Composite components and construction methods for co-construction of deep soft foundation channel and riverside embankment

A technology of combining components and construction methods, applied in infrastructure engineering, roads, roads, etc., can solve problems such as inability to save land, induce soil slope slippage, and increase construction costs, so as to reduce slippage risks, solve deformation coordination, and save money. land use effect

CN103981876BInactive Publication Date: 2016-06-22路港集团有限公司 +1
4 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Publication Date
2016-06-22
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure 1
    Figure 1
Patent Text Reader

Abstract

The invention relates to the technical field of civil construction engineering and particularly relates to and discloses a combined member for co-constructing a deep soft foundation river way and a river embankment. The combined member comprises an embankment subjected to foundation treatment, a river bank retaining wall built at a slope toe of an embankment slope, and a river bed dug at the outer side of the retaining wall; a river way is composed of the retaining wall and the river bed; a foundation adopts a solidification water discharging method or flexible pile compound foundation; anti-sliding piles are buried below a slope body region of the embankment slope and an embankment earth shoulder. The invention further discloses a construction method of the combined member. The construction method sequentially comprises the following steps: partially unloading the embankment after the embankment is pre-pressed; piling the anti-sliding piles, an inclinometer and a retaining wall pile and building the river bank retaining wall; digging the river way and monitoring slope deformation; recovering embankment filling and the like. With the adoption of the combined member and the construction method thereof, the river way is very close to the embankment foundation and the land is saved; the foundation can be treated by using the solidification water discharging method and the construction cost is low; the slip risks can be effectively reduced and the deformation coordination problem between the members can be solved well; the combined member has the advantages of economical efficiency, safety and environmental friendliness.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the technical field of civil construction engineering, in particular to a combined component used for co-construction of a deep soft foundation channel and an embankment next to a river and a construction method thereof. Background technique

[0002] The coastal area has a lot of people and little land, the economy is developed, the river network and road network in the area are dense, and the land resources for engineering construction are very precious. In recent years, in order to save land and promote intensive use of land resources, road construction often changes rivers or irrigation canals to the foot of the embankment slope and follows the road. However, in coastal areas with very weak foundations, the construction of embankments along rivers is quite difficult, including a series of key technical problems. The interaction between foundation treatment of embankment along the river and the deformation of river reforming...

Examples

Embodiment Construction

[0026] Combine below figure 1 The present invention will be further described with specific embodiments.

[0027] Composite components used for co-construction of deep soft foundation channels and riverside embankments, such as figure 1 As shown, it includes the embankment 2 formed after the deep and weak embankment foundation 1 is processed and filled. The embankment 2 is built with a river bank retaining wall 3 at the foot of the side slope 14 along the river, and the outside of the river bank retaining wall 3 is an excavated river bed. , the river bank retaining wall 3 and the river bed form a river channel 4, the embankment foundation 1 adopts a consolidation drainage method, and a plastic drainage board 13 is vertically arranged in the foundation 1 for consolidation drainage. Anti-slip piles 5 are embedded in the side slope area of ​​the embankment 2 and under the soil shoulder 11 of the embankment. An inclinometer pipe 6 is buried in the side slope area of ​​the embank...