Vertical layered drying preheater
The vertical layered drying preheater uses waste heat gas to preheat raw coal, which solves the problem of agglomeration of raw coal caused by moisture in the rotary kiln, improves product quality and production efficiency, reduces costs, and achieves better results. preheating effect.
Patent Information
- Application Number
- CN202010822875.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-08-17
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2040-08-17
AI Technical Summary
The raw coal in the rotary kiln agglomerates due to moisture, which affects product quality, and the drying process before entering the kiln increases production costs.
A vertical layered drying preheater is designed, which uses waste heat gas to preheat raw coal, including a shell, a feed chute, a material distribution cover, a flow distribution table, a waste heat utilization pipe, a blanking chute and an exhaust gas discharge pipe. The guide ramp and stirring mechanism ensure full contact between the raw coal and the waste heat gas to achieve uniform drying.
It improves the uniformity of product quality and production efficiency, reduces production costs, and achieves better preheating effect, energy saving and environmental protection by making full use of waste heat gas.
Smart Images

Figure CN111928666B_ABST
Abstract
Description
Technical Field
[0001] The invention discloses a vertical layered drying preheater, which belongs to the technical field of preheating and drying of granular material production, and in particular relates to drying and preheating of raw coal before it enters a rotary kiln. Background Art
[0002] The rotary kiln is a widely used kiln for calcining granular materials. After entering the rotary kiln, the material is laid on the inner wall of the rotary kiln, and then high-temperature raw coal gas is introduced into the rotary kiln to calcine the internal granular materials. The initial material is calcined directly after entering the rotary kiln, which is easy to agglomerate due to moisture, and the quality uniformity of the product will be affected due to the different calcination time and contact between the surface and bottom layers. Drying and transferring before entering the rotary kiln will increase production costs. Summary of the invention
[0003] The present invention overcomes the deficiencies of the prior art and aims to solve the following technical problems: providing a vertical layered drying preheater to preheat and dry materials before directly feeding them into a rotary kiln, thereby improving and stabilizing product quality and reducing production costs.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is: a vertical layered drying preheater, including a shell, a feed trough, a distribution cover, a diversion table, a waste heat utilization pipe, a blanking trough and an exhaust gas discharge pipe. The upper part of the shell is provided with a feed trough, and the blanking end of the raw coal conveyor is arranged at the upper entrance of the feed trough. The distribution cover is fixedly hoisted in the feed trough by multiple connecting rods. The distribution cover is a truncated cone type cavity shell structure with a closed upper end and an open lower end. A blocking ring is fixedly installed on the inner wall of the shell corresponding to the lower end edge of the distribution cover. The upper part of the blocking ring is provided with an inclined surface and the bottom end of the inclined surface forms a first blanking ring seam with the lower end of the distribution cover. The diversion table is a truncated cone type cavity shell structure with closed upper and lower ends. The upper part of the diversion table is fixed to the inner lower part of the distribution cover by multiple connecting plates, and a plurality of connecting plates are left between the distribution cover and the diversion table. The supported air outlet gap, the outer edge of the lower end of the diverter table and the lower end of the blocking ring form a second blanking ring seam, and the second blanking ring seam is located below the first blanking ring seam, and a plurality of guide holes are evenly arranged on the inner side of the blocking ring, the upper end of the guide hole corresponds to the first blanking ring seam and the lower end corresponds to the second blanking ring seam, and a conical blanking trough is arranged at the lower part of the shell, and the lower end outlet of the blanking trough is connected to the feeding end of the rotary kiln, one end of the waste heat utilization pipe is connected to the waste heat gas discharge port of the production system, the other end of the waste heat utilization pipe is extended into the blanking trough in the shell and its outlet is aligned with the bottom surface of the diverter table, one end of the exhaust gas discharge pipe is extended into the feeding trough of the shell and is fixed in the inside of the distribution cover, the other end of the exhaust gas discharge pipe is connected to the inlet of the cyclone dust collector, the outlet of the cyclone dust collector is connected to the main fan, and the outlet of the main fan is connected to the desulfurization tower.
[0005] A material guide inclined plate is provided on the inner wall of the middle and lower part of the shell, and the material guide inclined plate is located directly below the second blanking ring seam. A plurality of stirring mechanisms are installed on the shell, and the stirring mechanisms include a conduit, a push block, a push rod and a pressure plate. The conduit is fixed on the inner wall of the shell and its outlet corresponds to the material guide inclined plate. The push rod is movably installed in the conduit, one end of the push rod is fixedly connected to the push block and the other end thereof passes through the outside of the shell and is hinged on the pressure plate. The upper end of the pressure plate is hinged on the outer wall of the shell, and a power push-pull device is provided on the pressure plate.
[0006] A distribution device is installed on the lower end outlet of the material chute, and the distribution device includes a sealing shell, a distribution pipe, an adjusting rod and an adjusting knob. The upper end of the sealing shell is sealed and connected to the raw coal preheater, and the lower end thereof is sealed and connected to the inlet end of the rotary kiln. The upper inlet end of the distribution pipe is sleeved outside the lower end outlet of the raw coal preheater and is hinged to one side of the raw coal preheater. The outlet end of the distribution pipe extends into the interior of the rotary kiln and corresponds to the inner wall of the rotary kiln. One end of the adjusting rod is hinged to the middle part of the distribution pipe, and the other end of the adjusting rod passes through the sealing shell and is fixedly connected to the sealing shell through a nut-type adjusting knob.
[0007] Compared with the prior art, the present invention has the following beneficial effects: the raw coal first enters the preheater before entering the rotary kiln, and is dried and preheated by the gas with waste heat before entering the rotary kiln. The dry material is laid evenly, making the product production quality more balanced and improving the product production quality. The drying preheater fully utilizes and controls the flow direction of the waste heat gas and raw coal particles in multiple pipelines, so that the raw coal is more fully in contact with the waste heat gas, the preheating effect is better, and it is energy-saving and environmentally friendly. BRIEF DESCRIPTION OF THE DRAWINGS
[0008] The present invention will be further described in detail below in conjunction with the accompanying drawings;
[0009] Figure 1 It is a structural schematic diagram of the present invention; DETAILED DESCRIPTION
[0010] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions of the present invention will be clearly and completely described below in combination with the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all the embodiments; based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0011] like Figure 1As shown, the vertical layered drying preheater of the present invention comprises a shell body 1, a feed trough 2, a distribution cover 3, a diversion platform 4, a waste heat utilization pipe 5, a blanking trough 8 and an exhaust gas discharge pipe 6. The upper part of the shell body 1 is provided with a feed trough 2, and the blanking end of the raw coal conveyor is arranged at the upper entrance of the feed trough 2. The distribution cover 3 is fixedly hoisted in the feed trough 2 by a plurality of connecting rods 10. The distribution cover 3 is a truncated cone type cavity shell structure with a closed upper end and an open lower end. A blocking ring 9 is fixedly installed on the inner wall of the shell body 1 corresponding to the lower end edge of the distribution cover 3. The upper part of the blocking ring 9 is provided with an inclined surface, and the bottom end of the inclined surface forms a first blanking ring seam with the lower end of the distribution cover 3. The diversion platform 4 is a truncated cone type cavity shell structure with closed upper and lower ends. The upper part of the diversion platform 4 is fixed to the inner lower part of the distribution cover 3 by a plurality of connecting plates 7, and a plurality of connecting plates 7 are supported between the distribution cover 3 and the diversion platform 4. The air outlet gap, the outer edge of the lower end of the diverter table 4 and the lower end of the blocking ring 9 form a second blanking ring seam, and the second blanking ring seam is located below the first blanking ring seam, and the inner side of the blocking ring 9 is evenly provided with a plurality of guide holes 11, the upper end of the guide hole corresponds to the first blanking ring seam and the lower end corresponds to the second blanking ring seam, the lower part of the shell 1 is provided with a conical blanking trough 8, the lower end outlet of the blanking trough 8 is connected to the feed end of the rotary kiln, one end of the waste heat utilization pipe 5 is connected to the waste heat gas discharge port of the production system, the other end of the waste heat utilization pipe 5 extends into the blanking trough 8 in the shell 1 and its outlet is aligned with the bottom surface of the diverter table 4, one end of the exhaust gas discharge pipe 6 extends into the feed trough 2 of the shell 1 and is fixed in the inside of the distribution cover 3, the other end of the exhaust gas discharge pipe 6 is connected to the inlet of the cyclone dust collector, the outlet of the cyclone dust collector is connected to the main fan, and the outlet of the main fan is connected to the desulfurization tower.
[0012] A material guide inclined plate 12 is provided on the inner wall of the middle and lower part of the shell 1, and the material guide inclined plate 12 is located directly below the second blanking ring seam. A plurality of stirring mechanisms 13 are installed on the shell 1, and the stirring mechanism 13 includes a conduit, a push block, a push rod and a pressure plate. The conduit is fixed on the inner wall of the shell 1 and its outlet corresponds to the material guide inclined plate 12. The push rod is movably installed in the conduit, one end of the push rod is fixedly connected to the push block and the other end thereof passes through the outside of the shell 1 and is hinged on the pressure plate. The upper end of the pressure plate is hinged on the outer wall of the shell 1, and a power push-pull device is provided on the pressure plate.
[0013] A distribution device 14 is installed on the lower end outlet of the drop chute 8, and the distribution device 14 includes a sealing shell, a distribution pipe, an adjusting rod and an adjusting knob. The upper end of the sealing shell is sealed and connected to the raw coal preheater, and the lower end thereof is sealed and connected to the inlet end of the rotary kiln. The upper inlet end of the distribution pipe is sleeved outside the lower end outlet of the raw coal preheater and hinged on one side of the raw coal preheater. The outlet end of the distribution pipe extends into the interior of the rotary kiln and corresponds to the inner wall of the rotary kiln. One end of the adjusting rod is hinged to the middle part of the distribution pipe, and the other end of the adjusting rod passes through the sealing shell and is fixedly connected to the sealing shell through a nut-type adjusting knob.
[0014] Working process: The raw coal conveyor 8 delivers the raw coal into the feed trough 2 of the present invention, the raw coal falls on the distribution cover 3 in the feed trough 2 and slides along the first drop ring seam to the outer edge of the bottom surface of the diversion platform 4, and then falls on the guide inclined plate through the second drop ring seam. The raw coal on the guide inclined plate slowly slides to the drop trough 8 and covers a certain thickness on its inner wall. The raw coal drop state is as follows: Figure 1 As shown, the waste heat utilization pipe 5 introduces the waste heat gas from the production system into the blanking chute 8. After the waste heat gas hits the bottom surface of the diverter table 4, it is diverted to the surroundings to dry and preheat the raw coal on the guide inclined plate 12. At the same time, it will fill the inside of the blanking chute 8 to preheat and dry the raw coal on its inner wall. After the air pressure reaches a certain value, the waste heat gas will find a breakthrough. Since the thickness of the raw coal is the smallest at the guide hole 11, the waste heat gas will enter the guide hole 11. Similarly, when the waste heat gas leaves the guide hole 11, the next breakthrough found is the air outlet gap supported by multiple connecting plates 7. Finally, the waste heat gas completes the preheating work and becomes waste gas, which is discharged from the waste gas discharge pipe 6 above and is processed and discharged by a cyclone dust collector and a desulfurization tower, etc., and the preheated and dried material is sent into the rotary kiln for firing through the adjusted distribution device.
[0015] After the raw coal falls on the guide inclined plate 12, the control system controls the pressure plate of the stirring mechanism 13 to move up and down repeatedly and pushes and pulls the push block repeatedly through the push rod, thereby stirring the raw coal on the guide inclined plate 12, making it more fully contacted with the waste heat gas and achieving better preheating and drying effect.
[0016] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A vertical layered drying preheater, characterized in that: The invention comprises a shell (1), a feed trough (2), a material distribution cover (3), a diversion platform (4), a waste heat utilization pipe (5), a material drop trough (8) and an exhaust gas discharge pipe (6). The upper part of the shell (1) is provided with a feed trough (2). The material drop end of the raw coal conveyor is arranged at the upper entrance of the feed trough (2). The feed trough (2) is fixedly hoisted with a material distribution cover (3) via a plurality of connecting rods (10). The material distribution cover (3) is a truncated cone-shaped hollow shell structure with a closed upper end and an open lower end. A blocking ring (9) is fixedly mounted on the inner wall of the body (1) corresponding to the lower edge of the material distribution cover (3); the upper part of the blocking ring (9) is provided with an inclined surface, and the bottom end of the inclined surface and the lower end of the material distribution cover (3) form a first blanking ring gap; the flow distribution platform (4) is a truncated cone-shaped cavity shell structure with both upper and lower ends closed; the upper part of the flow distribution platform (4) is fixed to the inner lower part of the material distribution cover (3) through a plurality of connecting plates (7); and a plurality of connecting plates (7) are left between the material distribution cover (3) and the flow distribution platform (4) to support the material distribution cover (3). The outer edge of the lower end of the flow divider (4) and the lower end of the blocking ring (9) form a second blanking annular gap, and the second blanking annular gap is located below the first blanking annular gap. The inner side of the blocking ring (9) is evenly provided with a plurality of guide holes (11), the upper ends of the guide holes correspond to the first blanking annular gap and the lower ends correspond to the second blanking annular gap. The lower part of the shell (1) is provided with a conical blanking trough (8), the lower end outlet of the blanking trough (8) is connected to the feed end of the rotary kiln, and the waste heat utilization pipe One end of the waste heat utilization pipe (5) is connected to the waste heat gas discharge outlet of the production system, the other end of the waste heat utilization pipe (5) extends into the material drop chute (8) in the shell (1) and its outlet is aligned with the bottom surface of the diverter table (4), one end of the waste gas discharge pipe (6) extends into the material feed chute (2) of the shell (1) and passes through and is fixed inside the material distribution cover (3), the other end of the waste gas discharge pipe (6) is connected to the inlet of the cyclone dust collector, the outlet of the cyclone dust collector is connected to the main fan, and the outlet of the main fan is connected to the desulfurization tower; A material guide inclined plate (12) is provided on the inner wall of the middle and lower part of the shell (1), and the material guide inclined plate (12) is located directly below the second blanking annular seam. A plurality of stirring mechanisms (13) are installed on the shell (1), and the stirring mechanisms (13) include a conduit, a push block, a push rod and a pressure plate. The conduit is fixed on the inner wall of the shell (1) and its outlet corresponds to the material guide inclined plate (12). The push rod is movably installed in the conduit, one end of the push rod is fixedly connected to the push block and the other end thereof passes through the outside of the shell (1) and is hinged to the pressure plate. The upper end of the pressure plate is hinged to the outer wall of the shell (1), and a power push-pull device is provided on the pressure plate. A material distribution device (14) is installed on the lower outlet of the material drop chute (8).