Extra-long tunnel water inrush prevention system and its construction method

By using concrete water retaining walls and guide pipe systems in tunnel construction, the water influx and mud burst problems caused by water storage in the inclined shaft of the tunnel are solved, the construction risks are reduced, and the construction safety and smooth completion are ensured.

CN112901266BActive Publication Date: 2024-12-03CHINA CONSTR SEVENTH BUREAU FIRST CONSTR CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110318493.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-03-25
Publication Date
2024-12-03
Estimated Expiration
2041-03-25

AI Technical Summary

Technical Problem

During the tunnel construction process, when there is a large amount of water stored in the inclined shaft of the tunnel, water inflow, mud bursting and other phenomena are prone to occur when the main tunnel is constructed to the penetration surface of the inclined shaft, which has major safety hazards and inconvenient construction problems.

Method used

Adopt a special-length tunnel water inrush prevention and control system, including a water barrier wall and guide pipe formed by concrete pouring. The water barrier wall is set at a preset distance from the palm surface of the main hole, fits with the circumferential side wall of the main hole, and casts the bottom The water wall foundation is anchored into the bedrock by a mortar anchor rod around it. The guide pipe extends along the excavation direction and is arranged in a plum blossom shape. The drill rod of the drilling rig passes through the guide pipe to form a drain hole on the palm surface of the main hole, and the drain hole and inclined shaft. The water system is connected and discharges water that threatens the construction of the main hole. As the number of water discharge holes increases, the water level of the inclined well and the main hole decreases, the water pressure decreases, and the risk of water inrush is eliminated.

Benefits of technology

The water in the inclined shaft is discharged through the water discharge hole, reducing the water pressure, eliminating construction safety hazards, reducing the impact of water flow when the water discharge hole is penetrated, reducing the damage to personnel, machinery, and equipment, and achieving safe water discharge from the main hole and steady advancement of the palm surface .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112901266B_ABST
    Figure CN112901266B_ABST
Patent Text Reader

Abstract

The present invention proposes a super-long tunnel water gushing prevention and control system and a construction method thereof. The prevention and control system comprises a retaining wall formed by pouring concrete. The retaining wall is arranged at a position with a preset distance from the main tunnel face and is completely fitted with the circumferential side wall of the main tunnel. A retaining wall foundation is cast at the bottom of the retaining wall. A foundation trench for accommodating the retaining wall foundation is dug at the bottom of the main tunnel foundation pit. The periphery of the retaining wall is anchored into bedrock by mortar anchor rods. A guide pipe is pre-buried in the retaining wall. The guide pipe extends along the excavation direction and both ends thereof extend out of the retaining wall. The guide pipe is arranged in a plum blossom shape. A temporary drainage ditch is opened at a position near both sides of the main tunnel foundation pit below the retaining wall. The drill rod of a drilling rig passes through the guide pipe to drill the main tunnel face, and a drainage hole is formed on the main tunnel face. The problem in the prior art that when there is a large amount of water stored in the tunnel inclined shaft, water gushing, mud bursting and the like are prone to occur when the tunnel main shaft is constructed near the inclined shaft penetration face, which has a large safety hazard and inconvenience in construction is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of tunnel construction, and specifically provides a super-long tunnel water inrush prevention and control system and a construction method thereof. Background Art

[0002] In recent years, with the vigorous development of highway and railway transportation construction in my country, the mileage of tunnel construction has been continuously updated, and the geological conditions have become more and more complex. Sudden water and mud intrusion in tunnels have become one of the most serious engineering disasters. How to quickly solve the follow-up work of water and mud intrusion and quickly resume production is becoming a current research hotspot.

[0003] Taking the Yingpanshan Tunnel of Yunnan Huali Expressway as an example, it is 11.28km long and has a maximum buried depth of 883m. It passes through a fold belt with well-developed joints and fissures. The geology is dolomite and the surrounding rock is Grade IV. There is fissure water and karst water in the bedrock. The terrain and geological environment conditions are special, there are many difficulties and key points in the construction, and the technical problems are very complex.

[0004] During the construction process, water and mud suddenly gushed out from the left tunnel face of the main tunnel of the No. 2 inclined shaft of Yingpanshan Tunnel, with an instantaneous water inrush of 8,000 m³ and a mud inrush of more than 5,000 m³. After more than a year, the water volume in the inclined shaft and the inclined shaft conversion main tunnel reached 260,000 m³, and the air supply and exhaust inclined shaft openings were still discharged at a rate of 1,500 m³ / h.

[0005] With the excavation of the main tunnel, it is getting closer and closer to the penetration face of the 2# inclined shaft. Water gushing, mud bursting and large-scale collapse may occur at any time. The safety risk is getting higher and higher. It is urgently necessary to discharge the water in the inclined shaft to ensure the safe construction of the heading face and the smooth penetration of the main tunnel.

[0006] Accordingly, the art needs an extra-long tunnel water inrush prevention system and a construction method thereof to solve the above-mentioned problems. Summary of the invention

[0007] The present invention proposes a system for preventing and controlling water gushing in an extra-long tunnel and a construction method thereof, so as to solve the problem in the prior art that when there is a large amount of water stored in the inclined shaft of the tunnel, water gushing and mud bursting are prone to occur when the main tunnel of the tunnel is constructed near the through-face of the inclined shaft, which poses a great safety hazard and inconvenience in construction.

[0008] The technical solution of the present invention is implemented as follows: on the one hand, the present invention provides a super-long tunnel water inrush prevention and control system, the super-long tunnel includes an inclined shaft and a main tunnel, the super-long tunnel water inrush prevention and control system includes a retaining wall formed by pouring concrete, the retaining wall is arranged at a position with a preset distance from the main tunnel heading, and is completely fitted with the circumferential side wall of the main tunnel, the bottom of the retaining wall is cast to form a retaining wall foundation, a foundation trench for accommodating the retaining wall foundation is excavated at the bottom of the main tunnel foundation pit, the periphery of the retaining wall is anchored into the bedrock by mortar anchor rods, a guide pipe is pre-buried in the water retaining wall, the guide pipe extends along the excavation direction and its two ends extend out of the water retaining wall, the guide pipe is arranged in a plum blossom shape, a temporary drainage ditch is opened below the water retaining wall near both sides of the main tunnel foundation pit, the drill rod of the drilling rig passes through the guide pipe to drill the main tunnel heading, and a drainage hole is formed on the main tunnel heading.

[0009] The technical effect of this scheme is as follows: due to the development of joints and fissures in the reserved rock column, the drainage holes can be connected with the water system in the inclined shaft by drilling drainage holes, so as to discharge the accumulated water in the inclined shaft that threatens the construction of the main tunnel and release the huge water pressure of the stored water in the tunnel. With the continuous increase in the number of drainage holes, the water levels in the inclined shaft and the main tunnel will continue to drop, and the water pressure will continue to decrease, thereby eliminating the risk source of water gushing in the main tunnel - large-volume water storage in the inclined shaft, and eliminating the safety hazard caused by water pressure to the surrounding rock during the excavation of the main tunnel. When the water level drops to the safe water pressure requirement, the retaining wall can be removed to continue to excavate the remaining surrounding rock, so as to realize the connection between the main tunnel and the inclined shaft; the retaining wall can reduce the strong impact of water flow when the drainage holes are connected, reduce the damage to personnel, machinery and equipment, and minimize the construction risk. The gushing water flows into the drainage system in the tunnel through the temporary drainage ditches on both sides of the retaining wall and is discharged to the outside of the tunnel, so as to realize the safe drainage of the main tunnel and the steady advancement of the heading face.

[0010] In the preferred technical solution of the above-mentioned extra-long tunnel water inrush prevention system, the extra-long tunnel water inrush prevention system also includes a closed wall sprayed on the main tunnel face, and the closed wall is anchored to the main tunnel face by mortar anchor rods.

[0011] The technical effect of this solution is: the closed wall and mortar anchor rods reinforce the tunnel face and rock column, avoiding the combined action of the drill rod and water pressure to damage the tunnel face when the drilling rig drills the drainage hole, causing water gushing and turbulence or unstable rock column.

[0012] In the preferred technical solution of the above-mentioned extra-long tunnel water inrush prevention system, both ends of the guide pipe extend out of the water retaining wall by no less than 20 cm, and a ball valve is installed at the end of the guide pipe away from the main tunnel face.

[0013] The technical effect of this scheme is: both ends of the guide pipe extend out of the water retaining wall, which is conducive to the connection between the guide pipe and the end of the drilling rig, and better guidance of the drill rod of the drilling rig, ensuring the accuracy of the drilling; after the drilling is completed, the drill rod is slowly pulled out, and the ball valve on the guide pipe is closed to temporarily prevent water from flowing, creating a better construction environment for the drilling rig to drill other drainage holes.

[0014] In the preferred technical solution of the above-mentioned extra-long tunnel water inrush prevention system, the elevation angle of the guide pipe is 1° to 3°.

[0015] The technical effect of this solution is: since the drill tool is long, settlement will occur during drilling. In order to improve the drilling accuracy and meet the technical requirements, the guide tube is set to be slightly lifted upward to provide good guidance for the drill tool.

[0016] In the preferred technical solution of the above-mentioned extra-long tunnel water inrush prevention system, steel meshes and gate-shaped brackets are pre-embedded in the water retaining wall, the gate-shaped brackets are arranged between the steel meshes and connected to the steel meshes, and the guide pipes are arranged on the gate-shaped brackets and connected to the gate-shaped brackets.

[0017] The technical effect of this solution is to ensure that the guide tube is positioned accurately and securely, that the guide tube does not deviate during concrete pouring, and that the elevation angle and axis of the guide tube are ensured.

[0018] On the other hand, the present invention also provides a construction method of a super-long tunnel water inrush prevention system, which specifically comprises the following steps:

[0019] S10, measure and lay out, locate the pile center line and excavation boundary line;

[0020] S20, dig the trench and clean the bottom, use a breaker hammer to dig the foundation pit to the designed elevation to form a foundation trench, and dig two temporary drainage ditches on the side of the foundation trench away from the main tunnel face;

[0021] S30, mortar anchor bolt anchoring, mortar anchor bolts are arranged along the perimeter of the retaining wall, and parts of the mortar anchor bolts are anchored into the bedrock;

[0022] S40, retaining wall foundation construction, installing formwork in the foundation trench and pouring;

[0023] S50, water retaining wall construction, supporting formwork and steel mesh on the water retaining wall foundation, supporting gate-shaped brackets between the steel meshes, and connecting the gate-shaped brackets with the steel meshes on both sides thereof with steel bars, fixing guide pipes in a plum blossom shape on the gate-shaped brackets, and casting to form the water retaining wall;

[0024] S60, Drilling of drainage holes. The drilling rig is in place, and the drill rod of the drilling rig is passed through the guide pipe to drill a hole on the main tunnel face to form a drainage hole.

[0025] In the preferred technical scheme of the construction method of the extra-long tunnel water inrush prevention system, the step of "drilling a drainage hole, positioning the drilling rig, passing the drill rod of the drilling rig through the guide pipe and drilling a hole on the main tunnel face to form a drainage hole" specifically includes the following steps:

[0026] Pour a concrete cushion at the bottom of the drilling rig;

[0027] Fix the drilling rig base, control the drilling angle upward by 1° to 3°, and drill through the guide tube layer by layer from the middle to both sides and from bottom to top.

[0028] In the preferred technical solution of the construction method of the extra-long tunnel water inrush prevention system, before the step "S10, measuring and laying out, locating the pile center line and excavation boundary line", the following steps are also included:

[0029] Install mortar anchors on the main tunnel face, and fully spread steel mesh, connecting the steel mesh and mortar anchors;

[0030] Concrete is sprayed from bottom to top on the heading face of the Yuzheng tunnel to form a closed wall.

[0031] In the preferred technical scheme of the construction method of the extra-long tunnel water inrush prevention system, before the step of "driving mortar anchors on the main tunnel face, fully paving steel mesh, and connecting the steel mesh and mortar anchors", the following steps are also included:

[0032] Cast retaining walls outside the existing temporary facilities in the tunnel.

[0033] In the preferred technical scheme of the construction method of the extra-long tunnel water inrush prevention system, after the step of "drilling the drainage hole, positioning the drilling rig, passing the drill rod of the drilling rig through the guide pipe and drilling a hole on the main tunnel face to form the drainage hole", the following steps are also included:

[0034] Determine whether the water leakage from the drain hole is obvious;

[0035] If the water leakage is not obvious, pump out water in the inclined well to lower the static water level and deepen the drainage hole;

[0036] Repeatedly judge whether the water leakage from the drain hole is obvious;

[0037] If water leakage is not obvious, continue to deepen the drainage hole until it connects the main tunnel face and the inclined shaft face.

[0038] In summary, in the technical scheme of the construction method of the extra-long tunnel water gushing prevention system of the present invention, due to the development of joints and fissures in the reserved rock column, the drainage holes can be connected with the water system in the inclined shaft by drilling drainage holes, so as to discharge the accumulated water in the inclined shaft that threatens the main tunnel construction, and release the huge water pressure of the stored water in the tunnel. With the continuous increase in the number of drainage holes, the water levels in the inclined shaft and the main tunnel will continue to drop, and the water pressure will continue to decrease, thereby eliminating the risk source of water gushing in the main tunnel - large-volume water storage in the inclined shaft, and eliminating the safety hazard caused by the water pressure to the surrounding rock during the excavation of the main tunnel. When the water level drops to the safe water pressure requirement, the retaining wall can be removed to continue to excavate the remaining section of the surrounding rock, so as to realize the connection between the main tunnel and the inclined shaft; casting the retaining wall reduces the strong water flow impact when the drainage holes are connected, reduces the damage to personnel, machinery and equipment, and minimizes the construction risk. The gushing water flows into the drainage system in the tunnel through the temporary drainage ditches on both sides of the retaining wall and is discharged to the outside of the tunnel, so as to realize the safe drainage of the main tunnel and the steady advancement of the heading face. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0040] Figure 1 It is a front view of the super-long tunnel water inrush prevention system of the present invention;

[0041] Figure 2 It is a side view of the extra-long tunnel water inrush prevention system of the present invention;

[0042] Figure 3 A distribution diagram of mortar anchor rods on a water retaining wall of a super-long tunnel water inrush prevention system of the present invention;

[0043] Figure 4 A side view of a closed wall of the super-long tunnel water inrush prevention system of the present invention;

[0044] Figure 5 A distribution diagram of mortar anchor rods on the closed wall of the extra-long tunnel water inrush prevention system of the present invention;

[0045] Figure 6 It is a step diagram of the construction method of the extra-long tunnel water inrush prevention system of the present invention.

[0046] List of reference numerals: 1. retaining wall; 11. portal bracket; 2. retaining wall foundation; 3. temporary drainage ditch; 4. mortar anchor rod; 5. guide pipe; 6. drilling rig; 7. drainage hole; 8. closed wall. DETAILED DESCRIPTION

[0047] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0048] It should be noted that, in the description of the present invention, terms such as "center", "up", "down", "left", "right", "vertical", "horizontal", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it should not be understood as a limitation on the present invention.

[0049] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0050] Taking the Yingpanshan Tunnel of Yunnan Huali Expressway mentioned in the background technology as an example, a specific embodiment of a super-long tunnel water inrush prevention system of the present invention is as follows:

[0051] like Figure 1 , Figure 2 and Figure 3 As shown, the extra-long tunnel includes an inclined shaft and a main tunnel. When the main tunnel is constructed to 100m away from the penetration surface, a retaining wall 1 is formed by pouring concrete at a position 1.5m away from the main tunnel face. The retaining wall 1 is completely in contact with the circumferential side wall of the main tunnel. The bottom of the retaining wall 1 is poured to form a retaining wall foundation 2. The size of the retaining wall foundation 2 is: 11.9m*5m*1m. A foundation trench for accommodating the retaining wall foundation 2 is dug at the bottom of the main tunnel foundation pit. Temporary drainage ditches 3 are opened in the direction away from the main tunnel face near the two sides of the foundation trench. The periphery of the retaining wall 1 is anchored into the bedrock by mortar anchor rods 4. The mortar anchor rods 4 are 3m long, anchored into the bedrock for 2m, and exposed for 1m. Figure 3The direction pointed by the middle shear head is circumferential, and the mortar anchor rods 4 are spaced 100 cm in the circumferential direction and 60 cm in the transverse direction. A guide pipe 5 with an elevation angle of 1° to 3° is pre-buried in the retaining wall 1. The guide pipe 5 is arranged in a plum blossom shape. The guide pipe 5 extends along the excavation direction and its two ends extend 20 cm out of the retaining wall. A flange and a ball valve are provided at the end of the guide pipe 5 away from the main tunnel face. The drill rod of the drilling rig 6 passes through the guide pipe 5 to drill the main tunnel face, forming a drainage hole 7 on the main tunnel face.

[0052] Since the drilling tool is long, it will sink during drilling. In order to improve the drilling accuracy and meet the technical requirements, the guide pipe 5 is set to be slightly lifted up to guide the drilling tool. The flange on the guide pipe 5 is conducive to the connection between the guide pipe 5 and the end of the drilling machine 6, avoiding the huge water pressure during the drilling process to knock down the drilling machine 6, protecting the safety of the machine and construction personnel; after the drilling is completed, the drill rod is slowly pulled out, and the ball valve on the guide pipe 5 is closed to temporarily prevent water from flowing, creating a better construction environment for the drilling machine 6 to drill other drainage holes 7.

[0053] Continue reading Figure 1 In order to ensure that the guide pipe 5 is accurately and securely positioned, the guide pipe 5 does not deviate during the pouring of concrete, and ensure the elevation angle and axis of the guide pipe 5, a steel mesh and a gate-shaped bracket 11 are pre-buried in the retaining wall 1. The gate-shaped bracket 11 is formed by welding steel bars. The gate-shaped bracket 11 is arranged between the steel meshes and connected to the steel meshes through steel bars. The guide pipe 5 is supported on the gate-shaped bracket 11 and connected to the gate-shaped bracket 11, and is fixed by the gate-shaped bracket 11.

[0054] like Figure 4 and Figure 5 As shown, due to the development of joints and fissures in the reserved rock column, the drill rod and water pressure work together when the drilling rig 6 drills the drainage hole 7, which may damage the main tunnel face. In order to avoid causing water turbulence or unstable rock columns, the extra-long tunnel water inrush prevention and control system also includes a closed wall 8 sprayed on the main tunnel face. The closed wall 8 is anchored to the main tunnel face by mortar anchor rods. The closed wall 8 is 15 cm thick, the mortar anchor rods are 8 m long, and the spacing between the mortar anchor rods is 100 cm*100 cm.

[0055] Due to the development of joints and fissures in the reserved rock column, the drainage holes 7 are drilled and connected with the water system in the inclined shaft to discharge the accumulated water in the inclined shaft that threatens the construction of the main tunnel, and release the huge water pressure of the stored water in the tunnel. With the continuous increase in the number of drainage holes 7, the water levels in the inclined shaft and the main tunnel will continue to drop, and the water pressure will continue to decrease, thereby eliminating the risk source of water gushing in the main tunnel - large-volume water storage in the inclined shaft, and eliminating the safety hazard caused by water pressure to the surrounding rock during the excavation of the main tunnel. When the water level drops to the safe water pressure requirement, the retaining wall 1 can be removed to continue to excavate the remaining surrounding rock, so as to achieve the connection between the main tunnel and the inclined shaft; the retaining wall 1 reduces the strong water flow impact when the drainage holes 7 are connected, reduces the damage to personnel, machinery and equipment, and minimizes the construction risk. The gushing water flows into the drainage system in the tunnel through the temporary drainage ditches 3 on both sides of the retaining wall 1 and is discharged to the outside of the tunnel, so as to achieve safe water discharge in the main tunnel and steady advancement of the heading face.

[0056] like Figure 6 Specifically, the construction method of the above-mentioned super-long tunnel water inrush prevention system mainly includes the following steps:

[0057] S10, measure and lay out, locate the pile center line and excavation boundary line;

[0058] S20, dig the trench and clean the bottom, use a breaker hammer to dig the foundation pit to the designed elevation to form a foundation trench, and dig two temporary drainage ditches 3 on the side of the foundation trench away from the main tunnel face;

[0059] S30, mortar anchor bolt anchoring, mortar anchor bolts 4 are arranged along the periphery of the retaining wall 1, and the mortar anchor bolts 4 are anchored into the bedrock 2m deep, with 1m exposed;

[0060] S40, retaining wall foundation construction, install the formwork in the foundation trench and pour. The formwork adopts steel formwork, and uses D48*3.5 double steel pipes for horizontal and vertical reinforcement, and is fastened with large butterfly clamps. When pouring concrete, use a vibrating rod to vibrate, fast in and slow out, with a spacing of 30cm to 50cm, until the concrete no longer sinks and flows;

[0061] S50, water retaining wall construction, covering the temporary drainage ditch 3 with wooden boards to prevent concrete from entering, supporting the formwork and steel mesh on the water retaining wall foundation 2, supporting the door-shaped bracket 11 between the steel meshes, and connecting the door-shaped bracket 11 with the steel meshes on both sides thereof with steel bars, fixing 22 guide pipes 5 with a diameter of 20 cm and a length of 2.5 m in a plum blossom shape on the door-shaped bracket 11, controlling the angle of the guide pipe 5 to be 1° to 3° upward, and making the extension direction of the guide pipe 5 parallel to the axis of the tunnel, exposing the guide pipe 5 by 20 cm, and welding a flange and installing a ball valve on the side of the guide pipe 5 away from the main tunnel face, the horizontal spacing between the guide pipes 5 is 120 cm, and the vertical spacing is 100 cm, and pouring to form the water retaining wall 1;

[0062] S60, drilling a drainage hole, the drilling rig 6 is in place, the drill rod of the drilling rig 6 is passed through the guide pipe 5, the end of the drilling rig 6 is connected to the flange of the guide pipe 5, and a hole is drilled on the heading face of the main hole to form a drainage hole 7. When drilling the next drainage hole 7, the ball valve on the guide pipe 5 is closed.

[0063] To ensure that the drilling machine 6 is in place stably, the position of the drilling machine 6 does not shift during the drilling process, and the position of the drilling machine 6 remains unchanged after the drilling is completed, step S60 specifically includes the following steps:

[0064] S601, pouring a concrete cushion layer at the bottom of the drilling rig 6;

[0065] S602, fix the base of the drilling rig 6, control the drilling angle upward by 1° to 3°, mark the guide pipe serial number on the retaining wall 1, and drill holes through the guide pipe 5 layer by layer from the middle to both sides and from bottom to top to form drainage holes 7.

[0066] The drainage hole 7 is drilled 50 m for the first time. After step 602, the following steps are also included:

[0067] Determine whether the water leakage from the water leakage hole 7 is obvious;

[0068] If the water leakage is not obvious, pump out water in the inclined well to lower the static water level and deepen the drainage hole by 7 to 80m;

[0069] Repeatedly determine whether the water leakage from the water leakage hole 7 is obvious;

[0070] If the water leakage is not obvious, continue to deepen the drainage hole by 7 to 100m, that is, connect the main tunnel heading and the inclined shaft heading. If the water leakage is still not obvious, consider whether to drill through the rock pillar.

[0071] Due to the development of joints and fissures in the reserved rock column, the drill rod and water pressure may damage the tunnel face when the drilling rig 6 drills the drainage hole 7. In order to avoid causing turbulent water flow or unstable rock column, before step S10, the following steps are also included:

[0072] S01. Install mortar anchors on the main tunnel face, fully spread steel mesh, and connect the steel mesh with the mortar anchors;

[0073] S02. Shotcrete is sprayed from bottom to top on the heading face of the main tunnel. The spraying operation is carried out in layers, sections and pieces in sequence. The spraying sequence moves from bottom to top. The nozzle is directly facing the sprayed surface. The thickness of one spraying is about 50 to 80 mm. There must be a certain interval after each spraying, which is generally carried out after the previous layer of concrete has finally set. The concrete clumps hanging on the mesh should be removed in time to ensure the density of the shotcrete. The shotcrete will cover the entire steel mesh to form a dense, crack-free, non-falling-off, non-leaking spraying, non-leaking reinforcement, non-hollowing, and non-leakage closed wall 8.

[0074] In order to ensure that the existing temporary facilities of the tunnel, such as the air compressor room, power distribution room, security room and tunnel warehouse, are not damaged by the flooding during the water discharge, the following steps are also included before step S01:

[0075] A retaining wall is cast outside the existing temporary facilities of the tunnel. The retaining wall is 100cm high and 30cm thick.

[0076] It is understandable that the construction step of the retaining wall in the present invention is before the construction step of the closed wall at the face, but this is not a limitation on the construction order of the retaining wall. In other embodiments, the retaining wall can be constructed simultaneously with the closed wall, or after the construction of the closed wall is completed.

[0077] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. The construction method of the super-long tunnel water inrush prevention system is characterized by: The following steps are involved: S10, measure and lay out, locate the pile center line and excavation boundary line; S20, dig the trench and clean the bottom, use a breaker hammer to dig the foundation pit to the designed elevation to form a foundation trench, and dig two temporary drainage ditches on the side of the foundation trench away from the main tunnel face; S30, mortar anchor bolt anchoring, mortar anchor bolts are arranged along the perimeter of the retaining wall, and parts of the mortar anchor bolts are anchored into the bedrock; S40, retaining wall foundation construction, installing formwork in the foundation trench and pouring; S50, water retaining wall construction, supporting formwork and steel mesh on the water retaining wall foundation, supporting gate-shaped brackets between the steel meshes, and connecting the gate-shaped brackets with the steel meshes on both sides thereof with steel bars, fixing guide pipes in a plum blossom shape on the gate-shaped brackets, and casting to form the water retaining wall; S60, drilling of drainage holes, the drilling rig is in place, the drill rod of the drilling rig is passed through the guide pipe and a hole is drilled on the main tunnel face to form a drainage hole; The extra-long tunnel includes an inclined shaft and a main tunnel. The water inrush prevention and control system of the extra-long tunnel includes a retaining wall formed by pouring concrete. The retaining wall is arranged at a preset distance from the main tunnel face and is completely fitted with the circumferential side wall of the main tunnel. The bottom of the retaining wall is cast to form a retaining wall foundation. A foundation trench for accommodating the retaining wall foundation is excavated at the bottom of the main tunnel foundation pit. The periphery of the retaining wall is anchored into the bedrock by mortar anchor rods. A guide pipe is pre-buried in the water retaining wall. The guide pipe extends along the excavation direction and its two ends extend out of the water retaining wall. The guide pipe is arranged in a plum blossom shape. A temporary drainage ditch is opened below the water retaining wall near both sides of the main tunnel foundation pit. The drill rod of the drilling rig passes through the guide pipe to drill the main tunnel face to form a drainage hole on the main tunnel face.

2. The construction method of the super-long tunnel water inrush prevention system according to claim 1 is characterized in that: The step of "drilling a drainage hole, positioning the drilling rig, passing the drill rod of the drilling rig through the guide pipe and drilling a hole on the main tunnel face to form a drainage hole" specifically includes the following steps: Pour a concrete cushion at the bottom of the drilling rig; Fix the drilling rig base, control the drilling angle upward by 1° to 3°, and drill through the guide tube layer by layer from the middle to both sides and from bottom to top.

3. The construction method of the super-long tunnel water inrush prevention system according to claim 1 is characterized in that: Before the step "S10, measuring and laying out, locating the pile center line and excavation boundary line", the following steps are also included: Mortar anchor rods are driven into the heading face of the main tunnel, and steel mesh is fully spread to connect the steel mesh and mortar anchor rods; concrete is sprayed from bottom to top on the heading face of the main tunnel to form a closed wall.

4. The construction method of the super-long tunnel water inrush prevention system according to claim 3 is characterized in that: Before the step of "laying mortar anchor rods on the main tunnel face, fully paving steel mesh, and connecting the steel mesh and mortar anchor rods", the following steps are also included: Cast retaining walls outside the existing temporary facilities in the tunnel.

5. The construction method of the super-long tunnel water inrush prevention system according to claim 1, characterized in that: After the step of "drilling the drainage hole, putting the drilling rig in place, passing the drill rod of the drilling rig through the guide pipe and drilling a hole on the main tunnel face to form the drainage hole", the following steps are also included: Determine whether the water leakage from the drain hole is obvious; If the water leakage is not obvious, pump out water in the inclined well to lower the static water level and deepen the drainage hole; Repeatedly judge whether the water leakage from the drain hole is obvious; If water leakage is not obvious, continue to deepen the drainage hole until it connects the main tunnel face and the inclined shaft face.