A segmented support construction method for an underground passage

Through the segmented support construction method, the problems of inconsistent steel pipe lengths and poor stability in traditional underground ramp frame erection are solved, fast and safe underground passage construction is achieved, and traffic height and material savings are ensured.

CN111636665BActive Publication Date: 2024-10-29CHINA CONSTR FOURTH BUREAU FOURTH CONSTR ENG +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202010613468.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-06-30
Publication Date
2024-10-29
Estimated Expiration
2040-06-30

AI Technical Summary

Technical Problem

The traditional underground ramp frame erection has problems such as material waste, extended construction period, and poor safety caused by inconsistent steel pipe lengths. In addition, inconsistent steel pipe frame heights cause slippage, affecting traffic and material transportation costs.

Method used

Using the segmented support construction method, by measuring and positioning the slope of the ramp and the elevation of the shear wall, it is divided into low-section and high-section beams, and I-beam diagonal supports are installed between each group of beams, and thick steel plates are laid to ensure stability. and traffic height, and optimize the layout spacing and connection methods of support components.

Benefits of technology

It achieves rapid erection and stability of the basement entrance section, shortens the construction period, saves materials, ensures traffic height, reduces transportation costs, and improves construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111636665B_ABST
    Figure CN111636665B_ABST
Patent Text Reader

Abstract

The present invention discloses a segmented support construction method for an underground passage, which specifically comprises the following steps: S1, measuring, locating and laying out the elevations of the slope of a basement ramp and the ramp shear walls on both sides of the basement ramp; S2, selecting the traffic height limit of the underground passage as 3.5 meters, measuring the width and height of the basement ramp and segmenting the basement ramp into two sections, high and low; S3, measuring and finding out the shear wall installation points with a vertical height of 3.5 meters from the tops of the shear walls on both sides of the basement ramp to the basement ramp, and installing a first group of low-section beams on the installation points; S4, using support columns to erect a first group of high-section beams with a vertical height of 3.5 meters at the entrance of the basement ramp; while ensuring the overall stability of the basement entrance section, the required building materials are saved, so that the basement entrance section can be quickly erected, and can be opened to traffic and input and output large equipment before the overall construction period is fully completed, thereby greatly shortening the construction period and reducing the material transportation cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention is applied to the technical field of building construction, and specifically is a segmented support construction method for an underground passage. Background Art

[0002] With the rapid development of construction, construction period and safety are particularly important. The steel pipe frame erected on the underground ramp is easy to slip, and the overall stability of the frame is poor. The length of the steel pipe varies with the location of the ramp, which easily leads to the cutting of steel pipe materials and waste of resources. Steel beams are erected on the shear wall, and then steel plates are laid. This makes the steel pipe frame consistent in elevation, and the traffic below can be open and safe.

[0003] The traditional ramp frame is built with steel pipe scaffolding. According to different slopes and heights, steel pipes are processed and cut, and then the steel pipe scaffolding is built. The traditional ramp steel pipe scaffolding is not conducive to the control of the construction period. The ramp position is a high formwork that can only be removed after 28 days, which affects the passage of the ramp position and increases the material transportation cost. At the same time, the steel pipe frame at the ramp position has different heights, is easy to slip, and has poor integrity, which is not conducive to safety control. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a segmented support construction method for an underground passage in view of the deficiencies in the prior art.

[0005] In order to solve the above technical problems, a segmented support construction method for an underground passage of the present invention specifically comprises the following steps:

[0006] S1, measure, locate and lay out the slope of the basement ramp and the elevation of the ramp shear walls on both sides of the basement ramp;

[0007] S2, the traffic height limit of the underground passage is set to 3.5 meters, the width and height of the basement ramp are measured and the basement ramp is divided into two sections, high and low;

[0008] S3, measure and find the shear wall installation points with a vertical height of 3.5 meters from the top of the shear wall on both sides of the basement ramp to the basement ramp, install the first set of low-section beams on the installation points, and continue to extend into the basement ramp to set up multiple sets of low-section beams at intervals to complete the installation of the low-section support assembly;

[0009] S4, using support columns to erect the first set of high-section beams with a vertical height of 3.5 meters at the entrance of the basement ramp, and continue to extend into the basement ramp to set up multiple sets of high-section beams horizontal to the first set of high-section beams to complete the installation of the high-section support assembly;

[0010] S5, install the low-section I-beam oblique support between each set of low-section beams and the shear walls on both sides to complete the reinforcement of the low-section support assembly;

[0011] S6, install high-section I-beam oblique supports between each set of high-section cross beams and support columns to complete the reinforcement of the high-section support assembly;

[0012] S7, horizontally lay load-bearing thick steel plates on multiple groups of low-section beams and multiple groups of high-section beams to complete the overall construction of segmented support.

[0013] As a better choice, preferably, the layout spacing between the low-section beams and the layout spacing between the high-section beams are both 1.2-1.6 meters.

[0014] As a possible implementation manner, further, both ends of the lower cross beam are locked and connected to the ramp shear walls on both sides by bolts.

[0015] As a possible implementation manner, further, one end of the lower section I-beam oblique support is welded to the lower section cross beam, and the other end thereof is connected to the ramp shear wall by bolt locking.

[0016] As a possible implementation manner, further, both ends of the high-section I-beam oblique support are respectively welded to the support column and the high-section crossbeam.

[0017] As a possible implementation manner, further, the thick steel plate is a 5 mm thick steel plate, and a steel pipe scaffolding is laid on the thick steel plate.

[0018] The present invention adopts the above technical solution and has the following beneficial effects:

[0019] 1. This construction method ensures the overall stability of the basement entrance section by setting up low-section support components and high-section support components in sections. Compared with the existing construction method of using a large amount of cement pouring, it saves the required building materials, so that the basement entrance section can be quickly erected and opened to traffic and large equipment can be input and output before the overall construction period is fully completed, thereby greatly shortening the construction period and reducing material transportation costs.

[0020] 2. This construction method ensures the overall minimum traffic height of the underground passage by setting a high-section crossbeam at the basement entrance and a low-section crossbeam closest to the basement entrance of equal height, ensuring that the traffic height at the basement entrance is the traffic height of the entire basement, blocking vehicles that exceed the height limit outside the basement entrance, effectively preventing vehicles from getting stuck when passing through the basement ramp after entering the basement entrance, and unifying the overall height limit of the underground passage. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments:

[0022] Figure 1 It is a schematic diagram of the ramp sections of the present invention;

[0023] Figure 2 This is a schematic diagram of the layout of the low-section crossbeam of the present invention;

[0024] Figure 3 It is a curve diagram of the maximum force y of the thick steel plate of the low-section cross beam and the high-section cross beam of the present invention. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0026] like Figure 1-3 As shown, the present invention provides a segmented support construction method for an underground passage, which specifically includes the following steps:

[0027] S1, measuring, locating and laying out the slope of the basement ramp 1 and the elevation of the shear walls 2 on both sides of the basement ramp 1;

[0028] S2, the traffic height limit of the underground passage is set to 3.5 meters, the width and height of the basement ramp 1 are measured and the basement ramp 1 is divided into two sections, high and low;

[0029] S3, measuring and finding the shear wall 2 installation point where the vertical height from the top of the shear wall 2 on both sides of the basement ramp 1 to the basement ramp 1 is 3.5 meters, installing the first set of low-section beams 101 on the installation point, and continuing to extend into the basement ramp 1 to set multiple sets of low-section beams 101 at intervals to complete the installation of the low-section support assembly 100; the two ends of the low-section beams 101 are mutually locked and connected with the ramp shear walls 2 on both sides by bolts;

[0030] S4, using support columns 201 to set up a first set of high-section beams 202 with a vertical height of 3.5 meters at the entrance of the basement ramp, and continue to extend into the basement ramp 1 to set up multiple sets of high-section beams 202 at intervals that are horizontal to the first set of high-section beams 202 to complete the installation of the high-section support assembly 200;

[0031] S5, install the low-section I-beam oblique support 102 between each group of low-section cross beams 101 and the shear walls 2 on both sides, one end of the low-section I-beam oblique support 102 is welded to the low-section cross beam 101, and the other end is connected to the ramp shear wall 2 by bolt locking, completing the reinforcement work of the low-section support assembly 100;

[0032] S6, installing a high-section I-beam oblique support 203 between each set of high-section crossbeams 202 and support columns 201, and welding the two ends of the high-section I-beam oblique support 203 to the support columns 201 and the high-section crossbeams 202, respectively, to complete the reinforcement of the high-section support assembly 200;

[0033] S7, horizontally lay load-bearing thick steel plates 300 on multiple groups of low-section beams 101 and multiple groups of high-section beams 202. The thick steel plates 300 are 5 mm thick steel plates, and steel pipe scaffolding is laid on the thick steel plates 300 to complete the overall construction of segmented support.

[0034] The above-mentioned low-section cross beam 101, I-beam diagonal support 102, support column 201, high-section cross beam 202 and high-section I-beam diagonal support 203 are all made of 16# I-beam.

[0035] The spacing between the lower beams 101 and the spacing between the upper beams 202 are both 1.2-1.6 meters. The spacing between multiple groups of beams has a great influence on the load-bearing capacity and stability of the thick steel plates laid on them. If the spacing between the beams is too small, it will lead to excessive increase in costs. If the spacing between the beams is too large, it will lead to a decrease in the load-bearing capacity of the thick steel plates laid on them and easy deformation. Specifically, according to construction experience, when the spacing between the beams is less than 1.2 meters, the construction cost is too high. Please refer to Figure 3 , Figure 3 The crossbeam is made of 16# I-beam, and the thick steel plate is 5mm thick Q235 steel plate. The maximum stress of the thick steel plate is y=-20.543x 2 +2.7329x+2610.4 curve. During the experiment, multiple groups of cylinders were used to drive 0.1m*3m push bars to squeeze downward from the center of the thick steel plate erected between two groups of beams. The force was observed to determine how much force could cause the thick steel plate to deform vertically by more than 2cm, thereby determining the maximum force it could withstand. Figure 3 It can be seen that when the spacing between the beams is greater than 1.6 meters, the maximum force y that the thick steel plate can withstand decreases significantly. Therefore, the optimal spacing between the beams is determined to be 1.2-1.6 meters.

[0036] The above are embodiments of the present invention. For ordinary technicians in this field, according to the teachings of the present invention, all equivalent changes, modifications, substitutions and variations made within the scope of the patent application of the present invention without departing from the principles and spirit of the present invention should fall within the scope of the present invention.

Claims

1. A segmented support construction method for an underground passage, characterized in that: The specific steps include: S1, measure, locate and lay out the slope of the basement ramp and the elevation of the ramp shear walls on both sides of the basement ramp; S2, the traffic height limit of the underground passage is set to 3.5 meters, the width and height of the basement ramp are measured and the basement ramp is divided into two sections, high and low; S3, measure and find the shear wall installation points with a vertical height of 3.5 meters from the top of the shear wall on both sides of the basement ramp to the basement ramp, install the first set of low-section beams on the installation points, and continue to extend into the basement ramp to set up multiple sets of low-section beams at intervals to complete the installation of the low-section support assembly; S4, using support columns to erect the first set of high-section beams with a vertical height of 3.5 meters at the entrance of the basement ramp, and continue to extend into the basement ramp to set up multiple sets of high-section beams horizontal to the first set of high-section beams to complete the installation of the high-section support assembly; S5, install the low-section I-beam oblique support between each set of low-section beams and the shear walls on both sides to complete the reinforcement of the low-section support assembly; S6, install high-section I-beam oblique supports between each set of high-section cross beams and support columns to complete the reinforcement of the high-section support assembly; S7, horizontally lay load-bearing thick steel plates on multiple groups of low-section beams and multiple groups of high-section beams to complete the overall construction of segmented support.

2. The segmented support construction method for an underground passage according to claim 1 is characterized in that: The layout spacing between the low-section cross beams and the layout spacing between the high-section cross beams are both 1.2-1.6 meters.

3. The segmented support construction method for an underground passage according to claim 1 is characterized in that: The two ends of the low-section cross beam are locked and connected to the ramp shear walls on both sides by bolts.

4. The segmented support construction method for an underground passage according to claim 1 is characterized in that: One end of the lower section I-beam oblique support is welded to the lower section cross beam, and the other end is locked and connected to the ramp shear wall by bolts.

5. The segmented support construction method for an underground passage according to claim 1 is characterized in that: The two ends of the high-section I-beam oblique support are respectively welded to the support column and the high-section crossbeam.

6. The segmented support construction method for an underground passage according to claim 1, characterized in that: The thick steel plate is a 5mm thick steel plate, and a steel pipe scaffold is laid on the thick steel plate.