A pre-embedded casting system for the inner corner of a volute and a casting method for the volute

By using a pre-embedded pouring system in hydropower projects, combined with the arrangement of circumferential and radial pump pipes, and using diagonal quadrant simultaneous pouring and mortar filling, the problems of low construction efficiency and poor quality in the volute layer concrete pouring are solved. Efficient and dense pouring of the volute is achieved.

CN110318398BActive Publication Date: 2024-10-29SINOHYDRO BUREAU 6 CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN201910708363.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-08-01
Publication Date
2024-10-29
Estimated Expiration
2039-08-01

AI Technical Summary

Technical Problem

In hydropower projects, when the volute layer is poured with concrete, because there are many pump pipes embedded in advance, it is difficult for workers to construct in a narrow space, which takes a long time, low work efficiency, high labor intensity, and the pump pipes are easily blocked by concrete, which affects the construction quality.

Method used

Provide a pre-embedded pouring system, including concrete pump pipes and mortar pump pipes. Through the combined arrangement of circumferential and radial pump pipes, the method of simultaneous pouring in diagonal quadrants is used. The inside and outside are poured at the same time. The mortar fills the pores and uses reserved The grouting holes are vibrated and supplemented with materials to ensure dense pouring of the volute.

Benefits of technology

The construction efficiency of the concrete pouring of the volute layer is improved, the labor intensity is reduced, the construction quality is ensured, especially the compactness at the inner corners of the volute and the bin surface, and the capital investment and construction difficulty are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110318398B_ABST
    Figure CN110318398B_ABST
Patent Text Reader

Abstract

The invention discloses a pre-embedded casting system for a volute inner corner and a casting method for the volute. The casting method adopts a pre-embedded casting system with a novel structure. During casting, a diagonal quadrant is cast simultaneously to ensure the stability of the volute to be cast. During casting in each quadrant, inner and outer castings are cast simultaneously to achieve dense casting. After concrete casting is completed, mortar is poured by a mortar pump pipe to fill the pores during the previous concrete casting, especially to make up for the pore areas on the volute bin surface and the volute inner corner that are difficult to cast, so as to achieve dense casting of the volute. The casting method can effectively reduce capital investment and construction difficulty while ensuring quality, thereby ensuring the dense concrete effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention discloses a technical field of concrete construction of hydropower engineering, and in particular to a pre-embedded casting system for a volute inner corner and a casting method of the volute. Background Art

[0002] In hydropower projects, underground powerhouses are where volutes, turbines, generators and other equipment are arranged. Underground powerhouses in hydropower projects usually have complex structures. When pouring concrete in the volute layer of the underground powerhouse in hydropower projects, it is difficult to pour concrete because of the dense steel bars on the outside of the volute.

[0003] In order to ensure the quality of concrete pouring, at present, the four-quadrant pouring method is usually used for pouring concrete in the volute layer of the underground powerhouse of the hydropower project. At the same time, each quadrant concrete is divided into the first pouring block and the later pouring block (the inner corner part). Four radial pump pipes with one low and three high are pre-buried in the first pouring block, totaling 16. When pouring concrete, first use the low-position pump pipe to pour concrete in the order of I→Ⅱ→Ⅲ→Ⅳ, and finally use the high-position pump pipe to pour concrete in the volute seat ring part (the inner corner). During the pouring process, the reserved holes set on the volute seat ring are fully utilized for vibration (and grouting). The concrete is stored in the warehouse using first-grade, high-flow, self-compacting concrete.

[0004] Although the above method can complete the pouring of the volute layer concrete, due to the large number of pre-buried pump pipes, it is difficult for workers to construct in a narrow space, which is time-consuming and has low work efficiency. In addition, workers need to frequently switch between low-position and high-position pump pipes, which is labor-intensive and causes fatigue. Some pump pipes have been blocked by concrete before they are poured, resulting in the inability to utilize the pre-buried pump pipes and affecting the construction quality.

[0005] Therefore, how to develop a concrete pouring system or pouring method for the inner corner of the volute has become a problem that people are trying to solve. Summary of the invention

[0006] In view of this, the present invention discloses a pre-embedded casting system for the inner corner of a volute and a casting method for the volute, so as to at least solve the problems of low working efficiency and poor construction quality existing in the existing casting method for the volute.

[0007] In one aspect, the present invention provides a pre-embedded casting system for a volute inner corner, the pre-embedded casting system comprising: a concrete pump pipe and a plurality of mortar pump pipes;

[0008] The concrete pump pipe is fixedly connected to the adjacent foundation dowel bars in the volute installation platform to be cast, and the concrete pump pipe includes: an annular pump pipe and twelve radial pump pipes;

[0009] The annular pump pipe is sleeved on the outside of the volute to be cast;

[0010] The twelve radial pump pipes are all located between the annular pump pipe and the volute to be cast, and are arranged at intervals along the circumference of the annular pump pipe. A coordinate system is established with the center of the volute to be cast as the origin, and the volute to be cast is divided into four quadrant areas. Three radial pump pipes are distributed in each quadrant area. The three radial pump pipes are all arranged along the radial direction of the volute to be cast, and the feed end of each radial pump pipe is connected and communicated with the annular pump pipe, wherein the axial height of the radial pump pipes on both sides of each quadrant area along the volute to be cast is higher than the axial height of the radial pump pipe in the middle along the volute to be cast;

[0011] The multiple mortar pump pipes are located between the volute to be cast and the radial pump pipes, and are respectively arranged at intervals along the circumference of the volute to be cast. The discharge port of each mortar pump pipe is close to the bottom of the base ring in the volute to be cast, and the axial height of each mortar pump pipe along the volute to be cast is higher than the axial height of any radial pump pipe along the volute to be cast.

[0012] Preferably, the number of the mortar pump pipes is 8, and 2 mortar pump pipes are distributed in each quadrant area.

[0013] Further preferably, the horizontal distance between the discharge port of each radial pump pipe in the concrete pump pipe and the volute to be cast is greater than or equal to 50 cm.

[0014] Further preferably, the horizontal distance between the discharge port of each mortar pump pipe and the volute to be cast is greater than or equal to 20 cm.

[0015] Another aspect of the present invention further provides a method for casting a volute, the method comprising the following steps:

[0016] 1) Pre-buried pump pipe:

[0017] According to the above-mentioned pre-embedded casting system, the concrete pump pipe and the mortar pump pipe are pre-embedded, and the concrete pump pipe and the mortar pump pipe are fixedly connected to the adjacent foundation dowel bars in the installation platform of the volute to be cast, respectively. The four quadrants divided by the coordinate system are established with the center of the volute to be cast as the origin, and are marked as quadrant I, quadrant II, quadrant III and quadrant IV in a clockwise direction;

[0018] 2) Pour the blocks into the warehouse first:

[0019] With the first quadrant and the third quadrant as the first pouring block, the backfill pouring of the first quadrant and the third quadrant is first carried out. When the backfill pouring of the first quadrant and the third quadrant is carried out, the radial pump pipe in the corresponding quadrant is opened to pour the material inside, and the concrete placing machine is used to pour the material outside, and the concrete is poured from both sides at the same time. After the concrete pouring is completed, the mortar pump pipe in the corresponding quadrant is opened to pour the mortar backfill;

[0020] 3) Post-casting blocks into warehouse:

[0021] After the pouring of quadrants I and III is completed, backfill pouring of quadrants II and IV will be carried out. When backfilling and pouring of quadrants II and IV, open the radial pump pipe in the corresponding quadrant to carry out inner material pouring while using the concrete placing machine to carry out outer material pouring. Concrete is poured from both inside and outside at the same time. After the concrete pouring is completed, open the mortar pump pipe in the corresponding quadrant to carry out mortar backfill pouring.

[0022] Preferably, in step 2) the first blocks are poured into the bin and in step 3) the last blocks are poured into the bin, the radial pump pipe in the corresponding quadrant is opened to pour the material inside, and a concrete placing machine is used to pour the material outside. The specific process of pouring concrete from both inside and outside at the same time is as follows:

[0023] Open the radial pump pipe in the middle of the corresponding quadrant to pour the material on the inside, and use the concrete placing machine to pour the material on the outside. When pouring approaches the bottom of the volute, the pouring speed of the radial pump pipe and the concrete placing machine must be controlled. The pouring height of the inner side of the radial pump pipe must be higher than the pouring height of the outer side of the concrete placing machine to form a height difference. When the inner side pouring cannot be vibrated, the construction workers withdraw from the head on the side with the smaller radius of the volute.

[0024] The radial pump pipes on both sides of the corresponding quadrant are activated one by one from the large radius to the small radius of the volute, and the self-compacting concrete is pumped to the inner corner of the volute through the radial pump pipes to complete the pouring of the self-compacting concrete;

[0025] During the above pouring process, the reserved grouting holes on the volute foundation ring are used for vibration and at the same time, additional material is added through the reserved grouting holes. When the concrete is poured to the top surface of the volute foundation ring and the holes on the volute foundation ring begin to ooze grout, wooden plugs are used to plug the holes to complete the concrete pouring.

[0026] Further preferably, the height difference formed by the inner side of the radial pump pipe and the outer side of the concrete placing machine is less than or equal to 20 cm.

[0027] Further preferably, in step 2) the first blocks are poured into the bin and in step 3) the last blocks are poured into the bin, the specific process of opening the mortar pump pipe in the corresponding quadrant to perform mortar filling and pouring is as follows:

[0028] When opening the mortar pump pipe in the corresponding quadrant for mortar backfilling and pouring, observe the pouring situation from the exhaust holes on the volute seat ring, and clear the exhaust holes in real time. After mortar emerges from the concave corner of the volute, the mortar backfilling and pouring is completed.

[0029] The casting method of the volute provided by the present invention adopts a pre-embedded casting system of a novel structure. During casting, a diagonal quadrant is cast simultaneously to ensure the stability of the volute to be cast. During casting in each quadrant, inner and outer castings are cast simultaneously to achieve dense casting. After the concrete casting is completed, a mortar pump pipe is used to fill the pores during the previous concrete casting, especially the pores on the volute bin surface and the inner corner of the volute that are difficult to cast, so as to achieve dense casting of the volute.

[0030] The casting method of the volute provided by the present invention can effectively reduce capital investment and construction difficulty while ensuring quality, thereby ensuring the compacting effect of concrete.

[0031] It is to be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the invention and, together with the description, serve to explain the principles of the invention.

[0033] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0034] Figure 1 A schematic structural diagram of a pre-embedded casting system for a volute inner corner provided in accordance with an embodiment of the present invention. DETAILED DESCRIPTION

[0035] Exemplary embodiments will be described in detail herein, examples of which are shown in the accompanying drawings. When the following description refers to the drawings, the same numbers in different drawings represent the same or similar elements unless otherwise indicated. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with the present invention. Instead, they are merely examples of devices and methods consistent with some aspects of the present invention as detailed in the appended claims.

[0036] The construction of the volute casting has always been a difficult part of the construction in hydropower projects. How to improve the compactness of the volute casting has always been a technical problem that has troubled people in this field. Although the existing technology has adopted the form of four-quadrant casting, there are still problems such as low work efficiency and poor construction quality. In view of the above problems, this embodiment provides a new type of pre-embedded casting system for the inner corner of the volute, see Figure 1 The pre-embedded casting system is mainly composed of a concrete pump pipe 1 and a plurality of mortar pump pipes 2, wherein the concrete pump pipe 1 is fixedly connected to the adjacent foundation dowel bars in the installation platform of the volute to be cast, and the concrete pump pipe 1 is composed of an annular pump pipe 11 and twelve radial pump pipes 12, wherein the annular pump pipe 11 is sleeved on the outside of the volute A to be cast, and the twelve radial pump pipes 12 are all located between the annular pump pipe 11 and the volute A to be cast, and are arranged at intervals along the circumference of the annular pump pipe 11, and a coordinate system is established with the center of the volute A to be cast as the origin, and the volute A to be cast is divided into four quadrants, and three radial pump pipes 12 are distributed in each quadrant, and the three radial pump pipes 12 are arranged along the radial direction of the volute A to be cast, and the feed end of each radial pump pipe 12 is connected to the annular pump The tubes 11 are connected and communicated, wherein the axial heights of the radial pump tubes 12 on both sides in each quadrant area along the volute A to be cast are higher than the axial heights of the radial pump tubes 12 in the middle along the volute A to be cast, that is, two high-position radial pump tubes and one low-position radial pump tube are respectively arranged in each quadrant, and the above-mentioned multiple mortar pump tubes 2 are all located between the volute A to be cast and the radial pump tubes 12, that is, the mortar pump tubes 2 are closer to the volute A to be cast than the radial pump tubes 12, and the above-mentioned multiple mortar pump tubes 2 are respectively arranged at circumferential intervals along the volute A to be cast, and the discharge port of each mortar pump tube 2 is close to the bottom of the base ring in the volute A to be cast, and the axial height of each mortar pump tube 2 along the volute A to be cast is higher than the axial height of any radial pump tube 12 along the volute A to be cast.

[0037] The embedded casting system in the above-mentioned implementation scheme is mainly composed of two parts: a concrete pump pipe and a mortar pump pipe. Among them, the mortar pump pipe is closer to the side of the volute to be cast than the concrete pump pipe. When the embedded casting system is used to cast the volute, since the radial pump pipe and the mortar pump pipe in the embedded casting system are distributed according to quadrants, the casting is also carried out in the form of four quadrants. The casting sequence is to first select a diagonal quadrant as the first casting block, and then the other diagonal quadrant as the later casting block. The specific casting process of each quadrant is: first use a radial pump pipe to cast concrete, and after the concrete pouring is completed, use a mortar pump pipe for supplementary casting to fill the gaps in the early concrete pouring, especially to make up for the gaps in the volute bin surface and the volute inner corners that are difficult to cast, so as to achieve dense casting of the volute.

[0038] In order to ensure the construction speed and construction quality of the volute casting, the number of mortar pump pipes 2 required in the pre-buried casting system is reduced, preferably, see Figure 1 In the embedded casting system, 8 mortar pump pipes 2 are arranged, and 2 mortar pump pipes 2 are distributed in each quadrant area for supplementary filling and casting of mortar.

[0039] In order to ensure the pouring quality, the horizontal distance between the discharge port of each radial pump pipe 12 in the concrete pump pipe 1 in the above-mentioned pre-buried pouring system and the volute A to be poured is greater than or equal to 50 cm, and the horizontal distance between the discharge port of each mortar pump pipe 2 and the volute A to be poured is greater than or equal to 20 cm.

[0040] This embodiment provides a method for casting a volute using the above-mentioned pre-embedded casting system. The specific casting process is as follows:

[0041] 1) Pre-buried pump pipe:

[0042] According to the above-mentioned pre-embedded casting system, the concrete pump pipe and the mortar pump pipe are pre-embedded, and the concrete pump pipe and the mortar pump pipe are fixedly connected to the adjacent foundation dowel bars in the installation platform of the volute to be cast, respectively. The four quadrants divided by the coordinate system are established with the center of the volute to be cast as the origin, and are marked as quadrant I, quadrant II, quadrant III and quadrant IV in a clockwise direction;

[0043] 2) Pour the blocks into the warehouse first:

[0044] With the first quadrant and the third quadrant as the first pouring block, the backfill pouring of the first quadrant and the third quadrant is first carried out. When the backfill pouring of the first quadrant and the third quadrant is carried out, the radial pump pipe in the corresponding quadrant is opened to pour the material inside, and the concrete placing machine is used to pour the material outside, and the concrete is poured from both sides at the same time. After the concrete pouring is completed, the mortar pump pipe in the corresponding quadrant is opened to pour the mortar backfill;

[0045] 3) Post-casting blocks into warehouse:

[0046] After the pouring of quadrants I and III is completed, backfill pouring of quadrants II and IV will be carried out. When backfilling and pouring of quadrants II and IV, open the radial pump pipe in the corresponding quadrant to carry out inner material pouring while using the concrete placing machine to carry out outer material pouring. Concrete is poured from both inside and outside at the same time. After the concrete pouring is completed, open the mortar pump pipe in the corresponding quadrant to carry out mortar backfill pouring.

[0047] The specific process of pouring concrete from both inside and outside at the same time by opening the radial pump pipe in the corresponding quadrant in the above step 2) of pouring the first block into the bin and step 3) of pouring the last block into the bin for inner pouring and using the concrete placing machine for outer pouring is as follows:

[0048] Open the radial pump pipe in the middle of the corresponding quadrant to pour the material on the inside, and use the concrete placing machine to pour the material on the outside. When pouring approaches the bottom of the volute, the pouring speed of the radial pump pipe and the concrete placing machine must be controlled. The pouring height of the inner side of the radial pump pipe must be higher than the pouring height of the outer side of the concrete placing machine to form a height difference. When the inner side pouring cannot be vibrated, the construction workers withdraw from the head on the side with the smaller radius of the volute.

[0049] The radial pump pipes on both sides of the corresponding quadrant are activated one by one from the large radius to the small radius of the volute, and the self-compacting concrete is pumped to the inner corner of the volute through the radial pump pipes to complete the pouring of the self-compacting concrete;

[0050] During the above pouring process, the reserved grouting holes on the volute foundation ring are used for vibration and at the same time, additional material is added through the reserved grouting holes. When the concrete is poured to the top surface of the volute foundation ring and the holes on the volute foundation ring begin to ooze grout, wooden plugs are used to plug the holes to complete the concrete pouring.

[0051] Preferably, the height difference formed by the inner side of the radial pump pipe and the outer side of the concrete placing machine is less than or equal to 20 cm.

[0052] The specific process of the above step 2) pouring the first block into the warehouse and step 3) pouring the second block into the warehouse and opening the mortar pump pipe in the corresponding quadrant to perform mortar filling and pouring is as follows:

[0053] When opening the mortar pump pipe in the corresponding quadrant for mortar backfilling and pouring, observe the pouring situation from the exhaust holes on the volute seat ring, and clear the exhaust holes in real time. After mortar emerges from the concave corner of the volute, the mortar backfilling and pouring is completed.

[0054] The inner side and the outer side described in the above embodiments do not refer to the inside and the outside of the volute, but are relative to the outside of the volute. The side close to the volute is called the inner side, and the side far from the volute is called the outer side. Specific embodiments

[0056] The present invention is further explained below in conjunction with specific embodiments, but is not intended to limit the protection scope of the present invention.

[0057] Take the pouring of volute concrete of the unit section of the main powerhouse of the right bank underground power station of Wudongde Hydropower Station as an example.

[0058] The volute installation platform to the section with an elevation of 823.17m is divided into structural concrete including volute layer, turbine entrance gallery layer, turbine layer, busbar outlet layer and generator layer. The unit installation elevation is 803.00m, the volute installation elevation is 797.90m~808.10m, the volute entrance gallery bottom plate elevation is EL802.10m, the turbine entrance gallery bottom plate elevation is EL807.00m, the turbine layer casting top elevation is EL811.32m, the lower frame foundation installation elevation is 813.09, the stator foundation installation elevation is 815.60, the busbar outlet layer floor top elevation is EL816.35m and is flush with the busbar hole bottom plate, the generator layer (including wind shield wall) floor top elevation is EL823.17m, which is flush with the installation room bottom plate. The volute is made of SX780CF high-strength steel plate, with elastic cushions above the waistline. There are three layers of steel mesh around VE5~V8 sections, and double layers of steel mesh around V9~V24 sections. The main circumferential reinforcement is The downstream distribution reinforcement is The layer height of the volute concrete is 1.8m to 4.0m. The main construction projects include steel bar installation, embedded parts installation, elastic cushion laying, volute concrete pouring, contact grouting, etc.

[0059] 1. Construction focus and difficulties

[0060] The volute concrete is on a critical line, with a tight construction period and great construction difficulty. It is also affected by factors such as structural form and cross-operation. Therefore, it is key to organize the construction reasonably, strengthen management, increase resource input, and ensure the construction progress.

[0061] It is difficult to enter and vibrate the inner corner of the volute. The seat ring and the inner corner of the volute are complex in shape, narrow in space, and densely reinforced, making it difficult to enter and vibrate concrete. Pre-buried concrete pump pipes are used at the bottom of the volute to partially raise the closing elevation to ensure that the concrete at the inner corner and the first layer of concrete are cast in one go. Fullness and density are the difficulties in construction and are also the key to the pouring of volute concrete.

[0062] 2. Specific construction process

[0063] (1) Pump pipe embedded in the bottom of the volute

[0064] The inner corner of the bottom of the volute (including the seat ring and the bottom of the foundation ring) is mainly backfilled by pre-buried pump pipes, and the reserved Φ125mm grouting holes on the foundation ring are used as auxiliary material feeding. The four quadrants divided by the coordinate system are established with the center of the volute to be cast as the origin. They are marked as quadrants I, II, III and IV in a clockwise direction. The annular pump pipe set is attached to the outside of the volute. Three Φ150mm radial pump pipes and two Φ40 mortar pump pipes are pre-buried in each quadrant. The feed end of each radial pump pipe is aligned with the annular The pump pipe is connected and communicated with each other. The discharge port of the radial pump pipe in each quadrant is arranged according to the staggered arrangement of high and low pipes. Two high pipes and one low pipe are pre-buried in each quadrant, of which the two high pipes are located on both sides of the quadrant and one low pipe is located in the middle of the quadrant. The minimum distance between the discharge port of the radial pump pipe and the bottom of the seat ring and the foundation ring is controlled to be ≥50cm, and the minimum distance between the discharge port of the mortar pump pipe and the bottom of the seat ring is controlled to be ≥20cm. The radial pump pipe and the mortar pump pipe are fixed to the foundation dowel bars of the volute installation platform (they shall not be connected to the volute steel bars and metal embedded parts).

[0065] (2) Pour the blocks into the warehouse first

[0066] Quadrants I and III are cast first, first cast quadrant I, then cast quadrant III, or both quadrants are cast at the same time. In this embodiment, first cast quadrant I, then cast quadrant III. Concrete is mainly delivered to the warehouse by a concrete placing crane, supplemented by concrete pumps. A small bridge crane is hung with a height of 6.0m. 3 Horizontal tank emergency, (after the concrete placing machine equipment fails, if it still cannot be restored after 3.0 hours, a small bridge crane with a height of 6m 3 Tanks are used as emergency storage means). The slump of concrete entering the warehouse by the concrete placing machine and horizontal tank is 120-140mm, the slump of pumped concrete is 160-180mm, and the diffusion of pumped self-compacting concrete is 600-700mm. The concrete pump is mainly used for pouring concrete in the concrete pump pipe inside the volute, and the shuttle concrete placing machine is used for pouring concrete outside the volute. Before opening the warehouse, one concrete pump is arranged in quadrants I and III respectively. When pouring quadrant I, quadrant III will not be poured temporarily, and the concrete pump will be used as a standby for quadrant I. When pouring quadrant III, the concrete pump in quadrant I will not be withdrawn and will be kept as a standby for quadrant III. The concrete at the bottom corner of the volute (including the seat ring and foundation ring) cannot be poured densely. High-grade (M35) cement mortar (consistency 100-120mm) is used for backfilling using a mortar pump pipe. The mortar pump pipe is pre-buried in advance, and the minimum distance between the discharge port and the bottom of the seat ring is ≥20cm. The grouting pressure is controlled to be ≤0.2Mpa.

[0067] The inside (low pipe) and outside of the volute are poured at the same time, and the warehouse surface is poured from the side with larger radius of the volute, and the squeezing method of high inside and low outside is adopted. The vibrators are vibrating on both the inside and outside at the same time. The inside of the volute is discharged with a concrete pump, and the outside is discharged with a concrete placing machine. When pouring close to the bottom of the volute, it is necessary to effectively control the discharge to ensure that the inside is high and the outside is low, forming a certain height difference. The concrete's own fluidity and vibration drag material are used to squeeze the inner concrete into the bottom and outside of the volute to ensure that the bottom of the volute is dense. When the inside is poured to the point where it cannot be vibrated, the construction workers finally withdraw from the side with a small radius of the volute. Start pouring self-compacting concrete. The self-compacting concrete is pumped to the concave corner through the radial pre-buried high pump pipe. The radial high pump pipes are activated one by one from the large radius of the volute to the small radius, and the annular main pump pipes arranged on the outside of the volute are dismantled one by one. During the pouring process, the reserved on the foundation ring is used Reserve grouting holes for vibration and use Reserve grouting holes for additional material feeding. When the concrete is poured to the top surface of the foundation ring and the holes on the foundation ring plate begin to ooze out grout, plug the holes with wooden plugs, start the grouting machine to backfill with M30 cement mortar, observe the concrete pouring situation at the exhaust holes on the ring plate of the seat ring, arrange for special personnel to clear the exhaust holes with wire, and wait until the grout starts to ooze out from the concave corners (close the inner side of the volute).

[0068] Note: ①In the pouring process, install pressure gauges on the concrete pump pipe and grouting pipe, and control the pumping pressure and grouting pressure to no more than 0.2MPa to ensure that the lifting deformation value during pumping is controlled within the allowable range of the unit manufacturer; ②Focus on monitoring the pouring on the inside of the volute, but at the same time, the pouring on the outside of the volute must also meet the pouring requirements, and the warehouse must be leveled in an orderly manner, the material must be unloaded reasonably, and the joints must be covered in time; ③The vertical rising speed of the concrete inside and outside the volute is required to be no more than 0.3m / h, and the plane height difference must not exceed 20cm.

[0069] (3) Post-casting blocks into the warehouse

[0070] The latter concrete blocks are the second and fourth quadrants. Similarly, the second quadrant can be poured first, and then the fourth quadrant can be poured, or the two quadrants can be poured at the same time. In this embodiment, the second quadrant is poured first, and then the fourth quadrant is poured. The concrete is mainly delivered into the warehouse by a placing crane, supplemented by a concrete pump. The small bridge crane is hung with a 6.0m 3 In case of emergency with horizontal tank, concrete pump is mainly used for pouring concrete inside the volute, and shuttle type concrete placing machine is used for pouring concrete outside the volute. Concrete is poured from the side with larger radius of the volute, and the method of high inside and low outside is adopted. Before pouring to the bottom of the volute, the construction workers withdraw from the bottom of the volute on the side with smaller radius of the volute, and start pouring self-compacting concrete and mortar filling. The pouring method is basically the same as that of the first pouring block. The construction order of the first pouring block and the second pouring block can be adjusted according to the actual construction progress on site to ensure the close connection of each process.

[0071] The volute cast in the above manner has been quality inspected and the concrete has been cast evenly and densely, meeting the quality requirements.

[0072] Those skilled in the art will readily appreciate other embodiments of the present invention after considering the specification and practicing the invention disclosed herein. This application is intended to cover any variations, uses or adaptations of the present invention that follow the general principles of the present invention and include common knowledge or customary techniques in the art that are not disclosed by the present invention. The specification and examples are to be considered exemplary only, and the true scope and spirit of the present invention are indicated by the following claims.

[0073] It should be understood that the present invention is not limited to the exact construction that has been described above and shown in the drawings and that various modifications and changes may be made without departing from the scope thereof. The scope of the present invention is limited only by the appended claims.

Claims

1. A method for casting a volute, It is characterized in that include: A pre-buried casting system, the pre-buried casting system comprising: a concrete pump pipe (1) and a plurality of mortar pump pipes (2); The concrete pump pipe (1) is fixedly connected to the adjacent foundation dowels in the installation platform of the volute to be cast, and the concrete pump pipe (1) comprises: an annular pump pipe (11) and twelve radial pump pipes (12); the annular pump pipe (11) is sleeved on the outside of the volute (A) to be cast; The twelve radial pump pipes (12) are all located between the annular pump pipe (11) and the volute (A) to be cast, and are arranged at intervals along the circumference of the annular pump pipe (11). A coordinate system is established with the center of the volute (A) to be cast as the origin, and the volute (A) to be cast is divided into four quadrants. Three radial pump pipes (12) are distributed in each quadrant. The three radial pump pipes (12) are arranged along the radial direction of the volute (A) to be cast, and the feed end of each radial pump pipe (12) is connected to and communicates with the annular pump pipe (11), wherein: The axial height of the radial pump pipes (12) located on both sides of each quadrant region along the axial direction of the volute (A) to be cast is higher than the axial height of the radial pump pipe (12) located in the middle along the axial direction of the volute (A) to be cast; The plurality of mortar pump pipes (2) are all located between the volute (A) to be cast and the radial pump pipe (12), and are respectively arranged at intervals along the circumference of the volute (A) to be cast, the discharge port of each mortar pump pipe (2) is close to the bottom of the base ring in the volute (A) to be cast, and the axial height of each mortar pump pipe (2) along the volute (A) to be cast is higher than the axial height of any radial pump pipe (12) along the volute (A) to be cast; The casting method of the volute comprises: 1) Pre-buried pump pipe: Pre-embed the concrete pump pipe and mortar pump pipe according to the pre-embedded casting system, and fix the concrete pump pipe and mortar pump pipe to the adjacent foundation dowel bars in the installation platform of the volute to be cast, respectively. The four quadrants divided by the coordinate system are established with the center of the volute to be cast as the origin, and are marked as quadrant I, quadrant II, quadrant III and quadrant IV in a clockwise direction; 2) Pour the blocks into the warehouse first: With the first quadrant and the third quadrant as the first pouring block, the backfill pouring of the first quadrant and the third quadrant is first carried out. When the backfill pouring of the first quadrant and the third quadrant is carried out, the radial pump pipe in the corresponding quadrant is opened to pour the material inside, and the concrete placing machine is used to pour the material outside, and the concrete is poured from both sides at the same time. After the concrete pouring is completed, the mortar pump pipe in the corresponding quadrant is opened to pour the mortar backfill; 3) Post-casting blocks into the warehouse: After the pouring of quadrants I and III is completed, backfill pouring of quadrants II and IV is carried out. When backfilling and pouring of quadrants II and IV is carried out, the radial pump pipe in the corresponding quadrant is opened to pour the material from the inside, and the concrete placing machine is used to pour the material from the outside, and concrete is poured from both sides at the same time. After the concrete pouring is completed, the mortar pump pipe in the corresponding quadrant is opened to pour the mortar backfill; In step 2) the first block is poured into the bin and in step 3) the last block is poured into the bin, the radial pump pipe in the corresponding quadrant is opened to pour the material from the inside while the concrete placing machine is used to pour the material from the outside. The specific process of pouring concrete from both the inside and the outside at the same time is as follows: Open the radial pump pipe in the middle of the corresponding quadrant to pour the material on the inside, and use the concrete placing machine to pour the material on the outside. When pouring approaches the bottom of the volute, the pouring speed of the radial pump pipe and the concrete placing machine must be controlled. The pouring height of the inner side of the radial pump pipe must be higher than the pouring height of the outer side of the concrete placing machine to form a height difference. When the inner side pouring cannot be vibrated, the construction workers withdraw from the head on the side with the smaller radius of the volute. The radial pump pipes on both sides of the corresponding quadrant are activated one by one from the large radius to the small radius of the volute, and the self-compacting concrete is pumped to the inner corner of the volute through the radial pump pipes to complete the pouring of the self-compacting concrete; During the above pouring process, the reserved grouting holes on the volute foundation ring are used for vibration and at the same time, additional material is added through the reserved grouting holes. When the concrete is poured to the top surface of the volute foundation ring and the holes on the volute foundation ring begin to ooze grout, wooden plugs are used to plug the holes to complete the concrete pouring.

2. The casting method of the volute according to claim 1, It is characterized in that The number of the mortar pump pipes (2) is 8, and two mortar pump pipes (2) are distributed in each quadrant area.

3. The casting method of the volute according to claim 1, It is characterized in that The horizontal distance between the discharge port of each radial pump pipe (12) in the concrete pump pipe (1) and the volute (A) to be cast is greater than or equal to 50 cm.

4. The casting method of the volute according to claim 1, It is characterized in that The horizontal distance between the discharge port of each mortar pump pipe (2) and the volute (A) to be cast is greater than or equal to 20 cm.

5. The casting method of the volute according to claim 1, It is characterized in that The height difference formed by the inner side of the radial pump pipe and the outer side of the concrete placing machine is less than or equal to 20 cm.

6. The casting method of the volute according to claim 1, It is characterized in that The specific process of opening the mortar pump pipe in the corresponding quadrant to perform mortar filling and pouring in step 2) first pouring the blocks into the bin and step 3) second pouring the blocks into the bin is as follows: When opening the mortar pump pipe in the corresponding quadrant for mortar backfilling and pouring, observe the pouring situation from the exhaust holes on the volute seat ring, and clear the exhaust holes in real time. After mortar emerges from the concave corner of the volute, the mortar backfilling and pouring is completed.