A modular and integrated offshore booster station
Through the design of the offshore booster station combining modular and integral, the combined structure of the frame body and prefabricated box body is used to solve the problems of large steel consumption and low construction efficiency of the offshore booster station in the integrated steel structure, and the steel consumption is achieved The effect of low material costs and short construction cycle.
Patent Information
- Application Number
- CN202010970945.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-09-16
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2040-09-16
AI Technical Summary
The existing integrated steel structure offshore booster stations have problems such as large steel usage, high material cost, long construction cycle, high labor cost and low construction efficiency.
The offshore booster station design is adopted that combines modular and integral type. Through the combined structure of the frame body and the prefabricated box, the amount and weight of steel are reduced, the construction surface is increased, and the construction cycle is shortened.
It has achieved the effects of low steel usage, low material cost, short construction cycle, low labor cost and high construction efficiency, reducing the construction period and material cost of offshore booster stations.
Smart Images

Figure CN112627602B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to an offshore booster station combining modularization and integration, belonging to the technical field of offshore power generation equipment in electric power. Background Art
[0002] In recent years, my country's offshore wind power industry has developed rapidly, and more and more offshore wind power projects have started construction in the coastal provinces of the motherland. Offshore wind power projects can generally be divided into four parts: offshore wind turbines, offshore substations, submarine cables, and onshore control centers. The electricity generated by offshore wind turbines is collected to offshore substations through 35kV collecting submarine cables, and the voltage is increased from 35kV to 220kV through the offshore substations. Then, the electricity is transmitted from the sea to the onshore control center through 220kV submarine cables, and finally connected to the onshore control center and the power grid. It can be seen that the offshore substation is the core of the offshore wind power project, responsible for key tasks such as electricity collection and voltage increase.
[0003] In the prior art, such as Figure 5 As shown, it includes a seabed foundation 10 and a sea surface main body 20. The sea surface main body 20 is an integral steel structure with a design capacity ranging from 200MW to 400MW and a weight generally around 3,000 tons. The weight of the sea surface main body 20 of the lightest 400MW offshore substation is about 2,700 tons. In addition to the sea-entering foundation 10, the conventional offshore substation has a sea surface main body 20 block on the foundation divided into three layers. The first layer is a cable mezzanine (including a rest room, an accident oil tank, and escape equipment, etc.), the second layer is a main equipment layer (including a main transformer, GIS, a medium-voltage distribution cabinet, a low-voltage distribution cabinet, a grounding transformer, a grounding and station transformer, a fire equipment room, a communication battery room, etc.), and the third layer is an auxiliary equipment layer (including an electronic equipment room, a secondary battery room, a HVAC room, a diesel generator, an oil storage tank, etc.), and the top surface is arranged with a lightning rod, a radar antenna, and hoisting equipment, etc. The dimensions of a conventional booster station are 40.4m (length), 36m (width), and 17m (height).
[0004] The offshore booster station of the prior art has the following problems because the main body 20 of the sea surface is an integral steel structure: (1) The steel required to constitute the main body of the sea surface is relatively thick and large, and heavy, resulting in a large overall weight of the main body of the sea surface (generally 2800-3200t), which consumes a lot of steel, is heavy, and has a high cost. (2) Due to the heavy weight of the main body of the sea surface, the amount of steel required for the seabed foundation (including steel pipe piles and conductor frames) is also greatly increased, resulting in a large amount of steel and high material costs. (3) Since the main body of the sea surface is an integral steel structure, it must be constructed at the same location and on the same working surface, which limits the construction space and working surface, resulting in a long construction period (usually 9-10 months), high labor costs, and low construction efficiency. Summary of the invention
[0005] The purpose of the present invention, that is, the technical problem to be solved by the present invention, is to solve the problems of existing integral steel structure offshore booster stations, such as large steel consumption, high material cost, long construction period, high labor cost, and low construction efficiency, and to provide an offshore booster station that combines modularization and integration, which has outstanding substantial characteristics and significant progress such as less steel consumption, lower material cost, short construction period, lower labor cost, and higher construction efficiency.
[0006] The purpose of the present invention can be achieved by adopting the following technical solutions:
[0007] A modular and integral offshore booster station comprises a seabed foundation and a sea surface station house, wherein the sea surface station house comprises a frame body and a house shell; the structural features are as follows: the frame body has an integral three-layer space structure; the first layer of the frame body constitutes a rest room, an accident oil discharge tank and an escape equipment setting space, the second layer of the frame body constitutes a main transformer setting space, and the third layer of the frame body constitutes a main transformer maintenance equipment setting space; a left supporting structure is extended to the left at the bottom of the first layer or the second layer of the frame body, and a right supporting structure is extended to the right, and a left pre- A right prefabricated box is connected to the right supporting structure to form a modular combination structure; the left prefabricated box constitutes the installation space for medium-voltage equipment, low-voltage equipment and electronic equipment, secondary batteries, and diesel generators, and the right prefabricated box constitutes the installation space for GIS, communication batteries, fire-fighting equipment and GIS maintenance settings, and HVAC equipment; the bottom surface of the frame body is provided with a large tube-type foundation connecting end and a small tube-type foundation connecting end to form a fixed connection structure with the foundation; through the connection combination of the left prefabricated box, the right prefabricated box and the frame body, a modular and integral offshore substation structure is formed.
[0008] The purpose of the present invention can also be achieved by adopting the following technical solutions:
[0009] Furthermore, the left supporting structure 1 and the right supporting structure extend from the left and right sides of the second-layer bottom of the frame body respectively, and the bottom surface of the left supporting structure is provided with a left support, and the bottom surface of the right supporting structure is provided with a right support; forming a reinforced support for the left supporting structure and the right supporting structure; the left prefabricated box and the right prefabricated box each have a two-layer structure to form a two-layer equipment setting space.
[0010] Furthermore, the left prefabricated box includes a left upper box and a left lower box, and the right prefabricated box includes a right upper box and a right lower box. The left lower box is used to set medium-voltage equipment and low-voltage equipment, and the left upper box is used to set electronic equipment, secondary batteries, and diesel generators; the right lower box is used to set GIS, communication batteries, and fire-fighting equipment, and the right upper box is used to set GIS maintenance equipment and HVAC equipment.
[0011] Furthermore, the left prefabricated box is connected to the frame body and the left supporting structure by bolts to form an easily assembled and disassembled connection structure, and the right prefabricated box is connected to the frame body and the right supporting structure by bolts to form an easily assembled and disassembled connection structure; or the left prefabricated box is connected to the frame body and the left supporting structure by welding to form a fixed connection structure, and the right prefabricated box is connected to the frame body and the right supporting structure by welding to form a fixed connection structure.
[0012] Furthermore, the left support includes a left horizontal beam extending from the left side of the bottom of the frame body and two left oblique support rods, the upper ends of the two left oblique support rods are fixedly connected to the bottom surface of the left support structure, and the lower ends are fixedly connected to the left horizontal beam, forming a "V"-shaped support structure; the right support includes a right horizontal beam extending from the right side of the bottom of the frame body and two right oblique support rods, the upper ends of the two left oblique support rods are fixedly connected to the bottom surface of the right support structure, and the lower ends are fixedly connected to the right horizontal beam, forming a "V"-shaped support structure.
[0013] The present invention has the following outstanding substantive features and significant technical advances:
[0014] 1. The present invention has an integral three-layer space structure because the frame body has a first layer of the frame body, which constitutes a rest room, an accident oil tank and an escape equipment installation space; the second layer of the frame body constitutes a main transformer installation space; the third layer of the frame body constitutes a main transformer maintenance equipment installation space; a left supporting structure is extended to the left at the bottom of the first layer or the second layer of the frame body, and a right supporting structure is extended to the right, a left prefabricated box is connected to the left supporting structure, and a right prefabricated box is connected to the right supporting structure, forming a modular combination structure; the left prefabricated box constitutes a medium-voltage equipment, a low-voltage equipment and electronic equipment, a secondary battery, and a diesel generator installation space, and the right prefabricated box 4 constitutes a GIS, a communication battery, Fire-fighting equipment and GIS maintenance settings, HVAC equipment settings space; the bottom surface of the frame body 2 is provided with a large tube-type foundation connection end and a small tube-type foundation connection end to form a fixed connection structure with the foundation; through the connection combination of the left prefabricated box, the right prefabricated box and the frame body, a modular and integral offshore booster station structure is formed; therefore, it not only has the function and structure of an offshore booster station, but also can solve the problems of existing integral steel structure offshore booster stations with large steel consumption, high material cost, long construction period, high labor cost, low construction efficiency, etc. It has outstanding substantial characteristics and significant progress such as less steel consumption, lower material cost, shorter construction period, lower labor cost, and higher construction efficiency.
[0015] 2. The present invention adopts a combination of left and right prefabricated boxes connected with a frame body located in the middle to form an offshore booster station structure that combines modularization and integration. This allows the use of thinner and less steel, which can reduce the steel usage and weight of the frame body on the one hand, and the steel usage and weight of the seabed foundation on the other hand. It has outstanding substantial characteristics and significant progress such as less steel usage as a whole (including the seabed foundation 1 and the sea surface station building), lower material cost, shorter construction period, lower labor cost, and higher construction efficiency.
[0016] 3. The present invention applies modular prefabricated cabins to the integral offshore booster station, and uses modular prefabricated cabins to replace the structural main columns, steel beams, diagonal braces and other structural components of the original integral offshore booster station to reduce the weight of the upper modules and the lower foundation of the offshore booster station; after the prefabricated cabins are introduced, the construction period of the offshore booster station is shortened by increasing the construction working surface. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a front view of the frame structure of a specific embodiment of the present invention.
[0018] Figure 2 It is a front view of the frame structure of a specific embodiment of the present invention.
[0019] Figure 3It is a top view of the second layer structure of the lever frame main body of a specific embodiment of the present invention.
[0020] Figure 4 It is a top view of the third layer structure of the lever frame main body of a specific embodiment of the present invention.
[0021] Figure 5 It is the main view of the framework structure of the prior art. DETAILED DESCRIPTION Specific embodiment 1:
[0023] Figures 1 to 4 This constitutes the specific embodiment 1 of the present invention.
[0024] Reference Figure 1 and Figure 2 The specific embodiment 1 includes a seabed foundation 1 and a sea surface station house, and the sea surface station house includes a frame body 2 and a house shell; the frame body 2 has an integral three-layer space structure; the first layer 2-3 of the frame body 2 constitutes a rest room, an accident oil discharge tank and an escape equipment setting space, the second layer 2-4 of the frame body 2 constitutes a main transformer setting space, and the third layer 2-5 of the frame body 2 constitutes a main transformer maintenance equipment setting space; at the bottom of the second layer of the frame body 2, a left supporting structure 2-1 is extended to the left, and a right supporting structure 2-2 is extended to the right, and a left prefabricated box 3 is connected to the left supporting structure 2-1, and a right prefabricated box 3 is connected to the right supporting structure 2-2. The right prefabricated box 4 is connected to the structure 2-2 to form a modular combination structure; the left prefabricated box 3 constitutes the installation space for medium-voltage equipment, low-voltage equipment and electronic equipment, secondary batteries, and diesel generators, and the right prefabricated box 4 constitutes the installation space for GIS, communication batteries, fire-fighting equipment and GIS maintenance settings, and HVAC equipment; the bottom surface of the frame body 2 is provided with a large tubular foundation connection end 2-6 and a small tubular foundation connection end 2-7 to form a fixed connection structure with the foundation 1; through the connection combination of the left prefabricated box 3, the right prefabricated box 4 and the frame body 2, a modular and integral offshore substation structure is formed.
[0025] In this embodiment:
[0026] Reference Figure 2 The seabed foundation 1 has a large tubular connection frame body end 1-1 and a small tubular connection frame body end 1-2 that are connected to the large tubular connection base end 2-6 and the small tubular connection base end 2-7 of the frame body 2 to form a fixed connection structure connecting the frame body 2. The seabed foundation 1 includes a large tubular connection frame body end 1-1, a small tubular connection frame body end 1-2, a pile foot 1-3, an "A" type support column 1-4, a base 1-6 and a plurality of diagonal braces 1-8, a wedge 1-5 is provided between the pile foot 1-3 and the "A" type support column 1-4 to form a tight connection structure, and a telescopic foot 1-7 is provided in the pile foot 1-3.
[0027] In this embodiment, the large tubular connection frame main body end 1-1 is located at the four corners of the seabed foundation 1, the large tubular connection base end 2-6 is located at the four corners of the frame body 2, the small tubular connection frame main body end 1-2 is located in the middle of the seabed foundation 1 and is arranged in two rows, each row has a plurality of (two, or, four or more) small tubular connection frame main body ends 1-2, the small tubular connection base end 2-7 is located in the middle of the frame body 2 and is arranged in two rows, each row has a plurality of (two, or, four or more) connection base ends 2-7.
[0028] The connection between the large tubular connection frame main end 1-1 and the large tubular connection base end 2-6, and the connection between the small tubular connection frame main end 1-2 and the small tubular connection base end 2-7 can be welded and fixed after sleeve-type sleeve connection, so that the seabed foundation 1 and the frame main body 2 are fixedly connected as an integrated structure.
[0029] Reference Figure 1 , Figure 3-Figure 4 The left supporting structure 2-1 and the right supporting structure 2-2 extend from the left and right sides of the second bottom layer of the frame body 2 respectively. The bottom surface of the left supporting structure 2-1 is provided with a left support 5, and the bottom surface of the right supporting structure 2-2 is provided with a right support 6; forming a reinforced support for the left supporting structure 2-1 and the right supporting structure 2-2; the left prefabricated box 3 and the right prefabricated box 4 each have a two-layer structure to form a two-layer equipment setting space.
[0030] The left prefabricated box 3 includes a left upper box 3-1 and a left lower box 3-2, and the right prefabricated box 4 includes a right upper box 4-1 and a right lower box 4-2. The left lower box 3-2 is used to set medium-voltage equipment and low-voltage equipment, and the left upper box 3-1 is used to set electronic equipment, secondary batteries, and diesel generators; the right lower box 4-2 is used to set GIS, communication batteries, and fire-fighting equipment, and the right upper box 4-1 is used to set GIS maintenance equipment and HVAC equipment.
[0031] The left prefabricated box 3 is connected to the frame body 2 and the left supporting structure 2-1 by bolts to form an easily assembled and disassembled connection structure, and the right prefabricated box 4 is connected to the frame body 2 and the right supporting structure 2-2 by bolts to form an easily assembled and disassembled connection structure; or the left prefabricated box 3 is connected to the frame body 2 and the left supporting structure 2-1 by welding to form a fixed connection structure, and the right prefabricated box 4 is connected to the frame body 2 and the right supporting structure 2-2 by welding to form a fixed connection structure.
[0032] The left support 5 includes a left horizontal beam 5-1 extending from the left side of the bottom of the frame body 2 and two left oblique support rods 5-2. The upper ends of the two left oblique support rods 5-2 are fixedly connected to the bottom surface of the left support structure 2-1, and the lower ends are fixedly connected to the left horizontal beam 5-1, forming a "V"-shaped support structure; the right support 6 includes a right horizontal beam 6-1 extending from the right side of the bottom of the frame body 2 and two right oblique support rods 6-2. The upper ends of the two left oblique support rods 6-2 are fixedly connected to the bottom surface of the right support structure 2-2, and the lower ends are fixedly connected to the right horizontal beam 6-1, forming a "V"-shaped support structure.
[0033] This embodiment reduces the weight of the sea surface part of the booster station by reducing the main beams, secondary beams, auxiliary beams, diagonal braces, etc. of the steel structure by combining four prefabricated cabins with the frame body 2; at the same time, an integral booster station is split into five separate structures, expanding the number of working surfaces for structural construction and equipment installation, increasing one working surface to five working surfaces, thereby effectively shortening the total construction period.
[0034] In this embodiment, the electrical, fire protection, and HVAC equipment arranged in the booster station remain unchanged and are consistent with the conventional arrangement. However, the structure and outfitting are optimized and adjusted. The first floor and the middle main transformer area of the booster station in the present invention can adopt the form of a main frame, and the equipment rooms on the left and right sides of the second and third floors adopt a modular container structure.
[0035] GIS refers to power generation equipment.
[0036] Refer to Book 1 and Figure 3 In the second layer structure of the frame body, a prefabricated cabin-type box is used between the medium and low voltage equipment on the left, and a prefabricated cabin-type box is used for the GIS, communication battery, and fire-fighting equipment on the right side of the frame body 2. There is no change in the middle main transformer area.
[0037] Refer to Book 1 and Figure 4 In the third-layer structure of the frame body, the electronic equipment, secondary batteries, diesel generators, etc. on the left side use a prefabricated cabin-type box, the GIS maintenance area and HVAC equipment on the right side use a prefabricated cabin-type box, and the main transformer maintenance area in the middle remains unchanged.
[0038] From the above description, it can be seen that the four prefabricated cabin structures and the integral structure formed by the independent frame body 2 and the seabed foundation 1 in the middle form a split connection structure. The installation and unit debugging of process equipment are carried out in four independent pre-support cabins, and this part of the work is carried out simultaneously with the construction of the main structure and the installation of the main transformer. The construction work surface can be increased to five, and the individual work surfaces do not affect each other, which can effectively shorten the construction period. After each independent individual has completed the construction and unit debugging, the splicing of the four prefabricated cabins and the main structure will be completed at the onshore construction base, and finally hoisted out to sea as a complete offshore booster station.
[0039] In addition, compared with the prior art, the structure of the sea station building in this embodiment can reduce several structural columns, several struts, several beams, several node plates, several decking plates and warehouse walls, and the upper block structure (sea station building) can be reduced in weight by 245 tons. The weight reduction of the upper block (sea station building) is shown in the following table:
[0040] Table 1 Comparison of steel structure usage between conventional and optimized solutions for upper block
[0041]
[0042]
[0043] After the weight of the upper block of the booster station (sea station house) is reduced by 245 tons, the steel pipe piles of the lower foundation can be reduced by 100 tons, and the jacket can be reduced by 164 tons. The relationship between the steel pipe piles, jacket and the upper block of the booster station is shown in the figure below:
[0044] Figure 1 The frame body shown includes a jacket and steel pipe piles.
[0045] In terms of construction period, the traditional integral block prefabricates and assembles each layer of structure. After the corresponding installation layer is completed, the electrical equipment installation work at that layer is carried out, and then the structure and equipment installation work at a higher level is carried out to finally form an integral block. The integral solution requires a four-layer structure with a construction period of about 9-10 months. The solution of the present invention replaces the equipment installation with prefabricated cabin modules. The manufacture, equipment installation, and commissioning of the prefabricated cabin modules can be carried out in parallel with the installation of the first layer and the middle structure. After coordinating the delivery nodes of the prefabricated cabin, the main transformer delivery nodes, and the completion nodes of the first layer and the main structure, they are directly assembled with the prefabricated cabin modules to finally complete the construction of the block. The optimization scheme of the present invention reduces the construction period of the original structure and equipment installation, and the overall construction period can be optimized to 7-8 months (i.e., reducing the construction period by 1-2 months).
[0046] The benefits brought by the present invention are mainly reflected in the upper modules, lower structures and construction period of the offshore booster station. After comparison, the upper structure can be reduced by 245t, the lower foundation (steel pipe piles and conductor frame) can be reduced by 265t, and the construction period of the booster station can be shortened by 1-2 months. The prefabricated cabin solution has a reduction of about 13.94 million compared with the original solution. The specific technical and economic calculations are shown in the following table:
[0047] Table 2- Cost Calculation Table
[0048]
[0049] Specific embodiment 2:
[0051] The characteristic of the specific embodiment 2 of the present invention is that: a left supporting structure 2-1 is extended to the left side and a right supporting structure 2-2 is extended to the right side at the bottom of the second layer of the frame body 2; therefore, the left prefabricated cabin and the right prefabricated cabin can be a three-layer structure. The rest is the same as the specific embodiment 1.
[0052] The present invention applies modular prefabricated cabins to the integral offshore booster station, and uses modular prefabricated cabins to replace the structural main columns, steel beams, diagonal braces and other structural components of the original integral offshore booster station to reduce the weight of the upper modules and the lower foundation of the offshore booster station; after the prefabricated cabins are introduced, the construction period of the offshore booster station is shortened by increasing the construction working surface.
Claims
1. A modular and integrated offshore booster station, comprising a seabed foundation (1) and a sea surface station building, wherein the sea surface station building comprises a frame body (2) and a housing shell; the characteristics are: The frame body (2) has an integral three-layer space structure; the first layer (2-3) of the frame body (2) constitutes a rest room, an emergency oil drain tank and an escape equipment installation space, the second layer (2-4) of the frame body (2) constitutes a main transformer installation space, and the third layer (2-5) of the frame body (2) constitutes a main transformer maintenance equipment installation space; a left support structure (2-1) extends to the left at the bottom of the second layer of the frame body (2), and a right support structure (2-2) extends to the right. A left prefabricated box (3) is connected to the left support structure (2-1), and a right prefabricated box (2-2) is connected to the right support structure (2-2). 4), forming a modular combination structure; the left prefabricated box (3) forms a space for installing medium-voltage equipment, low-voltage equipment and electronic equipment, secondary batteries, and diesel generators, and the right prefabricated box (4) forms a space for installing GIS, communication batteries, fire-fighting equipment and GIS maintenance equipment, and HVAC equipment; the bottom surface of the frame body (2) is provided with a large tube-type foundation connection end (2-6) and a small tube-type foundation connection end (2-7) to form a fixed connection structure with the foundation (1); through the connection and combination of the left prefabricated box (3), the right prefabricated box (4) and the frame body (2), a modular and integral offshore booster station structure is formed; The bottom surface of the left support structure (2-1) is provided with a left support (5), and the bottom surface of the right support structure (2-2) is provided with a right support (6); a reinforced support is formed for the left support structure (2-1) and the right support structure (2-2); the left prefabricated box (3) and the right prefabricated box (4) each have a two-layer structure to form a two-layer equipment installation space; The left support (5) comprises a left horizontal beam (5-1) extending from the left side of the bottom of the frame body (2) and two left oblique support rods (5-2), the upper ends of the two left oblique support rods (5-2) being fixedly connected to the bottom surface of the left support structure (2-1), and the lower ends being fixedly connected to the left horizontal beam (5-1), forming a "V"-shaped support structure; the right support (6) comprises a right horizontal beam (6-1) extending from the right side of the bottom of the frame body (2) and two right oblique support rods (6-2), the upper ends of the two left oblique support rods (5-2) being fixedly connected to the bottom surface of the right support structure (2-2), and the lower ends being fixedly connected to the right horizontal beam (6-1), forming a "V"-shaped support structure.
2. According to claim 1, a modular and integrated offshore booster station is characterized in that: The left prefabricated box (3) comprises a left upper box (3-1) and a left lower box (3-2); the right prefabricated box (4) comprises a right upper box (4-1) and a right lower box (4-2); the left lower box (3-2) is used to set medium-voltage equipment and low-voltage equipment; the left upper box (3-1) is used to set electronic equipment, secondary batteries, and diesel generators; the right lower box (4-2) is used to set GIS, communication batteries, and fire-fighting equipment; and the right upper box (4-1) is used to set GIS maintenance equipment and HVAC equipment.
3. According to claim 1, a modular and integrated offshore booster station is characterized in that: The left prefabricated box (3) is connected to the frame body (2) and the left supporting structure (2-1) by bolts to form an easily assembled and disassembled connection structure, and the right prefabricated box (4) is connected to the frame body (2) and the right supporting structure (2-2) by bolts to form an easily assembled and disassembled connection structure; or the left prefabricated box (3) is connected to the frame body (2) and the left supporting structure (2-1) by welding to form a fixed connection structure, and the right prefabricated box (4) is connected to the frame body (2) and the right supporting structure (2-2) by welding to form a fixed connection structure.
Citation Information
Patent Citations
Integral type offshore booster station structure
CN201943059U
Preinstalled-module sea voltage booster station
CN204376281U
Modularization and integral type combined offshore booster station
CN214885930U
Construction process of lower assembly of offshore voltage booster substation
WO2019015260A1