A high-pressure pump system and control method for an LNG receiving station
By using a liquid level control valve in the high-pressure pump system of the LNG receiving station to adjust the liquid level in the vent line, the vibration problem caused by the encounter between BOG gas and LNG liquid is solved and the stable operation of the receiving station is ensured.
Patent Information
- Application Number
- CN201910672113.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-07-24
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2039-07-24
AI Technical Summary
In the LNG receiving station, the BOG gas generated during the pressurization process of the high-pressure pump meets the LNG liquid in the vent pipeline, causing the vent pipeline to vibrate greatly and posing risks to the stable operation of the receiving station.
A liquid level control valve is used to adjust the liquid level in the first venting line, so that only BOG gas or part of the LNG liquid is discharged through the liquid level control valve when the high-pressure pump is working. The LNG liquid is used to take away the heat generated by the high-pressure pump and avoid two-phase Fluids meet.
It effectively reduces the vibration of the venting pipeline and ensures the safe and stable operation of the LNG receiving station.
Smart Images

Figure CN110307469B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of LNG receiving stations, and in particular to a high-pressure pump system of an LNG receiving station and a control method thereof. Background Art
[0002] LNG (Liquefied Natural Gas) is the abbreviation of liquefied natural gas. During the operation of the LNG receiving station, low-pressure LNG is pressurized by the high-pressure pump and then enters the next stage for gasification and external transmission. Due to the low-temperature characteristics of LNG, the heat generated during the pressurization process of the high-pressure pump will cause part of the LNG to gasify and form BOG gas. In order to avoid cavitation of the high-pressure pump, the BOG gas needs to be released in time.
[0003] In the prior art, a vent line is usually set on the high-pressure pump, and the BOG gas generated during the pressurization process of the high-pressure pump is sent to the recondenser through the vent line. Since the recondenser is located above and on one side of the high-pressure pump, there is a long horizontal line in the vent line, so the horizontal line of the vent line is filled with a large amount of LNG liquid. The BOG gas generated during the pressurization process of the high-pressure pump meets the LNG liquid in the vent line, resulting in a large vibration of the vent line during the operation of the high-pressure pump, which brings a great risk to the stable operation of the LNG receiving station. Summary of the invention
[0004] The purpose of the present invention is to provide a LNG receiving station high-pressure pump system and a control method thereof, which can solve the problem in the prior art that the BOG gas generated during the pressurization process of the high-pressure pump meets the LNG liquid in the venting pipeline, causing large vibrations during operation.
[0005] To achieve this object, the present invention adopts the following technical solutions:
[0006] A high-pressure pump system for an LNG receiving station includes a high-pressure pump, wherein the high-pressure pump is provided with a vent port, and further includes:
[0007] a first vent line, one end of which is connected to the vent port;
[0008] A liquid level control valve, wherein the other end of the first vent line is connected to an inlet of the liquid level control valve, a height of the inlet of the liquid level control valve is higher than a height of the vent port, and the liquid level control valve is used to adjust the liquid level height in the first vent line.
[0009] As a preferred technical solution of the above-mentioned LNG receiving station high-pressure pump system, it also includes:
[0010] The venting buffer space is arranged on the first venting pipeline, the bottom of the venting buffer space is provided with a first connecting port connected to the venting port, and the top of the venting buffer space is provided with a second connecting port connected to the liquid level control valve inlet.
[0011] As a preferred technical solution of the above-mentioned LNG receiving station high-pressure pump system, it also includes:
[0012] A recondenser is used for mixing LNG liquid and BOG gas to condense BOG gas to form LNG liquid, and a liquid outlet of the recondenser is communicated with a liquid inlet of the high-pressure pump.
[0013] As a preferred technical solution of the above-mentioned LNG receiving station high-pressure pump system, it also includes:
[0014] A reflux pipeline, one end of which is connected to a discharge port of the high-pressure pump;
[0015] A flash separation device, the other end of the reflux line is connected to the recondenser through the flash separation device, and the flash separation device is used to perform gas-liquid separation on the LNG liquid and BOG gas that enter the recondenser through the reflux line.
[0016] As a preferred technical solution of the above-mentioned LNG receiving station high-pressure pump system, the flash separation device is located above the packing layer of the recondenser.
[0017] As a preferred technical solution of the above-mentioned LNG receiving station high-pressure pump system, it also includes:
[0018] A high-pressure pump outlet manifold, one end of which is connected to a liquid discharge port of the high-pressure pump;
[0019] A first control valve group, wherein the first control valve group controls the drain port to selectively communicate with the reflux line or the high-pressure pump outlet manifold.
[0020] As an optimal technical solution for the above-mentioned LNG receiving station high-pressure pump system, it also includes a second control valve group, which can enable the outlet of the liquid level control valve to selectively connect to the BOG system of the LNG receiving station, the exhaust system of the LNG receiving station or one of the recondensers.
[0021] As a preferred technical solution for the above-mentioned LNG receiving station high-pressure pump system, an LNG inlet and a BOG inlet are provided above the packing layer of the recondenser, and the LNG inlet and the BOG inlet are provided with an LNG main pipe and a BOG main pipe respectively.
[0022] As a preferred technical solution of the above-mentioned LNG receiving station high-pressure pump system, it also includes:
[0023] An air supply pipeline, wherein an air supply port is provided above the packing layer of the recondenser, and one end of the air supply pipeline is connected to the air supply port;
[0024] The air supply valve is arranged on the air supply pipeline.
[0025] The present invention also provides a control method for a high-pressure pump system of an LNG receiving station, which is applied to the above-mentioned high-pressure pump system of an LNG receiving station;
[0026] During the operation of the high-pressure pump, the liquid level height in the first vent line is adjusted by the liquid level control valve so that only BOG gas is discharged through the liquid level control valve, or part of the LNG liquid is discharged through the first vent line and the liquid level control valve so that the LNG liquid can take away the heat generated by the operation of the high-pressure pump.
[0027] Beneficial effects of the present invention: The LNG receiving station high-pressure pump system and control method thereof provided by the present invention are additionally provided with a liquid level control valve, one end of the first venting pipeline is connected to the venting port, and the other end is connected to the inlet of the liquid level control valve. The liquid level in the first venting pipeline is adjusted by the liquid level control valve, so that when the high-pressure pump is working, only the BOG gas formed by LNG gasification is discharged through the liquid level control valve, or part of the LNG liquid is discharged through the first venting pipeline and the liquid level control valve to use the LNG liquid to take away the heat generated by the operation of the high-pressure pump, which effectively solves the problem of large vibration of the venting pipeline caused by the encounter of the two-phase fluid of LNG liquid and BOG gas in the venting pipeline, and provides a guarantee for the safe and stable operation of the entire LNG receiving station. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments of the present invention. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the contents of the embodiments of the present invention and these drawings without paying any creative work.
[0029] Figure 1 It is a schematic diagram of a high-pressure pump system for an LNG receiving station provided in an embodiment of the present invention.
[0030] In the figure:
[0031] 1. High-pressure pump; 2. First venting pipeline; 3. Venting buffer space; 4. Liquid level control valve; 5. Recondenser; 51. Packing layer; 52. Flash separation device; 6. LNG main pipe; 7. BOG main pipe; 8. High-pressure pump inlet main pipe; 9. High-pressure pump outlet main pipe; 10. First isolation valve; 11. Second isolation valve; 12. Third isolation valve; 13. Reflux pipeline; 14. Air supply pipeline; 15. Second venting pipeline. DETAILED DESCRIPTION
[0032] In order to make the technical problems solved by the present invention, the technical solutions adopted and the technical effects achieved clearer, the technical solutions of the present invention are further described below in conjunction with the accompanying drawings and through specific implementation methods. It is understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for the convenience of description, only the parts related to the present invention are shown in the accompanying drawings, not all.
[0033] Figure 1 is a schematic diagram of the high-pressure pump system of the LNG receiving station provided in this embodiment, such as Figure 1 As shown, this embodiment provides a high-pressure pump system for an LNG receiving station, including a recondenser 5 for mixing LNG and BOG, and a high-pressure pump 1 connected to the liquid outlet of the recondenser 5 and located below the recondenser 5. Specifically, a BOG inlet and an LNG inlet are provided above the packing layer 51 of the recondenser 5, and a BOG main pipe 7 and an LNG main pipe 6 are provided at the BOG inlet and the LNG inlet, respectively. The BOG main pipe 7 and the LNG main pipe 6 respectively pass 0.5MPag~0.8MPag BOG and -160℃~-150℃ LNG into the recondenser 5 for mixing, and use the energy of LNG to condense BOG to form LNG, and then the mixed LNG is passed through the buffer chamber at the bottom of the recondenser 5 through the high-pressure pump inlet main pipe 8 into the high-pressure pump 1 for pressurization, and after pressurization, it enters the next stage through the high-pressure pump outlet main pipe 9 for gasification and external transmission.
[0034] During the operation of the high-pressure pump 1, BOG gas will be generated. In order to avoid cavitation of the high-pressure pump 1, this part of BOG needs to be released in time. The existing method is usually to set a vent port on the high-pressure pump 1, and connect one end of the first vent pipeline 2 to the vent port to discharge the BOG gas generated during the operation of the high-pressure pump 1. However, since the high-pressure pump 1 is located below one side of the recondenser 5, there is a large horizontal distance between the high-pressure pump 1 and the recondenser 5. There is a long horizontally placed part of the first vent pipeline 2 near the vent port, which will make the horizontally placed first vent pipeline 2 full of LNG liquid. The two-phase fluid of LNG liquid and BOG gas discharged through the vent port meet in the first vent pipeline 2, which will cause the first vent pipeline 2 to vibrate greatly, and bring greater risks to the operation of the LNG receiving station.
[0035] In this embodiment, a liquid level control valve 4 is added, and the height of the inlet of the liquid level control valve 4 is higher than the height of the venting port. One end of the first venting pipeline 2 is connected to the inlet of the liquid level control valve 4, and the other end is connected to the venting port. The liquid level in the first venting pipeline 2 is adjusted by the liquid level control valve 4, so that when the high-pressure pump 1 is working, only the BOG gas formed by the gasification of LNG is discharged through the first venting pipeline 2, or part of the LNG liquid is discharged through the first venting pipeline 2 and the liquid level control valve 4 to use the LNG liquid to take away the heat generated by the operation of the high-pressure pump 1, thereby preventing the LNG liquid from being gasified to form BOG gas due to the heat generated by the operation of the high-pressure pump 1.
[0036] Furthermore, the LNG receiving station high-pressure pump system further comprises a venting buffer space 3, which is located on the first venting pipeline 2. The bottom of the venting buffer space 3 is provided with a first connecting port connected to the venting port, and the top of the venting buffer space 3 is provided with a second connecting port connected to the inlet of the liquid level control valve 4. By adjusting the liquid level control valve 4 to make the liquid level in the venting buffer space 3 lower than its highest liquid level, only BOG gas enters the liquid level control valve 4 through the first venting pipeline 2 and is discharged from the outlet of the liquid level control valve 4. This part of BOG gas is mainly formed by gasification of part of LNG due to the heat generated by the operation of the high-pressure pump 1; or by adjusting the liquid level control valve 4 to make part of the LNG liquid enter the liquid level control valve 4 through the first venting pipeline 2 and be discharged from the outlet of the liquid level control valve 4, so as to use the LNG liquid to take away the heat generated by the high-pressure pump 1, effectively solving the problem of large vibration of the venting pipeline caused by the two-phase fluid of LNG liquid and BOG gas meeting in the venting pipeline, and providing guarantee for the safe and stable operation of the entire LNG receiving station.
[0037] Furthermore, due to the limitation of the installation space of the high-pressure pump system of the LNG receiving station, the venting buffer space 3 is located above the high-pressure pump 1. In the process of constructing the high-pressure pump system of the LNG receiving station, the length of the first venting pipeline 2 is reduced as much as possible, so that the venting buffer space 3 and the liquid level control valve 4 are arranged close to the high-pressure pump 1, so as to solve the problem of large vibration of the venting pipeline caused by the encounter of the two-phase fluid of LNG liquid and BOG gas in the venting pipeline without changing the overall arrangement of the recondenser 5 and the high-pressure pump 1.
[0038] Furthermore, the above-mentioned LNG receiving station high-pressure pump system also includes a second control valve group, which can connect the outlet of the liquid level control valve 4 to one of the BOG system of the LNG receiving station, the exhaust system of the LNG receiving station or the recondenser 5.
[0039] Specifically, the outlet of the liquid level control valve 4 is connected to the second venting pipeline 15, and the second control valve group includes a first isolation valve 10, which can selectively connect or disconnect the outlet of the liquid level control valve 4 with the recondenser 5 through the second venting pipeline 15. Preferably, a reflux port is provided above the packing layer 51 of the recondenser 5, and the second venting pipeline 15 is connected to the reflux port. When the recondenser 5 is in operation, the first isolation valve 10 is in an open state, and the BOG generated during the operation of the high-pressure pump 1 enters the venting buffer space 3. The liquid level height in the venting buffer space 3 is controlled by the liquid level control valve 4, so that only BOG gas enters the liquid level control valve 4 through the first venting pipeline 2, and is discharged from the outlet of the liquid level control valve 4, and then enters the recondenser 5 through the second venting pipeline 15 and the reflux port, and is mixed with the BOG gas entering the recondenser 5 through the BOG main pipe 7, and then mixed with the LNG entering the recondenser 5 through the LNG main pipe 6 to form LNG.
[0040] The second control valve group also includes a second isolation valve 11, which can selectively connect or disconnect the outlet of the liquid level control valve 4 with the BOG system. When the recondenser 5 stops operating, the first isolation valve 10 is closed, and the second isolation valve 11 can be opened, and the BOG generated during the operation of the high-pressure pump 1 enters the venting buffer space 3. The liquid level in the venting buffer space 3 is controlled by the liquid level control valve 4, so that only BOG gas enters the liquid level control valve 4 through the first venting pipeline 2, and is discharged from the outlet of the liquid level control valve 4, and then enters the BOG system through the second venting pipeline 15 and the second isolation valve 11.
[0041] The second control valve group also includes a third isolation valve 12, which can selectively connect or disconnect the outlet of the liquid level control valve 4 with the exhaust system. During the operation of the high-pressure pump 1, the third isolation valve 12 can be opened, and the liquid level in the venting buffer space 3 can be adjusted by the liquid level control valve 4, so that part of the LNG liquid directly enters the liquid level control valve 4 through the first venting pipeline 2, and is discharged from the outlet of the liquid level control valve 4, and then enters the exhaust system through the third isolation valve 12, thereby taking out the heat generated during the operation of the high-pressure pump 1, achieving no BOG generation during the operation of the high-pressure pump 1, and fundamentally ensuring the safety and stability of the operation of the high-pressure pump 1.
[0042] Furthermore, the LNG receiving station high-pressure pump system further includes a reflux pipeline 13, a high-pressure pump outlet manifold 9 and a first control valve group, one end of the reflux pipeline 13 is connected to the discharge port of the high-pressure pump 1, and the other end is connected to the recondenser 5; one end of the high-pressure pump outlet manifold 9 is connected to the discharge port; the first control valve group controls the discharge port to selectively connect to the reflux pipeline 13 or the high-pressure pump outlet manifold 9. During the startup or shutdown process of the high-pressure pump 1, the first control valve group controls the discharge port to connect to the reflux pipeline 13, so that the mixed fluid of LNG and BOG discharged through the discharge port is sent to the recondenser 5 for re-mixing and condensation. At this time, the first isolation valve 10 can be opened to send the BOG gas generated during the operation of the high-pressure pump 1 into the recondenser 5 through the first vent line 2 and the second vent line 15; the second isolation valve 11 can also be opened to send the BOG gas generated during the operation of the high-pressure pump 1 into the BOG system through the first vent line 2 and the second vent line 15; the third isolation valve 12 can also be opened to discharge part of the LNG liquid through the first vent line 2 and the second vent line 15 to take away the heat generated during the operation of the high-pressure pump 1 and avoid the generation of BOG gas.
[0043] The first control valve group may be two switch valves, which are respectively arranged on the return line 13 and the high-pressure pump outlet main pipe 9, or may be a three-way valve.
[0044] Preferably, a flash separation device 52 is provided in the recondenser 5, and the flash separation device 52 is provided above the packing layer 51. The reflux line 13 is connected to the flash separation device 52. The flash separation device 52 is used to perform gas-liquid separation on the LNG liquid and BOG gas entering the recondenser 5 through the reflux line 13. The flash separation device 52 timely separates the two-phase fluid in the reflux process to ensure the stable operation of the recondenser 5. The LNG liquid separated by the flash separation device 52 is mixed with the LNG liquid entering the recondenser 5 through the LNG inlet, and the BOG gas separated by the flash separation device 52 is mixed with the BOG gas entering the recondenser 5 through the BOG inlet.
[0045] Furthermore, the LNG receiving station high-pressure pump system further includes an air supply line 14 having one end connected to the air supply port of the recondenser 5, and an air supply valve provided on the air supply line 14. Preferably, the air supply port is provided above the packing layer 51. When the pressure in the recondenser 5 is low, the air supply valve is opened, and high-pressure natural gas is introduced into the recondenser 5 through the air supply line 14 to maintain the pressure in the recondenser 5 stable. The pressure in the recondenser 5 can be detected by a pressure gauge, and then the air supply valve is opened or closed manually. The pressure in the recondenser 5 can also be detected by a pressure sensor, and when the pressure in the recondenser 5 is low, the air supply valve is opened to supply high-pressure natural gas into the recondenser 5.
[0046] Furthermore, the above-mentioned high-pressure pump 1 is provided in plurality, and the high-pressure pump 1 is provided in one-to-one correspondence with the emptying buffer space 3 and the liquid level control valve 4. In this embodiment, three high-pressure pumps 1 are provided, and correspondingly, three emptying buffer spaces 3 and three liquid level control valves 4 are also provided. Of course, in other embodiments of the present invention, each high-pressure pump 1 can also be connected to the same emptying buffer space 3, and a liquid level control valve 4 can be used to control the liquid level in the corresponding emptying buffer space 3.
[0047] Furthermore, in this embodiment, the packing method for forming the packing layer 51 is preferably random packing.
[0048] The present embodiment also provides a control method for a high-pressure pump system of an LNG receiving station, which is applied to the above-mentioned high-pressure pump system of the LNG receiving station. During the operation of the high-pressure pump 1, the liquid level height in the first venting pipeline 2 is adjusted by the liquid level control valve 4 so that only BOG gas is discharged through the liquid level control valve 4, or part of the LNG liquid is discharged through the first venting pipeline 2 and the liquid level control valve 4 so that the LNG liquid can be used to take away the heat generated by the operation of the high-pressure pump 1.
[0049] When the BOG gas is led out through the first vent line 2 and the second vent line 15, the led out BOG gas has two uses, which are respectively described below with examples.
[0050] The first type is that during the operation of the recondenser 5, the temperature of the LNG in the LNG main pipe 6 is -155°C, the temperature of the BOG in the BOG main pipe 7 is -10°C, and the LNG and BOG enter the recondenser 5 at the same time. The temperature of the mixed LNG is -120°C, and it enters the high-pressure pump 1 through the inlet main pipe of the high-pressure pump 1, is pressurized to 9MPag, and is transported to the next stage for gasification and external transmission. The venting air temperature of each high-pressure pump 1 is -118°C, and the flow rate is about 200kg / h. The BOG gas generated during the operation of the high-pressure pump 1 enters the corresponding venting buffer space 3, and the corresponding liquid level control valve 4 is used to control the liquid level in the venting buffer space 3 to reach 50%, so that only the BOG gas enters the recondenser 5 for re-condensation.
[0051] The second type is that during the operation of the recondenser 5, the temperature of the LNG in the LNG main pipe 6 is -150°C, and the temperature of the BOG in the BOG main pipe 7 is 5°C. The LNG and BOG enter the recondenser 5 at the same time. The temperature of the mixed LNG is -125°C, and it enters the high-pressure pump 1 through the inlet main pipe of the high-pressure pump 1, is pressurized to 7MPag, and is transported to the next stage for gasification and external transmission. The venting air temperature of each high-pressure pump 1 is -120°C, and the flow rate is about 250kg / h. The BOG gas generated during the operation of the high-pressure pump 1 enters the corresponding venting buffer space 3, and the corresponding liquid level control valve 4 is used to control the liquid level in the venting buffer space 3 to 60%, so that only BOG gas enters the BOG system to recycle the BOG generated during the operation of the high-pressure pump 1.
[0052] The following describes in detail the method of adjusting the liquid level control valve 4 to discharge part of the LNG liquid through the first venting pipeline 2 and the liquid level control valve 4 so as to use the LNG liquid to take away the heat generated by the high-pressure pump 1 by operation by taking an example.
[0053] During the operation of the recondenser 5, the temperature of the LNG in the LNG main pipe 6 is -150°C, and the temperature of the BOG in the BOG main pipe 7 is 5°C. The LNG and BOG enter the recondenser 5 at the same time. The temperature of the mixed LNG is -125°C. It enters the high-pressure pump 1 through the inlet main pipe of the high-pressure pump 1, is pressurized to 9MPag, and is transported to the next stage for gasification and external transmission. Each high-pressure pump 1 uses the corresponding liquid level control valve 4 to adjust about 100kg / h of LNG, which directly enters the exhaust system. The heat generated by the operation of the high-pressure pump 1 is taken away by the small amount of LNG discharged into the exhaust system, so that no BOG is generated during the operation of the high-pressure pump 1, which fundamentally guarantees the safety and stability of the operation of the high-pressure pump 1.
[0054] Furthermore, during the startup or shutdown process of the high-pressure pump 1, the LNG pressurized by the high-pressure pump 1 is not transported to the next stage for gasification and external transmission, but is sent to the recondenser 5 through the reflux pipeline 13, and gas-liquid separation is performed through the flash separation device 52 to ensure stable operation of the recondenser 5.
[0055] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
[0056] In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance. Among them, the terms "first position" and "second position" are two different positions.
[0057] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
Claims
1. A high-pressure pump system for an LNG receiving station, comprising a high-pressure pump (1), wherein the high-pressure pump (1) is provided with a vent port, characterized in that: Also includes: a first vent pipeline (2), one end of the first vent pipeline (2) being connected to the vent port; a liquid level control valve (4), wherein the other end of the first venting pipeline (2) is connected to an inlet of the liquid level control valve (4), the height of the inlet of the liquid level control valve (4) is higher than the height of the venting port, and the liquid level control valve (4) is used to adjust the liquid level in the first venting pipeline (2); A venting buffer space (3), the venting buffer space (3) being arranged on the first venting pipeline (2), the bottom of the venting buffer space (3) being provided with a first communication port communicating with the venting port, and the top of the venting buffer space (3) being provided with a second communication port communicating with an inlet of the liquid level control valve (4); a recondenser (5), the recondenser (5) being used for mixing LNG liquid and BOG gas to condense the BOG gas to form LNG liquid, the liquid outlet of the recondenser (5) being in communication with the liquid inlet of the high-pressure pump (1); a return line (13), one end of the return line (13) being in communication with a discharge port of the high-pressure pump (1); a flash separation device (52), wherein the other end of the reflux pipeline (13) is connected to the recondenser (5) through the flash separation device (52), and the flash separation device (52) is used to perform gas-liquid separation on the LNG liquid and BOG gas entering the recondenser (5) through the reflux pipeline (13); a high-pressure pump outlet manifold (9), one end of the high-pressure pump outlet manifold (9) being in communication with a liquid discharge port of the high-pressure pump (1); a first control valve group, the first control valve group controlling the discharge port of the high-pressure pump (1) to selectively communicate with the return line (13) or the high-pressure pump outlet manifold (9); A second control valve group, wherein the second control valve group is capable of selectively connecting the outlet of the liquid level control valve (4) to one of the BOG system of the LNG receiving station, the exhaust system of the LNG receiving station or the recondenser (5).
2. The LNG receiving station high-pressure pump system according to claim 1, characterized in that: The flash separation device (52) is located above the packing layer (51) of the recondenser (5).
3. The LNG receiving station high-pressure pump system according to claim 1 or 2, characterized in that: An LNG inlet and a BOG inlet are provided above the packing layer (51) of the recondenser (5), and the LNG inlet and the BOG inlet are provided with an LNG main pipe (6) and a BOG main pipe (7), respectively.
4. The LNG receiving station high-pressure pump system according to claim 1 or 2, characterized in that: Also includes: An air supply pipeline (14), wherein an air supply port is provided above the packing layer (51) of the recondenser (5), and one end of the air supply pipeline (14) is in communication with the air supply port; An air supply valve is arranged on the air supply pipeline (14).
Citation Information
Patent Citations
Recovery system for gas emptied by high-pressure output pump in LNG (Liquefied Natural Gas) receiving terminal
CN202082615U
LNGL - CNG car BOG recovery unit of gas station
CN208671484U
High-pressure pump system of LNG receiving station
CN210266718U