Railway rescue traction lifting platform
By designing a traction and lifting platform for railway rescue, using tracks and traction mechanisms to achieve rapid transfer and transportation of construction equipment, the problems of timeliness and road conditions limitations in the existing technology are solved, and the rapid ability of railway construction equipment to go up and down is improved and rescue efficiency.
Patent Information
- Application Number
- CN202010807624.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-08-12
- Publication Date
- 2024-12-20
- Estimated Expiration
- 2040-08-12
AI Technical Summary
In the event of railway construction equipment failure, the road conditions and equipment timeliness of rescue equipment transportation and rescue sites are high. However, since most construction sites are far away from railway stations, it is difficult to meet the requirements, especially in mountainous or remote areas, and construction equipment is not allowed to be long distances. Driving to avoid damage to the rails, resulting in insufficient rescue time and affecting the normal driving of the railway.
A traction and lifting platform for railway rescue is designed, including tracks, traction mechanisms, walking devices and folding leg lifting mechanisms. It quickly transfers construction equipment through its own power, and uses railway flatbed vehicles to achieve rapid up-and-down railway line transportation and emergency rescue. Large traction force and folding leg lifting mechanism meet the management requirements of railway locomotives.
It realizes the rapid transfer of construction equipment between railway flatbed trucks and railway lines, which is simple and does not damage the rails. It has automatic rapid transportation and emergency rescue capabilities, meets the width requirements of railway locomotive management, and improves the speed and efficiency of rescue.
Smart Images

Figure CN111960326B_ABST
Abstract
Description
Technical field:
[0001] The present invention belongs to the technical field of engineering machinery, and in particular, relates to a traction lifting platform for railway rescue. Background technology:
[0002] At present, small-scale railway construction and maintenance equipment has replaced manpower on the railway. The weight of these equipment ranges from a few tons to dozens of tons. The transfer of maintenance and construction equipment from the ground to the rails requires a transition pavement, the construction of a transition platform, or the finding of a nearby station level crossing. When the construction equipment fails on the railway and stops, it is necessary to find lifting equipment to lift the faulty equipment away from the railway. When it is close to the station, the steel wheel brake can be released for a short distance traction to enter the station auxiliary road.
[0003] However, the existing technology has high requirements on the transportation and rescue environment of construction equipment, the road conditions at the rescue site, and the timeliness of rescue equipment, and has great limitations. Most railway maintenance construction sites are far away from railway stations or level crossings, especially in mountainous areas or remote areas, which makes it difficult to meet the requirements; in addition, construction equipment is not allowed to travel and tow long distances on the railway line to avoid damage to the rails. Therefore, when construction equipment fails on the railway line, the railway's window period (maintenance time) is short, generally about 2 hours, the rescue conditions are poor, and there is insufficient time, which causes inconvenience to the normal operation of the railway. Summary of the invention:
[0004] The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a traction lifting platform for railway rescue, which can cooperate with a railway flatbed car to transport construction equipment, assist in going online and perform emergency rescue operations.
[0005] In order to achieve the above object, the present invention is implemented by adopting the following technical solutions:
[0006] A traction lifting platform for railway rescue comprises a platform, on which are arranged tracks, a traction mechanism, a running device, a folding leg lifting mechanism and a control system, wherein the control system is respectively connected with the traction mechanism, the running device and the folding leg lifting mechanism.
[0007] Preferably, the platform comprises a frame body plate, on which a leg mounting seat, a top plate, a pulley seat and a cylinder seat are provided.
[0008] Preferably, the traction mechanism includes an oil cylinder, an upper slide rail, a bottom slide rail, a front pulley mechanism and a rear pulley mechanism, a slidable hook slide is provided on the upper slide rail, a slidable movable pulley seat is provided on the bottom slide rail, the cylinder body of the oil cylinder is installed on the oil cylinder seat, the piston rod end of the oil cylinder is connected to the movable pulley seat, the front pulley mechanism includes a fixed pulley A, a wire rope A, a fixed pulley D and a movable pulley, the wire rope A is installed on the hook slide, the fixed pulley A, the movable pulley, the fixed pulley D and the piston rod of the oil cylinder in sequence, and the movable pulley is installed on the movable pulley seat; the rear pulley mechanism includes a wire rope B, a fixed pulley B and a fixed pulley C, the wire rope B is installed on the hook slide, the fixed pulley C, the movable pulley, the fixed pulley B and the movable pulley seat in sequence.
[0009] Preferably, the pulley seat comprises a pulley seat A and a pulley seat B, the fixed pulley A is mounted on the pulley seat A, and the fixed pulley C is mounted on the pulley seat B.
[0010] Preferably, the walking device includes an active walking mechanism and a driven walking mechanism, the active walking mechanism includes a walking motor, a small sprocket and a wheel axle, the walking motor is provided with a large sprocket, the large sprocket is connected to the small sprocket through a roller chain, and the small sprocket is installed on the wheel axle; the driven walking mechanism includes a steel wheel and a shaft, and the steel wheel is rotatably installed on the shaft through a bearing.
[0011] Preferably, the folding leg lifting mechanism includes a telescopic leg, a leg frame and a leg cylinder. The telescopic leg can be slidably installed in the leg frame. The leg frame is hingedly connected to the frame main body plate through a pin shaft. The piston rod of the leg cylinder is hingedly connected to the lower end of the telescopic leg, and the cylinder body of the leg cylinder is hingedly connected to the leg frame. A locking mechanism is provided between the leg frame and the frame main body plate.
[0012] Preferably, the locking mechanism comprises a locking rod, and a locking rod mounting seat which is mounted in cooperation with the locking rod is also provided on the frame main body plate.
[0013] Preferably, the locking mechanism includes a rocker arm, a pull rod and a double-acting cylinder, the cylinder body of the double-acting cylinder is hingedly connected to the frame main body plate, the piston rod of the double-acting cylinder is hingedly connected to the rocker arm and the pull rod, the pull rod is also hingedly connected to the leg frame, and the pull rod is also hingedly connected to the frame main body plate.
[0014] Preferably, a ramp is also provided on the frame body plate, and the ramp is connected to the track.
[0015] Preferably, a limiting plate is provided at the end of the track.
[0016] Compared with the prior art, the present invention has the following beneficial effects:
[0017] 1. The present invention can realize rapid transfer of construction equipment between the railway flatbed car and the railway line by its own power, and is not affected by the construction location. It is simple and rapid, and will not cause scratches to the rails;
[0018] 2. With the help of the flatbed truck on the railway, the present invention can automatically and quickly transfer the construction equipment to the flatbed truck, so as to realize the rapid transportation of the construction equipment on and off the railway line and emergency rescue; and the present invention has a large traction force, and can pull the equipment to slide or roll on the track in both directions. The width of the folded outrigger lifting mechanism does not exceed the width of the flatbed truck by 3m, which meets the requirements of railway locomotive management, that is, the cargo on the flatbed truck does not exceed the outer contour of the flatbed truck when it is moving;
[0019] 3. The structure of connecting the ramp and the railway track allows construction equipment to move up and down the railway quickly. Description of the drawings:
[0020] Figure 1 It is a structural schematic diagram of the present invention;
[0021] Figure 2 It is a structural schematic diagram of the platform in the present invention (without the top plate);
[0022] Figure 3 It is a structural schematic diagram of the platform in the present invention (with a top plate);
[0023] Figure 4 It is a front view of the traction mechanism in the present invention;
[0024] Figure 5 for Figure 4 A partial enlarged view of the K in the middle;
[0025] Figure 6 for Figure 4 A partial enlarged view of the G in the middle;
[0026] Figure 7 A top view of the traction mechanism of the present invention;
[0027] Figure 8 A bottom view of the traction mechanism of the present invention;
[0028] Fig. 9 It is a structural schematic diagram of the walking device in the present invention;
[0029] Fig.10 for Fig. 9 Sectional view of AA in the middle;
[0030] Fig.11 for Fig. 9 Cross-sectional view of the middle BB;
[0031] Fig.12 It is a structural schematic diagram of the folding leg lifting mechanism in the present invention;
[0032] Fig.13 It is a structural schematic diagram of the locking mechanism in Example 3 of the present invention;
[0033] Fig.14 It is a structural schematic diagram of the control system in the present invention;
[0034] Fig.15 It is a structural schematic diagram of the locking rod in the present invention;
[0035] Fig.16 It is a structural schematic diagram of the locking mechanism in Example 4 of the present invention;
[0036] Fig.17 It is the hydraulic principle diagram of the control system in the present invention;
[0037] Fig.18 This is a reference diagram of the present invention when it is installed and used.
[0038] In the figure: 1, platform; 2, track; 3, traction mechanism; 4, walking device; 5, folding leg lifting mechanism; 6, control system; 7, frame body plate; 8, rectangular tube A; 9, rectangular tube B; 10, bottom plate; 11, locking rod mounting seat; 12, leg mounting seat; 13, ramp; 14, pulley seat A; 15, cylinder seat; 16, channel steel; 17, top plate; 18, limit plate; 19, fixed pulley A; 20, wire rope A; 21, cylinder; 22, wire rope B; 23, movable pulley seat; 24, fixed pulley B; 25, fixed pulley C; 26, hook slide plate; 27, upper slide rail; 2 8. Fixed pulley D; 29. Bottom slide rail; 30. Movable pulley; 31. Motor bracket; 32. Travel motor; 33. Large sprocket; 34. Roller chain; 35. Small sprocket; 36. Wheel axle; 37. Steel wheel; 38. Shaft; 39. Bearing; 40. Telescopic leg; 41. Outrigger frame; 42. Outrigger cylinder; 43. Pin shaft; 44. Locking rod; 45. Pulley seat B; 46. Battery; 47. Electric control reversing valve; 48. Motor; 49. Coupling; 50. Working pump; 51. Synchronous valve; 52. Hydraulic oil tank; 53. Hydraulic lock; 54. Rocker arm; 55. Pull rod; 56. Double-acting cylinder. Specific implementation method:
[0039] The present invention will be further described below through specific embodiments in conjunction with the accompanying drawings.
[0040] Embodiment 1:
[0041] like Figure 1As shown, a traction lifting platform for railway rescue includes a platform 1, on which a track 2, a traction mechanism 3, a walking device 4, a folding leg lifting mechanism 5 and a control system 6 are provided, and the control system 6 is connected to the traction mechanism 3, the walking device 4 and the folding leg lifting mechanism 5 respectively.
[0042] Embodiment 2:
[0043] A traction lifting platform for railway rescue, such as Figure 2 and Figure 3 As shown, the platform 1 includes a frame main plate 7, which includes a rectangular tube A8, a rectangular tube B9, a bottom plate 10 and a channel steel 16. The rectangular tube A8, the rectangular tube B9, the bottom plate 10 and the channel steel 16 form a frame structure with sufficient bearing capacity. A leg mounting seat 12, a top plate 17, a pulley seat and a cylinder seat 15 are welded to the frame main plate 7.
[0044] Platform 1 is a mounting platform for other equipment and a carrier for transporting rescue equipment. Its width is less than the maximum width of a flatbed truck, 3000 mm, and its length is in accordance with the needs of transporting rescue equipment. Track 2 is welded on platform 1, and its width is consistent with that of a railway track.
[0045] like Figure 4-8 As shown, the traction mechanism 3 includes an oil cylinder 21, an upper slide rail 27, a bottom slide rail 29, a front pulley mechanism and a rear pulley mechanism, and the oil cylinder 21, the upper slide rail 27, the bottom slide rail 29, the front pulley mechanism and the rear pulley mechanism are all installed on the top plate 17, the upper slide rail 27 is provided with a hook slide plate 26 that can slide forward and backward, and the bottom slide rail 29 is provided with a movable pulley seat 23 that can slide forward and backward. The cylinder body of the oil cylinder 21 is installed on the oil cylinder seat 15, and the piston rod end of the oil cylinder 21 is hingedly connected to the movable pulley seat 23. The front pulley mechanism includes a fixed pulley A19, a wire rope A20, a fixed pulley D28 and a movable pulley 30. The wire rope A20 is sequentially installed on the hook slide plate 26, the fixed pulley A19, the movable pulley Wheel 30, fixed pulley D28 and the piston rod of the cylinder 21, that is, the two ends of the wire rope A20 are respectively installed and fixed on the hook slide 26 and the piston rod of the cylinder 21, and the middle part passes through the fixed pulley A19, the movable pulley 30 and the fixed pulley D28 in sequence, and the movable pulley 30 is installed on the movable pulley seat 23; the rear pulley mechanism includes a wire rope B22, a fixed pulley B24 and a fixed pulley C25, and the wire rope B22 is installed on the hook slide 26, the fixed pulley C25, the movable pulley 30, the fixed pulley B24 and the movable pulley seat 23 in sequence, that is, the two ends of the wire rope B22 are respectively installed and fixed on the hook slide 26 and the movable pulley seat 23, and the middle part passes through the fixed pulley C25, the movable pulley 30 and the fixed pulley B24 in sequence.
[0046] The pulley seat includes a pulley seat A14 and a pulley seat B45, the fixed pulley A19 is mounted on the pulley seat A14, and the fixed pulley C25 is mounted on the pulley seat B45. The piston rod of the oil cylinder 21 extends to push the pulley seat 23 to slide in the bottom slide rail 29, and at the same time, the traction hook slide plate 26 slides forward along the upper slide rail 27; when the oil cylinder 21 contracts, the traction hook slide plate 26 slides backward, and the traction distance of the hook slide plate 26 is three times the stroke of the oil cylinder 21. Figure 7 As shown, in order to meet the needs of large traction force and safety factor, two cylinders 21 and four steel wire ropes A20 and steel wire ropes B22 are used for traction. Large traction force can be easily achieved through the cylinder 21. It is placed at the lower part of the platform 1 and is more compact in structure. In order to facilitate traction, the height of the present invention should not be too high. In order to meet the chassis passability of the construction equipment at the rear, a large traction device should not be installed.
[0047] like Figure 9-11 As shown, the walking device 4 includes an active walking mechanism and a driven walking mechanism, the active walking mechanism includes a walking motor 32, a small sprocket 35 and an axle 36, the walking motor 32 is provided with a large sprocket 33, the large sprocket 33 is transmission-connected with the small sprocket 35 through a roller chain 34, the small sprocket 35 is mounted on the axle 36, the axle 36 is rotatably mounted on the frame main plate 7, the walking motor 32 is mounted on the motor bracket 31, the motor bracket 31 is mounted on the frame main plate 7; the driven walking mechanism includes a steel wheel 37 and a shaft 38, the steel wheel 37 is rotatably mounted on the shaft 38 through a bearing 39, and the shaft 38 is rotatably mounted on the frame main plate 7.
[0048] The front travel is driven by a travel motor 32 installed on a motor bracket 31 and rotated under the drive of hydraulic oil. The large sprocket 33, roller chain 34, and small sprocket 35 transmit mechanical energy to the axle 36 to realize travel on the rails; the rear travel is a follow-up device and does not provide power.
[0049] like Fig.12 As shown, the folding leg lifting mechanism 5 includes a telescopic leg 40, a leg frame 41 and a leg cylinder 42. The telescopic leg 40 can be slidably installed in the leg frame 41. The leg frame 41 is hingedly connected to the frame body plate 7 through a pin 43. The leg frame 41 can rotate outward around the pin 43. To meet railway management regulations, when it is turned close to the side of the platform 1, the outer width of the leg frame 41 is within the width of the flatbed car, generally not exceeding 3200mm.
[0050] The piston rod of the leg cylinder 42 is hingedly connected to the lower end of the telescopic leg 40, and the cylinder body of the leg cylinder 42 is hingedly connected to the upper end of the leg frame 41; a locking mechanism is provided between the leg frame 41 and the frame body plate 7. The leg frame 41 adopts a folding mechanism. When the leg frame 41 is opened, it exceeds the width of the flatbed truck by 3m, and when folded, it is within the width of the platform 1 by 3m. The folding structure is simple and easy to ensure strength.
[0051] The folding leg lifting mechanism 5 needs to be arranged on both sides of the platform 1 to ensure working requirements, and the number can be 4, 6 or 8 symmetrical. The other parts are the same as those in the first embodiment.
[0052] Embodiment 3:
[0053] A traction lifting platform for railway rescue, the locking mechanism includes a locking rod 44, and a locking rod mounting seat 11 is provided on the frame body plate 7 to cooperate with the locking rod 44. Fig.13 As shown, the folding leg lifting mechanism 5 performs folding and lifting actions and is symmetrically installed at the front and rear parts of the platform 1 through the pin shaft 43 and the locking rod 44. The telescopic leg 40 is driven to slide inside the leg frame 41 under the extension and retraction of the leg cylinder 42; the leg frame 41 can be in an open or folded state as needed and locked with the locking rod 44.
[0054] The locking type of the folding leg lifting mechanism 5 is a rigid pull rod. Fig.15 The pins at both ends of the locking rod 44 are inserted into the mounting holes of the locking rod mounting seat 11 for locking, and the structure is simple, but manual operation is required for installation.
[0055] Embodiment 4:
[0056] like Fig.16 As shown, a traction lifting platform for railway rescue, the locking mechanism includes a rocker arm 54, a pull rod 55 and a double-acting cylinder 56, the cylinder body of the double-acting cylinder 56 is hingedly connected to the frame main body plate 7, the piston rod of the double-acting cylinder 56 is hingedly connected to the rocker arm 54 and the pull rod 55 at the same time, the pull rod 55 is also hingedly connected to the leg frame 41, and the pull rod 55 is also hingedly connected to the frame main body plate 7.
[0057] The locking mechanism is a six-link articulated mechanism, and the folding and opening of the leg frame 41 is realized by the extension and contraction of the double-acting oil cylinder 56, which does not require manual operation and installation, and is convenient and fast.
[0058] Embodiment 5:
[0059] A traction lifting platform for railway rescue, wherein the frame main body plate 7 is also provided with a ramp 13, the end of the track 2 is installed on the ramp 13, the ramp 13 has a certain angle, and is connected with the railway track, so that the steel wheels of the construction equipment can slide or roll from the railway track to the upper part of the platform 1 with the help of the track 2 under the traction of the traction mechanism 3; the front part of the track 2 is provided with a limit plate 18, which is installed at the upper end of the frame main body plate 7 to limit the front steel wheels of the construction equipment to prevent them from sliding. Fig.14As shown, the control system 6 includes a battery 46, an electronically controlled reversing valve 47, a motor 48, a working pump 50, a synchronization valve 51, a hydraulic oil tank 52 and a hydraulic lock 53. The battery 46 is connected to the motor 48, the motor 48 is connected to the working pump 50 through a coupling 49, the working pump 50 is connected to the hydraulic oil tank 52 and the electronically controlled reversing valve 47 respectively, and the electronically controlled reversing valve 47 is connected to the outrigger cylinder 42, the travel motor 32 and the cylinder 21 respectively through the synchronization valve 51.
[0060] like Fig.17 As shown, the control system 6 provides power and control for the traction lift, and the battery 46 provides power to the motor 48 to rotate, and drives the working pump 50 through the coupling 49. The working pump 50 sucks oil from the hydraulic oil tank 52 and pumps out the hydraulic oil to the electronically controlled reversing valve 47. After reversing operation, it can reach each synchronization valve 51 (i.e., diversion and collection valve) and then to the actuator. The function of the synchronization valve 51 is to ensure the consistency of the action when the leg frame 41 is raised or lowered, and the consistency of the wheel axle 36 when walking. The function of the hydraulic lock 53 is to ensure that the leg cylinder 42 does not sink when the leg cylinder 42 is in a stable state. The purpose of using the electronically controlled reversing valve 47 is to realize remote control of the traction lift. The rechargeable battery 46 can provide electricity to realize the transfer of construction equipment between the railway and the flatbed car. The other parts are the same as Example 3 or Example 4.
[0061] like Fig.18 As shown, when the construction equipment needs to be transported or fails on the railway line, the operation sequence of the present invention is:
[0062] 1. The present invention is transported to the line where the construction equipment stops by a railway flatbed car, the folding legs of the present invention are opened, the leg frame 41 exceeds the width of the flatbed car, locked with a locking rod 44, the leg cylinder 42 extends and falls on the ballast or sleepers, the platform 1 drives it to rise as a whole until it leaves the flatbed car in height, and the flatbed car drives away and leaves the present invention;
[0063] 2. The outrigger cylinder 42 is retracted, and the platform 1 is lowered until the axle 36 falls on the rail, and the present invention is driven to the front of the construction equipment;
[0064] 3. Use a traction rope to connect the construction equipment and the hook on the hook slide 26 of the traction mechanism 3, and the traction mechanism 3 is operated to pull the construction equipment from the rail along the track 2 to the upper part of the platform 1;
[0065] 4. The ballast under the outriggers 41 is padded, the outriggers 41 are extended again, and the platform 1 is raised until the height is higher than the height of the flatbed truck;
[0066] 5. The flatbed truck drives to the lower part of the platform 1, and the outriggers 41 are operated to lower the platform 1, and the axle 36 of the platform 1 falls on the track of the flatbed truck;
[0067] 6. The outriggers 41 are folded into the body of the flatbed truck and locked with the locking rod 44. If it is necessary to pass through a tunnel or the construction equipment is super-high on the lifting platform, the traction mechanism 3 and the track 1 can be used to tow the equipment again to the track of the flatbed truck and separate it from the lifting platform. The lifting platform and the construction equipment are fixed, and the flatbed truck transports the construction equipment to a suitable location.
[0068] The method for transporting construction equipment from the flatbed truck to the railway for construction is reversed from the above method.
Claims
1. A traction lifting platform for railway rescue, characterized in that: The platform (1) comprises a track (2), a traction mechanism (3), a walking device (4), a folding leg lifting mechanism (5) and a control system (6), wherein the control system (6) is respectively connected to the traction mechanism (3), the walking device (4) and the folding leg lifting mechanism (5); The platform (1) comprises a frame body plate (7), on which a leg mounting seat (12), a top plate (17), a pulley seat and a cylinder seat (15) are provided; The traction mechanism (3) comprises an oil cylinder (21), an upper slide rail (27), a bottom slide rail (29), a front pulley mechanism and a rear pulley mechanism. A slidable hook slide plate (26) is provided on the upper slide rail (27), and a slidable movable pulley seat (23) is provided on the bottom slide rail (29). The cylinder body of the oil cylinder (21) is mounted on the oil cylinder seat (15), and the end of the piston rod of the oil cylinder (21) is connected to the movable pulley seat (23). The front pulley mechanism comprises a fixed pulley A (19), a steel wire rope A (20), a fixed pulley D (28) and a movable pulley. The rear pulley mechanism comprises a steel wire rope B (22), a fixed pulley B (24) and a fixed pulley C (25), wherein the steel wire rope B (22) is sequentially mounted on the hook slide (26), the fixed pulley A (19), the movable pulley (30), the fixed pulley D (28) and the piston rod of the oil cylinder (21), and the movable pulley (30) is mounted on the movable pulley seat (23); the rear pulley mechanism comprises a steel wire rope B (22), a fixed pulley B (24) and a fixed pulley C (25), wherein the steel wire rope B (22) is sequentially mounted on the hook slide (26), the fixed pulley C (25), the movable pulley (30), the fixed pulley B (24) and the movable pulley seat (23).
2. The railway rescue traction lifting platform according to claim 1, characterized in that: The pulley seat comprises a pulley seat A (14) and a pulley seat B (45), the fixed pulley A (19) is mounted on the pulley seat A (14), and the fixed pulley C (25) is mounted on the pulley seat B (45).
3. The railway rescue traction lifting platform according to claim 2, characterized in that: The walking device (4) comprises an active walking mechanism and a driven walking mechanism, wherein the active walking mechanism comprises a walking motor (32), a small sprocket (35) and a wheel axle (36), wherein a large sprocket (33) is provided on the walking motor (32), wherein the large sprocket (33) is connected to the small sprocket (35) by a roller chain (34), and the small sprocket (35) is mounted on the wheel axle (36); wherein the driven walking mechanism comprises a steel wheel (37) and a shaft (38), wherein the steel wheel (37) is rotatably mounted on the shaft (38) by a bearing (39).
4. The railway rescue traction lifting platform according to claim 3 is characterized in that: The folding leg lifting mechanism (5) comprises a telescopic leg (40), a leg frame (41) and a leg cylinder (42); the telescopic leg (40) is slidably mounted in the leg frame (41); the leg frame (41) is hingedly connected to the frame body plate (7) via a pin shaft (43); the piston rod of the leg cylinder (42) is hingedly connected to the lower end of the telescopic leg (40); the cylinder body of the leg cylinder (42) is hingedly connected to the leg frame (41); and a locking mechanism is provided between the leg frame (41) and the frame body plate (7).
5. The railway rescue traction lifting platform according to claim 4, characterized in that: The locking mechanism comprises a locking rod (44), and a locking rod mounting seat (11) which is mounted in cooperation with the locking rod (44) is also provided on the frame main body plate (7).
6. The railway rescue traction lifting platform according to claim 5, characterized in that: The locking mechanism comprises a rocker arm (54), a pull rod (55) and a double-acting cylinder (56); the cylinder body of the double-acting cylinder (56) is hingedly connected to the frame main body plate (7); the piston rod of the double-acting cylinder (56) is hingedly connected to the rocker arm (54) and the pull rod (55); the pull rod (55) is also hingedly connected to the leg frame (41); and the pull rod (55) is also hingedly connected to the frame main body plate (7).
7. The railway rescue traction lifting platform according to any one of claims 1 to 6, characterized in that: The frame body plate (7) is also provided with a ramp (13), and the ramp (13) is connected to the track (2).
8. The railway rescue traction lifting platform according to claim 7, characterized in that: A limiting plate (18) is provided at the end of the track (2).