A floor integrated water supply device

By designing a comprehensive floor water supply device and using a combination of a warm water tank, a heat exchange box and a hot water storage box, the rapid cooling of hot water and the utilization of heat resources are achieved, solving the problem of long hot water cooling time in the existing technology. problem, improving drinking convenience and resource utilization efficiency.

CN109653300BActive Publication Date: 2024-10-15SHANXI FENHUI WATER TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910118254.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-02-16
Publication Date
2024-10-15
Estimated Expiration
2039-02-16

AI Technical Summary

Technical Problem

Existing drinking water heaters cannot provide hot water and warm boiled water at the same time, causing the hot water to cool down for too long, unable to meet the demand for rapid cooling, and affecting the convenience of people in urgent need of drinking water.

Method used

A comprehensive floor water supply device is designed, including a warm water tank, a heat exchange box, a hot water storage box and a heating box. The hot water is quickly cooled through a PLC controller and sensors, and the heat is used for heating by using heat pipes. Cold water, combined with the ventilation mechanism and insulation layer, achieves full utilization of resources and also has a scale cleaning function.

Benefits of technology

It achieves rapid cooling of hot water, making it convenient to drink warm boiled water. At the same time, the heat is used for washing and laundry, which improves resource utilization efficiency and ensures heating efficiency and drinking water safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109653300B_ABST
    Figure CN109653300B_ABST
Patent Text Reader

Abstract

The invention discloses a floor integrated water supply device, wherein a support plate, an electric control box and a warm water tank are fixed to the top of a bottom plate, a heat exchange box is fixed to the top of the support plate and the warm water tank; a hot water storage box is fixed to the top of the heat exchange box, a heat dissipation pipe is connected to the bottom of the hot water storage box, and the other end of the heat dissipation pipe is connected to the warm water tank; a heating device 1 is installed on the inner bottom wall of the hot water storage box, a hot water level sensor 1, a hot water level sensor 2 and a temperature sensor 1 are installed on the inner side wall of the hot water storage box; a heating box is fixed to the top of the hot water storage box, and the lower end of the heating box is connected to the hot water storage box through a hot water inlet pipe; a conical partition is also fixed to the inner side wall of the heating box, and a heating device 2 is installed at the bottom end of the conical partition; a ventilation mechanism is installed on the heat exchange box, the hot water storage box and the heating box. The beneficial effect of the invention is that it is convenient for people to drink warm water.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of water supply equipment, and more specifically, to a comprehensive floor water supply device. Background Art

[0002] In order to facilitate people's daily life, drinking water heaters are installed in many public places so that people can drink hot water at any time in public places, such as in dormitory buildings where people live together. When people drink hot water, they usually pour the hot water into a cup and let the hot water cool down naturally because it cannot be mixed, so they have to wait a long time to drink the hot water. As the pace of life continues to accelerate, this method cannot meet people's ideal requirements for rapid cooling, which brings inconvenience to people who are in urgent need of drinking water.

[0003] Therefore, it is necessary to develop a floor integrated water supply device that can provide hot water and warm water simultaneously. Summary of the invention

[0004] In view of the above defects, the present invention provides a comprehensive floor water supply device.

[0005] To achieve the above object, the present invention adopts the following technical solutions:

[0006] A floor integrated water supply device comprises a base plate; a support plate, an electric control box and a warm water tank are fixed on the top of the base plate, a PLC controller is arranged in the electric control box, a warm water outlet pipe is connected to the lower end of the warm water tank, a warm water outlet valve is installed on the warm water outlet pipe; a heat exchange box is fixed on the top of the support plate and the warm water tank, a hot water outlet pipe is installed on the lower end of the heat exchange box, a hot water outlet valve is installed on the hot water outlet pipe, a tap water inlet pipe is installed on the upper end of the heat exchange box, a tap water inlet electric control valve is installed on the tap water inlet pipe, A first hot water level sensor and a second hot water level sensor are installed on the inner wall of the heat exchange box; a hot water storage box is fixed on the top of the heat exchange box, and a heat dissipation pipe is connected to the bottom of the hot water storage box, and the other end of the heat dissipation pipe is connected to the warm water tank, wherein a heat dissipation pipe water inlet electric control valve is installed on the heat dissipation pipe, and the heat dissipation pipe is arranged in the heat exchange box; a hot water outlet pipe is connected to the lower end of the hot water storage box, and a hot water outlet valve is installed on the hot water outlet pipe, wherein a heating device 1 is installed on the inner bottom wall of the hot water storage box, and the hot water storage box A hot water level sensor 1, a hot water level sensor 2 and a temperature sensor 1 are installed on the inner wall; a heating box is fixed on the top of the hot water storage box, the upper end of the heating box is connected with a cold water inlet pipe, and a cold water inlet electric control valve is installed on the cold water inlet pipe, and the lower end of the heating box is connected to the hot water storage box through a hot water inlet pipe, and a hot water inlet electric control valve is installed on the hot water inlet pipe, wherein a cold water level sensor 1, a cold water level sensor 2 and a temperature sensor 2 are installed on the inner wall of the heating box; a A conical partition, a heating device 2 is installed at the bottom end of the conical partition; a ventilation mechanism is installed on the heat exchange box, the hot water storage box and the heating box; the tap water inlet electric control valve, the hot water level sensor 1, the hot water level sensor 2, the heat dissipation pipe inlet electric control valve, the hot water level sensor 1, the hot water level sensor 2, the temperature sensor 1, the heating device 1, the hot water inlet electric control valve, the cold water inlet electric control valve, the cold water level sensor 1, the cold water level sensor 2, the temperature sensor 2 and the heating device 2 are all electrically connected to the PLC controller.

[0007] Furthermore, a water-proof insulation box is fixed on the top wall of the hot water storage box, a lower partition is fixed on the inner bottom wall of the water-proof insulation box, a push-pull electromagnet 1 and a lower sleeve are fixed on the top of the lower partition, a middle sleeve is fixed on the top of the lower sleeve, an upper sleeve is fixed on the top of the middle sleeve, and the top of the upper sleeve is fixed to the top wall of the hot water storage box; a middle partition is fixed to the top of the extension rod of the push-pull electromagnet 1, the middle partition is arranged below the middle sleeve, a push-pull electromagnet 2 is fixed on the top of the middle partition, an upper partition is fixed to the top of the extension rod of the push-pull electromagnet 2, and the upper partition is arranged below the upper sleeve; a lower spring is arranged between the lower partition and the middle partition, and an upper spring is arranged between the middle partition and the upper partition; a reduction motor is fixed to the top of the upper partition, and the output shaft of the reduction motor is connected to the The keys and screws are connected and fixed to the rotating shaft, and a water-permeable sleeve is mounted on the rotating shaft, which is fixed on the top wall of the hot water storage box, wherein the water-permeable sleeve is connected to the drain pipe; a spline shaft is fixed to the top of the rotating shaft, and the spline shaft passes through the spline hole opened on the scraper fixing block, and a scraper is fixed on the scraper fixing block, and the scraper fixing block and the scraper are arranged above the conical partition; a shaft end screw is installed on the top of the spline shaft, and a spring is arranged between the shaft end screw and the scraper fixing block, and the spring is mounted on the spline shaft; the push-pull electromagnet 1, the push-pull electromagnet 2 and the reduction motor are electrically connected to the PLC controller; a cleaning button and a cleaning end button are installed on the electric control box, and the cleaning button and the cleaning end button are electrically connected to the PLC controller; a manual valve is also installed on the cold water inlet pipe.

[0008] Furthermore, the ventilation mechanism includes a ventilation valve, a valve cover and a dust-proof and breathable net. The upper end cover of the ventilation valve is covered with the valve cover. A dust-proof and breathable net is arranged between the inner wall of the valve cover and the outer wall of the ventilation valve. The dust-proof and breathable net is fixed on the valve cover.

[0009] Furthermore, insulation layers are installed on the outer side walls of the warm water tank, the heat exchange box, the hot water storage box and the heating box.

[0010] The beneficial effects of the present invention are: it can quickly cool down hot water, making it convenient for people to drink warm boiled water, and solving the problem that people need to wait for a long time for the water temperature to drop before drinking hot water; and the device uses the heat after the hot water is cooled down to heat cold water, making it convenient for people to wash and do laundry, so that resources are fully utilized; the device can also clean the scale in the heating box to ensure heating efficiency and drinking water safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a structural schematic diagram of a floor comprehensive water supply device according to the present invention;

[0012] Figure 2 yes Figure 1 A partial enlarged view of point A;

[0013] Figure 3 yes Figure 2 A partial enlarged view of point B;

[0014] Figure 4 yes Figure 1 A partial enlarged view of point C;

[0015] Figure 5 It is a structural schematic diagram of the scraper fixing block and the scraper;

[0016] Figure 6 yes Figure 5 A top view schematic diagram of

[0017] Figure 7 It is a top view schematic diagram of the spline shaft;

[0018] Figure 8 It is a partial schematic diagram of the present invention when the push-pull electromagnet 2 is retracted;

[0019] Fig. 9 It is a partial schematic diagram of the present invention when the push-pull electromagnet 1 and the push-pull electromagnet 2 are both retracted;

[0020] In the figure, 1, bottom plate; 2, support plate; 3, electric control box; 4, warm water tank; 5, warm water outlet pipe; 6, warm water outlet valve; 7, heat exchange box; 8, hot water outlet pipe; 9, hot water outlet valve; 10, tap water inlet pipe; 11, tap water inlet electric control valve; 12, hot water level sensor 1; 13, hot water level sensor 2; 14, heat pipe; 15, heat pipe inlet electric control valve; 16, hot water storage box; 17, hot water outlet pipe; 18, hot water outlet valve; 19, hot water level sensor 1; 20, hot water level sensor 2; 21, temperature sensor 1; 22, heating device 1; 23, ventilation mechanism; 24, heating box; 25, hot water inlet pipe; 26, hot water inlet electric control valve; 27, cold water inlet pipe; 28, cold water inlet Electric control valve; 29, cold water level sensor 1; 30, cold water level sensor 2; 31, temperature sensor 2; 32, heating device 2; 33, conical partition; 34, water-proof insulation box; 35, lower partition; 36, push-pull electromagnet 1; 37, middle partition; 38, lower spring; 39, lower sleeve; 40, push-pull electromagnet 2; 41, upper partition; 42, upper spring; 43, middle sleeve; 44, upper sleeve; 45, reduction motor; 46, connecting key; 47, screw; 48, rotating shaft; 49, water-permeable sleeve; 50, drain pipe; 51, spline shaft; 52, spring; 53, shaft end screw; 54, scraper fixing block; 55, scraper; 56, spline hole; 57, manual valve; 2301, vent valve; 2302, valve cover; 2303, dust-proof and breathable net. DETAILED DESCRIPTION

[0021] The present invention will be described in detail below in conjunction with the accompanying drawings. Figure 1-9As shown, a floor integrated water supply device comprises a base plate 1; a support plate 2, an electric control box 3 and a warm water tank 4 are fixed on the top of the base plate 1, a PLC controller is arranged in the electric control box 3, a warm water outlet pipe 5 is connected to the lower end of the warm water tank 4, a warm water outlet valve 6 is installed on the warm water outlet pipe 5; a heat exchange box 7 is fixed on the top of the support plate 2 and the warm water tank 4, a hot water outlet pipe 8 is installed on the lower end of the heat exchange box 7, a hot water outlet valve 9 is installed on the hot water outlet pipe 8, a tap water inlet pipe 10 is installed on the upper end of the heat exchange box 7, a tap water inlet electric control valve 11 is installed on the tap water inlet pipe 10, wherein a hot water level sensor 1 12 and a hot water level sensor 2 13 are installed on the inner wall of the heat exchange box 7; at the top of the heat exchange box 7 A hot water storage box 16 is fixed, and a heat dissipation pipe 14 is connected to the bottom end of the hot water storage box 16, and the other end of the heat dissipation pipe 14 is connected to the warm water tank 4, wherein a heat dissipation pipe water inlet electric control valve 15 is installed on the heat dissipation pipe 14, and the heat dissipation pipe 14 is arranged in the heat exchange box 7; a hot water outlet pipe 17 is connected to the lower end of the hot water storage box 16, and a hot water outlet valve 18 is installed on the hot water outlet pipe 17, wherein a heating device 22 is installed on the inner bottom wall of the hot water storage box 16, and a hot water level sensor 19, a hot water level sensor 20 and a temperature sensor 21 are installed on the inner side wall of the hot water storage box 16; a heating box 24 is fixed to the top of the hot water storage box 16, and a cold water inlet pipe 27 is connected to the upper end of the heating box 24, and the cold water inlet valve 18 is installed on the upper side wall of the hot water storage box 16. A cold water inlet electric control valve 28 is installed on the pipe 27, and the lower end of the heating box 24 is connected to the hot water storage box 16 through the hot water inlet pipe 25. The hot water inlet electric control valve 26 is installed on the hot water inlet pipe 25, wherein a cold water level sensor 1 29, a cold water level sensor 2 30 and a temperature sensor 2 31 are installed on the inner wall of the heating box 24; a conical partition 33 is also fixed on the inner wall of the heating box 24, and a heating device 2 32 is installed at the bottom end of the conical partition 33; a ventilation mechanism 23 is installed on the heat exchange box 7, the hot water storage box 16 and the heating box 24, and the ventilation mechanism 23 includes a ventilation valve 2301, a valve cover 2302 and a dust-proof air-permeable net 2303, and the upper end cover of the ventilation valve 2301 is closed with a valve cover 2302, and the valve cover 2302 A dustproof and breathable net 2303 is provided between the inner wall and the outer wall of the vent valve 2301, and the dustproof and breathable net 2303 is fixed on the valve cover 2302; the outer walls of the warm water tank 4, the heat exchange box 7, the hot water storage box 16 and the heating box 24 are all installed with a thermal insulation layer; wherein the tap water inlet electric control valve 11, the hot water level sensor 12, the hot water level sensor 2 13, the heat pipe inlet electric control valve 15, the hot water level sensor 19, the hot water level sensor 20, the temperature sensor 1 21, the heating device 1 22, the hot water inlet electric control valve 26, the cold water inlet electric control valve 28, the cold water level sensor 1 29, the cold water level sensor 2 30, the temperature sensor 2 31 and the heating device 2 32 are all electrically connected to the PLC controller;

[0022] A water-proof heat preservation box 34 is fixed on the inner top wall of the hot water storage box 16, a lower partition 35 is fixed on the inner bottom wall of the water-proof heat preservation box 34, a push-pull electromagnet 36 and a lower sleeve 39 are fixed on the top of the lower partition 35, a middle sleeve 43 is fixed on the top of the lower sleeve 39, an upper sleeve 44 is fixed on the top of the middle sleeve 43, and the top of the upper sleeve 44 is fixed to the inner top wall of the hot water storage box 16; a middle partition 37 is fixed on the top of the extension rod of the push-pull electromagnet 36, and a middle partition 37 is fixed on the top of the extension rod of the push-pull electromagnet 36. The partition 37 is arranged below the middle sleeve 43, and a push-pull electromagnet 2 40 is fixed to the top of the middle partition 37, and an upper partition 41 is fixed to the top of the extension rod of the push-pull electromagnet 2 40, and the upper partition 41 is arranged below the upper sleeve 44; a lower spring 38 is arranged between the lower partition 35 and the middle partition 37, and an upper spring 42 is arranged between the middle partition 37 and the upper partition 41; a reduction motor 45 is fixed to the top of the upper partition 41, and the output shaft of the reduction motor 45 is connected to the The key 46 and the screw 47 are connected and fixed to the rotating shaft 48. The rotating shaft 48 is provided with a water-permeable sleeve 49, which is fixed to the top wall of the hot water storage box 16, wherein the water-permeable sleeve 49 is connected to the drain pipe 50; a spline shaft 51 is fixed to the top of the rotating shaft 48, and the spline shaft 51 passes through the spline hole 56 opened on the scraper fixing block 54, and a scraper 55 is fixed to the scraper fixing block 54, and the scraper fixing block 54 and the scraper 55 are arranged above the conical partition 33; A shaft end screw 53 is installed at the top of 51, and a spring 52 is arranged between the shaft end screw 53 and the scraper fixing block 54, and the spring 52 is sleeved on the spline shaft 51; wherein the push-pull electromagnet 1 36, the push-pull electromagnet 2 40 and the reduction motor 45 are electrically connected to the PLC controller; a cleaning button and a cleaning end button are installed on the electric control box 3, and the cleaning button and the cleaning end button are electrically connected to the PLC controller; a manual valve 57 is also installed on the cold water inlet pipe 27.

[0023] In this embodiment, the manual valve 57 is in a normally open state, and drinking water enters the heating box 24 from the cold water inlet pipe 27. When the water level in the heating box 24 is lower than the cold water level sensor 1 29, the PLC controller controls the cold water inlet electric control valve 28 to open, and when the water level in the heating box 24 is higher than the cold water level sensor 2 30, the PLC controller controls the cold water inlet electric control valve 28 to close. When the temperature sensor 2 31 detects that the water temperature in the heating box 24 reaches 100 degrees, and the water level in the hot water storage box 16 is lower than the hot water level sensor 2 20, the PLC controller controls the hot water inlet electric control valve 26 to open and fill the hot water storage box 16 with water; when the water level in the hot water storage box 16 is higher than the hot water level sensor 2 20, the PLC controller controls the hot water inlet electric control valve 26 to close, and the PLC controller controls the heating device 2 32 to stop heating. When the water level in the hot water storage tank 16 is higher than the hot water level sensor 19, the PLC controller controls the heat pipe water inlet electric control valve 15 to open and fill the warm water tank 4 with water. When the water level in the hot water storage tank 16 is lower than the hot water level sensor 19, the PLC controller controls the heat pipe water inlet electric control valve 15 to close; the temperature sensor 21 monitors the water temperature in the hot water storage tank 16. When the water temperature is lower than 100 degrees and the water level is higher than the hot water level sensor 19, the PLC controller controls the heating device 22 to heat.

[0024] Tap water enters the heat exchange box 7 through the tap water inlet pipe 10. When the water level in the heat exchange box 7 is lower than the hot water level sensor 12, the PLC controller controls the tap water inlet electric control valve 11 to open. When the water level in the heat exchange box 7 is higher than the hot water level sensor 2 13, the PLC controller controls the tap water inlet electric control valve 11 to close. When the hot water passes through the heat dissipation pipe 14, the heat will be transferred to the water in the heat exchange box 7, making it convenient for people to use the water in the heat exchange box 7 for washing and laundry.

[0025] When it is necessary to clean the scale in the heating box 24, the staff first manually closes the manual valve 57, and then activates the cleaning button installed on the electric control box 3. At this time, the cleaning button will control the heating device 1 22 and the heating device 2 32 to stop heating through the PLC controller, and the PLC controller will control the push-pull electromagnet 2 40 to retract. Figure 8 As shown, the scraper 55 is fitted with the conical partition 33. At this time, the PLC controller controls the reduction motor 45 to rotate, the reduction motor 45 drives the rotating shaft 48 to rotate, the rotating shaft 48 drives the spline shaft 51 to rotate, the spline shaft 51 drives the scraper fixing block 54 to rotate, and the scraper fixing block 54 drives the scraper 55 to rotate, so that the scraper 55 cleans the scale on the conical partition 33; after the PLC controller completes the timing cleaning, it controls the reduction motor 45 to stop rotating, and then controls the push-pull electromagnet 36 to retract. At this time, Fig. 9The rotating shaft 48 shown no longer blocks the water outlet on the permeable sleeve 49. The water in the heating box 24 after cleaning will be discharged through the drain pipe 50. The staff can hold a water bucket to catch the water discharged from the drain pipe 50; after the drainage is completed, the staff presses the cleaning end button, and the push-pull electromagnet 1 36 and the push-pull electromagnet 2 40 are controlled to extend and return to the original position. At this time, the water in the heating box 24 will not be discharged through the drain pipe 50. At the same time, the PLC controller will control the heating device 1 22 and the heating device 2 32 to heat; at this time, the staff can manually open the manual valve 57. During the cleaning process, the staff must prevent the user from collecting water.

[0026] The above technical solutions only reflect the preferred technical solutions of the technical solutions of the present invention. Some changes that may be made to certain parts thereof by technicians in this technical field all reflect the principles of the present invention and fall within the protection scope of the present invention.

Claims

1. A floor integrated water supply device, characterized in that: The invention comprises a bottom plate (1); a support plate (2), an electric control box (3) and a warm water tank (4) are fixed to the top of the bottom plate (1); a PLC controller is arranged in the electric control box (3); a warm water outlet pipe (5) is connected to the lower end of the warm water tank (4); a warm water outlet valve (6) is installed on the warm water outlet pipe (5); a heat exchange box (7) is fixed to the top of the support plate (2) and the warm water tank (4); a hot water outlet pipe (8) is installed at the lower end of the heat exchange box (7); a hot water outlet valve (9) is installed on the hot water outlet pipe (8); a tap water inlet pipe (10) is installed on the upper end of the heat exchange box (7); ), a tap water inlet electric control valve (11) is installed on the tap water inlet pipe (10), wherein a first hot water level sensor (12) and a second hot water level sensor (13) are installed on the inner wall of the heat exchange box (7); a hot water storage box (16) is fixed to the top of the heat exchange box (7), and a heat dissipation pipe (14) is connected to the bottom of the hot water storage box (16), and the other end of the heat dissipation pipe (14) is connected to the warm water tank (4), wherein a heat dissipation pipe inlet electric control valve (15) is installed on the heat dissipation pipe (14), and the heat dissipation pipe (14) is arranged in the heat exchange box (7); the bottom of the hot water storage box (16) is connected to the bottom of the hot water storage box (16). The hot water storage box (16) is connected to a hot water outlet pipe (17) at its end, and a hot water outlet valve (18) is installed on the hot water outlet pipe (17); a heating device (22) is installed on the inner bottom wall of the hot water storage box (16); a hot water level sensor (19), a hot water level sensor (20) and a temperature sensor (21) are installed on the inner side wall of the hot water storage box (16); a heating box (24) is fixed to the top of the hot water storage box (16); a cold water inlet pipe (27) is connected to the upper end of the heating box (24); a cold water inlet electric control valve (28) is installed on the cold water inlet pipe (27); and the heating box (24) is connected to the upper end of the hot water storage box (16). The lower end of the heating box (24) is connected to the hot water storage box (16) through a hot water inlet pipe (25), and a hot water inlet electric control valve (26) is installed on the hot water inlet pipe (25), wherein a cold water level sensor 1 (29), a cold water level sensor 2 (30) and a temperature sensor 2 (31) are installed on the inner side wall of the heating box (24); a conical partition (33) is also fixed on the inner side wall of the heating box (24), and a heating device 2 (32) is installed at the bottom end of the conical partition (33); a ventilation mechanism (23) is installed on the heat exchange box (7), the hot water storage box (16) and the heating box (24);The tap water inlet electric control valve (11), the hot water level sensor 1 (12), the hot water level sensor 2 (13), the heat pipe inlet electric control valve (15), the hot water level sensor 1 (19), the hot water level sensor 2 (20), the temperature sensor 1 (21), the heating device 1 (22), the hot water inlet electric control valve (26), the cold water inlet electric control valve (28), the cold water level sensor 1 (29), the cold water level sensor 2 (30), the temperature sensor 2 (31) and the heating device 2 (32) are all electrically connected to the PLC controller; A water-proof heat preservation box (34) is fixed on the inner top wall of the hot water storage box (16); a lower partition (35) is fixed on the inner bottom wall of the water-proof heat preservation box (34); a push-pull electromagnet (36) and a lower sleeve (39) are fixed on the top of the lower partition (35); a middle sleeve (43) is fixed on the top of the lower sleeve (39); an upper sleeve (44) is fixed on the top of the middle sleeve (43); the top of the upper sleeve (44) is fixed to the inner top wall of the hot water storage box (16); a middle partition (37) is fixed on the top of the extension rod of the push-pull electromagnet (36); the middle partition ( The middle partition (37) is arranged below the middle sleeve (43); the top of the middle partition (37) is fixed with a push-pull electromagnet 2 (40); the top of the extension rod of the push-pull electromagnet 2 (40) is fixed with an upper partition (41); the upper partition (41) is arranged below the upper sleeve (44); a lower spring (38) is arranged between the lower partition (35) and the middle partition (37); an upper spring (42) is arranged between the middle partition (37) and the upper partition (41); a reduction motor (45) is fixed to the top of the upper partition (41); the output shaft of the reduction motor (45) is connected to the upper sleeve (44) by a connecting key (46) and screws (47) are connected and fixed to the rotating shaft (48), the rotating shaft (48) is sleeved with a water-permeable sleeve (49), the water-permeable sleeve (49) is fixed on the top wall of the hot water storage box (16), wherein the water-permeable sleeve (49) is communicated with the drainage pipe (50); a spline shaft (51) is fixed on the top end of the rotating shaft (48), the spline shaft (51) passes through a spline hole (56) provided on a scraper fixing block (54), a scraper (55) is fixed on the scraper fixing block (54), and the scraper fixing block (54) and the scraper (55) are arranged above the conical partition (33); The top end of the spline shaft (51) is provided with an end screw (53), a spring (52) is provided between the end screw (53) and the scraper fixing block (54), and the spring (52) is sleeved on the spline shaft (51); the push-pull electromagnet 1 (36), the push-pull electromagnet 2 (40) and the reduction motor (45) are electrically connected to the PLC controller; a cleaning button and a cleaning end button are installed on the electric control box (3), and the cleaning button and the cleaning end button are electrically connected to the PLC controller; a manual valve (57) is also installed on the cold water inlet pipe (27); The ventilation mechanism (23) comprises a ventilation valve (2301), a valve cover (2302) and a dustproof and breathable net (2303); the upper end cover of the ventilation valve (2301) is covered with the valve cover (2302); a dustproof and breathable net (2303) is arranged between the inner side wall of the valve cover (2302) and the outer side wall of the ventilation valve (2301); and the dustproof and breathable net (2303) is fixed on the valve cover (2302); The outer side walls of the warm water tank (4), the heat exchange box (7), the hot water storage box (16) and the heating box (24) are all provided with a thermal insulation layer.