Box pulling device, material transport robot and material transport method

By introducing the swing hook and the travel switch into the box pulling device of the material transport robot, the work process of the lifting and slide rail components is simplified, the problem of low work efficiency in the existing technology is solved, and more efficient material box pulling and transportation.

CN110127260BActive Publication Date: 2024-10-18ZHUHAI MAKERWIT TECH CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN201910478078.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-06-03
Publication Date
2024-10-18
Estimated Expiration
2039-06-03

AI Technical Summary

Technical Problem

When the existing material transport robot adjusts the position of the box pulling device until the hook enters the material box jack, the lifting device and slide rail assembly work multiple times, resulting in frequent position sensing and calculation and low work efficiency.

Method used

A box-pulling device including a main body, a driving component, a pendulum hook and a travel switch is designed. Through the rotation of the pendulum hook and the touch signal control of the travel switch, the work process of the lifting and slide rail components is simplified and the accurate entry of the hook is ensured. slot to reduce unnecessary movement and improve dragging efficiency.

Benefits of technology

The structure of the box pulling device is simplified and the work efficiency is improved, the working frequency of the lifting and slide rail components is reduced, and the pulling success rate and transportation efficiency of the material box are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110127260B_ABST
    Figure CN110127260B_ABST
Patent Text Reader

Abstract

The present invention provides a box-pulling device, a material transport robot and a material transport method. The box-pulling device includes a main body, a driving assembly, a swing hook and a first travel switch. The driving assembly is placed in the main body, and the swing hook and the first travel switch are both arranged outside the main body. The swing hook includes a connecting part, a cantilever part and a swing hook part, and the connecting part and the swing hook part are connected to both ends of the cantilever part. The connecting part is fixedly connected to the rotating output shaft of the driving assembly, the cantilever part extends along the axial direction of the rotating output shaft, and the swing hook part extends from the extended end of the cantilever part perpendicular to the cantilever part to the periphery. The material transport robot includes a box-pulling device, and the material transport method includes driving the slide rail assembly to make the box-pulling device translate outward in the horizontal direction; judging whether a contact signal from the first travel switch is obtained, and if so, stopping driving the slide rail assembly; and starting the driving assembly to make the swing hook rotate along the rotating output shaft. The work of the lifting device and the slide rail assembly is simplified, the box-pulling device has a simple structure, and the work efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of material transportation equipment, and in particular to a box pulling device, a material transportation robot and a material transportation method. Background Art

[0002] There is a material transport robot for dragging and transporting material boxes from a shelf. The material transport robot includes a body, a driving wheel assembly, a lifting device, a slide rail assembly and a box pulling device. The driving wheel assembly is installed at the bottom of the body, the lifting device is installed at the upper part of the body, the lifting device includes a lifting platform, the slide rail assembly is installed on the lifting platform, and the box pulling device is installed on the slide rail assembly; the lifting platform can translate in the vertical direction relative to the body, and the box pulling device can translate in the horizontal direction relative to the lifting platform.

[0003] The extended end of the box pulling device has a hook extending forward and bending downward, and the outer side of the wall of the material box has a socket opening facing upward. After the material transport robot reaches the front of the shelf, the box pulling device moves upward and forward through the cooperation of the lifting device and the slide rail assembly. After the hook reaches directly above the socket, the lifting device is controlled to move the box pulling device downward, and the hook enters the socket, and then the material box can be dragged out from the shelf.

[0004] The problem with the existing material transport robot is that in the process of adjusting the position of the box pulling device until the hook enters the socket of the material box, the lifting device and the slide rail assembly work multiple times, and each operation of the lifting device and the slide rail assembly involves position sensing and calculation, resulting in low work efficiency. Summary of the invention

[0005] A first object of the present invention is to provide a box pulling device that improves work efficiency.

[0006] A second object of the present invention is to provide a material transport robot with improved work efficiency.

[0007] The third object of the present invention is to provide a material transportation method that improves work efficiency.

[0008] The first purpose of the present invention provides a box pulling device including a main body, a driving assembly, a swing hook member and a first stroke switch; the driving assembly is placed in the main body, and the swing hook member and the first stroke switch are both arranged outside the first side of the main body; the swing hook member includes a connecting part, a cantilever part and a swing hook part, and the connecting part and the swing hook part are respectively connected to the extended ends of the cantilever part; the connecting part is fixedly connected to the rotating output shaft of the driving assembly, the cantilever part extends along the axial direction of the rotating output shaft, and the swing hook part extends from the extended end of the cantilever part perpendicular to the cantilever part to the periphery.

[0009] It can be seen from the above scheme that before reaching the material box, the swing hook part of the swing hook member is in a non-downward state. When the slide rail assembly pushes the box-pulling device forward, the contact part of the first travel switch touches the material box and sends a touch signal to the control system, and the system sends a control signal to the drive assembly to rotate the swing hook member, and the swing hook part swings and enters the slot. After the lifting platform reaches the horizontal position where the material box is located, there is no need to continue moving, and then the slide rail assembly only needs to move forward once. The work of the lifting device and the slide rail assembly is simplified, the box-pulling device has a simple structure and can effectively pull the material box, thereby improving work efficiency.

[0010] A further solution is that the main body includes a fixed part and a movable part, and an elastic member is connected between the fixed part and the movable part; the drive assembly is installed in the movable part, and the swing hook member and the first travel switch are installed on the outside of the movable part.

[0011] As can be seen from the above, the fixed part is connected to the slide rail assembly, and after the swing hook or the movable part hits the material box, a relative movement occurs between the movable part and the fixed part to achieve buffering.

[0012] A further solution is that the fixed part and the movable part are slidably connected along the axial direction of the rotating output shaft.

[0013] As can be seen from the above, this arrangement can ensure the relative position between the movable part and the fixed part in the horizontal direction, and ensure the accuracy of the swing hook grasping.

[0014] A further solution is that the box pulling device also includes a second travel switch and a second abutment; one of the second travel switch and the second abutment is arranged on the movable part, and the other of the second travel switch and the second abutment is arranged on the fixed part; the second travel switch and the second abutment are abutted in the sliding direction of the movable part.

[0015] As can be seen from the above, after the first travel switch provides the first sensing signal, the system controls the slide rail assembly to slow down and then stop working. During the process, the movable part produces relative movement relative to the fixed part and obtains the second sensing signal. The system then sends a control signal to the drive assembly to rotate the swing hook part, and the swing hook part swings and enters the slot of the material box. This setting can ensure the stability of the swing hook part when entering the slot, thereby ensuring the success rate of pulling the box.

[0016] A further solution is that the box pulling device also includes a third stroke switch and a fourth stroke switch; the third stroke switch and the fourth stroke switch are both arranged outside the first side of the main body, and the third stroke switch and the fourth stroke switch are both arranged on the circumference of the rotating output shaft; on the circumference of the rotating output shaft, the central angle of the third stroke switch and the fourth stroke switch with respect to the axis of the rotating output shaft is greater than 90 degrees; the swing hook member can rotate between a first swing position and a second swing position, the first swing position is the position where the swing hook member contacts the third stroke switch, and the second swing position is the position where the swing hook member contacts the fourth stroke switch.

[0017] As can be seen from the above, the third travel switch and the fourth travel switch are used to control the swing angle of the swing hook member to prevent the swing hook member from swinging excessively and causing the box pulling to fail.

[0018] A further solution is that the box pulling device includes at least two swing hook members, the driving assembly includes at least two rotating output shafts, and each rotating output shaft is connected to a swing hook member.

[0019] As can be seen from the above, this setting can improve the success rate of pulling the box, and can prevent the material box from swaying during the pulling process, affecting subsequent transportation work.

[0020] A further solution is that the rotation directions of at least two swing hook members are opposite to each other.

[0021] As can be seen from the above, this arrangement brings together the swinging spaces of the two swing hooks, and the slot of the material box can be set as a long slot, with both swing hooks entering the same slot, which is more conducive to the design of the swing hook size and the processing of the material box.

[0022] A further solution is that the drive assembly includes a drive motor, a transmission gear set and two rotating output shafts; the transmission gear set includes an input gear, a transition gear, a first output gear and a second output gear, the input gear is connected to the motor output shaft of the drive motor, the first output gear is meshed with the input gear, and the transition gear is meshed between the input gear and the second output gear; a rotating output shaft is installed in the first output gear, and another rotating output shaft is installed in the second output gear.

[0023] As can be seen from the above, this arrangement is simple and effective in achieving the opposite rotation of the two swing hook members.

[0024] The material transport robot provided by the second purpose of the present invention includes a body, a driving wheel assembly, a lifting device, a slide rail assembly and a box pulling device; the driving wheel assembly is installed at the bottom of the body, the lifting device is installed at the upper part of the body, the lifting device includes a lifting platform, the slide rail assembly is installed on the lifting platform, and the box pulling device is installed on the slide rail assembly; the lifting platform can translate in the vertical direction relative to the body, and the box pulling device can translate in the horizontal direction relative to the lifting platform; the box pulling device adopts the above-mentioned box pulling device; the rotating output shaft extends in the horizontal direction.

[0025] It can be seen from the above scheme that before reaching the material box, the swing hook part of the swing hook member is in a non-downward state. When the slide rail assembly pushes the box-pulling device forward, the contact part of the first travel switch touches the material box and sends a touch signal to the control system, and the system sends a control signal to the drive assembly to rotate the swing hook member, and the swing hook part swings and enters the slot. After the lifting platform reaches the horizontal position where the material box is located, it does not need to move further, and then the slide rail assembly moves forward once, which simplifies the work of the lifting device and the slide rail assembly, and the box-pulling device has a simple structure and can effectively pull the material box, thereby improving work efficiency.

[0026] The material transportation method provided by the third purpose of the present invention is executed by the above-mentioned material transportation robot. The material transportation method includes driving the slide rail assembly to make the box pulling device translate outward in the horizontal direction; judging whether a contact signal from the first stroke switch is obtained, and if so, stopping driving the slide rail assembly and starting the driving assembly to make the swing hook member rotate along the rotating output shaft.

[0027] It can be seen from the above scheme that after the lifting platform reaches the horizontal position where the material box is located, there is no need to continue moving, and then the slide rail assembly only needs to move forward once. The work of the lifting device and the slide rail assembly is simplified, the structure of the box pulling device is simple and the material box can be effectively dragged, thereby improving work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 This is a structural diagram of the material transport robot embodiment of the present invention from the first perspective.

[0029] Figure 2 This is a structural diagram of the material transport robot embodiment of the present invention from a second perspective.

[0030] Figure 3 It is a structural diagram of the lifting device in the embodiment of the material transport robot of the present invention.

[0031] Figure 4 This is a structural diagram from the first perspective of the slide rail assembly in an embodiment of the material transport robot of the present invention.

[0032] Figure 5 This is a structural diagram of the slide rail assembly from a second perspective in an embodiment of the material transport robot of the present invention.

[0033] Figure 6 This is a structural diagram from the first perspective of the box pulling device in the material transport robot embodiment of the present invention.

[0034] Figure 7 This is a structural diagram from a second perspective of the box pulling device in an embodiment of the material transport robot of the present invention.

[0035] Figure 8It is a side view of the swing hook member in the material transport robot embodiment of the present invention.

[0036] Fig. 9 Schematic diagram of the connection relationship between the transmission gear set and the swing hook member in the material transport robot embodiment of the present invention.

[0037] Fig.10 This is a working status diagram of an embodiment of the material transport robot of the present invention.

[0038] Fig.11 It is a structural diagram of the material box in the embodiment of the material transport robot of the present invention.

[0039] Fig.12 Schematic diagram of the first working state of the material transport robot embodiment of the present invention.

[0040] Fig.13 Schematic diagram of the second working state of the material transport robot embodiment of the present invention.

[0041] Fig.14 for Fig.13 A in the middle is a further detailed structural diagram after enlarging.

[0042] Fig.15 It is a partial schematic diagram of the third working state of the material transport robot embodiment of the present invention.

[0043] Fig.16 This is a working principle diagram of the transmission gear set and the swing hook member in the material transport robot embodiment of the present invention.

[0044] Fig.17 It is a schematic diagram of the matching relationship between the swing hook and the material box in the embodiment of the material transport robot of the present invention. DETAILED DESCRIPTION

[0045] See also Figure 1 and Figure 2 , Figure 1 and Figure 2 The material transport robot embodiment of the present invention is a structural diagram of the first and second perspectives. The material transport robot includes a body 1, a driving wheel assembly 21, a supporting wheel assembly 22, a lifting device 3, a slide rail assembly 4 and a box pulling device 5. The lifting device 3 is installed on the upper part of the body 1. The lifting device 3 includes a lifting platform 35, the slide rail assembly 4 is installed on the lifting platform 35, and the box pulling device 5 is installed on the slide rail assembly 4.

[0046] The body 1 is in a "U" shape and is composed of a base 11 and two side walls 12. The side walls 12 are erected on both lateral sides (in the y-axis direction) of the base 11. The body 1 penetrates along the X-axis direction in the space between the two side walls 12. The drive wheel assembly 21 and the support wheel set 22 are installed at the bottom of the base 11. The drive wheel assembly 21 includes two pairs of drive wheels rotatably installed at the bottom of the base 11, and the support wheel set 22 includes support wheels arranged at the four corners of the bottom surface of the base 11.

[0047] Combined Figure 1 with Figure 3 , Figure 3 FIG. is the structural diagram of the lifting device in the embodiment of the material transportation robot of the present invention. The lifting device 3 is composed of a lifting motor 31, a first belt transmission assembly 32, two sets of lead screw assemblies 33, a second belt transmission assembly 34, two sets of guide rail assemblies 39, and a lifting platform 35. The lead screw assembly 33 includes a lead screw 331 and a lead screw slide 332 with a lead screw nut sleeved on the lead screw 331. The guide rail assembly 39 includes a guide rail 391 and a slider 392.

[0048] The lifting motor 31, the first belt transmission assembly 32, the first set of lead screw assemblies 33, and the first set of guide rail assemblies 39 are arranged inside the side wall 12 on the first side. The second belt transmission assembly 34 is arranged inside the base 11. The second set of lead screw assemblies 33 and the second set of guide rail assemblies 39 are arranged inside the side wall 12 on the second side. The lead screw slides 332 of the two sets of lead screw assemblies 33 are respectively fixed on the opposite sides of the lifting platform 35, and the sliders 392 of the two sets of guide rail assemblies 39 are respectively fixed on the opposite sides of the lifting platform 35.

[0049] The output shaft of the lifting motor 31 is connected to the input pulley of the first belt transmission assembly 32. The output pulley of the first belt transmission assembly 32 is connected to the extended first end of the first lead screw 331. The input pulley of the second belt transmission assembly 34 is fixedly sleeved on the extended second end of this lead screw 331, and the output pulley of the second belt transmission assembly 34 is fixedly sleeved on the extended end of the other lead screw 331.

[0050] Two long strip-shaped pads 36 are installed on both sides of the upper surface of the lifting platform 35, and the two pads 36 are symmetrically arranged on the lifting platform 35. The pads 36 extend along the x-axis direction, and the upper surface of the pads 36 is a supporting surface. A protective wall 361 is arranged on the outer edge of the upper surface 360 ​​of the pads 36. The protective wall 361 is far away from the middle of the lifting platform 35 relative to the upper surface 360, and the protective wall 361 extends along the x-axis direction; the front end of the lifting platform 35 in the positive direction of the x-axis is the end where the material box enters, and the upper surface 360 ​​extends a downwardly inclined slope panel 362 at the extended end in the positive direction of the x-axis, and the protective wall 361 extends an extended wall 363 at the extended end in the positive direction of the x-axis. In the y-axis direction, the extended wall 363 gradually turns away from the lifting platform 35 from the extended start end to the extended end end. The two extended walls 363 form an entrance with a gradually narrowing width and a guiding effect in front of the lifting platform 35. The setting of the slope panel 362 can also reduce the interference problem.

[0051] See also Figure 4 and Figure 5 , Figure 4 and Figure 5 The first and second perspectives of the slide rail assembly in the material transport robot embodiment of the present invention are structural diagrams. The slide rail assembly 4 includes a first rail 411, a first slide 421, a second rail 412, a second slide 422, a first rack 451, a second rack 452, a first motor 431 and a second motor 432. The output shaft of the first motor 431 is equipped with a first gear 441, and the output shaft of the second motor 432 is equipped with a second gear 442. The first rail 411 is fixed to the lifting platform 35 along the x-axis direction, and the second rail 412 is fixed to the first slide 421 along the x-axis direction. The rack 451 and the second rack 452 are both fixed on the first slide 421, the first motor 431 is installed on the lifting platform 35, and the second motor 432 is installed on the second slide 422; the first slide 421 and the first track 411 slide in the x-axis direction, and the first rack 451 meshes with the first gear 441; the second slide 422 and the second track 412 slide in the x-axis direction, and the second rack 452 meshes with the second gear 442, and the box pulling device 5 is fixed on the second slide 422 ( Figure 1 Show).

[0052] The first rack 451 and the second rack 452 are symmetrically arranged on both sides of the first slide 421 in the x-axis direction, and the first track 411 is located directly below the second track 412. The first motor 431 is installed on the lower side of the lifting platform 35, and the output shaft of the first motor 431 passes through the lifting platform 35 to reach the top of the lifting platform 35. The material transport robot also includes a protective cover 49, which is installed on the lifting platform 35 and shields the first gear 441 from above.

[0053] The material transport robot also includes a first proximity sensor 461, a second proximity sensor 462, a third proximity sensor 463, a fourth proximity sensor 464, a fifth proximity sensor 465, a first detection member 471, a second detection member 472, a third detection member 473 and a fourth detection member 474; the first detection member 471 is installed on the first slide 421, and the first proximity sensor 461 and the second proximity sensor 462 are installed on the lifting platform 35; the first slide 421 can slide relative to the lifting platform 35 between a first extreme position and a second extreme position, the first extreme position is the position where the first detection member 471 is located within the detection range of the first proximity sensor 461, and the second extreme position is the position where the first detection member 471 is located within the detection range of the second proximity sensor 462.

[0054] The second detection member 472 and the third detection member 473 are mounted on the first slide 421, and the third proximity sensor 463 is arranged on the second slide 422; the second slide 422 can slide relative to the first slide 421 between the third limit position and the fourth limit position, the third limit position is the position where the second detection member 472 is located within the detection range of the third proximity sensor 463, and the fourth limit position is the position where the third detection member 473 is located within the detection range of the third proximity sensor 463. The fourth detection member 474 is mounted on the lifting platform 35, and the fourth proximity sensor 464 is mounted on the box pulling device 5; the box pulling device 5 can slide relative to the lifting platform 35 to the fifth limit position, and the fifth limit position is the position where the fourth detection member 474 is located within the detection range of the fourth proximity sensor 464.

[0055] The first detection member 471, the first proximity sensor 461 and the second proximity sensor 462 cooperate to control the moving range of the first slide 421; the second detection member 472, the third detection member 473 and the third proximity sensor 463 cooperate to control the moving range of the box pulling device 5; the fourth detection member 474 and the fourth proximity sensor 464 cooperate to control the extreme position of the box pulling device 5 relative to the lifting platform.

[0056] The fifth proximity sensor 465 is disposed adjacent to the second proximity sensor 462 in the x-axis direction and is farther from the first proximity sensor 461 than the second proximity sensor 462. The fifth proximity sensor 465 detects and controls the limit distance of the first slide 421 extending in the positive direction of the x-axis.

[0057] The upper side of the lifting platform 35 is provided with a first limiting protrusion (not shown in the figure) and a second limiting protrusion 482, and the lower side of the first slide 421 is provided with a third limiting protrusion (not shown in the figure); the upper limit of the third limiting protrusion in the y-axis direction is located between the first limiting protrusion and the second limiting protrusion 482. The upper side of the first slide 421 is provided with a fourth limiting protrusion 484 and a fifth limiting protrusion 485, and the lower side of the box pulling device 5 is provided with a sixth limiting protrusion 486; the upper limit of the sixth limiting protrusion 486 in the y-axis direction is located between the fourth limiting protrusion 484 and the fifth limiting protrusion 485. The setting of multiple limiting protrusions can limit the travel range of the slide rail assembly from a physical level, thereby improving the safety of the material transport robot.

[0058] See also Figure 6 and Figure 7 , Figure 6 and Figure 7 The box pulling device 5 comprises a main body 51, a driving assembly, a swing hook 54, a first travel switch 571, a second travel switch 572, a third travel switch 573, a fourth travel switch 574 and a second abutment 582. The driving assembly comprises a driving motor 52, a transmission gear set 53, a rotating output shaft 534 and a rotating output shaft 535 ( Fig. 9 Show).

[0059] The main body 51 includes a fixed part 511 and a movable part 512, a guide rail is arranged between the fixed part 511 and the movable part 512 to slide and connect along the x-axis direction; an elastic member is connected between the fixed part 511 and the movable part 512, and the elastic member is a spring 56. An L-shaped plate 551 is fixedly installed on the fixed part 511, and the movable part 512 is bent from the bottom wall to form a raised retaining wall 552. A positioning column is locked on the L-shaped plate 551 by a bolt, and after the spring 56 is sleeved on the positioning column, the other end of the positioning column can be slidably inserted into the through hole of the retaining wall 552. Therefore, the fixed part 511 and the movable part 512 can not only slide against each other along the x-axis direction, but also return to the position before sliding under the elastic force of the spring 56.

[0060] The driving motor 52 is fixed in the movable part 512, and the movable part 512 has a wall located in front of the X-axis. The two swing hooks 54 are rotatably mounted on the outside of the wall through bearings and a rotating output shaft, and a buffer block 59 is installed on the left and right sides of the wall of the movable part 512. The buffer block 59 is made of rubber block, silicone block or metal material.

[0061] Combination Figure 8 , Figure 8The figure is a side view of the swing hook member in the embodiment of the material transport robot of the present invention. The swing hook member 54 includes a connecting portion 541, a cantilever portion 542, a swing hook portion 543 and a touch protrusion 544. The connecting portion 541 and the swing hook portion 543 are respectively connected to the two ends of the extension of the cantilever portion 542, and the touch protrusion 544 is located adjacent to the connecting portion 541.

[0062] Recombination Fig. 9 , Fig. 9 The figure is a connection diagram of the transmission gear set and the swing hook member in the embodiment of the material transport robot of the present invention. The connecting portion 541 has an axial hole arranged along its thickness direction. Taking the rotating output shaft 534 as an example, the rotating output shaft 534 is inserted into the axial hole of the connecting portion 541; the cantilever portion 542 extends along the axial direction of the rotating output shaft 534, the swing hook portion 543 extends from the extended end of the cantilever portion 542 perpendicularly to the cantilever portion 542 to the outer periphery, and the contact protrusion 544 extends from the outer periphery of the connecting portion 541 in the radial direction away from the rotating output shaft 534.

[0063] The transmission gear set 53 includes an input gear 530, a transition gear 533, a first output gear 531 and a second output gear 532. The input gear 530 is connected to the motor output shaft of the driving motor 52. The first output gear 531 meshes with the input gear 530. The transition gear 533 meshes between the input gear 530 and the second output gear 532. A rotating output shaft 534 is installed in the first output gear 531, and a rotating output shaft 535 is installed in the second output gear 532. Due to the provision of the transition gear 533, the first output gear 531 and the second output gear 532 rotate in opposite directions. The two swing hooks 54 are respectively connected to the first output gear 531 and the second output gear 53, so the rotation directions of the two swing hooks 54 are also opposite.

[0064] The first travel switch 571, the second travel switch 572, the third travel switch 573 and the fourth travel switch 574 are all mechanical touch switches. The first travel switch 571 is installed on the outside of the movable part 512 and is located below the horizontal position of the swing hook 54. The elastic touch end of the first travel switch 571 has a swing stroke in the x-axis direction. When the box pulling device 5 moves in the positive direction along the x-axis, the elastic touch end of the first travel switch 571 can collide with the material box.

[0065] An L-shaped second abutment member 582 is disposed inside the fixed portion 511. The second abutment member 582 has a retaining wall located in the X-axis direction. The second travel switch 572 is fixedly disposed in the movable portion 512, and the elastic contact end of the first travel switch 572 has a swing stroke in the X-axis direction. When the movable portion 512 slides relative to the fixed portion 511, the elastic contact end of the second travel switch 572 may collide with the retaining wall of the second abutment member 582.

[0066] The third stroke switch 573 and the fourth stroke switch 574 are both arranged outside the wall body of the movable part 512 where the swing hook 54 is located, and the third stroke switch 573 and the fourth stroke switch 574 are both arranged on the circumference of the rotating output shaft 534, and the central angle between the third stroke switch 573 and the fourth stroke switch 574 with respect to the axis of the rotating output shaft 534 is 90 degrees, and the elastic touch end of the third stroke switch 573 has a swing stroke in the y-axis direction, and the elastic touch end of the fourth stroke switch 574 has a swing stroke in the z-axis direction.

[0067] In the circumferential direction of the rotating output shaft 534, the swing hook member 54 can rotate between a first swing position and a second swing position. The first swing position is a position where the touch protrusion 544 on the swing hook member 54 contacts the elastic touch end of the third travel switch 573, and the second swing position is a position where the touch protrusion 544 on the swing hook member 54 contacts the elastic touch end of the fourth travel switch 574.

[0068] The touching protrusion 544 and the swing hook portion 543 are located at the same circumferential position. When the swing hook member 54 is at the first swing position, the extension direction of the swing hook portion 543 is the y-axis direction. When the swing hook member 54 is at the second swing position, the extension direction of the swing hook portion 543 is the negative z-axis direction.

[0069] Combined with 1. Figure 3 , Fig.10 and Fig.11 , Fig.10 This is a working state diagram of an embodiment of the material transport robot of the present invention. Fig.11 The structural diagram of the material box in the embodiment of the material transport robot of the present invention. The lifting platform 35 is used to place the material box 9, which enters the space between the two side walls 12 along the x-axis direction and is supported on two pads 36 on both sides. The outer periphery of the material box 9 is square, and it has a square peripheral wall 91 surrounding the outer periphery of the bottom plate. The outer side of the peripheral wall 91 has a boss 911, and two slots 92 with upward openings are formed on the boss 911. The two slots 92 extend in a long shape along the y-axis direction.

[0070] Combination Fig.12 and Fig.13 , Fig.12 and Fig.13 Schematic diagrams of the first working state and the second working state of the material transport robot embodiment of the present invention. After the material transport robot 100 receives the system's pickup instruction, it goes to the shelf 200 to perform the pickup task. At this time, both swing hooks 54 are in the first swing position ( Fig.16 (a)

[0071] When the material transport robot 100 approaches the shelf 200, the system starts the lifting device 3 ( Figure 3The lifting platform 35 is raised until the sensor detects that the horizontal position of the lifting platform 35 matches the horizontal position of the cargo layer 201 where the material box 9 is located, and the system starts the slide rail assembly 4 ( Figure 4 As shown in the figure, the first slide 421 and the second slide 422 slide to make the box pulling device 5 enter the shelf layer 201.

[0072] Combination Figure 6 , Figure 7 , Fig.13 , Fig.14 and Fig.15 , Fig.14 for Fig.13 A in the middle is a further detailed structural diagram after enlarging. Fig.15 It is a partial schematic diagram of the third working state of the material transport robot embodiment of the present invention. The box-pulling device 5 approaches the material box 9, and the elastic contact end of the first stroke switch 571 first touches the peripheral wall 91 of the material box 9, and the system receives the switch current signal from the first stroke switch 571. The box-pulling device 5 continues to move forward toward the material box 9, and the buffer block 59 first hits the peripheral wall 91 of the material box 9, and then the movable part 512 slides in the negative direction of the x-axis relative to the fixed part 511, and the spring 56 is compressed, thereby achieving a buffering effect to protect the box-pulling device 5; until the elastic contact end of the second stroke switch 572 hits the retaining wall of the second abutment 582, the system receives the switch signal from the second stroke switch 572, and the slide rail assembly 4 stops working to stop the previous movement of the box-pulling device 5. At this time, the swing hook part 543 of the swing hook member 54 has reached the top of the opening of the slot 92.

[0073] Combination Fig.16 and Fig.17 , Fig.16 This is a working principle diagram of the transmission gear set and the swing hook member in the material transport robot embodiment of the present invention. Fig.17 Schematic diagram of the coordination relationship between the swing hook and the material box in the embodiment of the material transport robot of the present invention. When the system receives the switch signal from the second stroke switch 572, it sends a start signal to the drive motor 52, and the two swing hooks 54 are rotated through the transmission gear set 53, the rotation output shaft 534 and the rotation output shaft 535. The initial swing hook 54 is in the first swing position (as shown in the state diagram a). When the swing hook 54 rotates 90 degrees, the touch protrusion 544 touches the elastic touch end of the fourth stroke switch 574, the drive motor 52 stops rotating, and the swing hook 543 faces downward and enters the slot 92.

[0074] Then, the system starts the slide rail assembly 4 again to move the box pulling device 5 along the negative direction of the x-axis to pull the material box 9 out of the shelf. Figure 3After the lifting platform 35 reaches the horizontal position where the material box 9 is located, it does not need to move further, and then the slide rail assembly 4 only needs to move forward once, which simplifies the work of the lifting device 3 and the slide rail assembly 4, and the box pulling device 5 has a simple structure and can effectively pull the material box 9, thereby improving work efficiency.

[0075] Finally, it should be emphasized that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various changes and modifications. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A box pulling device, characterized in that: include: A main body, a driving assembly, a swing hook and a first travel switch; The driving assembly is disposed in the main body, and the swing hook and the first travel switch are both disposed outside the first side of the main body; The swing hook member comprises a connecting portion, a cantilever portion and a swing hook portion, wherein the connecting portion and the swing hook portion are respectively connected to two extended ends of the cantilever portion; The connecting portion is fixedly connected to the rotating output shaft of the driving assembly, the cantilever portion extends along the axial direction of the rotating output shaft, and the swing hook portion extends from the extending end of the cantilever portion perpendicular to the cantilever portion toward the outer periphery; The main body comprises a fixed part and a movable part, and an elastic member is connected between the fixed part and the movable part; The driving assembly is installed in the movable part, and the swing hook and the first travel switch are installed on the outside of the movable part; The box pulling device also includes a second travel switch and a second abutment member; One of the second travel switch and the second abutment is arranged on the movable portion, and the other of the second travel switch and the second abutment is arranged on the fixed portion; The second travel switch abuts against the second abutment member in the sliding direction of the movable portion; The elastic member is a spring; an L-shaped plate is fixedly mounted on the fixed portion, the movable portion is bent from the bottom wall to form a raised retaining wall, a positioning column is locked on the L-shaped plate by a bolt, and after the spring is sleeved on the positioning column, the other end of the positioning column can be slidably inserted into the through hole of the retaining wall; The movable part has a wall body located in front of the sliding direction of the movable part, and the two swing hooks are rotatably installed on the outside of the wall body through bearings and a rotating output shaft, and a buffer block is installed on both sides of the movable part on the left and right sides of the wall body.

2. The box pulling device according to claim 1, characterized in that: The fixed portion and the movable portion are slidably connected along the axial direction of the rotating output shaft.

3. The box pulling device according to claim 1 or 2, characterized in that: The box pulling device also includes a third travel switch and a fourth travel switch; The third travel switch and the fourth travel switch are both arranged outside the first side of the main body, and the third travel switch and the fourth travel switch are both arranged in the circumferential direction of the rotating output shaft; In the circumferential direction of the rotating output shaft, the central angle between the third travel switch and the fourth travel switch with respect to the axis of the rotating output shaft is greater than 90 degrees; The swing hook member can rotate between a first swing position and a second swing position, wherein the first swing position is a position where the swing hook member contacts the third travel switch, and the second swing position is a position where the swing hook member contacts the fourth travel switch.

4. The box pulling device according to claim 1 or 2, characterized in that: The box pulling device includes at least two swing hook members, and the driving assembly includes at least two rotating output shafts, each of which is connected to one swing hook member.

5. The box pulling device according to claim 4, characterized in that: The rotation directions of at least two of the swing hook members are opposite to each other.

6. The box pulling device according to claim 5, characterized in that: The driving assembly includes a driving motor, a transmission gear set and two rotating output shafts; The transmission gear set comprises an input gear, a transition gear, a first output gear and a second output gear, wherein the input gear is connected to the motor output shaft of the driving motor, the first output gear is meshed with the input gear, and the transition gear is meshed between the input gear and the second output gear; One of the rotating output shafts is installed in the first output gear, and another of the rotating output shafts is installed in the second output gear.

7. Material transport robot, including a body, a driving wheel assembly, a lifting device, a slide rail assembly and a box pulling device; The driving wheel assembly is installed at the bottom of the machine body, the lifting device is installed at the upper part of the machine body, the lifting device includes a lifting platform, the slide rail assembly is installed on the lifting platform, and the box pulling device is installed on the slide rail assembly; The lifting platform can translate in the vertical direction relative to the machine body, and the box pulling device can translate in the horizontal direction relative to the lifting platform; Features: The box pulling device adopts the box pulling device according to any one of claims 1 to 6 above; The rotation output shaft extends along the horizontal direction.

8. A material transportation method, characterized in that: The material transportation method is performed by the material transportation robot according to claim 7, and comprises: Driving the slide rail assembly to make the box pulling device translate outward along the horizontal direction; Determine whether a contact signal from the first travel switch is obtained. If so, the system controls the slide rail assembly to decelerate. During the deceleration process, the movable part moves relative to the fixed part and obtains the induction signal of the second travel switch; After acquiring the sensing signal of the second travel switch, the system controls the slide rail assembly to stop working, and then sends a control signal to the drive assembly to rotate the swing hook member.

Citation Information

Patent Citations

  • Transfer Device And Carrier System

    CN105398725A

  • Shift fork limit structure and fork assembly

    CN208233911U

  • Box pulling device and material transportation robot

    CN210028827U

  • Transfer device and control method of transfer device

    JP2017052599A