A modular factory prefabrication construction method for laboratory electromechanical systems
Through the modular factory prefabricated construction method, 3D digital modeling software and BIM technology are used to optimize the pipeline layout and modular design of the laboratory's electromechanical system, solving the problems of difficult control of traditional construction quality and environmental pollution, and achieving an efficient and environmentally friendly construction process. , reducing costs and construction time.
Patent Information
- Application Number
- CN202010916077.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-09-03
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2040-09-03
AI Technical Summary
The construction quality of traditional laboratory electromechanical systems is difficult to control, with low efficiency and high cost. On-site cutting and welding operations cause noise, light pollution, water pollution, dust and other problems to the environment.
Adopting modular factory prefabricated construction methods, using 3D digital modeling software for three-dimensional modeling and pipeline optimization, dividing standard and special modules, prefabricating factories to produce modular systems, rapid hoisting on site, and using BIM technology and REVIT software for refined processing and positioning Marking, reducing on-site cutting and welding operations.
It improves construction quality and precision, shortens the construction cycle, reduces environmental pollution and labor intensity, saves materials and energy, and significantly reduces construction costs.
Smart Images

Figure CN112052501B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of laboratory buildings, and in particular relates to a modular factory prefabrication construction method for a laboratory electromechanical system. Background Art
[0002] The construction of laboratory electromechanical systems mainly includes the processing and installation of water pipes, cables, air conditioning and ventilation pipes and other pipelines in the laboratory and their installation and fixtures. In the current traditional technology, most projects are processed by on-site production methods. Construction workers cut, weld and assemble raw materials such as pipes and steel on the construction site, and then measure and locate them on site before installing them on the laboratory building. The problems with this construction method include:
[0003] (1) Construction quality is difficult to control: The installation personnel are required to have high technical skills, such as cutting, welding, surveying and mapping. However, the laboratory construction industry is a niche industry, and the construction level of practitioners is generally not high;
[0004] (2) Low construction efficiency, difficult to control progress, long construction period and high construction cost;
[0005] (3) Carrying out a large amount of cutting and welding operations on site has a great impact on the environment, and will generate a lot of noise, light pollution, water pollution, dust and other problems. Summary of the invention
[0006] The purpose of the present invention is to provide a modular factory prefabrication construction method for a laboratory electromechanical system, aiming to solve the above-mentioned technical problems.
[0007] The present invention is implemented as follows: a method for modular factory prefabrication of a laboratory electromechanical system, the method comprising the following steps:
[0008] S1. Use 3D digital modeling software to perform three-dimensional modeling of the laboratory electromechanical system;
[0009] S2. Optimize the layout of the modeled electromechanical system to form a "standard + variable" pipeline layout mode and divide it into modules;
[0010] S3. Export the parts drawings and assembly drawings of each module according to the divided electromechanical system modules and send them to the prefabrication factory;
[0011] S4. The prefabrication factory builds the mechanical and electrical system frame in the laboratory according to the positioning diagram on the receiving drawing and makes the modules divided by each mechanical and electrical system according to the assembly drawing;
[0012] S5. The prefabrication factory transports the manufactured electromechanical system modules to the site for splicing and hoisting.
[0013] A further technical solution of the present invention is: the step S1 further includes the following steps:
[0014] S11, use the pipeline of REVIT software laboratory to carry out refined modeling processing;
[0015] S12. Set the laboratory's exhaust duct and fresh air duct at the same height and in a subdivided relationship to form a ladder-shaped layout;
[0016] S13. Adjust the pipelines in the suspended ceiling and layer them in the upper and lower order of the bridge, air duct and water pipe.
[0017] A further technical solution of the present invention is: the multiple standard modules and multiple special modules divided in step S2, the standard modules include side table electromechanical servo modules, fume hood electromechanical servo modules and central table electromechanical servo modules, the special modules include servo modules with exhaust main duct, aisle area servo modules and spare area servo modules.
[0018] A further technical solution of the present invention is: in step S3, REVIT software is used to locate and mark each module of the several point system in the model.
[0019] A further technical solution of the present invention is: in step S3, the pipelines inside each module are dimensioned and the construction requirements are marked, and a two-dimensional diagram is exported.
[0020] A further technical solution of the present invention is: the laboratory electromechanical system frame constructed in step S4 is constructed using a steel platform, is manufactured in accordance with the laboratory top plane structure, and vertical and horizontal positioning lines and elevation positioning lines are marked on the frame according to the positioning diagram.
[0021] A further technical solution of the present invention is: in the step S4, the tire frame is consistent with the laboratory structure, and is inspected and accepted after production. The tire frame must have a center line and a horizontal line.
[0022] A further technical solution of the present invention is: the tire frame is made of 1000*300mm steel plates, and the tire frame is provided with longitudinal and transverse positioning lines, margin lines and alignment lines.
[0023] A further technical solution of the present invention is: in the step S5, the on-site fixing parts are positioned by the BIM layout robot, and the electromechanical system module is lifted at a uniform speed by the hoist and fixedly installed in place.
[0024] The beneficial effects of the present invention are as follows: the construction quality is controllable and the construction precision is high: since all material processing is prefabricated in the factory and the manufacturing process is fully mechanized, the shapes and sizes of the pipes and brackets are of high precision, the modularization concept is adopted to make the product standardized to a high degree, and the factory prefabrication method makes the positioning of the later on-site hoisting and assembly all controlled by the prefabricated connectors on the components, thus avoiding the random fluctuation of the construction quality caused by human factors; the construction speed is fast and the construction period is shortened: the present invention moves all the electromechanical system work to the factory for completion, and there is no need to wait for the completion of the civil structure construction before starting, and the cross-construction can speed up the overall progress of the project, and there is no need to build scaffolding on-site, which effectively reduces the construction time of on-site assembly; it is more environmentally friendly, energy-saving and has low operating risks: on-site cutting and welding work are almost eliminated, and the workload of high-altitude operations is also reduced by about 90%, which greatly improves the environmental conditions of the construction site and effectively reduces the work intensity of the workers; the standardized manufacturing method and the processing material planning performance significantly save energy and materials, and can reduce the cost of production and installation of laboratory electromechanical systems. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a flow chart of a modular factory prefabrication construction method of a laboratory electromechanical system provided by an embodiment of the present invention.
[0026] Figure 2 It is a process flow chart of module workshop prefabrication provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0027] like Figure 1-2 As shown, the modular factory prefabrication construction method of the laboratory electromechanical system provided by the present invention uses BIM technology to carry out three-dimensional in-depth design of the laboratory electromechanical pipelines, and then the designer divides the electromechanical system into modules and draws the drawings. After receiving the processing drawings, the factory builds the frame and prefabricates the modules. After the prefabricated products are inspected by the quality inspectors, they are sent to the construction site for rapid hoisting. The details are as follows:
[0028] Step S1, use 3D digital modeling software to perform three-dimensional modeling of the laboratory electromechanical system; use BIM software to perform three-dimensional modeling of the laboratory electromechanical system; BIM modeling, apply BIM to conduct comprehensive in-depth design of pipelines, and optimize the electromechanical system pipelines, mainly in the following situations: Pipeline collision: Use REVIT software for refined modeling, HVAC, electromechanical, architecture and other multi-disciplinary review, and solve the problem of cross-collision of pipelines of different disciplines in the design stage; The exhaust duct is at the same height as the fresh air duct, forming a ladder-shaped layout with the subdivided pipelines. In the longitudinal laboratory, the electromechanical system pipelines are arranged in an H-shape, and the new return air main pipes are each one side of the H-shape, so that the subdivided pipelines leading to the use point are concentrated in the middle part; The pipeline is optimized to adapt to the integrated bracket: Adjust the electromechanical system pipelines in the ceiling so that the pipelines are layered in the order of bridge, air duct, and water pipe, so that the pipeline layout is more regular and beautiful.
[0029] Step S2, optimize the layout of the modeled electromechanical system to form a "standard + variable" pipeline layout mode and divide it into modules; after the three-dimensional modeling in step S1 is completed, optimize the layout of the electromechanical system to form a "standard + variable" pipeline layout form and divide it into modules; module division, design the side table electromechanical servo module, fume hood electromechanical servo module, central table electromechanical servo module, and other special modules, and divide the electromechanical system of the entire laboratory into 6 standard modules and 2 special modules through the standard + variable combination method; in this step The layout optimization includes rearranging the laboratory water pipes, bridges, and air ducts according to the number and requirements of the laboratory use points, so that the electromechanical pipelines are arranged as concentrated as possible in the laboratory top space; when optimizing the pipelines, according to the characteristics of the laboratory layout, which is mostly composed of the main equipment of the side table + central table + fume hood, the standard electromechanical system layout forms such as the side table electromechanical servo module, the central table electromechanical servo module, and the fume hood servo module are designed, thereby forming standard parts, and the entire laboratory electromechanical system is divided into a "standard module + special module" structure through a few specifications and multiple combinations. The standard modules include the side table electromechanical servo module, the fume hood electromechanical servo module, and the central table electromechanical servo module, and the special modules include the servo module with exhaust main pipe, the aisle area servo module, and the spare area servo module. The side table electromechanical servo module provides water, electricity and gas for the equipment on the side table; the fume hood electromechanical servo module provides water, electricity and gas for the fume hood and the equipment inside the fume hood; the central table electromechanical servo module provides water, electricity and gas for the equipment on the central table; the servo module with exhaust main pipe provides a passage for the exhaust duct to enter and exit the room, and the aisle area servo module and the spare area servo module provide water, electricity and gas for the aisle area and spare area.
[0030] Step S3, according to the divided electromechanical system modules, the parts drawings and assembly drawings of each module are exported and sent to the prefabrication factory; according to the divided electromechanical system module layout drawing, the parts drawings and assembly drawings of each module are issued and sent to the factory; the laboratory electromechanical system frame is built according to the size of the factory site; the BIM engineer uses REVIT software to locate and mark the electromechanical system modules in the model, and then dimensions the pipelines inside the module, indicating the construction requirements, and finally exports the two-dimensional drawing and delivers it to the factory.
[0031] Step S4, the prefabrication factory builds the frame of the electromechanical system in the laboratory according to the positioning diagram on the received drawing and makes the modules divided by each electromechanical system according to the assembly drawing; the electromechanical integrated module is made according to the electromechanical module assembly drawing, first the comprehensive support and hanger are manufactured and built, then the pipelines in each independent comprehensive support and hanger are installed and fixed, the components connected between each module are made, and finally the completion measurement is carried out and the structural acceptance and pre-installation acceptance are carried out; the factory prefabrication, after receiving the processing assembly drawing, the factory makes the frame according to the positioning diagram on the drawing, and the frame must be consistent with the laboratory structure. After the production is completed, it needs to be accepted by the inspection department. The frame must have sufficient rigidity, and the frame production needs to have a center line and a horizontal line. If the module is too heavy or too large, it needs to be strengthened enough to avoid deformation; the frame platform is paved with 1000*300mm steel plates, which can be easily disassembled and reused many times. It is necessary to draw horizontal and vertical positioning inspection lines, margin lines, and matching lines on the frame, and submit them to the quality inspection personnel for acceptance and keep records and archive them. General construction procedures for prefabrication of electromechanical modules: cutting of pipe fittings, production of integrated hangers-----installation of integrated hangers on the frame, positioning-----installation and welding of pipe brackets-----installation of pipelines inside the module-----positioning of pipelines outside the module-----lifting rings and reinforcement installation-----completion measurement-----pre-installation acceptance; the laboratory electromechanical system frame built in this step is made of a steel platform with a smooth surface. It is manufactured in the forward direction of the laboratory top plane structure, and the horizontal and vertical positioning lines and elevation positioning lines are marked on the frame according to the positioning diagram.
[0032] Step S5, the prefabrication factory transports the manufactured electromechanical system modules to the site for splicing and hoisting; transports the manufactured electromechanical modules to the site for rapid splicing and hoisting; uses the BIM layout robot to locate the on-site fixings, and after the electromechanical system modules are transported to the laboratory construction site, they are lifted at a uniform speed by a hoist and fixed to the structure after they are in place.
[0033] The construction quality is controllable and the construction precision is high: since all material processing is prefabricated in the factory and the production process is fully mechanized, the shapes and sizes of pipes and brackets are highly accurate, and the modularization concept makes the product highly standardized. The factory prefabrication method makes the positioning of the later on-site hoisting and assembly controlled by the prefabricated connectors on the components, avoiding the random fluctuation of construction quality caused by human factors; the construction speed is fast and the construction period is shortened: the present invention moves all electromechanical system work to the factory for completion, and there is no need to wait for the completion of the civil structure construction before starting. Cross-construction can speed up the overall progress of the project, and there is no need to build scaffolding on site, which effectively reduces the construction time of on-site assembly; more environmentally friendly, energy-saving, and low operating risk: on-site cutting and welding work are almost eliminated, and the workload of high-altitude operations is also reduced by about 90%, which greatly improves the environmental conditions of the construction site and effectively reduces the work intensity of workers; standardized production methods and processing material planning performance significantly save energy and materials, and can reduce the cost of production and installation of laboratory electromechanical systems.
[0034] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A modular factory prefabrication method for laboratory electromechanical systems, characterized in that: The modular factory prefabrication construction method of the laboratory electromechanical system comprises the following steps: S1. Use 3D digital modeling software to perform three-dimensional modeling of the laboratory electromechanical system; S2. Optimize the layout of the modeled electromechanical system to form a "standard + variable" pipeline layout mode and divide it into modules; S3. Export the parts drawings and assembly drawings of each module according to the divided electromechanical system modules and send them to the prefabrication factory; S4. The prefabrication factory lays the frame of the electromechanical system using steel plates in the laboratory according to the positioning diagram on the receiving drawing and makes the modules divided by each electromechanical system according to the assembly drawing; S5. The prefabrication factory transports the prepared modules of the electromechanical system to the site for splicing and hoisting; In the step S2, the laboratory water pipes, bridges, and air ducts are rearranged according to the number and requirements of the laboratory use points, so that the electromechanical pipelines are centrally arranged in the laboratory top space; according to the equipment composition characteristics of the laboratory layout consisting of a side table + a central table + a fume hood, a standard electromechanical system layout form of a side table electromechanical servo module, a central table electromechanical servo module, and a fume hood servo module is designed to form standard parts, and the entire laboratory electromechanical system is divided into a "standard module + special module" configuration in a manner of fewer specifications and more combinations; The plurality of standard modules and the plurality of special modules divided in step S2, the standard modules include a side table electromechanical servo module, a fume hood electromechanical servo module and a central table electromechanical servo module, and the special modules include a servo module with an exhaust main pipe, a corridor area servo module and a spare area servo module; The laboratory electromechanical system frame constructed in step S4 is constructed using a steel platform, and is manufactured in a forward direction according to the top plane structure of the laboratory, and the vertical and horizontal positioning lines and the elevation positioning lines are marked on the frame according to the positioning diagram; In step S4, the tire frame is consistent with the laboratory structure, and is inspected and accepted after production. The tire frame must have a center line and a horizontal line.
2. The modular factory prefabrication construction method of laboratory electromechanical system according to claim 1 is characterized in that: The step S1 also includes the following steps: S11. Use REVIT software to conduct detailed modeling of laboratory pipelines; S12. Set the laboratory's exhaust duct and fresh air duct at the same height and in a subdivided relationship to form a ladder-shaped layout; S13. Adjust the pipelines in the suspended ceiling and layer them in the upper and lower order of the bridge, air duct and water pipe.
3. The modular factory prefabrication construction method of laboratory electromechanical system according to claim 2 is characterized in that: In step S3, REVIT software is used to locate and mark each module of the electromechanical system in the model.
4. The method for modular factory prefabrication of laboratory electromechanical systems according to claim 3 is characterized in that: In step S3, the pipelines inside each module are dimensioned and construction requirements are noted, and a two-dimensional diagram is exported.
5. The method for modular factory prefabrication of laboratory electromechanical systems according to claim 4, characterized in that: The tire frame is made of 1000*300mm steel plates, and is provided with longitudinal and transverse positioning lines, margin lines and alignment lines.
6. The method for modular factory prefabrication of laboratory electromechanical systems according to claim 5, characterized in that: In step S5, the on-site fixing parts are positioned by the BIM layout robot, and the electromechanical system module is lifted into place at a uniform speed by a hoist and then fixedly installed.