Cantilever light structure cast-in-place suspension bracket and use method thereof
By adopting a combined structure of L-shaped load-bearing pipe and tripod in the cast-in-place suspension bracket in the cantilever light structure, combined with door-type embedded ribs and tensile steel bars, the problem of low installation and removal efficiency of suspension brackets in the prior art is solved, and adapted to The construction of bridges on complex terrain improves construction safety and efficiency.
Patent Information
- Application Number
- CN202010589284.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-06-24
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2040-06-24
AI Technical Summary
The existing cast-in-place suspension brackets are inefficient during installation and dismantling, and it is difficult to meet construction needs when the use of hanging baskets and cranes are not allowed, especially in bridge construction in mountainous terrain.
A cast-in-place suspension bracket is designed with a combination of L-type load-bearing pipe and tripod. The through-holes and limit bolts of the L-type load-bearing pipe are used to fix and disassemble the tripod, combined with door-type pre-buried The ribs and tensile steel bars provide support in horizontal and vertical directions, adapt to the special shape of the U-beam, and use suspended ropes to prevent the tripod from falling.
It realizes the convenience, flexibility and efficiency of construction, adapts to the construction of bridges on complex terrain, improves construction safety, and complies with the legal requirements of not using hanging baskets.
Smart Images

Figure CN111764289B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of bridge construction, and more specifically to a cantilever light structure cast-in-place suspension bracket and a method for using the same. Background Art
[0002] Conventional cast-in-place brackets are cast-in-place with traditional hanging formwork in China. They are mainly made of steel as upper and lower load-bearing beams, connected by hanging rods, and distribution beams and bottom formwork are laid on the lower load-bearing beam for casting. In foreign countries such as Malaysia, traditional tripod cast-in-place is mainly made of flat iron and steel welded into a tripod, and the tripod is fixed to the U-beam web by expansion bolts. Distribution beams and bottom formwork are laid on the tripod for casting. These conventional cast-in-place brackets require ladder trucks and cranes to assist in the installation and removal processes. The construction efficiency itself is not high. According to Malaysian law, the use of hanging baskets for high-altitude operations is not allowed. Due to the restrictions of mountainous terrain conditions, some bridge construction areas are located in mountainous areas and cross existing highways and MRTs, which cannot meet the construction requirements of ladder trucks and cranes. The upper structure of the bridge ramp in Malaysia is mainly a prefabricated U-beam with a notch at the top corner, and the side beam has no flange plate design. The bridge deck is cast-in-place on the U-beam. Therefore, it is a difficult problem to construct cast-in-place brackets for specific U-beam structures and meet the requirements of not using hanging baskets, cranes and other equipment. Summary of the invention
[0003] An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.
[0004] Another object of the present invention is to provide a cantilever light structure cast-in-place suspension bracket and a method of using the same, so as to solve the technical problems of inconvenient installation and removal and low construction efficiency of the existing cast-in-place suspension bracket.
[0005] In order to achieve these purposes and other advantages according to the present invention, a cantilever light structure cast-in-place suspension bracket is provided, comprising:
[0006] A plurality of L-shaped load-bearing tubes are respectively arranged at the top corners of the U-beam and are evenly distributed along the length direction of the U-beam. A notch is opened outwardly along the length direction of the U-beam at the top corners of the U-beam. The L-shaped load-bearing tube has a horizontal portion and a vertical portion. The horizontal portion of the L-shaped load-bearing tube is perpendicular to the length direction of the U-beam and one end away from the vertical portion is located in the notch. The vertical portion has a vertical through hole and a length slightly greater than the thickness of the bridge deck cast on the U-beam. A bolt hole connected to the through hole is horizontally opened on the side wall of the vertical portion located above the thickness of the bridge deck cast, and a limit bolt is arranged in the bolt hole;
[0007] A plurality of tripods, one of which is respectively provided for each L-shaped load-bearing tube, the tripod comprising a first support rod, a second support rod and a third support rod which are fixedly connected in sequence, wherein the second support rod is arranged horizontally, the first support rod is arranged vertically and the upper end of the first support rod extends upward to the outside of the second support rod and then passes through the through hole upward, the third support rod is fixedly connected to the lower end of the first support rod, and a load-bearing block is welded on the side wall of the upper end of the first support rod outside the through hole;
[0008] A plurality of gate-shaped embedded bars are respectively arranged vertically on the upper surface of the U-beam close to one end of the L-shaped load-bearing tube and evenly distributed along the length direction of the U-beam. Both ends of the gate-shaped embedded bars are embedded and fixed in the U-beam. The plane direction of the gate-shaped embedded bars is the same as the width direction of the U-beam.
[0009] A plurality of connecting ribs, one of which is provided for each L-shaped load-bearing tube, the upper end of the connecting rib is a first U-shaped curved portion with the notch facing the U-beam and arranged horizontally, the two ends of the first U-shaped curved portion are respectively bent downward twice to form a second U-shaped curved portion with the notch facing away from the U-beam, and each first support rod is located at the bottom of the notch of a first U-shaped curved portion;
[0010] A plurality of tensile steel bars are arranged horizontally and the two ends are respectively inserted into the notches of the two second U-shaped bending parts of a connecting bar. Each tensile steel bar is also respectively located in the notch of the gate-shaped embedded bar at the corresponding position on the U beam.
[0011] Preferably, a pair of through holes are formed on the side wall of the first support rod above the load-bearing block, and a safety pin is passed through each pair of through holes.
[0012] Preferably, at least two gate-shaped embedded bars are provided corresponding to each connecting bar, and the tensile steel bars corresponding to each connecting bar are simultaneously inserted into the recesses of the two gate-shaped embedded bars and the recesses of the two second U-shaped bends of the connecting bars.
[0013] Preferably, a supporting foot is further provided at the bottom of the tripod, one end of the supporting foot is fixedly connected to the lower end of the first supporting rod, and the other end of the supporting foot is in contact with the web surface of the U beam.
[0014] Preferably, the tripod is formed by 50mm*25mm*3mm square steel, the load-bearing block is 50mm*20mm*6mm flat iron, the L-shaped load-bearing tube is 65mm*35mm*3mm square steel, and the limiting bolt is 25mm long.
[0015] The present invention also provides a method for using a cantilever light structure cast-in-place suspension bracket, comprising the following steps:
[0016] S1. Several gate-shaped embedded bars are evenly arranged on one side of the upper surface of the U-beam near the installation position along the length direction of the U-beam. The gate-shaped embedded bars are arranged vertically and the plane direction is the same as the width direction of the U-beam. The top corner of the U-beam has a notch opened outward, and the notch extends along the length direction of the U-beam;
[0017] S2. Tie a hanging rope to each door-shaped embedded reinforcement corresponding to the position where each tripod is to be installed, and tie the other end of the hanging rope to the end of the tripod away from the U beam, put the L-shaped load-bearing pipe on the upper end of the tripod and fix it relatively, then hang the L-shaped load-bearing pipe and the tripod as a whole to the outside of the web of the U beam, and then vertically install the L-shaped load-bearing pipe at the top corner of the U beam, wherein the horizontal part of the L-shaped load-bearing pipe is perpendicular to the length direction of the U beam, and the end of the horizontal part away from the vertical part is located in the notch and conflicts with the surface of the notch;
[0018] S3, using the first U-shaped bend of the connecting bar to hook the vertical part of the L-shaped load-bearing tube, and then inserting a tensile steel bar into the second U-shaped bend of the connecting bar, and at the same time inserting the tensile steel bar into the notch of the gate-shaped embedded bar at the corresponding position, the L-shaped load-bearing tube and the connecting bar, the tensile steel bar and the connecting bar, and the tensile steel bar and the gate-shaped embedded bar are in close contact, respectively, so as to provide horizontal support force for the L-shaped load-bearing tube;
[0019] S4. A row of distribution beams are arranged on the second support rods of all tripods at intervals, and the length direction of the distribution beams is consistent with the length direction of the U beams. Then, bottom molds are laid on all distribution beams. After the bottom molds are laid, the bridge deck is poured. During the pouring, a protection area is set for the L-shaped load-bearing pipe to prevent cement slurry from entering the L-shaped load-bearing pipe.
[0020] S5. After the bridge deck is poured, first remove the bottom formwork and distribution beam in turn, then release the fixation between the tripod and the L-shaped load-bearing tube, use the lifting rope to lower the tripod so that the tripod is completely separated from the L-shaped load-bearing tube, and then pull the tripod back from the outside of the bridge deck, then cut all the connecting bars, take out all the L-shaped load-bearing tubes, and finally recycle all the lifting ropes.
[0021] Preferably, in step S1, when the L-shaped load-bearing tube is sleeved on the upper end of the tripod and relatively fixed, the first support rod of the tripod is vertically passed through the through hole of the L-shaped load-bearing tube until the load-bearing block is located above the L-shaped load-bearing tube, and then the position of the tripod is adjusted so that the load-bearing block is in full contact with the top surface of the L-shaped load-bearing tube, and then the limiting bolt is tightened. When releasing the fixation between the tripod and the L-shaped load-bearing tube, first unscrew the limiting bolt, and then adjust the position of the tripod so that the first support rod with the load-bearing block is moved downward to the outside of the through hole of the L-shaped load-bearing tube.
[0022] Preferably, a pair of through holes are opened on the side wall of the tripod located above the load-bearing block, and a safety pin is passed through the through holes. When the tripod and the L-shaped load-bearing tube are released from fixation, the safety pin is first pulled out and then the limit bolt is unscrewed.
[0023] Preferably, when setting the protection area for the L-shaped load-bearing pipe in step S4, a PVC pipe is sleeved on the L-shaped load-bearing pipe, and then the PVC pipe is filled with geotextile.
[0024] Preferably, before setting the distribution beam and laying the bottom formwork, a lifting ear is respectively welded at both ends of each distribution beam, a hole is opened on the outside of the bottom formwork, and a lifting rope is respectively connected to each lifting ear and the hole on the bottom formwork. The other end of the lifting rope is fixedly connected to a gate-shaped embedded reinforcement at the corresponding position. When removing the bottom formwork and the distribution beam, the lifting rope is used to pull the bottom formwork and the distribution beam outward in sequence along the width direction of the U beam until they completely leave the bottom of the bridge deck, and then pull them onto the bridge deck to recover the bottom formwork and the distribution beam.
[0025] The present invention includes at least the following beneficial effects: the cantilever light structure cast-in-place suspension bracket of the present invention and the use method thereof, according to the special shape of the top corner of the U-beam, the L-shaped load-bearing tube is designed as the support system of the entire suspension bracket, which plays the role of limiting and supporting the tripod and transmits the forces in the vertical and horizontal directions to the U-beam, and a through hole and a limit bolt are arranged on the L-shaped load-bearing tube, and the tripod can be detachably fixed to the outer side of the web of the U-beam for laying the bottom mold and casting the bridge deck. After the casting of the bridge deck is completed, the L-shaped load-bearing tube and the tripod can be removed by simply unscrewing the limit bolt and cutting the connecting ribs. The overall material and equipment investment is small. At the same time, a lifting rope is introduced during the construction process to prevent the tripod from accidentally falling during the installation process. During the disassembly process, the lifting rope is used to pull the tripod away from the bottom of the bridge deck and then lift it for recovery. The whole construction process is convenient, flexible and efficient, and it also specifically solves the legal requirements of Malaysia and other countries that do not allow the use of hanging baskets for high-altitude operations. It can adapt to bridge construction in complex and dangerous terrains and significantly improves the safety of construction operations.
[0026] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is the main structural diagram of the present invention;
[0028] Figure 2 It is a side view of the structure of the present invention arranged on a U beam;
[0029] Figure 3 For the present invention Figure 1 The enlarged structure diagram at A in the middle;
[0030] Figure 4 It is a top view of the connecting rib of the present invention;
[0031] Figure 5 It is a side structural diagram of the upper end of the first support rod of the present invention;
[0032] Figure 6 It is a front view structural diagram of the L-shaped load-bearing tube of the present invention.
[0033] Explanation of the reference numerals in the drawings in the specification: 1. U-beam, 2. Notch, 3. Bridge deck, 4. Horizontal portion, 5. Vertical portion, 6. Through hole, 7. Bolt hole, 8. Limit bolt, 9. Tripod, 10. First support rod, 11. Second support rod, 12. Third support rod, 13. Load-bearing block, 14. Door-type embedded reinforcement, 15. Connecting reinforcement, 16. First U-shaped bend, 17. Second U-shaped bend, 18. Tensile reinforcement, 19. Through hole, 20. Safety pin, 21. Support foot, 22. Lifting rope, 23. Distribution beam, 24. Bottom form, 25. Protection area, 26. Lifting ear. DETAILED DESCRIPTION
[0034] The present invention is further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.
[0035] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials are commercially available unless otherwise specified; in the description of the present invention, the terms "lateral", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0036] like Figures 1 to 6 As shown, the present invention provides a cantilever light structure cast-in-place suspension bracket, comprising:
[0037] A plurality of L-shaped load-bearing tubes are respectively arranged at the top corners of the U-beam 1 and are evenly distributed along the length direction of the U-beam 1. A notch 2 is opened outwardly along the length direction of the U-beam 1 at the top corners of the U-beam 1. The L-shaped load-bearing tube has a horizontal portion 4 and a vertical portion 5. The horizontal portion 4 of the L-shaped load-bearing tube is perpendicular to the length direction of the U-beam 1 and one end away from the vertical portion 5 is located in the notch 2. The vertical portion 5 has a vertical through hole 6 and a length slightly greater than the thickness of the bridge deck 3 cast on the U-beam 1. A bolt hole 7 connected to the through hole 6 is horizontally opened on the side wall of the vertical portion 5 located above the thickness of the bridge deck 3 cast, and a limit bolt 8 is arranged in the bolt hole 7;
[0038] A plurality of tripods 9, one of which is provided for each L-shaped load-bearing tube, the tripod 9 comprises a first support rod 10, a second support rod 11 and a third support rod 12 which are fixedly connected in sequence, wherein the second support rod 11 is arranged horizontally, the first support rod 10 is arranged vertically and the upper end of the first support rod 10 extends upward to the outside of the second support rod 11 and then passes through the through hole 6 upward, the third support rod 12 is fixedly connected to the lower end of the first support rod 10, and a load-bearing block 13 is welded on the side wall of the upper end of the first support rod 10 outside the through hole 6;
[0039] A plurality of gate-shaped embedded ribs 14 are respectively vertically arranged on the upper surface of the U-beam 1 near one end of the L-shaped load-bearing tube and evenly distributed along the length direction of the U-beam 1. Both ends of the gate-shaped embedded ribs 14 are embedded and fixed in the U-beam 1. The plane direction of the gate-shaped embedded ribs 14 is the same as the width direction of the U-beam 1.
[0040] A plurality of connecting ribs 15, one of which is provided for each L-shaped load-bearing tube, the upper end of the connecting rib 15 is a first U-shaped curved portion 16 which is horizontally arranged and faces the U beam 1 in the notch direction, and the two ends of the first U-shaped curved portion 16 are respectively bent downward twice to form a second U-shaped curved portion 17 which faces away from the U beam 1 in the notch direction, and each first support rod 10 is located at the bottom of the notch of a first U-shaped curved portion 16;
[0041] A plurality of tensile steel bars 18 are arranged horizontally and have their two ends respectively inserted into the notches of the two second U-shaped bends 17 of a connecting bar 15 . Each tensile steel bar 18 is also respectively located in the notch of the gate-shaped embedded bar 14 at the corresponding position on the U beam 1 .
[0042] When using the cantilever light structure cast-in-place suspension bracket, the specific steps are as follows:
[0043] S1. A plurality of gate-shaped embedded bars are evenly arranged on one side of the upper surface of the U-beam close to the installation position along the length direction of the U-beam. The gate-shaped embedded bars are vertically arranged and the plane direction thereof is the same as the width direction of the U-beam. A notch is provided at the top corner of the U-beam, and the notch extends along the length direction of the U-beam.
[0044] S2. Sleeve the L-shaped load-bearing tube on the upper end of the tripod and fix it relatively. Specifically, the first support rod of the tripod vertically passes through the through hole of the L-shaped load-bearing tube until the load-bearing block is located on the L-shaped load-bearing tube. Then adjust the position of the tripod so that the load-bearing block is just resting on the top of the L-shaped load-bearing tube. Then tighten the limit bolts to limit the tripod to ensure that the L-shaped load-bearing tube is in full contact with the load-bearing block on the tripod to transmit force. Then hang the L-shaped load-bearing tube and the tripod as a whole to the outside of the web of the U-beam, and then vertically install several L-shaped load-bearing tubes at the top corners of the U-beam, wherein the horizontal portion of the L-shaped load-bearing tube is perpendicular to the length direction of the U-beam, and the end of the horizontal portion away from the vertical portion is located in the notch and in conflict with the surface of the notch.
[0045] S3. Use the first U-shaped bend of the connecting bar to hook the vertical part of the L-shaped load-bearing tube, and then insert a tensile steel bar into the second U-shaped bend of the connecting bar. At the same time, the tensile steel bar is inserted into the recess of the door-type embedded bar at the corresponding position. The L-shaped load-bearing tube and the connecting bar, the tensile steel bar and the connecting bar, and the tensile steel bar and the door-type embedded bar are in close contact respectively, thereby providing horizontal support force for the L-shaped load-bearing tube.
[0046] S4. A row of distribution beams are arranged at intervals on the second support rods of all tripods. The length direction of the distribution beams is consistent with the length direction of the U beams. Then, bottom formwork is laid on all distribution beams. After the bottom formwork is laid, the bridge deck is poured. During the pouring, protective measures are taken for the L-shaped load-bearing pipes to prevent cement slurry from entering the L-shaped load-bearing pipes.
[0047] S5. After the bridge deck is poured, first remove the bottom formwork and distribution beam in turn, then release the fixation between the tripod and the L-shaped load-bearing tube, recycle the tripod, then cut all the connecting bars and take out all the L-shaped load-bearing tubes.
[0048] The cantilever light structure cast-in-place suspension bracket of the present invention is designed with an L-shaped load-bearing tube as the support system of the entire suspension bracket according to the special shape of the top corner of the U-beam. Through holes and limit bolts are arranged on the L-shaped load-bearing tube, and the tripod can be detachably fixed to the outer side of the web of the U-beam for laying the bottom mold and casting the bridge deck. The tripod is limited and supported by the L-shaped load-bearing tube, and then the forces in the vertical and horizontal directions are transmitted to the U-beam. After the casting of the bridge deck is completed, the connecting bars, tensile steel bars and gate-shaped embedded bars are retained in the bridge deck to enhance the internal shear strength of the bridge deck. At the same time, the gate-shaped embedded bars cooperate with the connecting bars and tensile steel bars to provide lateral support and stability to the L-shaped load-bearing tube and the tripod. When the device needs to be dismantled, it is only necessary to unscrew the limit bolts and cut the connecting bars to remove the L-shaped load-bearing tube and the tripod. The overall material and equipment investment is small, the installation and disassembly are simple and flexible, and the construction operation efficiency is high.
[0049] In another technical solution, Figure 1 , Figure 2 , Figure 3 , Figure 5 As shown, a pair of through holes 19 are formed on the side wall of the first support rod 10 above the load-bearing block 13 , and a safety pin 20 is inserted into each of the pair of through holes 19 .
[0050] A safety pin is added to the top of the tripod to provide double insurance for the vertical support force of the tripod when it is hung during installation and removed, to avoid the hidden danger of the entire tripod leaving the through hole of the L-shaped load-bearing tube due to the limit bolt not being tightened or the load-bearing block not completely contacting the top of the L-shaped load-bearing tube and slipping.
[0051] In another technical solution, Figure 1 , Figure 3 As shown, at least two gate-shaped embedded bars 14 are provided for each connecting bar 15, and the tensile steel bars 18 corresponding to each connecting bar 15 are simultaneously inserted into the notches of the two gate-shaped embedded bars 14 and the notches of the two second U-shaped bent portions 17 of the connecting bar 15. Each two gate-shaped embedded bars are provided to balance the forces at both ends of a tensile steel bar.
[0052] In another technical solution, Figure 1 As shown, a supporting foot 21 is further provided at the bottom of the tripod 9 , one end of the supporting foot 21 is fixedly connected to the lower end of the first supporting rod 10 , and the other end thereof contacts the web surface of the U beam 1 .
[0053] By welding supporting feet at the bottom of the tripod, the lateral slope can be adjusted and the tripod can be further stabilized.
[0054] In another technical solution, Figure 1 , Figure 3 As shown, the tripod 9 is formed by 50mm*25mm*3mm square steel, the load-bearing block 13 is a 50mm*20mm*6mm flat iron, the L-shaped load-bearing tube is a 65mm*35mm*3mm square steel, and the limiting bolt 8 is 25mm long.
[0055] Using the square steel to process and shape to provide rigid support is conducive to achieving the overall lightweight of the cantilever light structure cast-in-place suspension bracket, which is convenient for transfer, transportation and position adjustment. The specifications of square steel, flat iron and limit bolts are common and easy to obtain, which is conducive to reducing production costs and improving construction efficiency.
[0056] The present invention also provides a method for using a cantilever light structure cast-in-place suspension bracket, Figures 1 to 6 As shown, the following steps are included:
[0057] S1, a plurality of gate-shaped embedded ribs 14 are evenly arranged on one side of the upper surface of the U beam 1 close to the installation position along the length direction of the U beam 1, the gate-shaped embedded ribs 14 are vertically arranged and the plane direction thereof is the same as the width direction of the U beam 1, and a notch 2 is provided at the top corner of the U beam 1, and the notch 2 extends along the length direction of the U beam 1;
[0058] S2. Tie a hanging rope 22 to each gate-shaped embedded reinforcement 14 corresponding to the position where each tripod 9 is to be installed, and the other end of the hanging rope 22 is tied and fixed to the end of the tripod 9 away from the U-beam 1. Put the L-shaped load-bearing pipe on the upper end of the tripod 9 and fix it relatively. Then hang the L-shaped load-bearing pipe and the tripod 9 as a whole to the outside of the web of the U-beam 1, and then vertically install the L-shaped load-bearing pipe at the top corner of the U-beam 1, wherein the horizontal part 4 of the L-shaped load-bearing pipe is perpendicular to the length direction of the U-beam 1, and the end of the horizontal part 4 away from the vertical part 5 is located in the notch 2 and conflicts with the surface of the notch 2;
[0059] S3, using the first U-shaped bend 16 of the connecting rib 15 to hook the vertical portion 5 of the L-shaped load-bearing tube, and then inserting a tensile steel bar 18 into the second U-shaped bend 17 of the connecting rib 15, and at the same time inserting the tensile steel bar 18 into the notch of the door-shaped embedded rib 14 at the corresponding position, the L-shaped load-bearing tube and the connecting rib 15, the tensile steel bar 18 and the connecting rib 15, and the tensile steel bar 18 and the door-shaped embedded rib 14 are in close contact, respectively, thereby providing horizontal support force for the L-shaped load-bearing tube;
[0060] S4. A row of distribution beams 23 are arranged on the second support rods 11 of all tripods 9 at intervals, and the length direction of the distribution beams 23 is consistent with the length direction of the U beam 1. Then, a bottom mold 24 is laid on all the distribution beams 23. After the bottom mold 24 is laid, the bridge deck 3 is cast. During the casting, a protection area 25 is set for the L-shaped load-bearing pipe to prevent cement slurry from entering the L-shaped load-bearing pipe;
[0061] S5. After the pouring of the bridge deck 3 is completed, the bottom formwork 24 and the distribution beam 23 are removed in turn, and then the fixation between the tripod 9 and the L-shaped load-bearing tube is released. The tripod 9 is lowered by the lifting rope 22 so that the tripod 9 is completely separated from the L-shaped load-bearing tube, and then the tripod 9 is pulled back from the outside of the bridge deck. After that, all the connecting ribs 15 are cut, all the L-shaped load-bearing tubes are taken out, and finally all the lifting ropes 22 are recovered.
[0062] Before pouring the bridge deck, an L-shaped load-bearing tube is used to detachably install the fixed suspension bracket, and a protection area is set for the L-shaped load-bearing tube. During the installation process, a lifting rope is preset for the tripod to prevent the tripod from accidentally falling during the installation process. The lifting rope can be a nylon rope. After the bridge deck is poured, the connecting reinforcement is cut, the limit bolts are unscrewed to release the tripod, and the lifting rope is used to pull the tripod away from the bottom of the bridge deck and then lift it for recovery. The entire construction process is convenient, flexible and efficient, and it specifically solves the legal requirements of countries such as Malaysia that do not allow the use of hanging baskets for high-altitude operations. It can adapt to bridge construction in complex and dangerous terrain and significantly improves the safety of construction operations.
[0063] In another technical solution, Figure 1 , Figure 2 , Figure 3 As shown, in step S1, when the L-shaped load-bearing tube is sleeved on the upper end of the tripod 9 and relatively fixed, the first support rod 10 of the tripod 9 is vertically passed through the through hole 6 of the L-shaped load-bearing tube until the load-bearing block 13 is located above the L-shaped load-bearing tube, and then the position of the tripod 9 is adjusted so that the load-bearing block 13 is in full contact with the top surface of the L-shaped load-bearing tube, and then the limiting bolt 8 is tightened. When the tripod 9 and the L-shaped load-bearing tube are released from the fixation, the limiting bolt 8 is first unscrewed, and then the position of the tripod 9 is adjusted so that the first support rod 10 with the load-bearing block 13 is moved downward to the outside of the through hole 6 of the L-shaped load-bearing tube.
[0064] Before tightening the limit bolt, the load-bearing block and the first support rod can pass through the through hole smoothly. The load-bearing block and the limit bolt are arranged in the horizontal direction on the outer surface of the first support rod, so that the load-bearing block can completely transfer the force of the tripod to the L-shaped load-bearing tube. The horizontal displacement of the tripod can be adjusted according to the tightening degree of the limit bolt, and the bolt structure is easy to install and disassemble.
[0065] In another technical solution, Figure 1 , Figure 2 , Figure 3 , Figure 5 As shown, a pair of through holes 19 are opened on the side wall of the tripod 9 located above the load-bearing block 13, and a safety pin 20 is passed through the through holes 19. When the tripod 9 and the L-shaped load-bearing tube are released from fixation, the safety pin 20 is first pulled out and then the limit bolt 8 is unscrewed.
[0066] A safety pin is added to the top of the tripod for double insurance during the installation and removal of the tripod, to avoid the hidden danger of the entire tripod falling due to the limit bolt not being tightened and the load-bearing block not completely contacting the top of the L-shaped load-bearing tube and slipping. If the tripod moves down in advance, the two ends of the safety pin will just contact the top surface of the L-shaped load-bearing tube to bear the gravity of the tripod.
[0067] In another technical solution, Figure 1 , Figure 3 As shown, when setting the protection area 25 for the L-shaped load-bearing pipe in step S4, a PVC pipe is sleeved on the L-shaped load-bearing pipe, and then the geotextile is filled in the PVC pipe.
[0068] PVC pipes are set to isolate and seal the L-shaped load-bearing pipes when pouring the bridge deck, so as to prevent cement slurry from contacting the L-shaped load-bearing pipes and affecting subsequent disassembly work. At the same time, the PVC pipes are set so that when the L-shaped load-bearing pipes are disassembled, they can be directly taken out from the PVC pipes upwards, which makes the construction convenient and quick.
[0069] In another technical solution, Figure 1 , Figure 2 As shown, before setting the distribution beam 23 and laying the bottom formwork 24, a lifting ear 26 is welded at both ends of each distribution beam 23, and a hole is opened on the outer side of the bottom formwork 24. A lifting rope 22 is connected to each lifting ear 26 and the hole on the bottom formwork 24, and the other end of the lifting rope 22 is fixedly connected to a gate-shaped embedded reinforcement 14 at the corresponding position. When the bottom formwork 24 and the distribution beam 23 are removed, the lifting rope 22 is used to pull the bottom formwork 24 and the distribution beam 23 outward in sequence along the width direction of the U beam 1 until they completely leave the bottom of the bridge deck 3, and then pull them onto the bridge deck 3 to recover the bottom formwork 24 and the distribution beam 23.
[0070] The bottom formwork and distribution beam are also removed using lifting ropes, which is easy to operate and has low construction costs. It is especially suitable for bridge construction projects in countries such as Malaysia that have laws prohibiting the use of cranes and hanging baskets.
[0071] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.
Claims
1. Cantilever light structure cast-in-place suspension bracket, characterized in that: include: A plurality of L-shaped load-bearing tubes are respectively arranged at the top corners of the U-beam and are evenly distributed along the length direction of the U-beam. A notch is opened outwardly along the length direction of the U-beam at the top corners of the U-beam. The L-shaped load-bearing tube has a horizontal portion and a vertical portion. The horizontal portion of the L-shaped load-bearing tube is perpendicular to the length direction of the U-beam and one end away from the vertical portion is located in the notch. The vertical portion has a vertical through hole and a length slightly greater than the thickness of the bridge deck cast on the U-beam. A bolt hole connected to the through hole is horizontally opened on the side wall of the vertical portion located above the thickness of the bridge deck cast, and a limit bolt is arranged in the bolt hole; A plurality of tripods, one of which is respectively provided for each L-shaped load-bearing tube, the tripod comprising a first support rod, a second support rod and a third support rod which are fixedly connected in sequence, wherein the second support rod is arranged horizontally, the first support rod is arranged vertically and the upper end of the first support rod extends upward to the outside of the second support rod and then passes through the through hole upward, the third support rod is fixedly connected to the lower end of the first support rod, and a load-bearing block is welded on the side wall of the upper end of the first support rod outside the through hole; A plurality of gate-shaped embedded bars are respectively arranged vertically on the upper surface of the U-beam close to one end of the L-shaped load-bearing tube and evenly distributed along the length direction of the U-beam. Both ends of the gate-shaped embedded bars are embedded and fixed in the U-beam. The plane direction of the gate-shaped embedded bars is the same as the width direction of the U-beam. A plurality of connecting ribs, one of which is provided for each L-shaped load-bearing tube, the upper end of the connecting rib is a first U-shaped curved portion with the notch facing the U-beam and arranged horizontally, the two ends of the first U-shaped curved portion are respectively bent downward twice to form a second U-shaped curved portion with the notch facing away from the U-beam, and each first support rod is located at the bottom of the notch of a first U-shaped curved portion; A plurality of tensile steel bars are arranged horizontally and the two ends are respectively inserted into the notches of the two second U-shaped bending parts of a connecting bar. Each tensile steel bar is also respectively located in the notch of the gate-shaped embedded bar at the corresponding position on the U beam.
2. The cantilever light structure cast-in-place suspension bracket according to claim 1, characterized in that: A pair of through holes is formed on the side wall of the first support rod located above the load-bearing block, and a safety pin is passed through each of the pair of through holes.
3. The cantilever light structure cast-in-place suspension bracket according to claim 1, characterized in that: At least two gate-shaped embedded bars are provided corresponding to each connecting bar, and the tensile steel bars corresponding to each connecting bar are simultaneously inserted into the notches of the two gate-shaped embedded bars and the notches of the two second U-shaped bends of the connecting bars.
4. The cantilever light structure cast-in-place suspension bracket according to claim 1, characterized in that: A supporting foot is also provided at the bottom of the tripod, one end of which is fixedly connected to the lower end of the first supporting rod, and the other end of which is in contact with the web surface of the U beam.
5. The cantilever light structure cast-in-place suspension bracket according to claim 1, characterized in that: The tripod is formed by 50mm*25mm*3mm square steel, the load-bearing block is a 50mm*20mm*6mm flat iron, the L-shaped load-bearing tube is a 65mm*35mm*3mm square steel, and the limiting bolt is 25mm long.
6. The method for using the cantilever light structure cast-in-place suspension bracket according to claim 1, characterized in that: The steps include: S1. Several gate-shaped embedded bars are evenly arranged on one side of the upper surface of the U-beam near the installation position along the length direction of the U-beam. The gate-shaped embedded bars are arranged vertically and the plane direction is the same as the width direction of the U-beam. The top corner of the U-beam has a notch opened outward, and the notch extends along the length direction of the U-beam; S2. Tie a hanging rope to each door-shaped embedded reinforcement corresponding to the position where each tripod is to be installed, and tie the other end of the hanging rope to the end of the tripod away from the U beam, put the L-shaped load-bearing pipe on the upper end of the tripod and fix it relatively, then hang the L-shaped load-bearing pipe and the tripod as a whole to the outside of the web of the U beam, and then vertically install the L-shaped load-bearing pipe at the top corner of the U beam, wherein the horizontal part of the L-shaped load-bearing pipe is perpendicular to the length direction of the U beam, and the end of the horizontal part away from the vertical part is located in the notch and conflicts with the surface of the notch; S3, using the first U-shaped bend of the connecting bar to hook the vertical part of the L-shaped load-bearing tube, and then inserting a tensile steel bar into the second U-shaped bend of the connecting bar, and at the same time inserting the tensile steel bar into the notch of the gate-shaped embedded bar at the corresponding position, the L-shaped load-bearing tube and the connecting bar, the tensile steel bar and the connecting bar, and the tensile steel bar and the gate-shaped embedded bar are in close contact, respectively, so as to provide horizontal support force for the L-shaped load-bearing tube; S4. A row of distribution beams are arranged on the second support rods of all tripods at intervals, and the length direction of the distribution beams is consistent with the length direction of the U beams. Then, bottom molds are laid on all distribution beams. After the bottom molds are laid, the bridge deck is poured. During the pouring, a protection area is set for the L-shaped load-bearing pipe to prevent cement slurry from entering the L-shaped load-bearing pipe. S5. After the bridge deck is poured, first remove the bottom formwork and distribution beam in turn, then release the fixation between the tripod and the L-shaped load-bearing tube, use the lifting rope to lower the tripod so that the tripod is completely separated from the L-shaped load-bearing tube, and then pull the tripod back from the outside of the bridge deck, then cut all the connecting bars, take out all the L-shaped load-bearing tubes, and finally recycle all the lifting ropes.
7. The method for using the cantilever light structure cast-in-place suspension bracket according to claim 6, characterized in that: In step S1, when the L-shaped load-bearing tube is sleeved on the upper end of the tripod and relatively fixed, the first support rod of the tripod is vertically passed through the through hole of the L-shaped load-bearing tube until the load-bearing block is located on the L-shaped load-bearing tube, and then the position of the tripod is adjusted so that the load-bearing block is in full contact with the top surface of the L-shaped load-bearing tube, and then the limiting bolt is tightened. When releasing the fixation between the tripod and the L-shaped load-bearing tube, first unscrew the limiting bolt, and then adjust the position of the tripod so that the first support rod with the load-bearing block is moved downward to the outside of the through hole of the L-shaped load-bearing tube.
8. The method for using the cantilever light structure cast-in-place suspension bracket according to claim 7, characterized in that: A pair of through holes are provided on the side wall of the tripod located above the load-bearing block, and a safety pin is passed through the through holes. When the tripod and the L-shaped load-bearing pipe are released from fixing, the safety pin is first pulled out and then the limit bolt is unscrewed.
9. The method for using the cantilever light structure cast-in-place suspension bracket according to claim 6, characterized in that: When setting the protection area for the L-shaped load-bearing pipe in step S4, a PVC pipe is placed on the L-shaped load-bearing pipe, and then the PVC pipe is filled with geotextile.
10. The method for using the cantilever light structure cast-in-place suspension bracket according to claim 6, characterized in that: Before setting the distribution beam and laying the bottom formwork, first weld a lifting ear at both ends of each distribution beam, open a hole on the outside of the bottom formwork, connect a lifting rope to each lifting ear and the hole on the bottom formwork, and fix the other end of the lifting rope to a gate-shaped embedded reinforcement at the corresponding position. When removing the bottom formwork and distribution beam, use the lifting rope to pull the bottom formwork and distribution beam outward along the width direction of the U beam in turn until they completely leave the bottom of the bridge deck, and then pull them onto the bridge deck to recover the bottom formwork and distribution beam.
Citation Information
Patent Citations
A new support for U type flange board is cast -in -place
CN205576746U
Superelevation, jumbo size board structural template braced system that encorbelments
CN205604719U
Novel cantilever light structure cast-in-place suspension support
CN212294380U
Formwork support for construction of extensions to existing building - includes support designed for easy removal from cast external corners
DE4115597A1
Integrated form structure for constructing cantilever slab and protective wall of bridge, and construction method using the same
KR101941942B1