A GBF honeycomb core board construction auxiliary device and construction method
By using grid cloth and anti-floating shoulder pole device in the construction of GBF honeycomb core board, the slurry problem caused by the inconvenient fit between the prefabricated board and the template is solved, the construction quality and efficiency are improved, and the flatness of the bottom of the board is ensured.
Patent Information
- Application Number
- CN201911233995.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-12-05
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2039-12-05
AI Technical Summary
In the construction of GBF honeycomb core boards, the bottom of the prefabricated plate cannot be fully fitted with the formwork, resulting in serious slurry discharge after concrete pouring, affecting the quality of the project, and the installation of prefabricated plates requires high accuracy and time-consuming and labor-consuming.
The construction auxiliary device including templates, anti-floating shoulder pole devices, honeycomb core prefabricated plates and grid cloth is adopted. By laying grid cloth on the template and using anti-floating shoulder pole devices, the sealing between the honeycomb core prefabricated plates and the template is ensured. And use anti-floating pole devices during concrete pouring to prevent upward and displacement.
It effectively prevents concrete slurry, ensures flat bottoms, improves construction quality and efficiency, and reduces the complexity of post-processing.
Smart Images

Figure CN110984452B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction of concrete GBF honeycomb core panels in building engineering, and in particular to a GBF honeycomb core panel construction auxiliary device and a construction method. Background Art
[0002] As my country's industrial and civil buildings are developing towards large-scale and modernization, the span and bay of buildings are gradually increasing, and the requirements for structural strength and seismic performance of buildings are getting higher and higher. Traditional concrete floors need to increase the thickness of the slab to adapt to the structural requirements, resulting in an increase in the cross-section of the beam, a significant increase in the investment in steel bars and concrete, and an increase in cost and construction period. The use of GBF honeycomb core cast-in-place concrete can well solve the problem of large spans of buildings, reduce deadweight, improve seismic performance, and have good thermal insulation and sound insulation effects. This technology uses a series of honeycomb core products to cast into internal space load-bearing units in cast-in-place concrete slabs, forming a horizontal structural system of cast-in-place concrete bidirectional grid ribs with clear force transmission, thereby playing a role in bearing loads.
[0003] At present, the honeycomb core board is usually constructed by laying the formwork flat and placing the precast concrete board close to the formwork. This construction method has the following main problems: 1) Because the bottom of the precast board cannot fit the formwork completely, slurry leakage is very likely to occur after concrete pouring, and the joint between the bottom of the precast board and the rib beam is uneven, which makes post-processing troublesome and the project quality difficult to guarantee; 2) In order to avoid slurry leakage at the bottom of the board, the installation of the precast board requires high precision and high surface quality of the precast board, and the installation is time-consuming and labor-intensive. Summary of the invention
[0004] The object of the present invention is to provide a GBF honeycomb core board construction auxiliary device and construction method to solve the above-mentioned defects caused by the prior art.
[0005] A GBF honeycomb core board construction auxiliary device comprises: a template, an anti-floating shoulder pole device, a honeycomb core prefabricated board, and a mesh cloth; the mesh cloth is laid between the upper surface of the template and the lower surface of the honeycomb core prefabricated board; the anti-floating shoulder pole device comprises four parts, namely a welded steel pipe, a fixed large-diameter screw, an action steel bar, and a hanging bar; a first circular hole is opened at the center point of the length direction of the welded steel pipe and the midline point of the pipe diameter, and a first nut is welded on the upper part of the first circular hole, and the upper part of the hanging bar cooperates with the first nut; reserved holes are opened at both ends of the welded steel pipe to allow the action steel bar to pass through; holes are opened at both ends of the welded steel pipe, and second nuts with a diameter smaller than the diameter of the welded steel pipe are welded at the two ends of the welded steel pipe, and two fixed large-diameter screws cooperate with the second nuts to tighten the action steel bar.
[0006] Specifically, the mesh cloth is wider than the lower surface of the honeycomb core prefabricated panel.
[0007] Specifically, the first circular hole is a circular hole with a diameter greater than 10 mm, ensuring that a steel bar with a diameter of 10 mm can directly pass through the hole.
[0008] Specifically, the hanging rod is a hook made of a steel bar with a diameter of 10 mm.
[0009] Specifically, the diameter of the holes opened at both ends of the welded steel pipe is greater than 16 mm to ensure that 16 mm effective steel bars can penetrate.
[0010] The present invention also discloses a construction method using a GBF honeycomb core board construction auxiliary device, comprising the following steps:
[0011] S1: Construction of the support system: Mark the edge line of the rib beam and the center line of the honeycomb core on the upper surface of the formwork to ensure the cross-sectional dimensions of the beam and the accuracy of the installation of the honeycomb core;
[0012] S2: tying rib beam reinforcement;
[0013] S3: Laying a layer of mesh cloth on the upper surface of the floor slab and the lower surface of the honeycomb core prefabricated board, wherein the width of the mesh cloth is greater than the width of the lower surface of the honeycomb core prefabricated board;
[0014] S4: Install the anti-floating shoulder pole device at the location to be poured and pour concrete.
[0015] Specifically, step S4 also includes the manufacturing process of the anti-floating shoulder pole device, opening a hole with a diameter greater than 10 mm at the center point of the length direction of a steel pipe whose length is greater than the center distance between two adjacent honeycomb core plates and the midline point of the pipe diameter, and welding a nut on the hole, making a hook with a 10 mm diameter steel bar, threading the upper part of the hook with a threading machine, opening a hole with a diameter greater than 16 mm at each end of the welded steel pipe and welding a nut on the hole, and welding nuts with a diameter smaller than the diameter of the welded steel pipe at both ends of the welded steel pipe.
[0016] Specifically, in step S4, the method of using the anti-floating shoulder pole device is to insert the hanger bar into the rib beam steel bar, connect the welded steel pipe to the hanger bar, pass the working steel bar through the holes at both ends of the welded steel pipe, directly against the GBF honeycomb core plate, and install two fixing screws at the nuts at both ends of the welded steel pipe to tighten and secure the working steel bar.
[0017] Specifically, after step S4, the step of removing the anti-floating tool is also included, the two fixing screws are loosened, the working steel bars are taken out from the concrete, and the hanging steel bar threads are loosened and then taken out, and finally the surface concrete is vibrated, the bottom formwork of the floor slab is removed, and a thin plaster is applied on the lower part of the GBF honeycomb core board precast panel.
[0018] Specifically, during the construction process, the work is cyclically carried out on each working surface. After the concrete pouring is completed, the anti-floating tools are removed and transported to the next working surface for use.
[0019] The GBF honeycomb core board construction auxiliary device in the present invention adds a mesh cloth on the template to isolate the template from the prefabricated bottom plate, so that the cement mortar in the cast-in-place concrete can enter the gap between the prefabricated plate and the template, and the floor surface is a whole after the pouring is completed; at the same time, compressive steel bars are added to the top surface of the honeycomb core, and the steel bars are fixed between the rib beam and the honeycomb core, effectively solving the problem of floating and displacement of the honeycomb core. After the top plate is cast and formed once by this construction method, the bottom of the plate is smooth and flat, and there is no need to process the bottom of the rib beam, which greatly improves the construction quality and efficiency of the honeycomb core. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 This is a cross-sectional view of the GBF honeycomb core installation in the present invention.
[0021] Figure 2 This is a top view of the GBF honeycomb core installation in the present invention.
[0022] Figure 3 This is an assembly diagram of the anti-floating tool in the present invention.
[0023] Figure 4 It is a side view of the anti-floating tool assembly in the present invention.
[0024] Among them, 1. welded steel pipe, 2. nut, 3. hanger rod, 4. action steel bar, 5. GBF honeycomb core board, 6. rib steel bar, 7. mesh cloth, 8. fixing screws. DETAILED DESCRIPTION
[0025] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.
[0026] like Figures 1 to 4 As shown, a GBF honeycomb core board construction auxiliary device includes: a template, an anti-floating shoulder pole device, a honeycomb core prefabricated board 5, and a mesh cloth 7; the mesh cloth 7 is laid between the upper surface of the template and the lower surface of the honeycomb core prefabricated board 5; wherein the anti-floating shoulder pole device includes four parts, namely a welded steel pipe 1, a fixed large-diameter screw 8, an action steel bar 4, and a hanging bar 3; a first circular hole is opened at the center point of the length direction of the welded steel pipe 1 and the midline point of the pipe diameter, and a first nut is welded on the upper part of the first circular hole, and the upper part of the hanging bar 3 cooperates with the first nut; reserved holes are opened at both ends of the welded steel pipe 1 to allow the action steel bar 4 to pass through; holes are opened at both ends of the welded steel pipe 1, and second nuts with a diameter smaller than the diameter of the welded steel pipe are welded at the two ends of the welded steel pipe 1, and two fixed large-diameter screws 8 cooperate with the second nuts to tighten the action steel bar 4.
[0027] Specifically, the mesh cloth 7 is wider than the lower surface of the honeycomb core prefabricated panel 5 .
[0028] Specifically, the first circular hole is a circular hole with a diameter greater than 10 mm, ensuring that a steel bar with a diameter of 10 mm can directly pass through the hole.
[0029] Specifically, the hanging rod 3 is a hook made of a steel bar with a diameter of 10 mm.
[0030] Specifically, the diameter of the holes opened at both ends of the welded steel pipe 1 is greater than 16 mm, ensuring that the 16 mm active steel bars 4 can penetrate.
[0031] The working principle of the GBF honeycomb core board construction auxiliary device of the present invention is as follows: 1. According to the construction method of the general GBF honeycomb core board, the support system is first constructed, and the rib beam edge line and the center line of the honeycomb core are marked on the upper surface of the template to effectively ensure the cross-sectional size of the beam and the accuracy of the honeycomb core installation; 2. Tie the rib beam steel bars 6. Since the thickness of the GBF honeycomb core floor is relatively large, the cross-sectional area of the rib beam is also relatively large. During the installation process, the steel bars are firmly tied and the straightness of the steel bar beam is ensured; 3. A layer of mesh cloth 7 is laid on the upper surface of the floor and the lower surface of the honeycomb core prefabricated board, and the mesh cloth is wider than the lower surface of the honeycomb core prefabricated board 5; 4. Prepare for concrete pouring. Before concrete pouring, the anti-floating shoulder pole device is first installed on the first pouring position. The anti-floating shoulder pole device is mainly composed of a welded steel pipe 1, a large-diameter screw 8, an action steel bar 4, and a hanger 3.
[0032] The anti-floating shoulder pole device is mainly composed of four parts: welded steel pipe, large diameter bolt, action steel bar and hanging bar. During manufacturing: prepare a DN25 diameter welded steel pipe 1, the length of which is greater than the center distance between two adjacent honeycomb core plates. Open a hole at the center point of the length direction of the steel pipe and the midline point of the pipe diameter. The diameter of the hole is greater than the 10mm round hole to ensure that the 10mm diameter steel bar can directly pass through this hole. And weld a nut 2 on the upper part of the round hole, the role of the nut is to adjust the length of the steel bar hook; make a hook with a 10mm diameter steel bar, the upper part of the hook is in the form of a thread, and the length of the thread is made according to the required length on site; open holes at both ends of the welded steel pipe, the diameter of the round hole is greater than 16mm, to ensure that the threaded 16 steel bar is penetrated; weld nuts with a diameter smaller than the diameter of the welded steel pipe at both ends of the welded steel pipe, the role of the nut is to control the honeycomb core to prevent floating during the concrete pouring process.
[0033] When using the anti-floating shoulder pole device: first insert the hanger 3 into the ribbed beam reinforcement 6; connect the welded steel pipe 1 with the hanger 3; pass the working reinforcement 4 through the reserved holes at both ends of the welded steel pipe, and directly press against the GBF honeycomb core plate 5; install two fixing screws 8 at the nuts at both ends of the welded steel pipe 1 to ensure that the two fixing screws 8 press the working reinforcement tightly and firmly; during the installation process, attention should be paid to the height control of the welded steel pipe 1 and the hanger 3, which should correspond to the length of the working reinforcement 4 pushed into the GBF honeycomb core plate 5, to ensure that the entire tool transfers the force to the ribbed beam reinforcement 6; for pouring concrete beams and slabs, the anti-floating tool should be installed in advance for each area poured during the construction process, and it should be removed and replaced in time to the next area after the pouring is completed to realize the cyclic operation.
[0034] After the construction is completed, the anti-floating pole device can be removed: first loosen the two fixing screws 8, remove the working steel bar 4 from the concrete, and then remove it after the thread of the hanging bar 3 is sent. Finally, vibrate the surface concrete; after removing the bottom formwork of the floor slab, you can choose to thinly plaster the lower part of the GBF honeycomb core board precast plate.
[0035] It is known from common technical knowledge that the present invention can be implemented by other embodiments that do not deviate from its spirit or essential features. Therefore, the above disclosed embodiments are only illustrative in all respects and are not exclusive. All changes within the scope of the present invention or within the scope equivalent to the present invention are included in the present invention.
Claims
1. A GBF honeycomb core board construction auxiliary device, It is characterized in that include: A template, an anti-floating shoulder pole device, a honeycomb core prefabricated plate (5), and a mesh cloth (7); the mesh cloth (7) is laid between the upper surface of the template and the lower surface of the honeycomb core prefabricated plate (5); the anti-floating shoulder pole device comprises four parts, namely, a welded steel pipe (1), a fixing large-diameter screw (8), an action steel bar (4), and a hanging bar (3); a first circular hole is opened at the center point in the length direction of the welded steel pipe (1) and the midline point of the pipe diameter, and a first nut is welded on the upper part of the first circular hole, and the upper part of the hanging bar (3) cooperates with the first nut; reserved holes are opened at both ends of the welded steel pipe (1) to allow the action steel bar (4) to pass through; Holes are opened at both ends of the welded steel pipe (1), and second nuts with a diameter smaller than that of the welded steel pipe are welded at the two ends of the welded steel pipe (1). Two fixing screws (8) with a large diameter cooperate with the second nuts to tighten the working steel bar (4); the mesh cloth (7) is wider than the lower surface of the honeycomb core prefabricated plate (5); the first circular hole is a circular hole with a hole diameter greater than 10 mm, ensuring that a steel bar with a diameter of 10 mm can directly pass through the hole; the hanging bar (3) is a hook made of a steel bar with a diameter of 10 mm; the diameter of the holes opened at both ends of the welded steel pipe (1) is greater than 16 mm, ensuring that a working steel bar (4) with a diameter of 16 mm can pass through.
2. A construction method using the GBF honeycomb core board construction auxiliary device according to claim 1, Features , including the following steps: S1: Construction of the support system: Mark the edge line of the rib beam and the center line of the honeycomb core on the upper surface of the formwork to ensure the cross-sectional dimensions of the beam and the accuracy of the installation of the honeycomb core; S2: tying rib beam reinforcement; S3: Lay a layer of mesh cloth on the upper surface of the floor slab and the lower surface of the honeycomb core prefabricated board, and the width of the mesh cloth is greater than the width of the lower surface of the honeycomb core prefabricated board; S4: Install the anti-floating shoulder pole device at the location to be poured and pour concrete.
3. The construction method according to claim 2, Features Step S4 also includes the manufacturing process of the anti-floating shoulder pole device, a hole with a diameter greater than 10 mm is opened at the center point of the length direction of a steel pipe whose length is greater than the center distance between two adjacent honeycomb core plates and the midline point of the pipe diameter, and a nut is welded on the hole, a hook is made with a 10 mm diameter steel bar, and a thread is threaded on the upper part of the hook with a threading machine, a hole with a diameter greater than 16 mm is opened at both ends of the welded steel pipe and a nut is welded on the hole, and nuts with a diameter smaller than the diameter of the welded steel pipe are welded at the two ends of the welded steel pipe.
4. The construction method according to claim 2, Features In step S4, the method of using the anti-floating shoulder pole device is to insert the hanger bar into the rib beam steel bar, connect the welded steel pipe with the hanger bar, pass the working steel bar through the holes at both ends of the welded steel pipe, directly against the GBF honeycomb core plate, and install two fixing screws at the nuts at both ends of the welded steel pipe to tighten and secure the working steel bar.
5. The construction method according to claim 2, It is characterized in that After step S4, the process also includes the step of removing the anti-floating tool, loosening the two fixing screws, taking out the working steel bars from the concrete, taking them out after loosening the hanging bar threads, and finally vibrating the surface concrete, removing the floor bottom formwork, and thinly plastering the lower part of the GBF honeycomb core board precast panel.
6. The construction method according to claim 2, It is characterized in that During the construction process, the work is cyclically carried out on each working surface. After the concrete pouring is completed, the anti-floating tools are removed and transported to the next working surface for use.
Citation Information
Patent Citations
Construction method for prefabricated perforated type filling module of ribbed cast-in-place concrete floor slab
CN102661051A
Structure for anti-floating constraint of honeycomb core
CN107327066A
Hollow floor slab anti-overturning structure
CN108824684A
Construction method for anti-floating structure of cast-in-place concrete hollow floor cover
CN108867965A
Construction method facilitating guarantee of hollow floor structural size
CN108930409A