An underwater large-diameter steel cylinder caisson wellhead protection device

By vibrating the steel cylinder and water-blocking conduit in the subsea mud layer, combined with concrete bottom cover, forming a protective structure, the problem of safety and difficulty in protecting the underwater production system in navigation areas is solved, and safe construction and low-cost underwater production system are realized Protection reduces waterway obstruction and accident risks.

CN112267846BActive Publication Date: 2024-11-19CNOOC ENERGY TECHNOLOGY & SERVICES LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202011257319.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-11-11
Publication Date
2024-11-19
Estimated Expiration
2040-11-11

AI Technical Summary

Technical Problem

In navigational areas or sensitive areas, the safety of underwater production systems is difficult to protect, the prior art cannot effectively prevent the harm of ship navigation to underwater production systems, and it is difficult to assess the safety of drilling and underwater protection facilities.

Method used

Design a protective device for caisson wellhead of large diameter steel cylinder caisson to sink to the subsea mud layer through the steel cylinder, combined with a water barrier conduit and a concrete bottom cover to form a protective structure that protects the drilling site and a removable cylinder top cover To connect the drilling platform, reduce obstacles on the water surface and reduce waterway risks.

Benefits of technology

It effectively protects the safety of the underwater production system, reduces construction difficulty and cost, reduces the occurrence of ship navigation accidents, integrates into the overall design during drilling, and improves the efficiency and safety of marine engineering construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112267846B_ABST
    Figure CN112267846B_ABST
Patent Text Reader

Abstract

The present invention discloses an underwater large-diameter steel cylinder caisson wellhead protection device, comprising a steel cylinder, the steel cylinder is vibrated and sunk into the seabed mud layer until the top of the steel cylinder is located above the mud layer, the bottom of the steel cylinder is provided with a water-blocking pipe penetrating the mud layer, a concrete bottom is cast on the mud layer between the bottom inner wall of the steel cylinder and the water-blocking pipe; the water-blocking pipe is composed of at least three sections of pipes that are mutually threaded or quickly connected. The present invention aims to provide a large-diameter steel cylinder caisson wellhead protection device suitable for protecting the production safety of underwater production systems in navigation areas or sensitive areas.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of marine engineering, and in particular to a wellhead protection device for an underwater large-diameter steel cylinder caisson. Background Art

[0002] In principle, no development above the water surface is allowed in areas sensitive to oil and gas resources in the sea. In navigable areas, due to restrictions on ship navigation, development through fixed drilling platforms will have a significant impact on ship navigation. At the same time, the platforms also face a great risk of ship collision. In order to avoid or reduce safety accidents between navigable ships and offshore platforms, offshore platforms are not allowed to be built in most sensitive areas.

[0003] When developing underwater production systems in navigable areas, the risk of damage to underwater production systems with protective covers caused by activities such as anchoring and dragging of anchors by passing ships is greater than that in sensitive areas. At the same time, it is difficult to assess the stability of seabed foundation treatment or foundation pit support, as well as the safety of structures and foundation pits, drilling and underwater protection facilities, etc. Therefore, there is an urgent need for a large-diameter steel cylinder caisson wellhead protection device suitable for protecting the production safety of underwater production systems in navigable areas or sensitive areas. Summary of the invention

[0004] The purpose of the present invention is to overcome the deficiencies in the above-mentioned prior art and to provide a large-diameter steel cylinder caisson wellhead protection device suitable for protecting the production safety of underwater production systems in navigation areas or sensitive areas.

[0005] To achieve the above object, the technical solution of the present invention is achieved as follows:

[0006] An underwater large-diameter steel cylinder caisson wellhead protection device comprises a steel cylinder, the steel cylinder is vibrated and sunk into the mud layer on the seabed until the top of the steel cylinder is located above the mud layer, a water-blocking pipe penetrating the mud layer is arranged at the bottom of the steel cylinder, a concrete bottom seal is poured on the mud layer between the bottom inner wall of the steel cylinder and the water-blocking pipe; the water-blocking pipe is composed of at least three sections of pipes connected to each other by threads or quick buckles; the top of the steel cylinder is detachably provided with a cylinder top cover that can pass through a pipeline; the implementation method steps are as follows:

[0007] (1) hoisting a steel cylinder having at least two cylinder sections by an offshore engineering vessel and lowering it to a drilling setting position on the seabed;

[0008] (2) Vibrate and sink the steel cylinder into the seabed mud layer through a multi-hammer linkage system, so that the steel cylinder at the bottom reaches a predetermined depth in the mud;

[0009] (3) Use pumping equipment to pump out the seawater and silt in the steel cylinder, use a multi-hammer linkage system to penetrate the watertight pipe into the mud layer in the steel cylinder, and vibrate each section of the pipe downward in turn to make the watertight pipe penetrate deeper into the mud layer on the seabed. Then use a delivery pump to continuously pour concrete at the bottom of the steel cylinder to form a concrete bottom that surrounds the watertight pipe and seals the watertight pipe to the inner wall of the steel cylinder;

[0010] (4) Remove the cylinders above the lowest steel cylinder and hoist them away through the offshore engineering vessel, and then move the offshore engineering vessel away;

[0011] (5) Drag the drilling platform to the steel cylinder, connect the top of the riser to the drilling platform's elevated riser, complete the drilling and completion operations, and install the underwater production system in the steel cylinder through the drilling platform;

[0012] (6) A cylinder top cover that can pass through the rising riser is installed on the top of the steel cylinder, completing the overall installation of the steel cylinder and the underwater production system and putting it into production.

[0013] Furthermore, the steel cylinder is composed of at least two sections of detachably connected cylinders.

[0014] Furthermore, the concrete bottom seal is provided with a wellhead, a wellhead connector, a guide base plate and an underwater Christmas tree production system at the water-blocking conduit.

[0015] Furthermore, in step (1), the length of each section of the steel cylinder is 9-13 m.

[0016] Furthermore, in step (2), the top of the steel cylinder at the bottom is 0.5-1 m higher than the seabed mud layer.

[0017] Furthermore, the concrete bottom seal height in step (3) is 2-3m.

[0018] Compared with the prior art, the present invention has the following beneficial effects:

[0019] The present invention solves the problem of safety protection of underwater production systems in restricted areas and waterway areas. A steel cylinder formed by connecting multiple sections of cylinders is pre-vibrated and sunk in the seabed mud layer of the oil field to be developed to form a steel cylinder that surrounds the drilling site of the oil field for protection. The sections of cylinders above the lowest cylinder that is vibrated and sunk into the mud layer are removed, and only the lowest cylinder is retained to reduce the number of cylinders above the water surface and between the water surface and the mud layer, avoid obstruction of the waterway, provide convenience for passing ships, and reduce the occurrence of accidents. In the present invention, the placement of the marine engineering of the steel cylinder is effectively configured with the drilling process, and the marine engineering construction is integrated into the overall design of drilling and completion, which reduces the difficulty of construction and reduces costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1It is a structural schematic diagram of the present invention;

[0021] Figure 2 Schematic diagram of hoisting steel casing for offshore engineering vessel;

[0022] Figure 3 This is a schematic diagram of the steel casing vibrating and sinking into the seabed mud layer;

[0023] Figure 4 This is a schematic diagram of the structure of the present invention after installation in the seabed mud layer.

[0024] Description of reference numerals:

[0025] 1- offshore engineering vessel, 2- sea level, 3- mud layer, 4- steel cylinder, 5- concrete bottom seal, 6- watertight pipe, 7- wellhead, 8- wellhead connector, 9- guide base plate, 10- subsea oil production tree production system, 11- cylinder top cover. DETAILED DESCRIPTION

[0026] The present invention will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments.

[0027] like Figure 1 As shown, an underwater large-diameter steel cylinder caisson wellhead protection device comprises a steel cylinder 4, wherein the steel cylinder 4 is vibrated and sunk into the mud layer 3 on the seabed until the top of the steel cylinder 4 is located above the mud layer 3, a watertight pipe 6 penetrating into the mud layer 3 is arranged inside the steel cylinder 4, a concrete bottom seal 5 is cast on the mud layer 3 between the bottom inner wall of the steel cylinder 4 and the watertight pipe 6; the watertight pipe 6 is composed of at least three sections of pipes which are threadedly connected to each other or quickly connected; the concrete bottom seal 5 is installed with a wellhead at the watertight pipe 6, as well as a wellhead connector 8, a guide base plate 9 and an underwater oil production tree production system 10.

[0028] Among them, the steel cylinder 4 is composed of at least two sections of detachably connected cylinders. The steel cylinder 4 is assembled by detachably connecting multiple sections of cylinders, which can reduce the processing difficulty of making the steel cylinder 4. The steel cylinder 4 can be extended to the seabed mud layer 3 by connecting the sections.

[0029] Among them, a cylinder top cover 11 through which a pipeline can pass is fixedly arranged on the top of the steel cylinder 4. The cylinder top cover 11 can protect the underwater production system in the cylinder and reserve a cylinder opening through which a pipeline can pass for connection with a drilling platform or other platforms when needed.

[0030] The implementation method of the present invention comprises the following steps:

[0031] (1) Figure 2 As shown, a steel cylinder 4 having at least two cylinder sections is hoisted by an offshore engineering vessel 1 and lowered to a drilling setting position on the seabed. The length of each cylinder section of the steel cylinder 4 is 9-13 m, and can be used to accommodate and install an underwater production system.

[0032] (2) Figure 3 As shown, the steel cylinder 4 is vibrated and sunk into the seabed mud layer 3 through a multi-hammer linkage system, so that the top of the steel cylinder 4 at the bottom is 0.5-1m higher than the seabed mud layer to prevent the seabed rocks or mud from being washed into the steel cylinder. The multi-hammer linkage system can use the YCS series double-acting underwater full hydraulic pile hammer produced by Zhongji Forging to vibrate and sink the steel cylinder 4;

[0033] (3) Figure 4 As shown, the seawater and silt in the steel cylinder 4 are pumped out using a pumping device, and the watertight pipe 6 is inserted into the mud layer 3 in the steel cylinder 4 using a multi-hammer linkage system. The pipe with threaded connection or quick-release connection can be directly vibrated and sunk in the mud layer, and each section of the pipe is vibrated and sunk downward in turn, so that the watertight pipe 6 penetrates deeper into the seabed mud layer 3, and then a delivery pump is used to continuously pour concrete at the bottom of the steel cylinder 4 to form a concrete bottom seal 5 that surrounds the watertight pipe 6 and seals the watertight pipe 6 and the inner wall of the steel cylinder 4. The height of the concrete bottom seal 5 is 2-3m;

[0034] (4) The cylinders above the lowest steel cylinder 4 are removed and lifted by the offshore engineering vessel 1, and the offshore engineering vessel 1 is moved away, leaving the steel cylinder 4 hammered into the mud layer, and the interior of the steel cylinder 4 forms a drilling protection space sunk below the mud layer 3;

[0035] (5) Drag the drilling platform to the steel cylinder 4, connect the top of the watertight pipe 6 to the rising riser of the drilling platform, complete the drilling and completion operation, and install the wellhead 7, wellhead connector 8, guide base plate 9 and underwater Christmas tree production system 10 on the watertight pipe 6 through the drilling platform;

[0036] (6) A cylinder top cover 11 that can pass through the rising riser is installed on the top of the steel cylinder 4. The cylinder top cover 11 is used to cover the drilling protection space surrounded by the steel cylinder 4 to prevent the collision of the underwater production system caused by activities such as anchoring and dragging of anchors by passing ships, thereby protecting the overall safety of the interior of the steel cylinder 4. After the overall installation of the steel cylinder 4 and the underwater production system, it can be put into production.

[0037] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. An underwater large-diameter steel cylinder caisson wellhead protection device, comprising a steel cylinder, characterized in that: The steel cylinder is vibrated and sunk into the mud layer on the seabed until the top of the steel cylinder is located above the mud layer. A watertight pipe that penetrates the mud layer is provided at the bottom of the steel cylinder. A concrete bottom seal is poured on the mud layer between the bottom inner wall of the steel cylinder and the watertight pipe. The watertight pipe is composed of at least three sections of pipes that are mutually threaded or quickly connected. A removable cylinder top cover that can pass through a pipeline is provided on the top of the steel cylinder. The implementation method steps are as follows: (1) hoisting a steel cylinder having at least two cylinder sections by an offshore engineering vessel and lowering it to a drilling setting position on the seabed; (2) Vibrate and sink the steel cylinder into the seabed mud layer through a multi-hammer linkage system, so that the steel cylinder at the bottom reaches a predetermined depth in the mud; (3) Use pumping equipment to pump out the seawater and silt in the steel cylinder, use a multi-hammer linkage system to penetrate the watertight pipe into the mud layer in the steel cylinder, and vibrate each section of the pipe downward in turn to make the watertight pipe penetrate deeper into the mud layer on the seabed. Then use a delivery pump to continuously pour concrete at the bottom of the steel cylinder to form a concrete bottom that surrounds the watertight pipe and seals the watertight pipe to the inner wall of the steel cylinder; (4) Remove the cylinders above the lowest steel cylinder and hoist them away through the offshore engineering vessel, and then move the offshore engineering vessel away; (5) Drag the drilling platform to the steel cylinder, connect the top of the riser to the drilling platform's elevated riser, complete the drilling and completion operations, and install the underwater production system in the steel cylinder through the drilling platform; (6) A cylinder top cover that can pass through the rising riser is installed on the top of the steel cylinder, completing the overall installation of the steel cylinder and the underwater production system and putting it into production.

2. The underwater large-diameter steel cylinder caisson wellhead protection device according to claim 1 is characterized by: The steel cylinder is composed of at least two sections of detachably connected cylinders.

3. The underwater large-diameter steel cylinder caisson wellhead protection device according to claim 1 is characterized by: The concrete bottom seal is provided with a wellhead, a wellhead connector, a guide base plate and an underwater Christmas tree production system at the water-blocking conduit.

4. The underwater large-diameter steel cylinder caisson wellhead protection device according to claim 1 is characterized by: In step (1), the length of each section of the steel cylinder is 9-13m.

5. The underwater large-diameter steel cylinder caisson wellhead protection device according to claim 1 is characterized by: In step (2), the top of the steel cylinder at the bottom is 0.5-1 m higher than the seabed mud layer.

6. The underwater large-diameter steel cylinder caisson wellhead protection device according to claim 1 is characterized by: The concrete bottom seal height in step (3) is 2-3m.