing component of the hanger.
[0018] The lifting lug 2 is a U-shaped structure made of carbon steel and welded to the cross beam 1. A lifting lug 2 is arranged at each lower end of both sides of the cross beam 1 in the X direction to form a group, and multiple lifting lugs 2 can be arranged in the Y direction of the cross beam 1 according to the length of the pipeline 10.
[0019] like Figure 2 As shown, the lifting ear 2 is provided with a through hole 21 for the first lifting rod 5 to pass through, and the through hole 21 extends along the first direction X to form a rectangular hole.
[0020] A slider 3 is provided at the upper end of the first suspension rod 5. After the first suspension rod 5 passes through the through hole 21, the slider 3 contacts the upper surface of the lifting ear 2. The slider 3 extends along the second direction Y. The first direction X and the second direction Y are perpendicular to each other on the same top projection plane.
[0021] like Figure 1 As shown, a polytetrafluoroethylene plate 4 is provided between the slider 3 and the lifting ear 2 to reduce friction and enhance the stability of the hanger.
[0022] The connecting member 7 is a sleeve tube, and a mounting groove 72 is provided inside the connecting member 7. The inner cavity size of the mounting groove 72 is adapted to the cross-sectional size of the suspension rod. A plurality of mounting holes 71 are provided on the side wall of the connecting member 7 forming the mounting groove 72, and the plurality of mounting holes 71 are arranged in the height direction Z.
[0023] The first suspension rod 5 and the second suspension rod 8 are both made of carbon steel. The lower end of the first suspension rod 5 and the upper end of the second suspension rod 8 are both provided with connection holes. The lower end of the first suspension rod 5 is inserted into the mounting groove 72, so that the connection hole thereon is connected to one of the groups of mounting holes 71 on the upper side of the connector 7 through fasteners 6 (including bolts, nuts, washers, etc.). The upper end of the second suspension rod 8 is inserted into the mounting groove 72, so that the connection hole thereon is connected to one of the groups of mounting holes 71 on the lower side of the connector 7 through fasteners 6. In this way, the height position of the pipe bracket 9 fixed at the lower end of the second suspension rod 8 can be adjusted.
[0024] The pipe support 9 includes a bottom plate 91, a bracket 92 connected to the bottom plate 91, and a support plate 93 connected to the bracket 92. The support plate 93 is an arc-shaped plate that is concave in the height direction Z.
[0025] The extension length of the bottom plate 91 and the support plate 93 in the Y direction can cover all the ears 2 in the Y direction, and can also adopt an intermittent structure.
[0026] When in use, the pipe 10 is placed on the support plate 93, and the lower surface of the pipe 10 is limited by the arc surface of the support plate 93. The height of the pipe support 9 can be adjusted in advance as needed.
[0027] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. An industrial pipeline load-bearing hanger, comprising a crossbeam (1), characterized in that: It also comprises a lifting lug (2), a first lifting rod (5), a fastener (6), a connecting piece (7), a second lifting rod (8) and a pipe support (9) for limiting the position of an industrial pipeline; the lifting lug (2) is connected to the lower ends of both sides of the crossbeam (1) in the X direction; the lifting lug (2) is provided with a through hole (21) for the first lifting rod (5) to pass through; the upper end of the first lifting rod (5) is provided with a slider (3), the slider (3) is in contact with the upper surface of the lifting lug (2); the through hole (21) passes through in a first direction X; the slider (3) extends in a second direction Y; the first direction X and the second direction Y are perpendicular to each other on the same top projection plane; the lower end of the first lifting rod (5) is connected to the upper end of the connecting piece (7) through a fastener (6); the upper end of the second lifting rod (8) is connected to the lower end of the connecting piece (7) through a fastener (6); the lower ends of the two second lifting rods (8) are connected to the pipe support (9).
2. The industrial pipeline load-bearing hanger according to claim 1, characterized in that: The connecting member (7) is provided with a plurality of groups of mounting holes (71) in the height direction Z, the first suspension rod (5) is connected to one group of mounting holes (71) on the upper side of the connecting member (7), and the second suspension rod (8) is connected to one group of mounting holes (71) on the lower side of the connecting member (7).
3. The industrial pipeline load-bearing hanger according to claim 1, characterized in that: The connecting member (7) is provided with a mounting groove (72) which passes through from top to bottom, and the first suspension rod (5) and the second suspension rod (8) are connected to the connecting member (7) in the mounting groove (72).
4. The industrial pipeline load-bearing hanger according to any one of claims 1 to 3, characterized in that: The pipe support (9) comprises a bottom plate (91), a bracket (92) connected to the bottom plate (91), and a support plate (93) connected to the bracket (92); the support plate (93) is an arc-shaped plate that is concave in a Z-shape in a height direction.
5. The industrial pipeline load-bearing hanger according to any one of claims 1 to 3, characterized in that: A polytetrafluoroethylene plate (4) is provided between the sliding block (3) and the lifting ear (2).
6. The industrial pipeline load-bearing hanger according to any one of claims 1 to 3, characterized in that: The crossbeam (1) is an H-shaped steel, and a plurality of the lifting ears (2) are arranged in the Y direction of the crossbeam (1).
Citation Information
Patent Citations
High-pressure pipe hanging frame for coal chemical industry
WO2021227485A1
Novel support hanger assembly
CN212056140U
Novel anti-seismic support hanger
CN212839805U
Water pipeline hanging bracket
CN213117783U
Support hanger device for fixing pipeline
CN215487999U