Combined supply system based on storage tank BOG
By designing a joint supply system in LNG storage tanks, the BOG's cold energy is recovered and used as fuel for fuel cells, efficient energy utilization and comprehensive efficiency improvement is achieved, the problem of unused BOG's cold energy is solved, and the system's adaptation is enhanced Sex and reliability.
Patent Information
- Application Number
- CN202420859497.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-24
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-24
AI Technical Summary
The BOG cold energy generated in existing LNG storage tanks has not been effectively utilized, and the energy utilization efficiency of fuel cells is low. A method is needed to recover the BOG cold energy and use it as fuel of fuel cells to improve overall efficiency.
A joint supply system based on the storage tank BOG is designed, including a storage tank, a first heat exchanger, a second heat exchanger, a buffer tank and a fuel cell. The BOG is entered into the buffer tank through a pressurized pump and serves as fuel for the fuel cell. , and use the BOG's cold energy to generate electricity through the heat exchange circulation loop, and combine the working fluid pump and the expander for power supply in multiple ways.
It realizes efficient recycling and utilization of BOG cooling energy, improves the comprehensive efficiency of fuel cells and the adaptability of the joint supply system, enhances the reliability of the system, and has the advantages of simple structure, convenient operation and low maintenance costs.
Smart Images

Figure CN222068266U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of energy utilization, and more specifically, the utility model is a joint supply system based on storage tank BOG. Background Art
[0002] When the liquefied natural gas (LNG) storage tank is in a static state or in a state of disturbance caused by unloading or loading, the LNG stored in the tank will produce boil-off gas (BOG) due to heat absorption. There are two processing procedures for BOG in existing LNG receiving stations. One is that BOG is directly compressed and transported; the other is that BOG is recondensed and returned to the storage tank. The BOG direct compression method is adopted, that is, the BOG discharged from the LNG storage tank is sent to the compressor room for pressurization and then sent to the natural gas pipeline for use by downstream city gas users. In this case, the cold energy of BOG is not recovered, and at the same time, pressurizing a large amount of BOG also consumes a lot of energy.
[0003] A fuel cell is an electrochemical device that converts chemical energy directly into electrical energy. Unlike ordinary batteries, fuel cells will continue to generate electricity as long as the continuous supply of fuel is guaranteed. Fuel cells do not need to generate electricity by driving power devices through fuel combustion like gas internal combustion engines and gas turbines, but instead rely on electrochemical reactions to generate electricity, which makes the entire working process very quiet and pollution-free. The power generation efficiency is 2 to 3 times higher than traditional power generation methods, achieving true zero emissions. Solid oxide fuel cells (SOFC) are currently the most efficient power generation technology in the world, with an operating temperature of 800°C to 1000°C and no NO emissions. X 、SO X and solid particulate matter, which will help accelerate the transformation of energy strategy.
[0004] Therefore, how to reasonably utilize BOG in combination with fuel cells has become a technical problem that needs to be solved urgently and a research focus for those skilled in the art. Utility Model Content
[0005] The utility model aims to provide a combined supply system based on BOG storage tanks, which can recover the cold energy of BOG for power generation and use BOG as fuel cell fuel, forming a combined supply system based on BOG cold energy power generation and fuel cell, thereby improving the comprehensive efficiency of the fuel cell and the adaptability of the combined supply system.
[0006] In order to achieve the above technical objectives, the embodiment of the utility model discloses a cogeneration system based on a storage tank BOG, including a storage tank, a first heat exchanger, a second heat exchanger, a buffer tank and a fuel cell. LNG is stored in the storage tank. BOG formed by evaporation of LNG in the storage tank enters the buffer tank through the primary side of the first heat exchanger through a pressure pump installed on the top of the storage tank. The BOG in the buffer tank is used as fuel for the fuel cell. The electric energy generated by the fuel cell is transmitted to the power supply bus through the first conductive bar. The cooling water inlet and outlet of the fuel cell are connected to the secondary side of the second heat exchanger through a water pump to form a first heat exchange circulation loop. The second heat exchanger The primary side of the heat exchanger is connected to the secondary side of the first heat exchanger to form a second heat exchange circulation loop, a working fluid pump is installed on the pipeline between the secondary side outlet of the first heat exchanger and the primary side inlet of the second heat exchanger, an expander is installed on the pipeline between the secondary side inlet of the first heat exchanger and the primary side outlet of the second heat exchanger, the output shaft of the expander is connected to a generator, the electric energy generated by the generator is transmitted to the power supply bus through the second conductive bar, the power supply bus is connected to the first transformer, one end of the power supply bus is connected to the public power grid bus through the second transformer, and the other end of the power supply bus is connected to the user's intranet bus through the third transformer.
[0007] Furthermore, the utility model provides a cogeneration system based on a storage tank BOG, which also includes an absorption chiller, wherein the water inlet of the absorption chiller is connected to the water outlet of the fuel cell cooling water, the water outlet of the absorption chiller is connected to the secondary side inlet of the second heat exchanger, and the absorption chiller is also provided with a cold water circulation interface.
[0008] Furthermore, the utility model provides a cogeneration system based on storage tank BOG, which also includes an submerged combustion gasifier, wherein the primary water inlet of the submerged combustion gasifier is connected to the cooling water outlet of the fuel cell, the primary water outlet of the submerged combustion gasifier is connected to the secondary inlet of the second heat exchanger, LNG is introduced into the secondary air inlet of the submerged combustion gasifier, the secondary air outlet of the submerged combustion gasifier is connected to the city gas pipeline, and a hot water circulation interface is also provided on the submerged combustion gasifier.
[0009] Furthermore, the utility model provides a cogeneration system based on a BOG storage tank, wherein the water pump is installed on the pipeline between the secondary side outlet of the second heat exchanger and the cooling water inlet of the fuel cell, and the first switch valve and the second switch valve are installed in sequence on the pipeline between the secondary side inlet of the second heat exchanger and the cooling water outlet of the fuel cell according to the water flow direction.
[0010] Furthermore, the utility model provides a cogeneration system based on a BOG storage tank, wherein a third switch valve is installed on the pipeline between the cooling water outlet of the fuel cell and the water inlet of the absorption chiller, and a fourth switch valve is installed on the pipeline between the water outlet of the absorption chiller and the secondary side water inlet of the second heat exchanger, one end of the fourth switch valve is connected to the water outlet of the absorption chiller, and the other end of the fourth switch valve is connected to the pipeline between the first switch valve and the second switch valve.
[0011] Furthermore, the utility model provides a cogeneration system based on a storage tank BOG, wherein a fifth switch valve is installed on the pipeline between the primary water inlet of the submerged combustion gasifier and the cooling water outlet of the fuel cell, and a sixth switch valve is installed on the pipeline between the primary water outlet of the submerged combustion gasifier and the secondary inlet of the second heat exchanger, and the water outlet of the sixth switch valve is connected to the pipeline between the second switch valve and the secondary inlet of the second heat exchanger.
[0012] Furthermore, the utility model provides a joint supply system based on storage tank BOG, wherein an air supply pump is installed on the pipeline between the buffer tank and the city gas pipeline, and the outlet of the air supply pump and the secondary side outlet of the submerged combustion gasifier are connected to the city gas pipeline.
[0013] Furthermore, the utility model provides a joint supply system based on a storage tank BOG, wherein an air supply pipeline is connected between the buffer tank and the submerged combustion gasifier, and an air supply switch valve is installed on the air supply pipeline.
[0014] Compared with the prior art, the utility model has the following advantages in a combined supply system based on a storage tank BOG: the system includes core components such as a storage tank, a first heat exchanger, a second heat exchanger, a buffer tank and a fuel cell. Through a series of heat exchange and energy conversion processes, the recovery and utilization of BOG cold energy is realized, and the comprehensive efficiency of the fuel cell and the adaptability of the combined supply system are improved. The storage tank is the starting point of the system, and LNG is stored inside. In the storage tank, part of the LNG will evaporate to form BOG. After these BOGs are pressurized by a pressure pump installed on the top of the storage tank, they pass through the primary side of the first heat exchanger and further enter the buffer tank. In this process, the cold energy of BOG is effectively utilized, providing cold energy for the system. At the same time, the pressurized BOG is sent to the fuel cell as fuel, realizing its reuse as energy. The fuel cell converts the chemical energy in the BOG into electrical energy through a chemical reaction. The generated electrical energy is directly transmitted to the power supply bus. In addition, the heat generated by the fuel cell during operation is dissipated through cooling water. The inlet and outlet of the cooling water are connected to the secondary side of the second heat exchanger to form a first heat exchange circulation loop. Through this loop, the heat generated by the fuel cell is transferred and dissipated using the cold energy of BOG, ensuring the stable operation of the fuel cell. The primary side of the second heat exchanger is connected to the secondary side of the first heat exchanger to form a second heat exchange circulation loop. In this loop, the working fluid pump is responsible for driving the circulating working fluid to flow in the loop, while the expander uses the pressure energy and thermal energy of the working fluid to generate electricity. The output shaft of the expander is connected to a generator, which converts the mechanical energy output by the expander into electrical energy and transmits it to the power supply bus again. The power supply bus is connected to a first transformer, one end of the power supply bus is connected to the public power grid bus through the second transformer, and the other end of the power supply bus is connected to the user's intranet bus through the third transformer. The innovation of the utility model lies in combining the cold energy recovery of BOG with power generation and fuel cell energy utilization to form an efficient combined power supply system. Through this system, not only the effective utilization of BOG and the efficient recovery of energy are achieved through a series of heat exchange and energy conversion processes, the comprehensive efficiency of the fuel cell is improved, but also the adaptability and reliability of the combined power supply system are enhanced. In addition, the system also has the advantages of simple structure, convenient operation and low maintenance cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a structural schematic diagram of a cogeneration system based on BOG storage tank in the utility model. DETAILED DESCRIPTION
[0016] The following is a detailed explanation and description of a cogeneration system based on BOG storage tank and a control method thereof of the utility model in conjunction with the drawings of the specification.
[0017] like Figure 1As shown, the embodiment of the utility model discloses a combined supply system based on a storage tank 1 BOG, including a storage tank 1, a first heat exchanger 2, a second heat exchanger 3, a buffer tank 4 and a fuel cell 5. LNG is stored in the storage tank 1, and the BOG formed by evaporation of the LNG in the storage tank 1 enters the buffer tank 4 through the primary side of the first heat exchanger 2 through the booster pump 6 installed on the top of the storage tank 1, so that the BOG in the buffer tank 4 is used as the fuel of the fuel cell 5, and the electric energy generated by the fuel cell 5 is transmitted to the power supply bus 8 through the first conductive bar 7. The cooling water inlet and outlet of the fuel cell 5 are connected to the secondary side of the second heat exchanger 3 through the water pump 9 to form a first heat exchange circulation loop, which is used to cool down the inside of the fuel cell 5. The primary side of the second heat exchanger 3 is connected to the secondary side of the first heat exchanger 2 to form a second heat exchange circulation loop for generating electricity using the cold energy of BOG. More specifically, a working fluid pump 10 is installed on the pipeline between the secondary side outlet of the first heat exchanger 2 and the primary side inlet of the second heat exchanger 3, and an expander 11 is installed on the pipeline between the secondary side inlet of the first heat exchanger 2 and the primary side outlet of the second heat exchanger 3. The output shaft of the expander 11 is connected to a generator 12, and the electric energy generated by the generator 12 is transmitted to the power supply bus 8 through the second conductive bar 13. The power supply bus 8 is connected to a first transformer 26, one end of the power supply bus 8 is connected to a public power grid bus through a second transformer 27, and the other end of the power supply bus 8 is connected to a user intranet bus through a third transformer 28.
[0018] In actual use, the storage tank 1 is the starting point of the combined supply system, and LNG is stored inside. The fuel cell 5 adopts a solid oxide fuel cell 5 (SOFC). In the storage tank 1, part of the LNG will evaporate to form BOG. After these BOGs are pressurized by the booster pump 6, they pass through the primary side of the first heat exchanger 2 and further enter the buffer tank 4. In this process, the cold energy of the BOG can be effectively utilized by the first heat exchanger 2 to provide cold energy for the second heat exchange circulation loop. At the same time, the pressurized BOG is sent to the fuel cell 5 as fuel, realizing its reuse as energy. The fuel cell 5 converts the chemical energy in the BOG into electrical energy through chemical reactions, and the generated electrical energy is directly transmitted to the power supply bus 8. In addition, the heat generated by the fuel cell 5 during operation is dissipated through cooling water. The inlet and outlet of the cooling water of the fuel cell 5 are connected to the secondary side of the second heat exchanger 3, forming a first heat exchange circulation loop. Through this loop, the heat generated by the fuel cell 5 is transmitted and dissipated using the cold energy of the BOG, ensuring the stable operation of the fuel cell 5. The primary side of the second heat exchanger 3 is connected to the secondary side of the first heat exchanger 2, forming a second heat exchange circulation loop. In this loop, the working fluid pump 10 is responsible for driving the circulating working fluid to flow in the loop, and the expander 11 uses the pressure energy and thermal energy of the working fluid to generate electricity. The output shaft of the expander 11 is connected to the generator 12, which converts the mechanical energy output by the expander 11 into electrical energy and transmits it to the power supply bus 8 again. The electrical energy generated by the fuel cell 5 and the generator 12 is transmitted to the power supply bus 8, forming a multi-mode joint power supply system. The electrical energy generated by the generator 12 and the fuel cell 5 can be adjusted by the first transformer 26 and incorporated into the intranet of the electricity user, and adjusted to the appropriate power voltage for the user by the third transformer 28. The excess electrical energy of the generator 12 can be adjusted by the second transformer 27 and incorporated into the public power grid. In the second heat exchange circulation loop, more specifically, after the working fluid pump 10 is started, the low-temperature and low-pressure liquid working fluid in the second heat exchange circulation loop is converted into a high-pressure and low-temperature liquid working fluid under the action of the working fluid pump 10. The high-pressure and low-temperature liquid working fluid passes through the primary side of the second heat exchanger 3 and absorbs the heat of the cooling water in the secondary side of the second heat exchanger 3 to be converted into a high-pressure and high-temperature gaseous working fluid. After the high-pressure and high-temperature gaseous working fluid is supplied to the expander 11, the expander 11 works to convert the high-pressure and high-temperature gaseous working fluid into a low-pressure and high-temperature liquid-gas working fluid. The low-pressure and high-temperature liquid-gas working fluid passes through the secondary side of the first heat exchanger 2 and absorbs the cold energy of BOG in the primary side of the first heat exchanger 2, so that the low-pressure and high-temperature gaseous working fluid is converted into a low-pressure and low-temperature liquid working fluid and returns to the working fluid pump 10, forming a working fluid cycle. In this process, when the expander 11 works, the output shaft drives the generator 12 to rotate to generate electricity. In summary, the innovation of this system lies in combining the cold energy recovery of BOG with power generation and energy utilization of the fuel cell 5 to form an efficient joint supply system.Through this system, not only the effective utilization of BOG and efficient recovery of energy are achieved through a series of heat exchange and energy conversion processes, the overall efficiency of the fuel cell 5 is improved, but also the adaptability and reliability of the combined power supply system are enhanced. In addition, the system also has the advantages of simple structure, convenient operation and low maintenance cost.
[0019] In one embodiment of the utility model, on the basis of the above embodiment, an absorption chiller 14 and an immersed combustion gasifier 15 are also included. The water inlet of the absorption chiller 14 is connected to the water outlet of the cooling water of the fuel cell 5, and the water outlet of the absorption chiller 14 is connected to the secondary side inlet of the second heat exchanger 3. The absorption chiller 14 is also provided with a cold water circulation interface 24. More specifically, the water inlet of the absorption chiller 14 is actually the hot water inlet of the generator in the absorption chiller 14. Through this connection structure, the hot water flowing out of the cooling water outlet of the fuel cell 5 flows back through the water inlet of the absorption chiller 14 into the generator inside it to provide the required heat for it. However, the generator cannot absorb all the heat of the cold water. The cooling water flowing out of the generator will flow into the secondary side of the second heat exchanger 3, and the cooling water will be recovered by the second heat exchanger 3. This step not only helps to increase the temperature of the working medium in the first heat exchange circulation loop, but also allows most of the heat to be recovered. The cooling water after secondary heat recovery will flow back to the fuel cell 5 through the secondary side outlet of the second heat exchanger 3 and the water pump 9, and continue to be used for cooling the fuel cell 5. The cooling water is circulated back and forth through the water pump 9 to ensure that the absorption chiller 14 is always supplied with hot water. In this way, the absorption chiller 14 can continuously use the internal evaporator to produce chilled water, and this chilled water can be used by external cold equipment through the cold water circulation interface 24 for refrigeration. Through this setting, the heat energy generated by the fuel cell 5 is fully utilized, thereby effectively reducing energy waste. This heat recovery method not only improves energy utilization efficiency, but also helps to reduce environmental pollution and achieve green and sustainable development. The primary water inlet of the submerged combustion gasifier 15 is connected to the cooling water outlet of the fuel cell 5, the primary water outlet of the submerged combustion gasifier 15 is connected to the secondary inlet of the second heat exchanger 3, the secondary air inlet of the submerged combustion gasifier 15 is fed with LNG, the secondary air outlet of the submerged combustion gasifier 15 is connected to the city gas pipeline, and the submerged combustion gasifier 15 is also provided with a hot water circulation interface 25. Through this connection structure, the cooling water from the cooling water outlet of the fuel cell 5 flows through the submerged combustion gasifier 15, the submerged combustion gasifier 15 absorbs part of the heat of the cooling water to gasify LNG, and supplies it to the heating equipment through the hot water circulation interface 25 for heating. After the residual heat of the cooling water is heat-exchanged between the secondary side of the second heat exchanger 3 and its own primary side, this step not only helps to increase the temperature of the working medium in the first heat exchange circulation loop, but also allows most of the heat to be recovered. In this way, the heat energy generated by the fuel cell 5 is fully utilized, thereby effectively reducing energy waste. Through this arrangement, the heat energy generated by the fuel cell 5 can be effectively utilized, achieving efficient use of energy and reducing waste.
[0020] In one embodiment of the utility model, a water pump 9 is installed on the pipeline between the secondary side outlet of the second heat exchanger 3 and the cooling water inlet of the fuel cell 5, and is used to provide power for fluid circulation for the first heat exchange circulation loop. A first switch valve 16 and a second switch valve 17 are installed in sequence on the pipeline between the secondary side inlet of the second heat exchanger 3 and the cooling water outlet of the fuel cell 5 according to the water flow direction. A third switch valve 18 is installed on the pipeline between the cooling water outlet of the fuel cell 5 and the water inlet of the absorption chiller 14, and a fourth switch valve 19 is installed on the pipeline between the water outlet of the absorption chiller 14 and the secondary side water inlet of the second heat exchanger 3. One end of the fourth switch valve 19 is connected to the water outlet of the absorption chiller 14, and the other end of the fourth switch valve 19 is connected to the pipeline between the first switch valve 16 and the second switch valve 17. A fifth switch valve 20 is installed on the pipeline between the primary water inlet of the submerged combustion gasifier 15 and the cooling water outlet of the fuel cell 5, and a sixth switch valve 21 is installed on the pipeline between the primary water outlet of the submerged combustion gasifier 15 and the secondary inlet of the second heat exchanger 3. The outlet of the sixth switch valve 21 is connected to the pipeline between the second switch valve 17 and the secondary inlet of the second heat exchanger 3. Through this arrangement, three parallel pipelines can be formed between the cooling water outlet of the fuel cell 5 and the secondary inlet of the second heat exchanger. In more detail, the first pipeline is the pipeline where the first switch valve 16 is located; the second pipeline is the pipeline where the third switch valve 18, the absorption chiller 14, and the fourth switch valve 19 are located; and the opening and closing of the first pipeline and the second pipeline are controlled by the second switch valve 17; the third pipeline is the pipeline where the fifth switch valve 20, the submerged combustion gasifier 15 and the sixth switch valve 21 are located. This not only increases the flexibility of the system, but also provides operators with more options, allowing them to finely control the cooling water circuit according to different operating conditions and external environmental conditions. In other words, by controlling the on and off of the relevant switch valves, operators can flexibly choose which pipeline to participate in the first heat exchange circulation loop to adapt to different operating requirements and environmental conditions. This setting not only improves the adaptability of the system, but also makes the cooling process more precise and efficient.
[0021] In one embodiment of the utility model, an air supply pump 22 is installed on the pipeline between the buffer tank 4 and the city gas pipeline. The outlet of the air supply pump 22 and the secondary side outlet of the submerged combustion gasifier 15 are connected to the city gas pipeline, thereby absorbing the excess BOG and avoiding waste of resources. An air supply pipeline is connected between the buffer tank 4 and the submerged combustion gasifier 15, and an air supply switch valve 23 is installed on the air supply pipeline. When the gasifier 15 is insufficient in heat, the air supply switch valve 23 can be quickly opened to supply fuel to the gasifier 15, thereby increasing heat and meeting its operating requirements. This setting improves the economy of the BOG recovery project and reduces the energy consumption of BOG processing.
[0022] Based on the unified concept, the utility model provides a control method for a joint supply system based on a storage tank 1BOG, comprising the following steps:
[0023] Close the absorption chiller 14, the submerged combustion gasifier 15, the third switch valve 18, the fourth switch valve 19, the fifth switch valve 20 and the sixth switch valve 21;
[0024] The booster pump 6 is started to make the BOG evaporated in the storage tank 1 absorb heat on the primary side of the first heat exchanger 2 and then be stored in the buffer tank 4, and one part of the BOG in the buffer tank 4 is supplied to the fuel cell 5 and the other part is supplied to the city gas pipeline;
[0025] The working fluid pump 10 is started to convert the low-temperature and low-pressure liquid working fluid in the second heat exchange circulation loop into a high-pressure and low-temperature liquid working fluid, and the high-pressure and low-temperature liquid working fluid is converted into a high-pressure and high-temperature gaseous working fluid through the primary side of the second heat exchanger 3, and the high-pressure and high-temperature gaseous working fluid is converted into a low-pressure and high-temperature liquid working fluid through the expansion machine 11; the low-pressure and high-temperature gaseous working fluid is converted into a low-pressure and low-temperature liquid working fluid through the secondary side of the first heat exchanger 2 and returns to the working fluid pump 10, forming a working fluid cycle, and the output shaft drives the generator 12 to rotate when the expansion machine 11 is working;
[0026] Start the water pump 9, and open the first switch valve 16 and the second switch valve 17, so that the cooling water flows from the outlet of the water pump 9 through the cooling water inlet of the fuel cell 5, the cooling water outlet of the fuel cell 5, the first switch valve 16, the second switch valve 17, the secondary side inlet of the second heat exchanger 3 and the secondary side outlet of the second heat exchanger, and then returns to the inlet of the water pump 9, forming a cooling water cycle;
[0027] The electric energy generated by the generator 12 is transmitted to the power supply bus 8 through the first conductive bar 7, and the electric energy generated by the fuel cell 5 is transmitted to the power supply bus 8 through the second conductive bar 13, thereby forming a combined power supply system.
[0028] Based on the above embodiment, the following steps are also included:
[0029] 1. In summer conditions, the second switch valve 17, the third switch valve 18 and the fourth switch valve 19 are opened, and the first switch valve 16, the fifth switch valve 20 and the sixth switch valve 21 are closed; the absorption chiller 14 is started, so that the cooling water at the cooling water outlet of the fuel cell 5 flows through the absorption chiller 14, and the absorption chiller 14 absorbs part of the heat of the cooling water to generate cold water for use by the cold equipment through the cold water circulation interface 24, and the secondary side of the second heat exchanger 3 uses the residual heat of the cooling water to perform heat exchange with its own primary side, so as to provide heat for the working medium circulation;
[0030] 2. Under winter working conditions, the fifth switch valve 20 and the sixth switch valve 21 are opened, and the first switch valve 16, the second switch valve 17, the third switch valve 18 and the fourth switch valve 19 are closed; the submerged combustion gasifier 15 is started, and the absorption chiller 14 is closed; the cooling water at the cooling water outlet of the fuel cell 5 flows through the submerged combustion gasifier 15, and the submerged combustion gasifier 15 absorbs part of the heat of the cooling water to gasify the LNG, and supplies it to the heating equipment through the hot water circulation interface 25; and the secondary side of the second heat exchanger 3 uses the residual heat of the cooling water to exchange heat with its own primary side to provide heat for the working medium circulation; when the heat required for LNG gasification is insufficient, the air supply switch valve 23 is opened, so that the BOG in the buffer tank 4 enters the submerged combustion gasifier 15 through the air supply pipeline for combustion and heat supplement.
[0031] In this embodiment, the control method can not only flexibly adjust the system operation mode according to the changes in seasons and working conditions, improve energy utilization efficiency, but also ensure the stability and reliability of the system. At the same time, the method also has strong adaptability and scalability, which not only improves energy utilization efficiency and reduces operating costs, but also makes positive contributions to environmental protection and sustainable development.
[0032] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0033] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0034] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present utility model, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0035] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modification, equivalent replacement and simple improvement made to the essential content of the present invention shall be included in the protection scope of the present invention.
Claims
1. A joint supply system based on BOG storage tank, Features: The invention comprises a storage tank, a first heat exchanger, a second heat exchanger, a buffer tank and a fuel cell. LNG is stored in the storage tank. BOG formed by evaporation of LNG in the storage tank enters the buffer tank through the primary side of the first heat exchanger via a pressure pump installed on the top of the storage tank. The BOG in the buffer tank is used as fuel for the fuel cell. The electric energy generated by the fuel cell is transmitted to the power supply bus through a first conductive bar. The cooling water inlet and outlet of the fuel cell are connected to the secondary side of the second heat exchanger through a water pump to form a first heat exchange circulation loop. The primary side of the second heat exchanger is connected to the secondary side of the first heat exchanger to form a second heat exchange circulation loop. A working fluid pump is installed on the pipeline between the secondary side outlet of the first heat exchanger and the primary side inlet of the second heat exchanger. An expander is installed on the pipeline between the secondary side inlet of the first heat exchanger and the primary side outlet of the second heat exchanger. The output shaft of the expander is connected to a generator. The electric energy generated by the generator is transmitted to the power supply bus through a second conductive bar. The power supply bus is connected to a first transformer. One end of the power supply bus is connected to a public power grid bus through a second transformer, and the other end of the power supply bus is connected to a user intranet bus through a third transformer.
2. A combined supply system based on BOG storage tank according to claim 1, Features: It also includes an absorption chiller, the water inlet of the absorption chiller is connected to the outlet of the fuel cell cooling water, the outlet of the absorption chiller is connected to the secondary side inlet of the second heat exchanger, and the absorption chiller is also provided with a cold water circulation interface.
3. A combined supply system based on BOG storage tank according to claim 2, Features: It also includes an submerged combustion gasifier, wherein the primary water inlet of the submerged combustion gasifier is connected to the cooling water outlet of the fuel cell, the primary water outlet of the submerged combustion gasifier is connected to the secondary inlet of the second heat exchanger, LNG is introduced into the secondary air inlet of the submerged combustion gasifier, the secondary air outlet of the submerged combustion gasifier is connected to the city gas pipeline, and a hot water circulation interface is also provided on the submerged combustion gasifier.
4. A combined supply system based on BOG storage tank according to claim 3, Features: The water pump is installed on the pipeline between the secondary side outlet of the second heat exchanger and the cooling water inlet of the fuel cell. The first switch valve and the second switch valve are installed in sequence on the pipeline between the secondary side inlet of the second heat exchanger and the cooling water outlet of the fuel cell according to the water flow direction.
5. A combined supply system based on BOG storage tank according to claim 4, Features: A third switch valve is installed on the pipeline between the cooling water outlet of the fuel cell and the water inlet of the absorption chiller, and a fourth switch valve is installed on the pipeline between the water outlet of the absorption chiller and the secondary side water inlet of the second heat exchanger. One end of the fourth switch valve is connected to the water outlet of the absorption chiller, and the other end of the fourth switch valve is connected to the pipeline between the first switch valve and the second switch valve.
6. A combined supply system based on BOG storage tank according to claim 5, Features: A fifth switch valve is installed on the pipeline between the primary water inlet of the submerged combustion gasifier and the cooling water outlet of the fuel cell, and a sixth switch valve is installed on the pipeline between the primary water outlet of the submerged combustion gasifier and the secondary inlet of the second heat exchanger. The water outlet of the sixth switch valve is connected to the pipeline between the second switch valve and the secondary inlet of the second heat exchanger.
7. A combined supply system based on BOG storage tank according to claim 6, Features: An air supply pump is installed on the pipeline between the buffer tank and the city gas pipeline, and the outlet of the air supply pump and the secondary side air outlet of the submerged combustion gasifier are communicated with the city gas pipeline.
8. A combined supply system based on BOG storage tank according to claim 7, Features: An air supply pipeline is connected between the buffer tank and the submerged combustion gasifier, and an air supply switch valve is installed on the air supply pipeline.
Citation Information
Cited By
Combined supply system based on storage tank BOG and control method thereof
CN118293356A
A combined supply system based on tank BOG and a control method thereof
CN118293356B