Multi-section non-pillar staggered tunnel protection and inter-section non-pillar filling method for thick coal seams with large inclination angle

By adopting multi-section coal pillar-free staggered roadway protection and natural filling methods of collapsed gangue in thick coal seams with large dip angles, the problem of roadway and coal pillar deformation and damage caused by superposition of stope stresses has been solved, and the recovery rate of coal resources and mining have been improved. Field stability ensures safe mining of the working face in the lower section.

CN109763822BActive Publication Date: 2024-10-15XIAN UNIV OF SCI & TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910054223.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-01-21
Publication Date
2024-10-15
Estimated Expiration
2039-01-21

AI Technical Summary

Technical Problem

During the mining process of thick coal seams with large dip angles, the superposition of stope stresses between sections causes deformation and damage of roadways and coal pillars, affecting the stability of the stope, and the load on the roof of the lower section of the stope is unbalanced, affecting safe mining.

Method used

Multi-section coal-pillar-free staggered lane protection and natural filling methods of collapsed gangue are adopted. Hydraulic supports, return air tunnels and transport tunnels are set up in the coal seam, and anchor net cables are used for flexible support to achieve staggered coal pillars between sections. Layout and gangue filling can alleviate the superposition of stope stress and improve the coal resource recovery rate and stope stability.

Benefits of technology

It effectively alleviates the deformation and damage problems of roadways and coal pillars between sections, improves the coal resource recovery rate, improves the unbalanced loading of the stope roof in the lower section, and ensures safe mining of the working face.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109763822B_ABST
    Figure CN109763822B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for multi-section non-coal pillar staggered lane protection and inter-section non-coal pillar filling in a thick coal seam with a large inclination angle, including a bottom plate, a coal seam, an immediate roof and a basic roof in a multi-section coal seam, wherein the bottom plate is arranged below the coal seam, a hydraulic support is arranged in the section between the bottom plate and the immediate roof, a return air lane and a transport lane are arranged on the left and right sides of each section respectively, the return air lane in each section is connected with the transport lane through a working face, and the return air lane of the next section and the transport lane of the previous section are arranged in a staggered layer without coal pillars. The crushed coal body is moved to the top of the goaf of the second section, the collapsed gangue of the goaf of the first section moves to the goaf of the second section, and is filled with the crushed coal body to the upper part of the inclination of the goaf of the second section, and the upper, middle and lower parts of the inclination of the goaf of the second section are filled with damaged rock layers. The invention has a reasonable design, realizes the mining of thick coal seams without coal pillars or small coal pillars on a long wall working face with a large inclination angle, and ensures the safe mining of the working face of the lower section.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a method for arranging and filling tunnels in an underground coal mining working face, in particular to a method for naturally filling goafs with collapsed gangue in a long wall working face without coal pillars under thick coal seams with large dip angles. Background Art

[0002] High-angle coal seams refer to coal seams with a burial angle of 35~55°. They are found in major mining areas in Xinjiang, Sichuan, Gansu, Ningxia, Guizhou and other places in my country. Among them, high-angle thick coal seams account for a large proportion, reaching 60% in some mining areas (Xinjiang, Ningxia, etc.). It is well known that the existing longwall comprehensive mechanized mining technology of high-angle coal seams is gradually maturing. However, in the multi-segment mining process of high-angle coal seams, the mechanism of the action of the inclined upper segment stope on the lower segment stope is significantly different from that of the near-horizontal coal seam mining. The migration and stress superposition effect of the surrounding rock in the multi-segment stope not only seriously affects the stability of the segment coal pillars and the mining roadway, but also changes the load characteristics of the roof of the lower segment stope. In particular, when mining high-angle thick coal seams, the segment coal pillars have larger spatial dimensions, and their deformation, destruction and migration characteristics are more complex, which seriously affects the stability of the mining roadway and the surrounding rock of the lower segment stope. Therefore, a feasible method is urgently needed to effectively alleviate and solve the interaction problem between segments. Summary of the invention

[0003] The purpose of the present invention is to provide a method for forming staggered lanes and protecting lanes without coal pillars in a long-wall working face of a thick coal seam with a steep inclination angle, and for naturally filling the goaf with collapsed gangue. The method is reasonably designed and can not only effectively alleviate the deformation and damage problems of lanes and coal pillars between sections caused by the superposition of stress in the mining field, but also realize the mining of thick coal seams without coal pillars or with small coal pillars in a long-wall working face with a steep inclination angle, thereby improving the recovery rate of coal resources between the upper and lower sections, improving the unbalanced loading of the roof of the mining field in the lower section, ensuring the safe mining of the working face in the lower section, and solving the problems existing in the prior art.

[0004] The present invention is achieved through the following technical solutions.

[0005] A multi-section coal pillar-free staggered tunnel protection system in a thick coal seam with a large inclination angle comprises a bottom plate, a coal seam, an immediate roof and a basic roof in the multi-section coal seam, the bottom plate being arranged below the coal seam, a hydraulic support being arranged in the section between the bottom plate and the immediate roof, a return air tunnel and a transport tunnel being arranged on the left and right sides of each section respectively, the return air tunnel in each section being connected with the transport tunnel through a working face, and the return air tunnel of the next section and the transport tunnel of the previous section being arranged in a staggered layer without coal pillars.

[0006] For the above technical solution, the present invention has a further preferred solution:

[0007] Furthermore, the staggered layer arrangement without coal pillars should meet the thickness of the coal seam between the return air lane of the next section and the transport lane of the previous section, that is, the vertical distance between the lanes should be greater than 2m.

[0008] Furthermore, when the thickness of the coal seam in the section is between 3.5 and 4.0 m, the return air lane of the next section and the transport lane of the previous section are arranged in a staggered manner, that is, the return air lane of the next section is placed on the lower right side of the transport lane of the previous section.

[0009] Furthermore, when the thickness of the coal seam in a section is between 4.0 and 5.5 m, the return air lane of the next section and the transport lane of the previous section are arranged in a superimposed manner, that is, the return air lane of the next section is placed directly below the transport lane of the previous section.

[0010] Furthermore, when the thickness of the coal seam in a section is greater than 5.5m, the return air lane of the next section and the transport lane of the previous section are arranged in an upward staggered manner, that is, the return air lane of the next section is placed on the lower left side of the transport lane of the previous section.

[0011] Furthermore, the return air lanes in each section adopt flexible support methods using anchor net cables.

[0012] The present invention provides a method for inter-segment non-coal pillar filling of the above-mentioned multi-segment non-coal pillar staggered lane protection in a thick coal seam with a large inclination angle, comprising the following steps:

[0013] 1) During the longwall mining of thick coal seams with a high dip angle, after the first section working face is mined, as the second section working face is mined, the coal body on the lower side of the second section return air roadway is mined out, and the hydraulic supports are evacuated in sequence to the next section working face. The roadway becomes unstable, and the fissured coal body in the first section on the upper side of the tilt is destroyed, forming a broken coal body, which is then transported to the upper side of the goaf of the second section;

[0014] 2) At the same time, the collapsed waste rock in the goaf of the first section also moves along the channel to the goaf of the second section, and is filled with the broken coal body to the upper part of the goaf of the second section, so that the upper, middle and lower parts of the goaf of the second section are all filled with damaged rock layers;

[0015] 3) Similarly, the tunnel layout, mining and filling of the third, fourth, ... Nth section working faces are carried out in the same way as in the second section.

[0016] Furthermore, all mining tunnels adopt flexible support methods using anchor nets and cables to ensure that the waste rock in the goaf of the upper section is transported to the goaf of the lower section in a timely and effective manner.

[0017] The present invention adopts the above technical solution, which has the following beneficial effects:

[0018] The present invention proposes a method for staggered lane formation and lane protection without coal pillars in a long-wall working face with a steep inclination and thick coal seam, and natural filling of goafs with collapsed gangue. The method is reasonably designed and can not only effectively alleviate the deformation and damage problems of lanes and coal pillars between sections caused by the superposition of mining field stress; at the same time, it also realizes the mining of thick coal seams without coal pillars or with small coal pillars in a long-wall working face with a steep inclination, improves the coal resource recovery rate between the upper and lower sections, improves the unbalanced loading of the roof of the mining field in the lower section, and ensures the safe mining of the working face in the lower section. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The drawings described herein are used to provide a further understanding of the present invention, constitute a part of the present application, and do not constitute an improper limitation of the present invention. In the drawings:

[0020] Figure 1 (a) is a layout diagram of multi-section tunnels and working faces;

[0021] Figure 1(b) is a layout diagram of the roadway in the second section of the first section working face mining;

[0022] Figure 1 (c) is a characteristic diagram of the second section mining and the gangue transportation and filling in the goaf;

[0023] Figure 2 (a)-(c) are the location diagrams of staggered tunnels: Figure 2 (a) is the upper staggered layout; Figure 2 (b) is the superimposed layout; Figure 2 (c) is the lower staggered layout.

[0024] In the figure: 1—bottom plate; 2—coal seam; 3—direct roof; 4—basic roof; 5—return air lane of the first section; 6—transport lane of the first section; 7—return air lane of the second section; 8—transport lane of the second section; 9—working face of the first section; 10—second section; 11—hydraulic support; 12—goaf of the first section; 13—working face of the second section; 14—fractured coal body; 15—return air lane of the third section; 16—goaf of the second section; 17—broken coal body. DETAILED DESCRIPTION

[0025] The present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments. The exemplary embodiments and descriptions of the present invention are used to explain the present invention but are not intended to limit the present invention.

[0026] The overall structure of the present invention can be seen in Figures 1 (a) and (b). The present invention proposes a multi-section coal pillar-free staggered layer protection tunnel in a thick coal seam with a large inclination angle, including a bottom plate 1, a coal seam 2, a direct roof 3 and a basic roof 4 in a multi-section coal seam 2, wherein the bottom plate 1 is arranged below the coal seam 2, a hydraulic support 11 is provided in the section between the bottom plate 1 and the direct roof 3, and a return air tunnel and a transport tunnel are provided on the left and right sides of the section. The return air tunnel in each section is connected with the transport tunnel through a working face, and the return air tunnel of the next section and the transport tunnel of the previous section are arranged in a staggered layer without coal pillars.

[0027] As shown in Figure 1 (a), during the longwall mining of a thick coal seam with a high dip angle, the first section working face 9 is arranged in the coal seam 2, wherein the first section return air lane 5 is arranged along the coal seam floor 1, and the first section transport lane 6 is arranged along the immediate roof 3. The inclined lower area of ​​the working face connects the first section working face 9 with the first section transport lane 6 by gradually lowering the mining height. During the mining of the second section 10, the second section return air lane 7 and the second section transport lane 8 are arranged in the same arrangement as the first section, wherein the position of the second section return air lane 7 mainly depends on factors such as the thickness and strength of the coal seam and the roof and floor, and the specific parameters can be determined by combining theoretical calculation, physical simulation and numerical research.

[0028] The principles for selecting the position of the return air channel 7 in the second section are:

[0029] (1) Reduce or eliminate the coal pillars in the sections as much as possible to achieve the goal of pillar-free mining; (2) Arrange the second section return air lane 7 outside the range of the stress concentration of the roof between sections or at the edge as much as possible to avoid the second section return air lane 7 being affected by concentrated stress; (3) When objective conditions permit, adopt the staggered arrangement of the second section return air lane 7 as much as possible to place it in the fracture zone of the coal seam, and use the buffering effect of the fractured coal seam to reduce the deformation of the lane. At the same time, the lane can also be placed under the protection of the inclined masonry structure in the goaf 12 of the first section, ensuring the stability of the second section return air lane 7 and reducing maintenance costs.

[0030] As shown in Figure 1 (b), during the mining process of the second section, the second section return air lane 7 and the second section transport lane 8 are arranged in the same manner as the first section. The position of the second section return air lane 7 mainly depends on factors such as the thickness and strength of the coal seam and the roof and floor plates. The specific parameters can be determined by combining theoretical calculations, physical simulations and numerical studies.

[0031] Under the condition that the thickness and strength of the coal seam and the roof and floor plates allow, the position of the second section return air lane 7 can be determined according to the size of the lane spacing, that is, to ensure that the thickness of the coal seam between lanes is greater than 2m. The coal seam with a thickness of about 3.5~4.0m adopts the lower staggered layout, the coal seam with a thickness of 4.0~5.5m adopts the superimposed layout, and the coal seam with a thickness greater than 5.5m adopts the upper staggered layout.

[0032] As shown in Figure 2 (a)-(c), it is the position diagram of the staggered roadway of the first section transport roadway 6 and the second section return air roadway 7 in the present invention. Under the condition that the thickness and strength of the coal seam 2, the direct roof 3 and the basic roof 4 are allowed, the position of the second section return air roadway 7 can be determined according to the size of the roadway spacing, that is, to ensure that the thickness of the coal seam between the roadways (the vertical distance from the first section transport roadway 6 to the second section return air roadway 7) is greater than 2m. When the thickness of the coal seam is about 3.5~4.0m, the lower staggered layout is adopted, as shown in Figure 2 (c); when the thickness is 4.0~5.5m, the superimposed layout is adopted, as shown in Figure 2 (b); when the thickness is greater than 5.5m, the upper staggered layout is adopted, as shown in Figure 2 (a).

[0033] As shown in Figure 1 (c), the second section mining and goaf gangue transportation and filling characteristics of the present invention are shown. The inter-section non-coal pillar filling method of the steep-angle thick coal seam multi-section non-coal pillar staggered protection roadway of the present invention is as follows: in the longwall mining process of the steep-angle thick coal seam, after the first section working face is mined, as the second section working face is mined, the coal body on the lower side of the second section recovery roadway 7 is mined, and the hydraulic supports are evacuated in turn and placed in the next section working face, the roadway becomes unstable, and the first section fissure coal body 14 on the upper side of the inclination is immediately destroyed to form a broken coal body 17, and the broken coal body 17 is moved to the upper side of the goaf 16 of the second section. At the same time, the collapsed waste rock from the goaf 12 of the first section also moves along the channel to the goaf 16 of the second section, and is filled together with the broken coal body 17 to the inclined upper range of the goaf 16 of the second section, so that the inclined upper, middle and lower parts of the goaf 16 of the second section are all filled with damaged rock strata, thereby avoiding the unbalanced filling phenomenon of the roof of the goaf 16 of the second section, reducing or eliminating the unbalanced load of the "support-surrounding rock" system of the working face 13 of the second section, and solving the core technical problems in longwall mining of steep-angle coal seams.

[0034] The tunnel layout and mining steps of the working face of the third, fourth, ... Nth section are the same as those of the second section. Figure 1 (c) shows the staggered layout of the return air lane 15 of the third section and the transport lane 8 of the second section of the previous section without coal pillars.

[0035] In order to ensure that the gangue from the upper section goaf is moved to the lower section goaf in a timely and effective manner, all the above-mentioned return tunnels should adopt the flexible support method of anchor net cable. At the same time, in order to prevent air leakage in the return air tunnel in the middle and lower sections of the coal pillar-free mining, anti-leakage measures should be taken in the tunnel. In mines rich in water, gas, etc., pre-extraction measures should be taken in advance to ensure the safety of the working face when the upper and lower sections are connected.

[0036] The above shows and describes the basic principles, main features, specific methods and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and the description in the specification are only to illustrate the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which are within the scope of protection claimed by the present invention. The scope of protection claimed by the present invention is defined by the attached claims and their equivalents.

Claims

1. A method for filling coal pillars between sections of thick coal seams with steep inclination angles and multi-sections without coal pillars and staggered layers, wherein the multi-sections without coal pillars and staggered layers of thick coal seams with steep inclination angles include the bottom plate, coal seam, direct roof and basic roof in the multi-section coal seams, characterized in that: The bottom plate is arranged below the coal seam, a hydraulic support is arranged in the section between the bottom plate and the immediate roof, a return air lane and a transport lane are arranged on the left and right sides of each section respectively, the return air lane in each section is connected with the transport lane through the working face, and the return air lane of the next section and the transport lane of the previous section are arranged in staggered layers without coal pillars; The inter-segment non-coal pillar filling method for multi-segment non-coal pillar staggered lane protection in a thick coal seam with a large dip angle comprises the following steps: 1) During the longwall mining of thick coal seams with a high dip angle, after the first section working face is mined, as the second section working face is mined, the coal body on the lower side of the second section return air roadway is mined out, and the hydraulic supports are evacuated in sequence to the next section working face. The roadway becomes unstable, and the fissured coal body in the first section on the upper side of the tilt is destroyed immediately, forming a broken coal body, which is then transported to the upper side of the goaf of the second section; 2) At the same time, the collapsed gangue in the goaf of the first section moves to the goaf of the second section, and is filled with the broken coal body to the upper part of the goaf of the second section, so that the upper, middle and lower parts of the goaf of the second section are filled with damaged rock layers; 3) Similarly, the tunnel layout, mining and filling of the third, fourth, ... Nth section working faces are carried out in the same way as in the second section.

2. The method for filling coal pillars between sections of thick coal seams with large inclination angles and multi-section staggered-layered tunnels according to claim 1 is characterized in that: The staggered layer arrangement without coal pillars should meet the requirements of the thickness of the coal seam between the return air lane of the next section and the transport lane of the previous section, that is, the vertical distance between the lanes should be greater than 2m.

3. The method for filling coal pillars between sections of thick coal seams with large inclination angles and multi-section staggered-layered tunnels according to claim 1 is characterized in that: When the coal seam thickness in a section is between 3.5 and 4.0 m, the return air lane of the next section and the transport lane of the previous section are arranged in a staggered manner, that is, the return air lane of the next section is placed on the lower right side of the transport lane of the previous section.

4. The method for filling coal pillars between sections of thick coal seams with large inclination angles and multi-section staggered-layered tunnels according to claim 1 is characterized in that: When the coal seam thickness of the section is between 4.0 and 5.5 m, the return air lane of the next section and the transport lane of the previous section are arranged in a superimposed manner, that is, the return air lane of the next section is placed directly below the transport lane of the previous section.

5. The method for filling coal pillars between sections of thick coal seams with large inclination angles and multi-section staggered-layered tunnels according to claim 1 is characterized in that: When the coal seam thickness of a section is greater than 5.5m, the return air lane of the next section and the transport lane of the previous section are arranged in an upward staggered manner, that is, the return air lane of the next section is placed on the lower left side of the transport lane of the previous section.

6. The method for filling coal pillars between sections of thick coal seams with large inclination angles and multiple sections of staggered-layered tunnels without coal pillars according to claim 1 is characterized in that: The return air lanes in each section adopt flexible support method of anchor net cables.

7. The method for filling coal pillars between sections of thick coal seams with large inclination angles and multi-section staggered-layered tunnels according to claim 1 is characterized in that: All mining tunnels use flexible support methods such as anchor nets and cables to ensure that the waste rock from the upper section goaf is promptly and effectively transported to the lower section goaf.