Montoring control system
Patent Information
- Application Number
- LAP685
- Authority / Receiving Office
- LA · LA
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2017-04-26
- Filing Date
- 2018-04-23
- Publication Date
- 2022-09-16
AI Technical Summary
Current supervisory control systems for power transmission and distribution lack efficient data coordination between systems, leading to inefficiencies in planning and execution of maintenance operations, which can result in power outages and increased operational complexity.
A supervisory control system with a grid monitoring and control subsystem, a power distribution supervisory control subsystem, and a calculation server, connected via a network, that streamlines data coordination by converting outage plans into a common format, managing operation procedures, and determining switchability, thereby improving data linkage and operational efficiency.
Enhances data coordination and operational efficiency by allowing seamless integration of outage plans and operation procedures across systems, minimizing power outages and simplifying maintenance operations.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
Monitoring and Control Systems
[0001] The present invention relates to a monitoring and control system.
[0002] An electric power system that supplies electric power from a power plant to consumer loads is divided into a transmission system and a distribution system. The transmission system transmits electric power generated at a power plant to a transmission substation via a primary transmission line, and transmits the power stepped down in the transmission substation to a distribution substation via a secondary transmission line. The distribution system supplies the power stepped down in the distribution substation to consumer loads via a distribution line. Monitoring and control systems that monitor and control the above-mentioned electric power system are known. The monitoring and control system includes a system monitoring and control system that monitors and controls the transmission system, a distribution monitoring and control system that monitors and controls the distribution system, and an equipment status monitoring system that monitors the status of facility equipment and supports maintenance work.
[0003] In a power system, work such as the addition of equipment or maintenance and inspection may be performed. In this case, work such as system switching in a transmission system or section switching in a distribution system is performed to eliminate or minimize power outages to consumer loads. Prior to the execution of these work, an outage plan is first created, and then a procedure chart defining individual operations of the equipment or devices is created based on the outage plan (see, for example, Patent Document 1 listed below).
[0004] Japanese Patent Application Publication No. 7-163052
[0005] In creating the above-mentioned procedure table, various systems such as a system for formulating an outage plan, a grid monitoring and control system, and a power distribution monitoring and control system are used separately, and data sharing between the systems is currently inefficient. The present invention has been made in consideration of the above-mentioned circumstances, and an object of the present invention is to provide a monitoring and control system that can efficiently share data between systems.
[0006] The monitoring and control system of the present invention includes at least one system monitoring and control subsystem that monitors and controls the power transmission system, at least one distribution monitoring and control subsystem that monitors and controls the power distribution system, a calculation server that stores shutdown plan subjects related to the shutdown of the power transmission system and the power distribution system, and a network that connects the system monitoring and control subsystem, the distribution monitoring and control subsystem, and the calculation server, and monitors and controls the power transmission system and the power distribution system based on the shutdown plan subjects.
[0007] In addition, in the present invention, the system monitoring and control subsystem and the distribution monitoring and control subsystem each include a shutdown plan subject registration unit that transmits the shutdown plan to the calculation server, and the shutdown plan subject registration unit may convert the shutdown plan subject into a common data format that can be used by each of the system monitoring and control subsystem and the distribution monitoring and control subsystem.
[0008] In addition, in the present invention, the system monitoring and control subsystem and the power distribution monitoring and control subsystem may each include an operation unit that creates an operation procedure based on a shutdown plan subject, and the operation unit of one of the system monitoring and control subsystem and the power distribution monitoring and control subsystem may create the operation procedure based on the system state when the other subsystem executes the operation procedure. In this case, the operation unit may include an operation subject management unit that receives a switchover feasibility determination request indicating whether the shutdown plan is executable, and the operation subject management unit may create a planned system based on the shutdown plan subject and transmit a switchover feasibility determination response based on the planned system.
[0009] According to the present invention, the grid monitoring and control subsystem, the power distribution monitoring and control subsystem, and the calculation server are connected via a network, so that data linkage between the systems can be made more efficient.
[0010] 1 is a diagram showing a power system to which a monitoring and control system according to an embodiment is applied. FIG. 2 is a diagram showing a monitoring and control system according to an embodiment. FIG. 3 is a block diagram showing an LJ1 system, a data linkage server, and a monitoring and control system. FIG. 4 is a block diagram showing the functional configuration of a monitoring and control system according to an embodiment. FIG. 5 is a conceptual diagram showing shutdown plan subjects. FIG. 6 is a conceptual diagram showing operation subjects. FIG. 7 is a diagram showing operations related to shutdown plans of a monitoring and control system according to an embodiment. FIG. 8 is a diagram showing operations related to system operation of a monitoring and control system according to an embodiment. FIG. 9 is a flowchart showing operations of a monitoring and control system related to switchover feasibility determination. FIG. 10 is a conceptual diagram showing operation procedures according to an embodiment. FIG. 11 is a flowchart showing operations of a system operation unit according to an embodiment. FIG. 12 is a flowchart showing operations of a system operation unit according to an embodiment. FIG. 13 is a diagram showing processing for combining operation subjects for distribution monitoring and control according to operation subjects for system monitoring and control. FIG. 14 is a sequence diagram showing cooperation between a system monitoring and control subsystem and a distribution monitoring and control subsystem.
[0011] Hereinafter, an embodiment will be described with reference to the drawings. FIG. 1 is a diagram showing a power system to which a monitoring and control system according to an embodiment is applied. In this embodiment, "network" is abbreviated as "NW," "firewall" is abbreviated as "FW," and "database" is abbreviated as "DB" as appropriate. The power system 1 shown in FIG. 1 includes multiple server bases 2, an inter-base NW 3, a wide area NW 4, and multiple local systems 5. A monitoring and control system 14 according to the embodiment (shown later in FIG. 2, etc.) is provided at the server base 2.
[0012] Each of the multiple server bases 2 has the functions of a monitoring and control system. The multiple server bases 2 are installed in geographically distant locations in preparation for natural disasters such as earthquakes. The multiple server bases 2 are communicatively connected to each other via an inter-base network 3 and provide backup for each other. Furthermore, if the load on one server base 2 is heavy, the load can be distributed among multiple server bases 2. The number of server bases 2 can be set arbitrarily taking into account redundancy and the like, and does not have to be three.
[0013] The local system 5 is communicatively connected to the server base 2 via the wide area network 4. The local system 5 is a system provided for each area jurisdiction, such as the Chiba area, the Kanagawa area, the Saitama area, etc. (administrative districts, etc.). The local system 5 includes a power supply station 6, a branch network 7, and multiple control centers 8. The power supply station 6 (power supply control center) is connected to the wide area network 4 and communicatively connected to the server base 2 via the wide area network 4. The branch network 7 is connected to the wide area network 4, and the multiple control centers 8 are each communicatively connected to the server base 2 via the branch network 7 and the wide area network 4. The multiple control centers 8 are each provided for each regional area jurisdiction.
[0014] Each of the control centers 8 is communicatively connected to power transmission facilities 9 within the jurisdiction of the corresponding regional area. The power transmission facilities 9 include, for example, equipment provided in a power transmission substation, and equipment provided on a power transmission line or a power transmission tower. Furthermore, each of the control centers 8 is communicatively connected to power distribution facilities 10 within the jurisdiction of the corresponding regional area. The power distribution facilities 10 include, for example, equipment provided in a power distribution substation (e.g., a line switch, a circuit breaker) and equipment provided on a power distribution line or a utility pole (e.g., a section switch, a smart meter).
[0015] The inter-base network 3 is multiplexed, so that if a failure occurs in one network, operation can be continued using other networks. The wide-area network 4 and the branch network 7 are also multiplexed, like the inter-base network 3. The communication lines between the wide-area network 4 and the power supply station 6 are provided in multiple systems, so that if a failure occurs in one communication line (e.g., a wired communication line), communication can be continued using other communication lines (e.g., a wireless communication line). The communication lines between the branch network 7 and the control center 8, the communication lines between the control center 8 and the power transmission equipment 9, and the communication lines between the control center 8 and the power distribution equipment 10 are also provided in multiple systems, like the communication lines between the wide-area network 4 and the power supply station 6.
[0016] 2 is a diagram showing a monitoring and control system according to an embodiment. The server base 2 includes a data link server 11, a firewall 12, a data bus 13, a monitoring and control system 14, a file server 15, a firewall 16, and a firewall 17.
[0017] The data linkage server 11 is communicably connected to a system (hereinafter referred to as an external system) external to the server base 2 via the business network. The data linkage server 11 performs data linkage with the external system via the business network. The data linkage server 11 is provided, for example, in only one of the multiple server bases 2. For example, one server base 2 is provided with multiple physical computers (physical hardware devices), and the data linkage server 11 is multiplexed across the multiple physical computers.
[0018] The data linkage server 11 is connected to an LJ1 system 18 (work shutdown coordination system) and a power distribution information management system 19 as external systems. The LJ1 system 18 supplies shutdown plan information (system monitoring and control shutdown plan information) related to shutdown plans for the power transmission system to the data linkage server 11. The power distribution information management system 19 supplies shutdown plan information (distribution monitoring and control shutdown plan information) related to shutdown plans for the power distribution system to the data linkage server 11. The data linkage server 11 is connected to a data bus 13. In the following description, when system monitoring and control shutdown plan information and distribution monitoring and control shutdown plan information are handled in the same way, they will be referred to as shutdown plan information as appropriate.
[0019] The monitoring and control system 14 monitors and controls the transmission system and the distribution system based on the shutdown plan subject. The application configuration of the monitoring and control system 14 is divided into subsystems according to business purposes. The monitoring and control system 14 includes a system monitoring and control subsystem, a distribution monitoring and control subsystem, and a substation equipment maintenance subsystem. Each of the above subsystems is realized by an application provided by the following servers provided in the monitoring and control system 14.
[0020] The monitoring and control system 14 includes a grid monitoring and control server 21, a power distribution monitoring and control server 22, and a calculation server 23. The grid monitoring and control server 21, the power distribution monitoring and control server 22, and the calculation server 23 are each connected to a data bus 13. The data bus 13 is connected to the wide area network 4 via a firewall 16. The data bus 13 is also connected to the inter-base network 3 via a firewall 17.
[0021] The grid monitoring and control subsystem is realized by an application provided by the grid monitoring and control server 21, and monitors and controls the power transmission grid. The grid monitoring and control subsystem is functionally divided and logically separated for each jurisdiction (area jurisdiction). One power supply station 6 is provided in each area jurisdiction, and a control terminal 25 is provided in the power supply station 6. The control terminal 25 is, for example, a control console. The control terminal 25 is communicably connected to the grid monitoring and control server 21 via the wide area network 4. The control terminal 25 functions as the grid monitoring and control subsystem by the application provided by the grid monitoring and control server 21.
[0022] The power distribution monitoring and control subsystem is realized by an application provided by the power distribution monitoring and control server 22, and monitors and controls the power distribution system and maintains the controlled equipment in the power distribution system. The power distribution monitoring and control subsystem is functionally divided by jurisdiction (regional area jurisdiction) and is also logically divided.
[0023] Each regional area jurisdiction belongs to one area jurisdiction and does not overlap with multiple area jurisdictions. One control center 8 is provided in each regional area jurisdiction, and a control terminal 26 is provided in the control center 8. The control terminal 26 is, for example, a control desk. The control terminal 26 is communicatively connected to the distribution monitoring and control server 22 via the branch network 7 and the wide area network 4. The control terminal 26 functions as a distribution monitoring and control subsystem using an application provided by the distribution monitoring and control server 22.
[0024] The substation equipment maintenance subsystem performs maintenance on the equipment managed by the system monitoring and control subsystem. The substation equipment maintenance subsystem is realized by an application provided by the system monitoring and control server 21. The substation equipment maintenance subsystem performs monitoring and control of equipment within the monitoring and control range of the system monitoring and control subsystem. The substation equipment maintenance subsystem is a system with some of the functions of the system monitoring and control subsystem limited. The substation equipment maintenance subsystem is capable of equipment shutdown operations like the system monitoring and control subsystem, but differs from the system monitoring and control subsystem in that it is unable to perform system change operations.
[0025] A maintenance terminal 27 is provided in the control center 8. The maintenance terminal 27 is, for example, a maintenance desk. The maintenance terminal 27 is communicably connected to the system monitoring and control server 21 and the distribution monitoring and control server 22 via the branch network 7 and the wide area network 4. The maintenance terminal 27 functions as a substation equipment maintenance subsystem by an application provided by the system monitoring and control server 21.
[0026] As described above, the monitoring and control system 14 has a configuration in which each server is consolidated at the server base 2, and is a system that is less dependent on the organization, location, etc. to which each power supply station 6 or each control station 8 belongs. Access to each server from the power supply station 6 and / or the control station 8, etc., is performed via a thin client (for displaying a screen, operating equipment, etc.).
[0027] The system monitoring control server 21 is the main server of the system monitoring control subsystem and the substation equipment maintenance subsystem. The system monitoring control server 21 monitors and controls various states and collects information. The system monitoring control server 21 utilizes a physical computer installed at each server base 2. A physical computer that operates as the system monitoring control server 21 is provided at each server base 2. For example, there are three server bases 2, and one system monitoring control server 21 is provided at each server base 2, for a total of three. These three system monitoring control servers 21 are synchronized, with one in regular operation and two in standby operation, ensuring redundancy.
[0028] Furthermore, a logical computer is configured for each area jurisdiction in the physical computer operating as the grid monitoring and control server 21. A logical computer is a virtual machine that runs on the physical computer, and multiple guest operating systems (logical computers) can be implemented in the host operating system of the physical computer. Multiple logical computers are implemented according to the number of area jurisdictions, and these multiple logical computers can be executed on the physical computer operating as the grid monitoring and control server 21. This makes it possible to level the calculation load within the physical computer.
[0029] The power distribution monitoring and control server 22 is the main server of the power distribution monitoring and control subsystem. The power distribution monitoring and control server 22 monitors and controls various states and collects information. The power distribution monitoring and control server 22 utilizes a physical computer installed at each server base 2. A physical computer that operates as the power distribution monitoring and control server 22 is provided at each server base 2. For example, there are three server bases 2, and one power distribution monitoring and control server 22 is provided at each server base 2, for a total of three. These three power distribution monitoring and control servers 22 are synchronized, with one in regular operation and two in standby operation, ensuring redundancy.
[0030] Furthermore, a logical computer is configured for each regional area jurisdiction in the physical computer operating as the power distribution monitoring and control server 22. A plurality of logical computers are implemented according to the number of regional areas jurisdiction, and these plurality of logical computers can be executed on the physical computer operating as the power distribution monitoring and control server 22. This makes it possible to level the calculation load within the physical computer.
[0031] The calculation server 23 stores shutdown plan subjects related to the shutdown of the power transmission system and the shutdown of the power distribution system. The calculation server 23 manages the subjects of the shutdown plan. The calculation server 23 saves the shutdown plan subjects. The calculation server 23 uses a physical computer installed at each server base 2. In addition, a file server 15 is provided at the server base 2. The file server 15 is, for example, a data warehouse. The file server 15 stores the shutdown plan subjects and operation subjects for a long period of time.
[0032] Figure 3 is a block diagram showing the LJ1 system, data linkage server, and monitoring and control system. As shown in Figure 2, the monitoring and control system 14 includes a grid monitoring and control server 21 and a power distribution monitoring and control server 22. A grid monitoring and control subsystem (shown later in Figure 7) is a subsystem executed on the computer of the grid monitoring and control server 21. The grid monitoring and control subsystem performs grid monitoring and control of, for example, one local system 5. By executing multiple grid monitoring and control subsystems on one grid monitoring and control server 21, grid monitoring and control of multiple local systems is realized by the single grid monitoring and control server 21.
[0033] The power distribution monitoring and control subsystem is one power distribution monitoring and control subsystem executed on the computer of the power distribution monitoring and control server 22. The power distribution monitoring and control subsystem performs, for example, power distribution monitoring and control of one local system 5. By executing multiple power distribution monitoring and control subsystems on one power distribution monitoring and control server 22, power distribution monitoring and control of multiple local systems is realized by one power distribution monitoring and control server 22.
[0034] The power distribution monitoring and control subsystem and the system monitoring and control subsystem each include a shutdown plan management unit 31 and an operation unit 32. The shutdown plan management unit 31 of the system monitoring and control subsystem manages shutdown plan subjects and operation subjects for the power transmission system. The operation unit 32 of the system monitoring and control subsystem manages operations for the power transmission system. The shutdown plan management unit 31 of the power distribution monitoring and control subsystem manages shutdown plan subjects and operation subjects for the power distribution system. The operation unit 32 of the power distribution monitoring and control subsystem manages operations for the power distribution system.
[0035] The LJ1 system 18 transfers the grid shutdown plan information to the data linkage server 11. The grid shutdown plan information is information registered by the operator when shutting down power facilities such as electric power stations and transmission lines, indicating shutdown plans such as shutdown equipment and shutdown periods. The grid shutdown plan information is data in a predetermined format (e.g., CSV format). The LJ1 linked data reception processing unit 33 of the calculation server 23 imports the grid shutdown plan information from the data linkage server 11 at a predetermined interval. The LJ1 linked data reception processing unit 33 converts, edits, and associates the grid shutdown plan information with the equipment DB. For example, the LJ1 linked data reception processing unit 33 converts (modifies) the imported grid shutdown plan information into setting data using pre-registered definition information (e.g., maintenance dictionary definitions). The LJ1 linked data reception processing unit 33 also determines whether there are any errors in the grid shutdown plan information.
[0036] The calculation server 23 requests the shutdown plan management unit 31 of the monitoring and control system 14 to register the shutdown plan subject acquired by the LJ1 linked data reception processing unit 33. The shutdown plan management unit 31 (a shutdown plan subject registration unit 34 shown later in FIG. 7 ) registers, in the calculation server 23, a shutdown plan subject based on the system shutdown plan information acquired by the LJ1 linked data reception processing unit 33. If there is no error in the shutdown plan subject acquired by the LJ1 linked data reception processing unit 33, the shutdown plan management unit 31 registers the shutdown plan subject in the calculation server 23. Furthermore, if there is an error in the system shutdown plan information acquired by the LJ1 linked data reception processing unit 33, the shutdown plan management unit 31 corrects the system shutdown plan information. Furthermore, the shutdown plan management unit 31 registers, in the calculation server 23, a shutdown plan subject based on the corrected system shutdown plan information. Furthermore, the shutdown plan management unit 31 (an operation subject registration unit 38 shown later in FIG. 7 ) registers the shutdown plan subject as an operation subject in the monitoring and control system 14.
[0037] Furthermore, the shutdown plan management unit 31 manages the status of shutdown decisions or work suspensions, etc., based on the system shutdown plan information, and hands over the information to the operation unit 32. The shutdown plan management unit 31 creates shutdown plan subjects based on information input by the operator regarding scheduled work shutdown operations, operation shutdown operations, or system change operations. The scheduled work shutdown operations are operations associated with scheduled work such as construction and inspection. The operation shutdown operations are operations that suspend the operation of power equipment for a certain period of time. The system change operations are operations that change the connection of power equipment. The shutdown plan subjects are centrally managed using subject data for system monitoring and control and power distribution monitoring and control, allowing the operator to refer to all subjects regardless of the operation location.
[0038] 4 is a block diagram showing the monitoring and control system. The shutdown plan management unit 31 includes a shutdown plan subject registration unit 34, a shutdown plan subject edit / delete unit 35, a shutdown plan subject display unit 36, a shutdown decision / work cancellation unit 37, an operation subject registration unit 38, an equipment DB inconsistency determination unit 39, a planned power outage operation unit 40, a work item management unit 41, a report printing unit 42, and an operator setting unit 43.
[0039] The shutdown plan subject registration unit 34 converts the shutdown plan subject into a common data format that can be used by both the grid monitoring and control subsystem and the distribution monitoring and control subsystem. The shutdown plan subject registration unit 34 creates a shutdown plan subject that corresponds to identification information for the shutdown plan subject information, based on at least one of the information on the shutdown plan input by the operator, the grid shutdown plan information imported from the LJ1 system 18, and the information supplied from the distribution information management system 19. FIG. 5 is a conceptual diagram showing the shutdown plan subject and the shutdown plan information. A "plan number," which serves as identification information, is assigned to the shutdown plan information. The "plan number" is assigned according to the power supply station classification, operation classification, shutdown type, month, sequential number, branch number, etc. Here, for convenience of explanation, the "plan number" is represented by a positive integer such as 1, 2, 3, etc.
[0040] The shutdown plan information includes information on the "business establishment" and the "facility name." For example, the shutdown plan information having a "plan number" of "1" has an "business establishment" of "area A" and an "facility name" of "substation A, transformer No. 1." The shutdown plan subject registration unit 34 generates, for example, "Transformer No. 1 shutdown plan" as a "shutdown plan subject" based on the shutdown plan information having a "plan number" of "1." The shutdown plan subject registration unit 34 associates and registers "Plan No. 1" and the "shutdown plan subject."
[0041] The shutdown plan subject editing / deletion unit 35 edits or deletes registered shutdown plan subjects in response to a request from an operator. The shutdown plan subject display unit 36 outputs various information, such as a list of registered shutdown plan subjects or individual detailed information display, to the display unit, and causes the display unit to display an image showing the various information.
[0042] The shutdown decision work cancellation unit 37 sets a status (state), such as shutdown decision or work cancellation, for a registered shutdown plan subject in response to a request from the operator. The operation subject registration unit 38 registers the shutdown plan subject as an operation subject in response to a request from the operator. The operation subject registration unit 38 registers the operation subject in a database separate from the shutdown plan subject registered by the shutdown plan subject registration unit 34. When system equipment is changed due to maintenance, the equipment DB inconsistency determination unit 39 detects whether or not there is an impact on registered shutdown plan subjects, and if there is an impact, suppresses operations for the shutdown plan subject. The planned power outage operation unit 40 executes shutdown operations, power transmission operations, or monitoring operations for the specified shutdown plan subject. When a planned power outage is implemented, the planned power outage operation unit 40 sets a group of switches to be operated that has been registered in advance for the planned power outage subject and the post-power transmission monitoring subject, and executes the above processing.
[0043] The work item management unit 41 creates work items based on the shutdown plan subject. The work item management unit 41 also displays a work schedule and sets the work content. The form printing unit 42 outputs various information, such as the shutdown plan subject or planned power outage information, to a printer and causes the printer to print the various information. The operator setting unit 43 displays or edits definition data used in the monitoring and control system 14 in response to requests from the operator.
[0044] The operation unit 32 creates an operation subject based on the shutdown plan subject notified by the shutdown plan management unit 31. An operation subject is, for example, a subject that summarizes (combines) each shutdown plan subject as a series of operations. An operation subject may be generated for one shutdown plan subject. Furthermore, multiple operation subjects may be combined within the same subsystem, or may be combined between different subsystems. Operation subjects related to the monitoring and control of a power transmission system (system monitoring and control) include types such as "scheduled shutdown operation," "operation shutdown operation," "system operation operation," "occasional operation," and "direct selection operation."
[0045] The operation subject of "scheduled shutdown operation" is a subject for creating an operation procedure based on the shutdown plan subject determined by the shutdown plan. The operation procedure is information that defines a series of operations for operating and controlling power system equipment through operation commands from the power dispatching station 6 in each area's jurisdiction. The operation subject of "operational shutdown operation" is a subject for creating the above operation procedure based on the operational shutdown operation determined by the shutdown plan. The operation subject of "system change operation" is a subject for creating the above operation procedure based on the shutdown plan subject and system change subject determined by the system change plan.
[0046] The operation subject of "system operation" is a subject for creating operation procedures and carrying out operations as required for system operation, such as power retransmission in the event of an accident, voltage adjustment operations, protective relay operations, and the use or locking of local automatic operation devices. Operations related to "system operation" can be carried out even without approval from the system. The operation subject of "on-demand operations" is a subject for carrying out unplanned, sudden operations such as operations in the event of an accident. "Direct selection operations" is a subject for directly controlling equipment that can be operated online by selecting equipment from a system diagram without creating operation procedures and individual equipment operation procedures in advance.
[0047] Furthermore, operation subjects related to the monitoring and control of distribution systems (distribution monitoring and control) include "scheduled shutdown operation," "operational shutdown operation," "system change operation," "distribution equipment operation," "direct selection operation," and "fault recovery operation." "Scheduled shutdown operation," "operational shutdown operation," "system change operation," and "direct selection operation" are the same as those for the above-mentioned system monitoring and control. The operation subject of "distribution equipment operation" is a subject for operating distribution line equipment based on power line shutdown or switching plan information. "Fault recovery operation" is a subject for restoring power by switching distribution lines in distribution sections that have lost power due to an accident but are not affected by the accident.
[0048] In addition, operation subjects related to the maintenance of facilities managed by the monitoring and control system 14 include "scheduled shutdown operation," "operation shutdown operation," "occasional operation," and "direct selection operation," which are similar to those of the system monitoring and control described above.
[0049] The operation unit 32 creates operation procedures for work stoppage or restoration work on busbars, transmission lines, etc., for each subject, and automatically executes the subject. The operation unit 32 includes an operation subject management unit 45, an initial system creation unit 46, an operation procedure creation unit 47, a simulation execution unit 48, an actual execution unit 49, and an operation setting unit 50.
[0050] The operation subject management unit 45 creates an operation subject upon notification from the shutdown plan management unit 31. FIG. 6 is a conceptual diagram showing an operation subject. An "operation number," which is identification information, is assigned to the operation subject. The "operation number" is assigned according to the system identification number, month, serial number, etc. For ease of explanation, the "operation number" is represented here as a positive integer such as 1, 2, 3, etc.
[0051] The operation subject management unit 45 associates and manages the "plan number" (see FIG. 5 ), which is identification information of the shutdown plan subject notified from the shutdown plan management unit 31, with the "operation number" created by the operation unit 32. For example, the operation subject management unit 45 assigns "1" as the "operation number" to the shutdown plan subject whose "plan number" is "1." The operation subject management unit 45 generates "operation subject A" as the "operation subject" for which the "operation number" is "1." The operation subject management unit 45 associates and manages the "operation number," "operation subject," "plan number," and "operation procedure." For example, the operation subject management unit 45 associates and manages various information, such as when the "operation number" is "2," the "operation subject" is "operation subject C," the "plan number" is "3," and the "operation procedure" is "TH."
[0052] The operation subject also includes a "subject status" that indicates the administrative status of the operation subject, such as editing, created, applying for review, applying for approval, approved, waiting for operation, in progress, suspended, and completed.
[0053] The operation subject management unit 45 receives a notification from the shutdown plan management unit 31 of a shutdown decision or work cancellation and updates the operation subject. The operation subject management unit 45 also accepts, copies, combines, reverts, deletes, reviews, approves, and searches for manually created operation subjects. Review and approval are actions in which a supervisor or other high-ranking person confirms the operation subject (a confirmation action for registering it as an operation procedure). The operation subject management unit 45 also prints the operation subject. The operation subject management unit 45 also switches the online system diagram to a direct selection operation mode, and when an individual operation is performed, saves the control content as a directly selected operation subject. The operation subject management unit 45 also updates the subject status upon notification for each operation subject. The operation subject management unit 45 also receives a notification from the actual execution unit 49 when the operation is completed, and registers information indicating the operation completion in the file server 15.
[0054] The operation subject management unit 45 also determines whether the equipment DB information associated with the operation subject notified by the maintenance work matches the contents of the equipment DB. When the screen is cleared due to an accident or other reason while editing a procedure, the operation subject management unit 45 saves the procedure being edited in a waiting area. The operation subject management unit 45 also receives a request from the power distribution information management system 19 (see FIG. 2) via the data linkage server 11 to determine whether switching is possible, and responds to this notification by returning the determination result.
[0055] The initial system creation unit 46 creates initial system information. The initial system information is system status information that serves as the basis for creating and checking operation procedures. The initial system information includes equipment status and load status. The initial system creation unit 46 reads outage plan subjects up to the scheduled date and time from the calculation server 23, performs simulations using the simulation execution unit 48 (described later), and creates the outage plan by accumulating the system status. The operation procedure creation unit 47 is notified of a request for automatic procedure creation and automatically creates an operation procedure based on the information about the shutdown equipment included in the outage plan subject. The operation procedure creation unit 47 is also notified of a request for manual procedure creation and accepts editing of the operation procedure.
[0056] The simulation execution unit 48 is notified of the request to start the simulation execution and starts the simulation execution. The simulation execution is a process of expanding the created operation procedures one by one in a simulated system and checking them. The simulation execution unit 48 performs a simulation execution check (affected subject search check or procedure check) for each operation procedure and operates it in a simulated system. The simulation execution unit 48 performs a simulation execution based on the approved operation subject data prior to the actual execution described below. The simulation execution unit 48 may also perform a simulation execution based on a user's specification.
[0057] The actual execution unit 49 receives a request to start actual execution and starts the actual execution. The actual execution involves performing a pre-operation check, then checking each operation procedure and executing each procedure one by one according to the operation procedure. Furthermore, during the actual execution, the actual execution unit 49 determines whether to stop the actual execution if an automatic state change occurs in the equipment to be operated (e.g., a substation or a switchgear) (e.g., if a state change is automatically detected). Upon completion of the actual execution, the actual execution unit 49 counts up the number of executions as post-processing and stores the count value for a long period of time. Furthermore, the actual execution unit 49 switches to a system operation mode from the online system diagram and creates and executes procedures. The operation setting unit 50 stores operation setting information related to the operation unit 32 and outputs it when the operation setting information is changed.
[0058] Next, the operation of the monitoring and control system 14 regarding shutdown planning will be described. FIG. 7 is a diagram showing the operation of the monitoring and control system according to the embodiment. The data linkage server 11 (see FIG. 2) acquires system shutdown plan information from the LJ1 system 18. The LJ1 linked data reception processing unit 33 imports the system shutdown plan information stored in the data linkage server 11 into the calculation server 23 at a predetermined interval. The LJ1 linked data reception processing unit 33 converts (modifies) the setting data for the imported system shutdown plan information using dictionary definitions. The LJ1 linked data reception processing unit 33 also associates the equipment information included in the system shutdown plan information with information stored in the equipment DB. In this way, the LJ1 linked data reception processing unit 33 converts the received system shutdown plan information into a data format that can be used by the operation unit 32. The shutdown plan management unit 31 generates a shutdown plan subject by editing the system shutdown plan information, for example.
[0059] The shutdown plan management unit 31 also changes the shutdown plan subject in response to requests from operators, etc., and creates a new document with the changed subject data. The shutdown plan management unit 31 also registers the subject data included in the shutdown plan information received from the LJ1 system 18 and the created subject data in DB 51 as "shutdown plan subject A," "shutdown plan subject B," etc. The shutdown plan management unit 31 also performs check processing and extracts related parts when registering.
[0060] Furthermore, the shutdown plan management unit 31 sends a notification to the operation unit 32. This notification is, for example, a notification requesting that the shutdown plan subject be registered as an operation subject in the DB 52, a notification requesting that the shutdown plan subject that has already been registered as an operation subject be changed, a notification requesting that a shutdown decision be reflected, a notification requesting that a cancellation of a shutdown decision be reflected, a notification requesting that a work stoppage be reflected, or the like.
[0061] In response to a notification from the shutdown plan management unit 31, the operation unit 32 registers the shutdown plan subject as an operation subject in the DB 52. The operation subject is generated in association with the shutdown plan subject. For example, shutdown plan subjects registered in the DB 51 include "Transformer No. 1 shutdown plan" and "Distribution line section 1 shutdown plan," and operation subjects registered in the DB 52 include "Transformer No. 1 shutdown operation" and "Distribution line section 1 shutdown operation."
[0062] 7, reference numerals 21-1, 21-2, ..., 21-n each denote a system monitoring and control subsystem on the system monitoring and control server 21. The system monitoring and control subsystems 21-1, 21-2, ..., 21-n each correspond to a logical computer configured on the system monitoring and control server 21. The LJ1 linked data reception processing unit 33 of the calculation server 23 acquires system shutdown plan information. The calculation server 23 requests the shutdown plan management unit 31 of the system monitoring and control subsystem 21-1 to register a shutdown plan subject based on the shutdown plan information acquired by the LJ1 linked data reception processing unit 33. The shutdown plan subject registration unit 34 of the system monitoring and control subsystem 21-1 registers a shutdown plan subject based on the shutdown plan information acquired by the LJ1 linked data reception processing unit 33 in the DB 51 of the calculation server 23. In addition, the operation subject registration unit 38 of the system monitoring and control subsystem 21-1 registers the shutdown plan subject as an operation subject in the DB 52 of the system monitoring and control subsystem 21-1.
[0063] Furthermore, in the system monitoring and control subsystem 21-1, when the operation unit 32 receives a notification regarding a decision to shut down or a notification regarding the suspension of work from the shutdown plan management unit 31, it notifies the relevant parties. Furthermore, in the system monitoring and control subsystem 21-1, the operation unit 32 notifies the shutdown plan management unit 31 by performing an operation subject change and deletion process. This notification may be, for example, a notification that the operation unit 32 of the system monitoring and control subsystem 21-1 has changed the shutdown plan subject, a notification that an operation for the operation subject has been performed, a notification that an operation for the operation subject has been completed, or a notification that an operation subject has been deleted automatically or manually due to the passage of time. In the system monitoring and control subsystem 21-1, the shutdown plan management unit 31, in response to a notification from the operation unit 32, reflects the content of the notification in the shutdown plan subject stored in DB 51 or the operation subject stored in DB 52.
[0064] 7 each represent a power distribution monitoring and control subsystem on the power distribution monitoring and control server 22. The power distribution monitoring and control subsystems 22-1, 22-2, ..., 22-n each correspond to a logical computer configured on the power distribution monitoring and control server 22.
[0065] The distribution information management system linked data processing unit 53 of the calculation server 23 acquires distribution shutdown plan information from the distribution information management system 19. The distribution information management system linked data processing unit 53 converts, edits, and associates the distribution shutdown plan information with the equipment DB through processing similar to that of the LJ1 linked data reception processing unit 33. The calculation server 23 requests the shutdown plan management unit 31 of the distribution monitoring and control subsystem 22-1 to register a shutdown plan subject. The shutdown plan subject registration unit 34 of the distribution monitoring and control subsystem 22-1 registers a shutdown plan subject based on the shutdown plan information acquired by the distribution information management system linked data processing unit 53 in the DB 51 of the calculation server 23 via the shutdown plan management unit 31 of the distribution monitoring and control subsystem 22-1. In addition, the operation subject registration unit 38 of the distribution monitoring and control subsystem 22-1 registers the shutdown plan subject as an operation subject in the DB 52 of the distribution monitoring and control subsystem 22-1 via the shutdown plan management unit 31 of the distribution monitoring and control subsystem 22-1.
[0066] Next, the operation of the monitoring and control system 14 related to grid operation will be described. FIG. 8 is a diagram showing the operation related to grid operation of the monitoring and control system according to the embodiment. When creating new shutdown plan information, the power distribution information management system 19 transmits a switchover determination request to the data linkage server 11, requesting a switchover determination as to whether the shutdown plan information is executable. The switchover determination is a process of determining whether an operation procedure based on the new shutdown plan subject is executable. In other words, the switchover determination is a process of determining whether an operation of equipment in the power distribution system is executable. For example, the switchover determination is a determination as to whether a power supply path can be switched for a specified distribution section in the power distribution system. Note that the LJ1 system 18 may also transmit a switchover determination request to the data linkage server 11, requesting a switchover determination as to whether the new shutdown plan information is executable.
[0067] FIG. 9 is a flowchart showing the operation of the monitoring and control system related to the switchover determination. In step S21, the operation subject management unit 45 of the operation unit 32 receives a switchover determination request from the data linkage server 11. The switchover determination request includes a shutdown plan subject. In step S22, the operation unit 32 creates a planned system based on the scheduled date and time of the new shutdown plan subject included in the switchover determination request. The planned system is created by the initial system creation unit 46 (see FIG. 3 ) in the same manner as the initial system. In step S23, the operation unit 32 automatically creates an operation procedure (distribution equipment procedure) indicating the procedure for operating the equipment installed in the distribution system based on the new shutdown plan subject included in the switchover determination request. In step S24, the operation subject management unit 45 of the operation unit 32 determines whether or not there is a voltage deviation or an overload based on the operation procedure created from the planned system and the new shutdown plan subject. The operation subject management unit 45 of the operation unit 32 creates a switchover determination response indicating the determination result. In step S25 , the operation subject management unit 45 of the operation unit 32 transmits a switching possibility determination response to the power distribution information management system 19 via the data linking server 11 .
[0068] In addition, the operation unit 32 automatically creates an operation procedure for the specified operation subject. Figure 10 is a conceptual diagram showing an operation procedure according to the embodiment. The operation procedure HT includes a "target procedure" and an "individual procedure." The "target procedure" is a procedure that indicates the purpose of the operation and includes the following items: The "target command procedure" is a procedure for performing the target operation. The "contact procedure" is a procedure for contacting the relevant business establishments. The "comment procedure" is a procedure for displaying confirmation items or supplementary information. The "break procedure" is a procedure for increasing the visibility of the operation procedure. The "end of procedure" is a procedure that indicates the end position of the operation procedure. The "main registration procedure" is a procedure for performing DB switching. The "voltage adjustment procedure" is a procedure for adjusting voltage when loop switching is performed in the power distribution monitoring control management control subsystem.
[0069] In addition, "individual procedures" are procedures for operating equipment individually and include the following items: "general operating procedures" are procedures for directly controlling various equipment such as circuit breakers (CBs) and line switches (LSs). "tap operating procedures" are procedures for controlling tap paralleling, tap changes, and voltage matching. "confirmation procedures" are procedures for automatically or manually checking SV or TM values. "standby procedures" are procedures that indicate the standby time (seconds). "status setting procedures" are procedures for setting or canceling in-work, in-test, operation prohibited, and status change mask. "memory procedures" are procedures for saving the status of specified equipment and are called up by confirmation procedures and operating procedures. "limit procedures" are procedures for lowering the tap until the limit display appears. "delimitation procedures" are procedures for improving the visibility of operating procedures. "comment procedures" are procedures for displaying content such as confirmation items or supplementary information.
[0070] Returning to the explanation of Figure 8, the monitoring and control system 14 creates and executes operation subjects in cooperation with multiple logical computers (A system operation unit 32A, B system operation unit 32B) according to the range of operation targets. Here, the A system operation unit 32A is a management system that issues instructions when creating and executing operation subjects that cooperate with the B system operation unit 32B. Also, the B system operation unit 32B is an associated system that receives instructions from the management system when creating and executing operation subjects that cooperate with the A system operation unit 32A.
[0071] The management system and related systems are, for example, a local system 5 corresponding to an area jurisdiction including one power supply station 6 (see FIG. 2 ), or a system corresponding to a regional area jurisdiction including one control center 8. The number of related systems is determined by the area to be operated, and may be two or more.
[0072] The monitoring and control system 14 configures the management system and related systems based on the shutdown plan information. The monitoring and control system 14 requests the A system operation unit 32A (management system) to register a subject, but does not request the B system operation unit 32B (related system) to register a subject. The A system operation unit 32A creates an operation subject and operation procedure based on the received shutdown plan subject. The A system operation unit 32A performs a simulation run, review, and approval based on the created operation procedure. The monitoring and control system 14 may also be configured so that the operator can manually change the management system.
[0073] After the review is complete, the A system operation unit 32A notifies the B system operation unit 32B, and the operation subject created by the A system operation unit 32A can be referenced or edited by the B system operation unit 32B. The A system operation unit 32A and the B system operation unit 32B then work together to edit the procedures of the related systems and perform a mock execution or review and approval. After approval is complete in all related systems, actual execution becomes possible. The monitoring and control system 14 sends the created operation procedures to the file server 15 (data warehouse). The A system operation unit 32A and the B system operation unit 32B also work together to execute the operation procedures.
[0074] Next, the operation of the operation unit will be described. Figures 11 and 12 are flowcharts showing the operation of the operation unit according to the embodiment. In step S1, the operation unit 32 creates an operation subject. If a related system has been set, the operation unit 32 transmits an operation procedure to the related system. From step S2 onwards in Figure 11, it is assumed that a related system has not been set. The case where a related system has been set will be described with reference to Figure 12.
[0075] In step S2, the operation unit 32 creates an initial system. In step S3, the operation unit 32 creates an operating procedure. In step S4, the operation unit 32 performs a simulation run. In step S5, the operation unit 32 accepts review and approval. In step S6, the operation unit 32 performs a preliminary simulation run under the reviewed and approved conditions. In step S7, the operation unit 32 performs an actual run.
[0076] Next, a case where an associated system has been set will be described. In step S31, the operation unit 32 of the associated system creates an operation subject. In step S32, the operation unit 32 of the associated system receives an operation procedure for the power transmission system from the management system. In step S33, the operation unit 32 of the associated system creates an initial system. In step S34, the operation unit 32 of the associated system creates an operation procedure that combines operation procedures from the management system based on the initial system. In step S35, the operation unit 32 of the associated system performs a simulation of the operation procedure. In step S36, the operation unit 32 of the associated system accepts review and approval of the operation procedure. In step S37, the operation unit 32 of the associated system performs a preliminary simulation of the operation procedure under the reviewed and approved conditions. In step S38, the operation unit 32 of the associated system actually executes the combined operation procedure.
[0077] The operation unit 32 can also combine (adjust) the operation subject of the equipment (operation subject of the power system monitoring and control) created based on the shutdown plan information and the operation subject of the equipment (operation subject of the power distribution monitoring and control) created based on the operation information. Fig. 13 is a diagram showing an example of the processing of the power system monitoring and control subsystem and the power distribution monitoring and control subsystem when the operation subject of the power system control subsystem and the operation subject of the power distribution control subsystem are combined. In the example of Fig. 13, the management system is the power system monitoring and control subsystem (power system equipment monitoring and control in the jurisdiction), and the related system is the power distribution monitoring and control subsystem (power distribution equipment monitoring and control in the jurisdiction).
[0078] FIG. 13(A) is a diagram showing the state before the operation subject is executed. Symbols Tr1 and Tr2 are transformers. Symbols LS1 and LS2 are line switches connected to transformer Tr1. Symbol LS3 is a line switch connected to transformer Tr that cannot be remotely controlled. Line switches LS1, LS2, and LS3 are all in a power-on state (closed state). Symbols SW1, SW2, SW3, and SW4 are section switches. The section switches are indicated by solid black when power is on and by white when power is off. In the state shown in FIG. 13(A), power is supplied to both distribution sections SC1 and SC2 from transformer Tr2.
[0079] Here, it is assumed that "operation subject A" shown in Fig. 6 is the No. 1 transformer shutdown operation (an operation to shut down transformer Tr1 in Fig. 13(A)). Also, it is assumed that "operation subject C" shown in Fig. 6 is the distribution line section 1 shutdown operation (an operation to shut down distribution section SC2 in Fig. 13(A)). In Fig. 13(B), symbol SH denotes the operation procedure for system monitoring control, and symbol TH1 denotes the operation procedure for distribution monitoring control when the operation subject of system monitoring control is not combined.
[0080] 13(B), the system monitoring and control operation procedure SH includes an operation to remotely open line switch LS1 and line switch LS2, and an operation to open line switch LS3 on-site. Also, the distribution monitoring and control operation procedure TH1 includes an operation to remotely open section switch SW1, an operation to remotely open section switch SW2 on-site, and an operation to remotely open section switch SW3.
[0081] Here, let us assume that the scheduled operation time of operation procedure SH precedes the scheduled operation time of operation procedure TH1. If operation procedure SH of the grid monitoring control is not scheduled, power distribution section SC1 will be supplied with power from transformer Tr1 when section switch SW1 is closed. However, if operation procedure SH is scheduled, power distribution section SC1 will not be supplied with power because line switch LS2 will be opened.
[0082] In Figure 13(B), symbol TH2 denotes an operation subject of the distribution monitoring control adjusted according to the operation subject of the grid monitoring control. The operation procedure TH2 of the distribution monitoring control includes an operation of remotely turning on section switch SW4 instead of turning on section switch SW1 in the above-mentioned operation procedure TH1. At the time of completing the execution of operation procedure TH2, the distribution section SC1 receives power supply from a system different from both transformer Tr1 and transformer Tr2 by closing section switch SW4 and opening section switch SW3. Therefore, it is possible to minimize power outages to only the distribution section SC2.
[0083] When combining operation subjects in this manner, the operation unit 32 of the related system receives an operation procedure SH related to system monitoring and control from the management system in step S32 of FIG. 12. The operation unit 32 of the related system performs a simulation of the operation procedure SH and generates a candidate operation procedure TH2 based on the initial system after the simulation (step S34 of FIG. 12). The operation unit 32 of the related system performs a simulation of the candidate operation procedure TH2 (step S35 of FIG. 12). In the simulation of the candidate operation procedure TH2, the operation unit 32 determines whether all processes corresponding to the operation procedure TH2 have been executed. If the operation unit 32 determines that all processes corresponding to the operation procedure TH2 have been executed in the simulation of the candidate operation procedure TH2, the operation unit 32 adopts the candidate operation procedure TH2 as the regular operation procedure TH2.
[0084] In this way, the operation unit 32 of one of the system monitoring and control subsystems (the operation unit 32 of the related system) creates an operation procedure (e.g., operation procedure TH2) based on the system state when the other subsystem (management system) executes an operation procedure (e.g., operation procedure SH).
[0085] In this way, the operation unit 32 can combine operation subjects of different management systems (e.g., "Operation Subject A" and "Operation Subject C" in Figure 6) and generate a single operation subject that encompasses the procedures included in the two operation subjects.
[0086] Furthermore, the system monitoring and control subsystem and the power distribution monitoring and control subsystem cooperate with each other so that their respective operation units can execute operation procedures. The operation unit of the system monitoring and control subsystem cooperates with the power distribution monitoring and control subsystem that does not have control authority and can execute operation procedures corresponding to the operation subject.
[0087] 14 is a sequence diagram showing cooperation between the power system monitoring and control subsystem and the power distribution monitoring and control subsystem. In step S11, the power system monitoring and control subsystem starts execution of operation subject A. In step S12, the power system monitoring and control subsystem sends an execution instruction request to the power distribution monitoring and control subsystem, requesting execution of processing corresponding to operation subject A.
[0088] In step S13, the distribution monitoring control subsystem receives the execution instruction request of step S12. In step S14, the distribution monitoring control subsystem starts execution of operation subject C related to operation subject A. After the execution of operation subject C is completed, in step S15, the distribution monitoring control subsystem transmits a notification of the completion of execution of operation subject C to the grid monitoring control subsystem. In step S16, the grid monitoring control subsystem receives the notification of the completion of execution of step S15.
[0089] The technical scope of the present invention is not limited to the aspects described in the above-mentioned embodiments. One or more of the requirements described in the above-mentioned embodiments may be omitted. Furthermore, the requirements described in the above-mentioned embodiments may be combined as appropriate. Furthermore, to the extent permitted by law, the disclosures of Japanese Patent Application No. 2017-087104 and all documents cited in the embodiments of this specification are incorporated by reference as part of the present description.
[0090] DESCRIPTION OF SYMBOLS 1... Power system 2... Server base 3... Inter-base network 4... Wide area network 6... Power supply station 7... Branch network 8... Control center 11... Data linkage server 14... Monitoring and control system 19... Power distribution information management system 21... System monitoring and control server 22... Power distribution monitoring and control server 23... Calculation server 31... Outage planning management unit 32... Operation unit
Claims
1. A monitoring and control system comprising: at least one system monitoring and control subsystem that monitors and controls a power transmission system; at least one distribution monitoring and control subsystem that monitors and controls a power distribution system; a calculation server that stores shutdown plan subjects related to shutdown of the power transmission system and the power distribution system; and a network that connects the system monitoring and control subsystem, the distribution monitoring and control subsystem, and the calculation server, and that monitors and controls the power transmission system and the power distribution system based on the shutdown plan subjects.
2. The monitoring and control system according to claim 1, wherein the grid monitoring and control subsystem and the distribution monitoring and control subsystem each include a shutdown plan subject registration unit that transmits the shutdown plan to the calculation server, and the shutdown plan subject registration unit converts the shutdown plan subject into a common data format that can be used by each of the grid monitoring and control subsystem and the distribution monitoring and control subsystem.
3. A monitoring and control system according to claim 1 or claim 2, wherein the system monitoring and control subsystem and the distribution monitoring and control subsystem each have an operation unit that creates an operation procedure based on the shutdown plan subject, and the operation unit of one of the system monitoring and control subsystem and the distribution monitoring and control subsystem creates the operation procedure based on the system state when the other subsystem executes the operation procedure.
4. The monitoring and control system of claim 3, wherein the operation unit includes an operation subject management unit that receives a request for determining whether a shutdown plan can be executed or not, and the operation subject management unit creates a scheduled system based on the shutdown plan subject and transmits a response to determine whether a shutdown plan can be executed or not.