A method for removing rock pillars in giant span caverns and its pre-support system
By applying pre-supporting hole group and anchor cable pre-anchoring above the middle rock column, the risks of rock mass loosening and stress field conversion during the excavation of rock columns in giant span cave rooms are solved, and the stable transformation of the stress field in the cave rooms is achieved and improve construction safety.
Patent Information
- Application Number
- CN202011253546.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-11-11
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2040-11-11
AI Technical Summary
During the process of digging out rock columns in giant span cave chambers, the risks brought by loose rock mass and stress field redistribution are high. How to ensure the stability of rock mass above the middle rock column and the smooth conversion of the stress field in the cave chamber is a technical challenge.
Pre-supporting holes are formed above the middle rock column, including the super-propelled guide holes and connecting channels, longitudinal and transverse foundation beams are laid, and anchor cables are anchored on the longitudinal foundation beams, and the end of the anchor cable extends into the middle rock column to achieve pre-suppose Anchor support prevents stress sudden changes and avoids shear damage through interlaced rigid joints and full-length bonded prestressed anchor cables.
Effectively prevent sudden stress changes caused by excavation of medium rock columns, realize a smooth transition from small span to large span chamber stress field, improve rock mass stability and construction safety, and avoid the problems of prestress loss and insufficient anchoring force .
Smart Images

Figure CN112253189B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, and in particular to a method for excavating rock pillars in a giant span cavern and a pre-support system thereof. Background Art
[0002] With the improvement of underground space development level and the needs of social development, the span of underground projects is bound to develop towards giant spans, and the corresponding technical challenges will be unprecedented.
[0003] For giant span caverns, the construction method is generally to excavate in blocks and finally remove the reserved middle rock pillar. When the middle rock pillar is removed, the span of the cavern changes suddenly, the loose circle of the rock mass increases, and the stress field of the cavern is redistributed, which brings extremely high risks. How to ensure the stability of the rock mass above the middle rock pillar and the smooth conversion of the cavern stress field is the key to cave construction. Summary of the invention
[0004] In order to solve the above problems, the present invention provides a method for excavating the middle rock pillar of a giant span cavern and a pre-support system thereof, by constructing a pre-support hole group above the middle rock pillar to prevent the rock mass from loosening when the middle rock pillar is excavated, thereby achieving a smooth transition of the cavern stress field during the excavation of the middle rock pillar.
[0005] To achieve the above purpose, the technical solution adopted by the present invention is as follows:
[0006] A method for excavating a rock column in a giant span cavern comprises the following steps:
[0007] S1: Set up excavation zones and determine the locations of the middle rock pillar and side rock mass;
[0008] S2: construct a pre-support tunnel group above the middle rock pillar, which includes several advanced pilot tunnels arranged in the same direction as the cavern and several connecting passages connecting adjacent advanced pilot tunnels;
[0009] S3: excavate the side rock mass and provide initial support for the side rock mass;
[0010] S4: In the pilot tunnel, longitudinal foundation beams are constructed along the entire length of the pilot tunnel; in the connecting passage, transverse foundation beams are constructed along the entire length of the connecting passage, and the longitudinal foundation beams and the transverse foundation beams are rigidly connected;
[0011] S5: anchor a number of anchor cables on the longitudinal foundation beam and along the entire length of the longitudinal foundation beam, with the ends of the anchor cables extending into the middle rock column;
[0012] S6: Excavation of the middle rock column:
[0013] S6-1: Anchor the anchor cable extending into the middle rock column, cut off the portion of the anchor cable extending into the middle rock column, and reinforce the anchor cable again after cutting off;
[0014] S6-2: Dig out the middle rock pillar, implement initial support for the middle rock pillar, and form a giant span cavern.
[0015] Furthermore, in step S1: there are multiple middle rock pillars, which are symmetrically arranged with the central axis of the cave as the symmetry axis.
[0016] Furthermore, in step S6: after each middle rock pillar is removed, after the cavern deformation is stabilized, step S6-1 and step S6-2 are repeated until all the middle rock pillars are removed to form a giant span cavern.
[0017] Furthermore, in step S3: the side rock masses are excavated in sequence from one side of the cavern, and initial support of the side rock masses is performed at the corresponding side rock masses.
[0018] Furthermore, the leading hole is vertically arranged to the connecting channel.
[0019] Furthermore, the ratio of the minimum spacing b1 between the leading pilot hole and the cavern to the cavern span b2 is greater than or equal to 0.5, and the ratio of the clear distance c1 in the leading pilot hole to the spacing c2 between the leading pilot holes is greater than or equal to 1.
[0020] Furthermore, the minimum spacing b1 between the pilot tunnel and the cavern is 30m, and the cavern span b2 is 60m; the clear distance c1 in the pilot tunnel is 4m, and the spacing c2 between the pilot tunnels is 4m.
[0021] Furthermore, the ratio of the longitudinal spacing a1 of the connecting channel to the longitudinal spacing a2 of the anchor cable is 2-4.
[0022] Furthermore, the length of the anchor cable extending into the middle rock column is 1 m, and the annular spacing d1 of the anchor cables is 4 m.
[0023] The present invention also provides a pre-support system used in the above method, wherein excavation partitions are arranged in the cavern, the excavation partitions include a plurality of middle rock pillars and a plurality of side rock masses, the middle rock pillars and the side rock masses are arranged alternately, and the middle rock pillars are arranged symmetrically with the central axis of the cavern as the symmetry axis;
[0024] A number of advanced pilot tunnels arranged in the same direction as the cavern and a number of connecting passages connecting adjacent advanced pilot tunnels are arranged obliquely above the middle rock pillar;
[0025] A longitudinal foundation beam is laid in the pilot tunnel, and a transverse foundation beam is laid in the connecting channel. The longitudinal foundation beam and the transverse foundation beam are vertically rigidly connected;
[0026] A number of anchor cables are arranged along the entire length of the longitudinal foundation beam, the ends of the anchor cables are anchored in the middle rock column, and the anchor cables are full-length bonded prestressed anchor cables.
[0027] A method for removing rock pillars in a giant span cavern and a pre-support system thereof of the present invention have the following beneficial effects:
[0028] 1. The present invention constructs a pre-support tunnel group above the middle rock column. The pre-support tunnel group is formed by a plurality of advanced pilot tunnels and a plurality of connecting passages connected horizontally and vertically. A longitudinal foundation beam and a transverse foundation beam are laid in the advanced pilot tunnel and the connecting passage, respectively, and the longitudinal foundation beam and the transverse foundation beam are rigidly connected. A plurality of anchor cables are anchored on the longitudinal foundation beam, and the ends of the anchor cables are extended into the middle rock column, thereby completing the pre-anchor support of the middle rock column, effectively preventing the stress mutation caused by the excavation of the middle rock column, and realizing the smooth transition of the cavern stress field from a small span to a large span.
[0029] 2. In the present invention, the longitudinal foundation beams and the transverse foundation beams are rigidly connected in a staggered manner, and the anchor cables are anchored on the staggered foundation beams, which can convert the concentrated load generated by the anchor cables into a uniformly distributed load, thereby avoiding shear damage of the rock mass under the action of concentrated force and improving the overall stress performance of the stable rock layer above the cavern.
[0030] 3. The present invention adopts a full-length bonded prestressed anchor cable, which can avoid the problems of prestress loss and insufficient anchoring force caused by cave excavation disturbance.
[0031] 4. In the present invention, a longitudinal foundation beam and a transverse foundation beam are arranged obliquely above the middle rock column, and the anchor cables connected to the longitudinal foundation beam are obliquely anchored in the middle rock column, so that the tension and stability are stronger.
[0032] 5. The overall construction sequence of the present invention is: construct a pre-support cave group above the middle rock column - excavate the side rock mass and implement the initial support of the side rock mass - construct the longitudinal foundation beam and the transverse foundation beam - anchor the anchor cable on the longitudinal foundation beam, and the end of the anchor cable is anchored in the middle rock column - excavate the middle rock column and implement the initial support of the middle rock column. The construction sequence is scientific and orderly, with clear levels, which can effectively ensure the smooth transition of the cavern stress field during the entire construction process, with high construction efficiency and high construction safety.
[0033] 6. In the present invention, the ratio of the longitudinal spacing a1 of the connecting channel to the longitudinal spacing a2 of the anchor cables is 2 to 4. The ratio of the minimum spacing b1 between the leading pilot tunnel and the cavern to the cavern span b2 is greater than or equal to 0.5, and the ratio of the clear distance c1 in the leading pilot tunnel to the spacing c2 between the leading pilot tunnels is greater than or equal to 1. The length of the anchor cable extending into the middle rock column is 1m, and the annular spacing d1 of the anchor cables is 4m. It is preferred to control various parameters during the construction process to achieve the optimal choice of a smooth transition of the cavern stress field during the construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying any creative work.
[0035] Figure 1 It is a schematic diagram of the structure in steps S1-S2 of an embodiment of the present invention;
[0036] Figure 2 This is a schematic diagram of the structure of a pre-support tunnel group according to an embodiment of the present invention;
[0037] Figure 3 This is a schematic diagram of the structure of step S3 of an embodiment of the present invention;
[0038] Figure 4 This is a schematic diagram of the structure of step S4 in an embodiment of the present invention;
[0039] Figure 5 This is a schematic diagram of the structure of step S5 of an embodiment of the present invention;
[0040] Figure 6 This is a schematic diagram of the structure of step S6 in an embodiment of the present invention;
[0041] Figure 7 Schematic diagram of the structure of step S7 of the embodiment of the present invention.
[0042] Description of reference numerals:
[0043] 1-middle rock pillar; 11-initial support of middle rock pillar; 2-side rock mass; 21-initial support of side rock mass; 3-pre-support tunnel group; 31-advanced pilot tunnel; 32-connecting passage; 33-longitudinal foundation beam; 34-transverse foundation beam; 35-anchor cable. DETAILED DESCRIPTION
[0044] In order to better understand the purpose, structure and function of the present invention, a method for excavating a rock pillar in a giant span cavern of the present invention is further described in detail below in conjunction with the accompanying drawings.
[0045] like Figure 1-7 A method for removing rock pillars in a giant span cavern is shown, comprising the following steps:
[0046] S1: Set excavation zones to determine the positions of the middle rock pillar 1 and the side rock mass 2. There can be many ways to partition, for example, the middle rock pillar 1 and the side rock mass 2 are set alternately. When the middle rock pillar 1 is an odd number, at least one middle rock pillar 1 is located on the central axis of the cavern, and the other middle rock pillars 1 are evenly divided on both sides of the central axis of the cavern, and are set symmetrically; when the middle rock pillar 1 is an even number, they are evenly divided on both sides of the central axis of the cavern, and are set symmetrically. Or when the span of the cavern is long enough and there are many middle rock pillars 1, the middle rock pillars 1 do not need to be evenly divided on both sides of the central axis of the cavern, and can be roughly symmetrical. This setting method can better ensure the stability of the cavern.
[0047] S2: A pre-support hole group 3 is constructed above the middle rock column 1. The pre-support hole group 3 includes a number of advanced pilot holes 31 arranged in the same direction as the cavern and a number of connecting passages 32 connecting adjacent advanced pilot holes 31. The advanced pilot holes 31 and the connecting passages 32 are arranged vertically. The size of the advanced pilot hole 31 must meet the construction space of the longitudinal foundation beam 33 and the anchor cable 35, and the size of the connecting passage 2 must meet the construction space of the transverse foundation beam 34. And the better setting is to construct the pre-support hole group 3 obliquely above the middle rock column 1, so that the anchor cable 34 pulled out by the advanced pilot hole 31 is obliquely connected to the middle rock column 1, and the pulling anchoring force is stronger.
[0048] Furthermore, the ratio of the minimum spacing b1 between the leading guide hole 31 and the cavern to the cavern span b2 is greater than or equal to 0.5, and the ratio of the clear distance c1 in the leading guide hole 31 to the spacing c2 between the leading guide holes 31 is greater than or equal to 1.
[0049] Furthermore, the minimum distance b1 between the leading pilot tunnel 31 and the cavern is 30 m, and the cavern span b2 is 60 m; the clear distance c1 in the leading pilot tunnel 31 is 4 m; and the distance c2 between the leading pilot tunnels 31 is 4 m.
[0050] S3: excavate the side rock mass 2 and apply the initial support 21 of the side rock mass. Preferably, the side rock mass 2 is excavated sequentially from one side of the cavern, and the initial support 21 of the side rock mass is applied at the corresponding side rock mass 2. Of course, under the condition of ensuring the stability of the entire construction, the side rock mass 2 can also be excavated from both sides at the same time, or the side rock mass 2 in the middle part can be selected for excavation. For the excavation of a single side rock mass 2, the side rock mass 2 can be excavated from the top to the bottom, and after enough space is excavated at the top of the side rock mass 2, the initial support 21 of the side rock mass is applied in time to anchor the side rock mass 2.
[0051] S4: In the advanced pilot tunnel 31, a longitudinal foundation beam 33 is constructed along the entire length of the advanced pilot tunnel 31, and in the connecting passage 32, a transverse foundation beam 34 is constructed along the entire length of the connecting passage 32. The longitudinal foundation beam 33 and the transverse foundation beam 34 are rigidly connected to form a criss-cross overall frame structure with strong structural stability.
[0052] S5: A plurality of anchor cables 35 are anchored on and along the longitudinal foundation beam 33 , and the ends of the anchor cables 35 extend into the middle rock column 1 .
[0053] Furthermore, the ratio of the longitudinal spacing a1 of the connecting channel 32 to the longitudinal spacing a2 of the anchor cable 35 is 2 to 4. The preferred ratio is 2.
[0054] Preferably, the length of the anchor cable 35 extending into the middle rock column 1 is 1 m, and the annular spacing d1 of the anchor cables 35 is 4 m.
[0055] S6: Dig out the middle rock column 1:
[0056] S6-1: Anchor the anchor cable 35 extending into the middle rock column 1, and cut off the portion of the anchor cable 35 extending into the middle rock column 1. The cutting process may cause the anchor to loosen, and thus, according to the looseness, the anchor cable 35 is pulled to reinforce it again;
[0057] S6-2: Excavate the middle rock column 1. Excavate from the top to the bottom of the middle rock column 1. After enough space is excavated at the top of the middle rock column 1, the initial support 11 of the middle rock column is carried out in time.
[0058] In step S6: after each middle rock column 1 is excavated, after the cavern deformation is stabilized, steps S6-1 and S6-2 are repeated until all the middle rock columns 1 are excavated to form a giant span cavern.
[0059] The present invention also provides a pre-support system used in the above method, wherein excavation partitions are arranged in the cavern, the excavation partitions include a plurality of middle rock pillars 1 and a plurality of side rock masses 2, the middle rock pillars 1 and the side rock masses 2 are arranged alternately, and the middle rock pillars 1 are symmetrically arranged with the central axis of the cavern as the symmetry axis;
[0060] A plurality of leading pilot holes 31 arranged in the same direction as the cavern and a plurality of connecting passages 32 connecting adjacent leading pilot holes 31 are arranged obliquely above the middle rock column 1;
[0061] A longitudinal foundation beam 33 is laid in the leading tunnel 31, and a transverse foundation beam 34 is laid in the connecting passage 32. The longitudinal foundation beam 33 and the transverse foundation beam 34 are vertically rigidly connected;
[0062] A plurality of anchor cables 35 are provided along the entire length of the longitudinal foundation beam 33 , and the ends of the anchor cables 35 are anchored in the middle rock column 1 .
[0063] The present invention is further described above with the aid of specific embodiments, but it should be understood that the specific description here should not be construed as limiting the essence and scope of the present invention, and various modifications made to the above embodiments by ordinary technicians in the field after reading this specification are all within the scope of protection of the present invention.
Claims
1. A method for removing rock pillars in a giant span cavern, characterized in that: The following steps are involved: S1: Set up excavation zones and determine the locations of the middle rock pillar (1) and the side rock mass (2); S2: constructing a pre-support tunnel group (3) above the middle rock column (1), wherein the pre-support tunnel group (3) includes a plurality of advanced pilot tunnels (31) arranged in the same direction as the cavern and a plurality of connecting passages (32) connecting adjacent advanced pilot tunnels (31); S3: excavating the side rock mass (2) and providing initial support for the side rock mass (21); S4: in the advanced pilot tunnel (31), a longitudinal foundation beam (33) is constructed along the entire length of the advanced pilot tunnel (31); in the connecting passage (32), a transverse foundation beam (34) is constructed along the entire length of the connecting passage (32); and the longitudinal foundation beam (33) and the transverse foundation beam (34) are rigidly connected; S5: anchoring a plurality of anchor cables (35) on and along the longitudinal foundation beam (33), with the ends of the anchor cables (35) extending into the middle rock column (1); S6: Remove the middle rock column (1): S6-1: Anchoring the anchor cable (35) extending into the middle rock column (1), cutting off the portion of the anchor cable (35) extending into the middle rock column (1), and reinforcing the anchor cable (35) after cutting off; S6-2: excavating the middle rock pillar (1), carrying out the initial support of the middle rock pillar (11), and forming a giant span cavern; In step S1: there are multiple middle rock pillars (1), which are symmetrically arranged with the central axis of the cave as the symmetry axis; The leading guide hole (31) and the connecting passage (32) are arranged vertically; The ratio of the minimum spacing b1 between the leading guide hole (31) and the cavern to the cavern span b2 is greater than or equal to 0.5, and the ratio of the clear distance c1 in the leading guide hole (31) to the spacing c2 between the leading guide holes (31) is greater than or equal to 1; The minimum spacing b1 between the leading pilot tunnel (31) and the cavern is 30 m, and the cavern span b2 is 60 m; the clear distance c1 in the leading pilot tunnel (31) is 4 m, and the spacing c2 between the leading pilot tunnels (31) is 4 m; The ratio of the longitudinal spacing a1 of the connecting channel (32) to the longitudinal spacing a2 of the anchor cable (35) is 2-4.
2. The method for removing rock pillars in a giant span cavern according to claim 1, characterized in that: In step S6: after each middle rock column (1) is excavated, after the cavern deformation is stabilized, steps S6-1 and S6-2 are repeated until all the middle rock columns (1) are excavated to form a giant span cavern.
3. The method for removing rock pillars in a giant span cavern according to claim 1, characterized in that: In step S3: the side rock masses (2) are excavated in sequence from one side of the cavern, and the side rock mass initial support (21) is applied to the corresponding side rock masses (2).
4. The method for removing rock pillars in a giant span cavern according to claim 1, characterized in that: The length of the anchor cable (35) extending into the middle rock column (1) is 1 m, and the annular spacing d1 of the anchor cables (35) is 4 m.
5. A pre-support system used in the method for excavating rock pillars in a giant span cavern as claimed in any one of claims 1 to 4, wherein excavation partitions are arranged in the cavern, characterized in that: The excavation partition includes a plurality of middle rock pillars (1) and a plurality of side rock bodies (2), the middle rock pillars (1) and the side rock bodies (2) are arranged alternately, and the middle rock pillars (1) are arranged symmetrically with the central axis of the cavern as the symmetry axis; A plurality of advanced pilot holes (31) arranged in the same direction as the cavern and a plurality of connecting passages (32) connecting adjacent advanced pilot holes (31) are arranged obliquely above the middle rock column (1); A longitudinal foundation beam (33) is laid in the leading tunnel (31), a transverse foundation beam (34) is laid in the connecting passage (32), and the longitudinal foundation beam (33) and the transverse foundation beam (34) are vertically rigidly connected; A plurality of anchor cables (35) are arranged along the entire length of the longitudinal foundation beam (33), the ends of the anchor cables (35) are anchored in the middle rock column (1), and the anchor cables (35) are full-length bonded prestressed anchor cables.