Ballastless track boss damage treatment structure and treatment method

By setting up a new boss in the frame groove of the ballless track plate and filling the fill body, the problem of damage failure of the original boss is solved, the safety of track operation is improved, and the normal operation of the railway is ensured.

CN111893808BActive Publication Date: 2025-03-28CHINA RAILWAY SIYUAN GRP ENG OPERATION & MAINTENANCE CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202010852384.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-08-21
Publication Date
2025-03-28
Estimated Expiration
2040-08-21

Smart Images

  • Figure CN111893808B_ABST
    Figure CN111893808B_ABST
Patent Text Reader

Abstract

The embodiments of the present application provide a structure and method for managing damaged bosses on ballastless tracks, the structure comprising a base plate, a track plate, an original boss and a new boss. The track plate is disposed on the base plate, and has open grooves formed at both ends thereof, and a frame groove formed between the two ends. The original boss is disposed between two adjacent track plates, and is located in a space enclosed by two adjacent open grooves. The new boss is formed in the frame groove and is connected to the base plate. The management structure and method provided in the present application form a new boss in the frame groove on the track plate to limit the track plate, thereby effectively solving the problem of the original boss being damaged and failing, and being unable to ensure stable and safe operation of the track.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of rail transit technology, and in particular to a ballastless track boss damage management structure and a management method thereof. Background Art

[0002] Due to construction reasons, environmental factors and the dynamic load of the train, the original bosses between the track plates have cracked, broken and other damages, which weakened or even lost the limiting and fixing effect of the track plates, which is not conducive to maintaining the overall stability of the track structure and poses certain safety hazards to train operation.

[0003] In the prior art, temporary limiting measures are usually adopted on the track plate to deal with the problem. This treatment method cannot fundamentally solve the problem of damage and failure of the original boss, and cannot ensure the stability of the track and the safety of train operation in the long term. Summary of the invention

[0004] In view of this, the embodiments of the present application hope to provide a structure and method for treating damage to a ballastless track boss, so as to solve the problem of damage and failure of the original boss of the ballastless track in the prior art.

[0005] To achieve the above-mentioned purpose, one aspect of an embodiment of the present application provides a ballastless track boss damage treatment structure, comprising:

[0006] Base plate;

[0007] A track plate is arranged on the bottom plate, and opening grooves are formed at both ends of the track plate, and a frame groove is formed between the two ends;

[0008] The original boss is connected to the base, disposed between two adjacent track plates and located in the space surrounded by two adjacent opening grooves; and

[0009] A new boss is formed in the frame groove, and the new boss is connected to the bottom plate.

[0010] Furthermore, the management structure also includes a filling body, which is filled around the new boss and is located between the new boss and the track plate.

[0011] Furthermore, the filling body comprises a foam layer and a buffer layer, the foam layer is filled on the bottom plate, the top surface height of the foam layer is equal to the bottom surface height of the track plate, and the buffer layer is filled on the foam layer.

[0012] Further, the buffer layer comprises a resin bag and a resin, and the resin is cast and formed in the resin bag; and / or,

[0013] The filling body also includes a waterproof layer for preventing rainwater from penetrating into the buffer layer.

[0014] Furthermore, the new boss comprises:

[0015] A steel frame connected to the base plate; and

[0016] The boss body is formed by pouring concrete onto the steel reinforcement frame.

[0017] Further, the number of the new bosses in each of the frame grooves is one, and both ends of the new bosses along the extension direction of the ballastless track are adjacent to the track plate; or,

[0018] The number of the new bosses in each frame groove is two, which are respectively arranged on both sides of the frame groove along the extending direction of the ballastless track.

[0019] The ballastless track boss damage management structure provided in the embodiment of the present application utilizes the frame groove in the structure of the track plate itself and arranges a new boss in the frame groove to disperse the force borne by the original boss, thereby compensating for the insufficient force borne by the original boss and improving the safety of track operation caused by the damage problem of the original boss of the ballastless track.

[0020] Another aspect of the embodiment of the present application provides a method for treating ballastless track boss damage, comprising:

[0021] A new boss connected to the base plate is formed in the frame groove of the track plate;

[0022] Repair the original bosses in the open grooves at both ends of the track plate.

[0023] Furthermore, the step of constructing a new boss connected to the base plate in the frame groove of the track plate includes:

[0024] Implant the steel bar body on the bottom plate in the track plate frame groove;

[0025] Fixing the first template in the frame groove to surround the steel bar body;

[0026] pouring concrete in the first formwork to form the new boss;

[0027] removing the first template;

[0028] A filling body is filled between the new boss and the track plate.

[0029] Further, the step of filling the filling body between the new boss and the track plate comprises:

[0030] Filling a foam layer on the bottom plate between the new boss and the track plate;

[0031] placing a resin bag on the foam layer;

[0032] pouring resin into the resin bag;

[0033] A sealant is applied between the new boss and the track plate for waterproofing.

[0034] Furthermore, the steps of repairing the original bosses in the open grooves at both ends of the track plate include:

[0035] Chiseling away the damaged concrete of the original boss and the filling body around the original boss;

[0036] Inspect and replant damaged steel bars of the original boss;

[0037] Install a second template to surround the original boss;

[0038] Pouring concrete in the second formwork to repair the original boss;

[0039] removing the second template;

[0040] A new filling body is filled around the original boss.

[0041] The ballastless track boss damage treatment method provided in the embodiment of the present application provides a certain limit effect on the track plate by setting a new boss in the frame groove of the track plate, and repairing the damaged original boss. After the repair is completed, the new boss and the original boss together limit the track plate. This treatment method uses the idle time of the railway to effectively solve the problem of damage and failure of the original boss without affecting the normal operation of the railway. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] Figure 1 A schematic diagram of the structure of the governance structure provided for an embodiment of the present application;

[0043] Figure 2 for Figure 1 Sectional view of section AA;

[0044] Figure 3 for Figure 2 A partial enlarged view of point C in the middle;

[0045] Figure 4 A schematic diagram of a governance structure provided for another embodiment of the present application;

[0046] Figure 5 for Figure 4 Sectional view of the middle BB section;

[0047] Figure 6 A flowchart of a governance method provided for an embodiment of the present application; and

[0048] Figure 7 A flowchart of a governance method provided for another embodiment of the present application.

[0049] Description of reference numerals:

[0050] 1. Base plate; 2. Track plate; 21. Opening groove; 22. Frame groove; 3. Original boss; 4. New boss; 5. Filling body; 51. Foam layer; 52. Buffer layer. DETAILED DESCRIPTION

[0051] It should be noted that, in the absence of conflict, the embodiments and technical features in the embodiments of the present application can be combined with each other, and the detailed description in the specific implementation method should be understood as an explanation of the purpose of the present application and should not be regarded as an improper limitation on the present application.

[0052] The directional terms in the description of this application are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be understood as limiting this application.

[0053] One aspect of the present application provides a structure for treating ballastless track boss damage, as shown in FIG. Figure 5 The governance structure includes a bottom plate 1, a track plate 2, an original boss 3 and a new boss 4. The track plate 2 is arranged on the bottom plate 1, and an opening groove 21 is formed at both ends of the track plate 2, and a frame groove 22 is formed between the two ends. The original boss 3 is connected to the base, arranged between two adjacent track plates 2, and located in the space surrounded by two adjacent opening grooves 21. The new boss 4 is formed in the frame groove 22, and the new boss 4 is connected to the bottom plate 1.

[0054] Specifically, when the ballastless track is built, an original boss 3 is provided between two adjacent track plates 2, and a frame groove 22 is formed between the two ends of the track plate 2. For example, if the track plate 2 is an I-type track plate 2, the original boss 3 is used to limit the adjacent track plate 2. However, as the operation time of the ballastless track gradually increases, the original boss 3 is affected by impact loads, etc., and gradually cracks, breaks, etc., weakening or even losing the limiting and fixing function of the track plate 2, which is not conducive to maintaining the overall stability of the track structure. If it is not promptly treated, it will cause certain safety hazards to railway operations.

[0055] The management structure provided in the present application utilizes the frame groove 22 in the structure of the track plate 2 itself, and arranges a new boss 4 in the frame groove 22, thereby dispersing the force borne by the original boss 3, compensating for the insufficient force borne by the original boss 3, and effectively improving the safety performance of track operation caused by damage to the original boss 3 of the ballastless track. The structure is simple, the construction efficiency is high, and it does not affect the normal operation of the railway.

[0056] In one embodiment, see Figure 1 to Figure 5The governance structure provided by the present application further includes a filling body 5, which is filled around the new boss 4 and is located between the new boss 4 and the track plate 2. By arranging the filling body 5 between the new boss 4 and the track plate 2, the track plate 2 can be better limited, the impact between the track plate 2 and the new boss 4 can be reduced, and the service life of the original boss 3 can be increased.

[0057] In one embodiment, see Figure 3 In the governance structure provided in the present application, the filling body 5 includes a foam layer 51 and a buffer layer 52. The foam layer 51 is filled on the base plate 1, and the top surface height of the foam layer 51 is higher than or equal to the bottom surface height of the track plate 2. The buffer layer 52 is filled on the foam layer 51. Specifically, the buffer layer 52 has a certain elasticity. When there is a tendency for impact between the new boss 4 and the track plate 2, the buffer layer 52 can absorb part of the impact potential energy between the two, thereby reducing damage to the new boss 4 and the track plate 2. By providing the foam layer 51, the buffer layer 52 can be prevented from gradually entering the bottom of the track plate 2 during long-term use, so as to ensure that the buffer layer 52 is always located between the track plate 2 and the new boss 4 to play its due role. Preferably, the height of the foam layer 51 is equal to the bottom surface height of the track plate 2, so that more buffer layers 52 can be filled, so that the buffer layer 52 provides a better buffering effect for the track plate 2 and the new boss 4.

[0058] Furthermore, in one embodiment, the buffer layer 52 includes a resin bag and a resin, and the resin is cast and formed in the resin bag. It is understandable that artificially preparing a resin material with good elasticity is of great significance to alleviating the impact load between the new boss 4 and the track plate 2. The resin is generally formed by weathering after casting, so a resin bag is provided and the resin with fluidity is cast in the resin bag, so that the shape and position of the resin during the forming process can be better controlled, and the resin can be prevented from flowing into unnecessary spaces such as the bottom of the track plate 2, resulting in waste of resin.

[0059] In one embodiment, in the treatment structure provided by the present application, the filling body 5 further includes a waterproof layer (not shown) for preventing rainwater from penetrating into the buffer layer 52. Specifically, the waterproof layer is filled on the buffer layer 52 between the new boss 4 and the track plate 2. By providing the waterproof layer, rainwater can be effectively prevented from entering the buffer material such as resin, thereby causing adverse effects on the performance of the resin, that is, the various performances of the buffer material such as resin are effectively guaranteed.

[0060] In one embodiment, in the governance structure provided by the present application, the new boss 4 includes a steel frame (not shown) and a boss body (not shown). The steel frame is connected to the bottom plate 1, and the boss body is formed by pouring concrete on the steel frame. It can be understood that the reinforced concrete material itself is inexpensive, has high strength after forming, and is convenient and fast when cast on site, so that while ensuring the strength of the new boss 4, it can also ensure the speed of construction and prevent affecting the normal operation of the railway.

[0061] In one embodiment, see Figure 1 and Figure 2 In the governance structure provided by the present application, the number of new bosses 4 in each frame groove 22 is one, and the two ends of the new bosses 4 along the extension direction of the ballastless track are adjacent to the track plate 2. It can be understood that when the size of the frame groove 22 on the track plate 2 is small, only one new boss 4 can be set in the frame groove 22. At this time, the two ends of the new bosses 4 along the extension direction of the ballastless track provide a certain limit effect on the track plate 2 to prevent the track plate 2 from moving.

[0062] Optionally, in one embodiment, see Figure 4 and Figure 5 In the governance structure provided by the present application, the number of new bosses 4 in each frame groove 22 is two, which are respectively arranged on both sides of the frame groove 22 along the extension direction of the ballastless track. It can be understood that when the length of the frame groove 22 of the track plate 2 is large, it is not necessary to arrange new bosses 4 in the entire frame groove 22, but only to arrange new bosses 4 on both sides of the frame groove 22 along the extension direction of the ballastless track to meet the limit function of the track plate 2, thereby saving construction materials and reducing the construction period.

[0063] The second aspect of the embodiment of the present application provides a method for treating ballastless track boss damage, see Figure 6 , governance methods include:

[0064] S10, constructing a new boss 4 connected to the base plate 1 in the frame groove 22 of the track plate 2;

[0065] S20, repairing the original bosses 3 in the open grooves 21 at both ends of the track plate 2.

[0066] Specifically, the frame groove 22 of the track plate 2 is used to construct a new boss 4 in the frame groove 22 to limit the track plate 2. After the new boss 4 is constructed, since the new boss 4 can withstand a certain impact force, the new boss 4 can first withstand the impact load of the track plate 2, and the original boss 3 in the open grooves 21 at both ends of the track plate 2 is repaired. After the original boss 3 is repaired, the new boss 4 and the original boss 3 work together.

[0067] The method for treating the damaged ballastless track boss provided in the embodiment of the present application provides a certain limiting effect on the track plate 2 by setting a new boss 4 in the frame groove 22 of the track plate 2, and then repairing the damaged original boss 3. After the repair is completed, the new boss 4 and the original boss 3 together limit the track plate 2. The treatment method is carried out during the railway's idle time, and the construction is simple and fast. It can effectively solve the problem of damage and failure of the original boss 3, and does not affect the normal operation of the railway.

[0068] In one embodiment, see Figure 7 In the treatment method provided in the present application, S10, the step of constructing a new boss 4 connected to the base plate 1 in the frame groove 22 of the track plate 2, comprises:

[0069] S11, implanting a steel bar body on the bottom plate 1 in the frame groove 22 of the track plate 2;

[0070] S12, fixing the first template in the frame groove 22 to surround the steel bar body;

[0071] S13, pouring concrete in the first template to form a new boss 4;

[0072] S14, removing the first template;

[0073] S15, filling the filling body 5 between the new boss 4 and the track plate 2.

[0074] Specifically, the new boss 4 is formed by pouring concrete on the steel bar body. During pouring, in order to prevent the concrete from flowing into unnecessary spaces such as the bottom of the track plate 2, a first template is provided to limit the flow direction of the concrete and prevent the loss of the concrete.

[0075] Preferably, the steel bar body includes vertical bars (not shown) and stirrups (not shown). Holes are drilled on the base plate 1 in the frame groove 22, and the vertical bars are implanted into the track plate 2 using a reinforcing bar glue, and the stirrups are tied to the vertical bars. Preferably, the diameter of the drilled hole is 32 mm, the depth is 220 mm, the diameter of the vertical bar is 25 mm, the length is 435 mm, and the hardness is 400 HRB. The stirrups are made of steel bars with a diameter of 12 mm and a hardness of 400 HRB. The steel bar body formed in this way has higher strength, so that the strength of the new boss 4 formed after pouring concrete is also higher.

[0076] After pouring concrete, when the concrete is fixed and formed, preferably, after the concrete strength reaches 10 MPa, the first template is removed and the concrete is polished to make the outer surface of the formed concrete smooth. A gap is formed between the new boss 4 and the track plate 2. By filling the filler 5 between the new boss 4 and the track plate 2, the impact load between the track plate 2 and the new boss 4 can be effectively reduced.

[0077] In one embodiment, in the treatment method provided by the present application, S15, the step of filling the filling body 5 between the new boss 4 and the track plate 2, comprises:

[0078] Fill the foam layer 51 on the bottom plate 1 between the new boss 4 and the track plate 2;

[0079] Placing the resin bag on the foam layer 51;

[0080] Pouring resin into the resin bag;

[0081] Apply sealant between the new boss 4 and the track plate 2 for waterproofing.

[0082] Specifically, the resin is cast, and a foam layer 51 is filled on the bottom plate 1 between the new boss 4 and the track plate 2 to prevent the resin from flowing into the bottom of the track plate 2 during the casting process, causing certain waste. In the subsequent use process, in order to prevent rainwater from entering and affecting the performance of the resin, a sealant is applied between the new boss 4 and the track plate 2 to waterproof the resin. Preferably, the sealant is a silicone sealant.

[0083] In one embodiment, see Figure 7 In the treatment method provided in the present application, S20, the step of repairing the original bosses 3 in the open grooves 21 at both ends of the track plate 2, comprises:

[0084] S21, chiseling away the damaged concrete of the original boss 3 and the filling body 5 around the original boss 3;

[0085] S22, inspect and replant the damaged steel bars of the original boss 3;

[0086] S23, installing the second template to surround the original boss 3;

[0087] S24, pouring concrete in the second template to repair the original boss 3;

[0088] S25, removing the second template;

[0089] S26, filling a new filling body 5 around the original boss 3.

[0090] Specifically, before repairing the original boss 3, it is necessary to first chisel out the filling body 5 around the original boss 3 and the damaged concrete of the original boss 3 to facilitate subsequent construction. In the process of chiseling out the damaged concrete of the original boss 3, it is necessary to completely chisel out the damaged concrete and extend a little toward the middle direction of the original boss 3 to completely expose the new surface of the concrete. In the process of replanting the steel bars, it is necessary to adjust the position of the steel bars, extend the steel bars of insufficient length by welding, and replant the steel bars as needed so that the steel bars in the original boss 3 meet the relevant design requirements.

[0091] After installing the second formwork, the remaining concrete on the original boss 3 needs to be sprinkled with water or coated with an interface agent, and then the polymer concrete is configured and poured in proportion. After the concrete solidifies and the strength reaches the relevant requirements, the second module is removed and the solidified concrete is polished and cleaned.

[0092] S26, the step of filling a new filling body 5 around the original boss 3 specifically comprises: firstly installing a foam board and a resin bag at the bottom of the base plate 1, the top surface of the foam board should be higher than or equal to the bottom surface of the track plate 2, and then configuring a resin material with good elasticity in proportion, stirring it evenly and pouring it into the resin bag.

[0093] The various embodiments / implementations provided in this application can be combined with each other without causing any contradiction.

[0094] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A structure for treating ballastless track boss damage, characterized in that: include: Base plate; A track plate, wherein the track plate is an I-type track plate, which is arranged on the bottom plate, and has opening grooves formed at both ends of the track plate, and a frame groove formed between the two ends; The original boss is connected to the bottom plate, is arranged between two adjacent track plates, is located in the space surrounded by two adjacent opening grooves, and is used to limit the track plates adjacent to it; and A new boss is formed in the frame groove in the structure of the track plate itself, and the new boss is connected to the bottom plate, so as to disperse the force borne by the original boss; The number of the new bosses in each frame groove is one, and both ends of the new bosses along the extension direction of the ballastless track are adjacent to the track plate; or, The number of the new bosses in each frame groove is two, which are respectively arranged on both sides of the frame groove along the extending direction of the ballastless track.

2. The governance structure according to claim 1, characterized in that: The treatment structure further includes a filling body, which is filled around the new boss and is located between the new boss and the track plate.

3. The governance structure according to claim 2, characterized in that: The filling body comprises a foam layer and a buffer layer, the foam layer is filled on the bottom plate, the top surface height of the foam layer is equal to the bottom surface height of the track plate, and the buffer layer is filled on the foam layer.

4. The governance structure according to claim 3, characterized in that: The buffer layer comprises a resin bag and a resin, and the resin is cast and formed in the resin bag; and / or, The filling body also includes a waterproof layer for preventing rainwater from penetrating into the buffer layer.

5. The governance structure according to any one of claims 1 to 4, characterized in that: The new boss comprises: A steel frame connected to the base plate; and The boss body is formed by pouring concrete onto the steel reinforcement frame.

6. A method for treating ballastless track boss damage, characterized in that: Utilizing the governance structure described in any one of claims 1 to 5, comprising: A new boss connected to the base plate is formed in the frame groove of the track plate; Repair the original bosses in the open grooves at both ends of the track plate.

7. The treatment method according to claim 6, characterized in that: The steps of constructing a new boss connected to the base plate in the frame groove of the track plate include: Implant the steel bar body on the bottom plate in the track plate frame groove; Fixing the first template in the frame groove to surround the steel bar body; pouring concrete in the first formwork to form the new boss; removing the first template; A filling body is filled between the new boss and the track plate.

8. The treatment method according to claim 7, characterized in that: The step of filling a filling body between the new boss and the track plate comprises: Filling a foam layer on the bottom plate between the new boss and the track plate; placing a resin bag on the foam layer; pouring resin into the resin bag; A sealant is applied between the new boss and the track plate for waterproofing.

9. The treatment method according to claim 6, characterized in that: The steps of repairing the original bosses in the open grooves at both ends of the track plate include: Chiseling away the damaged concrete of the original boss and the filling body around the original boss; Inspect and replant damaged steel bars of the original boss; Install a second template to surround the original boss; Pouring concrete in the second formwork to repair the original boss; removing the second template; A new filling body is filled around the original boss.

Citation Information

Patent Citations

  • Novel slab ballastless track structure