ZrN plasma preparation system

By increasing the heat dissipation contact area and adjusting the plasma torch position in the ZrN plasma preparation system, the problem of poor heat dissipation effect of the plasma torch is solved, and the preparation efficiency and preparation effect are improved.

CN222192622UActive Publication Date: 2024-12-17WUHAN MERTING ENVIRONMENTAL PROTECTION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420803388.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-18
Publication Date
2024-12-17
Estimated Expiration
2034-04-18

AI Technical Summary

Technical Problem

The heat dissipation effect of the plasma torch during the preparation of existing ZrN plasma is poor, which affects the preparation efficiency.

Method used

A preparation system including arc furnace body, graphite crucible, plasma torch, cooling water pump, air-cooled pump and hydraulic pump group was designed. By setting up the left frame plate, the right frame plate and the heat dissipation hole, the heat dissipation contact area is increased, and the heat dissipation contact area is used. The hydraulic pump set adjusts the position of the plasma torch to improve preparation efficiency.

Benefits of technology

It effectively improves the heat dissipation effect of the plasma torch, ensures the high temperature state of the reactants inside the graphite crucible, and improves the preparation efficiency of ZrN and the overall performance of the preparation system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222192622U_ABST
    Figure CN222192622U_ABST
Patent Text Reader

Abstract

The utility model discloses a ZrN plasma preparation system, relates to the field of ZrN preparation, solves the problem that the subsequent preparation efficiency is possibly influenced due to the poor heat dissipation effect of a plasma torch in the existing preparation process, and adopts the following scheme that the ZrN plasma preparation system comprises an electric arc furnace body and a graphite crucible; a plasma torch is placed in a graphite crucible on the inner side of the electric arc furnace body, an electrode body is fixedly installed at the bottom end of the plasma torch, a power line and a water inlet pipe are fixedly connected to the top side of the plasma torch, and the outer end of the water inlet pipe communicates with an air cooling pump. The outer wall of the plasma torch is fixedly connected with an air pipe and a drainage pipe, and the outer end of the air pipe is communicated with a cooling water pump; according to the ZrN plasma preparation system, the electric arc furnace body and components on the top side of the electric arc furnace body are arranged, the plasma torch and the electrode body on the bottom side of the plasma torch can be utilized, the inner side of the graphite crucible can be in a high-temperature state, so that reactants on the inner side of the graphite crucible are heated, and the ZrN preparation effect is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of ZrN preparation, in particular to a ZrN plasma preparation system. Background Art

[0002] ZrN is zirconium nitride. During its preparation, it is generally prepared by plasma. Due to the high temperature and high power density characteristics, plasma has incomparable advantages as a heat source in some special occasions.

[0003] After searching, the application with patent number CN202022036543.2 discloses a nano-silicon powder plasma preparation device, including a bottom plate, a bracket, two fixed blocks and a drive motor are installed on the top of the bottom plate, a ball mill is installed between the two fixed blocks, one end of the ball mill is fixedly connected to the output shaft of the drive motor, a grinding barrel is installed on the top of the bracket, and a funnel is installed at the bottom of the grinding barrel;

[0004] The above application document prepares nano silicon powder by setting up a grinding component, but the plasma preparation method generally uses a heat source as the main source to prepare ZrN, and uses a crucible as a carrier to heat the reactants inside it. However, the plasma high-temperature preparation method itself has a poor heat dissipation effect, which may affect the subsequent preparation efficiency.

[0005] Therefore, we proposed a ZrN plasma preparation system. Utility Model Content

[0006] In view of the deficiencies in the prior art, the utility model provides a ZrN plasma preparation system, which solves the problem that the heat dissipation effect of the plasma torch in the prior preparation process is poor and may affect the subsequent preparation efficiency.

[0007] To achieve the above objectives, the utility model is implemented through the following technical solutions: A ZrN plasma preparation system includes an arc furnace body and a graphite crucible inside which reactants are placed;

[0008] A left frame plate and a right frame plate are respectively arranged on both sides of the arc furnace body, a plasma torch is placed in a graphite crucible inside the arc furnace body, an electrode body is fixedly installed at the bottom end of the plasma torch, a power line and a water inlet pipe are fixedly connected to the top side of the plasma torch, and the outer end of the water inlet pipe is connected to an air cooling pump;

[0009] An air duct and a drain pipe are fixedly connected to the outer wall of the plasma torch, and the outer end of the air duct is connected to a cooling water pump.

[0010] Preferably, a furnace groove matching the specifications of the plasma torch is arranged on the inner side of the arc furnace body, and ten groups of heat dissipation holes arranged in a ring shape and located outside the furnace groove are opened on the top side of the arc furnace body;

[0011] Among them, the setting of ten groups of heat dissipation holes can increase the contact area between the inner furnace groove of the arc furnace body and the outer air, thereby increasing the heat dissipation effect.

[0012] Preferably, the left frame plate is an L-shaped frame, and a cooling water pump and an air cooling pump are fixedly installed on the inner side wall of the left frame plate;

[0013] Among them, the setting of the left frame plate is convenient for installing a cooling water pump and an air cooling pump to ensure subsequent air cooling and water cooling.

[0014] Preferably, the water inlet pipe and the air duct are both made of soft pipes;

[0015] Among them, the arrangement of the water inlet pipe and the air duct can ensure the flexibility of the plasma torch in adjusting up and down, so as to facilitate the taking and discharging of the reactants inside the graphite crucible and ensure the normal ZrN preparation work.

[0016] Preferably, the right frame plate is a U-shaped frame, a hydraulic pump group is fixedly installed at the bottom of the inner side of the right frame plate, and a clamp is fixedly connected to the bottom end of the hydraulic pump group;

[0017] The hydraulic pump group is configured to drive the clamp to move up and down, thereby adjusting the upper and lower positions of the plasma torch held inside the clamp to ensure high-temperature plasma preparation for the reactants in the graphite crucible at the bottom.

[0018] Preferably, the clip is a quarter ring clip, and the clip is made of an outer hard plastic ring and an inner cotton ring pad.

[0019] The utility model provides a ZrN plasma preparation system, which has the following beneficial effects:

[0020] 1. The ZrN plasma preparation system, through the arrangement of the arc furnace body and the components on the top side thereof, can utilize the arrangement of the plasma torch and the electrode body on the bottom side thereof, so that the inside of the graphite crucible is in a high temperature state, thereby raising the temperature of the reactants inside the crucible, thereby ensuring the preparation effect of ZrN. Meanwhile, the arrangement of the cooling water pump and the air cooling pump can achieve both water cooling and air cooling of the plasma torch, thus solving the problem that the poor heat dissipation effect of the plasma torch in the existing preparation process may affect the subsequent preparation efficiency;

[0021] 2. The ZrN plasma preparation system, through the setting of the hydraulic pump group, can drive the clamp to adjust the overall height of the plasma torch clamped inside it, so as to facilitate the addition and removal of materials and ensure the preparation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the structure of the utility model;

[0023] Figure 2 This is a structural schematic diagram of the left frame plate of the utility model;

[0024] Figure 3 This is a structural schematic diagram of the right frame plate of the utility model;

[0025] Figure 4 It is a structural schematic diagram of the electric arc furnace body of the utility model.

[0026] In the figure: 1. arc furnace body; 2. left frame; 3. right frame; 4. plasma torch; 5. cooling water pump; 6. air cooling pump; 7. water inlet pipe; 8. air duct; 9. power cord; 10. drain pipe; 11. electrode body; 12. hydraulic pump group; 13. clamp; 14. crucible; 15. heat dissipation hole. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0028] Embodiment 1:

[0029] A ZrN plasma preparation system comprises an arc furnace body 1 and a graphite crucible 14 for placing reactants inside the arc furnace body 1; a left frame plate 2 and a right frame plate 3 are respectively arranged on both sides of the arc furnace body 1; a plasma torch 4 is placed in the graphite crucible 14 inside the arc furnace body 1; an electrode body 11 is fixedly installed at the bottom end of the plasma torch 4; a power line 9 and a water inlet pipe 7 are fixedly connected to the top side of the plasma torch 4; the outer end of the water inlet pipe 7 is connected to an air cooling pump 6; an air duct 8 and a drain pipe 10 are fixedly connected to the outer wall of the plasma torch 4, and the outer end of the air duct 8 is connected to a cooling water pump 5;

[0030] Among them, the ZrN plasma preparation system, through the arrangement of the arc furnace body 1 and the components on the top side thereof, can utilize the arrangement of the plasma torch 4 and the electrode body 11 on the bottom side thereof, so that the inside of the graphite crucible 14 is in a high temperature state, thereby heating the reactants inside thereof, and ensuring the preparation effect of ZrN. At the same time, the arrangement of the cooling water pump 5 and the air cooling pump 6 can perform both water cooling and air cooling on the plasma torch 4, thereby solving the problem that the poor heat dissipation effect of the plasma torch 4 in the existing preparation process may affect the subsequent preparation efficiency.

[0031] Embodiment 2:

[0032] A furnace groove matched with the specifications of the plasma torch 4 is arranged on the inner side of the arc furnace body 1, and ten groups of heat dissipation holes 15 distributed in a ring shape on the outside of the furnace groove are opened on the top side of the arc furnace body 1; wherein, the setting of the ten groups of heat dissipation holes 15 can increase the contact area between the furnace groove inside the arc furnace body 1 and the outside air, thereby increasing the heat dissipation effect.

[0033] The left frame plate 2 is an L-shaped frame, and a cooling water pump 5 and an air cooling pump 6 are fixedly installed on the inner wall of the left frame plate 2; wherein, the setting of the left frame plate 2 facilitates the installation of the cooling water pump 5 and the air cooling pump 6 to ensure subsequent air cooling and water cooling.

[0034] The water inlet pipe 7 and the air duct 8 are both made of soft tubes; wherein, the arrangement of the water inlet pipe 7 and the air duct 8 can ensure the flexibility of the plasma torch 4 in adjusting up and down, so as to facilitate the taking and discharging of the reactants inside the graphite crucible 14, and ensure the normal ZrN preparation work.

[0035] The right frame plate 3 is a U-shaped frame, and a hydraulic pump group 12 is fixedly installed on the bottom of the inner side of the right frame plate 3, and a clamp 13 is fixedly connected to the bottom end of the hydraulic pump group 12; wherein, the setting of the hydraulic pump group 12 can drive the clamp 13 to move up and down, thereby adjusting the upper and lower positions of the plasma torch 4 clamped inside thereof, to ensure high-temperature plasma preparation for the reactants in the graphite crucible 14 on the bottom side.

[0036] The clip 13 is a quarter ring clip, and the clip 13 is made of a hard plastic ring on the outside and a cotton ring pad on the inside.

[0037] In addition, the ZrN plasma preparation system, through the provision of the hydraulic pump group 12, can drive the clamp 13 to adjust the overall height of the plasma torch 4 clamped inside thereof, so as to facilitate material addition and removal and ensure preparation efficiency.

[0038] The working principle and use process of the utility model are as follows: when the device is needed to work, the hydraulic pump group 12 is turned on to drive the plasma torch 4 to move upward to expose the top groove of the graphite crucible 14, and then the reactant is placed in the graphite crucible 14, and then the hydraulic pump group 12 is turned on to drive the bottom end of the plasma torch 4 clamped in the clamp 13 to be placed in the graphite crucible 14, and then the power cord 9 is used to energize the plasma torch 4, and the electrode body 11 is used to heat the reactant inside the graphite crucible 14 to achieve efficient preparation of ZrN, and finally the air cooling pump 6 and the cooling water pump 5 are turned on to ventilate and fill the plasma torch 4 with water to ensure the heat dissipation effect of the plasma torch 4 and increase the preparation efficiency.

[0039] The above shows and describes the basic principles and main features of the utility model and the advantages of the utility model. For those skilled in the art, it is obvious that the utility model is not limited to the details of the above exemplary embodiments, and can be implemented in other specific forms without departing from the spirit or basic features of the utility model. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the utility model is limited by the attached claims rather than the above description, and it is intended to include all changes within the meaning and scope of the equivalent elements of the claims. Any figure mark in the claims should not be regarded as limiting the claims involved.

[0040] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A ZrN plasma preparation system, comprising an arc furnace body (1) and a graphite crucible (14) inside which reactants are placed; Features: A left frame plate (2) and a right frame plate (3) are respectively arranged on both sides of the arc furnace body (1); a plasma torch (4) is placed in a graphite crucible (14) inside the arc furnace body (1); an electrode body (11) is fixedly mounted on the bottom end of the plasma torch (4); a power line (9) and a water inlet pipe (7) are fixedly connected to the top side of the plasma torch (4); and an outer end of the water inlet pipe (7) is connected to an air cooling pump (6); An air duct (8) and a drainage pipe (10) are fixedly connected to the outer wall of the plasma torch (4), and the outer end of the air duct (8) is connected to a cooling water pump (5).

2. A ZrN plasma preparation system according to claim 1, characterized in that: A furnace groove matching the specifications of the plasma torch (4) is arranged on the inner side of the arc furnace body (1), and ten groups of heat dissipation holes (15) arranged in a ring shape and located outside the furnace groove are opened on the top side of the arc furnace body (1).

3. A ZrN plasma preparation system according to claim 1, characterized in that: The left frame plate (2) is an L-shaped frame, and a cooling water pump (5) and an air cooling pump (6) are fixedly mounted on the inner side wall of the left frame plate (2).

4. A ZrN plasma preparation system according to claim 1, characterized in that: The water inlet pipe (7) and the air duct (8) are both made of soft pipes.

5. A ZrN plasma preparation system according to claim 1, characterized in that: The right frame plate (3) is a U-shaped frame, a hydraulic pump group (12) is fixedly installed at the bottom of the inner side of the right frame plate (3), and a clamp (13) is fixedly connected to the bottom end of the hydraulic pump group (12).

6. A ZrN plasma preparation system according to claim 5, characterized in that: The clamp (13) is a quarter ring clamp, and the clamp (13) is made of a hard plastic ring on the outside and a cotton ring pad on the inside.